HomeMy WebLinkAboutR-3693158C'')
rn
(D
ce)
O
LLI
F_
NOTES:
1. PILES SHALL MEET THE MATERIAL REQUIREMENTS OF ASTM A252.
GRADE 3 WITH A MINIMUM YIELD STRENGTH OF 50 KS] OR APPROVED
EQUIVALENT AND SHALL BE DRIVEN IN ACCORDANCE WITH PROJECT
SPECIFICATIONS AND THESE NOTES.
2. ALL DIMENSIONS ARE GIVEN AT PILE CUTOFF.
3. STEEL CONICAL PILE POINTS WITH DULL TIP SHALL BE WELDED ONTO
ABUTMENT PILES AND PIER PILES. REINFORCED TIP SHALL BE FLUSH
WITH OUTSIDE OF THE PILE. THE CONTRACTOR SHALL ANTICIPATE
OBSTRUCTIONS CONSISTING OF COBBLES. BOULDERS AND LOGS DURING
THE PILE INSTALLATION.
4
THE CONTRACTOR SHALL FOLLOW ANY NOISE ORDINANCE ESTABLISHED BY
THE CITY OF RENTON. A TIME LIMITATION ON PILE DRIVING ACTIVITY
MAY BE IMPLEMENTED AND THE CONTRACTOR MAY BE REQUIRED TO PROVIDE
A SOUND SHIELD DURING PILE DRIVING ACTIVITIES IF THE NOISE
ORDINANCE CANNOT BE MET.
5. THE CONTRACTOR SHALL MONITOR FOR VIBRATION AND LOCAL GROUND
SETTLEMENT WITHIN 20 FT. OF THE PILE BEING DRIVEN. THE
CONTRACTOR IS RESPONSIBLE FOR ANY VIBRATION INDUCED DAMAGE TO
ALL ADJACENT STRUCTURES SUCH AS RAILROADS AND UTILITIES.
Notes:
1. Rotate leg of hook bar to ovoid interference with other
bars.
2. Headed studs shall meet the requirements of section 7 of
the current A.W.S. structural welding code D1.1 for grade
1020 solid flux fixed headed studs. Headed studs shall be
outomlotically end welded with complete fusion in
accordance with section 7 of the current A.W.S.
structural welding code 01.1
3. The cost of headed studs and pile reinforcement (RC1) and
installation are incidental to the cast of the structural
steel pile.
4. The quantity of concrete used to fill the piles is
not included in C.I.P. Concrete Class 40 Ouantitles for
Slab/Footings. Concrete to fill piles shall be WSDOT Class
4000P concrete.
5. Piles shall be filled with concrete on a day
with a minimum temperature greater than 40'F.
After the piles are filled with concrete. the
Contractor is responsible for nuintoining on
ombient air temperature above 40'F surrounding
the exposed piling until the footing slob is poured.
PILE DATA TABLE
DESCRIPTION
N0.
SIZE
CUTOFF
ELEV.
ESTIMATED
TIP ELEV,
MINIMUM
TIP ELEV.
ESTIMATED
LENGTH (FT.)
MAX. DESIGN LOAD (KIPS)
COMPRESSION
I * LC
TENSION
* LC
FOUNDATION SLAB
1 110
24" DIA. w/ 1.2" WALL
1 0.00
-86.5
-86.5
86.5
1 479
1 GM3
MGM3
6. THE CONTRACTOR SHALL FURNISH THE MANUFACTURER'S SPECIFICATIONS
AND CATALOG FOR THE PILE DRIVING HAMMER PROPOSED. AT A MINIMUM.
THE CONTRACTOR SHALL FURNISH THE INFORMATION ON THE PILE DRIVING
EQUIPMENT DATA SHEET FOUND IN THE SPECIAL PROVISIONS. IF THE
PROPOSED HAMMER IS FOUND INSUFFCIENT BY THE OWNER, RE -MOBILIZING
AND REPLACING EQUIPMENT SHALL BE AT THE CONTRACTOR'S EXPENSE.
7. ALL PILES SHALL BE DRIVEN TO THE MINIMUM PILE TIP ELEVATION
SPECIFIED AND TO THE REQUIRED FINAL DRIVING RESISTANCE AS
DETERMINED BY WAVE EQUATION ANALYSIS FOR PILE DRIVING (WEAP)
WITHIN THE LAST FOOT, IN THE EVENT THE PILE DRIVING
* GROUP LOADING COMBINATIONS ARE FOR SERVICE LOAD DESIGN PER
A.R.E.M.A. CHAPTER B. SECTION 2.2.4 d 4.2.2. AND CHAPTER 9.
SECTION 1.4.6.
ESTIMATED QUANTITIES
DESCRIPTION I EST. LENGTH (FT.) QUANTITY
FURNISH d INSTALL STRUCTURAL STEEL PILES (CLOSED END 24" DIA. PIPET I LF 9.515
RESISTANCES AT THE MINIMUM PILE TIP ELEVATION ARE LESS THAN
THE MINIMUM PILE DRIVING CRITERIA SET FOR THE PROJECT.
THE CONTRACTOR SHALL CONTINUE DRIVING UNTIL THE REQUIRED DRIVING
RESISTANCE IS MET, EXCEPT FOR PILES THAT ARE WITHIN 6" OF
FINAL CUTOFF. FOR PILES THAT ARE WITHIN 6" OF FINAL CUTOFF
DRIVING MAY BE DISCONTINUED FOR AT LEAST 24 HOURS AND REDRIVEN
UNTIL THE MINIMUM DRIVING RESISTANCE IS ACHIEVED. `rj�����/ L3L-
IF THE RESTRIKE RESISTANCE DOES NOT ACHIEVE THE KK /_ Cc ` J 3
SPECIFIED VALUES. THE ENGINEER WILL DETERMINE THE SUBSEQUENT /N47 /N /
PROCEDURES TO BE TAKEN. SHOULD THE MINIMUM PILE DRIVING RESISTANCE
BE ACHIEVED ABOVE THE MINIMUM PILE TIP ELEVATION, THE PILES SHALL
BE DRIVEN TO "REFUSAL" WITHIN THE SPECIFIED NON-LIOUIFIABLE LAYER,
TO THE REQUIRED DEPTH. WITHOUT OVERSTRESSING THE PILE SECTION.
"REFUSAL" WILL BE DETERMINED BY THE ENGINEER.
B. A TEST PILE PROGRAM BY PERFORMING DYNAMIC PILE TESTING WITH A
PDA (PILE DRIVING ANALYZER) AND CAPWAP ANALYSES (CASE PILE WAVE dG
ANALYSIS PROGRAM) SHALL BE UNDERTAKEN TO ESTABLISH DRIVING bl� 1
CRITERIA AND DETERMINE LENGTHS FOR PRODUCTION PILES, PILES SHALL
BE DRIVEN TO A MINIMUM ULTIMATE RESISTANCE OF 479 TONS.
9. CHECK ALL PILES FOR POSSIBLE HEAVE PRIOR TO CUTOFF BY
SURVEYING THE ELEVATION OF EACH PILE BUTT AFTER A PILE IS
DRIVEN WITHIN THE GROUP. THE HEAVE DATA SHOULD BE PROVIDED
TO THE ENGINEER TO DETERMINE IF REDRIVE IS REQUIRED. IN
GENERAL, IF THE HEAVE IS GREATER THAN 0.25 INCH. THE PILE
SHOULD BE REDRIVEN TO THE ORIGINAL PILE TIP ELEVATION. FOR
PILE GROUPS. THE CENTRAL PILES SHOULD BE DRIVEN FIRST AND
SUBSEQUENT PILES SHOULD BE INSTALLED FROM THE CENTER OUT.
10. NO SPLICES WILL BE PERMITTED IN THE UPPER 30 FEET OF THE
PILES, MEASURED FROM THE PILE CUTOFF ELEVATION. DRIVE SPLICES
ARE NOT PERMITTED AT ANY LOCATION.
11. ALL WELDING SHALL CONFORM TO THE REQUIREMENTS OF THE
STRUCTURAL WELDING CODE AWS D1.1.
12. NONDESTRUCTIVE TESTING - THE ENTIRE LENGTH OF THE COMPLETE
JOINT PENETRATION GROOVE BUTT WELDS OF PILE SPLICES SHALL BE
EXAMINED BY ULTRASONIC TESTING. THESE INSPECTIONS SHALL BE IN
ACCORDANCE WITH THE STRUCTURAL WELDING CODE AWS D1.1.
9---IF---I-9
QII
5 c: a-%4600,'
o -,
NOTE A•'
THE CONTRACTOR SHALL FURNISH CONICAL PILE POINTS CONSISTING
OF A SINGLE PIECE AS SHOWN. THE PILE POINTS SHALL BE CAST
IN ONE PIECE STEEL ACCORDING TO ASTM A 148 RADE 90-60
(A.A.S.H.T.O. M 103 GRADE 65-35) AND SHALL PROVIDE FULL
BEARING OVER THE FULL CIRCUMFERENCE OF THE PILE. THE PILE
POINT SHALL HAVE TAPERED LEADS TO ASSURE PROPER ALIGNMENT
AND FITTING AND SHALL BE SECURED TO THE PILE WITH A
CIRCUMFERENTIAL WELD.
KFA 00076
Steel Pile
STEEL CONICAL PILE POINT
(See Note A)
/Shop or
\Field Weld d
Steel Pii
RC1- See reinf. cage See Note 1 d Section A -A
detail this Sheet
C.I.P. Class 40
Conc.Foundction
Slab
A I I ---
i I A
c
10
M r---- r
----fir Top of pile
= w
24" dio. pipe pile headed studs field
'\ I 10 - #7 Hook Bars (IT wall thickness) welded to pile W
equally spaced - even spacing
Concrete to fill pipe -
piles shall be WSDOT
ti -
G�T aI� #5 Hoop Tie
Edge of Foundation Slab
(Maintain 4" clearance w/ Hook Bars)
SECTION A -A
(Shear Studs not shown for clority)
PILE SPLICE DETAIL
23>+,
Clr.
t— — C
I I�
---- 1 N
24" DIA. PIPE PILE
Ties @ 4
#5 Hoop Ties - splice
shall be mode by butt
splice. Reber shall
be ASTM A706.
%Zlc/ 00033
0 0
E U
+ m
o
co a + 10-#7 Hook Bars.
r-1- rr -1-1- -1 T__r - , - ��equally spoced.
No splice permitted.
Field fabricated I I I I I I I I I I I I I I I I I jl Reber shall be ASTM
A706.
or comrc i a l I I I I I I I I I I I I I I I I I I me
backing ring I I I I I I I I I I I I I I I I I I I I \
o
Top of Pile o
i
-vj I 27'A"
29'-91r2' S�c�77i'1/ ��h�•l � Y�i
REINFORCING CAGE - RC1
10-#7 Hook Bars
83-#5 Hoop Ties
Weight (Each Cage) = 817 Lbs.
5ubrll�i��1 0�.�3� Z
R-3693158
FED: ID: STPUL-1276(004)
HPP-1276(005)
') BergerABAM
�I
33301 9th Avenue South, Suite 300
Federal Way, Washington 98003-2600
(206) 431-2300 Fax: (206) 431-22SO
'
IIIIII HANSON
®Copyright Hanson Professional Services Inc. 2011
a1ME1°
ors sr+owN
�" '�'^�
DATUM
CITY OF
RENTON
Public Works Deportment
A roved For Construction
PP
Robert M. Hanson P.E. Dote
STRANDER BOULEVARD EXTENSION
PHASE 1, SEGMENT 2A
BNSF BRIDGE N0.11.07 L.S. 0051
PILE DETAILS
12/05/11
RECORD DRAWINGS 7/31/2014
°"�`ina
"aoaaa
CALL 48 HOURS
BEFORE YOU DIG
1-800-424-5555
'"" CDP
��.,� 1
r..�i':cco.o
RA-13
oxccu
,,,�,
NO.
REVISION
BY
DATE
APPR
,,,,,,,f,
s 1 69'231