CONSTRUCTION MITIGATION
Project: SEA MILL AVE- Verizon
Project Location: 304 MAIN AVE S
Parcel: 7231500720
Zoning: CD – CENTER DOWNTOWN
Proposal:
Verizon is proposing to construct an unmanned telecommunications facility on the facade of an existing
commercial building. The existing parking lots will be utilized for construction staging and execution.
Construction Dates:
Current forecast is for work to occur approximately between 7/17/18-8/14/18.
Hours/Days of Operation:
The wireless site will be on-air 24/7, once constructed. It is a passive use, and unstaffed except for an
occasional technician visit, 1-2x per month on average.
Proposed Hauling/Transportation Routes:
The construction access will be via the existing driveways leading to the property, from Main Ave S. on
the west side of the property and Houser Way S from the north side of the property. Construction debris
will be minimal, as the proposed project is the installation of wireless equipment on the façade of an
existing commercial building, not building demolition. Off-site warehousing locations for the proposed
wireless equipment and shroud materials is TBD, as is the contractor assignment.
Measures to Minimize Construction Impacts:
The project is of short duration and is not anticipated to generate mud, erosion, or substantial noise that
would impact adjacent properties. The construction will be coordinated with the property, based on
their current business needs, so that the project does not interfere with their existing tenants’ or lot
users’ access and preserves the on-site parking in the lot that will be shared for construction staging.
Construction Hours:
Construction hours will be negotiated with the property owner. Business hours are preferred, but
weekend or evening hours may be requested if the tenant needs at the time of construction place spots
at a premium. Hours are expected to be subject to City input regarding noise ordinances and project
approval conditions. Weekend and evening construction hours are not expected to impact adjacent
property uses.
9725 3rd Ave NE, Suite 410, Seattle, WA 98115
Traffic Control:
The location of the construction is not in right-of-way, and is more than 15 feet from the edge of the
roadway. Staging and parking for construction machinery and vehicles will be in the parking lot adjacent
to the office building, on private property.
Project Contact:
Becky Todd
MD7 on behalf of Verizon Wireless
206-310-1793
btodd@md7.com
9725 3rd Ave NE, Suite 410
Seattle, WA 98115