HomeMy WebLinkAboutPre-App Meeting SummaryDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Planning Division | 1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200 |www.rentonwa.gov
PREAPPLICATION MEETING FOR
SCWSD - Lift Station #5B North Force Main Replacement
South of 17321 125th Ave SW to the City Limits of Kent
PRE 24-000378
December 19, 2024
Contact Information:
Planner: Jill Ding, 425-430-6598, jding@rentonwa.gov
Public Works Plan Reviewer: Nathan Janders, 425-430-7382, njanders@rentonwa.gov
Fire Prevention Reviewer: Corey Thomas, 425.276.9582, cthomas@RentonRFA.org
Building Department Reviewer: Rob Shuey, 206.550.8523, rshuey@rentonwa.gov
Please retain this packet throughout the course of your project as a reference. Consider giving
copies to engineers, architects, and contractors who will work on the project. You will need to
submit an PDF copy of this packet when you apply for land use and/or environmental permits.
When the project application is ready for submittal, you may email the project planner to start
the prescreen process. Similarly, you may contact the assigned planner if there are any
questions regarding submittal requirements.
The pre-application meeting is informal and non -binding. The comments provided on the
proposal are based on the codes and policies in effect at the time of review. The applicant is
cautioned that the development regulations are regularly amended and the pr oposal will be
formally reviewed under the regulations in effect at the time of project submittal. The
information contained in this summary is subject to modification and/or concurrence by
official decision-makers (e.g., Hearing Examiner, Planning Directo r, Development Services
Director, Development Engineering Director, Department of Community & Economic
Development Administrator, Public Works Administrator and City Council).
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: December 19, 2024
June 20, 201
TO: Jill Ding, Senior Planner
FROM: Nathan Janders, Development Engineering Manager
SUBJECT: Soos Creek Water & Sewer District – lift station #5B north force main
replacement project
17634 122nd Pl SE, Renton, WA
PRE24-000378
NOTE: The applicant is cautioned that information contained in this summary is preliminary and non-
binding and may be subject to modification and/or concurrence by official city decision-makers. Review
comments may also need to be revised based on site planning and other design changes required by
City staff or made by the applicant.
I have completed a preliminary review for the above-referenced proposal. The following comments are
based on the pre-application submittal made to the City of Renton by the applicant.
WATER COMMENTS
1. The project is within Soos Creek Water and Sewer District. The project does not propose impacts
to the utility system. All proposed work shall conform to Soos Creek Water and Sewer standards
pertaining to utility separation.
SEWER COMMENTS
1. The project is within Soos Creek Water and Sewer District. The project shall conform to Soos Creek
Water and Sewer District standards pertaining to the sewer pipe, structures, backfill and similar
equipment. The project shall adhere to restoration requirements as defined by: the City of Renton
within City Right-of-Way (ROW), easement(s) within private property, or the City of Kent within
Kent ROW.
2. A franchise permit shall be required to be obtained by the City of Renton for work within City
ROW.
SURFACE WATER
1. Drainage plans and a drainage report complying with the adopted 2022 Renton Surface Water
Design Manual may be required. Refer to Figure 1.1.2.A – Flow Chart of the 2022 Renton Surface
Soos Creek Water & Sewer District lift station #5B north force main replacement project _PRE24-000378
Page 2 of 2
December 19, 2024
2
Water Design Manual (RSWDM) to determine what type of drainage review is required for this
site. Based on the City’s flow control map, the site falls within the Flow Control Duration Standard
Matching Forested Site Conditions. The site falls within the Soos Creek drainage basin.
a. If drainage review is required a Civil Construction Permit shall be required.
2. A Construction Stormwater Permit from Department of Ecology is required if clearing and grading
of the site exceeds one acre.
3. Erosion control measures to meet the City requirements shall be provided.
4. The site contains critical areas that may impact surface water requirements: wetlands, erosion
hazard, flood hazard zone AE, streams and aquifer protection area zone 2.
TRANSPOTATION
1. Based on the project proposal it is exempt from street improvements.
2. Paving and trench restoration within the City of Renton right of way shall comply with the City’s
Trench Restoration and Street Overlay Requirements.
GENERAL COMMENTS
1. Adequate separation between utilities as well as other features shall be provided in accordance
with code requirements:
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other utilities is
required with the exception of water lines which require 10-ft horizontal and 1.5-ft vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.
2. All civil construction permits for utility and street improvements will require separate plan
submittals. All utility plans shall confirm to the Renton Drafting Standards. A licensed Civil
Engineer shall prepare the civil plans. Please visit the Development Engineering Forms page for
the most up-to-date plan submittal requirements:
http://rentonwa.gov/business/default.aspx?id=42473
3. A landscaping plan and tree retention shall be included with the civil plan submittal. Each plan
shall be on separate sheets.
4. Additional Building Permit Applications will be required for the following:
a. Any retaining walls that exceed 4 feet in height, as defined by RMC 4-4-040.
b. Detention vaults for storm water flow control.
c. Demo of any existing structures on the project site(s).
5. Fees quoted in this document reflect the fees applicable in the year 2024 only and will be assessed
based on the fee that is current at the time of the permit application or issuance, as applicable to
the permit type. Please visit www.rentonwa.gov for the current fee schedule.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: December 19, 2024
TO: Pre-Application File No. 24-0000378
FROM: Jill Ding, Senior Planner
SUBJECT: SCWSD - Lift Station #5B North Force Main Replacement – South
of 17321 125th Ave SW to the City Limits of Kent, 17634 122nd Pl
SE, Renton, WA 98058 (PID 3323059023)
General: We have completed a preliminary review of the pre-application for the above-
referenced development proposal. The following comments on development and permitting
issues are based on the pre-application submittals made to the City of Renton by the applicant
and the codes in effect on the date of review. The applicant is cautioned that information
contained in this summary may be subject to modification and/or concurrence by official decision-
makers (e.g., Hearing Examiner, Community & Economic Development Ad ministrator, Public
Works Administrator, Planning Director, Development Services Director, Development
Engineering Director, and City Council). Review comments may also need to be revised based on
site planning and other design changes required by City staff or made by the applicant. The
applicant is encouraged to review all applicable sections of the Renton Municipal Code. The
Development Regulations are available online at https://www.codepublishing.com/WA/Renton.
Project Proposal: The project area within the City of Renton includes work starting to the south
of parcel 17321 125th Ave extending roughly south to the Kent City limits. The proposed project
includes the replacement and redirection of approximately 7,600-feet of existing 8-inch and 10-
inch asbestos concrete (AC) and ductile iron (DI) sewer force main with 8,000-feet of 18-inch C900
DI pipe, installation of a steel casing with sealed end caps, asphalt concrete trench patch and
roadway repair, and surface restoration. The existing sewer force main would be abandoned in
place after being disinfected and capped. The surrounding areas consist of existing residential
uses, roadways, and Boulevard Lane Park. Work would occur within the existing City right-of-way,
existing Soos Creek Water and Sewer District (SCWSD) easements and on private property after
obtaining easements. The project site crosses the Big Soos Creek stream. According to COR Maps,
the following critical areas are mapped on and around the project site: high erosion hazard areas,
100-year floodway and flood plain, high seismic hazard areas, a Type F stream (Big Soos Creek),
wetlands and a zone 2 wellhead protection area.
Current Use: The surrounding areas consist of existing residential uses, roadways, and Boulevard
Lane Park. Work would occur within the existing City right-of-way, existing Soos Creek Water and
Sewer District (SCWSD) easements and on private property after obtaining easements.
1. Zoning /Land Use Designation, and Overlays: The project area is partially located within both
the Residential-10 (R-10), Residential-Multi-Family (RM-F), Residential-4 (R-4), and Resource
Conservation (RC) zones.
SCWSD - Lift Station #5B North Force Main Replacement
Page 2 of 5
December 19, 2024
If the proposal includes sewer facilities included within a Council-adopted utility plan, then
the proposal would be considered a Utilities, Small use. Utilities, Small are defined as:
“Small scale facilities serving local areas within the City, including underground power lines,
water, sewer, and storm water facilities included within a Council-adopted utility system
plan, fiber optic cable, pump stations and hydrants, switching boxes, and other str uctures
normally found in a street right-of-way to serve abutting properties. Facilities also include
electric vehicle infrastructure located on public or private property such as a charging
station.”
Within all residential zoning designations, the small utilities use is permitted provided that
aboveground public utility facilities, such as water towers, reservoirs, water treatment
facilities and pump stations shall be treated with public art, subject to approval by the Arts
Commissions.
If the proposed facilities are not included in a Council-adopted utility system plan, then the
proposal would be considered a Utilities, Medium use. Utilities, Medium are defined as:
“Moderate scale facilities serving the City, including subregional switching stations (one
hundred fifteen (115) kv and smaller), and municipal sewer, water, and storm water
facilities not included in a Council-adopted utility system plan.”
Within all residential zoning designations, the medium utilities use is reviewed and
approved through an Administrative Conditional Use Permit provided that aboveground
public utility facilities, such as water towers, reservoirs, water treatment facilities and pump
stations shall be treated with public art, subject to approval by the Arts Commissions.
2. Significant Tree Retention: A review of COR Maps appears to show that there are mature
trees within the project corridor. When significant trees (greater than 6-inch caliper or 8-
caliper inches for alders and cottonwoods) are proposed to be removed, a tree inventory and
a tree retention plan along with an arborist report, tree retention plan and tree retention
worksheet shall be provided with the formal land use application as defined in RMC 4-8-120.
The tree retention plan must show preservation of at least 30% of significant trees. Please
refer to RMC 4-4-130, Tree Retention and Land Clearing Regulations for further general and
specific tree retention and land clearing requirements.
In addition to retaining a minimum of 30% of existing significant trees, the project would be
required to provide a minimum tree density of 30 tree credits per net acre. Tree credits
encourage retention of existing significant trees with larger trees being worth more tree
credits.
TREE SIZE TREE CREDITS
New small species tree 0.25
New medium species tree 1
New large species tree 2
Preserved tree 6 – 9 caliper inches 4
SCWSD - Lift Station #5B North Force Main Replacement
Page 3 of 5
December 19, 2024
TREE SIZE TREE CREDITS
Preserved tree 10 – 12 caliper inches 5
Preserved tree 12 – 15 caliper inches 6
Preserved tree 16 – 18 caliper inches 7
Preserved tree 19 – 21 caliper inches 8
Preserved tree 22 – 24 caliper inches 9
Preserved tree 25 – 28 caliper inches 10
Preserved tree 29 – 32 caliper inches 11
Preserved tree 33 – 36 caliper inches 12
Preserved tree 37 caliper inches and greater 13
Significant trees shall be retained in the following priority order:
Priority One: Landmark trees; significant trees that form a continuous canopy; significant
trees on slopes greater than twenty percent (20%); significant trees adjacent to critical areas
and their associated buffers; significant trees over sixty feet (60') in height or greater than
eighteen inches (18") caliper; and trees that shelter interior trees or trees on abutting
properties from strong winds, which could otherwise allow such sheltered trees to be blown
down if removed.
Priority Two: Healthy tree groupings whose associated undergrowth can be preserved; other
significant native evergreen or deciduous trees; and other significant non-native trees.
Priority Three: Alders and cottonwoods shall be retained when all other trees have been
evaluated for retention and are not able to be retained, unless the alders and/ or
cottonwoods are used as part of an approved enhancement project within a critical area or
its buffer.
The Administrator may require independent review of any land use application that involves
tree removal and land clearing at the City's discretion.
The Administrator may authorize the planting of replacement trees on the site if it can be
demonstrated to the Administrator's satisfaction that replacement requirements in RMC 4-4-
130H.1.e can be met.
Unless exempted by critical areas, RMC 4-3-050C, no tree removal, or land clearing, or
ground cover management is permitted within critical areas or associated buffers. It is
expected that removed significant trees will be replaced based on the tree credit value of
each significant tree removed.
3. Fences/Retaining Walls: Fences or retaining walls installed as part of this project must be
designated on a landscape plan and grading plan with top of wall and bottom of wall
elevations. A fence and/or wall detail should also be included on the plan. A retaining wall
SCWSD - Lift Station #5B North Force Main Replacement
Page 4 of 5
December 19, 2024
that is 4 feet or taller, as measured by the vertical distance from the bottom of the footing to
the finish grade at the top of the wall requires a building permit. The maximum height of any
fence or retaining wall is 72-inches subject to further height limitations in setbacks and clear
vision areas noted in RMC 4-4-040D. A fence shall not be constructed on top of a retaining
wall unless the total combined height of the retaining wall and the fence does not exceed the
allowed height of a standalone fence. For more information about fences and retaining walls
refer to RMC 4-4-040.
4. Critical Areas: According to COR Maps, the following critical areas are mapped on and around
the project site: high erosion hazard areas, 100-year floodway and flood plain, high seismic
hazard areas, a Type F stream (Big Soos Creek), wetlands and a zone 2 wellhead protection
area. The overall purpose of the wellhead protection regulations is to protect aquifers used
as potable water supply sources by the City from contamination by hazardous materials. Some
uses are restricted that store, handle, treat, use, or produce substances that pose a hazard to
groundwater quality. Development within high seismic hazard areas require a geotechnical
study completed by a licensed professional.
A geotechnical report may be required based on the final proposed scope of work. A wetland
report and standard stream study prepared by a qualified biologist would be required to
demonstrate compliance with the Critical Areas Regulations RMC 4-3-090. If the proposal
requires mitigation for impacts to the existing vegetation buffer in order to demonstrate no
net loss of ecological functions, a supplemental stream study and mitigation plan would be
required. It is the applicant’s responsibility to determine whether any other critical areas
are present on the site prior to formal land use application.
5. Environmental Review: The proposal would require environmental review pursuant to the
State Environmental Policy Act (SEPA) in accordance with WAC 197-11-800. An Environmental
Checklist must be submitted with the proposal and the City’s Environmental Review
Committee is required to issue a Threshold Determination prior to any issuance for permits
on the site.
6. Conditional Use: A conditional use is a land use which may be permitted within a zoning
district following review by staff to establish conditions mitigating impacts of the use and to
assure compatibility with other uses in the district. Staff will consider the following criteria
when reviewing a request for a conditional use permit:
a. Consistency with Plans and Regulations: The proposed use shall be compatible with
the general goals, objectives, policies and standards of the Comprehensive Plan, the
zoning regulations and any other plans, programs, maps or ordinances of the City of
Renton.
b. Appropriate Location: The proposed location shall not result in the detrimental
overconcentration of a particular use within the City or within the immediate area of
the proposed use. The proposed location shall be suited for the proposed use.
c. Effect on Adjacent Properties: The proposed use at the proposed location shall not
result in substantial or undue adverse effects on adjacent property.
d. Compatibility: The proposed use shall be compatible with the scale and character of
the neighborhood.
e. Parking: Adequate parking is, or will be made, available.
SCWSD - Lift Station #5B North Force Main Replacement
Page 5 of 5
December 19, 2024
f. Traffic: The use shall ensure safe movement for vehicles and pedestrians and shall
mitigate potential effects on the surrounding area.
g. Noise, Light and Glare: Potential noise, light and glare impacts from the proposed use
shall be evaluated and mitigated.
h. Landscaping: Landscaping shall be provided in all areas not occupied by buildings,
paving, or critical areas. Additional landscaping may be required to buffer adjacent
properties from potentially adverse effects of the proposed use.
7. Permit Requirements: The proposed project would require Environmental (SEPA) Review and
may require an Administrative Conditional Use Permit. The applications would be reviewed
concurrently within an approximate timeframe of 6-8 weeks. The 2025 application fees would
total $3,897.60 ($1,856 Conditional Use Permit review + $1,856 SEPA Review + $185.60 5%
technology fee = $3,897.60). Any modification requests to code standards are $299.00 per
modification + an additional 5% technology fee. All fees are subject to change prior to
submittal. Detailed information regarding the land use application submittal can be found on
the City’s Permit Center website. The City requires electronic plan submittal for all
applications.
8. Waivers of Submittal Requirements: The submittal checklist is not an exhaustive list of
submittal requirements and may be modified in cases where additional information is
required to complete the review of an application. In addition, non-applicable submittal
requirements may be waived. The applicant should contact the assigned Project Manager if
there are any questions regarding submittal requirements.
9. Public Information Sign: Public Information Signs are required for all Type II and Type III Land
Use Permits as classified by RMC 4-8-080. Public Information Signs are intended to inform the
public of potential land development, specific permits/actions being considered by the City,
and to facilitate timely and effective public participation in the review process. The applicant
must follow the specifications provided in the public information sign handout. The applicant
is solely responsible for the construction, installation, maintenance, removal, and any costs
associated with the sign.
10. Impact Fees: It is not anticipated that there would be impact fees associated with the project.
A handout listing all of the City’s Development related fees is available for your review at
https://edocs.rentonwa.gov/Documents/Browse.aspx?id=8217302&dbid=0&repo=CityofRe
nton.
11. Next Steps: When the formal application materials are complete, the applicant shall have the
materials pre-screened prior to submitting the complete application package. Please contact
Jill Ding, Senior Planner, at 425-430-6598 or jding@rentonwa.gov to submit prescreen
materials and subsequent land use application.
12. Expiration: Once the Conditional Use Permit application has been approved, building permits,
licenses or land use permits required for the operation of a Conditional Use Permit shall be
applied for within two (2) years of the date of Conditional Use Permit approval, u nless an
extended time frame is granted by the Administrator or Hearing Examiner. A single two (2)
year extension may be granted for good cause by the Administrator. It is the applicant’s
responsibility to monitor the expiration dates.