HomeMy WebLinkAboutSWP2701997 TERRA ASSOCIATES, Inc.
Consultants in Geotechnical Engineering, Geology
and
Environmental Earth Sciences
January 23, 1997
Project No. T-3065-1
U.S. Rentals
c/o Mr. Bart Treece
Treece and Company
320-2nd Avenue South, Suite 200
Kirkland,Washington 98033
Subject: Geotechnical Report Revision
U.S. Rentals
SW 34th Street and Lind Avenue
Renton, Washington
Reference: 1. Geotechnical Report, Warehouse/Office Facility, by Terra Associates, Inc. dated
February 9, 1996
Dear Mr.Treece:
We understand that the subject site will be developed by U.S. Rentals as a new rental facility. The proposed
construction will differ considerably from what we expected and evaluated in the referenced report.
Accordingly, you have asked us to review our recommendations with respect to the planned construction.
A preliminary grading plan for the project by Treece and Company dated January 3, 1997 shows that a
10,600 square foot office/rental building will be situated within the central portion of the site. With existing
site grades at Elev. 16, an approximately two-foot thick fill pad will be required to construct the building to
the proposed finished floor elevation of 18.5 feet. We understand the building will be of metal-frame
construction that will impose relatively light foundation loads. With the planned building, we expect
relatively low floor slab loading of approximately 150 to 200 pounds per square foot (psf).
As we discussed with you, the recommendations in our referenced report pertaining to site preparation and
foundation design would still be applicable for the revised site development. However, because of the
reduced building loads and the type of construction planned, we do not believe it will be necessary to
surcharge the site to the extent or magnitude recommended for the previously planned structure. The
revision to our surcharge recommendations is to reduce the four foot surcharge fill above the finished floor
subgrade elevation to a minimum of six inches. Following fill placement, monitoring for settlements should
be completed as previously recommended in our referenced report. RECEIVE
APR 18 1997
12525 Willows Road, Suite 101, Kirkland, Washington 98034 • Phone (206) 821-7777
Mr. Bart Treece
January 23, 1997
We estimate that the 2.5-foot thick fill pad will induce primary settlements of about 2-1/4 inches within the
peat and clayey silt layers underlying the building area. Analysis indicates that these settlements should
occur within about six weeks. The time rate for these expected settlements can be accelerated by placing
additional depth of surcharge fill. For four feet of surcharge fill above the finished subgrade elevation,
analysis indicates that the expected settlements would occur within two to three weeks.
Following successful completion of the preload program, we estimate that post-construction primary
settlements will range from 1/2 to 1 inch. Secondary compression of the peat layer beneath the building will
continue for several years once the primary settlements are complete. We estimate that over a 50 year
period, up to 1-1/2 inches of settlement will occur in addition to the primary settlements. Approximately 75
percent of the secondary settlements will occur within the initial ten years of the life of the structure.
Local variations in building loads and subsurface conditions will introduce a differential component to the
above settlements. Accordingly, you should expect some building movements and cracking of the floor slabs
during the initial years of the life of the structure.
If the risk of building settlement as discussed is not acceptable to you, then we recommend implementing the .
surcharge program outlined in the referenced geotechnical report. Other than the modification to the building
surcharge, all other geotechnical recommendations for design and construction remain valid.
We trust the information presented is sufficient to meet your current needs. If you have any questions or
need additional information, please call.
Sincerely yours,
TERRA ASSOCIATES,INC.
Kevin P. Roberts P •�.
Project Engineer
eodore J. Sc , P.
Principal Engine ' 26742 W
'�srsp
KPR/TJS:tm
��IR€s 6/18/9$
Project No.T-3065-1
Page No. 2
..........
.......... ....... ... ...........
.. ................ ....................
.......... ... ............
.............
........... ............. .......1 ...........
"s GEOTECHNICAL REPORT .:
Warehouse/Office Facility
r SW 34th Street and Lind Avenue
Renton, Washington
Project No. T-3065
M.
.,'s .ng
f
Terra Associates, Inc.
Q gg
.: .:..
c
l Prepared for:
Powell Development Company
Kirkland, Washington
February 9, 1996
L_
.......
-_..._
l
TERRA ASSOCIATES, Inc.
Consultants in Geotechnical Engineering, Geology
and
Environmental Earth Sciences
February 9, 1996
Project No. T-3065
Mr. Peter Powell
Powell Development Company
737 Market Street
Kirkland, Washington 98033
Subject: Geotechnical Report
Warehouse/Office Facility
SW 34th Street and Lind Avenue
Renton, Washington
Dear Mr. Powell:
As requested, we have conducted a geotechnical engineering study for the subject project. In general, the site is
underlain by five to six feet of dense granular fill overlying two to four feet of clayey silt, organic silt, and peat.
These compressible soils are underlain by medium dense.to dense alluvial sands. To reduce post-construction
settlements to what may be considered to tolerable levels, we recommend that the building area be pre-loaded
with a surcharge fill. Following successful completion of the surcharge program, the proposed warehouse/office
facility may be constructed using conventional spread footings placed on the existing fill or on new structural
fell, as required. If the estimated post-construction differential settlements of 1/2 inch cannot be tolerated by the
construction,you should plan for deep foundation support or removal of the organic consolidating layer.
The attached report describes our exploration and explains our recommendations in greater detail. We trust this
information is sufficient for your present needs. Please call if you have any questions or need additional
information.
Sincerely yours,
I TERRA A I =
Kevin P R� erts, III
Project Xgjneer -,
4
2 ,742 _
T eodore J. Sc he P_r
Principal-£n.gineer___._...__
EXPIRES
KPR/TJS:eb
cc: Mr. Bart Treece, Horton Dennis and Associates, Inc.
12525 Willows Road, Suite 101, Kirkland, Washington 98034 Phone (206) 821-7777
1
TABLE OF CONTENTS
Page
r1 1.0 Project Description I
2.0 Scope of Work 1
3.0 Site Conditions 2
3.1 Surface 2
i 3.2 Soils 2
3.3 Groundwater 2
3.4 Seismic Hazards 3
4.0 Discussion and Recommendations 3
4.1 General 3
4.2 Site Preparation and Grading 4
4.3 Surcharge and Settlements 5
4.4 Spread Footing Foundations 6
4.5 Excavate and Refill Procedure 7
4.6 Timber Piling 7
4.7 Augercast Piling g
4.8 Slab-on-grade Floors 8
4.9 Excavations 9
4.10 Utilities
9
4.11 Lateral Earth Pressures 9
4.12 Drainage 10
4.13 Pavements 10
5.0 Additional Services 11
6.0 Limitations 11
Figures
Vicinity Map Figure I
Exploration Location Plan Figure 2
Typical Settlement Marker Detail Figure 3
Reinforced Soil Wall Section Figure 4
QAppendix
Field Exploration and Laboratory Testing Appendix A
a
(i)
Geotechnical Report
Warehouse/Office Facility
SW 34th Street and Lind Avenue
Renton, Washington
J 1.0 PROJECT DESCRIPTION
The project will consist of construction of a warehouse/office facility in Renton, Washington. The location of
the project site is shown on the Vicinity Map, Figure 1. Horton Dennis and Associates, Inc. provided an
undated conceptual site plan showing the location of the warehouse facility and associated loading and parking
areas. The site plan shows a 65,400 square foot warehouse building occupying the central portion of the site.
Truck loading areas will be located at the eastern and western sides of the building. Parking areas will lie within
the northern and western sections of the site.
Whiles specific design details are not available to us we expect the warehouse building
p g p b d g will be constructed using
pre-cast concrete tilt-up wall panels or masonry blocks. Grades at the site may be raised up four to six feet
above existing site grades to create a dock-high floor level. We anticipate building loads will be about three
kips per lineal foot along walls, 80 to 100 kips for columns, with floor loads of approximately 200 to 300
{ pounds per square foot(psf).
f ,
The recommendations in the following sections of this report are based on our understanding of the project's
design features. We should review final design drawings and specifications to verify that our recommendations
have been properly interpreted and incorporated into project design.
1 �
2.0 SCOPE OF WORK
On January 9, 1996, we drilled two test borings at the site to depths of 28.5 and 29 feet below existing site
grades. We also reviewed and used test boring information from the adjacent Farwest Steel site. Using the
information obtained from the subsurface exploration, we performed analyses to develop geotechnical
arecommendations for project design and construction. Specifically,this report addresses the following:
• Soil and groundwater conditions
• Site preparation and grading
U • Foundation alternatives
• Surcharge and settlements
U • Lateral earth pressures
• Slab-on-grade floors
• Utilities
• Pavements
0 Drainage requirements
i ,
February 9, 1996
Project No. T-3065
3.0 SITE CONDITIONS
3.1 Surface
The subject site is located at the southeast corner of the intersection of SW 34th Street and Lind Avenue in
Renton, Washington. This location is shown on Figure 1. The site is bounded to the south and north by
undeveloped property and SW 34th Street, respectively. Lind Avenue bounds the site on the west. An open,
undeveloped parcel (Farwest Steel site) bounds the site on the east.
The site and vicinity are flat. An existing railroad spur track enters the northeastern corner of the property and
curves in a southwestward direction to join a track leading west of the site. We noted that the track was raised
slightly above surrounding grades. We observed shallow ditches filled with standing water adjacent to the spur
4 ; track.
Vegetation at the site consisted of sparse grasses. Standing water was observed over much of the site at the time
of our visit. Stormwater drainage from adjacent roadways is directed to storm drains along curbs and gutters
located along the northern and western margin of the site.
3.2 Soils
The soil conditions at the site generally consist of sand with gravel and silt fill overlying a variably thick layer of
compressible peat, clayey silt, or organic silt. The compressible soils were underlain by generally competent
sand and silty sand deposits.
S.�
Each boring showed fill soil comprised of sand with gravel and silt to a depth of about five feet. This material
was generally medium dense to dense, indicating it was compacted. The compressible native soils under the fill
consisted mostly of dark brown silty peat, gray organic silt, or gray to brown clayey silt. These soils occur at
five feet below existing grades and were between two and four feet thick. Interbeds of black to brown sand that
was fine to coarse-grained and loose to medium dense was found underlying the compressible layers. Borings
( � B-I'and B-2 were terminated within very dense horizons of the black sand.
The Geologic Map of the Renton Quadrangle, King County, Washington by D.R. Mullineaux (1965) shows that
the soils are mapped as peat (Qlp). The peat seen in Boring B-I correlates with the published description of this
soil unit. Figures A-2 through A-4 in Appendix A present more detailed descriptions of the subsurface
conditions encountered in the test borings. The approximate test boring locations are shown on Figure 2.
3.3 Groundwater
We encountered groundwater in each of the test borings. Groundwater levels observed are recorded on the
Boring Logs. Water encountered near the ground surface appeared to consist of a perched zone of infiltration
from recent heavy rains. In general, the static groundwater table was found at a depth of about seven feet.
Annual and seasonal fluctuations in the depth of the groundwater table should be expected.
,1 Page No. 2
.3
1 February 9, 1996
Project No. T-3065
E.1
3.4 Seismic Hazards
The Puget Sound area falls within Seismic Zone 3 as classified by the Uniform Building Code (UBC). Based on
the soil conditions encountered and the local geology, Table 16-J of the 1994 UBC indicates a site coefficient of
J 1.5 should be used in design of the structure.
We reviewed the results of our field and laboratory testing and assessed the potential for liquefaction of the
site's soils during an earthquake. Liquefaction is a phenomenon where there is a reduction or complete loss of
soil strength due to an increase in pore water pressure induced by vibrations from a seismic event. Based on the
information obtained and considering the additional confining stresses from the building and fill weight, it is our
opinion that the risk of liquefaction-related impacts to the structure are minimal.
4.0 DISCUSSION AND RECOMMENDATIONS
4.1 General
Based on our study, in our opinion, there are no geotechnical constraints that would preclude construction of the
proposed facility. The primary geotechnical concern for construction at this site is the two to four foot-thick
layer of clayey silt, organic silt, and silty peat at depths of five to nine feet below existing site grades.
Consolidation of these soils will occur when subjected to loads comparable to those expected from construction
of the warehouse/office building.
A fill surcharge program implemented prior to construction will consolidate the compressible soil layers and
induce most of the primary settlements under loads expected from the project. Once the primary settlements are
complete, lesser amounts of secondary settlement will continue throughout the life of the structure. These
j secondary settlements are in addition to settlements that will occur from placement of the building's foundation.
Analysis indicates that over a 50 year span, one inch of total secondary settlement and 1/2 inch differential
settlement are expected. If the settlements cannot be tolerated by the facility, other foundation alternatives will
need to be considered. These alternatives can consist of:
Q Overexcavation and removal of the organic soils and replacement with a structural engineered fill for
foundation support
• Piling support using either timber or augercast piling systems
The foundation option chosen for design of the facility will depend on how much risk of damage to the structure
Q from differential settlement is acceptable to the owner. The following sections provide detailed
recommendations regarding the above issues and other geotechnical design considerations. These
recommendations should be incorporated into the final design drawings and construction specifications.
i�
Page No. 3
February 9, 1996
• Project No. T-3065
4.2 Site Preparation and Grading
Following clearing, the fill surface should be proofrolled with heavy construction equipment prior to placement
of additional fill. Soft yielding areas should be overexcavated to firm bearing soil and replaced with structural
fill. Where excavations to achieve firm conditions are excessive, use of a geotextile fabric such as Mirafi 500X
d in conjunction with limited overexcavation and replacement with a structural fill can be considered. Typically,
18 inches of clean granular structural fill over the fabric will achieve a stable subgrade.
Our laboratorytest results show that the existing fill was above its optimum moisture content at the time of our
P
investigation, and that some of the fill contains up to 12 percent fines. These conditions may be difficult to
compact if the moisture conditions cannot be carefully controlled. Extreme care should be taken to ensure that
exposed surfaces of the on-site fill do not become disturbed due to weather and construction traffic. Moreover,
llthe ability to use these soils as structural fill will depend on their moisture content and the prevailing weather
J conditions at the time of construction. It will be difficult to achieve proper compaction of these soils when their
moisture content is above optimum. When the moisture is excessive, the soil can be dried by aeration to a
moisture content which will allow for proper compaction.
We recommend that the structural fill required to achieve site grades consist of inorganic granular soil meeting
the following grading requirements:
Maximum Aggregate Size 6 inches
Minimum Retained on the No. 4 Sieve 25 percent
QMaximum Passing the No. 200 Sieve 25 percent
(Based on the Minus 3/4-inch Fraction) (see following narrative)
If fill placement takes place during wet weather or if the moisture conditions of the fill material cannot be
a controlled, consideration should be given to importing fill soil that conforms with the above gradation, but with
the maximum passing the No. 200 sieve reduced to five percent.
Q Structural fill materials should be placed in uniform loose layers not exceeding 12 inches and compacted to a
minimum of 95 percent of the soil's maximum density, as determined by ASTM Test Designation D-698
(Standard Proctor). The moisture content of the soil at the time of compaction should be within about two
percent of its optimum, as determined by this same ASTM method.
Prior to constructing foundations and floor slabs, we recommend probing or proofrolling the subgrade to
determine if any isolated soft and yielding areas are present. As discussed above, soft.or yielding areas should
be overexcavated and filled to grade with structural fill or crushed rock.
Page No. 4
4� 4
February 9, 1996
Project No. T-3065
4.3 Surcharue and Settlements
For spread footing foundation support and slab-on-grade construction, we recommend placing a surcharge fill
over the building area. The surcharge program is necessary to limit building settlements to what may be
{� considered tolerable levels. Our surcharge and settlement analysis is based on an assumed existing ground
surface elevation qf/ 2jfeet. In addition, our analysis is based on a finished floor(top-of-slab)elevation of about
�an
feet and the antieipated floor loads discussed above. We should review the final foundation and gradings in order to better assess expected settlements.
i 41
Primary Consolidation
The site grades should be raised using structural fill as outlined in the Site Preparation and Grading section.
Once grade is achieved, an additional four feet of fill should be placed as a surcharge. This surcharge fill does
not need to meet any special requirements other than having a minimum in-place unit weight of 125 pounds per
cubic foot (pcf). However, it may be advisable to use a good quality fill which could be used to raise grades in
other portions of the site, such as parking and driveway areas, if necessary.
We do not believe it is necessary to place a surcharge of fill within the parking and access easement areas.
However, the structural fill required in the pavement areas should be placed as soon as possible to allow enough
time for consolidation of the compressible layers and to reduce potential settlement impacts to pavement and
E1` utilities.
The estimated total primary settlements under the recommended surcharge range from six to eight inches across
the building area. These settlements are expected to occur eight to ten weeks following full application of the
surcharge loading. The actual period for completion and magnitude of the primary settlements will be governed
by variations in subsurface conditions at the site. The rate of consolidation can be accelerated by placing an
additional thickness of fill surcharge. We estimate that placing an additional three feet of surcharge will reduce
the surcharge time by about 30 percent.
To verify the amount of settlement and the rate of movement, the surcharge program should be monitored by
installing settlement markers. A typical settlement marker installation is shown on Figure 3. The settlement
markers should be installed on the existing grade prior to placing any building or surcharge fills. Once installed,
elevations of both the fill height and marker should be recorded daily by a registered land surveyor until the full
height of the surcharge is in place. Once fully surcharged,readings should continue weekly until the anticipated
settlements have occurred.
It is critical that the grading contractor recognize the importance of the settlement marker installations. All
efforts must be made to protect the markers from damage during fill placement. It is difficult, if not impossible,
to evaluate the progress of the surcharge program if the markers are damaged or destroyed by construction
equipment. As a result, it may be necessary to install new markers and to extend the surcharging time to ensure
that settlements have ceased and that building construction can begin.
Page No.5
February 9, 1996
Project No. T-3065
i
We recommend that the surcharge pad extend a minimum of five feet beyond the building perimeter and then
slope down at an inclination of 1:1 (Horizontal:Vertical). It appears that sections of the southeastern building
perimeter may be located close to the railroad spur that curves along the southern property line. If sufficient
area is not available to slope the surcharge, the surcharge may be supported at a near vertical inclination
(minimum 1:12) using a reinforced soil wall. Figure 4 shows a typical reinforced soil wall section.
Post-construction Settlements
Primary consolidation of compressible soils at the site will be achieved upon completion of the surcharge
program. Secondary consolidation will continue at the site throughout the life of the structure. During
t secondary consolidation, you should expect a maximum post-construction settlement of one inch and differential
settlement of 1/2 inch. These values represent expected settlements over a 50 year period. We anticipate that
most of these settlements will occur within five to ten years after completion of the structure.
Impact of Surcharge on Adjacent Roadway and Utilities
Depending on its location, the proximity of the surcharge fill pad to the adjacent railroad spur and roadways
may result in settlement of these structures due to soil beneath them being influenced by the pre-load fill pad.
We recommend placing monitoring points on the roadway curbs and pavement as necessary to record possible
movements during surcharge. A similar monitoring program should be implemented for the railroad spur if it
cannot tolerate possible settlement from the pre-load.
Sufficient monitoring points should be established since some of these points will likely be disturbed by traffic.
In addition,we suggest making a photographic survey of the curbs and pavement before placing the surcharge to
determine if any movement occurs during surcharging.
Similarly, if the pre-load fill pad is placed over or near underground utilities, they may experience vertical
and/or lateral movement as a result of the stress changes in the soil associated with the placement of a pre-load
fill pad. Utility organizations should be prepared to relocate utilities as required prior to construction of the pre-
load, if necessary. We can better assess the level of risk to adjacent structures and utilities upon review of the
final plans.
4.4 Spread Footing Foundations
Following successful completion of the surcharge program, if the above estimated settlements are considered
tolerable, the building may be supported on conventional spread footing foundations bearing on a minimum of
four feet of structural fill. Existing competent fills may be included in determining the depth of the structural
fill. Perimeter foundations exposed to the weather should be at a minimum depth of 1.5 feet below final exterior
grades.
We recommend designing foundations for a net allowable bearing capacity of 3,000 psf. For short-term loads
such as wind and seismic, a 1/3 increase in this allowable capacity can be used. With the anticipated loads and
bearing stresses, the estimated total settlements are as discussed in the Post-construction Settlements section.
Page No. 6
February 9, 1996
Project No. T-3065
r-J
7
For designing foundations to resist lateral loads, a base friction coefficient of 0.4 can be used. Passive earth
pressures acting on the side of the footing and buried portion of the foundation stem wall can also be considered.
We recommend calculating this lateral resistance using an equivalent fluid weight of 350 pcf. We recommend
- not including the upper 12 inches of soil in this computation because they can be affected by weather or
disturbed by future grading activity. This value assumes the foundation will be constructed neat against
competent fill soil or backfilled with structural fill as described in the Site Preparation and Grading section. The
recommended lateral resistance value includes a safety factor of 1.5.
l..l
4.5 Excavate and Refill Procedure
For this procedure, the consolidating soil layer will be excavated and removed from below the foundations, with
f grades then restored to the desired construction elevation using structural fill. Based on the information
obtained, excavations of nine to ten feet below existing surface grades will be necessary. The excavation will
also need to be oversized to allow for placing structural fill a distance laterally from the edge of the foundation
equal to 1/2 the depth of the fill below the foundation.
Once removed, grades can be restored using a structural fill placed and compacted in accordance with the
recommendations in the Site Preparation and Grading section. The excavation to remove the clayey silt, organic
tv� silt, or peat layers will expose loose to medium dense silty sand and sand in a water-bearing condition.
Therefore, it will probably be necessary to place an initial 12 to 18 inch layer of quarry rock or railroad ballast
in order to establish a firm base on which to place the remaining portion of the structural fill. For this method of
obtaining support, spread footing foundations can be designed as discussed in the preceding section. Foundation
settlements should be negligible, with less than 1/2 inch total settlement anticipated. This settlement will be
immediate, occurring as building loads are applied.
4.6 Timber Pilina
Transferring structural loading below the consolidating layers with the use of timber piling can be considered.
We estimate that timber piling with a minimum tip diameter of eight inches will achieve an allowable axial load
of 25 tons when driven into the medium dense, black to brown-gray sand at a minimum tip elevation of 20 feet
below existing surface grades. This allowable axial load takes into account potential negative loading caused by
downdrag on the pile due to consolidation of the organic layer under building fill and floor slab loading.
Full axial capacity can be used provided the piles are spaced at a minimum of three pile diameters. Closer
spacing in pile groups will require a reduction in the single pile capacity. This reduction will depend on the
number of piles in the pile group and the spacing used. For resistance to lateral loading, a lateral pile capacity of
six tons can be used. Estimated pile settlements are 1/2 inch and less. Elastic shortening of the pile is not
included in the above value.
Page No. 7
February 9, 1996
Project No. T-3065
To successfully install timber piling at the site, it may be necessary to predrill the upper five to six feet of
existing fill soils. The pile driving hammer used to install the piles should have sufficient energy to drive the
piling to the estimated tip elevation without damaging the pile. For this purpose, we recommend the pile driving
equipment have a minimum rated energy of 15,000 foot-pounds with an efficiency factor of at least 70 percent.
We also recommend that prior to ordering and installing production piles, a minimum of three test piles be
driven at the site to verify anticipated tip elevations and establish driving criteria for use in evaluating
production pile capacities. The test piles should be driven with the same equipment that will be used in the
production pile installation.
E �
4.7 Augercast Piling
Augercast piling can be considered as an alternative to timber piling in transferring foundation loading below
the peat and gray-brown clayey silt layers. For 16-inch diameter pilings with a tip elevation of 20 feet below
$ existing surface grades, an allowable axial load of 30 tons is available for design. This loading takes into
} account the potential negative loading effects due to downdrag. Similar effects on the reduction of axial pile
capacity due to close spacing apply to augercast piles. For resistance to lateral loads, an allowable lateral pile
capacity of four tons is available. The estimated pile settlement is 1/2 inch and less. Elastic shortening of the
pile is not included in this value.
Augercast piles are formed by the pressure injection of grout through a hollow stem auger which is slowly
retracted from the ground after advancement to the recommended tip elevation. The grout pressure used will
compress the soils within the immediate vicinity of the pile, thereby increasing to some extent the pile diameter
and the amount of grout required to construct the pile. For planning purposes, we suggest considering a 30
percent increase in the amount of grout necessary to form the pile.
a j To construct augercast piling, a higher than normal reliance on quality workmanship is required for successful
installations. It is extremely important that the grout pressure be consistent and uniform during the installation
land that retraction of the auger occurs at a slow uniform pace beneath a sufficient head of grout in the pile
t.1 column. The contractor should have adequate means for verifying grout pressure and estimating the volume of
grout used in construction of the piles. Because of the compression effects and the possible influence on
adjacent pile construction, the installation sequence should be based on a minimum pile spacing of five pile
#� diameters. Once the grout column has achieved its initial 24 hour set, pile construction between these spacings
can be completed.
4.8 Slab-on-grade Floors
With site preparation completed as described in the Site Preparation and Grading section, new structural fill soils
should be suitable for supporting slab-on-grade construction. Immediately below the floor slabs, we recommend
making an allowance for placing a six-inch layer of clean free-draining sand or gravel which has less than five
percent passing the No. 200 sieve. This capillary break will guard against wetting of the floor slab due to the
underlying soil conditions.
}
Page No. 8
z
February 9, 1996
Project No. T-3065
Where moisture via vapor transmission is not desired, a polyethylene vapor barrier should also be installed. We
I, suggest that this vapor barrier be placed on an initial four inch layer of the capillary break material and then
covered with the final two inches to help protect it during construction and to aid in uniform curing of the
. , concrete floor slab. For slab thickness design,with respect to floor deflection due to traffic and point loadings, a
j subgrade modulus of 300 pounds per cubic inch (pci)can be used.
Estimated floor slab settlements of less than 3/4 inch are expected due to post-primary consolidation. This
movement assumes that settlements due to required building fills would be allowed to occur prior to floor slab
construction.
4.9 Excavations
( `I Excavations will need to be completed in accordance with local, state, or federal regulations. In accordance
with the Occupational Safety and Health Administration (OSHA), inorganic soils encountered at the site are
classified as Group C soils. Accordingly, excavations made within the native soils or fill at the site greater than
j four feet in depth but not exceeding 20 feet in depth will need to be laid back with side slope gradients of 1.5:1.
As another option, a trench shoring box to support excavations throughout the lower depth may be used in
conjunction with sloping of the upper portion of the excavation as outlined above. Because of groundwater
seepage within the upper fills, temporary dewatering of the excavation may need to be considered where
excavation depths exceed two to three feet below existing site grade. Excavations below depths of seven feet
will likely encounter the groundwater table and require more intensive dewatering efforts to maintain trench
stability.
4.10 Utilities
c �
We recommend that all site utilities be bedded and backfilled in accordance with applicable American Public
Works Association (APWA) specifications. For site utilities within City rights-of-way, bedding and backfill
should be completed in accordance with City of Renton specifications. At a minimum, utility trench backfill
should be placed and compacted in accordance with recommendations presented in the Site Preparation and
Grading section. Where utilities will occur below unimproved areas, the degree of compaction can be reduced
to a minimum of 90 percent of the soil's maximum density as determined by the referenced ASTM standard.
Because of the potential for long-term settlements, utility pipe joints and connections should be flexible,
allowing for up to one inch of differential movement.
4.11 Lateral Earth Pressures
The magnitude of earth pressure development on retaining walls constructed in loading dock areas will partly
depend on the quality of backfill. Where fill is.placed behind retaining walls, we recommend placing and
compacting it as structural fill. The fill should be compacted to a minimum of 95 percent of its maximum dry
unit weight as determined by ASTM Test Designation D-698 (Standard Proctor). To guard against the buildup
of hydrostatic pressure, wall drainage must also be installed as discussed in the Drainage section.
Page No.9
February 9, 1996
Project No. T-3065
With granular backfill placed and compacted as recommended and drainage properly installed, we recommend
jdesigning restrained walls for an at-rest earth pressure equivalent to a fluid weighing 50 pcf. A value of 35 pcf
I may be used where the wall is unrestrained. These values do not include other surcharge loading such as from
fill backslopes or adjacent footings that may act on the wall. If such conditions will exist, the imposed loading
k 1 must be included in the wall design. Friction at the base of foundations and passive earth pressure will provide
resistance to these lateral loads. Values for these parameters are provided in the Foundations section.
4.12 Drainage
Surface
Final exterior grades should promote free and positive drainage away from the building areas at all times. Water
must not be allowed to pond or collect adjacent to foundations or within the immediate building area. We
recommend providing a gradient of at least three percent for a minimum distance of ten feet from the building
perimeter, except in paved locations. In paved locations, a minimum gradient of one percent should be provided
unless provisions are included for collection and disposal of surface water adjacent to the structure.
Subsurface
In our opinion, perimeter foundation drains will not be necessary if the area immediately adjacent the structure
is paved and positive surface drainage is maintained. If the grade is not positively drained away from the
structure or if it is landscaped,perimeter foundation drains should be installed.
To guard against hydrostatic pressure development, retaining wall drainage must be installed. We recommend
that wall drainage consist of a minimum 12-inch thick layer of washed rock or pea gravel placed adjacent to the
wall. A four-inch diameter perforated pipe should be placed on a bed of gravel at the base of the wall footing
and gravel drainage column. The pipe should be directed to a suitable outlet.
4.13 Pavements
With subgrade soils prepared as described in the Site Preparation and Grading section, suitable support for
pavement construction should be provided. However, regardless of the compaction results obtained subgrades
must be in a stable non-yielding condition prior to paving. Immediately prior to paving,the area of the subgrade
should be proofrolled with heavy construction equipment to verify this condition.
The required pavement thickness is not only dependent upon the supporting capability of the subgrade soils but
also on the traffic loading conditions which will be applied. For light commercial vehicles and typical passenger
vehicle traffic,the following pavement sections are recommended:
• Two inches of asphalt concrete (AC)over four inches of crushed rock base (CRB)
• Two inches of AC over three inches of asphalt treated base (ATB)
Page No. 10
February 9, 1996
Project No. T-3065
For heavy truck traffic areas, we recommend the following pavement sections:
• Three inches of AC over six inches of CRB
• Three inches of AC over four inches of ATB
If there is a potential that pavement construction will be delayed until the wet winter months, the subgrade soils
must consist of a clean granular material as described in the Site Preparation and Grading section. In addition,
we strongly suggest that the subgrade be further protected by placing a layer of ATB, on which construction
traffic could access the project without excessively disturbing the subgrade soils. The ATB thickness for this
purpose should be four inches. Repair of failed ATB areas should be anticipated prior to final paving.
However, the overall integrity of the subgrade soils will be considerably less impacted if this protection is
provided.
Because of secondary compression of the clayey silt, organic silt, or peat layers, some degree of post-
construction settlement within the pavement structure should be anticipated. This settlement will probably result
in some longitudinal and transverse cracking of the pavement. Cracks in the pavement should be sealed in a
timely fashion to prevent excessive surface water infiltration into the subgrade soils.
5.0 ADDITIONAL SERVICES
Terra Associates, Inc. should review the final design and specifications in order to verify that earthwork and
foundation recommendations have been properly interpreted and incorporated in the project design. We should
also provide geotechnical services during construction in order to observe compliance with the design concepts,
specifications, and recommendations. This will also allow for design changes if subsurface conditions differ
from those anticipated prior to the start of construction.
J 6.0 LIMITATIONS
J We prepared this report in accordance with generally accepted geotechnical engineering practices. This report is
the property of Terra Associates, Inc. and is intended for specific application to the Warehouse/Office Facility
project in Renton, Washington. This report is for the exclusive use of Powell Development Company and their
authorized representatives. No other warranty, expressed or implied, is made.
The analyses and recommendations presented in this report are based upon data obtained from the test borings
drilled on-site. Variations in soil conditions can occur, the nature and extent of which may not become evident
until construction. If variations appear evident, Terra Associates, Inc. should be requested to reevaluate the
recommendations in this report prior to proceeding with construction.
Page No. 1 I
PAAK
X, t SW cn wtav YILLASC 1 3 a
ENTON J ' R �, KVIARMW
rA7EL f
g,SMI 1 G T ■ S R ON VILLAGE 7l s 117N ST
A
20
S � s- 75TN
A � �
'J,176TH � S]6T11 51 �8 J. K 416nc
ilU�Oo TOW LA
�'1 •'sm•• =�S 7 � ST
Y:
EprG�G'LT 1 Y ' I I SY 19TH ST ". ✓•I ST p0
V�
s :9rH ST,
.f i V+ I IEDAuAGRES L i y rX.F t i S n,us•+`
PKWY '' r TR.a I RA2 SW 21ST ST r 1 PUGET �-LLL JJJ nu GR£FN e� TRACK
b sl?
L 1 1 3 J
71 I '^ SN 23RD s-23RD ST
BAKER Bl D' r�• ul 1 P [nwf 1 KID F
��
L------ 1 s ---- —
BIYD • `\ �}R NTON SH 'vTH
c` I IS 27TH ST t W� ,1 TH
' , IT
ST S
TREGK INDU [ E I yETX'
p NCT I O I 29TH ST
3 J., �.5 F st 1t T� !
25 I 0 y ��. $
N 3 1 9—
s - 5E
Sw nr Se
SW 33RD 33RD 5T 76ttX E
4. •1 I .y lE9n t+ ltf"+t r �I sC 7DTX S7 170T
�
T
SY TX o .,
�.i S_7�st,5T �' - SE Z�7� XDJ ST� sE
6tw
"I 1T g
CC TH)T , I _ 1 ;>.�37 5 '17<TX ST E� i:;ne ST a' s[ _
FS
ST
2 S
T 176T
' RILL SITE 415T n aL 51 } �I`pFP unn s t
=1x st :Tsn rt Efx Eti r i-
t ss:tt 'i 3 f SW 43RD R E-
ST J< — �?<pp�
f S SW F 43RD tST SE 4c , Est n x i ,S
J gig s I ]RST ST
` 16,NDA
RIY\ i' 1122ND I <'I �, t E� 's[
y E S - SE 1B3RD �lE•
s I j 3SPRING8R00K I �ti C $' F 31Pl` '1
'I TODD •^�. <'I :7} GREENBELT ! ` P� I I ``''''' m cEa
La i J to 16<TH`-
1: N e
0l8 D .. c i f , i ' R E N -_N' ' y �. SE Xl i86TF
s iSUT_H sr i 1= 3 1p�
4 —5 _ �_ ' .p.s
S ' t S 188TH
$128TH S I ST I S 1BETM ST I 5 167iX ST I 1 Ct
- 1 - f F SF]RET.5T f g l� e�
ST H i 190TH ST `;sE �..: > St;en�'Sie �; nn
< S '.90TH ST I s[7?:^sr -
1 190TH N, -- -- i
S N 192ND _ ST cT __ c2ND�ST S cSTH ST �.4 SE I -I c 19i
i_c 2ND
•(
sl w III 1 S�I'
9+T .'1� 3'
:s sr 1X 5T I'..SH 19<TH ST o' sE PC
T i�. 1 ———— 395.•r.�
_ Ste, I i S N I%TH -ST_ '
ST S r I I �
r j '^ S I S :96TH ST p•Ery ?'
y} (19BTH $T S596TX$T Nr—T-1 , , J/sy,��a ` :SE
w s zoorH m Do X 5 I I I S 5 200TH �l S7� -- =i ;SE ST 200TH ST ;
f0Wt
3 _ <I .I �I
FFF �
1 I
.S- i 202ND 1 $T o :I 'I ._1 Sc`.707Nt1 ST N y
REFERENCE: THE THOMAS GUIDE, KING COUNTY, WASHINGTON, PAGES 655, 656, 685 AND 686, 1995 EDITION.
VICINITY MAP
-.,�•. •.: TERRA WAREHOUSE/OFFICE FACILITY
ASSOCIATES RENTON, WASHINGTON
• •Geotechnical Consultants Proj. No.3065 Date 1/96 Figure 1
I
,r
i.,
I
1
2U B-6 II
PARKING c PARKING
280
C'7 PARKING
� ' / 2:
Y
1 !r
Q
PARKING LOADING a
• APPROXIMATE SCALE
100 0 100 200 feet
B-1
' BU LDI G B
g N ,400 F
f I B-2
a . I LEGEND:
270 i 1� APPROXIMATE BORING LOCATION
I 60 ^' LOADING w 60
APPROXIMATE BORING LOCATION
PARVI.NG - PARKING FROM TERRA ASSOCIATES REPORT
T-3064, DATED FEBRUARY, 1996.
PARKING
LIND AVENUE S.W. REFERENCE:
FACSIMILE OF SITE PLAN PROVIDED BY HORTON DENNIS
AND ASSOCIATES, INC., JOB No. UNKNOWN, UNTITLED
AND UNDATED.
EXPLORATION LOCATION PLAN
TERRA WAREHOUSE/OFFICE BUILDING
9 ASSOCIATES RENTON, WASHINGTON
Geotechnical Consultants Proj. No.3065 Date 1/96 Figure 2
STEEL ROD
PROTECTIVE SLEEVE
77-77 7
HEIGHT VARIES
SURCHARGE (SEE NOTES) SURCHARGE
_ l OR FILL OR FILL
o
o
LJI
NOT TO SCALE
I NOTES:
1. BASE CONSISTS OF 1/2" THICK, 2'x2' PLYWOOD WITH CENTER DRILLED 5/8" DIAMETER HOLE.
2. BEDDING MATERIAL, IF REQUIRED, SHOULD CONSIST OF CLEAN COARSE SAND.
3. MARKER ROD IS 1/2" DIAMETER STEEL ROD THREADED AT BOTH ENDS.
4. MARKER ROD IS ATTACHED TO BASE BY NUT AND WASHER ON EACH SIDE OF BASE.
5. PROTECTIVE SLEEVE SURROUNDING MARKER ROD SHOULD CONSIST OF 2" DIAMETER
PLASTIC TUBING. SLEEVE IS NOT ATTACHED TO ROD OR BASE.
6. ADDITIONAL SECTIONS OF STEEL ROD CAN BE CONNECTED WITH THREADED COUPLINGS.
7. ADDITIONAL SECTIONS OF PLASTIC PROTECTIVE SLEEVE CAN BE CONNECTED WITH PRESS—FIT
PLASTIC COUPLINGS.
8. STEEL MARKER ROD SHOULD EXTEND AT LEAST 6" ABOVE TOP OF PLASTIC PROTECTIVE SLEEVE.
9. STEEL MARKER ROD SHOULD EXTEND AT LEAST 1' ABOVE TOP OF FILL SURFACE.
TYPICAL SETTLEMENT MARKER DETAIL
TERRA WAREHOUSE/OFFICE FACILITY
P#Geotechnical
ASSOCIATES RENTON, WASHINGTON
Consultants Proj. No. 3065 Dote 1/96 Figure 3
� l
c_J
SLOPE 12:1(V:H) GEOTEXTILE FACING COMPACTED STRUCTURAL FILL
MINIMUM WRAP (typical) 95% MAX. DRY DENSITY f 2%
OPTIMUM MOISTURE CONTENT
PER D-698 (STANDARD PROCTOR)
0.8H feet (TYPICAL)
3 feet
(TYPICAL)
H feet
18 in. (max.)
:J MIRAFI 5T
" •" GEOGRID
[� (TYPICAL)
U
NOT TO SCALE
REINFORCED SOIL WALL SECTION
R#Geotechnical
TERRA WAREHOUSE/OFFICE BUILDING
ASSOCIATES RENTON, WASHINGTON
Consultants Proj. No.3065 Date 1/96 Figure 4
s�
z1
APPENDIX A
FIELD EXPLORATION AND LABORATORY TESTING
Warehouse/Office Facility
Renton, Washington
On January 9, 1996, we performed our field exploration using a truck-mounted hollow stem auger drill
rig. We explored subsurface soil and groundwater conditions at the site by drilling two hollow stem
auger test borings to a maximum depth of 29 feet below existing grade. An additional test boring was
( J drilled on the adjacent Farwest Steel site. This log is included in Appendix A as Boring B-6. The test
l
boring locations are shown on Figure 2. The Boring Logs are presented on Figures A-2 through A-4.
An engineer from our office maintained a log of each test boring as it was drilled, classified the soil
conditions encountered, and obtained representative soil samples. All soil samples were visually
classified in accordance with the Unified Soil Classification System shown on Figure A-1.
Representative soil samples were obtained from the test borings using sampling procedures outlined in
ASTM Test Designation D-1586. The samples were placed in jars or tubes (ring samples) and taken to
our laboratory for further examination and testing. The moisture content of each sample was measured
and is reported on the Boring Logs. Plasticity characteristics of the fine-grained soils were determined
by conducting Atterberg limit tests. Grain size analyses were performed on three of the samples. The
results of the grain size analyses are presented as Figures A-5 and A-6.
�1
0
Project No. T-3065
r�
•
i
MAJOR DIVISIONS LETTER GRAPH TYPICAL DESCRIPTION
SYMBOL SYMBOL
Clean Q; O.•G Well-graded gravels, gravel-sand mixtures, little
GRAVELS
r, 0 Gravels .Q•p• or no fines.
(less than •••• •• Poorly-graded gravels, gravel-sand mixtures, little
co ai More than GP •••• ••
N 5% fines) ••�� •� or no fines.
50% of coarse
¢, O) .F fraction is GM Silty gravels, gravel-sand-silt mixtures, non-
i 0 0 > larger than No. Gravels plastic fines.
LLJz ( Ln 4 sieve. with fines GC Clayey gravels, gravel-sand-clay mixtures, plastic
Q o0 • •• • � fines.
0O O SANDS Clean Well-graded sands, gravelly sands, little or
Sands
SW no fines.
z More than (less than v < c; poorly-graded sands or gravelly sands, little
ssri :r;#,s.N
Q +' 50% of coarse 5% fines) SP or no fines.
:ilr::fi:i
O L fraction is
O o smaller than SM Silty sands, sand-silt mixtures, non-plastic fines.
No. 4 sieve. Sands
with fines Sc Clayey sands, sand-clay mixtures, plastic fines.
N
SILTS AND CLAYS ML Inorganic silts and very fine sands, rock flour, silty or clayey fine sands or clayey silts with slight plasticity.
J
O 5 � Inorganic clays of low to medium plasticity, gravelly
� •N Liquid limit is less than 50% CL clays, sandy clays, silty clays, lean clays.
E
o o O L l i I'I'I i I I I I I'1 1 Organic silts and organic clays of low plasticity.
Z
LO z Jill III Inorganic silts, micaceous or diatomaceous fine
L SILTS AND CLAYS MH sandy or silty soils, elastic.
co w In
w
Z o 8 Liquid limit is greater than 50% CH Inorganic clays of high plasticity, fat clays.
LL' E OH IIIIIIIII Organic clays of medium to high plasticity,
N I I I I I I I I I
IIIIIIIII organic silts.
HIGHLY ORGANIC SOILS PT Peat and other highly organic soils.
h /.
n n n n
11 .1
DEFINITION OF TERMS AND SYMBOLS
J Standard Penetration 2" OUTSIDE DIAMETER SPLIT
F w Density Resistance in Blows/Foot T SPOON SAMPLER
1 >
J � Very loose 0-4 � 2.4" INSIDE DIAMETER RING SAMPLER
Loose 4-4 OR SHELBY TUBE SAMPLER
° Medium dense 10-30 P SAMPLER PUSHED
0 Dense 30-50 * SAMPLE NOT RECOVERED
Very dense >50 Q WATER LEVEL (DATE)
Cn
WATER OBSERVATION STANDPIPE
Standard Penetration C TORVANE READINGS, tsf
r Consistency Resistance in Blows/Foot qu PENETROMETER READING, tsf
UVer soft O 2 W MOISTURE, percent of dry weight
O y
o Soft 2-4 pcf DRY DENSITY, pounds per cubic foot
� Medium stiff 4-8 LL LIQUID LIMIT, percent
-� Stiff 8-16
Lo Very stiff 16-32 pl PLASTIC INDEX
j Hard >32 N STANDARD PENETRATION, blows per foot
�j SOIL CLASSIFICATION SYSTEM
TERRA WAREHOUSE/OFFICE FACILITY
ASSOCIATES RENTON, WASHINGTON
Geotechnical Consultants
_Prof. No. T-3065 I Date 1/96 Figure A-1
J
Y
A
Boring No. B-1
Logged by: KPR
z--
Date: 1/9/96
m
Graph/ n. (N) Water
Relative Depth glows/ Content
USCS Soil Description Density (ft.) foot (%)
Gray SAND with gravel and silt
r, ,..frr•..J...
fill cuttings, saturated bearing,
......
moist at 2 feet
SP-SM
FILL: Gray SAND with silt and few 37 9.7
gravel, medium-grained, moist. Dense
---------------------------------------- ---------- ---------- 5 _
A A A A Dark brown silty PEAT, 3 59.6 Initially no
A PT AA amorphous, wet. Soft AAAAAAA recovery.
ff
UL
Re-drove
Gray to brown clayey SILT, sampler.
low plasticity, saturated. Medium Stiff T 7 64.4
1
Brown to gray SAND, fine to Loose
very fine-grained, saturated. 10
10 to 11.5 feet black SAND 21 25.4
with silt, fine-grained, saturated. Medium Dense
Black SAND, as above but with T 21 27.1
trace of silt. Medium Dense
—15
:rr.:.'•:.:
r r
-------------------------------------------------------
I
sw > . Black SAND, medium to 51 24.4
coarse-grained, saturated. Very Dense
...........
20
xrM
-------------------------------------------------------
..........
rBlack SAND, medium-grained, Very Dense 73/10" 21.2 Water added
saturated. to hole to
control heave.
—25
Very Dense 50+ 30.0
Black SAND, as above.
Test boring terminated at 28.5 feet.
Hole plugged with 1 bag of bentonite chips mixed with cuttings.
a Ponded surface water.
Groundwater encounterd at 7 feet.
BORING LOG
TERRA WAREHOUSE/OFFICE FACILITY
ASSOCIATES RENTON, WASHINGTON
Geotechnical Consultants Proj. No. T-3065 Date 1/96 Figure A-2
v
Boring No. B-2
Logged by: KPR
Date: 1/9/96
f Graph/ Relative Depth Q' (N) Water
USCS Soil Description Density (ft.) o Blows/ ContentU, foot M
Brown sand with silt and few
gravel fill cuttings, fine to
medium grained, moist. 1
FILL: Brown SAND with silt and 17.0
SP-SM Medium Dense 12
few gravel, medium-grained,
saturated.
FILL: As above but gray. 5
Gray organic SILT interbedded with 1 12 60.3 LL=85
Medium Stiff
OH
I I inch thick peat layers,low plasticity. PL=46
ay silty SAND,very Dark gr PI=39
SM fine rained, saturated. Medium Dense 16 37.8
g
Black SAND, fine grained,
saturated. 10
1 26 30.4
Black SAND, very fine to fine-
>•'•'`'?'>"?'`' grained, with occasional 1 inch Medium Dense
`r$"""`''`''`: thick layers of non plastic silt, 15
a saturated.
Black to brown silty SAND with
interbeds of sandy SILT,very Medium Dense
y fine-grained, saturated. 17 36.5
SM 20
ML
Black to brown silty SAND with
interbeds of silt(as above). Very Dense
57 24.1
Black SAND, medium-grained,
r `''`<` '«< � saturated. 25
:{
Sp
Black SAND, as above but Very Dense 81 35.0
;.. fine grained.
Test boring terminated at 29 feet.
Groundwater encountered at 2 feet.
Hole plugged with 1 bag of bentonite chips mixed with cuttings.
Bentonite slurry added to hole to control heave.
BORING LOG
TERRA WAREHOUSE/OFFICE FACILITY
` ASSOCIATES RENTON, WASHINGTON
Geotechnical Consultants
Proj. No. T-3065 Date 1/96 Figure A-3
Boring No. B-6
Logged by: KPR
Date: 1/11/96
Graph/ Relative Depth Q_ (N) Water
USCS Soil Description Density E Blows/ Content
foot
Brown-gray, gravelly medium
grained silty sand FILL cuttings,
saturated.
SM FILL: Gray SAND with gravel, Dense 32 9.3
medium-grained, wet.
FILL: Gray SAND, medium Loose 5
grained, saturated. 3 62.9
Dark brown PEAT, amorphous,wet. Soft
----------------------------
M L Gray sandy SILT,very fine-grained Soft
sand, saturated, medium plastic. 3 58.2
Unit wt=94.3 pcf
Gray silty SAND, very fine to Loose Bentonite slurry
fine-grained, saturated. — 10 added to hole
to control heave
s M
Dark gray silty SAND,very fine
to fine-grained, saturated, grades Medium Dense
19 28.7
to black sand in sampler tip.
............
.................
jj
15
......... ..
.................
....................................
Black SAND, fine to coarse-
ij SW grained, saturated. Dense
. .. ...........
33 21.5
—20
-------------------------------------------- ------------------------
Black SAND, medium to coarse- Very Dense
grained.
64 20.5
—25
..... ......
Black SAND, as above. Very Dense 75 26.5
Page 1 of 2
BORING LOG
TERRA FARWEST STEEL
ASSOCIATES RENTON, WASHINGTON
Geotechnical Consultants
I Proj. No. T-3064 � Date 1/96 � Figure A-
Boring No. B-6 (Continued)
Logged by: KPR
Date: 1/11/96
Graph/ a (N) Water
' Relative Depth Blows/ Content
USCS Soil Description Density (ft.) a
foot (%)
Black SAND, as above. Very Dense
s%,+SPJ%ss 54 22.6
35
-------------------------------------------------------------------
{ 1
Dark gray silty SAND with
trace clam shells, fine to
medium grained, saturated. Loose 7 25.1
40
Dark gray silty SAND, as above.
58
29.8
Dark gray SAND with silt,trace
€ SP SM clamshells, very fine to fine Very Dense
grained, saturated. 45
r�
Dark gray silty SAND,with trace Loose
Li
bits of wood,clam shells and to 10 36.9
clay, very fine to fine-grained, Medium Dense
{ saturated. 50
� l
SM
Dark gray silty SAND, as above. Loose 6 32.1
55
�1
Dark gray silty SAND, as above. Medium Dense I T
28 24.2
Test boring terminated at 59 feet.
Ponded surface water.
Groundwater encountered at 7 feet.
Hole plugged with 2 bags of bentonite chips mixed with cuttings. Page 2 of 2
BORING LOG
ROMTERRA FARWEST STEEL
ASSOCIATES RENTON, WASHINGTON
Geotechnical Consultants
Proj. No. T-3064 Date 1/96 Figure A-4
SIEVE ANALYSIS HYDROMETER ANALYSIS
SIZE OF OPENING IN INCHES NUMBER OF MESH PER INCH, U.S. STANDARD GRAIN SIZE IN MM
CV
CO Cq 00\ Il- Cq
_
N \\\\ \ O O O O S O O n N O CO CO O O O
1D d' rM N �- MrA r7 d' N 1D N O O O O O O O O O O O
100 0
90 10
o — -
s U) M 80 20
c� O D 70 n 70 30 rC
0
C 60 40 c7
M O
�
50 50 N
rri
40 60 CO
v m --
o = 30 qP 70 M
p
o — _
C D 20 80
cn :;0 -
Z p D 10 --- - 90
o pCZ -- I =RCD M - -
o_ Cn
z�N OO O CD 40 O O CD O O 00 to d- rM N — 00 c0 d- rM N -7 00 cD d- rM N 00 CO -0- M N _1 OO
MC)
CD 00 c0 d rh N O O O O O O 0, O O O O
o m GRAIN SIZE IN MILLIMETERS
D
COARSE I FINE COARSE MEDIUM T FINE
Z m D COBBLES GRAVELAND FINES
ODC
z n Boring Moisture
or De th Moist
r Key Test
(fP) USCS Description Content (�) LL PL
• B-1 2.5 SP—SM SAND with silt and some gravel
0 B-1 17.5 SP—SW clean SAND
awrwr � a■w�
SIEVE ANALYSIS HYDROMETER
�• •� GRAIN SIZE IN MM
-- — -••--w ---•_E•--- In ■■ww—
� �CC��C::��"� �� C'.���C:: ■::CCU
• w.ww.ww.w■.ww. �
■ mom
�ww.wwiw.www.w����ww.wwwww....w w■�■■■■■www.ww
ww.Cww.ww.w.www.-�100000000 .�ww■�' ..www.�==.'�■.ww.�
�w.ww.ww.w..w�www■w�ww.► wwww .■www■� .=..www.
ww.w.wwww.w.www.w��ww..�wwww .■www■�■■ ■■www■�
•� Caw—�'■�iC�::-wl�w-�� �ww..www��.www.�;i:=���ww. ,• � ww■.www ■www
w.ww.ww.w■.ww.w��ww..www ,� ■www� ■�i■ www.ww.
w.ww■ww.w■www■w_�_ww.wwww■w�..www.�..s..www.ww.
� CCC:�C��
ww■Cn
www ■wwwwww
w.ww.ww.w■.ww.w �ww■ wwwww ■www� No ww
w.ww.ww.w■�Cw .w� �ww.wwww� ■www■�■■■■■www■ww■ •
w■www w w M �ww.w.ww� ■www■� ■■■■www■ww
•• , —w■�w`ww. �ww■w.ww� ■ww�w■�=C■■■www.ww. ,, ..
www ■■ w w. �ww.w..ww ■w w ■ . www■
ww.Cww■ww.w..ww. ■rww■w..MENOMINEE
ww�w.www.�..=.C.ww.�
NONE
w.ww.ww.w.www.w��ww.ww.� ■www■�■■■■■ ww.ww.
■�www�ww■.ww.w �ww.ww.���■.ww=■�....`■.ww.ww.
• w.ww.�ww.w..ww. �ww■ww.►�
w.ww.ww.w■www. �ww.www..w� ■www�■■■■■www■ww .
- � w.ww■ww■w■www■w.w��ww■www�.■ww..www�■■■■■www■ww■ .�
�ww� w■www■wwww�ww■www. ww.■www�■■■■■www■ww
EMENRIMIM!�ww �w—w■ww�■�■�■�wwwwwiw►�■1■www�■■■■■www�
• EC�ww.wwww��.www.�.....www.ww.
. - w■w �ww■wwww�w.■www�■■■■■www.
MOM mmmm
' � �■■owl�w■www■w■w��ll■W�w■O�■I��ww�� ■■■■ww�� ��
• ® :• •.• 1 • ® Moisture
Description • •
• SAND with silt
• • •