Project Memo Page 2 of 4 Renton School District Transportation Lot Expansion
2240590.30
October 16, 2024
Urban Design District D standards. Landscaping consists of approximately 5,743 SF of total ground
cover, including interior as well as landscaping strips adjacent to the sidewalk on the north and west
side of the two parcels. In addition, four catch basins and associated storm drainage piping, as well as
a heat pump will be removed as part of the demolition activities for the project.
Currently there are 13 significant trees on-site, five of those are intended to be removed due to
construction requirements. The eight remaining trees will be protected in compliance with Renton
Municipal Code requirements. 16 new trees will be planted.
Proposed filling, excavation, and grading is to support the new structure and for general site
improvements. Total excavation is 39 CY, total earthwork proposed is 401 CY. Materials used for fill will
be imported from clean, local sources.
Criteria for CUP approval (4-9-030-D)
The following are the criteria for CUP approval followed by applicant responses in bold text.
-
--
-
-