Loading...
HomeMy WebLinkAboutRSD Transportation Center Expansion - Civil - EV Deviation Request Letter_V1_250203 255 S. King Street, Suite 800, Seattle, WA 98104 | 206.426.2600 | JACOBSONENGINEERS.COM February 3, 2025 Clark Close Current Planning Manager City of Renton Community and Economic Development 1055 S Grady Way Renton, WA 98057 Re: RSD Transportation Center Expansion – EV Parking Exception Request Letter Dear Mr. Close, The project proposes expanding the existing transportation center parking lot in the NW corner of the property (parcels 7224000676 and 7224000675), which will consist of a new paved parking lot with sidewalks, landscaping, and a public amenity space at the northwest corner of the site adjacent to the public right-of-way. Additionally, some right-of-way improvements are proposed to remove existing driveway access to the parcels and replace them with new concrete sidewalks and curbs/gutters. The Renton School District’s Transportation Center is located at 420 Park Ave N in Renton. As part of the parking lot expansion project (see Figure 1 below), a total of 32 standard parking stalls (9’X20’) and 12 angled parking stalls (9’x20’x60O) are being proposed to be constructed with the standard stalls slated to be used by School Bus Driver’s vehicles and the angled stalls to be used by Renton School District Fleet vehicles (i.e. Shuttle Bus or equivalent). Figure 1 255 S. King Street, Suite 800, Seattle, WA 98104 | 206.426.2600 | JACOBSONENGINEERS.COM It is our understanding that the project shall also provide Electric Vehicle Charging Infrastructure per the Washington Administrative Code (WAC) Section 51-50-0429. This WAC Code requires the construction of new buildings and accessory structures, which may include parking lots, to account for 10% of the total parking spaces to have EV charging capability. Table 429.2 of the WAC Code defines the requirement based on the International Building Code (IBC) occupancy classifications. Our interpretation of WAC Code Section 51-50-0429 is a minimum of (5) five parking spaces would be required to have infrastructure installed and be EV Charging Ready. The project would also be required to install vaults/handholes and conduits with terminated wires for (5) additional parking spaces for future EV Charges. The project also be required to provide infrastructure and be EV Charging Ready for the (1) Accessible Parking Space located in the SE corner of the proposed parking lot. In addition, an EV Capable Vault would need be installed for (5) additional future chargers – see Figure 2 below. Figure 2 Based on these additional requirements by the WAC for this project, there is a potential for 16 total parking spaces that could not be used by Renton School District staff in the standard parking stall lot, which would leave only 16 parking spaces that could be utilized. The EV charging station infrastructure requirements for the project may leave the school district with potentially unusable parking spaces for non-electric vehicles, significantly increasing the construction costs per parking space and for the EV infrastructure installation. 255 S. King Street, Suite 800, Seattle, WA 98104 | 206.426.2600 | JACOBSONENGINEERS.COM Furthermore, when interpreting the WAC Code, the project is not constructing any new buildings that would be tied to this parking lot. There is an existing building and the parking lot is possibly considered an accessory structure, however, the parking lot will be used by school bus drivers who would have an access card to gain access through the new pedestrian gate in SE corner of the expanded parking lot, then walk over to the bus parking lot on east side of existing transportation facility property. They would not be accessing or working inside the existing building. Because of this interpretation, we believe EV parking stalls aren’t required for the new parking lot expansion project and would therefore request that the provisions for EV Parking Infrastructure be removed for this project. Thank you for your consideration and time in reviewing this exception request. Should you have questions, or if I can provide you with additional information, please feel free to contact me at (206) 293-9134 or sascha@jacobsonengineers.com. Regards, Sascha Eastman, P.E., Senior Project Manager Attachment: C010 OVERALL SITE PLAN and C501 PAVING PLAN (11x17’s) NOTE: SHEET HAS BEEN PRINTED TO BE 11X17 AND NOT TO SCALE EV Capable - vault near parking stalls for future (5) chargers EV Ready - (2) vaults/handholes with terminated wires near parking stalls for future (5) chargers EV Charging - (3) vaults/handholes with terminated wires and chargers for (5) chargers (2 doubles, 1 single) EV Accessible Charging - (1) vault/handhole with terminated wires and chargers for (2) chargers (1 doubles) GATE WITH CARD READER NOTE: SHEET HAS BEEN PRINTED TO BE 11X17 AND NOT TO SCALE STANDARD PARKING STALLS ANGLED PARKING STALLS