HomeMy WebLinkAboutCAG-20-065 -Duvall - Construction Meetings - Progress Meetings CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
May 09, 2023
Comments made during the Meeting are shown in italics
Meeting Attendees
Bob Hanson, City of Renton Joel McCann, City of Renton x
Flora Lee, City of Renton x Tani Stafford, G&O x_
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad,
Renton School District _
Michael Sippo, City „f Yong Qui, City of Renton
Renton
Justin Johnson, City of Ross Widener, Widener & As oc.
Renton
1. Safety Report — No issues
2. Prior Meeting Minutes—Comments/Acceptance — Accepted
3. Weekly Statement for Working Days ending May 08, 2023
Days Expired: 273.5
Days Remaining: 3.5
4. Schedule Progress
Contractor's Look Ahead Schedule — Electrical work completed
today, anti-graffiti pant tomorrow.
Page 1 of 3
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. RSD Elementary School 16 Coordination—
Suspend, then thermoplastic and paint next. Looking to add two days
for extra paint work. Installation of plastic over paint to be checked
• Signal pole at NE 10th Street arrives 5/26, coordinate with remaining
striping
6. Engineer's Report
a. Monument— cast in place concrete used to form monument below
the case, the concrete is required to be independent of (not
touching) the monument case. The restoration outside the case
may be all HMA. Approx. 3 days out to stamp monuments.
b. PMX to do as-built survey of face of curb after the monuments are
stamped.
7. Inspector's Report
■ Contractor is ready for City teams to come out do final
punchlist work walk through.
■ Signs R-10 school speed limit sign and R-21 School
reduced speed limit ahead have not been installed yet.
8. Environmental Compliance Report— gone
9. Public Outreach — no new outreach.
10.Submittals/Documentation
a. Review ROM — current ROM is on the CMS
b. Material Submittals complete
c. Non-Material Submittals needed: Survey Monument DNR forms,
Recycled Material Form at project completion
11. RFIs— nothing new
12. FWD/ Change Orders—
Page 2 of 3
r ..
if? CITY OF RENTON
DUVALL AVE NE
• E N T° CAG-20-065
• CO No 33 Restripe Longitudinal Lines? Tani sent limits of proposed
paint refresh. Is unit bid price acceptable?
13.Subcontractor Status— no issues
14.Certified Payrolls —
Propess Payment No 16(Axil) Progress Payama No 17(May)
Week Ead ag Oa: 8-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jr
Reed Trucking No Work 20-Apr 1-May No Work
'W.E.Coates 20-Apr No Work No Work X X
Puget Construction No Work No Work 1-May X
Transportation Systems(Concrete) No Work 2-May 2-May
Transportation Systems(Electrical) 2-May 2-May 2-May
Evergreen Sawctating No Work No Work No Work X X
Ground Up No Work No Work X X X
Stripe Rite No Work X X X X
Green City No Work 1-May X X
Integrity Networks No Wok No Work No Work X X
CAP Fencing X X X X
Week Contractor Subcontractor is on the job site,payroll required. **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
jApprenticeship doc's required
- -
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
15.Progress Payment—
• Progress Payment No 16 — City processing
• Progress Payment No 17 — Final Progress Payment, May 31, 2023
cutoff. City needs documentation by June 7, 2023.
Other Items:
12th and Duvall intersection: complaint filed Friday May 5 about a loose
water valve lid. Joel noted it had been put back on with sealant added to
keep in place.
Page 3 of 3
CITY OF RENTON
%IR DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
May 02, 2023
Comments made during the Meeting are shown in italics
Meeting Attendees
Bob Hanson, City of Renton x Joel McCann, City of Renton x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad,
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Renton
Justin Johnson, City of Ross Widener, Widener & Assoc. x
Renton
1. Safety Report — No issues
2. Prior Meeting Minutes—Comments/Acceptance — Accepted
3. Weekly Statement for Working Days ending May 01, 2023
Days Expired: 268.5
Days Remaining: 8.5
4. Schedule Progress
Contractor's Look Ahead Schedule — Work 5/3, then suspension, then
resume 5/8 for pole and monuments.
Page 1 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. RSD Elementary School 16 Coordination —
• Schedule for signal foundations at NE 10th ? Not an issue
• Signal pole arrives 5/26
• Can topsoil that was placed in planter strip near School frontage,
west side of Duvall Ave NE, north of NE 10th St. remain? No, topsoil to
be removed.
• NPDES in place to protect Filterras Dustin to ask Contech if they can
plant trees now. School to protect from their construction water.
Question on if school will water trees.
6. Engineer's Report
a. Cure time for grout at street light L08 anchor—7 days required
b. Street Light Thread update— L02, L12, L10, L18, L11 need
adjustments for anchor bolt thread reveal Finish tomorrow
c. PMX to do as-built survey of face of curb Tani to ask for horizontal
alignment survey notes
d. FH paint color -Joel to get new paint spec
7. Inspector's Report
• City teams to come out once most of the preliminary
punchlist work is complete. Dustin to let us know when
most is completed.
• Limits for longitudinal paint line restripe Tani to send to
Dustin to confirm price
8. Environmental Compliance Report— Ross to look over
9. Public Outreach — no new outreach.
10.Submittals/Documentation
a. Review ROM — current ROM is on the CMS
b. Submittals under review: none
c. Material submittals that need to be submitted: Joel
to take pic's
Page 2 of 4
CITY OF RENTON
DUVALL AVE NE
1
CAG-20-065
d. Non-Material Submittals that need to be submitted: Survey
Monument DNR forms, Recycled Material Form at project
completion
e. Material Documentation — no issues
11. RFIs — nothing new
12. FWD/ Change Orders —
• CO No 31 restake of the monument. —To City for final sigs
• CO No 32 wood fence —To City for final sigs
• CO No 33 Restripe Edge Line? Tani to send limits of paint refresh
13.Subcontractor Status— no issues
14.Certified Payrolls —
Progress Parneat No 16(Aril) Progress Payment No 17(May)
Week Eliding Oa: 9-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3Jaa
Reed TnKk6sg No Work 20-Apr
W.E.Coates 20-Apr No Work X
Puget Construction No Work No Work X
Transportation Systems(Concrete) X X X
Transportation Systems(Electrical) X X
'Evergreen Sawcuttmg No Work No Work X
Grand Up X X X
Stripe Rite No Work X X
!Green City No Work X _
integriy Networks _No Work X
Week Contractor/Subcontractor is on the job site,payroll required- **(o122)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
. Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
-Feb "Final"payroll
Page 3 of 4
CITY OF RENTON
iRDUVALL AVE NE
CAG-20-065
15.Progress Payment—
• Progress Payment No 16—April 28, 2023 cutoff, City needs
documentation and signed PP by May 4, 2023. Draft sent to Reed
for review
• Progress Payment No 17 — Final Progress Payment, May 31, 2023
cutoff. City needs documentation by?May 315t good if paint line
and plastic can be scheduled.
Other Items:
Discussed field modification for CO 24 work, sonotube was temporarily
needed for the work per the subcontractor. The cardboard sonotube was
removed from the foundation anchor holes prior to placing grout around
the anchor rods.
Page 4 of 4
REEDc Date:4/29/23-5/19/23 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
11ua11•91.in Ci it Cr.trvn.r wont.1991
April May
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes / Resources
29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Illumination critical path X X X X
Seeding window begins 3/1 also
landscaping critical path wanting illumination complete prior to
X X final restoration
thermoplastic Critical path ? ? ? Scheduled long wait list!
Fencing X X
Monuments X
Punchlist work X X X
Suspension for ThermoPlastic _ — —
X X _ X X X X X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
APRIL 18, 2023
Comments made during the Meeting are shown in italics
Meeting Attendees
Bob Hanson, City of Renton x Joel McCann, City of Renton x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Re iton
Justin Johnson, City of Ross Widener, Widener & As oc.
Renton
1. Safety Report— Nothing
2. Prior Meeting Minutes —Comments/Acceptance —Accepted
3. Weekly Statement for Working Days ending April 17, 2023
Days Expired: 264.5
Days Remaining: 12.5
4. Schedule Progress
Contractor's Look Ahead Schedule —
Fence, then hydroseed, then monuments. One more day of work before
suspension. Lift suspension next week when weather is better.
Page 1 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. RSD Elementary School 16 Coordination —
• Lane Closures/ traffic control:
• Start signal foundations at NE 10th in 2-3 weeks
• Signal pole arrives 5/26
• Question on topsoil that was placed in planter strip near School
frontage, west side of Duvall Ave NE, north of NE 10th St. Can it
remain?
• Discussed hydroseed areas need to be completed in order to activate
Filterras and school frontage may drain to some of the Filterras
• Construction runoff may have filled filterra
6. Engineer's Report
a. Cure time for grout at street light L08 anchor — 7 days required
b. Street Light Thread email sent — any issues — City to inspect the
threads
c. Discuss grout of necks of CB's. Do not cover over the mortared joints.
7. Inspector's Report
■ City Preliminary punch-list status. City teams to come
out once most of the preliminary punchlist work is
complete. Dustin to let us know when most is completed.
8. Environmental Compliance Report— Silt fence at 4th until final
seeding. All other BMPs have been removed.
9. Public Outreach — no new outreach.
10.Submittals/Documentation
a. Review ROM — current ROM is on the CMS
b. Submittals under review: none
c. Material submittals that need to be submitted: L08 Foundation
Modification shop drawings
Page 2 of 4
CITY OF RENTON
MIRDUVALL AVE NE
N CAG-20-065
d. Non-Material Submittals that need to be submitted: Survey
Monument DNR forms, Recycled Material Form at project
completion, Project Redline Resubmittal.
e. Material Documentation — no issues
11. RFIs— nothing new
12. FWD/ Change Orders —
• FWD No 35 (Draft in the works) for wood fence in gap —waiting on 2
quotes from Dustin Sent 4/18/23
• CO No 31 restake of the monument. — Draft sent to Dustin.
• CO No 32 wood fence — pending quote In the works
• CO No 33 quantity reconciliation - hold Internal CO
13.Subcontractor Status— no issues
14.Certified Payrolls—
Pooh...hyrM No 14 bhaea y) Para hymnaa No 15(Fokramny) Fans hymnal No 16(Muey
Week Wag Oa 31-Doe 7-Jan 14-Jn 11-Jan Mho 4-Fob 11-Fob 16Pob 25-F.b 4-She 11-Moe 111-Mos IS-Mae 1-Apr
Reed Madan{ No Work 11-Jet 20-ha 26Jos I-Feb 6-Feb 15-Feb 22-Feb No Work No Work No Work No Wadi No Work 6-Apr
WE.Cores No Work No Wok No Work 31-3a I-Feb No Work No Work No Week No Work No Work 20-Mar X X X
PaD Loggia No Week No Week No Work No Wok No Work W X X X X X X X X
Pup Camnucia No Wok No Work No Work No Weds No Work No Work No Work No Wok No Work No Work No Wok No Wok No Weak No Wags
Caere*Services No Work No Work No Work No Week Whoa X X X X X X X X X
Trerparam Syoems(Cmaae) _ No Work 3-Feb 3-Feb 3-Feb 8-Frb IS-Feb 28-Feb No Work No Work 10-Mr 20-Mr No Wok No Work No Work
Traspataim Syssems(FJecoical) _ No Work No Work No Work No Work No Work No Work No Work 21-Feb No Work No Work No Work No Work 7-Ape No Wok
Evergreen Saw vtiy No Work No Work No Work No Week No Work No Work No Work No Work No Week No Work No Work No Work No Work No Work
Goad Up No Week No Week No Work No Wok No Work No Work No Week No Wok No Work No Wak No Work No Wok No Work No Work
Tyre Concrete No Work No Week No Week No Wak .: X X X X X X X X X
Snipe Rite No Wok No Work No Work No Week 30-Jai IS-Feb No Work No Work No Work No Week No Work No Work No Wok No Wade
Green City No Week 23-Jet 27-Ls 3-Fab 3-Feb 13-Feb No Week 21-Feb No Week No Wade No Week X X X
lore®iy Networks X X X I5-Feb 15-Feb 1S-Feb No Wok No Wadc No Work No Work No Wok No Work No Work No Work
Papas Papaw No 16(Api)
Week Eden Oa: 1-Apr IS-Apr 22-Apr 19-Apr
Reed?name No Wadi
WE.Cores X
Puget Construction No Week
Teaspanra Syoeem(Cmae) X
Trmspateieo Syoemaeadnp X
_Evergreen Swede{ X
Goad Up X
Saipe Ri, No Work
Gras City X
Malty Networks No Week
Page 3 of 4
CITY OF RENTON
+ DUVALL AVE NE
f.
CAG-20-065
Week Contractor Subcontractor is on the job site,payroll required. **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
NMICorrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Rork Received"No Work Performed"payroll
15-Feb "Final"payroll
15.Progress Payment—
• Progress Payment No 16 — April 28, 2023 cutoff, City needs
documentation and signed PP by May 4, 2023. Will there be 1
remaining PP after this one, or can the thermoplastic be
scheduled sooner to fit within the timeline for one PP ending in
April?
• Progress Payment No 17— Final Progress Payment
Other Items:
Do not push for thermoplastic installation. Wait for warm/dry conditions
Re-paint lines that were worn away by traffic shift
Redo lines/bike lane on west side —South of 10th west side (Joel to confirm
limits)
City to send Parametrix survey request for curb line as-built— 10th to tie in
near Sunset
Page 4 of 4
CITY OF RENTON
iRDUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
APRIL 11, 2023
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Huy Huynh, City of Renton
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener & x
President, Reed Trucking & Assoc.
Excavating Inc. Joel McCann, City of Renton
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer_Rogstael
Renton School District ,
Michael Sippo, City of Yong Qui, City of Renton
Renton
Justin Johnson, City of Ross Widener, Widener & Assoc.
Rcnton
2. Safety Report — No issues
3. Prior Meeting Minutes —Comments/Acceptance — Accepted
4. Weekly Statement for Working Days ending April 10, 2023
Days Expired: 260.5
Days Remaining: 16.5
The temporary suspension was lifted on March 28, 2023 and then
resumed again on March 29, 2023.
Page I of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
The temporary suspension was lifted on April 11, 2023 for of street light
poles.
5. Schedule Progress
Contractor's Look Ahead Schedule — Sign, Wire, Walls, pole
tomorrow, topsoil Thursday, trees in Filterra vaults. 3 weeks of dry
weather before thermoplastic can be scheduled. Probably in May.
6. RSD Elementary School 16 Coordination —
• Lane Closures/ traffic control: The only work that the school has
along Duvall that will require any lane closures will be sidewalks and
driveways at the church at 12th. Concrete and striping schedules are
weather dependent. Cornerstone requests that they be told in
advance of when Reed Trucking has striping dates firmed up and they
will not work in the ROW during those days.
• School Contractor does have work with the signal at 10th that will
need to commence but they have yet to schedule a precon for that
scope of work. Our assumption is that we won't be able to
decommission the existing ped signal until after Hazen High School's
last day of operation in the middle of June and should not affect any
striping work.
• School Contractor's electrician has confirmed with Integrity that they
will be addressing the fiber optics issue on Monday (4/10).
7. Engineer's Report
a. Property owner written release received for staging yard.
b. The City is working on updating the punch list. No update yet.
Will send to Reed asap.
Page 2 of 4
\I N' O CITY OF RENTON
+ + DUVALL AVE NE
gircx,
o CAG-20-065
8. Inspector's Report
• City Preliminary punch-list status? Tani to send last
version to Joel.
• Joel McCann {tentative) from the City will provide field
observation for the next two weeks. City prefers 2 days'
notice for scheduling field observer.
• Toni noted, Joel will track FA for Light Pole #8
modifications.
9. Environmental Compliance Report— Silt fence still remains at 4th until
final seeding. All other BMPs have been removed.
10. Public Outreach — no new outreach. Wood fence quote needed
11.Submittals/Documentation
a. Review ROM — current ROM is on the CMS
b. Submittals under review: none
c. Material submittals that need to be submitted: bronze tack for
monument
d. Non-Material Submittals that need to be submitted: Survey
Monument DNR forms, Recycled Material Form at project
completion (can be done now), Project Redline Resubmittal.
e. Material Documentation — no issues
12. RFIs — nothing new
13. FWD/ Change Orders —
• FWD No 34 for re-stake of monument at NE 10th Street — Sent out
• FWD No 35 (Draft in the works) for possible wood fence in gap —
waiting on quotes from Dustin
• CO No 31 in the works for the restake of the monument. — Draft sent
to Dustin. Dustin confirming survey invoice amount.
Page 3 of 4
CITY OF RENTON
+ DUVALL AVE NE
N T°' CAG-20-065
14.Subcontractor Status— no issues
15.Certified Payrolls —
Progress Pajama N.14 Vamp). Papaw No 15(hYgray) Progress Papoose No lP(larch)
_ 1I eek Ludios rru )I Dec 7-Jar 144r 11Jw 2FJ_ Fab II-Fab 11-Fob 25-Fab 4-Mar 11-Mar 13-Mar 25-Mar I-Apr
Reed Trot'Las o Walk 11-Sa 20-1a 261a I-Feb 8-Feb 15-Feb 22-Feb No Work No Work No Week No Work No Work X
WE.Cores — - - - _ - No Week No Week No Work 31-1a I-Feb No Wod No Work No Wodc No Work No Week 20-Mr X X X
ND Los* 'No Work No Work No Work No Week No Work X X X X X X X X
Pogo Comeacdaa No Week No Wok No Week No Work No Work No Work No Work No Work No Work No Work No Week X X X
Concrete Servkes No Wale N.Wad No Work No Weds X X X X X X X X X
Trarporrraa Syaema(Coanoe) No Wok 3-Feb 3-Feb 3-Feb 1-Feb 15-Feb 21-Feb No Wade No Work 20-Mr 20-Mr X X X
Trapa"rao Syvemc(Flecoical) No Wok No Work No Work No Work No Work No Work No Work 28-Feb No Work No Work No Work No Wrack X X
Evawes S.oraeq No Wok No Work No Week No Work No Work_No Wad No Wok No Wok No Work No Week No Wok X X X
Gonad Up No Wok No Wok No Wok No Work No Work No Wad No Work No Work No Work No Work No Work No Work X X
Tore Caeoer Na Week No Wed No Work No Week r1lip 35/13 X X X X X X X X X
Sage Ric No Work No Work No Work No Wok 30.1a 15-Feb No Work No Wad No Work No Wad No Work X X X
Geer Cry No Week 23-1w 27-3.e 3-Feb 3-Feb 13-Fob No Work 28-Feb No Wok No Wod No Work X X X
Integrity Neroarks X X X I5-Feb 15-Feb 15-Feb No Work No Work No Work No Work No Work X X X
Week Contractor/Subcontractor is on the job site,payroll required. **(=12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
EMICorrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16.Progress Payment—
• Progress Payment No 16—April 28, 2023 cutoff, City needs
documentation and signed PP by May 4, 2023.
• Payment for March? There was just one day of grind and
pavement patches. Dustin to let us know if it can roll into April's
Other Items:
Tani to send Dustin the email with street light threads.
Dustin asked if the City had received any feedback on paving? No
complaints received.
Reed to let G&O know if a Progress Payment is needed for March for the
small quantity of grinding and paving.
Page 4 of 4
REEDC. Date: 4/08/23 -4/28/23 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
C,r,l ConWMww..n[.I99!
April
Sched
ID Work Description SSM TWT F SS M T W T F SS M T W T F Notes / Resources
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
L08 foundation Modification X X
Illumination critical path X X X X X X X
Seeding window begins 3/1 also
landscaping critical path wanting illumination complete prior to
X X X X final restoration
thermoplastic Critical path ? ? ? Scheduled long wait list!
Monuments X X
Punchlist work X X X X X
Suspension for ThermoPlastic X
°� CITY OF RENTON
+ DUVALL AVE NE
W+,
o CAG-20-065
CONSTRUCTION MEETING MINUTES
March 28, 2023
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Vice X Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed X Ed Thompson, Representing X
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Renton
Justin Johnson, City of X Ross Widener, Widener & Assoc.
Renton
2. Safety Report— no issues
3. Prior Meeting Minutes—Comments/Acceptance — Minutes are
accepted.
4. Weekly Statement for Working Days ending March 27, 2023
Days Expired: 259.5
Days Remaining: 17.5
The project has been under temporary suspension since Feb 16, 2023.
Suspension lifted for today's work.
Page 1 of 4
'T Y o. CITY OF RENTON
+ + DUVALL AVE NE
W4'NT° CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule — Dustin inquired regarding pole
status; 2 poles to be completed by Friday or Monday of next week.
Pole installation/electrical work tentatively would begin April 10th and
all remaining work would continue with the caveat that Thermal
plastic needs 50 degree and rising temperature. Need good weather.
Landscaping to be completed after electrical work.
6. RSD Elementary School 16 Coordination — Coordination with traffic
control. School Contractor has small right lane closure at NE 12th St.
Not an issue until electrical/thermal plastic work begins. Reed to
coordinate with School Contractor.
Landscaping will require right lane closure for both NB and SB traffic
to shoot hydroseeding —should not impact School Contractor, Reed to
coordinate.
Ed noted area of synthetic turf to be installed by School Contractor.
Requested City provide spec. Flora has sent Duvall Spec to Michael
Sippo.
7. Engineer's Report
a. Staging yard still in use? Property owner written release
required per SP 1-07.24. Reed is out of the staging yard.
Dustin will work on the written release.
8. Inspector's Report
• Preliminary punch-list sent out in February. City to perform
walk thru from various groups and provide any additional
punch-list items. Dustin asked to receive these prior to
beginning the next resume work.
• Joel McCann (tentative) from the City will provide field
observation. City prefers 2 days'notice for scheduling field
observer.
Page 2 of 4
,1 v o CITY OF RENTON
+ DUVALL AVE NE
r°a CAG-20-065
9. Environmental Compliance Report— Silt fence still remains at 4th until
final seeding. All other BMPs have been removed.
10. Public Outreach — City coordinating with property owner near fence
gap north of NE 10th Street, east side, regarding possible fence
replacement.
11.Submittals/Documentation
a. Review ROM — current ROM is on the CMS
b. Submittals under review: 81.02/81.03 monument concrete has
been approved and return via CMS; Project Redlines need to
include all revisions issued via FWD or CO—G&O has placed all
revised sheets on the CMS under Supporting Documents. There are
water main improvements that need to be surveyed and other
items per Special Provisions. Dustin requests this review before
the monument re-stake.
c. Material submittals that need to be submitted: bronze tack for
monument
d. Non-Material Submittals that need to be submitted: Survey
Monument DNR forms, Recycled Material Form — this form to be
submitted when project is complete to include any recycled
material used in patch work.
e. Material Documentation — no issues
12. RFIs— nothing new
13. FWD/ Change Orders—
FWD No 34 (DRAFT) for re-stake of monument at NE 10th Street— City
reviewing. City and G&O working on issuing this FWD soon.
FWD No 35 (Draft in the works) for possible wood fence in gap —
waiting on quotes from Dustin
Page 3 of 4
CITY OF RENTON
+ DUVALL AVE NE
N 7° CAG-20-065
14.Subcontractor Status— no issues
15.Certified Payrolls —
Progress Namur,No 14(Januar) Progress Pacueut No 15(Febnuy) !mime hymn.No I4(N.n8)
Week E.drkg Or: 31-Dec 7-Jar 14Je 21-Jam 28-Jae 4-Fob 11-Feb 18-Feb 25-Feb 4-M 11-31r 1$114nr 25-116ae I,MN
Reed Took* No Work 11-he 204r 26-1ao I-Feb 8-Feb IS-Feb 22-Feb X
W.E.Caro No Wo1c No Work No Work 31-Jr I-Feb No Work No Week NoWtlt X X X X X X
P.M Logpi No Work No Work No Work No Work No Rork No Work X X X X X X X X
Paget Casockoo No Week No Week No Work No Work No Work No Wodr No Ware No Wok X
' m
Concrete Seines No Work No Wade No Work No Work No Wok X X X X X X X X X
Trrrparrdoo S7aemr(Caweee) No Week 3-Feb 3-Feb 3-Feb 6-Feb 15-Feb 28-Feb No Wade X
Trrspmrabm Sya ]gems.) No Wok No Wadc No Work No Wok No Work No Work No Work 28-Feb X
Evergreen S.osmeg No Work No Work No Wok No work No Wok No Work No Wok No Weds X _
Grand Up No Work No Work No Work No Wok No Work No Week X X X
Tyee Caicrek No Work No Wak No Was No Work MEM X X X X X X X X
Snipe Rice No Wok No Work No Week No Work 30-Jo I5-Feb X X X
(Green City No Work 23-Jm 27-10 3-Feb 3-Feb 13-Feb No Wak 28-Feb No Week
Integrity Networks X X _ X 15-Feb 15-Feb I5-Feb No Week X X
Week Contractor Subcontractor is on the job site,payroll required. **(=12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Re submittal
No Work Received No Work Performed"payroll
15-Feb "Fatal"payroll
16.Progress Payment—
• Progress Payment No 15 — check to be issued on March 31, 2023
• Progress Payment No 16 — April 28, 2023 cutoff, City needs
documentation and signed PP by May 4, 2023.
Other Items:
City and Reed are in agreement that section of pavement (15ft wide by
68LF) will be removed and patched to two patch areas. Dustin stated
additional trucks have been added and this work will be completed today.
Page 4 of 4
REEDC. Date: 3/25/23-4/14/23 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
March April '
Sched
ID Work Description SSM TWT F SS M T W T F SS M T W T F Notes/ Resources
25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
L08 foundation Modification (�X X� i y
Illumination critical path X X X -$
Seeding window begins 3/1 also
landscaping critical path wanting illumination complete prior to
X X X final restoration
Grind and overlay 14 day cure prior to thermo,Critical
Path for plastic X
thermoplastic Critical path X X X
Monuments X X
c.\ '' o CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING AGENDA
FEBRUARY 14, 2023
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x JordTQan-Widener, ` ae
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
ReR-te44
Ross Widener, Widener & Assoc.
2. Safety Report —
Traffic control issues — issue reported with Contractor's truck in the
travel lane at MH adjustment near NE 4th Street. This work has been
completed. Confirmed. Complete sweep on Wednesday then temp
shutdown. One more day of work tomorrow. Warning about CB 39 left
in travel lane with crushed rock. Do not do that again.
3. Prior Meeting Minutes— Comments/Acceptance — accepted
4. Weekly Statement for Working Days ending February 13, 2023
Days Expired: 258.5
Days Remaining: 3.5
Page 1 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule —See attached
Temp Suspension for street light poles, grind/pavement repairs and
thermoplastic to begin 2-16-23.
No weekly meeting next week. Next meeting tentatively scheduled
for Feb 28.
6. RSD Elementary School 16 Coordination — Electric work in school
frontage. May need another conduit for flashing beacon from their SL
beacon
7. Engineer's Report
a. Chain link fence needs to be added to prelim punch list- this is
anticipated to be done in March
b. Any property releases needed? Tani to find out if the work in
the temp construction easement areas triggers the need for a
property release.
8. Inspector's Report
• Preliminary punchlist Phil to send out on Thursday
• Irrigation system testing—final coverage test completed
Monday
9. Environmental Compliance Report—Silt fence still remains at 4th until
final seeding
10. Public Outreach — none
11.Submittals/Documentation
a. Review ROM — the most recent is on the CMS
Page 2 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Submittals under review: 81.02/81.03 precast concrete, bronze
tack, ADA Feature Survey
c. RAMs that need to be submitted:
a. Photocell resubmittal due to operating temp
d. Non-Material Submittals that need to be submitted: Survey
Monument DNR forms, Project Red Lines, Recycled Material Form
10th Change order to restake
e. Material Documentation — no issues
12. RFIs— nothing new
13. FWD/ Change Orders—
FWD No 32 issued for deleting synthetic turf—Signed by Reed
FWD No 33 issued for FO revisions—Signed by Reed
FWD No 34 (DRAFT) for paint line refresh—City reviewing Both sides have
faded edge lines. West side is worse. East side is a maybe.
CO No 27—Delete Synthetic Turf—sent to Reed for sigs Signed by Reed
CO NO 28—Added Working Days—sent to Reed for sigs Signed by Reed
CO No 29—FO Revisions—sent to Reed for sigs
CO No 30—Paint Line Refresh (PLACEHOLDER)
14.Subcontractor Status— no issues
15.Certified Payrolls—
Progress Parma No 1414aeearr) P ss Pa>neew No It(Febnan) Progress Payreer No 16(March)
r.Week Fading O. 31-Dec 7-Jae 14Jae 21Jae 28Jaa 4-Feb re 11-Feb 13-Feb 23-Feb 4-Mar I1-31ar 13-Nar 15-Nar 1-Apr
Reed Turkic No Wark 11-Jo. 20-Iao 16-lee 1-Feb 8-Feb
WI.Cones No Work No Work No Wads 31-Jan 1-Feb X X
PeD Loggeg No Wodc No Wodc No Wodc No Wadc No Work_ X X
Port Cortex-bon No weds No Week No Wok No Wok No Week X X
Concrete Scrims No Winds No Wads No Wodc No Winds X X X X X X X X X
Trooparmm Sy000.(Concrete) No Week 3-Feb 3-Feb 3-Feb P-Feb
T..puresm Systew(F]o.okoD No Wodc No Week No Work No Work No Wodc X X
Evergreen Sawetaiog No Week No Weds No Wade No Wodc No Weds No Week X
Good Up No Work No Wodc No Work No Week No Work X X
Ty«Coocrale No Work No Work No Work No Work No Work, X X X X X X X X X
Snipe Rise No Wade No Wodc No Wads No Wodc 30-1® X
Green City No Work 23-1es 27-fan 3-Feb 3-Feb X
hoepoy Netsuke _ X X X X X
Page 3 of 4
\• Y O, CITY OF RENTON
alfe + DUVALL AVE NE
°a CAG-20-065
Week Contractor Subcontractor is on the job site.payroll required- **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
MINCorrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16.Progress Payment—
• Progress Payment No 15 — cutoff Feb 28, 2023, send paperwork
and signed progress payment to City by March 7, 2023
Other Items:
Gravel Backfill for Walls is required for backfilling walls located behind PSE
vault walls (Plan Sheet WD3).
Gravel Borrow required for backfilling walls located behind Filterra Units
(Plan Sheet WD1)
Gravel Borrow required for backfilling walls 2' and higher (Plan Sheet WD1)
All walls under 2'have already been backfilled
Filterras need to be cleaned out and made ready for plants
Only Right lane closures needed for remaining work,from now on
Reed nearly out of staging yard
Page 4 of 4
REEDC. Date: 3/11/23 -3/31/23 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
..,.tle...a in Civil Co..w...la.sins.1 V9t
March
Sched
ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/ Resources
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
L08 foundation Modification X X
Illumination critical path X X X X X X
Seeding window begins 3/1 also
landscaping critical path y- wanting illumination complete prior to
X d final restoration
Grind and overlay 14 day cure prior to thermo,Critica'
Path for plastic X X
thermoplastic Critical path X X X
Monuments X X
•
CITY OF RENTON
iRDUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
FEBRUARY 08, 2023
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Renton
Ross Widener, Widener & Assoc.
2. Safety Report —
Traffic control issues —Sweeper needed for the area of cones removed.
Put up cones and caution tape for wall forms.
3. Prior Meeting Minutes — Comments/Acceptance — No comments.
Accepted
4. Weekly Statement for Working Days ending February 7, 2023
Days Expired: 256.5
Days Remaining: 5.5
Page 1 of 4
\1'' Oits CITY OF RENTON
Al+ DUVALL AVE NE
MR4,Ni° CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule — Raise iron, driveway pave
questionable, wall pour.
Temp Suspension for street light poles, grind/pavement repairs and
thermoplastic effective 2/14/23
The Contractor has requested 15 added working days:
o Grind/overlay irrigation patch, 2 hydrant patches and 10th St
intersection. 3 days
o Thermoplastic 3 days
o Landscaping 3 days
o Illumination 6 days one day overlap with electrical
6. RSD Elementary School 16 Coordination — Notify when traffic control
done near school
7. Engineer's Report
a. A list of paving areas that are rejected was sent to Dustin last
week. L shaped patch ok per COR 110
b. The bicycle lane needs to be restriped due to traffic shift for
WZF —South bound traffic, get a price to restripe. $950.00 Mob
fee and use bid item A88 for the paint stripe.
8. Inspector's Report
• Preliminary punchlist
• Irrigation system testing — main line testing completed only.
Planter No. 3 coverage test needs to be complete. Question on
whether coverage test is the same as lateral test. Northerly
most planter not complete.
• Walked asphalt issues with sub
Page 2 of 4
\ Y O CITY OF RENTON
+ DUVALL AVE NE
�F N T 0 CAG-20-065
9. Environmental Compliance Report— Silt fence installed at 4th. All
catch basin inserts removed.
10. Public Outreach — Nothing
11.Submittals/Documentation
a. Review ROM —
b. Submittals under review:
c. RAMs that need to be submitted:
-i 42 05 non shrink grout for fence post
b. 81.02/81.03 precast concrete, bronze tack - Under review
c. Photocell resubmittal due to operating temp
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
12. RFIs — nothing new
13. FWD/ Change Orders —FWD No 32 and 33 in the works for deletion
or turf and FO revisions. These will be followed by three Change
Orders to also include added working days.
14.Subcontractor Status — no issues
15.Certified Payrolls —
Progress Payment No 14(January) Progress Payment No 15(February)
Neck Eaig On: 31-Mc 7-Jan 14-Jan 21Jaa 2SJan 4-Feb 11-Feb 18-Feb 25-Feb
Reed Trucking — No Work 11-Jan 20-Jan 26-Jan 1-Feb
WE.Coats No Work No Walk No Work 31-Jan 1-Feb X
Pnr L No Wok No Wads No Week No Work No Work X
Paget Camtraction No Wort No Work No Work No Work No Work X
Concrete Services No Work No Work No Work No Work No Work X X X X
Transportation Systems(Conaaete) No Work 3-Feb 3-Feb 3-Feb
Transportation Systems(Electrical) No Work No Work No Work No Work X X
Evergreen Saw cutting No Wok No Work No Work No Work No Work X
Ground tip No Work No Work No Work No Wok No Work X
Tyre Concrete No War No War No Work No Wok No Work X X X X
Stripe Rite No Work No Work No Work No Work 30-Jan
Green City No Work 23-Jan 27-Jan 3-Feb 3-Feb
Integrity Networks X X X X
Page 3 of 4
CITY OF RENTON
�_y + DUVALL AVE NE
CAG-20-065
Week Contractor Subcontractor is on the job site,payroll required. **(=12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16.Progress Payment—
• Progress Payment No 14— cutoff Jan 31, 2023, sent to City for
processing
• Progress Payment No 15 — cutoff Feb 28, 2023, send paperwork
and signed progress payment to City by March 7, 2023
Other Items:
- Small section of fence left to do on walls to be completed by March per
Dustin
Page 4 of 4
REEDcr. Date: 3/11/23-3/31/23 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVA77NG Name: Duvall Avenue
March
Sched
ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes / Resources
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
L08 foundation Modification X X
Illumination critical path X X X X X
Seeding window begins 3/1 also
landscaping critical path wanting illumination complete prior to
X X X final restoration
Grind and overlay 14 day cure prior to thermo,Critical
Path for plastic X X
thermoplastic Critical path X X X
Monuments X X
i
REEDC. Date: 2/4/23-2/24/23 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
Febuary
Sched
ID Work Description SSMTWT F S S M T W T F SS M T W T F Notes / Resources
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Illumination critical path Waiting on Pole Mods
Finish wall and backfill,Critical Path for landscape X X X a X
Wall cure time so we can backfill,Critical Path X X X X
Raise iron X X
landscaping
Grind and overlay
thermoplastic
Temp Suspension for electrical,paving,landscape and thermoplastic X X X X X X X X X
c,tY ^ CITY OF RENTON
• + DUVALL AVE NE
F N T°� CAG-20-065
CONSTRUCTION MEETING MINUTES
FEBRUARY 01, 2023
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Ed Thompson, Representing
Trucking & Excavating Inc. Renton School District
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Renton
Bryson, TSl Ross Widener, Widener & Assoc.
2. Safety Report—
Traffic control issues — Missing signs need to be installed prior to temp
shutdown. Dustin says signs will be installed this week. Discussed the
right only sign on the Albertson driveway for exiting vehicles, is it
needed due to WZF lane closures? Phil will look at it.
3. Prior Meeting Minutes—Comments/Acceptance — no comments,
accepted
4. Weekly Statement for Working Days ending January 38 31, 2023
Days Expired: 250.5 251.5
Page 1 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Days Remaining: 11.5 10.5
5. Schedule Progress
Contractor's Look Ahead Schedule — see attached 3-week look
ahead schedule
Expected materials that are coming out on-site— curb paint and
temp paint, topsoil, seeding, monuments
Feb 16 tentative for physical completion
Discussed a Contractor requested temporary suspension in work. The
eight street lights to be modified are at Streich Brothers (welding). No
date is forthcoming as to when the modifications will be completed.
Will City allow contractor to work on non-critical path items during a
suspension without charging days? Bob H says "No". However the
City will consider adding approx. 9 working days for completion of the
light poles, monument, landscaping and plastic markings/lines.
Work that needs to be completed prior to a temp suspension includes
walls, permanent signing, casting adjustments, temp paint/curb paint.
6. RSD Elementary School 16 Coordination—Turf is deleted from City
project. School contractor will be occupying this area with trenching,
street lights and final landscape.
7. Engineer's Report
a. FO revisions were sent to Contractor, main change is addition
of slack needed at vaults and reduction of FO cable pull to the
south. This is a no-cost change, confirmed by Dustin.
b. The location of the photo cell is confirmed to be inside the
service cabinet.
c. Tani to send a list of paving areas that are rejected.
Page 2 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
8. Inspector's Report
• Preliminary punchlist started
• Irrigation system testing—
9. Environmental Compliance Report— nothing
10. Public Outreach — nothing
11.Submittals/Documentation
a. Review ROM — Rom is on the CMS
b. Submittals under review:
• sign band —316 SS band is not available — City reviewing
available band again.
c. RAMs that need to be submitted:
a. 42.05 non-shrink grout for fence post
b. 81.02/81.03 concrete, bronze tack
c. Photocell resubmittal due to operating temp
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
12. RFIs— nothing new
13. FWD/ Change Orders—Will deletion of turf and FO revisions trigger
FWD and CO? Yes, issue a FWD and CO for deletion or turf, FO
revisions and added working days.
14.Subcontractor Status— no issues
15.Certified Payrolls— Please ask TSI to submit certified payrolls for no
deferrals on PP 14
Page 3 of 4
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Progress Payment No 14(January) Progress Payment No 15(Febrnarr)
Week EndingO.: 31-Dec 7-Jaz 14Jaz 21Jau 2S-Jan 4-Feb 11-Feb 1S-Feb 25-Feb
Reed Trucking No Work 11-Jan 20-Jan
W.E.Coates No Work No Work No Work X X
PoD Logging No Work No Work X X X
Puget Construction No Work X X X X
Concrete Services No Work No Work No Work No Work X _
Transportation Systems(Concrete) No Work
Transportation Systems(Electrical) No Work X X X X
Evergreen Sawcotirg No Work No Work No Work X X _
Ground tip X X X X X
Tyee Concrete No Work No Work X X X
Stripe Rite No Work No Work No Work X X
Green City No Work 23-Jan X
Integrity Networks X X X X
Week Contractor Subcontractor is on the job site,payroll required_ **(#12)indicates payroll number**
X Subcontractor was not on-site this week "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16.Progress Payment—
• Progress Payment No 14— cutoff Jan 31, 2023, with signed
progress payment and backup to the City by Feb 6, 2023.
Other Items:
Page 4 of 4
REEDcr. Date: 1/28/23-2/17/23 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
�aullenee In Civil C.w.rww wince,W
January
Sched
ID Work Description SSMTWT FSSM TWT F SS M TWT F Notes/ Resources
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Illumination critical path Waiting on Pole Mods
Finish wall and backfill X X X X X
landscaping X X X X
Raise iron X X X X X
Fiber X X X
Permenant signs X
Suspension allowed to work on non critical items X X X X X X X X X X X X X
a
\I Y 4 CITY OF RENTON
+ DUVALL AVE NE
�F N T o CAG-20-065
CONSTRUCTION MEETING MINUTES
JANUARY 24, 2023
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Ed Thompson, Representing
Assoc. Renton School District
2. Safety Report —
Traffic control issues — No issues
3. Prior Meeting Minutes—Comments/Acceptance —Accepted
4. Weekly Statement for Working Days ending January 23, 2023
Days Expired: 245.5
Days Remaining: 16.5
Page 1 of 5
`\T Y O" CITY OF RENTON
+ + DUVALL AVE NE
MF N T°� CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule — Working on fiber and walls/wall
backfill. Pave driveway this week. Raise Iron Thursday/Friday.
Irrigation after walls done. Estimated, one week for pole installation,
pull wire and energize illumination (once pole modifications are
complete). 2 weeks to complete fiber. Walls this week into next week.
Stripe Rite tomorrow. Dustin anticipates completing all—except
street lights, turf, and plastic— by end of next week.
Expected materials that are coming out on-site — Concrete, paint,
fiber optic cable
Feb 16 tentative for physical completion —Suspension if no turf
(procurement delayed) and poles delivered. Disregard turf if area
replanted by School Contractor
6. Utility Coordination -
a. COR Water Department —
a. Backflow preventers tested and passing results sent to City.
b. Block wall behind FH at 10`h status - Completed
7. RSD Elementary School 16 Coordination — Question regarding
whether school will place turf or replant. Phil will check with Kyle.
8. Engineer's Report
a. TCP J approved for right lane closures as needed through end
of project. No PCMS board needed for same. Arrow boards up
now.
b. Concern from Eric Cutshall regarding fiber design. City to reach
out to Parametrix. Revisions to be issued to Integrity Networks
9. Inspector's Report
• Preliminary punchlist started
• Integrity Network wage interview - Done
• Irrigation system testing — wait for walls to be complete.
Page 2 of 5
CITY OF RENTON
DUVALL AVE NE
°UR
CAG-20-065
• Two flaggers for striping.
• Removal of silt fence complete.
• East side ready to place concrete.
10.Environmental Compliance Report— Nothing
11. Public Outreach —Nothing
12.Su bm itta is/Documentation
a. Review ROM — Updated
b. Submittals under review:
• conduit foam sealant, grout and photo cell - Returned RAM
100. Photo cell rejected due to operating temperature.
• sign post and band — Returned RAM 45C. Fasteners rejected
due to 316 SS requirement, banding for signs on luminaire
poles shall be black banding.
• 71.17/72.17 Galv. Steel Pipe (Landscaping) — Confirmed as
same as for walls
c. RAMs that need to be submitted:
a. 42.05 non-shrink grout for fence post
b. 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
—Synthetic Turf may not be needed. Email has been sent to
Tiffani detailing submittals needed.
c. 81.02/81.03 concrete, bronze tack
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—None
14. FWD/ Change Orders— CO 26—Wall rev's in WZD, Sidewalk
replacement and fence/root removal. — it has three signatures and
sent to City for final signatures
Page 3 of 5
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
15.Subcontractor Status— all good. City Business License for Reed
Trucking will expire 1/31/23, renew ASAP.
16.Certified Payrolls —
I Progress Payment No 14(January) Progress Payment No 15(February)
Week Ending Or. 31-Dec 7-Jam 14-Jam 21-Jam 23-Jan 4-Feb 11-Feb 13-Feb 25-Feb
Reed True-king No Wads 11-Jan _
'W.E.Codes No Work No Work X X
PnD Logging No Wodc No Wads X X
I Puget Construction No Work X X X
I Concrete Services No Work X X X
Transportation Systems(Concrete) No Work
''Transportation Systems(Electrkal) No Work X _ X X
Evergreen Sawconiog No Work No Work No Work X
I Ground Up X X X X
Tyee Concrete No Work No Work X X
Stripe Rite No Work X X X
'Green City No Wady
Week Contractor Subcontractor is on the job site:payroll required. **(.121 indicates pa}Toll number**
X Subcontractor was not on-site this week "Pin Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Rork Performed"payroll
"Final"payroll
17.Progress Payment—
• Progress Payment No 14— cutoff Jan 31, 2023, with signed
progress payment and backup to the City by Feb 7, 2023.
Other Items:
Dustin to reapply for Reed business license by 1/31/23
Page 4 of 5
C,\1 Y o CITY OF RENTON
+ t ,} + DUVALL AVE NE
"PF N T°'' CAG-20-065
/
WZC-Jan-May 2022
WZA-Feb-May 2022 �` f.
WZB& E-Mar-Aug 22. 2022 ?'-'" NI ' !DD it
WZD -Sept-Nov 14. 2022 1 '1 1
WZF(Medians)-Nov-Jan 8.2023
-,>\, jacil' L R' .E4-1 EillO' li. t LI II
-Am 1 1
- �, LOCATION
SC , ._ 11,
Ir
_, ...... Ira
iir
"Ir I NEON ST z
i\\„ lb Ill MIPPII -
7 , 1 Fe- L
PRIDE i
plri Awl' LOCATION wE
.. Fri' i i I
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NUT TO xA4 -SCHF DUI E L.
City of Renton - Duvall Ave NE, CAG 20-065
Page 5 of 5
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JANUARY 17, 2023
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x ,
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton x
#eon
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener Widener Q. Ed Thompson, Representing
Assoc. Renton School District
2. Safety Report—
Traffic control issues— Phil had a previous discussion with TCS on what's
needed. Payment and tracking of flagging hours in question. WZF has
no flagging stations but spotters are needed to allow deliveries in and
out of WZ. Didn't need any spotters (no delivery trucks)per Phil, but one
flogger kept on site. Moving barrels is other TC labor. Jesse is TCS if in
truck, only paid as flogger if out spotting. Hoping to get on same page
regarding when to send flaggers. Flagging paid per hour. TCS paid by
lump sum. Dustin is on board with above description of work/payment.
Page 1 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
3. Prior Meeting Minutes—Comments/Acceptance — accepted
4. Weekly Statement for Working Days ending January 16, 2023
Days Expired: 240.5
Days Remaining: 21.5
5. Schedule Progress
Contractor's Look Ahead Schedule— Dustin reached out to TSl for
wall pour schedule. Optimistic work will get done on time. Other work
including permanent signs, Illumination, paint/plastic striping. Reed
will aslo address bolt asjustments sent via email.
Upcoming Plant Delivery dates for inspection —To be determined.
Landscaping ongoing. Plants on site, more being delivered.
Coordinating with Fiber. Waiting on pole mods as well. Feels
confident can get it all done in 4 weeks.
Expected materials that are coming out on-site — Plants and possibly
concrete.
6. Utility Coordination -
a. COR Water Department—
a. Backflow preventer test results to City, the water meters are
installed for the irrigation services Dustin trying to confirm
testing date.
b. Block wall behind FH at 10th status Iron raised/paved back and
will finish wall up per Dustin.
7. RSD Elementary School 16 Coordination — None identified. FO vault
has been adjusted.
Page 2 of 6
CITY OF RENTON
• ._7.; DUVALL AVE NE
CAG-20-065
8. Engineer's Report
a. Mail box relocation not needed per face to face with post
office supervisor— Box to be put back
b. Street Light poles —the following 11 poles need adjustments to
provide the required 2 thread of bolt above the top of nut per
WSDOT Standard Spec's: SL02, SL05, SL06, SL07, SL10, SL11,
SL12 (and chip conc away), SL18, SL19, SL20, SL25
9. Inspector's Report Heavy rains. Filterra vaults along Albertson's
leaking out. Some grouting wasn't done. Phil will point out to Nate.
10.Environmental Compliance Report — nothing identified.
11. Public Outreach — in person visit to post office manager last week
12.Submittals/Documentation
a. Review ROM —posted. Push button assembly and central control
unit submittal returned via CMS.
b. Submittals under review: conduit foam sealant submittal
includes photo cell, push button assembly, central control unit,
sign post and band
c. RAMs that need to be submitted:
• 42.05 non-shrink grout for fence post
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.17/72.17 Galv. Steel Pipe (Landscaping) —Same as for
walls? Phil to check if steel pipe is being used on the
project.
• 81.02/81.03 concrete, bronze tack
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
Page 3 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
13. RFIs—
14. FWD/ Change Orders—
• CO 26—Wall rev's in WZD, Sidewalk replacement and
fence/root removal — reissued to Reed for sigs to incl. vertical
bar. Dustin to sign when scanner/printer is fixed
15.Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City,Inc. $139,480.00
3. Totem Electric of Tacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
3b. Transportation Systems,Inc. $100,000.00
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E.Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services,Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. $15,000.00
15. Integrity Networks $22,432.15
16. Transportation Systems,Inc. $100,000.00
16.Certified Payrolls—
Page 4 of 6
CITY OF RENTON
• cr, DUVALL AVE NE
CAG-20-065
Propm Payment N.11(C(Camber) Progress Foloeat No 12(.November) Prop...Pay-meal No 13
Week Wing Om 1-0.t 15-0.t 22-0.1 211Oat 5-Nr 12-Nr 10-No. 26-Na 3-Dee 10-Der 17-Da 24-Do.
Reed Truck* 13-001 240et 27-Oct 2-Nov 18-Nov 11-Nov 23-Nov I-Da 7-Da 15-Da 22-Dec 4-ha
WE.Coates No W odr Ne Work 31-Ott No Work No Work No Watt 1-Dee No Work 15-Da No Wok No W-air No Work
P.D Lag No Week No Work No Work No Wed No Wok No Work No Work ek k No W. No Week No Wok No Work No Work
' v�Polar Caestmain No W-ark No Work 2-Nov No Woes Il-Nov No Work No Work No Work No Work No Work No Work No Work
Caeaete Services 17-Oct No Work No Work 8-Nov No Work No Work No Wok No Work No Wed No Work No Week No Work
Tampo0.t oo Svsteos(Coeuae) No Work 2-Nov 2-Nov No Week No Work 0-he No Work 4-he No W-ark No Week 5-he
Transportation Svstems(Elaniol) No Work 22-Dte 1}.)1m 4-he 41an 4-Jr 4-Jan 4-Jae 1Jm 4-Jan No Week No Wok
Evnpeeo Smarting No Work No Wink t-Nov No Work No Work No Week No Work No Wade 7-Dee 15-Da No Wed No Wod
(land Up No Work No Week No Work No Week No Work No Week No Work No W'aek No Work No Wok No W'ark No Wad
Lgoey T.ppi.e 10-Oct No Week No Wort No Work No Wok X X X X X X X
Laknidea Paint No Work No Wort No Work I-Nov 22-Nov No Work No Work No Work No Work No Wad X
Tyee Comet. No Work No Week No Work No Work No Work Noltetk No Work 1-Dix No Work 15-Dee No Wart X
Stripe Rite X X X X X X X 5-Dec No Watt :2-Dec No Wod No Work
'Ores.City X X X X X X X X X X 3Jm 5-ha
Progress P.2mwt N.14 51.e.r4 Preper rrymene No 15(FeM.ot) Prepen Ptyme.t N.►0 Want),
Wetland/et Om 31-Dee 7-he 14-Jae 21-70 Wee 4id 11-Feb 13-Feb ?Mel _4-11r 11-Ler Iakl.r 25-Nr 1-Apr
Read Tree No Work 11Jae
WE.Coates X X
ND Lowrie No Work X
!Paler Contraction No Work X
ICo.c000 Semite, No Work X
',Transportatioo Systeme(Cooaete) No Work
Tamportuioa Syotems(Electiat) No Work X
Everpeee Sassoottiop No Work X
Ground Up X X
Tyee Concrete No Watt X
Stripe Rate No W'ad X
C City No Work 1
Week Contractor•Subcontractor is on the job site,payroll required. **(=12)indicates payroll
X Subcontractor was not on-site this week_ "No Work Performed"payroll required-
15-Feb Date certified payroll was recieved
1 Corrections to payroll required
II _Al'
Apprenticeship doe's required
Payroll Resubrnittal No Work Received"No Work Performed"payroll
15 Feb "Final"pasToll — i -r
17.Progress Payment—
• Progress Payment No 14— cutoff Jan 31, 2023, with signed
progress payment and backup to the City by Feb 7, 2023.
Other Items:
Discussion on temperature affecting final items. Ideally remaining than to
be completed in one day.
Based on remaining Working Days, targeting Feb. 16th for Physical
Completion. Dustin sees no issue completing work within remaining
Working Days.
Page 5 of 6
CITY OF RENTON
• s: DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 - ^.,rrrI ,/ I ``. )
WZA-Feb-May2022
�Nf "- I
WZB& E-Mar-Aug 22, 2022MD =_J
WZD-Sept-Nov Noy
2022 n
WZF(Medians)-Nov-Jan8,2023 ' 11.
.____r NE 12TH SH
'.I
' .. NE ,�x +- `, PROJEG xT H
4 LOCATION
, �. -SCHF DUI A h 1NC 10THST
l al i I, II �. � 1, I
1N•:4 sr
I t _
1 to
i ILIN I y�� E 11
I
r /1-11 'ti4it 1
i _ S i i
NE4TMn g
PRe1Eci _
LOCATION
1\11111111111.
lLE ED LEA i...
* \\En Fa i l I ,
WATER MAIN IMPROVEMENTS
N -SCHEDULE 13
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT IU MAr[ -SD*DU IF(.
City of Renton - Duvall Ave NE, CAG 20-065
Page 6 of 6
REEDc Date: 1/14/23-2/03/23 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
6.dlw.,..u.a C.. n.a.....,....1991
January
Sched
ID Work Description SSMT W T F S S M T W T F S S M T W T F Notes /Resources
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
Illumination ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? Waiting on Pole Mods
Form wall X X X X X X X X X X X X X
walls X X X X Waiting on Schedule
Irigation and landscaping X X X X X X X X X X X X X X X
Raise iron X X X X _
Fiber ? ? ? ? ? waiting on schedule confirmation
CITY OF RENTON
'IR DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JANUARY 10, 2023
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan4A idener-71.4 idener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Ed Thompson, Representing
Assoc. Renton School District
2. Safety Report—
Traffic control issues— 12/22/22 complaint on TC—cars stuck in median
curb. Resolve with plantings & paint.
3. Prior Meeting Minutes—Comments/Acceptance — Accepted
4. Weekly Statement for Working Days ending January 09, 2023
Days Expired: 235.5
Days Remaining: 26.5
Feb. 17th tentative for physical completion.
Page 1 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule — Landscapers working. Pavement
marking requested. Monument waiting for iron. ADA feature survey.
Other punch list items. Dustin trying to get wall crew on site.
Upcoming Plant Delivery dates for inspection —
Expected materials that are coming out on-site—
Plants coming on site. Signs.
6. Utility Coordination -
a. COR Water Department—
a. Storz Adapters remaining to be installed? Done
b. Backflow preventer test results to City. Email Holly for meter
drop in schedule. Flora contacted Tom Main.
c. Block wall behind FH at 10th Started this work yesterday,
additional blocks needed.
7. RSD Elementary School 16 Coordination—
Lowering one fiber vault in school frontage
8. Engineer's Report
a. Mail box relocation not needed per mail delivery person. No
response from post master Phil to follow up with post master
b. Special Provisions say Contractor's surveyor to furnish and
install the monument
c. CSI Lien. Cadman's standard process—material lien.
d. Walls in WZD— Contractor sub asking for extra to extend
vertical rebar. Tani to check change order and follow up.
Potentially pay for work to extend rebar. Disagreement on
payment for extra rebar.
e. Planting issue sent to Reed, regarding the depth of the
plantings.
Page 2 of 6
c. CITY OF RENTON
% DUVALL AVE NE
CAG-20-065
9. Inspector's Report
Waiting on concrete cylinder breaks. Stamp monuments to do.
10.Environmental Compliance Report— None
11. Public Outreach — Phil to try post master at post office
12.Submittals/Documentation
a. Review ROM - On CMS
b. Submittals under review: conduit foam sealant, push button
assembly, central control unit, sign post and band
c. RAMs that need to be submitted:
• 42.05 non-shrink grout for fence post
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.17/72.17 Galv. Steel Pipe (Landscaping) — Same as for
walls?
• 81.02/81.03 concrete, bronze tack
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs —
RFI 28 — Fertilizer—Response sent. G&O responded by email,
will follow up via CMS
RFI 29 — Irrigation Box — Response sent
14. FWD/ Change Orders —
• CO 24 — L08 Foundation modification — to City for final sigs
• CO 25 — extended limits for paint stripe with supplemental
RPM's —to City for final sigs
Page 3 of 6
CITY OF RENTON
• DUVALL AVE NE
CAG-20-065
• CO 26 -Wall rev's in WZD, Sidewalk replacement and
fence/root removal -to City for final sigs
15.Subcontractor Status-
REQUEST
NO. SUBCONTRACTOR .1MOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City,Inc. $139,480.00
3. Totem Electric of Tacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier). $22,432.15
3b. Transportation Systems,Inc. $100,000.00
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E.Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services,Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. $15,000.00
15. Integrity Networks $22,432.15
16. ITransportation Systems,Inc. $100,000.00
16.Certified Payrolls-
PreQese Palomar N.11(October) ?regress Format N.12(November) Progress P.r.e.t N.13
Week'Yin Om 8-Oee 150.t 22-0.. 28-0.t 5-N. 12-Nov 1-N. 26-Nev 3-Dec - 10-Dec 17-Dee 24-Dec
Reed Tackle( 13-Oct 24-05 27-0ct 2-Nov 1B-Nov it-Nov 23-Nov 1-De. 7-Dec 15-Dec 22-Dee 4i.,
WI Cowes No Week No Week 31-0er No Work No Week No Work 1-De. No Work 15-Dec No Week No Week X
ND Logpng No Work No Wed No Work No Wo.k No Week No Work No Work No Work No Week No Work X X
PoBet Constroctioo No Work No Week 2-Nor No Work 18-Nov No Work No Work No Wodt No Work No Week No Week X
Comete Servitea 17-Oct No Work No Wort 8-Nov No Week No Work No Watt No Work No Watt No Wait No Work X
Trm.porterioo Systems(Concrete) No Work 2-Nov 2-Nov No Work No Work 4J. No Work 4J. No Week No Wo.k X
Ttamportatiw Syst oiral) No Week 22-Dec 4-Jan 4L. 4-1eo 4Ja. 4-1. 4Js 4-2.. No Wok No Wo k
Evapren Saacottme No Work No Wed 3-Nov No Work No Week No Work No Week No Wad 7--Do. 15-Do. No Work- X
(kesmd Up No Week No West No Week No Work No Work No Work No Week No Week No Week No Wed X X
Lep.y Tappet¢ 10-Oct No Work No Week No Work NiNiallaC X X X X X X
Lakes-dm Pool No Work No Work No Work 8-Nov 22-Nov No Week No Week No Wort No Work No Week X
Tyee Cortaro No Work No Work No Week No Week No Work No Work No Work 1-Dec No Work 15-Dec No Week X
Stripe Roe X X X X X X X 5-Dce No Week 22-Dee No Work X
Green Cely X X X X X X X X X X
!moms Pavement N. (Jw}) 'men?spasm N.15(Partway) Progress Pas....N.10 01r.k�
Week robin Our 31-Dec 74.m 14J.. 21Jr 28Ja. 4-Feb - 11-Fell18-Fek 25-Fok 3(4- .r 11-31.r �18-Mar 25-bler 1-ABr
Reed Trude* No Work _
WE Cost. X X
P,DLogptg X X
Puget Ceent.ct= X X
Coeecne Services X X
Tr.speetatiov Svztems(Ceecsete) X
Ttaosponatron Svstms(Elecmd) No Work X
Evergreen Smcuttml X X
G.mmd Up X X
Tvee Conerete X X
S.npe Rne X X
Green City X
•
Page 4 of 6
CITY OF RENTON
• ,_:: DUVALL AVE NE
CAG-20-065
Week Contractor Subcontractor is on the job site.payroll required. **( 12)indicates payrolnumber""
X Subcontractor was not on-site this week_ "'No Work Performed"payroll required_ '
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Resubmittal
No Work Received'No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 13 — City is processing
• Progress Payment No 14— cutoff Jan 31, 2023, with signed
progress payment and backup to the City by Feb 7, 2023.
Other Items:
Page 5 of 6
CITY OF RENTON
• 1=y DUVALL AVE NE
1,
CAG-20-065
WZC-Jan-May 2022 -E-,,,y-r-r-r ,�,Z
WZA-Feb-May 2022 .Wort.7an&E ti!
hE SLNS'T �[
WZB& E-Mar-Aug 22. 2022 • 2- . Nvq _i
WZD-Sept-Nov 14.2022 ilPr
WZF(Medians)-Nov-Jan 8. 2023 71 — N"..!„.....
7PR(S1ECT NE17TH$f
NEP:&� 1 1�
1 i;
(`I,% LOCATION I i
` 101,f MAI.A _._1NE lUT!1 1
the
N! Dipliiff, C ,
W Y
1
) * I t 7-Y _
NF 6TH ST
ri-do
i 14 1
PROM LT
" 1L�S"'OyC�ATILON
11ii el fDilLf A Ii.1
Air . . � I
WATER MAIN IMPROVEMENTS
N -SCHEDULE 8
VICINITY MAP UNDERGROUND IMPROVEMENTS
NUT 10 S[11;F -SC HE DUI I C.
City of Renton - Duvall Ave NE, CAG 20-065
Page 6 of 6
REEDc Date: 1/07/23-1/27/23 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
�aNb-sue a G.I G-..�wM�w Maur IVpt
January
Sched
ID Work Description S S M T W T FSSM T W T F SS M T W T F Notes I Resources
7 8 9 10 11 12 13 14 105 16 17 18 19 20 21 22 23 24 25 26 27
Illumination ? ? ? ? ? ? ? ? ? ? Waiting on Pole Mods
Form wall X X X X X X X X
walls X Waiting on Schedule
Irigation and landscaping X X X X X X X X X X X X X X X
Raise iron X X X X X X X X X
CITY OF RENTON
Life DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JANUARY 03, 2023
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan `rr Wiven^cr, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Ed Thompson, Representing
Assoc. Renton School District
2. Safety Report—
Traffic control issues—
Nail/tire complaint—site was inactive Dec 20 to Jan 3- Unlikely nail
came from project. Flora to respond to complaint. City sweeper went
through site today.
Phil noted issues with cars parking in the planters. Icy conditions.
3. Prior Meeting Minutes—Comments/Acceptance —Accepted
Page 1 of 6
Y ° CITY OF RENTON
+ DUVALL AVE NE
N T° CAG-20-065
4. Weekly Statement for Working Days ending January 02, 2023
Days Expired: 230.5
Days Remaining: 31.5
5. Schedule Progress
Contractor's Look Ahead Schedule —
TSI forming walls, Landscaper doing work.
Electricians waiting for pole modifications to be done.
Permanent Signs
Plant Delivery to site 7day notification — Request for plant review
(Aurora Dogwoods for medians) and shrubs. Thursday 1/5 at 9:30.
Flora to check with Ian. Dustin to ask for future dates for inspection
of plants.
Expected materials that are coming out on-site — Plants and concrete,
topsoil.
6. Utility Coordination -
a. COR Water Department— Storz Adapters installed on 2 FH's? Still
waiting on storz adapters. Phil to confirm. Dustin to follow up.
b. Lumen - Pedestal removal complete —yes
7. RSD Elementary School 16 Coordination — None identified. Still some
work at 10th needed. School needs to finish pours per Michael Sippo.
Keep on agenda for now.
8. Engineer's Report
a. Good break obtained on the retest conc sample, over 4000 psi
No issue
b. Mail box relocation — City reached out to postmaster. waiting
on official response. If moved to 12th, mail box should be
replaced with locking mail box (lots of foot traffic from high
Page 2 of 6
CITY OF RENTON
DUVALL AVE NE
'IR
CAG-20-065
school). Phil to reach out to homeowner and look at possible
locations.
Bob requested use of Union project locking mailbox spec.
9. Inspector's Report Testing is done.
10.Environmental Compliance Report—Some restoration areas require
silt fencing. Remain for now.
11. Public Outreach — email sent to postmaster regarding mail box
relocation —See #8 above
12.Submittals/Documentation
a. Review ROM - posted this morning
b. Submittals under review: plastic type D glass beads, irrigation
angle valve, electrical grout, conduit foam sealant, photo cell,
push button assembly, central control unit, CalPortland Conc Mix
for extruded curb
c. RAMs that need to be submitted: Tani to research if City provides
brass for monuments.
• 42.05 non-shrink grout for fence post
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.17/72.17 Galv. Steel Pipe (Landscaping) —Same as for
walls?
• 81.02/81.03 concrete, bronze tack
• 86.02.01 2" sq. sign post/support/anchor
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
Page 3 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
13. RFIs—
14. FWD/Change Orders—
• CO 24— L08 Foundation modification —sent to Reed for sig
• CO 25 —extended limits for paint stripe with supplemental
RPM's—to City for final sigs
• CO 26—Wall rev's in WZD, Sidewalk replacement and
fence/root removal —to City for final sigs
15.Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City,Inc. $139,480.00
3. Totem Electric of Tacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
3b. Transportation Systems,Inc. $100,000.00
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E.Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services,Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. $15,000.00
15. Integrity Networks $22,432.15
16. Transportation Systems,Inc. $100,000.00
16.Certified Payrolls— missing TSI, Evergreen and Green City payrolls
Page 4 of 6
o,, CITY OF aii).._ + DUVALL AVE NE
°� CAG-20-065
' Progress Payment N.11(October) Progress PPP��ayyy ...I No 12151.resk. N r) Progress .17,Decet.6er)
• Ear hog E. .e Ow_8-Oct 15-Oct 22-00 28-001 5-Nov 12-Nov199-Nor 26-Nor 3-Doe 18-Dec 17_Dec 24-Der
.Reed Trucking 13-Oct 24-Oct 27-0Oct 2-Nov 18-Nov 18-Nov 3-Nov 1-Dec 7-Doc 15-Dec 22-Dec
W.E.Costes NoWork No Work 31-0Oct No Work No Work No Week 1-Dee No Wort I5-Dec No Work No Work X
ND Logging No Work No Work No Work No Work No Work No Work ' No Work No Work No Work No Work X X
Puget Construction No Work No Work 2-Nov No Work 18-Nov No Work ! No Work No Work No Work No Work No Work X
Concrete Services 17-Oct No Work No Work 8-Nov No Work No Work No Work No Work No Work No Work No Work X
•Transportation Systenc(Conarb) No Work 2-Nov 2-Nov I X X
•Trantpodation Systews(Eleclried) No Work 22-Dec X X
Evergreen Sawcrrttwg No Work No Work i 8-Nov No Work No Work No Work No Work No Work '7-Dec 15-Doc No Work X
Ground Up No Work No Work No Work No Work No Work No Work No Work No Work No Work No Week X X
Legacy Tappet8 10-Oct No Work No Work No Work IIINDAD X X X X X X X
•Lakeridpe Paving No Work No Work No Work 8-Nov Nov y;"Y,)- .1$-14rC I No Work No Wok No Wort No Work No Wan X
•Tyee Concrete _ No Work No Work No Wark No Work No Work No Work No Wort I-D.e No Week IS-Dec No Work X
Stripe Rite X X X X X X X 5-0.e No Wort 22-Dee No Work 1 X
Green City X X X X X X X X X X
Week Contractor•Subcontractor is on the job site,pal.roll required. **(#12)indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed"payroll required-
15-Feb Date certified payroll was recieved
Mil Corrections to payroll required
•
Apprenticeship doe's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Einar'payroll
17.Progress Payment—
• Progress Payment No 13 — draft to Reed sent 1/2/23 and final
submittal to the City by Jan 03.
Other Items:
Page 5 of 6
CITY OF RENTON
DUVALL AVE NE
+ i,,FR
CAG-20-065
WZC-Jan-May 2022 — L)
WZA- Feb-May 2022 4.
WZB& E-Mar-Aug 22.2022 r� ME•
, eon ..J
g
WZD-Sept- Nov 14. 2022 g * , J
WZF(Medians)-Nov-Jan 8,2023
f� : kl 1 NE lint 1
LOCATION 1
rr----, lite -SCFIF DIAI A i .- �NE" ST
, I
\VII 11.1111111.-- 2 \> 1
o _ -__Ii: _ 31
cc
_•.,,,), lie v. 2
NE aTH sr t
PROJECT
LOCATION
.4016. 1 icro lid E A 1
me , ' (14 FPIT fi I
WATER MAIN IMPROVEMENTS
N -SCHEDULER
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT io x.ml -Sail DUUIF
City of Renton - Duvall Ave NE, CAG 20-065
Page 6 of6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MEETING
DECEMBER 20, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordanidener Widener
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo City „f Yong Qui, City of Renton
genten
Bryson, TSI Dmitri Suslikov, Paramctrix Inc.
Ross Widener, Widener & Tanaiya Anderson, Lumen.
Assoc.
Ed Thompson, Representing Paul Elsaeed, Lumen
Renton School District
Reed requested non-working day for today (weather/rain/snow). G&O
submitted request to City— City confirmed today is non-working day.
Page 1 of 7
CITY OF RENTON
ifeDUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues— None per Phil
3. Prior Meeting Minutes—Comments/Acceptance —accepted
4. Weekly Statement for Working Days ending December 19, 2022
Days Expired: 230.5
Days Remaining: 31.5
5. Schedule Progress
Contractor's Look Ahead Schedule— last week's schedule. Work next
week tentative. Dustin waiting to hear back from landscapers. Some
wall forming possibly. Waiting on one result of hammer tests done
today: (Between 12th and 10r'') 2100 psi/2650 psi (13 days) —within
300 psi but unlikely to reach 4,000 psi. Will do one more coring. 7-day
break was 1210 psi.
Phil has tickets for mix design. Looked like concrete mix slump and air
passed. 3 remaining cylinders (took 7, 14, 28 and 56 days).
Foundation is part of sidewalk. 700 linear feet, but only tested first
truck and then last truck poured (took them today). Phil suspect's
MTC got the cylinders mixed up with another jobsite, possibly.
Concrete cylinders photos don't match what we poured—all cylinders
look different. First truck did minimal work(10th ramps and
surrounding).
2 pieces from the in place concrete to be sent to lab for coring. Break
one immediately, cure other "at temperature"for 7 days before
breaking. Question on if this can be done next week. If near 3000 psi,
pour wall.
Page 2 of 7
Gas °i CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Between Christmas and New Year's Day work, will work weather
permitting. 12/26 and 12/27 and 1/2 are City's holidays — City not
available these dates for plant inspection.
Weekly meeting for the 27th is cancelled
Plant Delivery to staging yard 7 day notification — Dustin to
check/email Phil a week in advance. Phil to notify City (Flora) to
inspect before planting. Question of low temperatures for planting.
Expected materials that are coming out on-site — topsoil (some onsite
already) and concrete if it warms up/good break
6. Utility Coordination -
a. COR Water Department —
• Storz Adapters installed on FH? Switched them out per Dustin.
Only one Storz adapter is complete. Three have brass change
outs and two more still require Storz adapters (in front of
Albertson's) per Phil. Phil spoke with sub in field.
b. Lumen - Pedestal removal yet to be completed and sidewalk patch
with HMA removed and repaired with cement concrete - nothing per
Phil. Tani to send strongly-worded email and Flora to follow up. Phil
questioned about a franchise agreement.
7. RSD Elementary School 16 Coordination — No issues/coordination.
8. Engineer's Report
a. Curb paint quote requested — received, under review. Question
regarding painting backside of curb?— not needed.
9. Inspector's Report
MTC - retesting for concrete cores for strength for Sidewalk due to
low break - See above.
Page 3 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
10.Environmental Compliance Report— no update
11. Public Outreach —no update
12.Submittals/Documentation
a. Review ROM - Posted
b. Submittals under review: plastic type D glass beads, irrigation
angle valve, electrical grout, conduit foam sealant, photo cell,
push button assembly, central control unit, CalPortland Conc Mix
for extruded curb
c. RAMs that need to be submitted:
• 42.05 non-shrink grout for fence post
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
—need submittal for upcoming landscaping work.
• 71.17/72.17 Galv. Steel Pipe (Landscaping) —Same as for
walls? G&O to follow up with email.
• 81.02/81.03 concrete, bronze tack
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
Flora should talk to Postmaster at USPS on 4th and
homeowner per Bob. Check bike lane crossing for mail
delivery. Consider move to side street(12th) and adding
locking box. Sleeve is already installed for new mailbox
location per Dustin.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
14. FWD/ Change Orders—
• CO 24— L08 Foundation modification --sent to Reed for sigs
• CO 25 —extended limits for paint stripe with supplemental
RPM's—City reviewing draft
• CO 26—Wall rev's in WZD, Sidewalk replacement and
fence/root removal — in the works Bob confirmed removal
tracked by CO—create new FA Bid Item. Draft to City
15.Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City,Inc. $139,480.00
3. Totem Electric of Tacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
3b. Transportation Systems,Inc. $100,000.00
4. Lakeridge Paving Company,LLC $706,900.00/
5. Stripe Rite,Inc. $42,778.60+
6. C&P Fencing $2,177.70
7. W.E.Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.0&
10. Concrete Services $192,934.00
11. Puget Construction Services,Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. $15,000.00
15. Integrity Networks $22,432.15
16. Transportation Systems,Inc. $100,000.00
16.Certified Payrolls— missing TSI payrolls Dustin — will get it this
week.
Page 5 of 7
CITY OF RENTON
MRDUVALL AVE NE
CAG-20-065
Prowess Paym.st N.II(October) Progress Pav 000l No 12(November) Prop.,.Payme t No 13(D.coetc)
Week Gaya Om e-00 15-0e 22-On Mkt 5-Nov u-Nee 19-Nov 26-Nov 3-Dec 10-Dee 171Do. 24-Doe 31-Dor
Reed Trckie 13-On 24-On 37-On 2-Nov 18-Nov IS-No. 23-Nov 1-Dee 7-Dee 15-Dec
W_E.Comm No Wade No Wodc 31-On No Wade No Work No Wodc I-Dee No Work 15-Dec No Work X
POD L. No Work No Work No Work No Work No Work No Work No Wok No Work No Work No Work X
Pose CmMrim No Wade No Wok 2-Nov No Wade 18-Nov No Work No wok No Wok No Work No Work X
Coacete Services 17-On No work No wet 8-Nov No Wok No Wodc No Work No Wok No Week No Work X
Lwyortaam systems No work 2-Nov 2-Nov X
Evergreen Seems* No Work No Work 8-Nov No Work No Work No Work No Work No Work 7-Dec X
Crowd Up No Wok No Wok No Week No Work No Week No Work No Work No Work No Work No Wok X
Lepcy Typi*B 10-On No Wodc No Wdc No Week X X X X X X X X
Lactic*Psvog No Work No Work No Work 8-Nov 22-Nov X X X X X X X
Tyee Co.eeete No Week No Wok No Wok No work No Wok No Wet No West I-Dec No weds 15-Dec X
'Seipe Rite X X X X X X X 5-Dee No Work X _
Caeca Cry X I X X X X X X X X X
Week Contractor Subcontractor is on the job site,payroll required- '°(#12)indicates payroll number**
X Subcontractor was not on-site this week "No Work Performed"payroll required
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Resubmirtal
No Work Received"No Work Perfuiiued"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 13 — cutoff Dec 23 and submittal to the City
by Jan 03.
Other Items:
Page 6 of 7
�\T Y OA, CITY OF RENTON
0+ + DUVALL AVE NE
4Ae N T°`" CAG-20-065
WZC-Jan-May 2022
WZA- Feb-May 2022
WZB& E-Mar-Aug 22.2022 - RYD ___IWZD-Sept-Nov 14. 2022 Z ` -j/`
WZF(Medians)-Nov-Jan 8,2023 r
, loci!. ( i
, 0_7-- :,. fir
IT-- �� HELMS PiorJECTI- 1
LOCATION 1
7 y „`_N[1, ST
,,' — ,
N
Y T Y Y
�' 4 Z"� J wat Zae C
\ T* to . *,,
1
id ____ 81
) 'b" NF 6TH Si N
/ ,
/ 2
r 3
: APROJECT
LOCATION
LIIIIIIIIIIIk
1 -SCHEDULE A
l—)
r
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NO lO',LAlk -SCHEDULE C
City of Renton - Duvall Ave NE, CAG 20-065
Page 7 of 7
o'Y o CITY OF RENTON
+ DUVALL AVE NE
"TO T°� CAG-20-065
CONSTRUCTION MEETING MINUTES
DECEMBER 14, 2022, 3:00 PM
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Tanaiya Anderson, Lumen
Assoc.
Ed Thompson, Representing Dustin Weller, PSE
Renton School District
Paul Elsaced, Lumen
Page 1 a 6
CITY OF RENTON
;IR DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues— Median accident—reverted lane closures to TCP
for Work Zone F
Sequential arrow board accident—sequential arrow board light lenses
were cleaned off
3. Prior Meeting Minutes— Comments/Acceptance — No comments
4. Weekly Statement for Working Days ending December 13, 2022
Days Expired: 226.5
Days Remaining: 35.5
5. Schedule Progress
Contractor's Look Ahead Schedule — Finish before Christmas, weather
permitting
Illumination — Wiring
Walls
Irrigation/Landscaping
Permanent Signing/Striping
Between Christmas and New Year's Day work, will work weather
permitting
Plant Delivery notification of 7 days — Unsure of plant's timeframe.
Deliver to staging yard
Expected materials that are coming out on-site — Irrigation
6. Utility Coordination -
a. COR Water Department—
• Storz Adapters installed on FH? Tomorrow
b. PSE — need to remove extra conduit and handhole from staging area,
Coordinate with Phil/Dustin. Done
Page 2 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Lumen - Pedestal removal yet to be completed and sidewalk patch
with HMA removed and repaired with cement concrete - Working on
it
7. RSD Elementary School 16 Coordination —
a. School's Contractor to repair damaged F.O. conduit, status?
Finished
b. School contractor would like to leave chain link/security fence
as is for safety. No issue with leaving the fence as is.
8. Engineer's Report
a. Thermoplastic schedule —40 degrees min and dry day needed.
The temp paint marking limits for crosswalks and stop lines
sent out to Reed Trucking. Reflective yellow paint needed for
extruded curb in medians. Tani requested quote from Dustin
b. City changing permanent crosswalk lines to two transverse
lines, no piano key lines.
c. Concrete walls in WZE — WZD heights increased
d. Ped Detour to be removed - has been removed
9. Inspector's Report
MTC - testing for concrete for Sidewalk and extruded curb completed
—All done. Waiting for crushed surfacing test
10.Environmental Compliance Report— none
11. Public Outreach — no issues
12.Submittals/Documentation
a. Review ROM - update is posted on CMS
b. Submittals under review: irrigation and plastic type D in review
—plastic boxes ok for irrigation purposes if H2O rated
c. RAMs that need to be submitted:
• 42.05 non-shrink grout—for fence post
Page 3 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.04..84/72.02.02 p.ri-Faer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping) —Same for
walls?
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
• Utah beads resubmittal.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders —
• FWD No 31 —Wall terminations at SL Foundations — WZD—if}
the works sent out
• CO 24— L08 Foundation modification in the works —City
reviewing draft sent to Reed for sigs
• CO 25 — extended limits for paint stripe with supplemental
RPM's — City reviewing draft, Tani to add curb paint
15.Subcontractor Status—
Page 4 of 6
CITY OF RENTON
• cm DUVALL AVE NE
s°a CAG-20-065
REQUEST
NO. SUBCONTRACTOR A6IOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City,Inc. S 139,480.00
3. Totem Electric of Tacoma,Inc. S734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
3b. Transportation Systems,Inc. $100,000.00
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E.Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services,Inc. $15,000.00
12. 1 Transporation Systems,Inc $48,110.00
13. ;Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. $15,000.00
15. Integrity Networks $22,432.15
16. Transportation Systems,Inc. $100,000.00
16.Certified Payrolls — missing TSI payrolls
Process Poymwt N.11(October) Primrose Par..t N.12(Nov.tiar) Progress P.2troe No 13(Member)
Week Lodl.g Or. 1-0e1 15Oct 22-Oct 29-Oct 5-Nov 12-Nw 19-Nov 24-Nov 3-Dea 10-Doe 17-D.c 24-Dec 31-Doc
Reed Trucking 13-Oa 24-Oct 27-Oct 2-Nov 18-Nov 18-Nov 23-Nov 1-Dec 7-Dec
WE.Coates No Wodc_No Work 31-Oct No Wade No Wade No Week 1-Dec No Wodc X X
AD Logging No Week No Wak No Wak No Wade No Weak No Work No Wodc No Work No Work X
Paget Construction No Wade No Wodc 2-Nov No Work 18-Nov No Work No Work No Work X X
Commie Services 17-Oct No Wolk No Week 8-Nov No Week No Wade No Work No Work X X
Transportation Systems No Week_ 2-Nov 2-Nov
Evergreen S.svcatrag No Work No Work 8-Nov No Work No Wade No Work No Work No Wok 7-Dee _
Gromd Up No Work_No Work No Work No Work No Wok No Work No Work No Wade X X
Legacy Tapped 10-Oct _No Wodc No Wade No Work No Wet& X X X X X X X X
Lakmdge Posing No Week Na Wok No Wade 8-Nov 22-Nov Miss X X X X X _ X X
Tyee Cmoee No Wade Na Work No Work No Wad, No Weak No Work No Wodc 1-Dec X
Stripe Rite X X X X X X X 5-Dec No Week
Week Contractor/Subcontractor is on the job site,payroll required_ "(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required-
- -_ __ -.-- -
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required i ( ��i
Payroll Resubrnittal
No Work Received"No Work Performed"payroll pa3z r ,
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 12 — submitted
Page 5 of 6
CITY OF RENTON
if? DUVALL AVE NE
CAG-20-065
• Progress Payment No 13 — cutoff Dec 23 and submittal to the City
by Jan 03.
Other Items:
Weekly meeting next week on 12/20, not on following week on 12/27
WZC-Jan-May 2022 j
WZA-Feb-May2022 Nf WNSp7 A� �Y 4 J.
WZB&E-Mar-Aug 22,2022 --__ _ Z
WZD-Sept-Nov 14,2022 \ 1 i ! - . yr
WZF(Medians)-Nov-Jan 8,2023
Y L NIp...-J H
'1 T
TT___ ti► LOCATION gU , 51 1
1 • i 41 eh
MEP ••
1.1 mo..._11.111. EIS. NM . z; : =Ilk
woos w
Vett ma
- - �GTE ST W
'A il N
ye 4 k _
r 3
PROJECT :
LOCATION — NE RH ST �
I
E I ' '
_::. 4 ---1 _ r
WATER MAIN IMPROVEMENTS
N -SCHEDULEB
VICINITY MAP i UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
City of Renton- Duvall Ave NE, CAG 20-065
Page 6 of 6
REEDC. Date: 12/10122- 12/30122 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
December
Sched
ID Work Description S S M T W T FSSM T W T F SS M T W T F Notes / Resources
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Illumination X X X X X
Form wall X X X X
walls X
Irigation and landscaping X X X X X X X X X
Raise iron X X X X X
Signs X X X X X
Punchlist items X X X X X X X
CITY OF RENTON
DUVALL AVE NE
1,1R
CAG-20-065
CONSTRUCTION MEETING MINUTES
DECEMBER 06, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Rcnton School District
Michael Sippo, City of x Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Tanaiya Anderson, Lumen
Assoc.
Ed Thompson, Representing Dustin Weller, PSE
Renton School District
Paul Elsaeed, Lumen
Page 1 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report —
Traffic control issues— None
3. Prior Meeting Minutes — Comments/Acceptance — Accepted
4. Weekly Statement for Working Days ending December 5, 2022
Days Expired: 220.5
Days Remaining: 41.5
5. Schedule Progress
Contractor's Look Ahead Schedule — 4 days for curb at medians per
Dustin. Suspension likely needed if concrete curb cannot be placed.
CSI to do Sidewalk pour tomorrow, at 9am. 2-3 pours remain for TSI
walls. Temp. painted stop bars/x-walk. Stop removal of planter
islands and fill with dirt. Work on permanent signing.
Plant Delivery notification of 7 days
Expected materials that are coming out on-site —
6. Utility Coordination -
a. COR Water Department —
• 2 Irrigation services to be done with WZF: 12/06/22 8:00 am?
Completed
• Storz Adapters installed on FH? No update
b. COR Transportation Maintenance - HAWK Signal Turn. Later today,
module needed from signal shop. Use paint for stop bar. Painted
crosswalk will be minimized and thermoplastic placed over it later.
Then remove pedestrian detour.
c. PSE — need to remove extra conduit and handhole from staging area,
Coordinate with Phil/Dustin. Not done
Page 2 of 6
CITY OF RENTON
DUVALL AVE NE
„IR
CAG-20-065
d. Lumen - Lumen contractor on site Monday for conduit/wire repair.
Pedestal removal yet to be completed. Existing telephone vault to be
adjusted to finished grade by Lumen at WZD, Sta 919+40 RT buck out
the sidewalk and surface sidewalk section with HMA or CSTC if lumen
does not come out
7. RSD Elementary School 16 Coordination —
a. School's Contractor to repair damaged F.O. conduit, status?
b. Is it possible to shift chain link/security fence back at back of
curb along frontage so peds do not walk in bike lane? Has not
been completed. Previously, security was placed approx. 5ft
from back of curb.
8. Engineer's Report
a. Thermoplastic schedule — 40 degrees min and dry day needed
b. Concrete pours 35 degrees or higher forecast —
c. Ped Detour to be removed with HAWK signal Turn on or hold
for conc. pour?
9. Inspector's Report
MTC - upcoming testing for concrete for Sidewalk and extruded curb
10.Environmental Compliance Report— no updated
11. Public Outreach — Nothing
12.Submittals/Documentation
a. Review ROM
b. Submittals under review: irrigation in review, plastic type D
additional information requested from Reed, Tuff Curb approved
c. RAMs that need to be submitted:
Page 3 of 6
CITY OF RENTON
DUVALL AVE NE
".11R
CAG-20-065
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
• Utah beads resubmittal.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs — RFI 27 for Plant Substitution sent
14. FWD/ Change Orders —
• CO 23 — to be signed by Bob today
• FWD No 32 — Wall terminations at SL Foundations —WZE
• CO 24— L08 Foundation modification in the works -quote
received, in review. Tani to get in final form as FA
• CO 25 — extended limits for paint stripe with supplemental
RPM's — in the works
Page 4 of 6
a.
0 Y o . CITY OF RENTON
+ + DUVALL AVE NE
,ok"N 1 o CAG-20-065
15.Subcontractor Status—
REQUEST
NO. ;SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. i Green City,Inc. $139,480.00
3. Totem Electric ofTacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
3b. Transportation Systems,Inc. $100,000.00
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E.Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. 1 Puget Construction Services,Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. j $15,000.00
15. Integrity Networks $22,432.15
16. Transportation Systems,Inc. j $100,000.00
16.Certified Payrolls —
Progress Payment No 11(October) Progress Payment No 12(November)
I Week Ending On: 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
Reed Trucking 13-Oct 24-Oct 27-Oct 2-Nov 18-Nov 18-Nov 23-Nov I-Dec
W.E.Coates No Work No Work 31-Oct No Work No Work No Work I-Dec No Work X
PnD Logging No Work X X No Work No Work No Work X X X
Puget Construction No Work No Work 2-Nov No Work 18-Nov No Work No Work No Work X
Concrete Services 17-Oct No Work No Work 8-Nov No Work No Work No Work No Work X
Transportation Systems No Work 2-Nov 2-Nov
Evergreen Sawcutting No Work No Work 8-Nov No Work No Work No Work No Work No Work
Ground Up No Work No Work No Work No Work No Work No Work No Work No Work X
Legacy Tapping 10-Oct No Work No Work No Work No Work X X X X
lakeridge Paving No Work No Work No Work 8-Nov 22-Nov I8-Nov X X X
Tyee Concrete No Work No Work X No Work No Work No Work No Work I-Dec X
Stripe Rite X X X X X X X X
Week ContractorSubcontractor is on the job site,payroll required_ **(=12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
—AM Corrections to payroll required
Apprenticeship doe's required
Payroll Resubmittal
-o Work Received"No Work Performed"payroll
15-Feb "Final"payroll
Page 5 of 6
CITY OF RENTON
DUVALL AVE NE
I,
11R
CAG-20-065
17.Progress Payment—
• Progress Payment No 12 — cutoff November 30 and submittal to
the City by Dec 6
• Progress Payment No 13 — cutoff Dec 23 and submittal to the City
by ??
Other Items: Per Contract, Christmas to New Year's Day are non-Working Days.
Reed available for working Christmas week if weather permits/conducive to placing
concrete or other subcontractor work. Phil available. Ok with Bob. Tani available off
and on.
WZC-Jan-May 2022
WZA-Feb-May 2022
WZB&E-Mar-Aug 22,2022 r 4Es etvo Z
WZD-Sept-Nov 14, 2022 z
WZF(Medians)-Nov-Jan 8,2023 ' i
C14Eatir
� NE IZTUCps _ -1
----A
LOCATION �W _-_-,
-SC _EDTIOULE 21 I NE AT
.r S kJ
� _
1 WsVc
Wat Zone
WI K
Nirk ty
) II%1 [ ‘:"r NM i
Wo NE6THST N
. ' W
2 4—II I
' NE 47H Si ' -- S
PR ��� T.t; _—
, Am-
LOCATION!I
HE LE A
• rt_
i
T c�• F—'-
WATER MAIN IMPROVEMENTS
N -SCHEDULE 8
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCAIf -SCHEDULE C
City of Renton - Duvall Ave NE, CAG 20-065
Page 6 of 6
1-
REEDc Date: 12/03122-12/23/22 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
c..u...+w...a«.wvi
December
Sched
ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes/ Resources
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Illumination X X X X X
hawk signal X X
Form wall ? ? ? ? ?
pour walks ? ? ? ? ?
walls ? ? ? ? ?
Demo islands X X X
!ligation services X
Pour Island curb ? ? ? ?
Weather suspension X X X X X X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
DECEMBER 01, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Tanaiya Anderson, Lumen
Assoc.
Ed Thompson, Representing Dustin Weller, PSE x
Renton School District
Page 1 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues— cones that were knocked down were righted
3. Prior Meeting Minutes— Comments/Acceptance —
4. Weekly Statement for Working Days ending November 30, 2022
Days Expired: 218.5
Days Remaining: 43.5
5. Schedule Progress
Contractor's Look Ahead Schedule— next Wednesday for HAWK
signal turn-on, tentatively. Dec 5th/6th for irrigation services, topsoil,
wiring in the next week, no gluing of irrigation pipe in freezing temps
An updated project schedule requested for remaining work.
Expected materials that are coming out on-site — topsoil
6. Utility Coordination -
a. COR Water Department—
• 2 Irrigation services to be done with WZF:
• Reed Trucking has coordinated with water group for the taps
on 12/5 and12/6 at 8am.
• Per standard plan 320.1, the 1-inch copper water service from
the tap to the meter box and setter is "direct-bury" under the
roadway pavement. No PVC sleeve is required or needed on
the copper service line that will owned and maintained by the
City.
• The city water maintenance section will provide all water
materials (copper pipe, meter setter, corporation stop) and
will perform the tap onto the existing water main and they will
install the service line(s), meter setter(s) and meter box(es) in
the new median planter strip.
Page 2 of 8
CITY OF RENTON
zsm DUVALL AVE NE
CAG-20-065
• Dustin noted,freezing weather will limit Landscapers ability to
glue/install pvc piping.
• The contractor is responsible for excavating the trench, expose
the existing water main at the 2 locations, backfill the trench,
restore the roadway, and providing traffic control. Dustin
confirms that Reed will provide steel sheets
b. Storz Adapters installed on FH? Received but not installed
c. PSE—need to remove extra conduit and handhole from staging area,
Coordinate with Phil/Dustin.
d. Lumen - Lumen ROW permit application submitted 11-16-22. The
permit was issued 11-17-22. Waiting to hear the schedule for the
work:
i. Existing telephone vault to be adjusted to finished grade
by Lumen at WZD, Sta 919+40 RT
ii. Existing pedestal at Sta 919+15 RT exposed for removal
— Lumen getting locates. They began work but broke a
conduit with live feed to private property
7. RSD Elementary School 16 Coordination—
a. School's Contractor to repair damaged F.O. conduit, status?
When does Reed need the repair complete? Integrity is the sub
to do the FO work. Dustin wants the conduit repaired ASAP
b. Is it possible to shift HVF fence back at back of curb along
frontage so peds do not walk in bike lane?
8. Engineer's Report
a. Thermoplastic schedule — 40 degrees min and dry day needed
b. Cold weather and concrete pours— Will City sign a waiver?
City to let Contractor know. The answer "No- the City will not
sign a waiver", was later delivered.
c. Cement Conc. Retaining Walls at Street Light Foundations—
WZE— discussed change at exposed street light foundations.
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Dustin says there may be more surface finish to incorporate
foundation as part of wall. Vertical rebar at termination ends
per existing detail.
' � 3/g" PREMOLDED
JOINT FILLER
9. Inspector's Report
MTC - upcoming testing for concrete for Sidewalk and extruded curb
10.Environmental Compliance Report— nothing new
11. Public Outreach — nothing new
12.Submittals/Documentation
a. Review ROM — see CMS
b. Submittals under review: Utah beads (will go out today),
irrigation, plastic type D
c. RAMs that need to be submitted:
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
Page 4 of 8
CITY OF RENTON
DUVALL AVE NE
iiR
CAG-20-065
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
• Tuff Curb Submittal — received today and under review.
d. Non-Material Submittals that need to be submitted: cold weather
concrete plan. Plan may not be needed since concrete will not be
placed in cold weather.
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders—
• CO 22 — Extra Depth Pulverization — sent to City for approval
• CO 23 — Eight Street Light Pole Mods in the works --sent to City for
approval
• CO 24— L08 Foundation modification in the works -quote
requested. Dustin is finalizing and will send.
• CO 25 — extended limits for paint stripe with supplemental RPM's—
in the works
15.Subcontractor Status—
Page 5 of 8
ca\1 Y Ok CITY OF RENTON
+ +
` DUVALL AVE NE
ill
M',T o, CAG-20-065
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. ::Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. j Integrity Networks(Lower Tier); $22,432.15
3b. Transportation Systems, Inc. $100,000.00
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. :W.E. Coates $61,500.00
8. Legacy Tapping, Inc. I $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc I $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks $22,432.15
16. 'Transportation Systems, Inc. I $100,000.00
16.Certified Payrolls —
Progrress Payment No I1(October) Progress Payment No 12(November)
1 Week Ending On: 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
Reed Trucking _ 13-Oct 24-Oct 27-Oct 2-Nov 18-Nov 18-Nov 23-Nov
W E.Coates No Work No Work 31-Oct No Work No Work X X X
PnD Loggig No Work X X No Work No Work X X X
Puget Construction No Work No Work 2-Nov No Work 18-Nov No Work s X X
Concrete Services 17-Oct No Work No Work 8-Nov No Work No Work X X
Transportation Systems No Work 2-Nov 2-Nov
EvergreenSawcutting No Work No Work 8-Nov No Work No Work No Work X X
Ground Up No Work No Work No Work No Work X X X X
Legacy Tapping 10-Oct No Work No Work No Work X X X X
Lakeridge Paving No Work No Work No Work 8-Nov 22-Nov 18-Nov X X
Tyee Concrete No Work No Work X No Work No Work No Work X X
Stripe Rite X X X X X X X
Page 6 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor/Subcontractor is on the job site,payroll required ""(#12)indicates payroll number**
X Subcontractor was not on-site this week "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship dot's required
Payroll Resubnuttal
No Work Received"No Work Performed"payroll
,H,7111"Finar payroll
17.Progress Payment—
• Progress Payment No 12 — cutoff November 30 and submittal to
the City by Dec 6th
Page 7 of 8
CITY OF RENTON
DUVALL AVE NE
-IR
CAG-20-065
18. Other Items:
WZC-Jan-May 2022
WZA-Feb-May 2022 A
IIEV'
WZB&E-Mar-Aug 22,2022 r ' litvn 1 - w�zn
WZD-Sept-Nov 14,2022 z iWZF(Medians) Nov-Jan 8,2023r ' _
toi.
, dP
• UM TT _I
£o L P' 1
LOCATION J
1
RULE a --I }NE iun sr 1
:,:,;_,.,i4... 1i1I)1i411r W N-.-, i
l 1‘i01p 0.
z1 C
F::
.
■W_� r
o
o
I_ -
NE 4TN ST `.....0 g
PROJECT a
0 LOCATION NM
E 4051
DuLEA,
�� r
• s
se . a4 I -1-
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCAUE -SCHEDULE C
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
NOVEMBER 22, 2022
Comments made during the meeting are shown in italics.
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Tanaiya Anderson, Lumen
Assoc.
Ed Thompson, Representing Dustin Weller, PSE
Renton School District
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
.ilFe
CAG-20-065
2. Safety Report—
Traffic control issues— Get warning signs back up
3. Prior Meeting Minutes— Comments/Acceptance —Accepted
4. Weekly Statement for Working Days ending November 21, 2022
Days Expired: 215.5
Days Remaining: 46.5
Thanksgiving and day after are non-working days - Reed taking the days
off
Reed requesting a rain day for 11/22/22 and it will be approved
5. Schedule Progress
Contractor's Look Ahead Schedule —
Electrical work delayed. Next week signs, light poles, grade
sidewalk/crosswalk, #6 bar
An updated project schedule requested for remaining work.
Expected materials that are coming out on-site — Thermoplastic,
Plants (December 1).
6. Utility Coordination -
a. COR Water Department —
• 2 Irrigation services to be done with WZF - Dustin
to coordinate with water group for the taps. Tom
Main is point of contact. Notify within 10
calendar days of when tap needed.
Dustin proposes no grind for irrigation trenches.
Mole if possible. Ok per Bob.
• Storz Adapter status— Received
b. PSE Power
• PSE meter is installed. PSE underground work is
complete.
Page 2 of 7
CITY OF RENTON
ifeDUVALL AVE NE
CAG-20-065
c. Lumen - Lumen ROW permit application submitted 11-16-22.
The permit was issued 11-17-22. Waiting to hear the
schedule for the work:
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT
• Existing pedestal at Sta 919+15 RT exposed for removal
7. RSD Elementary School 16 Coordination —
a. Conflict between new conduit on Duvall Ave NE project and
School Dist project Street light foundations. School's
Contractor to repair conduit as needed. Phil talked with Kyle.
Electrician has not repaired yet
8. Engineer's Report
• At school frontage. Use hydroseeding in lieu of topsoil for
restoration.
• Striping updates:
o East side paint/RPM's completed on Saturday 11-19-22.
o West side paint/RPM's under construction on Monday
11-21-22.
o Thermoplastic schedule— Wednesday with waiver
o Paint Line with supplemental RPM's installed between
8th and 10th in lieu of all RPM lane lines and cl.
Question on if change order should be made to replace
paint line with RPMS. Yes per Bob. No field work
directive needed.
9. Inspector's Report
MTC— completed testing for wall concrete
MTC - upcoming testing for concrete for Sidewalk
MTC— Extruded curb
10.Environmental Compliance Report— Nothing
Page 3 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11. Public Outreach —
12.Submittals/Documentation
a. Review ROM — Updated
b. Submittals under review: Utah beads, irrigation
c. RAMs that need to be submitted:
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
• Thermoplastic Type D
d. Non-Material Submittals that need to be submitted: cold weather
concrete plan.
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders —
Page 4 of 7
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 22 — Extra Depth Pulverization — sent to Reed for sig. .
• CO 23 — Eight Street Light Pole Mods in the works — City reviewing
quote change order sent to Reed for signature
• CO 24— L08 Foundation modification in the works -quote
requested
15.Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
3b. Transportation Systems, Inc. $100,000.00
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. !Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. 1Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. 1 Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. 1Tyee Concrete Construction, Inc. $15,000.00
15. {Integrity Networks $22,432.15
16. 'Transportation Systems, Inc. $100,000.00
Page 5 of 7
•
CITY OF RENTON
gimR% DUVALL AVE NE
CAG-20-065
16.Certified Payrolls—
Progress Payment No 11(October) Progress Payment No 12(November)
Week Ending On: 8-Oct 15-Oct 22-Oct 29-Oct - 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
Reed Trucking 13-Oct 24-Oct 27-Oct 2-Nos
W.E.Coates No Work No Work 31-Oct No Work X X
PnD Long No Work X X No Work No Work X
Puget Construction No Work No Work 2-Nov No Work X
Concrete Services 17-Oct No Work No Work 8-Nov X X
Transportation Systems No Work 2-Nov 2-Nov
Evergeen Sawcutting No Work No Work 8-Nov No Work No Work X
Ground Up No Work No Work No Work No Work_ X X
Legacy Tapping 10-Oct No Work No Work No Work X X
Lakeridge Paving No Work No Work No Work 8-Nov
Tyee Concrete No Work No Work X X X X
Week Contractor/Subcontractor is on the job site,payroll required- **(#12)indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed"pa\Toll required{
15-Feb Date certified payroll was recieved
Corrections to
hi payroll required
Apprenticeship does required L
Payroll Resubmittal
I
-
No Work Received"No Work Performed payroll
15-Feb "Final payroll
17.Progress Payment—
• Progress Payment No 12 — cutoff November 30 and submittal to
the City by Dec 6th
• Question on if City can provide sure curb. Dollar value requested.
Bob told Dustin to buy what was needed
• Provide Tuff curb submittal
• Question on closing crosswalk for thanksgiving. Yes per Bob
Page 6 of 7
CITY OF RENTON
RDUVALL AVE NE
CAG-20-065
18. Other Items:
WZC-Jan-May 2022 — L--)
WZA-Feb-May 2022
WZB&E-Mar-Aug 22,2022 r MEs icon z _
WZD-Sept-Nov 14,2022 1 i • ii
—
WZF(Medians)-Nov-Jan 8,2023 II
N 12TH•
1 P'�jj _ 1
-- / LOCATION iI`
TT
■ EMI
`, '� UJPN.
Z 1 Waft ant C
411114
` Nf 7TH Mo
i
‘[
-
W
NE 6TH 3T N
j W
ll, 1
lir '— I NE 4TH ST I g
PRO1E
ss LOCATION gal
s►dis L -�CFf ELNJLE A
`a
(..O fr: — . ____
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP I UNDERGROUND IMPROVEMENTS
NOT TO soul -SCHEDULE C
City of Renton- Duvall Ave NE, CAG 20-065
Page 7 of 7
REEDC. Date:11/19122-12/09/22 3 Week Look-Ahead Schedule
TRUCICM &EXCAVA7W Name: Duvall Avenue
-1November -�'1December
Sched
ID Work Description S S M T W T FSSM T W T F SS M T W T F Notes/Resources
19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9
Illumination X X X X X X X X X X X X X
hawk signal X X X X X X X X X X
grade sidewalk X X X X
Form wall X X
pour walks X X
walls X X X X X X X
Set up WKZ F X X
Saw cut Islands X X
Demo islands X X
Irigation services X
Pour Island curb X X X X
Raise iron - X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
NOVEMBER 15, 2022
Comments made during the meeting are shown in italics.
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tanaiya Anderson, Lumen
Assoc.
Ed Thompson, Representing Dustin Weller, PSE x
Renton School District
Page 1 of 8
CITY OF RENTON
DUVALL AVE NE
NR
CAG-20-065
2. Safety Report—
Traffic control issues— No issues
3. Prior Meeting Minutes— Comments/Acceptance — accepted
4. Weekly Statement for Working Days ending November 14, 2022
Days Expired: 209.5
Days Remaining: 52.5
Veteran's day was a non-working day
Thanksgiving and day after are non-working days - Reed taking days off
per Dustin
5. Schedule Progress
Contractor's Look Ahead Schedule — Months need to be updated on
look ahead schedule. Waiting for TSI. #6 bar holding things up (wall
footing), and rebar cages not ready for street light foundations per
Dustin. This holds up sidewalk as well. Dustin reaching out to get ETA
but waiting to hear back. Prepping for landscaping in WZE. Pavement
markings down soon hopefully, but Dustin needs survey. 72-hour
notice for them. Will likely take 3 days. Striping on short notice is
challenging. 50 degrees for plastic, and 40 degrees for paint is
needed. Air/surface temp. Unlikely this week. Dustin to check. City
hoping to avoid work suspension due to striping delay. City will waive
14 day HMA curing period.
Expected materials that are coming out on-site — Pavement
markings, rebar, Plants (December 1).
6. Utility Coordination -
a. COR Water Department —
• 2 Irrigation services to be done with WZF end of
November - Dustin to coordinate with water
Page 2 of 8
CITY OF RENTON
DUVALL AVE NE
•IFe
CAG-20-065
group - City does the tap. End of November for
Dustin's work. Flora to confirm with Tom Main as
point of contact. Notify within 10 calendar days.
• Storz Adapter status - No update per Dustin.
Difficulty procuring brass.
b. PSE Power
• Rush reconnect - PSE to replace meter at HAWK
signal per connect/disconnect permit. The meter
number the City has on file for this location is:
A016876876. The reference number for this
reconnect is 512134058. What is the schedule
for this work? No update on timing for meter
reconnection for HAWK per Dustin Weller.
Reached out to NCC group that handles
installation, but have not heard back. Phil to
forward email of PSE contact to Dustin Weller.
c. Lumen - Have not heard back. Some conduits that feed
pedestal are empty. Other conduit needs to move 2 inches.
Pedestal can be pushed back to get 4' clearance from back of
curb to face of pedestal. Phil concerned that Lumen will never
fix it if it is pushed out of the way, so City will continue to tell
Lumen they are in the way— wall at back of walk can't be
constructed until pedestal is relocated. Tani to help Flora craft
email.
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT
• Existing pedestal at Sta 919+15 RT exposed for removal
7. RSD Elementary School 16 Coordination —
a. The conduit status at SW corner of 10th/Duvall - Complete
b. Conflicts between new conduit on Duvall Ave NE project and
School Dist project Street light foundations. School's
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
-IR
CAG-20-065
Contractor to repair conduit as needed. School to excavate at
two more locations for foundations —only one has potential for
conflict.
c. Landscaping along school frontage in front of 10t". City plan for
synthetic turf. Ped scale light going with conduit in planter
area. Synthetic turf ok. Remove and reinstall synthetic turf if
conduit needs to go in after turf installation.
d. Plans show 2 inches topsoil/hydroseed at 12th to 10th behind
curb. School contractor wants to do sidewalk. Question on use
of hydroseed if sidewalk going in. Won't be doing restoration
until middle of summer per Michael Sippo. Use hydroseeding in
lieu of topsoil—Reed to hydroseed in late December.
8. Engineer's Report
a. One HMA wearing course area completed on 11-9-22
b. Confirm treatment for shoulder/embankment along school
frontage. Plans call for hydroseed/topsoil. Lots of pedestrian
activity observed there. See above.
c. Solvent based paint may be installed at 40 degrees per manuf.
recommendations, WSDOT Spec calls for 50 degrees and
rising but also references per manufacturer's
recommendations. 50°F for plastic, 40°F for solvent-based
paint per Mfg.'s recomendations. Consider plastic that allows
for less than 50° F for installation.
9. Inspector's Report HMA testing complete. Wall testing complete.
Will be out for testing one more time for final sidewalk and wall
footing along east side.
MTC— completed testing for HMA placement 11-9-22
MTC upcoming testing for concrete for Sidewalk/walls
10.Environmental Compliance Report— No update
11. Public Outreach — No update.
Page 4 of 8
CITY OF RENTON
DUVALL AVE NE
;IR
CAG-20-065
12.Submittals/Documentation
a. Review ROM — Updated ROM on CMS this morning
b. Submittals under review: glass beads submittal returned with
note to submit on Utah Blend glass beads for lettering, fence posts
submittal for alt source noted 21 inch versus 18 inch per detail. 21
inch or cutting to 18 inch okay.
c. RAMs that need to be submitted:
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
d. Non-Material Submittals that need to be submitted: cold weather
concrete plan.
e. Material Documentation — Ok. See above
13. RFIs— none
14. FWD/ Change Orders—
Page 5 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 22 - Extra Depth Pulverization - sent to Reed for sig. Dustin will
sign today.
• CO 23 - Eight Street Light Pole Mods in the works - City reviewing
quote 15% markup is incorrect, commented. Some labor rates
seem high. Need FA rates for TSI.
• CO 24- L08 Foundation modification in the works -quote
requested - Phil confirmed modification work wasn't done- L08
foundation has been installed per original Plan. Dustin looking into
it.
15.Subcontractor Status- all up to date.
REQUEST THIS PREVIOUS SUBLET Rec'd
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS
1. Ground Up Road Construction,Inc. $25,575.00 0.49% 0.00% 0.49% 8/11/2021
2. Green City,Inc. $139,480.00 2.70% 0.49% 3.19% 8/11/2021
3. Totem Electric of Tacoma,Inc. $734,636.80 14.21% 3.19% 17.39% 8/12/2021
3a. Integrity Networks(Lower Tier) $22,432.15 3.05% 0.00% 3.05% 12/15/2021
3b. Transportation Systems,Inc. $100,000.00 13.61% 3.05% 16.67% 11/8/2022
4. Lakeridge Paving Company,LLC $706,900.00 13.67% 17.39% 31.07% 8/16/202I
5. Stripe Rite,Inc. $42,778.60 0.83% 31.07% 31.89% 8/16/2021
6. C&P Fencing S2,177.70 0.04°A° 31.89% 31.94% 8/20/2021
7. W.E.Coates $61,500.00 1.19% 31.94% 33.13% 12/15/2021
8. Legacy Tapping,Inc. $20,150.00 0.39% 33.13% 33.52% 1/27/2022
9. PnD Logging $10,000.00 0.19% 33.52% 33.71% 2/16/2022
10. Concrete Services $192,934.00 3.73% 33.71% 37.44% 3/17/2022
11. Puget Construction Services,Inc. $15,000.00 0.29% 37.44% 37.73% 3/18/2022
12. Transporation Systems,Inc $48,110.00 0.93% 37.73% 38.66% 3/21/2022
13. Evergreen Concrete Cutting,,Inc $3,000.00 0.06% 38.66% 38.72%,4/15/2022
14. Tyee Concrete Construction,Inc. $15,000.00 0.29% 38.72% 39.01% 8/2/2022
15. Integrity Networks $22,432.15 0.43% 39.01% 39.44% 8/30/2022
16. Transportation Systems,Inc. $100,000.00 1.93% 39.44% 41.38% 11/8/2022
16.Certified Payrolls-
Progress Payment No II(October) Progress Payment No 12(November)
Week Ending On: 8-Oct 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
Reed Trucking 13-Oct 24-Oct 27-Oct 2-Nov
W.E.Coates No Work No Work 31-Oct No Work X X
PnD Long No Work X X No Work No Work X
Puget Construction No Work No Work 2-Nov _ No Work X
Concrete Services 17-Oct No Work No Work 8-Nov X X
Transportation Systems No Work 2-Nov 2-Nov
Evergreen Sawcutting No Work No Work 8-Nov No Work No Work X
Ground Up No Work No Work No Work No Work X X
Legacy Tapping 10-Oct No Work No Work No Work X X
Lakeridge Paving No Work No Work No Work 8-Nov X
Tyee Concrete No Work No Work X X X X
Page 6 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor/Subcontractor is on the job site,payroll required. **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 11 — submitted to the City with deferral for
last week of TSI work.
• Progress Payment No 12 — cutoff November 30 and submittal to
the City by Dec 6th
18. Other Items: Dustin — requested to stay on after to discuss schedule of
wall/sidewalk in WZD and WZE (Ecology funded).
Phil wants to modify north end to open up left lane at Sunset and allow
more cars now that paving lift is complete; will make traffic flow more
efficient in the morning. Flora agrees.
Question regarding TSI work on wiring for HAWK Signal. No comment per
Dustin
Page 7 of 8
CITY OF RENTON
„IR DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 r -_ )
\ w V
WZA-Feb-May 2022 •
ArESU ewe t—IWZB&E-Mar-Aug 22,2022 a lipr
IWZD-Sept-Noy 14,2022 L g ,,,
WZF(Medians)-Nov-Jan 8,2023
�� P•• Jii p irni ST 1 i
ECT^ _ i l
LOCATION , •
110, 4EDULE. i NE 1013,sr j I
IN IL IN -
•---"1... 111411111* 11101 .=
�
I� Hlj ATM
W , L-- '
'<
�
W �
W NE 6TH ST u.
A_ i a` ' >
F' S
�' + [I NE 4TH ST ` g
PROJECT _— —
LOCATION
, Fr-; —i ,
"� i E I_1
7:L3
lY WATER MAIN IMPROVEMENTS
N -SCHEDULE S
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULE[
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
REEDcr. Date:11112/22-12/02/22 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
,- ••< a......... ..... (October I [November
Sched
ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes/Resources
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2
Illumination X X X X X X X X X X X X X
hawk signal _ X X X X X X X X
grade sidewalk X X X X X X X X
pour wall footing X X
pour walks X X �
walls \A X X
raise iron X X X X _1�
Lumen Ped is in the
way of this pour
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
NOVEMBER 8, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Vice X Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc. X
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Dustin Weller, PSE
Assoc.
Ed Thompson, Representing Tanaiya Anderson, Lumen
Renton School District
Page 1 of 8
CITY OF RENTON
• DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues— Phil—long talk with TCS—inclement
weather/stop signs/signs, should be more prepared for signs blowing
over...need sandbags onsite. Also an option to place signs on a 4x4 post
(available onsite); payment under Bid Item for Construction Signs
Class A.
3. Prior Meeting Minutes— Comments/Acceptance — accepted.
4. Weekly Statement for Working Days ending November 7, 2022
Days Expired: 205.5
Days Remaining: 56.5
5. Schedule Progress
Contractor's Look Ahead Schedule — Dustin — working on updating
schedule. Hoping TSI picks up pace. Paving— would like tomorrow
(noon to 3) but not sure weather will comply—may be too cold. Phil
verified 35 degrees & rising is compliant due to lift thickness. Actual
measurement varies from 2.5 inches to 3 inches. It's over 2/10
threshold so 35 is compliant. Phil thinks 11 trucks will adequately
pave during those three hours. City confirmed should be okay
tomorrow since it's 35 and rising.
Next challenge will be striping....may need to use temp until Spring.
Conversation over paint versus MMA...City leaning towards paint. But
MMA threshold is 40 degrees. Paint threshold is 50 degrees.
Friday Nov 11 is a non-working day for Veteran's Day per the
Contract
Dustin —only if subs want to work— unlikely. Dustin to follow up.
Expected materials that are coming out on-site— none.
Page 2 of 8
CITY OF RENTON
DUVALL AVE NE
5
CAG-20-065
6. Utility Coordination -
a. COR Water Department—
• 2 Irrigation services to be done with WZF Dustin —
one of first order of work, waiting for TSI,
tentatively Dec 1, so end of Nov for irrigation.
• Storz Adapter status —Supplier received 1-2
pumper ports, waiting on rest to show up.
• 10th FH Bolts, stolen from bottom flange are
replaced
b. PSE Power
• Work status: Everything is complete. PSE to replace
meter at HAWK signal when ready per
connect/disconnect permit Hot and ready to go with
PSE sticker. Needs meter globe—PSE will furnish.
Additional info needed for PSE application (unsure if it's
old service number?)
c. Lumen - Dustin to block out around the pedestal. No
franchise agreement exist; Flora to check City Code. Lumen
has not responded in timely manner and they need to get out
to the way. Contact person appears to not have ability to
direct this work. Flora to draft email to Lumen (Lynn), and give
it to Martin to send. Pouring next week. Unsure what is live in
the vault. Also new cell tower complicates it.
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT
• Existing pedestal at Sta 919+15 RT exposed for removal
7. RSD Elementary School 16 Coordination —
a. The conduit at SW corner of 10th/Duvall prior to concrete pour.
Yes and no...some was done but then stopped. Unsure of why.
b. SW corner - Waiting on hardware before pouring signal base.
Planning to install as soon as hardware is available.
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
8. Engineer's Report
a. One HMA wearing course area was not completed last week
due to rain. Contractor will try to pave this week if
temps/weather permits, less than half a day needed to
complete wearing course
b. Median curb modification could be considered if final wearing
course cannot be completed until Spring 2023.
9. Inspector's Report Phil updated:
MTC— completed testing for HMA placement - all test results passing,
but have not received 11/3/22 results yet.
MTC upcoming testing for concrete for Sidewalk/walls
10.Environmental Compliance Report— None identified except taking
out CB socks last Friday.
11. Public Outreach —
Property owner on NW corner of NE 12" says FH pad is into his
property— R/W was staked by PMX surveyor. FH pad is in the
permanent easement. Further comments received from property
owner. Phil—owner is convinced that the easement is only 5'from
BOW. Home owner plans to follow up with City.
Residents off of 10t" and 12' east side of Duvall — second round of
fliers handed out regarding temp closures for paving on 11/3/22.
Property management for Argo Investment took photo of Reed
Trucking water truck dumping water into the parking lot drainage
system. Dustin clarified it was True Value parking lot. Dustin
apologized for dumping clean water and won't do it again.
Page 4 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
12.Submittals/Documentation
a. Review ROM — updated last week.
b. Submittals under review: glass beads coordinating with City.
Fence posts—coordinating with Parametrix.
c. RAMs that need to be submitted:
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
d. Non-Material Submittals that need to be submitted: Dustin to
submit cold weather concrete plan.
e. Material Documentation —
13. RFIs— none
Page 5 of 8
CITY OF RENTON
MIRDUVALL AVE NE
CAG-20-065
14. FWD/ Change Orders —
• CO 22 — Extra Depth Pulverization —sent to Reed today
• CO 23 — Eight Street Light Pole Mods in the works — Dustin sending
quote today
• CO 24— L08 Foundation modification in the works -quote
requested — Dustin still waiting on quote.
15. Subcontractor Status—
REQU EST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
Page 6 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
16.Certified Payrolls— Tiffani to send to Tani by 2 pm today— TSI has
received approval on their Statement of Intent and will fill missing
payroll. Alternatively, Progress Payment#11 will be revised with
deferral for missing payroll and sent to the City by 2pm.
Progress Payment No 11(October) Progress Payment No 12(November)
Week Ending On: 8-Oct 15 Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nov 26-Nov 3-Dec
Reed Trucking 13-Oct 24-Oct 27-Oct 2-Nov
W.E.Coates No Work No Work 31-Oct X X
PnD Logging No Work X X X X
Paget Construction No Work No Work 2-Nov No Work X
Concrete Services 17-Oct No Work No Work X
Transportation Systems No Work 2-Nov 2-Nov
Evergreen Sawcutting No Work No Work X X
Ground Up No Work No Work X X X
Legacy Tapping 10-Oct X X X X
Lakeridge Paving No Work No Work No Work
Tyee Concrete No Work No Work X X X
Week Contractor/Subcontractor is on the job site,payroll required. **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-FebDate certified payroll was recieved
Corrections to payrol required ; 1
_ Apprenticeship doc's required I
- -
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 11 — submitted to the City
• Progress Payment No 12 — cutoff November 30 and submittal to
the City by Dec 6th
18. Other Items:
Confirmed (tentative)schedule for paving is tomorrow at noon.
Prior to the meeting, Phil reported the following pavement surface
temperatures for today:
• 37 degrees @ 7am
• 41 degrees @ 10:45am
• Will take a temperature reading at noon
Page 7 of 8
CITY OF RENTON
aliz DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022
r WZA-Feb-May 2022
I WZB&E-Mar-Aug 22,2022 NEsu eLvp z4 IMP *
1 WZD-Sept-Nov 14,2022 IR 101 It ,..\
WZF(Medians)-Nov-Jan 3,2023 ' _
A ? __ ti--
N£4
L P�O1 _ „ ,__
aib LOCATION N
-SCHEDULE, NE 10T_F ST j _
c? ii. N Ilir _
low
Irk
N
le
vist4
__74.1
Waa Zane C
H ?rN -----
Z
w di' Q W
l—
a — NE 6TM sr
-4_
/ c m
1 C
' � 1.. 111 NE 4T115T
PROJECT ' __ I- L_t- _
LOCATION�rlNana
diiik
LIT LDILE2
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO sous -SCHEDULE C
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
NOVEMBER 1, 2022
Comments made during the meeting are shown in Italics
1. Meeting Attendees
Bob Hanson, City of Renton ✓ Phil Van Earwage, G&O ✓
Flora Lee, City of Renton ✓ Tani Stafford, G&O
Josef Harnden, City of ✓ David Roman-Sanchez, G&O ✓
Renton
Dustin Wright, Vice ✓ Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed ✓ Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of ✓ Yong Qui, City of Renton ✓
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. ✓
Ross Widener, Widener & Dustin Weller, PSE
Assoc.
Ed Thompson, Representing Tanaiya Anderson, Lumen
Renton School District
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
iR
CAG-20-065
2. Safety Report—
Traffic control issues— none
3. Prior Meeting Minutes— Comments/Acceptance — accepted
4. Weekly Statement for Working Days ending October 31, 2022
Days Expired: 201.5
Days Remaining: 60.5
5. Schedule Progress
Contractor's Look Ahead Schedule — TSI this week,foundation pours
Paving, sweeping, tack(no update, shoot for tomorrow)
PCMS boards- off until paving day chosen
Expected materials that are coming out on-site —
6. Utility Coordination -
a. COR Water Department—
• 2 Irrigation services to be done with WZF
• Storz Adapter status—
10th FH Bolts, stolen from the bottom flange, FH is
bagged and will fix asap
b. PSE Power
• Work status:
I. West side of Duvall - blow string line in to existing
power vault on 12th to the new meter base for
Hawks signal. - Complete
II. West side - reroute PSE conduits into the new J08
Vault in the sidewalk section on Duvall, so that
the existing J07 vault can be removed and
sidewalk poured in that section — Partially
complete
Page 2 of 7
CITY OF RENTON
• ,:y DUVALL AVE NE
CAG-20-065
III. East side - provide a line man to retrieve string
line from proofing, in existing vault J05 - Status?
Complete
IV. East side - install new pole P06 - Complete.
V. West side— install new pole P07 for Church -
complete
VI. West side - Outage notification for Oct 31 shutoff
at Albertsons - complete
VII. Pull wires/complete cut over— status? - Need
cutovers for church +cell tower
VIII. East side - remove existing poles i (gone) and
P06—status? - Thurs this week will be complete
c. Lumen - work covered under existing CIP permit
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT
• Existing pedestal at Sta 919+15 RT to be removed
Both items above: no power involved
7. RSD Elementary School 16 Coordination —
a. The conduit at SW corner of 10th/Duvall prior to concrete pour.
On track for concrete pour
b. SW corner - Waiting on hardware before pouring signal base.
Planning to install as soon as hardware is available.
8. Engineer's Report
a. Storm belly repair work accepted
9. Inspector's Report
MTC— completed testing for HMA placement - one more day for
compaction testing
MTC upcoming testing for concrete for Sidewalk/walls
Page 3 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
10.Environmental Compliance Report—
11. Public Outreach —
Property owner on NW corner of NE 12th says FH pad is into his
property— R/W was staked by PMX surveyor. FH pad appcirs to be
is in the permanent easement ✓
Residents off of 10th and 12th east side of Duvall —fliers handed out
regarding temp closures for paving.
12.Submittals/Documentation
a. Review ROM — posted
b. Submittals under review: glass beads
c. RAMs that need to be submitted:
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
Page 4 of 7
CITY OF RENTON
• frz DUVALL AVE NE
CAG-20-065
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders—
• CO 22 — Extra Depth Pulverization — draft in review by City
• CO 23 — Eight Street Light Pole Mods in the works — Dustin getting
quote - Reed will Finalize
• CO 24— L08 Foundation modification in the works -quote
requested
15. Subcontractor Status —
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
Page 5 of 7
CITY OF RENTON
;I DUVALL AVE NE
CAG-20-065
16.Certified Payrolls—
Progress Paymeet No 9(Ask) Peeress Peyreeet No 0(Aaret) Prey.'Papw.No 10(September)
Week E.ig Om PJ.1 16J.1 23-Jot 30Jul 6-Aeg 13-A.g 24A.g 27-Ao0 3-Sep 18-Sep 17-Sep 24-Sep 1-Oct
Reed Tackier 14J4 22Jd 29-Jul 5-Aug 12-Aug 2-Sep 2-Sep 2-Sep t-Sep 15-Sep 4-Od 29-Sep 6-Oct
W.E.Comes 15-161 22-14 No Wait No W'ak No Work No Woek No Woek No Wodc 7-Sep No Wart No Wort 4-Oct 17-Oct
Totem Ekssic 2-Aug 2-Aeg ® X X X X X X X X X X
ND Logging No Work Nowak 2-Aug No Wart No Wort No Work No Wade Nowak No Week No Work No Week No Work Nowak
Puget Comeecti. No Wort No Work No Work No Work No Work No Wale No Wore No Wak No Wok No Wad No Wak No Work 17-Oct
Coto Services No Wok 2-Aug - 2-Aug 2-Sep 2-Sep No Week No Wade No Wadc No Week Nowak Nowak No Work 10-Oct
To.sportetios Systems 22Jd No Work No work 5-Aug 7-Sep 7-Sep No Work No Wok 8-Sep 4-Oct No Work 4-Oct
Evergreen Sawcmfng No Work No Wok No Week No Work 12-Aug No Work No Work No Wort No Work No Walt No Wok No Weds No Work
Ground Up No Work No Work No Work No Work No Work 2-Sep No Wade No Work 9-Sep No Wodc No Wort No Wak No Work
Legacy Teppkg No Work No Wade No Work No Work 5-Aug No Work No Wort No Wort No Work No Work No Work No Week No Watt
Luck ridge Pmig No Work No Work No Wort No Week No Weds No Wort 7-Sep No Wok No Wok No Work No Wak No Work No Wort
lye'Co.oreoe X X 4-Aug No Work No Wok No Wort No Wak No Week No Wok No Work No Work No Wort No Work
Pewee.Parrot No 11(October) Progress Pane.Ne 12(Noveroe) Progress Pay.e.t No 13(D.o.r.d
Week Poly Om 6-Ott 15-Oct 22-Oct 29-Oct 5-Nov 12-Nov 19-Nes 26-Nov 3-Dec 10-Dec 17-Dec 24Dee 31-Dot
HeedTmdirg 13-Oct 24-Oct 27-Oct
W.H.Comm No Work No Work X
PtD Logging No Work X X X
Puget Construction No Wale X X
Concrete Services 17-Oct X X
To.spaoreaa Systems X
Evergreen Sewottog No Wok No Work X
Gamd Up No Week No Work X X -
Leopcy Tappug 10-Oct X X X
'Attridge Pests No Work No Wak No Wade
Tyre Concrete X X X X
Week Cofactor/Subcontractor is on the job site,payroll required. **(#12)indicates payrol ember** 1
X Subcontractor was not on-site this week. "No Work Performed"payroll required-
15-Feb Date certified payroll was recieved j
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
.eb "Final"payroll
17.Progress Payment—
• Progress Payment No 11 — cutoff Oct 31st for Nov 3rd submittal to
the City
18. Other Items:
Thurs — updated Fliers for temp closures for paving
Page 6 of 7
,-1-'' oA• CITY OF RENTON
tift? DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 iii i
___.
WZA-Feb-May 2022
WZB&E-Mar-Aug 22, 2022 7-'' kf awn 1_j
WZD-Sept-Nov 14, 2022 Z
WZF(Medians)-Nov-Jan S,2023 ' ' 77f.(11/11*
citt i
k.`
y
, \ ilN 12'TH ,1 E
1 i
„o ;
P• JE - i
-�s, LOCATION
m , MEDULEI — NE1. i 1
.___ J ]
;, lli..
lNIP �N • • +
a., _,A,_.
r.
.,.. .
Z 3
11111011110
[ 1I --- - o-
o .I I i_ NE 6711 ST N
ec }——
W
,,,,.r. Ali N _,
' o -i- 1.
1 4
I Il ME4TH ST
PROJECT S
5� LOCATION '-
IdokIEDU
II I. f-r- —
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCAEE -SCHEDULE C
City of Renton - Duvall Ave NE, CAG 20-065
Page 7 of 7
CITY OF RENTON
• o_. DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
OCTOBER 25, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Dustin Weller, PSE x
Assoc.
Ed Thompson, Representing x Tanaiya Anderson, Lumen
Renton School District
Page 1 of 8
CITY OF RENTON
• ,_:: DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues— No issues
3. Prior Meeting Minutes—Comments/Acceptance — Accepted.
4. Weekly Statement for Working Days ending October 24, 2022
Days Expired: 196.5
Days Remaining: 65.5
5. Schedule Progress
Contractor's Look Ahead Schedule— Paving Thursday (weather
permitted) per Dustin. Question brought up on if all pipes and
conduits complete below paving area. TSI may be out tomorrow.
Flatwork TBD. Paving across 10th and 12th intersections. Phil
commented that 12th can be closed (Apartment has second access),
but people will be landlocked at 10th. Need to have emergency access,
so tapered joint won't work. Need wedges. If 12th is closed, provide
outreach to apartment building. Distribute door hangers if no face-to-
face contact is made. Dustin will talk with paver and look at phased
closures to alternate shut downs. Two lifts per day. Question brought
up on if steel sheets will be used at 10th. Dustin will send plan.
PCMS Boards Required:
PCMS boards are activated for paving work -
Expected materials that are coming out on-site — HMA and wire.
6. Utility Coordination -
a. COR Water Department—
• 2 Irrigation services to be done with WZF
• Storz Adapter status — No update.
b. PSE Power
Page 2 of 8
CITY OF RENTON
DUVALL AVE NE
iR
CAG-20-065
• 17 working days window for PSE crew to complete work
per Dustin Weller—PSE move up the start date to-Oct.
25th. Started today. Dustin Weller working with Reed
regarding timing/sequencing, Scheduling outages, and
trying to minimize impacts as much as possible. Focused
on South of 12th work currently. New transformer, then
Jbox near Albertson's is next. PSE generally provides 3-
day notifications for outages minimum, but tries to give
7 days. Question brought up on what work is critical for
street light and sidewalk completion.
• Can likely work around Reed paving.
• Work to complete by PSE:
I. On the west side of Duvall, PSE will need to allow
TSI to blow string line in to existing power vault
on west side of Duvall on 12th to the new meter
base for Hawks signal. This is the power feed for
the Hawks signal.
II. On the west side PSE needs to reroute their
existing conduits into the new J08 conduits in the
sidewalk section on Duvall, so that the existing
J07 vault can be removed and sidewalk poured in
that section.
III. On the east side, PSE will need to provide a line
man to retrieve string line from proofing, in
existing vault J05.
IV. On the east side the new pole at P06 needs to be
installed
V. On the west side the existing pole P07 will need
to be held
VI. Outage notifications
VII. PSE needs to pull wires, complete cut over, heat
up service to church and remove existing poles
P08 and P06 existing so sidewalk can be poured
and walls completed.
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
TIR
CAG-20-065
c. Lumen Raul Elsaeed at Lumen is working on permit for
pedestal removal and on vault adjustment near SL 18.
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT
• Existing pedestal at Sta 919+15 RT to be removed
7. RSD Elementary School 16 Coordination —
a. The conduit at SW corner of 10th/Duvall prior to concrete pour.
Per Kyle, City can move forward with pouring and school will
have to fix, but would rather have conduit installed first if
possible. This work is most critical.
b. New PSE pole to be installed at church after all? Happening
today per Dustin Weller.
c. Waiting on hardware before pouring signal base. Planning to
install as soon as hardware is available.
8. Engineer's Report
a. Storm belly repair work in review - Waiting on okay from
maintenance.
9. Inspector's Report
MTC -Upcoming testing for HMA placement and concrete for
Sidewalk/walls
Did have curb pour yesterday. Will test cylinders when sidewalk pour
takes place and compaction on paving when it takes place.
10.Environmental Compliance Report— No update. Plastic has been
going over piles within staging areas.
11. Public Outreach —
Page 4 of 8
CITY OF RENTON
• I_. DUVALL AVE NE
1
CAG-20-065
Property owner on NW corner of NE 12th says FH pad is into his
property— R/W to be staked by PMX— Next week
Albertsons and other PSE affected customers— PSE to notify
customers regarding planned outages associated with their work
Kaba Investments, Starbucks - Outreach regarding restoration limits
on west side of Duvall, north end
12.Submittals/Documentation
a. Review ROM — no updates
b. Submittals under review: glass beads and Mon case/cover-
Discussing internally
c. RAMs that need to be submitted:
• 42.05 non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor
• 98.01 mailbox support, type 1
d. Non-Material Submittals that need to be submitted:
Page 5 of 8
CITY OF RENTON
• _; DUVALL AVE NE
A,
CAG-20-065
e. Material Documentation — good shape
13. RFIs— no new
14. FWD/ Change Orders—
• CO 22 — Extra Depth Pulverization — draft in review by City
• CO 23 — Eight Street Light Pole Mods in the works — Dustin getting
quote. Bracket welding
• CO 24— L08 Foundation modification in the works -quote
requested
15. Subcontractor Status— nothing new.
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
16.Certified Payrolls— needs updating
Page 6 of 8
c0 Y o CITY OF RENTON
+ iltl';' +
DUVALL AVE NE
CAG-20-065
r Poly)Payment No 8 .ty) Progress?aroma No 9(Amid) Progress Pay.«t No 16(SapbmkM
Eedm ) -
WeekgOec 9.1.t 16Jet 23.1.1 3PJe1 6-Avg 13-Aag 20-Avg 27-Am 3-Sap 18Sap 17Sep 24Scp 1-Oet
Reed Tmckeg 14-1u1 22-1u1 29-Jul 5-Aug 12-Aug 2-Sep 2-Sep 2-Sep 8-Sep 15-Sep 4-Oct 28-Sep 6-Oct
WE.Coates 15-88 22-Id No Wad No Wed No Work No Work No Work No Wad 7-Sep No Work No Work 4-Oct 17-Oa
Totem Electric 2-Aug 2-Aug - X X X X X X X X X X _
PoD Logging No Work No Work 2-Am No Wedc 14o Work No Work No Work No Work No Work No Wodc No Work No Work No Work
!Paget Construction No Wad No Work No Work No Work No Work No Work No Work No Wak No Work No Work No Work No Wad 17-Oct
!Concrete Services No Work 2-Aug 2-Aug 2-Sep 2-Sep No Work No Work No Work No Work No Work No Work No Work 10-Oct
'Transportation Systems 22-Jul No Work No Work 5-Aug 7-Sep 7-Sep No Work No Work 8-Sep 4-Oct No Work 4-Oct
Evergreen Sawcutrmg No Week No Work No Work No Wadc 12-Aug No Work No Work No Work No Wodc No Work No Wed No Work No Work
Grand tip No Work No Work No Work No Work No Work 2-Sep No Wert No Work 9-Sep No Wad No Work No Work No Wart
;Legacy Topping No Wark No Work No Work_No Wad_ 5-Aug No Work No Work No Work No Week No Work No Work No Work No Work
.Lakaidge Paving No Wod No Work No Wad No Work No Work No Wak 7-Sep No Work No Work No Work No Work No Wade No Work
;Tyne Canaete X X 4-Am No Work No Work No Work No Work No Wort No Wodc No Work No Work No Wade No Work
I_.-..... Prowess Pasme.t No 11(OcWer) Progress Pawnee&No 12(November) Progress Pay-moot No 13(December)
Week Ending Oar 8-Oct 15-Oct 22-Oct 29Oct 5-Noe 12-Noe 19-Nov 26-Nov 3-Dec 10-Dec 17-Dee 24-Der 31-Der
Seed Trucking 13-Oct -.
W'E.Coates No Work X X
PaD Logging No Wade X X .-,
Puget Construction No Wad X
,Concrete Services 17-Oct X X
Traosgartatioo Systems X
Evergreen Sawmill* No Work No Work
Grand Up No Wed No Work X
Lemey Toppng 10-Oct X X
Lekeridge Pavng No Work No Work No Work i
,Tyne Cooaete X X X
Week Contractor/Subcontractor is on the job site,payroll required. **(#12)indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed"payroll required-
•
1 5-Feb Date certified payroll was recieved
IIIIIIIIICorrections to payroll required
Apprenticeship dot's required
Payroll Resubmittal 1 - I
No Work Received"No Work Performed"payroll j
15-Feb "Final"payroll l
_ l I
17.Progress Payment—
• Progress Payment No 11 — cutoff Oct 315t for Nov 3rd submittal to
the City
18. Other Items:
Page 7 of 8
1
CITY OF RENTON
% DUVALL AVE NE
CAG-20-065
.. _ ____]
WZC-Jan-May 2022 `_vim'
'WZA-Feb-May 2022 .
WZB&E-Mar-Aug 22,2022 r?' Pk sat i;rni, __
WZD-Sept-Nov 14,2022 fl
WZF(Medians)-Nov-Jan 8,2023
. I l..__I 10 l'
TT LOCATION I
g . ` P-FIECF" ' \ --I ( Li
Ilk F{EOULE, �... I NE 1ST ....J
� -� J
lir N il
r , fN gsft
, ;Ars"
16,40.,, ,_ }
14, 111
o
NE 6TH ST
W
i C
' HE 4TH 5T
Yiffe
PROlE � � g_ ._
LOCATION NI
OF Tt£3,01 PRP riillIllk rate.E j
Is Fr5: — 7
WATER MAIN IMPROVEMENTS
N -SCHEDULE a
VICINITY MAP UNDERGROUND IMPROVEMENTS
Nor TOSCAIE -SCHEDULEC
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
REEDC. Date:10/22/22-11/11/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
441*wOwl Gm.*Woo rM
September October
Sched
ID Work Description MTWT FSSMTWTF 7- �- M T W T F Notes/Resources
24 25 26 27 28 29 30 31 1 2 3 4 7 8 9 10 11
CSBC and CSTC —.1 X X X -
Illumination X X X X X X X X X X X X X
Sidewalk and curb prep X X X X X X
•
Flatwork and curb pour X
Paving X X X
PSE X X X X X X X X X X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
OCTOBER 18, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O _ x_
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener &
Assoc.
Ed Thompson, Representing x
Renton School District
Dustin Weller, PSE x
Tanaiya Anderson, Lumen
Page 1 of 9
CITY OF RENTON
DUVALL AVE NE
iiIR
CAG-20-065
2. Safety Report— No safety issues
Traffic control issues—
City Operations wants Hawk Signal Operational ASAP — TSI still has all
their work to do to set new box, pull wires and set signal cabinet. Per
City Operations: HAWK at 10th needs to remain in operation as long as
12th is still down —at least 1 crossing for the school children. Bob
questions if having an operational HAWK signal at 12th is safe within all
the other construction activities. Ed agrees. Flaggers are present to
assist pedestrians crossing Duvall during working hours. We discussed
that the critical path item of paving and flatwork are also required for
reinstating a ped crossing at 12th
3. Prior Meeting Minutes— Comments/Acceptance — Accepted
4. Weekly Statement for Working Days ending October 17, 2022
Days Expired: 191.5
Days Remaining: 70.5
5. Schedule Progress
Contractor's Look Ahead Schedule—Sidewalk prep. Ready to install
light pole bases. Working with TSI to hurry up on HAWK signal- Can
get arms low enough (up to 4 feet). TSI is busy with Totem work, so
HAWK signal work may not take place soon. Proposed use of FA for
payment on pole mods. Need TSI FA rates. Curb pour next week,
depending upon CSI. May demand a short load fee. Dustin to follow
up.
Work hours shifting with shorter days? Yes, 7:30 to 3:30
PCMS Boards Required:
10 days in advance of Intersection closure for paving —start Oct 17
Onsite. Need to know message — Tani to send Dustin message and CC
Phil.
Page 2 of 9
CITY OF RENTON
DUVALL AVE NE
aR
CAG-20-065
Expected materials that are coming out on-site— wire
6. Utility Coordination -
a. COR Water Department— all out in the future.
• 2 Irrigation services to be done with WZF schedule
• Storz Adapter status — No update; should be
heading this way.
• City to turn FH on today per Flora.
b. PSE Power
• 17 working days window for PSE crew to complete work
per Dustin Weller—PSE move up the start date to Nov 1
—Start date moved up to Oct. 25th. 17 working days
confirmed.
• Paving 27th/28th/315t per Dustin Wright. Weather not
looking good. Installation of first base lift considered.
• Work to complete by PSE: Challenging to prioritize work
since much is contingent on other orders of work per
Dustin Wright
I. On the west side of Duvall, PSE will need to allow
TSI to blow string line in to existing power vault
on west side of Duvall on 12th to the new meter
base for Hawks signal. This is the power feed for
the Hawks signal. Need lineman to open vaults
per Dustin Weller. Should be early order of work
per Tani.
II. On the west side PSE needs to reroute their
existing conduits into the new J08 conduits in the
sidewalk section on Duvall, so that the existing
J07 vault can be removed and sidewalk poured in
that section. Reed trucking has to excavate and
expose these conduits for PSE or will PSE use a
vac truck to expose their live power feeds to be
Page 3 of 9
CITY OF RENTON
DUVALL AVE NE
iiR
CAG-20-065
relocated? This question was asked of Potelco
inspectors but no answer was given. Need to pull
out ex vault in sidewalk, has live wires per Phil.
Reed to expose conduit per Dustin Weller. Need
to notify Albertson's about an upcoming power
outage per Phil. Dustin Weller to follow up.
III. On the east side, PSE will need to provide a line
man to retrieve string line from proofing, in
existing vault J05.
IV. On the east side the new pole at P06 needs to be
installed to finish the conduit sweep to that pole
V. On the west side the existing pole P07 will need
to be held to finish the conduit sweeps up that
pole for the switchover from overhead to
underground.
VI. PSE needs to pull wires, complete cut over, heat
up service to church and remove existing poles
P08 and P06 existing so sidewalk can be poured
and walls completed.
• PSE permit confirmed to be in order Noted.
c. Lumen Tanaiya Anderson is our new contact Paul at Lumen is
working on permit for pedestal removal and on vault
adjustment near SL 18.
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT
• Existing pedestal at Sta 919+15 RT to be relocated
behind new wall
7. RSD Elementary School 16 Coordination —
a. Schedule for elevated signal foundation in SW corner of NE
10t" St— 10th pole bases are approved to install but waiting on
hardware per Ed. No word on when pole bases to be poured.
Page 4 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. The conduit crossings at 10th across Duvall are complete for
paving, are they extended for sidewalk pour? Conduits
crossings across 10th and Duvall are in place. TS] working with
Reed on east side work. All conduit needs to be done in
sidewalk on SW corner of 10th/Duvall prior to pour. Ed will
discuss timing with Cornerstone.
c. 12th street church pole - all is good.
8. Engineer's Report
a. Street light L18 new location sent to Reed. Standard
foundation. PMX is revising curb ramp to go with.
b. Storm pipe accepted
c. Structure Exc CI B— Contractor calc's 175 CY for storm
structures, storm structures also include excavation. G&O
confirming quantity for PP11.
d. Pulverization payment limit, extra depth — Phil confirmed extra
depth of HMA was observed. City will pay for the
subcontractor's direct cost submitted $5050, Change order to
follow.
9. Inspector's Report
MTC -Upcoming testing for Asphalt placement and concrete for
Sidewalk/walls
10.Environmental Compliance Report—
11. Public Outreach —
Property owner on NW corner of NE 12th says FH pad is into his
property— R/W to be staked by PMX?To confirm - Next week
12.Submittals/Documentation
a. Review ROM —
Updated
Page 5 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Submittals under review: glass beads and Mon case/cover - Mon
case/cover reviewed and uploaded to CMS. Fence post sleeve and
PVC pipe has also been reviewed. Glass beads currently under
review
c. RAMs that need to be submitted:
• 42.05 fence post sleeve galv pipe and non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor (need
resubmittal)
• 98.01 mailbox support, type 1
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders—
Page 6 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 22 — L08 Foundation modification in the works -quote requested
• CO 23 — Eight Street Light Pole Mods in the works - quote requested.
• CO 24 — Extra Depth Pulverization — in the works
15. Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
16.Certified Payrolls —
Page 7 of 9
CITY OF RENTON
0 DUVALL AVE NE
CAG-20-065
i_—.--_-_ Propose Payment No Sgt.) Dogmas Payreat No 9(Aoeos) Progress Pomat No 10 ..)
Week Pais Om 94r 16Jd 23dd II 30dd 6-Aas 13-Aog 20-Avg 27-Aug 3-Sep 10-Sop 17 24Sep 1-Oc
'..,Reed Truckee 14-hi 22-1111 29-Li 5-Aug 12-Aug 2-Sep 2-Sep 2-Sep 2-Sep 1S-Sop INIMI 20-Sep 6-Oa
W.E.Cores 1S-16 22-1d No Work No Work No Work No Work No Work No Wok 7-Sep No Wodt No Work 4-Oct X
I Totem Electric 2-Avg 2-Aug 3-Ara X X X X X X X X X X
!PED Logging No Work No Work 2-Aug No Work No Work No Wodc No Windt No Work No Work No Work No Wok No Work No Work
IPoga Co a-rico No Week No Weir No Week No Wad. No Work No Work No Work No Weak No Work No Work No Work No Weak X
!Camels Services No Week 2-Aeg 2-Aug 2-Sep 2-Sep No Work No Wag No Weak No Wad: No Work No Wank No Weak 10-Oct
irampartetioo Systems 22-3d No Work No Work 5-Aug 7-Sep 7-Sep No Wed No Work S-Sep 4-Oct No Work 4-Oct
Eva grern Sav deog No Work No Wed: No Week No Work 12-Aug No Work No wag No Work No Work No Week No Work No weak No work
;Cneaod Up No Wog No wog No Wog No work No Work 2-Sep No Wok No Work 9-Sep No Wog No Wog No Week No wag
iLescy Teppcg No work No Work No Work No Wak 5-Aug No wog No Week No Weak No Wog No Weak No Weds No Wog No weak
ILdouidge Po.eg No Work No Work No Work No Work No Work No Work 7-Sep No Wort No Wog No wog No Wok No Work X
Tye<C ete X X 4-Aug No Work No Wog No Wog No Wog No Work No Wog No Walk No Work No Wog No weak
I _.. Parsed N.11(Odder) Progress Pummels No 12(Novembe) Progrote Payment No 13(December)
W.ek iarmg Oo g-Oct 15-Oct 22-0tl 29-0A 5-Nov 12-N1.• MN.- 26-Nov 3-Dec 1S-Doc 17-Dec 24-Doc 31-Dr
j Reed Tracking 13-Oct
!W.E.Cores X X _
!PDD Long X X ..
IPoget Coosa-action X X
:Concrete Sonses X _
Inespansion System X •
&agrees Sewrotiae No Work X - -
1Gomdlip X X
Leeocy Teppse 10-Oct X - .
jLakaidge Pm* X X
ITyce Corded X _ X _
Week Conlrador/Snbcontractor is on the job site,payroll required 'g'e(#12)indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
1111.Apprenticeship doc's required
I
Payroll Resubmittal
No Work Received No Work Performed'payroll ,
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 11 — cutoff Oct 31st for Nov 3rd submittal to
the City
18. Other Items:
Page 8 of 9
\I" O CITY OF RENTON
0 DUVALL AVE NE
CAG-20-065
WZA-Janb-May 2022 * 11
WZB&E- r-Aug 2
WZ8&E-Mar-Aug 22,2022 ) .1.11=
41' BLVD Z_I 111111p
WZD-Sept-Nov 14,2022 o r
WZF(Medians)-Nov-Jan 8,2023 ' il ip
tl„
4Pra
IfALOO _b
ATION - A_ :
Plall II • our•
I
pe Viiiii
'N' 111111110j MR u.
.,ilirlik _ 4 is. Pi•7TH '
41
NE 6TH ST 1u
� $1 _
c
rI4 I NE4TMST J i g
PPPPR•JE �I— ___—
LOCATION-i
jk
; , / J f — FL F I I
WATER MAIN IMPROVEMENTS
N -SCHEDULE 8
via NM'MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SQIEDULEC
City of Renton- Duvall Ave NE, CAG 20-065
- Thicker pavement in spots-$5050 ok
-Phil can verify extra depth
-Structure Excavation Cl. B—175 CY ok
Page 9 of 9
REEDe Date:10/15/22-11/04/22 3 Week Look-Ahead Schedule
TRUCKING 6£ CAVATWG Name: Duvall Avenue
IwNIw..uva CA*.•11.1 INI
September October
Schecl ,
ID Work Description MTWT F ,.S S. M T W T F - • r M T W T F Notes/Resources
17 18 19 20 21 `2 231 24 25 26 27 28 31 1 2 3 4
C59C and CSTC X X ' X X X >A 'j X X X X X X
Illumination X X X X X i 1 X X X . X X X
Sidewalk and curb prep X X X X . FN
Flatwork and curb pour I p X X
Paving 143 X X X
POE : 1 X X X X
4!
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
OCTOBER 11, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Vice X Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc. X
Trucking & Excavating Inc.
Traci Brewer-Rogstad, Michael Ballard, G&O X
Renton School District
Michael Sippo, City of Yong Qui, City of Renton X
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing X Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE X Eric Cutshall, City of Renton
Tanaiya Anderson, Lumen
Page 1 of 9
CITY OF RENTON
• .z, DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues — Phil noted forms and rebar needs to be removed
from sidewalk on west side. Dustin will follow up with foreman.
3. Prior Meeting Minutes— Comments/Acceptance — accepted
4. Weekly Statement for Working Days ending October10, 2022
Days Expired: 186.5
Days Remaining: 75.5
5. Schedule Progress
Contractor's Look Ahead Schedule— Dustin —buttoning up loose
ends. Demo & prep 10rh avenue to get ready for paving,
curb/gutter/sidewalk. Trenching for illumination began yesterday.
Waiting for TSI schedule; will follow after them. Grading prep for
paving and backfill of walls. Paving 27rh, 28th and 31.
Curb/gutter at 10th — likely to be last minute to paving. No firm date.
Waiting for TSI's schedule (walls/electric) before CSI does work
(curb/gutter/sidewalk). CSI will likely use same concrete mix as
before; they have not indicated a change.
PCMS Boards Required:
10 days in advance of Intersection closure for paving — start mid-
October for End of October pave — next week?
Expected materials that are coming out on-site— Dustin —none
scheduled. Wire forthcoming.
Page 2 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
6. Utility Coordination
a. COR Water Department—
• One FH in WZD schedule- complete
• 2 Irrigation services to be done with WZF schedule
— Dustin holding off Waiting for a while (closer to
median construction)
• 1 Irrigation service completed in WZD
• Storz Adapter status — Per Dustin, it looks like
they've been shipped, but no Date for ETA yet.
b. PSE Power per Dustin Weller—begin work on Nov 8th. Dustin
W. will research and send additional information. Dustin
Wright says 11/8 will cause delay getting to next work zone.
Reed expects to start WZF right after paving, expecting to shift
closures on November 7th. PSE work will include new pole,
pulling string into vaults, etc. Can't finish wall and sidewalk
next to power vault due to pole relocation. Pole is in the way.
PSE's 1" order of work was to relocate pole (per Phil). Unsure
of why this changed. Dustin Weller to look into accelerating
schedule but confirmed 17 working days to do work.
West side work won't delay paving. East side either.
•JUT and conduit install complete. Conduits need to be
proofed and mule tape installed by Reed—
• PSE to hold the existing pole on west side of roadway so
Reed can finish installing sweeps up existing pole—
Dustin Weller to set up a pole hold
• PSE to install the new pole on east side of roadway so
they can finish installing conduit up the new pole. New
pole needs to be installed prior to wall installation.
• Schedule for splices and wreck-out— 11/8 Start. Delay
into next work zone. Retaining wall work. 17 working
days
• PSE permit
Page 3 of 9
CITY OF RENTON
DUVALL AVE NE
iR
CAG-20-065
c. Lumen Tanaiya Anderson was invited to this meeting but did
not attend. Have pedestals requiring relocation. Need new
contact info.
• Existing telephone vault to be adjusted to finished
grade by Lumen at WZD, Sta 919+40 RT cut over
• Existing pedestal at Sta 919+15 RT to be relocated
behind new wall cut over
7. RSD Elementary School 16 Coordination — Ed—curb/gutter at NE
corner of 10th — Cornerstone is talking to Reed about constructing.
Discussion of conduit crossings from NE to SE(School's responsibility).
Ed to discuss with RSD and note any discrepancies. Pole update at
Church property— City's electrician will go across and feed ex pole at
ex location and then RSD will handle switchover.
a. Schedule for elevated signal foundation in SW corner of NE
10" St—
b. Schedule for 2 conduit crossings at 10th, one halfway across
Duvall — prior to paving possible? yes
8. Engineer's Report
a. Street light L18 new location, City confirming the easement —
Dustin needs SL 18 final location ASAP. Cindy checking on this
b. Storm belly to be repaired between CB 26 and CB 27, two
other storm bellies - City Engineering department is okay with
it, City checking with Maintenance department if bellies are
ok. City to check first report to see if bellies were identified.
c. Curb & sidewalk at NE corner of 10th, curb at FH and curb at
Filterra prior to pave
d. Structure Exc CI B— Contractor calc's 175 CY for storm
structures, storm structures also include excavation. Dustin
discussed payment for Exc CL B states payment will be made if
Bid Item is included in Proposal. Dustin's calc includes 26
structures that are wider than then they are deep. City to
consider if payment will be made under Exc CI B Bid Item.
Page 4 of 9
CITY OF RENTON
DUVALL AVE NE
iR
CAG-20-065
e. Pulverization payment limit— G&O noted Boring Logs are
included in the Contract Documents. Dustin discussed
subcontractor's request for additional payment since
additional effort/passes were made to pulverize the
pavement. Subcontract had also requested additional
compensation for previous phase however Dustin denied this
request since payment for that work had already been made—
this reduced the requested additional amount from $15K to
approx. $5K. City, G&O and PMX to discuss offline.
9. Inspector's Report
MTC -Upcoming testing for Asphalt placement and concrete for
Sidewalk/walls and CSTC.
10.Environmental Compliance Report —
11. Public Outreach —
Property owner on NW corner of NE 12th says FH pad is into his
property— 0.1'over on his property. Phil will meet with him, will
sawcut. Additionally, ADS pipe (broken during silt fence installation)
will need to be repaired at this property after silt fence is removed.
12.Submittals/Documentation
a. Review ROM —on CMS
b. Submittals under review: glass beads and Mon case/cover
c. RAMs that need to be submitted:
• 42.05 fence-post sleeve galv pipe and non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
Page 5 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.02/81.03 concrete, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor (need
resubmittal)
• 98.01 mailbox support, type 1
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs— No 26— landscape hatch. Response has been provided.
City can stake ROW if contractor will not
14. FWD/ Change Orders—
• CO 21 - Storm revisions at CB 37 — sent to City for approval
• CO 22 — L08 Foundation modification in the works -quote requested
• CO 23 — Eight Street Light Pole Mods in the works - quote requested.
Dustin indicated TSI will mock up one of the poles—they are leaning
towards cutting the tops. Discussed, this option is acceptable to the
City departments.
• CO xx—Supplemental RPM's/Traffic Arrows — in the works
Page 6 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
15. Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
Page 7 of 9
CITY OF RENTON
.41R% DUVALL AVE NE
CAG-20-065
16.Certified Payrolls —
Progress Payment No 4(2.1y) Progress?domed No 9(A. 8) Progress Payao.e No 11(S.Wwk..)
Week Ending O. 9-Jul 16.1 23401 3LJel 4-Ateg 13-A. 20-A.` 27-A.g 3-Sep 10-Sop 17- 24Sep 1-0d
Reed Tracking 14-Jut 22-Jul 29-101 7-Au! 12-Aug 2-Sep 2-Sep 2-Sep 8-Sep 13-Sep is 2.8-Sop boa
WE Cosies 15-Jul 22-Jd No Wok No Work No Work No Wade No Wok No Week 7-Sep No Wade No Wodc 4-Oct X
Totem Ekctasc 2-Aq 2-An X X X X X X X X X X
Pao Logging No Week No Wok 2-Aq No Wok No Wade No Week No Work-No Week No Wok No Wok No Wok No Week No Wok
Paget Coosbimm No Wodc Nowak No Wok No Work No Watt No Wok No Work No Week No Week No Wade Nowak No Work X
Concrete Services No Wad 2-Aq 2-Aug 2-Sep 2-Sep No Wok No Work No Work No Weak No Week No Work X -
Trmaporodon Systems 22-h8 No Wade No Wok 5-Aug 7-Sep 7-Sep No Work No Work 8-Sep 4-Oct No Work 4-06
E000po.n Snoozing No Wee No Wade No Wade No Week 12-Aag No Work No Work No wet No Wade No Wok No Wok No Wok X
Ground Up No Wok No Work No Wade Nowak Nowak 2-Sep No Work-No Wok 9-Sep No Wok No Wad Nowak No Wok
Legacy Tapping No Wok No Week No Wok No Work 5-Aug No Wade No Work No Wok No Week No Week No Wok No Week No Work
Ldreridge Paving No Week No Wok No Week No Week No Wok No Wade 7-Sep No Wok No Wads No Week No Work No Work X
Tyco Concrete X X 4-A.g No Week No Wok No Wok No Work No Wok No Wok No Wok No Wok X X
at Payment N.11(Oeede.r) Proeoo.Pay.wl No 12(Nov.mkoe) Progress P.yora.t N.13(Dec.obw)
Week S. O. &Ocl 85-0ol 22-0a 29-0et 5-Nov 12-Nov 19-N.. 26-Nov 3-Dos Nam 17-D.c 24-D.c 31-Doe
Reed reading _
W.E.Cosies X
Pao Lo88i8 X
Paget Co odd. - X -
Coaorere Services
r Systems _- X
Ever X - -
Ground Up X _ - -
Legcy Tapping X
Lakerid4e Paving X
Tyre Concrete X - - - - - -
Week Contractor/Snbcontractor is on the job site payroll required_ -'(#12)indicates payro8number"
X Subcontractor was not on-site this week "No Work Performed"payronregn<ed.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Resubrlvttal
No Work Received"No Work Performed"payroll
"Final"payroll!
17.Progress Payment—
• Progress Payment No 10 — sent to City for processing
• Progress Payment No 11 — cutoff Oct 31st for Nov 3rd submittal to
the City
18. Other Items:
Page 8 of 9
CITY OF RENTON
I + DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 -. _
WZA-Feb-May 2022 -, Wadi'
`WZB&E-Mar-Aug 22,2022 + su Eve 1_ Walt Zone o
'WZD-Sept-Nov 14.2022 4 i -
WZF(Medians)-Nov-Jan 8,202311
' I
ct:t rum III
41.00 ,
ll
Ill
LOCATION
��y DULE. III NE .i.Tr
r It ' . n 1
1111.1S111,IbM111160 t
.. TI NE 7 1
11411PAIMIN
NE e1N Sr N
l‘it z a
/kill
_i
' NElTNST t i
lirP" E.
LOCATION on
adillik .. 1,0ln,'A
r';' - . ► �
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NW TO SCALE -SCHEDULE C
City of Renton - Duvall Ave NE. CAG 20-065
- Thicker pavement in spots-$5050 ok ,
-Phil can verify extra depth
-Structure Excavation Cl. B—175 CY ok
Page 9 of 9
REEDc Date:1 O/08/22-10/28/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
September October
Sched
ID Work Description S S M T W T F M T W T F S S M T W T F Notes/Resources
8 9 10 11 12 13 14 17 18 19 20 21 22 23 24 25 26 27 28
roadwayax X X X X X
CSBC and CSTC X X X X X X X X
Illumination X X X X X .. X X X X X X X X _
Storm tasting X X
JUT proofing _ X
Flatwork and curb X X
Paving _ X X
PSE ????
Flatwork
7???
Walls
CITY OF RENTON
FIN DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
OCTOBER 4, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x
Jesse Patjens, Lumen Eric Cutshall, City of Renton
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
if?
CAG-20-065
2. Safety Report—
Traffic control issues— None
3. Prior Meeting Minutes—Comments/Acceptance —
Accepted
4. Weekly Statement for Working Days ending October 3, 2022
Days Expired: 181.5
Days Remaining: 80.5
5. Schedule Progress
Contractor's Look Ahead Schedule— Waiting on illumination. Belly in
storm crossing to be resolved. Add Fire Hydrant on Friday. Paving set
for October
PCMS Boards Required:
10 days in advance of Intersection closure for paving —start mid-
October for End of October pave
Expected materials that are coming out on-site — None
6. Utility Coordination
a. COR Water Department—
• One FH in WZD schedule- October 7th
• 3 Irrigation services to be done with WZF schedule
— Looking for Parts for WZD. Nate trying to get
ahold of Tom
• Storz Adapter status —Nothing new
b. PSE Power
•JUT and conduit install complete. Conduits need to be
proofed and mule tape installed — Reed does Proofing.
Reed will confirm PSE inspector not required during
proofing.
Page 2 of 7
CITY OF RENTON
IR DUVALL AVE NE
CAG-20-065
• PSE to hold the existing pole on west side of roadway so
Reed can finish installing sweeps up existing pole—
Dustin Weller to set up a pole hold
• PSE to install the new pole on east side of roadway so
they can finish installing conduit up the new pole. New
pole needs to be installed prior to wall installation.
• Schedule for splices and wreck-out— Dustin Weller
working on it, will give update by end of week
c. Lumen
• Existing telephone vault to be adjusted by Lumen at
WZD, Sta 919+40 RT and possible pedestal to be
relocated - Need to find out replacement for Jesse
7. RSD Elementary School 16 Coordination —
a. Schedule for elevated signal foundation in SW corner of NE
10th St— City Reviewing
b. JUT/conduit goes to existing pole location on School frontage
per Duvall Ave plan. New pole is months out
c. 2 conduit crossings at 10th, one halfway across Duvall— Ed will
provide Schedule for installation. Conduit needs to be installed
soon/prior to HMA paving.
8. Engineer's Report
a. Street light L18 potholing complete— 2.94' from top of shaft to
top of FO and Communication conduits. PMX checking to see
if a shallow footing design is possible.
b. Storm TV reveals belly to be repaired between CB 26 and CB 27
c. Curb & sidewalk at NE corner of 10th
9. Inspector's Report
MTC was out for concrete & compaction testing— October 3rd — Good
test results. Upcoming testing for Asphalt placement and concrete for
Sidewalk
Page 3 of 7
CITY OF RENTON
• 07.".: DUVALL AVE NE
CAG-20-065
10.Environmental Compliance Report— Nothing New
11. Public Outreach —
12.Submittals/Documentation
a. Review ROM — updated ROM posted to CMS.
b. Submittals under review: received glass beads submittal on CMS.
c. RAMs that need to be submitted:
• 42.05 fence-post sleeve galv pipe and non-shrink grout
• 66.02 fertilizer— need resubmittal
• 70.03/70.04/70.05 infil, nails, weed fabric for Synthetic Turf
• 71.01.01/72.02.02 primer and glue (Landscaping)
• 71.07/71.08/71.09 valve box, ball valve, and angle valve
(resubmittal)
• 71.17/72.17 Galv. Steel Pipe (Landscaping)
• 81.01/81.02/81.03 mon case/cover, bronze tack
• 8501.02 conduit sealing (S.P. 9.29.1)
• 85.08 photocell —need to see submittal. Installed on service
cabinet (not on street light poles).
• 85.12.01 pedestrian pushbutton assembly
• 85.12.02 central control unit
• 85.16 grout
• 86.02.01 2" sq. sign post/support/anchor (need
resubmittal)
• 90.02-93.02 glass beads
• 98.01 mailbox support, type 1
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — None outstanding
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
a
fe
CAG-20-065
13. RFIs—
14. FWD/ Change Orders —
• CO 20 —Tree Removal and Restoration in WZE —signed by City
• CO 21 - Storm revisions at CB 37 in the works
• CO 22 — L08 Foundation modification in the works -quote requested
• CO 23 — Eight Street Light Pole Mods in the works - quote requested.
Reed has send all info to TSI for quote; will follow up for quote.
• CO xx—Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
Page 5 of 7
CITY OF RENTON
MIRDUVALL AVE NE
CAG-20-065
16.Certified Payrolls —
Prope.o Payment No 8(ity) Progress Pavement No 9(August) Progress Paya...t No 10(September)
Woek Erin Om 9-JoI 1SJa1 21401 3011 6-A.g 1 13-A.0 20-A.0 27-.A.0 I.Sq 10-Sep 17-Sop 2-Sop 1-Oct
Reed-frackag 14.Jd 22-7.1 29-1u1 5-An 12-An 2-Sep 2-Sep 2-Sep 8-Sep 15-Sep 28-Sep 28-Sep
W.E.Coates 15-Id 22-1o1 No Work No Work No Wad No Work No Weak No Work 7-Sep No Work- X X X
,roan Electric 2-Aug 2-An X X X X - X X X X X X
d)R Logging Na Wort No Work 2-An No Wade No well No Work No Wade No Work No Work No Work No Wak' X X
Pager Coosoucmo No Wade No Walk No Wode No Work Na Work No Work No Wan No Wade No Wort No Work No Wade X X
Commie Services No wade 2-An 2-Aug 2-Sep 2-Sep No Wade No Wade No Week No Walk No Work No Week X x
Trmrporrado.Systems 22-26 No We.k No Wort 5-Ass 7-Sep 7-Sep No Wade No Work 8-Sep X X
Evergreen SarcMeg No Work No Week No Work No Week 12-And No Wart No Work No Wak No Week No Week No Work No Wok X
Cooled Up No Work No Walk No Week No Welk No Work 2-Sep No Work No Work 9-Sep No Work No Work X X
Leggy Lppog No Work No Week No Work No Work 5-A.g No Wool No Wodc No Work No Work No Wort No Work X X
LakedAe Pro* No Work No Wade No Work No Wade No Work No Wadk 7-Sep No Work No Work No Week No Work No Work X
liyee Cascara X X 4-An No Wodc No Work No Work No Work No Walk No Wed No Week No Wak X X
Week Contractor/Subcontractor is on the job site,payroll required "(#12)indicates payroll mambo'* _
X Subcontractor was not on-site this week_ "No Work Performed'payroll required
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required _
Payroll Resubmi tal
No Work Received"No Wank Perfomxd payrof
15- "Final"payroll
17.Progress Payment —
• Progress Payment No 10 —cutoff September 30 for October 5
submittal to City.
18. Other Items:
Page 6 of 7
o,,, CITY OF RENTON
ZIR_ +. DUVALL AVE NE
°� CAG-20-065
WZC-Jan-May 2022 —
WZA-Feb-May 2022
WZ8&E-Mar-Aug 22,2022 ?"-' g4f ,ID _f - w m,.0
WZD-Sept-Nov 14,2022 I g
.
WZF(Medians)-Nov-Jan 8,2023 , '
Sej . =12Tif• ill
fir PROJ
LOCATION
Latil -SCHEDULE° N ST 1
--
"Rio IP .
-11.1 16 kre s 1 AMIN 4C-Nt-
l'I 10 CUM
wTI
-vrAmik I_
V4TNST '
J—illir
` -
LOCATION a
,+ Piik. j -�t4tEG ylE A,
' I Ca '-er --,
- 'iWATER MAIN IMPROVEMENTS
htJ -SCHEDULE 6
VicINITY MAP I UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
City of Renton - Duvall Ave NE, CAG 20-065
Pa3e 7 of 7
REEDC. Date:09/24/22-10/14/22 3 Week Look-Ahead Schedule
TRUCKING&EXCAVA77NG Name: Duvall Avenue
September October
Sched
ID Work Description SSMTWT F ,5 S M T w T F S s M T w T F Notes/Resources
24 25 28 27 28 29 30 §1 2 3 4 5 6 7 8 9 10 11 12 13 14
JUT X X X X X /-
roadway ea i X X X X X "b?>
CSBC and CSTC = X X X X X ;, XXXXX X X X X X
Illumination X X X X X X X X X X X X X X X
Storm testing _ X Curb and and gutter X X
Flatwork form and grading X X X X
flatwork pour X
Walls X X X X X
CITY OF RENTON
FIN DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
September 27, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer-Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x
Jesse Patjens, Lumen Eric Cutshall, City of Renton.
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report— No issues
Traffic control issues— None
3. Prior Meeting Minutes— Comments/Acceptance —Accepted
4. Weekly Statement for Working Days ending September 26, 2022
Days Expired: 176.5
Days Remaining: 85.5
5. Schedule Progress
Contractor's Look Ahead Schedule — Finishing JUT this week, Curb on
Monday, intermittent excavation and grading. Illumination today. If
not today, can do after Curb & Gutter installation. Hot tap on 10/7 for
hydrant.
Winter is coming discuss Paving work on October 27th & 28th and
recycled CSTC — Dustin aiming for this date. Tani expressed concern of
wet weather conditions and asked Dustin if paving could be moved
forward after Curb & Gutter finished, perhaps placing at least the
base lift. Dustin will talk with pavers —may require additional mob
charge.
Notifications to Public Required:
Driveway closures and 72 hour notice— One short term driveway
closure for JUT crossing approx 916+80 RT, contractor to coordinate
directly with resident. No issue per Dustin.
PCMS Boards Required:
10 days in advance of Intersection closure - Paving
Expected materials that are coming out on-site— nothing new
6. Utility Coordination
a. COR Water Department —
Page 2 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• One FH in WZD schedule- October 7th
• 3 Irrigation services to be done with WZF, Sta and
offsets sent to Reed — done prior to paving.
Dustin will look into seeing if this work will be
done same day as FH
• Storz Adapter status — No update per Dustin, but
checking with supplier
b. PSE Power
• Status of JUT—Setting vaults now per Phil. JUT in
intersection
• Pole removal after transfer to UG system. Dustin W.
checking on crew availability. Should take approx. 2+
weeks. New pole will likely happen at same time or right
afterwards.
• Phil asked how west side pole gets conduit fed. Dustin
W. to investigate. Phil gave update on accessibility to
ex. vault on NE corner of 12th. Conduit is in.
Phil to coordinate on west side with Potelco for Splicing.
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated —Jesse painted locates, Phil needs to go by
as-builts in some spots. Treating everything as live.
• Locate status for JUT, PSE vault and street lights Per
Phil, Cannot see lumen vault on figure. Paint shows two
4-inch conduits that go down street across to west will
be in conflict with new streetlight L18 base. Has not
been potholed. Phil believes best location for new SL
would be to put at ex. power pole location.
Page 3 of 7
CITY OF RENTON
14
alft? DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination — Pole base and pole have
been submitted to RSD team for approval per Ed. Should go to City
soon.
a. Church service Pole to be shifted north about 9 feet at school
frontage schedule update Ed expressed concern about 4 ft cut
in future. Phil commented that Ed needs to have new pole
location staked. Discussion of underground conduit and
sweeping up to pole. No handhole in contract per Phil. Need
direction from SD on where new pole will go. Ed will work on
getting the City the new pole location and elevation of finished
ground (PSE will bury it deep enough). Need information ASAP
per Phil. Ed is working on it. Dustin W. will work with Ed and
Jenny.
b. Schedule for elevated signal foundation in SW corner of NE
10th St —SD getting ready to submit to City
8. Engineer's Report
a. Street light L18 potholing schedule - May require shallow
footing design.
b. Street light L08—foundation design modification sent to Reed
for a quote Dustin working on it.
c. Eight Street Light modifications — quote requested — Dustin
working on it.
9. Inspector's Report
Get MTC out for concrete & compaction testing — October 3rd
10.Environmental Compliance Report — No update.
11. Public Outreach — nothing new
12.Submittals/Documentation
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
a. Review ROM — on CMS
b. Submittals under review: none
c. RAMs that need to be submitted:
• 42.05 fence-post base grout— Need submittal for 4 in.
galvanized pipe sleeve. WD3 detail shows sleeve cast in
place with wall. If Reed wants to core drill, send RFI for
approval of construction method.
• 42.06 weep hole — Sch 40 PVC — Usable Sch 80 PVC onsite
already. No formal submittal needed.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs— none
14. FWD/ Change Orders—
• FWD 27—sent out - CB 37 Revs
• FWD 28—sent out - Foundation for L08 — quote requested
• FWD 29 —sent out - Street Light Mods — quote requested
• CO 20 —Tree Removal and Restoration in WZE — sent to City to final
• CO X — L08 Foundation modification in the works
• CO XX - Storm revisions at CB 37 in the works
• CO XXX — Eight Street Light Pole Mods in the works
• CO IV—Supplemental RPM's/Traffic Arrows — in the works
Page 5 of 7
CITY OF RENTON
• _; DUVALL AVE NE
„.., -4
4-r° CAG-20-065
15. Subcontractor Status —
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction,Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
16.Certified Payrolls —
Pr Pavnewt No S(J.ly) Preto. Pasel No 9(A.gest) Progress Pavmeet No 10(September)
Woo F.di.g O.: 9Jd 16J•s.1 21Jd 30.1tl 6-A.g 11 me
A.g 2-A.g x7-Aag 2 SR ilSop l7-Sep 24.Sep 1-Ort --
ReedTmcJmg 14-74 22-Jul 29-1d 5-Avg 12-Aog 2-Sep 2-Sep 2-Sep g-Sep 15-Sep
W E.Coates 15-14 22 W No Work No Work No Work No Work No Work No Work 7-Sep X X X
Totem Electric 2-Aog 2-Aog ® X X X X X X X X X X
PoO Logging No Work No Wodc 2-Aug _No Work No Work No Week No Work No Work X X X X
Puget Congruence No Work No Work No Work No Work No Work No Work No Work No Work No Work X X X
''.Concrete Service; No Work 2-Aug 2-Aog 2-Sep 2-Sep No Work No Work No Work X X X X
-Transportation Systems 22-Ad No Work No Week 5-Arg 7-Sep 7-Sap No Work No Work S-Sep X
Evergreen Sr000r.tg No Work No Work No Work No Work 12-Aug No Work No Work No Work No Work X X X _
Ground Up No Work No Work No Work No Work No Work 2-Sep No Work No Work 9-Sep X X X
!Legooy17ppieg No Welk No Work No Work No Week 5-Aug No Work No Rica No Walt No Work X X X
Lakeridge Paving No Work No Work No Week No Work No Wodc No Wade 7-Sep No Work No Week X X X
Tyee Concrete X X _ 4-Arg No Work No Work_No Work No Work No Work X X X X
Week Contractor/Subcontractor is on the job site,payroll required_ **( 12)indicates payroll number** '
X Subcontractor was not on-site this week. "No Work Performed"payroll required
15-Feb Date certified payroll was recieved
Corrections to payroll required j
&p _
l i Apprenticeshnp dnc'c required
Payroll ResubmittaI i f
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
Page 6 of 7
CITY OF RENTON
o .; DUVALL AVE NE
CAG-20-065
17.Progress Payment—
• Progress Payment No 10 —cutoff September 30 for October 5
submittal to City. PP No 10 may not have Sch. B items for
payment, G&O to confirm.
18. Other Items:
WZC-Jan-May 2022 I. �_
WZA-Feb-May 2022
�� _
WZ8&E-Mar-Aug 22,2022 7" +�esuv z®Lva z_I _ w—o
WZD-Sept-Nov 14,2022 z ) '� '"
WZF(Medians)-Nov-Jan S,2023 —
p -_ f-� ►IE 1Tr1t S[ 1
tT v( , %togAi
I I \i__;_,,_n....-
\•
#per P'UJECT ` �
EDE
IOCAU`ON _ INEi s- - —
l' I ki ___--J
r ... , +N_:
j
tab", 5,1 ''‘41"1.° 0
4 z NE 6T s-r .
♦ a
114001011 � a i— 7
�t I NE.THST l g
PROJE ..zr — —
LOCATION an
---) fri , J
___
___ i
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
-
Norco SCALE -SCHEDULE C
City of Renton- Duvall Ave NE, CAG 20-065
Page 7 of 7
REED c
Date:09/24/22-10/14/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
September October
Sched
ID Work Description S SMT W T F SSM T W T F SS M T W T F Notes/Resources
24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14
JUT X X X X X
roadway ex X X X X X
CSBC and CSTC X X X X X X X X X X X X X X X
Illumination X X X X X X X X X X X X X X
Storm testing X
Curb and gutter X X
Flatwork form and grading X X X X
flatwork pour X
Walls X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
September 20, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI x Dmitri Suslikov, Parametrix Inc.
Jordan Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x
Jesse Patjens, Lumen Eric Cutshall, City of Renton
x
Page 1 of 8
4 Y o CITY OF RENTON
o DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues— No safety issues today per Phil. Steel sheets are
needed for sidewalk when exposing conduit. No complaints per Dustin.
3. Prior Meeting Minutes— Comments/Acceptance —No Comments
4. Weekly Statement for Working Days ending September 19, 2022
Days Expired: 171.5
Days Remaining: 90.5
5. Schedule Progress
Contractor's Look Ahead Schedule— Concrete pour on 3rd. Paving
work on 27th & 28th
Notifications to Public Required:
Driveway closures and 72 hour notice— One short term driveway
closure for JUT crossing approx 916+80 RT, contractor to coordinate
directly with resident. There may be an additional access point for
homeowner. Reed will still need to discuss driveaway closure with
homeowner.
PCMS Boards Required:
10 days in advance of Intersection closure -
2 days in advance of driveway closure (flatwork and paving) —
Secondary access - Notify resident.
Expected materials that are coming out on-site— Cadman or Corliss
concrete for curb mix
6. Utility Coordination
a. COR Water Department—
• One FH in WZD schedule- October 7th per Dustin
Page 2 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• 3 Irrigation services to be done with WZF, Sta and
offsets sent to Reed —done prior to paving.
• Storz Adapter status —No update.
b. PSE Power
•JUT and Vault Discussion of J05 vault at intersection of
12th/Duvall. Dustin W. looking into it. Issue with where
plumbing can take place with other 6"conduits.
Currently investigating. Hope for answer this week. If
vault is too full, a second vault would be needed.
• Pole removal after transfer to UG system. Need 10 foot
offset. New pole sta. & offset to Phil.
• Power transfer Existing duct bank has 36 inches of cover
with storm conflict that results in less than ideal cover
(30 inches for 6"conduit and 32 inches for 4"conduit)
for PSE JUT. Dustin W. will discuss with his CM group.
Shallow crossing needed for JUT due to existing duct
bank crossing & storm.
• Phil asked how west side pole gets conduit fed. Dustin
W. to investigate.
c. Lumen Getting paint locates has been challenging. Locates
requested. Their facilities are not matching their drawings.
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated — locate status For PSE vaults
• Existing direct bury and 4" conduit following storm
trench Had been abandoned, but other portions may be
live. Need locate paint.
7. RSD Elementary School 16 Coordination -
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
a. Church service Pole to be shifted north at school frontage
schedule update—Add hand hole. Ed is not sure of schedule.
Waiting for PSE.
b. Schedule for elevated signal foundation in SW corner of NE
10th St—Structural is getting close to having design completed
per Ed. No date given
8. Engineer's Report
a. Street light L18 potholing schedule - May require shallow
footing design. On schedule— TSl will be onsite tomorrow. Can
Pothole tomorrow.
b. Street light L08— design modification sent to Reed for a quote
No update. Field Work Directive to follow.
c. Eight Street Light modifications - status on quote/schedule—
Poles are powder coated—question on taking bottom off. Phil
proposed to install arms lower, but then they couldn't access
photocell. Photocell on service cabinet per Eric. Cutting pole
top off to make it look consistent would be desired. Unsure if
cap will fit then. Tani will send another email describing the
request to lower arm and cut in access panel. Pole Cap
Receptacle/photo cell installed on caps per Dustin. It's not per
City standard. Dustin to check with manufacturer. Phil
suggests Zoom meeting with TSI. Tani to schedule meeting.
Bryson (TSI)joined the meeting and confirmed photocells were
being installed on the top cap. He also confirmed that
lowering the arms are preferable. Bryson to investigate the
clamp and ability to slide arm down and move photocell. Will
look at skirts. Photocells will be on service, not pole top.
9. Inspector's Report
Get MTC out for concrete & compaction testing
10.Environmental Compliance Report —
Page 4 of 8
CITY OF RENTON
Nan DUVALL AVE NE
CAG-20-065
11. Public Outreach —
• Argo Investments parcel (Albertsons) —Argo requesting info on who
maintains SW corner of ROW at Sunset/Duvall City to respond
• Hazen High School —ped detour map sent again
• Schell claim of popped tire —sent to Reed
12.Submittals/Documentation
a. Review ROM — Updated
b. Submittals under review:
c. RAMs that need to be submitted:
• 42.05 fence-post base, Drilled in after/in grout
• 42.06 weep hole—Sch 40 PVC
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders —
• FWD 27 — draft to City for storm revisions at CB 37 Send to Reed
• FWD 28—Foundation for L08 being prepared
• FWD 29 —Street Light Mods being prepared
• CO 20 —Tree Removal and Restoration in WZE —sent to Reed for sig
• CO X — L08 Foundation modification
• CO XX - Storm revisions at CB 37
• CO XXX — Eight Street Light Pole Mods
Page 5 of 8
`1Y O CITY OF RENTON
+ + DUVALL AVE NE
.4
k"-"T 0 CAG-20-065
o CO iv—Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status —
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services,Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
16.Certified Payrolls—
Program Payment No 8(Jolt') Program Yo neat No 9(August) Proprta Payment No 10(September)
Week Ending Om 9-Jul 16Ju1 23Ju1 30-Jul 6-Aug 13-Aug 20-Aap 27-Aug 3-Sep 10-Sep 17-Sep 24-Sep 1-Oot
Reed TnrcEnp 14-Jul 22-Jul 29-Jul 5-Aug 12-Aug 2-Sep 2-Sep 2-Sep 8-Sep
WE.Codes 15-Jul 22-Jul No Work No Wolk No Wak No Wort No Wak No Walt 7-Sep X
Totem Electric 2-Aug 2-Aug 2-Asp X X X X X X X X X X
PnD Logging No Work No Work 2-Aug No Wak No Wort No Wok No Watt No Walt X X
Puget Construction No Work No Work No Wok No Wok No Work No Wag No Wok No Wok No Work X
Concrete Sereiees No Wok 2-Aug 2-Aug 2-Sep 2-Sep No Wok No Work No Wait X X
Trunspatanon Systems 22-Jul No Work No Work 5-Aug 7-Sep 7-Sep No Wok No Work 8-Sep
Evergreen Smutting No Work No Work No Wak No Work 12-Aug No Work No Work No Wok No Work X
Ground Up No Work No Work No Work No Work No Work 2-Sep No Wok No Walt 9-Sep X
Legacy tipping No Work No Work No Wak No Work 5-Aug No Wok No Wek No Wak No Work X
Lakaidee Paving No Work No Work No Work No Work No Work No Work 7-Sep No Wak No Work X
Tyee Concrete X X 4-Aug No Wak No Wok No Wak No Work No Wek X X
Page 6 of 8
CITY OF RENTON
MDUVALL AVE NE
CAG-20-065
Week Contractor/Subcontractor is on the job site,payroll required_ **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment —
• Progress Payment No 9 —submitted for processing
• Progress Payment No 10 —cutoff September 30 for October 5
submittal to City.
18. Other Items:
Page 7 of 8
CITY OF RENTON
iiRDUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 — 'J -2 L*
. )
__WZA-Feb-May 2022 ++w
WZB&E-Mar-Aug 22, 2022 ?-, HEsu i�vD 4 J -__
WZD-Sept-Nov 14, 2022 r .L ���
WZF(Medians) -
-Nov-Jan 8.2023
N£12 H
Irolp P•iii8CT-
� , LOCATION �_
ti HEDULE INE57
i
,
111
^
11.1.00.
I �
4,
...r
i
N
a _.H ill
TtH
. Ay' illip 2 5
z NE 6TH ST� 4L
'a
L
z ( qa
�j _1 NEiTHSi
PROJECT r- -' I 8
{ LOCATION
} N£3 ` -$CHEDULE 11 -
4151
Int ))1 _,_ -
Fr-r- - . - -
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NUT°SCAIF -UNWIREC
City of Renton - Duvall Ave NE, GAG 20-065
Page 8 of 8
•
REEDC. Date:09/17122-10107122 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
September
Sched
ID Work Description SSMTJWT FSSM TWT FSSM T W T F Notes/Resources
17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7
JUT X X X X X X X X X X
roadway ex X X X X X X X X X X
CSBC and CSTC X X X X X X X X X X
Illumination X X X X X X X
Curb and gutter X X X X X X
Flatwork form and grading X X X
fiatwork pour X
7,
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
September 06, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener & x
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Jordan Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE Joe Nerlfi, City of Renton
Jesse Patjens, Lumen Eric Cutshall, City of Renton x
Page 1 of 7
+ +
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues — Due to enclosed gate at 12th, kids need to go to
10th to get to Albertson's per Phil. Security guard at site at lunch. School
will restrict student lunch/leave privileges if jaywalking continues.
Contractor currently working on both sides of Duvall at 12th
City forces to switch signal at Sunset back to its regular phase, what is the
schedule tentatively Thursday. Scheduled for noon. Will need barrel
assistance in through lane for controller switchover. Hour to complete
work per Eric.
3. Prior Meeting Minutes — Comments/Acceptance - minutes not sent
out yet.
4. Weekly Statement for Working Days ending September 5, 2022
Days Expired: 161.5
Days Remaining: 100.5
5. Schedule Progress
Contractor's Look Ahead Schedule —
Reed hasn't sent note to PSE yet but they should be aware. Dustin
(Reed) to email Dustin (PSE). JUT scheduled to begin on the 19th
Notifications to Public Required:
Driveway closures and 72 hour notice — One short term driveway
closure for JUT crossing approx 916+80 RT, contractor to coordinate
directly with resident.
PCMS Boards Required:
10 days in advance of Intersection closure -
2 days in advance of driveway closure (flatwork and paving) —
Page 2 of 7
%
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Expected materials that are coming out on-site — Storm and Filterra
vaults.
6. Utility Coordination
a. COR Water Department —
• One FH in WZD schedule- Dustin to follow up.
• Irrigation services in WZD and WZB schedule—
Wait on irrigation to avoid conflict in
road/planter per Dustin
• Storz Adapter status — Dustin to follow up.
b. PSE Power
• PSE work in WZD schedule is Sept 19th to start
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated — locate status locates out for storm
7. RSD Elementary School 16 Coordination -
a. Pole relocate permit at school frontage update — Phil is hoping
new pole gets installed in sequence with our project. School
Contractor will cut/remove berm which will expose the bottom
of the existing pole.
b. Schedule for elevated signal foundation in SW corner of NE
10th St — No new reports
8. Engineer's Report
a. Street light L18 potholing needed to confirm if a conflict - May
require shallow footing design.
b. City has reviewed initial concrete cost adjustment in WZB and
WZE documentation from Reed. City requested more
particulars of the increase in cost, such as different supplier,
Page 3 of 7
;FIN + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
or change in current supplier's pricing. Dustin to work on
details. Dustin to follow up on cost adjustment.
c. Street light L08 - PMX working on this for foundation
enhancement —
d. A request has been made to Reed to confirm the range in
elevation possible to lower street light arm on tapered pole —
discussed this may not be desirable to the City since access to
arm and pole cap (all equipment) is needed,just not fixture
per Eric. Other option is to cut the pole and reattach the base
plate. Welding of base plates by Garmire a possibility, per Eric
from past projects. Eric can help contact. Tani to provide pole
number and amount to cut off bottom of poles.
9. Inspector's Report Pouring Filterra vaults today. Waiting on ETA
still; but formed up/ready. Getting ready to excavate subgrade.
10.Environmental Compliance Report— Socks at 9th/10th need to be
cleaned out per Jordan. Planting plan change per Tani; reduction in
shrubs along Albertsons. Will send to Jordan.
11. Public Outreach —
• Argo Investments parcel (Albertsons) —PMX provided the landscaper
contact info. Argo has not followed up/contacted the landscaper.
• Hazen High School —ped detour map sent again
12.Submittals/Documentation
a. Review ROM — Updated and posted to CMS
b. Submittals under review: NMS 23 - FA rates resubmittal, and
DWS submittal
c. RAMs that need to be submitted:
Page 4 of 7
TI CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• weep hole,
• fence-post base
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — HMA tickets need to show Mix ID—
MD 200031 (RAM 013). ICON to confirm product 12144230 is
MD 200031.
13. RFIs—
14. FWD/ Change Orders—
• CO 17— 19 —fully executed
• CO 20—Tree Removal and Restoration in WZE — in the works with
reduced planting scheme
• CO XX—Supplemental RPM's/Traffic Arrows— in the works
15. Subcontractor Status—
Integrity Networks RTS approved.
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
Page 5 of 7
•
%
'0 + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15. Integrity Networks(Lower Tier) $22,432.15
16.Certified Payrolls —
Progress Payment No S(J.k) Progress Payment No 9(August)
Week Ending O.: 9-Jet 16-Jal 23Jd 3O-J.1 6-A.g 13-A.g 20-A.g 27-A.g 3-Sep
Reed Trading 14-Jul 22-Jd 29-Jd 5-Aug 12-Aug
W.E.Comes _ 15-Jul 22-Jul No Work No Work No Work No Work X X X
Totem Electric 2-Aug 2-Aug 2-Aagl X X X X X X
IPd)Logging No Work No Work 2-Aug No Work No Work No Work X X X
Puget Construction No Work No Work No Work No Work No Work X X X X
Concrete Services . No Work 2-Aug 2-Aug 4-Aug X X X X
Transportation Systems 22-Jul No Work No Work 5-Aug X X X
Evergreen Sawcutting No Work No Work No Work No Work 12-Aug X X X X
Grand Up _No Work No Work No Work No Work No Work X X
Legacy Tapping No Work No Work No Work No Work 5-Aug X X X X
Lakeridge Paving No Work No Work No Work No Work X X X X
Tyee Concrete X X 4-Aag No Work X X X X X
Week Contractor'Subcontractor is on the job site,payroll requreti "(#12)indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed'payroll required.
1 5-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubntittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 9 — Cutoff Aug 31 for Sept 6 submittal to
City.
• Progress Payment No 10— cutoff September 30 for October 5
submittal to City.
Page 6 of 7
(
,I,R+ CITY OF RENTON
DUVALL AVE NE
CAG-20-065
18. Other Items:
•
WZC-Jan-May 2022
1u
WZA-Feb-May 2022 T�
WZB& E-Mar-Aug 22. 2022 ' 1- AIM z i
WZD-Sept-Nov 14.2022 2'
0, 40
WZF(Medians)-Nov-Jan 8,2023 II
o
Ti9?'' .----- , rill.II - • galli.i LI
..„, .
____,I,
Kyrip . ..... lipME ,,u n ■i
t
. _, .
73 iumilgi Pd sr
,,r)
al R
\1141.110 IIIIII!, V 1Ni L. i
• ,..
i NE RH SE
PROJECT � _ _.1 g
LOCATION
1 A
.....„ \.__ICHElltILE A ' _
, SI , J Fr..--;-: 4 !
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
-
NW to unie 5CHF I)UIE(
City of Renton - Duvall Ave NE, CAG 20-065
Page 7 of 7
REEDc Date: 09/03/22 -09/23/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
September
Sched
ID Work Description SSMTWT F S S M TWTFSSM T W T F Notes / Resources
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Clear and grub X
roadway ex X X X X X X X X X
Storm X X X X X X X X
JUT X X X X X
Illumination X X X X X
.
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
AUGUST 30, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE Joe Nerlfi, City of Renton
Jesse Patjens, Lumen Eric Cutshall, City of Renton
Page 1 of 8
. 4.
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues—shift traffic over for WZD, Left Turn lane on
south leg of Sunset intersection needs to be barreled off until the City
can remove the signal modification on Sept 6th. Add one more left turn
sign on the north leg Left Turn lane. Left Turn Sign ordered and should
be received/placed today. Signing to be placed up at North end, 180
feet beyond new end of asphalt for transition. Issues brought up with
new TCP. Cones changed down at Sunset. Driving on new pavement
only; smooth transition to existing pavement. Ongoing issue with cones
keeping sidewalk closed. Need to keep cones there on Albertson's
sidewalk. Dustin will find out flume lid pouring date.
3. Prior Meeting Minutes—Comments/Acceptance - accepted
4. Weekly Statement for Working Days ending August 29, 2022
Days Expired: 157.5
Days Remaining: 104.5
Sept 5 is a non-working day due to the Labor Day holiday
5. Schedule Progress
Contractor's Look Ahead Schedule —
Grinding today & tomorrow and Clear/grub gravel in ditch. Silt fence
and Curb & Gutter installation. Filterra vaults on radar, then JUT
trench/street lighting. JUT start scheduled for 19th. Streetlight
erection soon.
REEDCK Date:o81+3r22-09ro2re2 3 Week Look-Ahead ScheduM
TAUCKW40 i V CAletT1MO Name: Owed Avenue
scow
fD Work DssCrlpdoo $. SMIWI F ;. $ M T W T F 9. * M T W T F Notes I Reston
t0 11 a 12 1$ 11 Neil 22 20 20 21 20 VW 21 20 31 1s 2
P r% X X X X CJ
satse utrres X X X X X X
bwminatwn X X X X X X
Pi.rwmeid. X X
X
Asphaltpulwmahon X X X
Cla>and grub X X
Page 2 of 8
o
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Notifications to Public Required:
Driveway closures and 72 hour notice — One driveway crossing for
JUT.
PCMS Boards Required: None needed upcoming.
10 days in advance of Intersection closure -
2 days in advance of driveway closure (flatwork and paving) —
Expected materials that are coming out on-site —
6. Utility Coordination
a. COR Water Department — Dustin waiting to hear back
• One FH in WZD schedule- Dustin to schedule
• Irrigation services in WZD and WZB schedule—
• Storz Adapter status — Nothing
b. PSE Power
• PSE work in WZD schedule — Sept 19th to start
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated — locate status Locates should be taking
place now per Dustin.
7. RSD Elementary School 16 Coordination -
a. Pole relocate permit at school frontage update — Waiting to
see if both can be done at once.
b. Schedule for signal foundation in SW corner of NE 10th St — No
updates per Michael. Will be elevated. Not too concerned
about timing.
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
8. Engineer's Report
a. Street light L18 (WZD) potholing needed to confirm if a conflict
- May require shallow footing design.
b. Dustin has sent concrete cost adjustment documentation for
City's review. Due to concrete strike. Flora has it. City would
like to know particulars of the increase in cost, such as
different supplier, or change in current supplier's pricing.
Dustin to work on details.
c. City would like to add ped curb to back of sidewalk on
remainder of sidewalk to be poured in SW corner of NE 10th
Street — Noted.
d. Street light L08 - PMX working on this for foundation
enhancement—should have design soon.
9. Inspector's Report
No issues with paving. Traffic switchover took place last
night per Phil. People are adjusting. Need centerline barrels
at WZD—striping not enough. Keep barrels in place.
Grinding started, testing scheduled for later.
Discussion on opening NB three lanes at North End. Will
eventually be done. Transition has been moved from
Starbucks to a place where there's no bump/past the grind
per Phil. Left turn pocket for NB lane not open until light
switched over.
10.Environmental Compliance Report—
Widener did not attend— no issues known.
11. Public Outreach —
• Argo Investments parcel (Albertsons) — some correspondence with
with PMX regarding plant selection — Wanted to talk with
Landscaper. Unsure of continued coordination once shrub numbers
are decreased. Issue of watering shrubs. Use City's contractor
Page 4 of 8
•
Icy
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
(GreenCity)for water bags and shrub watering, Or Widener? Ross to
water plants for 1 year
12.Submittals/Documentation
a. Review ROM — No updates
b. Submittals under review: NMS 23 - FA rates resubmittal, and
DWS submittal
c. RAMs that need to be submitted:
• need weep hole,
• fence-post base,
• detectable warning surfaces. Received this morning.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — HMA tickets need to show Mix ID —
MD 200031 (RAM 013). ICON to confirm product 12144230 is
MD 200031. Clarification email sent to Tiffani, Lakeridge Paving is
the subcontractor and ICON is the supplier.
13. RFIs—
14. FWD/ Change Orders—
FWD 26— Restoration in WZE, need a revised quote for minimized new
plants. Use ex. bid items for excavation where possible. Tani to forward
to Dustin.
• CO 17 — 19 - to City for final signature
• CO 20—Tree Removal and Restoration in WZE — in the works, hold
for revised plant quote. City Reviewed
• CO XX— Supplemental RPM's/Traffic Arrows — in the works
Page 5 of 8
CITY OF RENTON
k
DUVALL AVE NE
CAG-20-065
15. Subcontractor Status—
Integrity Networks 501 needed before they are on site. Per Dustin,
they have all their materials ready to go/contracted with Reed
directly. Dustin to submit a request to sublet.
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15.
Page 6 of 8
•
ok
„Ire
.., CITY OF RENTON
o�
DUVALL AVE NE
CAG-20-065
16.Certified Payrolls—
Program Noma No 5(APog) Progress Povmnr No•(Mar) Progress Paymear No?IJooel
Week Imam Oa: W-Apr I4,Agr 23-Apr 311-Apr 7-Nay 14-ay 21Alm 21-My 4-Jon I IJon 114Jo 25-Jo WM
RaadTrucking Ia-Apr 22Apo 25Apr 4-lay I0-Ma7 40-May 27-May 6-Jo. _-Jun Io-luo 23-Jr _ .-Jul gdd
W.F..Comes I4-Apr 22-Apr No Work a-May No Work 2.2-N o ov 31-Mov 3-J 3-Jan No Work No Work No Work a-Ird
Token Ek.No 27-Ap No Work No Wank 13-My 20.Mav 24-Mov Woo o-3® o e Io-Ja -Jol 6-Jo) 7-Jost
RID Logging 25• X X X No Work UJo. No Work No Work No Work No Wok No Wok No Woh No Work
Pugh Co•trclion No Work No Work No Work No Work No Work No Wuh 6-Jun Nowoh o-Jon No Work No Work No Work No Work
Concreln Schram 23-Apt 25-Apr 3-Nay No Work No Work No Work No Woh No Work No Wok No Woh No Work No Work No Work
Trmpean=Sykm X X 3-Nay 5-My 227-My 31-Mor 27-Mar No Work No Wok No Work No Wok 1-1u1 22-Jol
Evagreca Unrolling X X X 0.Mav No Work No Work No WA No N ork No Work No Work No Wok No Wok No Wok
Chad lip X X X A-Mav 20-Mar No Work No Work No Work No Wok No Nook No Work No Work No Wok
Lapoy Tyl®g X X X 23Apr No Work No Work No Work No N oh No Woh No Woh No Wok No Nook No Wok
LAM*Paving X X X X 24-May No Work No Work No Work No Work No Work No Work No Work No Woh
hymn Poymeoe No a(Joh) Pregrem Ply own No W(Ammo) Program Pymmel No III(Scrambler)
I Wort[Mug On: 3-3M lbJM 23Jo) - 3PJo1 6-Mg I3-Aog 211-Am 27-.Avg 3-Me NSUP 17J4p 24-UP- 1-Oa
Rood Tmaluog 14-Jo) 22-1r1 29-1111 5-,Aug 12-Aug
WE Costes 15-Ad 22J111 No Woh No Wok No Woh No Woh X
Taken Eketrie 2-Au 2-Avg Illik . X X X X X X X X X X
ND leggsg No Work No Work 2-Aug No Woh No Wok No Wok X
Pope CaaWPds No Work No Wok No Woh No Wok No Woh X X
Casmlc Scrim No Woh 2-Aug 2-Aug 4-Aug X X
Thospurtatios Systm 22-Jul No Work No Work 5-Aug X
Eherpeea Sauaasg No War[ No Work No Woh No Wok 12-Aug X X
Gems Up No Work No Wok No Woh No Woh No Work X
espy Trppsg No Wok No Work No Wok No Work 5-Aug X X
lhcidge'MSC No Woh No Work No Wok No Woh X X
The Comoro X X +.Aug No Work X X X I
Week Contractor'Subcontractor is on the job site,payroll required_ **(=12)indicates payroll number**
X Subcontractor was not on-site this week No Week Performed"payroll required.
1 5-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubrnittal
No Work Received"No Work Performed"payroll
1$-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 9 — Cutoff Aug 31 for Sept 6 submittal to
City.
18. Other Items:
Page 7 of 8
R .....
CITY OF RENTON
O DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022
WZA- Feb-May 2022 C '
WZB R E-Mar-Aug 22. 2022 NrsaksF7AIVD z z«.o �
WZD-Sept-Nov 14.2022 i 3 a " 1'
WZF(Medians)-Nov-Jan 8,2023
f .' Nf�i?71I ST L_ I l:
�l
"� r PROJECT _ !I 1
T�' LOCATION /'` ill
L: �I IC111)Ull __INC!OTI ST _ 1 .
�, MINI/ <p,, N�lTHb{�
1111111101
- a
*iormam 11
[ NE MST 01
NE.TH ST
it
PROJE IMIll.":
111
LOCATION
.. 1 T1
4
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
-NIP ioun:e SCHIDUIF C
City of Renton - Duvall Ave NE, CAG 20-065
Page 8 of 8
.
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
AUGUST 23, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X ,
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Vice X Jordan Widener, Widener & X
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix
Ins
Trucking & Excavating Inc.
Traci Brewer-Rogstad,
Renton School District
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. X
Ross Widener, Widcncr & Tom Main, City of Renton relatiran
Assoc. to Water Imp.
Ed Thompson, Representing Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE Joe Nerlfi, City of Renton
X
Jesse Patjens, Lumen Eric Cutshall, City of Renton
X
Page 1 of 7
4
Get Y o�
CITY OF RENTON
N10 DUVALL AVE NE
CAG-20-065
2. Safety Report —
Traffic control issues—
3. Prior Meeting Minutes— Comments/Acceptance -
4. Weekly Statement for Working Days ending August 22, 2022
Days Expired: 152.5
Days Remaining: 109.5
5. Schedule Progress
Contractor's Look Ahead Schedule — This week, Reed continues to
adjust castings. TSI to erect Hawk Signal.
Pole arms have not been painted yet.
Reed will be flipping traffic on Friday, by end of day. Grinder is
expected on 29th and 30t". City confirmed PCMS boards not needed
for shifting traffic.
Does anything need to happen at the Signal? Will traffic expand to 3
lanes? If possible, City would prefer use of left turn lane.
Notifications to Public Required:
Driveway closures and 72 hour notice —
PCMS Boards Required:
10 days in advance of Intersection closure - 2 PCMS boards for NE
10th Street closure/paving notification was made via PCMS boards
and then removed at completion of pave in WZE/WZB
NE 10th Street closed at 9:30 am on Wednesday 8/17/22 and then
open again by 8:30 am the following day. Overnight closure needed
to allow pavement to cure due to high ambient temperature,
2 days in advance of driveway closure (flatwork and paving) — PCMS
in place for paving delays during paving and removed at completion
of driveway pave
Page 2 of 7
c
o� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Expected materials that are coming out on-site — wire for HAWK
Signal. Will wire be energized to discourage thief?
Arms. Illumination poles will be set with one way traffic.
6. Utility Coordination
a. COR Water Department —
• FH's in WZD schedule- Meter and tap to be
installed ahead of grind/pave. Reed to provide
notice to City Water Department.
• Irrigation services in WZD and WZB schedule—
• Storz Adapter status —
b. PSE Power
• Next PSE work is WZD —tentative schedule is mid-
September 2022 -
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated - beginning September 2022
7. RSD Elementary School 16 Coordination -
a. SW curb return and pole foundation schedule, added wall?—
b. Pole relocate permit at school frontage update —
8. Engineer's Report
a. Street light L18 (WZD) potholing needed to confirm if a conflict
b. Dustin has sent concrete cost adjustment documentation for
City's review.
c. Coordinate with school contractor regarding retaining wall to
be added at SW corner of NE 10th Street
Page 3 of 7
+ CITY OF RENTON
DUVALL AVE NE
CAG-20-065
9. Inspector's Report
a. Phil will be on vacation 8/15 to 8/29. Joe Nerlfi, City of Renton,
to provide inspection. Joe — crews are raising castings, TSI is
working on crosswalk lighting. Roadway, paved last week, rides
fantastic.
10.Environmental Compliance Report—
At 10th and 9th, on the east side of the roadway, the socks are full and need
to be emptied. In areas that have been stabilized, i.e. curb/gutter and
sidewalk has been installed, the silt fence can be removed
11. Public Outreach —
• Argo Investments parcel (Albertsons) — some correspondence with
with PMX regarding plant selection — PMX will provide formal
response.
12.Submittals/Documentation
a. Review ROM —
b. Submittals under review: FA rates resubmittal. Has been
returned to Reed.
c. RAMs that need to be submitted: need weep hole, fence-post
base, detectable warning surfaces. G&O to follow up with email
request.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — HMA tickets need to show Mix ID —
MD 200031 (RAM 013). ICON to confirm product 12144230 is
MD 200031.
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
13. RFIs—
14. FWD/Change Orders—
FWD 26— Restoration in WZE, need a quote for new plants and water
bags
• CO 17 — 19 - to City for final signature
• CO 20—Tree Removal and Restoration in WZE — in the works, hold
for plant quote.
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status—all SOI's are received.
Will Integrity Networks become a lower tier sub to TSI? Integrity
Networks will be subcontractor to Reed—paperwork need to be
submitted.
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15.
Page 5 of 7
G�j Y O�
+ CITY OF RENTON
TO DUVALL AVE NE
CAG-20-065
16.Certified Payrolls — updated status shared at meeting
PrFaso P9rr No 5(A.I) Pruipern Pom o..No 6(Mgl Program Pa,mewl No 7(Jar)
Work toig Om }Apr 16-Apr 23-APr JS.Aor 7-May 16May 21-May 2$-May a.J.a I14u lNu 121410. 244
Rood Trucking 18-Ap 22-Apr 21-Apr 4-May I6-May 20-May 27-Mar 64aa 7-Jon Whin 23-Jon IJd 54o)
W E.('oaten 14-Apr 22-Apr No Work 6-May No Work 24-Mao 31-Mar ]-Join R-Jm No Work No Work No Work k-Jo)
To1cm Ekrtric 25- 27-AprNo Work No Work Il-May 220-Mao 24-May l.hu o-Jon 16J." o-Jul 6-Jul '-1ul
PeD Logging ,5 X X X No Work 13-Jes No Work No Work No%Ark No Work No Work No Work No Work
Puke Costruceon No Wok No Work No Work No Work No Work No Work .Jon No Work o-Jo. No Work No Nork No Work No Wark
C.arur000 Semen 25-Apr 25-Apr J-May No Work No Work No Work No Work No Work No Work No Work No Work No Work No Work
Tranrporump Nook-no X X 3-May 5-May 127-May 31-May 2'-Mar No Work No Work No Work No Work 1-Jul 22-Jol
Eroryscn Sawcnpiog X X X e-May No Work No Work No Work No Work No Work No Work No Work No Work No Work
Cowed Up X - X X 4-May 20-May No Work No Work No Work No Work No Work No Work No Work No Work
Lcgooy reopen X X X 20-Ap No Work No Work No Work No Work No Work No Work No Work No work No Work
Lakendge Paring X X X X 24-May No Work No Work No Work No Work No Work No Work No N ork No Work
Program Payret No (J ) Prove.Pryor.No•(Amgorl Progreso Popmat No l0 INapr..barl
Wrak[oig OW: a-JOI 164a1 13-11 3114r 11-A01 11-Sog 26.keg 27-Aq 3-Soo I-Sap 17410p 26Nop I-4ler
Rood Trackrog 14-Jul 22-MI 20-J) 5-Aog 12-AK
W E.Coates I5-Jul 22-1n1 No Work No Work No Work No Work N
Token Electric 2-Aug 2-Aug 3•AR/ X X X X X X X X X X
POD logging No Work No Work 2-Aug No Work No Work No Work X
Pugcr Camuactm No Wyk No Work No Work No N'ork No Work X X
Cmcrcrc Snrittr No Wyk 2-Aug 2-Aog 4-Aug X X
Trwgyratmo Syslcna 22-Jol No Work No Work 3-Aug X
Ercrgrtee Saocaaing No Work No Work No Work No Work 12..Mg X X
Cunard Up No Nark No Wyk No Work No Work No Work X
Lcgacr Tapprog _... No N ork No Work No Wyk No Work 5-Aug X X
I akeridpe Paring No Work No Wart Na Work No Work X X
T7eo Commie X X 4-Aog No Work X X X f
Week Contractor Subcontractor is on the job site.payroll required. **( 12)indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed"payroll required
15-Feb Date certified payroll was recieved
•
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 9 — Cutoff Aug 31 for Sept 6 submittal to
City.
18. Other Items:
Bob requested G&O review the CM, may not allow retaining paper copy
or electronic copies of payroll and prohibits nonpayment due to missing
payrolls. G&O will review. May need to remove payrolls from CMS.
Need to coordinate with WSDOT Emergency Repair project? Might not
be in the vicinity.
Page 6of7
111 Izy
I, CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 _�
WZA- Feb May 2022 *Mk
WZB& E-Mar-Aug 22. 2022 �--'' Sue i I _ waam.0
WZD-Sept-Nov 14. 2022 Z' -'`'
n i 11
WZF(Medians)-Nov-Jan 8.2023 —
111
'�' 1- P'a lib - T H
II
.4
NJ .5
UpqLOCAION
� J lri
gm m hi NM
lk \ lir
4 N: Sr
�► ■
1 � I we GM
71104_
r
I ,. I NE ITII ST
PROJECT z
LOCATION \lialfai
d1 -SCHEDULE A _
'Cr'
•
f : -4 ---, 1
WATER MAIN IMPROVEMENTS
N -SCHEDULER
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT IC)VALE -SCHI DUIE(:
City of Renton - Duvall Ave NE. CAG 20-065
Page 7 of 7
r''(Y O
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
AUGUST 16, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x Joe Nerlfi, City of Renton x
Jesse Patjens, Lumen
Page 1 of 7
+ CITY OF RENTON
r0 DUVALL AVE NE
CAG-20-065
2. Safety Report —
Traffic control issues — none
3. Prior Meeting Minutes— Comments/Acceptance -accepted
4. Weekly Statement for Working Days ending August 15, 2022
Days Expired: 147.5
Days Remaining: 114.5
5. Schedule Progress
Contractor's Look Ahead Schedule — see attached
Notifications to Public Required:
Driveway closures and 72 hour notice — notifications made for
paving work
NE 10th Street intersection closures per TCP:
PCMS Boards Required:
10 days in advance of Intersection closure - 2 PCMS boards for NE
10th Street closure/paving notification — done
2 days in advance of driveway closure (flatwork and paving) — PCMS
in place for paving delays
Expected materials that are coming out on-site — HMA mix
6. Utility Coordination
a. COR Water Department —
• FH's in WZD - not scheduled yet
• Irrigation services in WZD and WZB — not
scheduled yet
• Storz Adapter status —nothing new
Page 2 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. PSE Power
• Next PSE work is WZD — tentative schedule is mid-
September 2022 - Dustin Weller to look at discrepancy
between school plans and City road plans regarding
pole
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated - beginning September 2022
7. RSD Elementary School 16 Coordination -
a. NW Curb return on NE 10th Street status - complete
b. SW curb return and pole foundation — Reed to check on
schedule
c. Pole relocate permit at school frontage update — may move
pole about 10 feet north
8. Engineer's Report
a. Street light L18 (WZD) potholing needed to confirm if a conflict
b. 3 EA Filterra Units re-plumbing status — they will arrive this
week
c. Paving limits in planter areas — see plans
d. Dustin has sent concrete cost adjustment documentation for
City's review.
9. Inspector's Report
a. Phil will be on vacation 8/15 to 8/29. Joe Nerifi, City of Renton,
to provide inspection.
Page 3 of 7
G O�
CITY OF RENTON
t° DUVALL AVE NE
CAG-20-065
b. MTC to take HMA compaction tests on 8/15/22, 8/16 and
8/17
c. MTC to take 2 HMA mix samples
d. MTC to take 1 HMA aggregate sample
10.Environmental Compliance Report — no report
11. Public Outreach —
• Argo Investments parcel (Albertsons) — some correspondence with
with PMX regarding plant selection - nothing new
12.5ubmittals/Documentation
a. Review ROM — updated on CMS
b. Submittals under review: none
c. RAMs that need to be submitted: need weep hole, fence-post
base, detectable warning surfaces.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — G&O to confirm Certs. for Filterra
vaults have been received,from original delivery.
13. RFIs —
14. FWD/ Change Orders —
FWD 26 — Restoration in WZE, need a quote for new plants and water
bags, PMX researching Contractor ?s on type of tree answered
questions, Contractor has received quote
• CO 17 —to City for final signature
Page 4 of 7
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 18—sent again to Reed with updated description
• CO 19- Wall Revisions in WZB and WZD—to City for final signature
• CO 20—Tree Removal and Restoration in WZE — in the works, hold
for plant quote.
• CO XX—Supplemental RPM's/Traffic Arrows— in the works
15. Subcontractor Status— all SOI's are received.
Will Integrity Networks become a lower tier sub to TSI?
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15.
16.Certified Payrolls— need some no work performed payrolls from Pnd
and WE coates
Page 5 of 7
o,..
+
11) CITY OF RENTON
1)4'NT°x.,, DUVALL AVE NE
CAG-20-065
Proves Payment No 5(ARM/ Progress Payment No 6(May) Pretreat payment No 7(June/
Week Seeleeq: 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 28-May Nu 11Jue 18-Jun 25-Jun 2-Jul
Racd Tucking 18-Apr 22-Apr 28-Apr 4-May , IS-May 20-May 27-May 6-Jun 7-Jun IS-Jtm 23-Joy - 1-Jul 8-Jul
W.E.Coates 14-Apr 22-Apr No Work 6-May No Work 24-May 31-May 3-Jun 8-Jun No Work No Work X 8-Jul
Totem Electric 25- 27-Apr No Work No Work I3•May 20-May 24-May 6-Jun 6-Jun 16-tun 6-Jul 6-Jul ]-Jul
PnD Logging A X X X No Work 13-Jun No Work No Work No Work X X X X
Puget Construction No Work No Work No Work No Work No Work No Work 6-Joy No Work 6-Jun No Work No Work No Work No Work
Concrete Services 25-Apr 25-Apr 3-May No Work No Work No Work No Work No Work No Work No Work No Work No Work No Work
Transportation Systems X X 3-May 5-May 27-May 31-May 27-May No Work No Work No Work No Work 1-All 11-Jul
Evergreen Sawcretiog X X X 9-May No Work No Work No Work No Work No Work No Work No Work No Work No Work
Grand Up X X X 4-May 20-May No Work No Work No Work No Work No Work No Work No Work No Work
Legacy Tapping X X X 29-Apr No Work No Work No Work No Work No Work No Work No Work No Work No Work
Lakeridge Paving X X X X 24-May No Work No Work No Work No Work No Wort No Work No Work No Work
_ ProgressPosttest No 8(J ) Progress Payment No 9(Am) Proms.Parana No 10(September)
Week Eedtop Oa: 9J.1 16Ju1 23Ju1 38J.1 6-Aug I3-Aug 20-Ana 27-A.. 3-Sett 10-Sert 17-Sep 24Sep l-Oet
Reed Tucking 14-Jul 22-Jul 29-Jul 5-Aug
W.E.Coates 15-Jul X No Work No Work X X
Totem Elechic 2-Aug ' 2-Aug U'_ X X X X X X X X X X
PoD Logging X _ X 2-Aug X X X
Puget Construction No Work No Work No Work No Work X X
Concrete Services No Work 2-Aug 2-Art 4-Aug X
Transportation Systems 22-Jul No Work No Work 5-Aug__ _ X -
Evergreen Sawcmriog No Work No Work No Work No Work X
Ground Up No Work No Work No Work No Work X X
Legacy Tapping No Work No Work No Work No Work 5-Aug X
L.akeridge Paving No Work No Work No Work No Work X X
Tyre Concrete X X 4-Aug No Work X X
Week Contractor Subcontractor is on the job site,payroll required- "(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required-
15-Feb Date certified payroll was reciet-ed
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Rork Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 9 — Cutoff Aug 31 for Sept 6 submittal to
City.
18. Other Items: Tani out of office this Friday, she will send contact info for
Brian Sourwine and Michael Ballard
Page 6 of 7
•
'y +
''' CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 lJ ti <
( iwmkmrE
WZA-Feb-May 2022 „�„�,
WZB& E-Mar-Aug 22. 2022 2-, su&�fa(va zl I
WZD-Sept-Nov 14.2022 o 1.'f
WZF(Medians)-Nov-Jan 8,2023
I
r N 1ITH 9E
+�° L ' PRIME 1 I 5-1
TT tip LOCATION ���
$CEIEDULE A. L 3L�11 ],
1 IIIII il A_
4,immirsi i ,! v.
1. 1
,,,.
iew < :',,,:tiro!,
: ,_ I L ODA' nc
I——
PKen+sr N
i-do
r ► 1 a
r�411151.
rH$T g
PRb1EC7 "� _1
Wilipcil LOCATION-I
latE
.2!„, \Ma
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NO!inuaie -SIRE DUI E C
City of Renton - Duvall Ave NE. CAG 20-065
Page 7 of 7
FIEEDc Date:08/13/22 -09/02/22 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
August
Sched
ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes / Resources
13 14_ 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2
Paving X X X X
Raise utilities X X X X X X
Illumination X X X X X X
Pour flume lids X X _
switch WKZ X
Asphalt pulverization X X X
Clear and grub X X
• 1�'s
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
AUGUST 09, 2022
Comments made during the Meeting are shown in italics.
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Vice X Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. X
Trucking & Excavating Inc.
Traci Brewer Rogstad,
Renton School District
Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing X Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE X Eric Cutshall, City of Renton
X
Jesse Patjens, Lumen
Page 1 of 9
MIRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues—sidewalk closure at NE 10th sign (NW corner),
pedestrian sign needs to be swapped for sidewalk closed sign. Hawk
signal is out, due to the School Contractor's work.
3. Prior Meeting Minutes—Comments/Acceptance— no
comments/accepted
4. Weekly Statement for Working Days ending August 8, 2022
Days Expired: 142.5
Days Remaining: 119.5
5. Schedule Progress
Contractor's Look Ahead Schedule— heading towards pave
date...grading 10th intersection today;prepping for paving rest of
week. Paving following week. TS!finishing up walls. Getting poles
erected w/HAWK signals erected quickly, then jump to east side.
August
Work Description MSMTWT F d$ $' M T W T F .., Ig M T W T F
st 3 8 9 10 11 12 P; 15 16 17 16 19 4110plf 22 23 24 25 26
Grade 10th interseabn
CSTC X X X X X X
pour wall X X X
pour wall X X
form and pour Mena flumes X
Flaming X
Pawn{ X X X X X
Haminauon X X X X X
Plane uolrties X X X X X
Cleanup X X X X X
Notifications to Public Required:
Driveway closures and 72 hour notice — Coordination with
businesses for paving work - Tough during paving operation to fully
maintain. 8 inches in 3 lifts, so transition is challenging. Paid for
under HMA. Phil talked to Albertson's manager...told him look ahead
schedule. He can get nighttime deliveries. Won't need to worry about
deliveries during day. But need to put back asphalt wedges as lifts are
installed. PCMS board notification (see below).
Page 2 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
NE 10th Street intersection closures: TCP approved— Dustin would
love to close throughout until paving but must keep open for fire and
emergency access.
PCMS Boards Required:
10 days in advance of Intersection closure - 2 PCMS boards for NE
10th Street closure and leave on site for paving notification —
2 days in advance of driveway closure (flatwork and paving) — PCMS
in place "Paving 8/15 to 8/17-Expect delays/Dway closures during
paving."Hoping for 3 days of paving —8/15 to 8/17.
Expected materials that are coming out on-site — Asphalt
6. Utility Coordination
a. COR Water Department —
• FH's in WZD -not started
• FH at NE 10th — completed, thrust block to be
poured complete, waiting for test results
• Irrigation services in WZD and WZB —
• Storz Adapter status no feedback yet
b. PSE Power
• Next PSE work is WZD —tentative schedule is mid-
September 2022 - timing works for both Dustins.
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated - beginning September 2022 Lumen did
not attend.
Page 3 of 9
ill? CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination -
a. NW Curb return on NE 10th Street—schedule for school's HMA
patch along gutter, looks like the patch needs to be widened
Ed— 10th the NW corner curb...will be poured back on Thursday
but picture below...not enough asphalt removed to reinstall
asphalt....will school be able to remove and install. Ed— that
curb has been torn out and will repave.
Phil—met with Jerry today and discussed sawcut sliver that can
be patched back. Reed will backfill trench today so curb
forming/pouring can take place, on Thursday.
Phil to tell Reed to pull rest of pavement at 10th pavement
approach out. Discussed no additional trench crossing will be
required by School District since water crossing and conduit
have been installed.
Bob —in future, if patch against curb...doesn't want to do 2 foot
removal/patch — the smaller the patch the better and tamp it
first then vibratory compactor in for City projects
Page 4 of 9
RCITY OF RENTON
DUVALL AVE NE
CAG-20-065
' r
VIIIIII
.7.7ii*S-2:-- — ' 0 - am—go Attim
I
sx mot '
, x 4
s r: tea, "' �...
ri ; `
six i r M �4. : ,
r
w /
Or
a`
b. Pole relocate permit at school frontage? Ed—both reps for PSE
relocation and CED's relocation...trying to coordinate. Unsure if
coordination can happen at same time.
8. Engineer's Report
a. Street light L18 (WZD) potholing needed to confirm if a conflict
- noted. May need shallow foundation design, stay tuned.
b. Discuss paving limit at centerline, consider shifting west 6-
inches to give some distance from the vertical cut in lowered
area —Phil did measurements...from 12' to 320 feet south of
12`h where removal didn't get removed quite far enough.
Dustin —can be fixed but it is crunch time with schedule.
Bob/Parametrix agree that paved CL/joint is okay to adjust
approx. 6 inches west. Just keep joint out of wheel tracks.
c. 3 EA Filterra Units re-plumbing status —Dustin —no new
news...will ask again.
Page 5 of 9
') CITY OF RENTON
DUVALL AVE NE
CAG-20-065
d. Street light arms — Dustin - located caps. Arms are in transit
to Tacoma Electric then sent to TSI. Focus on WZD and E and
HAWK signal then shift/deal with WZC.
9. Inspector's Report
a. MTC to take compaction tests on CSTC 8/9/22 — went well.
Waiting for cylinder breaks. Bob asked about hot weather
procedures — Reed noted concrete has not been placed in
hot weather. Phil noted base has been watered with water
truck prior to concrete placement.
10.Environmental Compliance Report— No update. Widener did not
attend.
11. Public Outreach —
• Argo Investments parcel (Albertsons) — some correspondence with
with PMX regarding plant selection - Outreach to Dylan Bailey. Dylan
out this week.
Bob —left turn signs—said his supervisor are confused. Bob
disagreed.
• HOA irrigation was fixed.
12.Submittals/Documentation
a. Review ROM — no updates;
b. Submittals under review:
c. RAMs that need to be submitted: with wall on look-ahead...need
weep hole and fence-post base. May need submittals soon. 42.05
and 42.06 in ROM. Also detectable warning surfaces.
Page 6 of 9
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
d. Non-Material Submittals that need to be submitted: NMS 021 for
FA rates has been returned to Reed.
e. Material Documentation —
13. RFIs— nothing new
14. FWD/ Change Orders—
FWD 26— Restoration in WZE, need a quote for new plants and water
bags
• CO 17—to City for final signature
• CO 18— will update/expand the description.
• CO 19- Wall Revisions in WZB and WZD—in the works
• CO 20— Tree Removal and Restoration in WZE—in the works, hold for
plant quote. Planting plan was sent to property manager
• CO XX—Supplemental RPM's/Traffic Arrows— in the works
15. Subcontractor Status— all SOI's are received. Tyee approved as a
sub, need business license.
Will Integrity Networks become a lower tier sub to TSI?
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
Page 7 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
14. Tyee Concrete Construction, Inc. $15,000.00
15.
16.Certified Payrolls —
Prowess PaymeatNo5(Awl) Prowess Payment No 6(May) Progress Parasol No 7(J..e)
Wank Erin'One P-Apr 16-Apr 23.Apr 36-Apr 7-Mery 14-May 21-May 26-May Edo. 11Ja 15]r 25Js 2Jd
Reed Trmkrg 11-Apr 22-Apr 28-Apr 4-Mq 16-May 20-May 27-May 6-1m 7-1ne 16-1s 23-1m 1-1d 2-1d
WE Cores 14-Apr 22-Apr No Wads 6-May No Work24-Mq 31-May 3-1a. e-1a No Work No Work X 8-1d
Pkya Totem ic 25- 27-Apr No Work No Work 13-May 20-May 24-May 6-Ion 6-ke 16-lea 6-1d 6-201 7-1d
P.D Log X X X No Week 13-J.. No Work No Work No.Week X X X X
Puget Commetion No Work No Work NOVert No Work No Week No Work 6-1m No Work 6Jm No Wade No Work No Work No Work
Concrete Services 2S-Apr 25-Apr 3-k No Week No Work No Work No Wodk No Work No Work No Work No Work No Week No Work
Iron scion Systems X X 3-P 5-May 27-Moo 31-Mow 27-May No Work No Work No Work No Work 1-101 22-Jr
Evergreen Samoa* X X X 9-May No Work No Week No Woe No Work No Work No Work No Work No Work No Work
G.mdUp X X X 4-May 20-May No Work No Work No Work No Work No Week No Work No Work No Work
Lepaey Tappeg X X X 29-Apr No Work No Work No Work No Work No Week No Work No Work No Work No Work
Lakeridge Paring X X X X 24-May No Work No Work No Work No Work No Work No Wodk No Work No Work
!swam Payment No S(Jay) Prowess Payment No 9(Amor) Progress Palest No 10(September)
Weak Paling O.: PAM 164.1 23Jrd 34Jd 6-A.g 13_lag 241-Ang 27-A.g 3-Sep Mess 17-Sop 24-Sep 1-0r1
Reed Track* 14-1d 22-1d 29-1d
WX.Cores 15-11 X No Work No Work X
Totem Bennie 2-Aug 2-Aug 2-Avg X X X X X X X X X X
PoD Logging X X 2-Aug X X
Paget Construction No Week No Work No Work No Work X
Concrete Services No Work 2-A.g 2-Aug 4-Aug
TraosporM.on Symms 22-101 No Work X
Eaergem Sawant g No Work No Work No Work No Wee_ X
Good Up No Work No Work No Work No Work X
Lcpcy Tappig No Work No Work No Work X _
(lakeridge Paring No Work No Work No Work No Work X
•
Week ContractorSubcontractor is on the job site:payroll required- **(712)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
_.,.> Apprenticeship doe's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17.Progress Payment—
Page 8 of 9
0se n�
R + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Progress Payment No 8 — sent to the City for processing.
• Progress Payment No 9— Cutoff Aug 31 for Sept 6 submittal to City.
18. Other Items: Dustin has concrete cost adjustment documentation
ready. Dustin will send via email for City's review.
Phil will be on vacation 8/15 to 8/29. Joe Nerlfi, City of Renton, to provide
inspection.
WZC-Jan-May 2022 �.
WZA-Feb-May 2022 mrH •
WZB& E-Mar-Aug 22.2022 )"' iii' • am A__I
WZD-Sept-Nov 14. 2022 Z f
40 irr
WZF(Medians)-Nov-Jan 8,2023 r
( t 4 72.11i 9r 1
wesc
PILECP
LOCATION~r * ST 1L
"1% , Nr, 1 Work Zone C
.... L Nfj n-H t1.. .'
_ on-6TH ST M
)40'
NE 41M ST g
: A �eaE z
LOCATION
.....„ ,,_„:„.,
. -}-, .. , Ftl I i
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT iouat -soft DUI1 C.
City of Renton - Duvall Ave NE. CAG 20-065
Page 9 of 9
FEEDc Date:08/06/22 -08/26/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
�wIW.t-Ci.II GNw-IYM wws-Ifs
July August
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Grade 10th intersection X X X X X
CSTC X X X X X X
pour walls X X X
pour walls X X
form and pour Filterra flumes X
Plaining X
Paving X X X X X
Illumination X X X X X
Raise utilities X X X X X
Cleanup X X X X X
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
AUGUST 02, 2022
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc. x
Ross WWidener,CI�T;dener& Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x Dennis Booth, PSE
Jesse Patjens, Lumen Eric Cutshall, City of Renton
Page 1 of 7
� + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report —
Traffic control issues - None
3. Prior Meeting Minutes— Comments/Acceptance — Accepted
4. Weekly Statement for Working Days ending August 1, 2022
Days Expired: 137.5
Days Remaining: 124.5
5. Schedule Progress
Contractor's Look Ahead Schedule —see the attachment
Notifications to Public Required:
Driveway closures and 72 hour notice —
NE 10th Street intersection closures: TCP approved
PCMS Boards Required:
10 days in advance of Intersection closure - 2 PCMS boards for NE
10th Street
2 days in advance of driveway closure (flatwork and paving) -
Expected materials that are coming out on-site — Asphalt
6. Utility Coordination
a. COR Water Department—
• FH's in WZD
• FH at NE 10th — 8/3/22 Dustin asked if an Eco-block
could be used for the hydrant, and no thrust block
at tap. G&O to confirm with City Water
department.
• Irrigation services in WZD and WZB
Page 2 of 7
0,
IRi + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. PSE Power
• Next PSE work is WZD — tentative schedule is mid-
September 2022
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT and possible pedestal to
be relocated - beginning September 2022
7. RSD Elementary School 16 Coordination -
a. Curb and gutter return on NE 10th Street prior to paving 8/15-
8/19 Ped base at NW corner
b. Conduit to be buried below sidewalk on SW corner of NE 10th
Street, Reed to blank out sidewalk for now. Working on it
c. Conduit to go in FH stub crossing on NE 10th Street— submittal
review is OK for conduit
d. Pole relocate at school frontage? Applied for permit-Should
receive comments from PSE within a day or two.
e. Water tie-in backfilled
8. Engineer's Report
a. Street light L18 (WZD) potholing needed to confirm if a conflict
b. Revisions sent out to FH flange height and FH pad at NE 10th
Street. The FH pad is on a slope to match the future curb
ramp ped curb.
9. Inspector's Report
a. MTC to get Cadman CI 4000 Issaquah Plant mix aggregate
samples for sidewalk pours and take cylinders, slump and
air on 8/2/22 - Fine on testing. Took cylinders
Page 3 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. MTC to take compaction tests on CSTC— after SW pours
10.Environmental Compliance Report—
Ross not present
11. Public Outreach —
• Argo Investments parcel (Albertsons) —G&O sent them restoration
plan. They asked for status of irrigation system. G&O to let them
know that City will maintain for 1 year
• South of 8th Homeowners association — irrigation repair status —
Repaired last Friday. Phil asked HOA to notify him of any issues; Phil
anticipates HOA will reach out to confirm repair was successful.
12.Submittals/Documentation
a. Review ROM — Same as last week
b. Submittals under review: equipment rates, requested added info
from Reed.
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
Page 4 of 7
RCITY OF RENTON
DUVALL AVE NE
CAG-20-065
13. RFIs—
14. FWD/ Change Orders—
FWD 26— Restoration in WZE, i' the works- sent out today, need a
quote for trees and plants
• CO 13 — CO 18 to City for final signature
• CO 19- Tree Removal and Restoration in WZE — in the works
• CO 20—Wall Revisions in WZB and WZD —City is reviewing a quote
from Reed for expansion joints
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status— all SOI's are received. Will Integrity Networks
become a lower tier sub to TSI?
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
Page 5 of 7
me-
` Ill oe
CITY OF RENTON
-pFNT°NI' DUVALL AVE NE
CAG-20-065
16.Certified Payrolls —
Proper Pemymrt No 5(Aped) Peeress Payment No 6(May) Peeper Poymeel No 7(Jr)
Weeki6ke0= 9.b 16-As 23-Ap 30-Aar_7-Moy 14-May 21-My 2S-May 4-J 11-Jon 1$Jm 254. lid
Reed Tracking 18-Apr 22-hp 28-Apr 4-May 16-May 220-May 27-May 6-1r 7-1a 16-Jr 23-Ian l-Jd 8-Ai
WE.Comes 14-Am 22-Aga Nowak 6-Mey No Work 24-May 31-May 3-Jot 8-Jae No Work No Week X 8-161
Tom Electric 21A- 27-Apr No Work No Work 13-May XI-May-May24-May 6-bin 6-he16-1en 6-I d 6-1d 7-hd
PDD LoggingLoggingX X X No Work II-Im No Wodc No Week No Week X X X X
Paget Commsrrim No Work No Weds No Work No Wark No Work No Work 6-he No Work 6-1m No Work No Wads No Work No Work
Concrete Services 25-Ape 25-Age 3-My No Work No Work No Week No Work No Work No Welk No Work No Wwk No Work No Wade
Inespaeroo Symms X X 3-My 5-18p 27-May 31-1149 27-My No Work No Work No Wadc No Work 1-1 al 22-Id
Evergreen Sawcnmeg X X X 9-My No Work No Wok No Wodc No Week No Work No Work No Wodc No Wade No Week
Groan!Up X X X 4-My 20-My No Work No Walk No Work No Work No Work No Wade No Work No Work
Leper Typig X X X 29-Age No Work No Work No Work No Work No Week No Walk No Work No Work No Work
Ldcmkye Paving X X X X 24-My No Work No Woe No Work No Work No W-ortc,No Work No Week No Work
Pregame Payment Ne I(My) Proper Payment No 9(Airport) Progress Payment No 10(September)
Week Lae 4 o fad I64d 2344 30Jd 6-Aft 13-Aag 26-Aaa 27-Aeg 3-Se 10-Sep 1'-sop 24-Sep 1-On
Reed Tncddag 14-11 22-h6 -_
WE.Coreo 15-Id X X X _
Craws Meet x
AD Loup' X X X _
Paged Comm err No Week x X X
Concrete Services X _
''.Trrywlroe Spew 22-1d No Week X _.._
Evergreen Sreman rg No Work X X X
'Goad Up No Week X X X
ILepcy Top X X X X _ _ _--
Lakesidge Paiq No Work X X X
Week ContractorSubcontractor is on the job site,payroll required- **(=12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
1 S-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubnvttal
No Work Received"No Work Performed"payrol
15-Feb "Final"payroll
17.Progress Payment—
• Progress Payment No 8 — Draft sent to Reed. Documentation
needed by the City on August 4, 2022
18. Other Items:
Planing/Paving to occur with paving if possible. Planing sub could be
onsite this week. Dustin to determine if it feasible. May require
additional maintenance which may not be desirable to Reed.
Page 6 of 7
G\t Y O��+
CITY OF RENTON
�F"7°‘1. DUVALL AVE NE
CAG-20-065
a
WZA -Jan May 2022 \ l-
WZA Feb May2022 eVIVIF
)-s - (i°N5E7%VD ` I At ini
WZBBE-Mar-Aug22.2022 Z
WZD Sept Nov 14,2022 ' i /T
WZF(Medians)-Nov-Jan S,2023
tel!
I.
�° P•.1E VIa --
7A1,4 LOCATION ti
lik rr ��i�._MFj liH;rrilliddlill - _ 22411.11)
g,
NE OH ST
1 �• I
r t
� NE
� g
•
PROJE � Z
. A
Liar ttl_i_i%
LOCATION mil
'Nli'll-11.11111111' I
:1') as , 4 . , .-
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT in ti,ATI -SCHEDULE C
City of Renton - Duvall Ave NE, CAG 20-065
Page 7 of 7
REEDC. Date: 07/30/22-08/19/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVA77N6 Name: Duvall Avenue
9wwlNw Iw dull GwwrwNww YwN 1994
August
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources
30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Sidewalk prep X
Pour flat work X
Cstc X X X X X
Hydrant on 10th X X
plaining X
Grade 10th intersection X X X X X X X X
pour walls X X X X X
form and pour Filterra flumes X X X X X
Paving X X X X X
iIR
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
J U LY 26, 2022
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton
Renton
Bryson, TSI Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & x Tom Main, City of Rcnton relating
Assoc.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x Dennis Booth, PSE
Jesse Patjens, Lumen Eric Cutshall, City of Renton
Dylan Bailey, Parametrix Inc. x
Page 1 of 9
Y o
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report—
Traffic control issues - Place cones by gaps in sidewalk per Phil
3. Prior Meeting Minutes— Comments/Acceptance — one comment
received regarding attendance list, Traci and Ross did not attend the
meeting.
4. Weekly Statement for Working Days ending July 25, 2022
Days Expired: 132.5
Days Remaining: 129.5
5. Schedule Progress
Contractor's Look Ahead Schedule — Previous schedule from last
week:
REED C 3 Week L
Date:07/76/22-00lOS122
TRUCKING&EXCAVATING Name: Duvall Avenue
r.., ......(*.war„n.nw July August
Scher
ID Work Description S S M T W T F SS M T W T F SS M I W T F
15 17 18 19 20 21 22 22 24 25 26 21 25 29 20 31 1 2 9 4 5
Sidewalk prep X X X X X X X X X X
Pour flat work X X
extend water bbw off X
set pse vault X
nadwaye. X X X X X X X X
Base rock X X X X X X X X
x x X x X
ptwr walls X X X X X
,o r a d po,1r F ne a nme5 X X X X X
„Mra te ,nb X X
Subgrade prep for paving.
Concrete pour hinging on TSI taking over where Totem left off.
Friday's pour is uncertain. Waiting to hear from TSI. If does not
happen, MTC will need to be called off.
Hydrant on 3rd. Hot taps scheduled for 3rd at 11:00 A.M. Reed to
cooridnate with Tom Main.
Paving tentatively scheduled for 8/15
Notifications to Public Required:
Driveway closures and 72 hour notice — Reed to coordinate with
businesses and church for the 7/29 driveway pours
Change PCMS boards if no pour on 29th
Page 2 of 9
lf?
+ CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Any intersection closures? Reed to submit a Detour Plan for closure
of NE 10th Street. Submitted. City provided minor comments to be
addressed by Reed.
PCMS Boards Required:
10 days in advance of Intersection closure -
2 days in advance of driveway closure (flatwork and paving) - 2 PCMS
boards up 7/29 for driveway closures
Expected materials that are coming out on-site — Cadman Issaquah
Plant CI 4000 concrete mix, Miles wall mix
6. Utility Coordination
a. COR Water Department —
• FH's in WZD and FH at NE 10th. Done 8/4. Bollards
not needed for FH at 10th
• Irrigation services in WZD and WZB
• Discuss possible Irrigation at Albertsons — Change
to "Restoration Plan". Replace 1:1. City will take
responsibility to keep them alive for one year.
Plant during wet season. PMX concerned with
shrubs with no irrigation.
b. PSE Power
• PSE vault P2 install in WZE —status. Has been installed.
• Next PSE work is WZD —tentative schedule is mid-
September 2022 — Dustin ok with work schedule.
Looking into pole
•School is doing relocation of pole, outside of City's
project footprint. Question regarding whether or not the
Pole is PSE-owned
Page 3 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT - beginning September
2022
• Existing buried telephone already has been relocated by
Lumen at Filterra Vaults in WZD, completed in 2020.
Phil noted there is a pedestal which will need to be
checked against staking to see if it need to be relocated.
7. RSD Elementary School 16 Coordination -
a. Curb and gutter return on NE 10th Street prior to paving 8/15-
8/19
b. Conduit to be buried below sidewalk on SW corner of NE 10th
Street, Reed to blank out sidewalk for now. Reed does not
plan to pour on Friday per Dustin. TSI agreement will pour back
on Reed's contract.
c. Pole relocate at school frontage? Discussion of pole relocation
at 12th. Working with PSE per Ed. City will rush permitting to
get joint projects to work
d. Watermain tie in backfilled tomorrow/no later than Thursday
per Ed.
8. Engineer's Report
a. Totem Electric out of business —Materials moved to TSI yard.
Existing COR equipment stays at TSI yard, then delivered to
City Shop for testing as required. Flora confirmed retesting is
not needed.
b. Is it possible to accelerate schedule for HAWK signal in time for
back to school? Dustin needs to get a new electrical contractor
underway and will ask/let City know. Not likely and detour will
probably remain in place. Signal base poured
c. Street light L18 (WZD) potholing to confirm if a conflict
d. Hairline cracks on wall in WZC leave alone and proceed with
the anti-graffiti coating
Page 4 of 9
=R + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
e. Landscape design in review for Albertsons/Starbucks areas
Change "Landscape design"to "restoration design"
f. Direction given to the Contractor to construct traffic curb in
lieu of traffic curb and gutter on the portion of curb being
replaced west of the PC, on the NW corner of NE 12th Street
and Duvall.
9. Inspector's Report
a. MTC to get Cadman CI 4000 Issaquah Plant mix aggregate
samples for sidewalk pours and take cylinders, slump and
air on 7/25/22 7/29/22—next placement of concrete.
b. MTC to take compaction tests on CSTC— after SW pours
10.Environmental Compliance Report— Manage dust control per Ross.
Water truck onsite per Dustin.
11. Public Outreach —
• Argo Investments parcel (Albertsons) — G&O will send them
restoration plan.
• South of 8th Homeowners association — irrigation repair status — Phil
to check on status
12.Submittals/Documentation
a. Review ROM — Updated
b. Submittals under review: equipment rates
Page 5 of 9
c�1 Y 0,�,
+ +
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs —
14. FWD/ Change Orders—
FWD 25 — Wall Limits and Joints — issued 7/21/22
FWD 26 — Restoration in WZE, in the works
• CO 13 —for school frontage revisions/culvert removal — signed
• CO 14—for storm revisions at MH 33 and at 12th — to City for final
signature
• CO 15 —for proof roll acceptance of pulverized HMA backfill — To City
for final signature
• CO 16 - for water connection at north end and CDF removal — To City
for final signature
• CO 17 —for FH at 10th —on hold for quote from Reed for mod block
wall and survey To City for Final Signature
• CO 18—Storm pipe removal in CDF —no cost, drafted. To Reed
• CO 19- Tree Removal and Landscaping in WZE — in the works
• CO 20—Wall Revisions in WZB and WZD — looking for a quote from
Reed for expansion joints
• CO X.X Rcs-tera-tivn in WZE — in the works
• CO XX— Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status — all SOI's are received. Will Integrity Networks
become a lower tier sub to TSI?
Page 6 of 9
cytY ooe•
+ IR 4'
CITY OF RENTON
'C'FNT°`" DUVALL AVE NE
CAG-20-065
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma,Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls —
Prowess Paymrm No 3(Aril) Pr pess Payment Ne 6(.May) Progreso P.3a.ont No(Awe)
8 Work Zig Or }Ap 14-Apr 23-Ant NI-Apr 7-May 14-May 21-May 21-M v 4-Je. 11Js t$- 25- 2-Ia1
9 Reed Trottel 18-Apr 22-Apr 28-Apr 4-May 16-May 20-May 27,May 6-ho 7-Pro 16-1on 23-1ao l-Id 8-hd
o WE.Corks 14-Apr 22-Apr No Work 6-May No Work 24-;Nay 31-May 3-hm 8-Pro No Walk No Work X 8-I4
1 Toone Beene 23- 27-A Work No 6-hat 13-Nay 20-Nay 24-Nay 6-h 6-he 16-1m 6-hi 6-hi 7-hi
2 PID Lope pr No X X X No Work 137m No Work No Work No Work X X X X
3 Paget Camerae. N.Wet No Work Na Wet Ne Work Na Work No Work Slum No Wait 6-1.. No Work No Wok No Wok No Wok
4.Comore Sashes 23-Apr 23-Apr 3-Nay No Wok No Wok No Work No Wet No Work No Weds No Work No Work No Wok No Work
5 T.mspareita System X X 3-May 344.y 2,Mar 31.Ly 27-May No Work No Work No Wok No Work 1-hi
6 Eveepeem Sasa.hg X X X 9-Hay No Work No Wok No Wok No Wok No Wok No Work No Wok No Wok No Work
7 Gamd14 X X X 4-May 20-May No Wok No Wok No Wok No Wok No Wok No Work No Work No Wok
8 Legacy T.ppas X X X 29-Apr No Wok No Wok No Wok No Wok No Wok No Wok No Work No Work No Work
9 lLdmidge Pasig X X X X 24-May No Work No Wok No Work No Work o k No Work No Wok No Work No Wart
7 P4ym Payment No(Jot) Prowess Pager Ne 9(Amon) Progress Payment N.l9(September)2 Weak P.ai m:g O 9-1 �J 1 16 .1 23Jr II 39id 4-Ao 13-A.6 29-Aged 27-Ao 3-Sop 16S 17Sop 24Sop I-0,
3 Reed Bock* 14-14
4 WE.Cara 13-14 X X
61Tore.EI.o c
6 P.D Logpg X X
7 Paget Coeseeda. No Wok X X
8 Concrete Services X X
9 Trarpodreem Sy.ems X X
o Evapear SormerrOg No Work X X
1 Gomel Up No Wok X X
2 Lowey TiP( - X X X .-
3 Lakeridge Pali No Work X X
4
Week Contractor'Subcontractor is on the job site:payroll required. **(=1 )indicates payroll number**
X Subcontractor was not on-site this week- "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
_ Apprenticeship doe's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
Page 7 of 9
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
17.Progress Payment—
• Progress Payment No 8 — cutoff is July 28th. Documentation
needed by the City on August 4, 2022
18. Other Items:
Concern about Totem invoicing/certified payrolls being submitted.
Tani on vacation 7/26 after meeting and 7/27 — out of cell service,
reach out to David Roman-Sanchez and Michael Ballard for CM
backup for G&O.
Page 8 of 9
C.
1,
lik Emir,
+
CITY OF RENTON
4.FNTD`, DUVALL AVE NE
CAG-20-065
sloWZC-Jan-May2022
WZA-Feb-May 2022 �T\ _I
WZB& E-Mar-Aug 22.2022 max)- sty() =J Zone O
„,„„
WZD-Sept-Nov 14. 2022 r ,
•
WZF(Medians) Nov Jan S.2023
x ) --. L t 1aN 1
TUP. '
' • P•CUECT r-
LOCATION T t 1 4
r '�- ti I NEB
ti
_ 119` r t IN
1 % t ii.c__ _ =Mk
I' 1 1 1
l !'
` N
t 4
I NE 4TH ST ` O
"IV 1 CT 2
LOCATIONPROJE
'II Ell J Fr-...4-_ , ,
WATER MAIN IMPROVEMENTS
N -SCHEDULER
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT 10 SCALE -SCNF Dill E C
City of Renton - Duvall Ave NE, CAG 20-065
Page 9 of 9
, .
i CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JULY 19, 2022
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Vice x Jordan Widener, Widener &
President, Reed Trucking & Assoc.
Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating x
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE Dennis Booth, PSE
Jesse Patjens, Lumen
2. Safety Report—
Traffic control issues - None
Page 1 of 8
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
3. Prior Meeting Minutes— Comments/Acceptance — Accepted
4. Weekly Statement for Working Days ending July 18, 2022
Days Expired: 127.5
Days Remaining: 134.5
5. Schedule Progress
Contractor's Look Ahead Schedule— see attached.
Sidewalk prep. pouring on next 2 Fridays. Finishing blowoff, roadway
ex. top course for paving. Totem scheduled for 26th. Pouring walls
starting the 1st along with 10th Street FH. Need to schedule with water
dept.
Notifications to Public Required:
Driveway closures and 72 hour notice — Reed to coordinate with
businesses and church for the 7/22 and 7/29 driveway pours
Any intersection closures? Reed to submit a Detour Plan for closure
of NE 10th Street.
PCMS Boards Required:
10 days in advance of Intersection closure -
2 days in advance of driveway closure (flatwork and paving) - 2 PCMS
boards up 7/19 for driveway closures - Did yesterday per Phil.
Expected materials that are coming out on-site — Cadman Issaquah
Plant CI 4000 concrete mix, Miles wall mix
6. Utility Coordination
a. COR Water Department—
• FH's in WZD and at NE 10th. FWD to Reed. Need
quote from Reed for survey and wall for CO.
Comment from Phil—Run is longer than one stick
Page 2 of 8
. .
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
of pipe, cut off the bell/megalug per Abdoul.
G&O to send FWD to Tom Main.
• Irrigation services - None in work zone E. Talk to
property manager to see if they want it. Question
regarding if it would be possible to tie into
existing irrigation. Building that houses
Albertsons may have electrical
room/maintenance person that understands
what's in the room. Joey to check for 2006 as-
built.
• Blow off on NE 12th St— Happening today
b. PSE Power
• PSE vault P2 install in WZE - status — was scheduled for
today. Not there yet.
• Next PSE work is WZD —tentative schedule is mid-
September 2022
• Pole relocate at school frontage? Ed mentioned the pole
feeds Church property and questions if the pole relocate
could combine with City's project.
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT - beginning September
2022 Reached out to Jessie Patjens. No response to this
email yet. Tani to call.
• Existing buried telephone to be relocated by Lumen at
Filterra Vaults in WZD, Sta 918+45 RT and 916+45 RT—
Beginning - September 2022
Page 3 of 8
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination
a. Curb and gutter return on NE 10th Street - needs to be
completed prior to paving 8/15-8/19 — Coordinating with Reed
per Ed
b. Hole to be backfilled at FH stub — prior to subgrade prep for
paving 8/15-8/19 Backfill next Wednesday or Thursday
c. Pole serves only the Church. It is in School's Contract to deal
with pole per Ed.
8. Engineer's Report
a. What is the schedule for the street light install in WZC—
around 7/18/22 — no news.
b. Street light L18 (WZD) potholing to confirm if a conflict
c. Hairline cracks on wall in WZC — Bob commented it is too late
to install contraction joints. Leave them be. Need to make sure
future walls have joints. Parametrix to provide detail of
expansion joints. New bid item for joint per LF. Parametrix to
check if new vertical bar needed.
Parametrix to check with structural regarding dowels on large
walls as well.
d. 5 Tree removals and landscaping in WZE and associated
plantings —LS happening/possible irrigation. 1:1 replacement
per Jordan.
e. Control joints for walls in WZB and WZD?
f. Control joints and crack sealant in cured concrete — WZC? Slip
g. Expand wall limits in WZB? Pour Friday. Expansion joint detail
needed today.
9. Inspector's Report
a. MTC to get Cadman CI 4000 Issaquah Plant mix aggregate
samples for sidewalk pours and take cylinders, slump and
air on 7-22-22 Phil was out for curb pour. Need ETA for
sidewalk pour this Friday. Question regarding if concrete
subcontractor could help Totem out for their pole bases.
Page 4 of 8
. .
RCITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. MTC to take compaction tests on CSTC prior to paving After
s/w pours,just prior to paving.
c. Added testing not needed yet for street light foundations.
Unless they switch mixes.
10.Environmental Compliance Report—
Send FWD to Jordan
11. Public Outreach —
• Argo Investments parcel (Albertsons) — Flora/Bob regarding Trees
• South of 8th Homeowners association — irrigation repair status —
repair needed.
12.Submittals/Documentation
a. Review ROM — no new.
b. Submittals under review: equipment rates Still checking on these
c. RAMs that need to be submitted: CI 4000 Cadman Issaquah Plant
mix with ASR mitigation paperwork— reviewed and back to Reed
approved after meeting.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs—
14. FWD/ Change Orders —
FWD 24 — 5 Tree removal in WZE - issued
Page 5 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
FWD 25 —Wall Joints — in the works
• CO 13 —for school frontage revisions/culvert removal —sent to City
for final signatures
• CO 14 —for storm revisions at MH 33 and at 12th —sent to Reed
• CO 15 —for proof roll acceptance of pulverized HMA backfill —sent to
Reed
• CO 16 - for water connection at north end and CDF removal —sent to
Reed
• CO 17 —for FH at 10th — in the works. Dustin will provide quote soon.
No need to re-number CO 17& CO 18.
• CO 18 —Storm pipe removal in CDF — in the works. No cost CO, work
has been completed.
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status — all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
Page 6 of 8
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
16.Certified Payrolls—
Pr.gr.aa Payv.d Ne 5(Apr]) Progress Paymer N.6(Nay) Progress Pnaest No 7(J...)
Week Lulls 0.: f-Apr 16-Apr 23-Apr 30-Apr 7.Mav 14-Mav 21-Nay 221May 4Jan 11-2.e IS-Jma 25J.. 2Jul
Reed Ducking ISS-Apr 22-Apr 22-Apr 4-May 16-May 20-M.y 27-May 6-Jue 7-3m 16-km 23-Am 1-Jul 0-24
WE.Coates 14-Apr 22-Apr No Work 6-May No Work 24-May 31-May 3-Jm 8-3m No Work No Work X 6-hi
Totem Electric _ 27-Apr No Work No Work 13-May 20-May 21-M.y 6-1m 6-Jo 16-3m 6-16 6-Jul 7.14
PIO Loggiig 141� X X X No Wait I3Jm No Work No Work No Work X X X X
Puget Cons"ucdoo No Work No Work No Work No Work No Work No Work 6-her No Work 6-3m No Work No Work No Wale No Work
(.,mete Scioto 25-Apr 25-Apr 3-May No Work No Work No Wads No Work No Work No Work No Work No Work No Work No Work
Transportation Sy"mr. X X 3-May 5-May 27-Mav 31-Moy 27-May No Work No Work No Work No Work 1-hi
-Evergreen Sawemogr X X X 9-Moo No Nook No Work No Work No Work No Work No Wale No Work No Work X
Ground Up X X X 4-May 20-May No Wort No Work No Work No Work No Work No Wale No Work X
Leg.cy Tapp* X X X 29-Apr No Work No Work No Work No Work No Work No Work No Work No Work No Work
Lakeridge Pavag X X X X 24-Mar No Work No Work No Work No Work No Work No Work No Work No Work
Progress Seymour No 0(July) Propane Parson No 9(Ansel) Progress P.yse.t No 10(Septembr)
WeekEsd'ugOa: 9Jel 16Jd 23J.1 30J.1 6-Aug 13-A.g 20-A.g 27-Aog 3-Sep 10-Sep 17-Sep 24-Sep 1-0c1
Reed Truckkg
WE.Coates X
Teem Electric _
Pall Logging X -
Puget Construction X _
Concrete Services X
Trm portmon Svv .._......
Evaprrn Sawrumng X
Gourd Up X
Legacy Tapping X
Lakeridge Paring No Work
Week ContractoriSubcontractor is on the job site,payroll required- **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required-
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship dot's required --
-Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 8 — cutoff is July 28t". Documentation
needed by the City on August 4, 2022
18. Other Items:
Tani on vacation 7/26 after meeting and 7/27
Transition to vertical traffic curb at asphalt overlay area
Page 7 of 8
_ . •
aR
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 A V �_i
WZA-Feb-May 2022 �`+ - A_
4._I Zonea '
WZ8&E-Mar-Aug 22, 2022 � kE—
s BWp
WZD-Sept-Nov 14,2022
WZF(Medians)-Nov-Jan 3,2023 ' _
( -
_____ 12714 c___. •" /---.1
tycP0.---— !IV 7 — .
—2 LOCATION J
CATI Nei _ sr
Slip J i'
AIME MR"
N
,,,,,
Z Work Zane C
2 '
Ilitr" 'i CW __
4
o _AI______ NE 6T1t ST
W
I ii. . o
$ —Z— L
' NE 4TN ST 8
PROJECT L- I 1 — - _— --- —
Si LOCATION
N�� 1 -�CiEDULE_Aj,
WATER MAIN IMPROVEMENTS
N -SCHEDULE&
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TOSCAEE -SCHEDULE[
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
REED c
Date:07/16/22-08/05/22 3 Week Look-Ahead Schedule
7RUCIUNG 6 EXCAVATING Name: Duvall Avenue
July August
Sched
ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/Resources
_ 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
Sidewalk prep X X X X X X X X X X
Pour flat work X X
extend water blow off X
set pse vault X
roadway ex X X X X X X X X
Base rock X X X X X X X X
Cstc X X X X X
pour walls X X X X X
form and pour Filterra flumes X X X X X
Install Hydrant on 10th X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
J U LY 14, 2022
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener &
& Excavating Inc. Assoc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer-Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton
fired--Du-k-e, Totem Electric Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating x
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE x Dennis Booth, PSE
Jesse Patjens, Lumen Justin Johnson
2. Safety Report —
Traffic control issues—Starbucks driveway incident, driver drove over
fresh curb, 911 called, no injuries. Phil—driver was heading NB, and
barrels/signage clearly stated no left turn. Police did not give driver
Page 1 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
ticket, which is confusing. Had multiple witnesses. Per TCP it was illegal
to make left from NB lane. Signs are up stating so.
3. Prior Meeting Minutes—Comments/Acceptance — no comments.
4. Weekly Statement for Working Days ending July 4, 13 2022
Days Expired: 122.5 124.5
Days Remaining: 139.5137.5
5. Schedule Progress
Contractor's Look Ahead Schedule — Dustin —sidewalk fort weeks.
Pour on 22n`' and set up/pour again on 27th/29th TSI will work on
flumes/lids/bit of walls. Then finish subgrade/base rock, etc. HMA
very tentative 8-15 to 8-19
Notifications to Public Required:
Driveway closures and 72 hour notice — Reed Trucking has
coordinated with businesses for the 7/13 curb pour at the service
driveway? Planning to keep one driveway open for church and
Albertsons then alternate for second pour.
Any intersection closures? 72 hour notice
PCMS Boards Required:
10 day in advance of Intersection closure -
2 day in advance of driveway closure (flatwork and paving) - 2 PCMS
boards up 7/11 for temp driveway closures for curb. Need to add
PCMS boards for 7/19 and 7/26 advance notice
Expected materials that are coming out on-site —
Sidewalk/Driveway concrete from Cadman Issaquah plant. Wall mix is
the Miles Concrete mix. G&O will confirm testing requirements for
foundation concrete.
Page 2 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
6. Utility Coordination
a. COR Water Department—
• FH at 10th —What is the schedule? PMX has given FH
location and back of sidewalk elevation to compute the
flange height. PMX has wall design put together. Dustin
—not yet but need to schedule a lot of work there.
Curious of options for closures. Can close% at time?
Dustin concerned about% closure being challenging.
Dustin confirmed less than 24 hours for several days
during work hours—less than 8 hours per day.
Scheduled for 1 week, possibly less. Closure would be
access to &from Duvall from 10th. Dustin to provide
detour plan for City to review that utilizes 6th. Dustin
also thinks 12th is similar on paving day. Bob—can
detour 12th over to Sunset.
• Removal of wood forms for blocking Waived by the
City for the 16" connection at NE 12th St
• Bagging water pipe at connection at 12th - waived by
the City for the 16" connection at NE 12t1' St.
• Water Main Remaining work:
1. FH's in WZD and at NE 10t1
2. Irrigation services Dustin - Do we have one in this
phase? Confirmed via plans that we do not.
3. Blowoff on 12k", scheduled for Monday
Page 3 of 9
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. PSE Power
• PSE JUT crossings in WZE in the works Dustin —still
need to get to pole and get risers up but out of paving
section.
• PSE vault P2 install in WZE in the works — Confirmed
pipe found is abandoned. Dustin W. getting inspector
back out there— will provide timeframe tomorrow.
• Next PSE work is WZD—tentative schedule? Dustin W-
Within 5 to 6 weeks lead time. Dustin (Reed) says mid-
Sept-early October. Dustin W to put this timeframe into
PSE's scheduling.
c. Lumen Did not attend.
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT— Dustin —Would want
them there in 1st part of September.
• Existing buried telephone to be relocated by Lumen at
Filterra Vaults in WZD, Sta 918+45 RT and 916+45 RT—
What is the schedule for start of WZD?
d. City Illumination conduit WZE —
• City OK'd early removal of street lights and existing
street light conduit between NE 12th and Starbucks
driveway. Completed
7. RSD Elementary School 16 Coordination
a. Curb and gutter return on NE 10th Street - needs to be
completed prior to paving - poured yesterday except at 10tn
Reed paving middle of August...needs to take place prior. Ed—
the conduit is installed on west half of 10tn.
Page 4 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Hole to be backfilled at FH stub — prior to subgrade prep for
paving Ed - water stub hole to be filled prior to paving. Working
with City on connections/testing. Done w/in 2 weeks.
c. Power pole to be moved just north of school driveway....City
feeds off of it. Another pole relocation as part of Duvall....do
this pole also? Dustin Weller— will check with design team and
see if it can add on...it makes good sense. Phil—Potelco would
not let us dig to pole...in a bank with a large cut. Would end up
exposing base of pole—so likely need relocation prior. Ed—
may need to build rockery/some type of wall also.
8. Engineer's Report
a. What is the schedule for the street light install in WZC— Fred
email— week of July 18 for powder coating so possibly end of
July.
b. Street light L18 (WZD) has a conflict with other buried utilities.
Future pothole to determine if a shallow footing is needed.
G&O to send info to PMX. Dustin noted that pothole to be
performed by Totem.
c. Concrete costs for WZE, Reed to provide backup for any
proposed adjustments review. Dustin to follow up.
d. Hairline cracks on wall in WZC — Control joint idea at every
expansion joint. Will control future cracks. Ex cracks either by
filler or sacking prior to anti-graffiti coating. Per
Dustin....sacking took place last week. Need to add control
joints in WZB....stay tuned. Hold on anti-graffiti coating. Tani
shared below detail.
11. TOP Orsus
CONTROL JOINT
DETAIL
Page 5 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
9. Inspector's Report
a. Steel sheets are past the 10 day limit for the water main
connection.
b. MTC to get Cadman mix aggregate samples and take
cylinders, slump and air on 7-13-22 Phil—MJC was out for
concrete — went well.
c. Will need back out for CSTC compaction tests on pavement
subgrade.
d. G&O to check to see if MTC needs to get another set of
cylinders on foundations
10.Environmental Compliance Report— Widener did not attend.
11. Public Outreach —
• B&G Property Maintenance for Argo Investments parcel (Albertsons)
Phil met with their electrician...showed them our work. He was
getting back to Albertsons why their sign was out. Did confirm it was
out before our groundbreaking.
• South of 8th Homeowners association — irrigation should be OK— Phil
concerned about 5-foot concrete pad for FH...sprinkler system will be
encapsulated now. Bob is not worried about it.
• Albertsons manager - Driveway closure communication has been
done.
12.Submittals/Documentation — David-All are in good shape
a. Review ROM —
b. Submittals under review: Single tap service & equipment rates
Page 6 of 9
'5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. RAMs that need to be submitted: G&O to request resubmittal for
Cadman Class 4000 out of Issaquah plant.
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — Mfg. Cert. of Compliance for B9
Additional Ductile Iron Fittings may be waived
13. RFIs — RFI 25 regarding conduit behind Filterra vault at NW corner of
12th and Duvall — response sent
14. FWD/ Change Orders—
• CO 13 —for school frontage revisions/culvert removal — sent to City
for final signatures
• CO 14 —for storm revisions at MH 33 and at 12th —drafted and in
review Sent to Reed
• CO 15 —for proof roll acceptance of pulverized HMA backfill — drafted
and in review Sent to Reed
• CO 16 - for water connection at north end and CDF removal —
drafted and in review Sent to Reed
• CO 17 —for FH at 10th — in the works
• CO XX —Storm pipe removal in CDF
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status — all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
Page 7 of 9
a
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services • $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls—
Pr Arms Payment No 5(Ap7I Prams Pavan..No 6(May) Prop...,Pavan*No 7(7...)
Week Ending O. 9-Apr 16-Apr 23-Apr 36-Apr 7-May 14Mav 21-May 28-May 4J.. 11.3en 18Jen 25.. 2J.1
Reed Tmrlmg IS-Apr 22-Apr 28-Apr 4-May 16-May 20-May 27-May 6-Jm 7-Jun 16-Inn 23-3m 1-M 8-JuI
W E.Coates —_- 14-Apr 22-Apr No Wodc 6-May No Work 24-May 31.May 3-Jan S-Jun No Work No Work X 8-1u1
Totdu Electric 25-Apr 27-Apr No Work No Work 13-May 20-May 24-May 6-Jo 6-Jun 16-1m 6-101 6-3:3 7-M
P"D Logging 111P06611 X X X No Work 13-lire No Work No Work No Work X X X X
Puget Construction _ No Work No Work No Work No Work No Work No Weds 6-Jm No Wort 6-Jm No Work No Work No Work No Work
Concrete Services _ 25-Apr 15-Apt 3-May No Work No Wodc No Wore No Work No Wodc No Wo,k No Work No Work No Work No Work
Transportation Svaeaar X X 3-May 5-May 27-May 31-May 27-.May No Work No Work No Work No Work 1-3d
Evergreen Sawcraoog X X X 9-May No Work No Work No Work No Work No Work No Work No Work No Work X
Ground Up X X X 4-May 20-May No Work No Work No Work No Work No Work No Work No Work X
Legacy Tapping X X X 29-Apr No Work No Work No Work No Wodc No Work No Work No Work No Work No Work
Lakaidge Pang X _ X X X 24-May No Wade No Wort No Work No Work No Work No Work No Work No Work
Week Contractor/Subcontractor is on the job site,payroll required- **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship dot's required _ _
Payroll Resubmittal
No Work Received"No Work Performed"payroll
"Final"payroll
17. Progress Payment—
• Progress Payment No 7—cutoff was June 30th. Documentation
sent to the City
• Progress Payment No 8— cutoff is July 29th. Documentation
needed by the City on August 5, 2022 — Change cutoff date to 28th
and send documentation to City by August 4th? City need
additional time for all departments to review. Dustin —
mentioned it's not ideal for tax reasons but is ok with the 28th
Page 8 of 9
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
18. Other Items: Cut by Starbucks...less steep than 2:1...drops off quite
steeply to parking lot. Nice tree with roots sticking out. May need to remove
and put in new one. Look at tree just south of Starbucks. Another on
midway 100 feet south as well. Bob....if question of building wall or plant
new tree; plant new tree. Phil to put blue ribbon around trees and Bob to
contact owner to discuss replacing trees. Parametrix to provide revised
landscape design.
WZC-Jan-May 2022 - — .� ( - �
WZA-Feb-May 2022 ��—_
WZI3&E-Mar-Aug 22,2022 r tiEs °Eft Z __ —
WZD-Sept-Nov 14,2022
WZF(Medians)-Nov-Jan 8,2023
Js lL. N 127N ST
:N /g
LOCATION NEDVLE NE ST 1 I
, iiir _?W -‘ gi, piw 'N
1
r
-� gUMW 1 a . =11111k
iH7TH
z I-
t Ilk > I
1I
— NE bin si N
2 t us
2 a q 1
f +J i Ip
AI NE 4THST C O
PR CIE _N —t _
} sl LOCATION 1
lH�g9_0 uriEDULE ,
11 `:1 --)/ � -�
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
City of Renton- Duvall Ave NE,CAG 20-065
Page 9 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JULY 5, 2022
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener &
& Excavating Inc. Assoc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing Abdoul Gafour, City of Renton
Renton School District
Dustin Weller, PSE Dennis Booth, PSE
Jesse Patjens, Lumen Justin Johnson
x
2. Safety Report —
Traffic control issues— no issues
Page 1 of 9
ti
iCITY OF RENTON
DUVALL AVE NE
CAG-20-065
3. Prior Meeting Minutes— Comments/Acceptance — last week's
minutes are accepted
4. Weekly Statement for Working Days ending July 4, 2022
Days Expired: 117.5
Days Remaining: 144.5
5. Schedule Progress
Contractor's Look Ahead Schedule — From last week's schedule.
Roadway Ex/base rock...gettinq ready for curb. PSE vault/2 half
crossings on the 7th and 8th, curb scheduled for 13'. Working on CO.
Totem working on illumination, water system almost done. Driveway
process is straighforward but multi-step due to curing. Will keep at
least one driveway open.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice Dustin to talk to
Jordan, would rather full closure/sheet them. Can be done all in one
day. Reminder about 72 hours notice. Bob—closure scheduled to
accommodate Altbertson's delivery for service driveway. Dustin
belives mid-day to end of day is when it would take place. Bob...need
to meet manager of store (multiple stores).
Any intersection closures? 72 hour notice
PCMS Boards Required:
10 day in advance of Intersection closure -
2 day in advance of driveway closure (flatwork and paving)
Bob...would be for public driveway (3rd driveway is shipping driveway
so no need to have the PCMS). 1 in each direction can serve both. Phil
—need PCMS boards onsite Monday the 11th
Expected materials that are coming out on-site — Dustin —no.
Page 2 of 9
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
6. Utility Coordination
a. COR Water Department —
• FH at 10th —What is the schedule? Discuss type of wall
Would be nice to use ex. bid item but perhaps modular
block wall is more appropriate...need to look at height
(4.5 to 5')/length and ROW proximity. PMX to look into
it.
•Water Main Remaining work:
1. Removal of wood forms for blocking—Dustin—
`will disrupt traffic... .it is really worth it for /2
inch plywood? Bob would not pull it back out.
Justin suggests Reed formally asking the question
and the City would provide a response. G&O to
document officially and suggest left in place to
Abdoul for approval.
2. Bagging water pipe at connection at 12th Phil—
pointed out in specs... Contractor is supposed to
bag it after City is done. Unclear if required
during installation so it wasn't done. Installed
pipe does not touch native soil. Dustin—does the
bags meet the intent?Justin Johnson—described
typical practice.
3. FH's in WZD and at NE 10th
b. PSE Power
• Schedule for PSE JUT crossings in WZE — Dustin
answered...out on 7t" and 8rn
• Schedule for PSE vault P2 install in WZE — Dustin
answered...out on 7' and 8th.
c. Lumen
Page 3 of 9
if? CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT —Coming up.
• Existing buried telephone to be relocated by Lumen at
Filterra Vaults in WZD, Sta 918+45 RT and 916+45 RT —
Coming up. Phil...would want them onsite as soon as
begin work....Phil suggests sending Lumen an email
now, having them scheduled for week of Reed
beginning. 1st week of August.
d. City Illumination conduit WZE —
• City to lower conduit at three driveways in WZE,
coordinating with Contractor. One foundation was
exposed at Starbucks driveway....so it's removed now.
All are daisy chained. All are within driveway depth.
Dustin suggest removal. Bob suggests removal. G&O to
send out an email confirming OK to remove in advance
of new system on line. Phil also gave heads up about
possible additional between Starbucks and Albertson's
driveway (dead Junipers). Parametrix to follow up.
7. RSD Elementary School 16 Coordination
a. Conduit crossing at NE 10th Street —needs to be completed
before July— in the works
b. Curb and gutter return on NE 10th Street - needs to be
completed prior to paving (tentative mid-August) Phil has
concerns about large open hole and when work can take place
before closing up. Phil to email Tani photos. Tani to send reply
to Ed.
8. Engineer's Report
a. CDF for abandoning storm pipe has been deleted by FWD due
to procurement issues. The storm pipe will be removed.
Page 4 of 9
5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. What is the schedule for the street light install in WZC —week
of 7/18 anticipated for delivery of arms? Fred—still tracking.
Will report back on installation timing.
c. Street light L18 (WZD) has a conflict with other buried utilities.
Future pothole to determine if a shallow footing is needed.
G&O to send info to PMX. Stay tuned.
d.TV inspection confirmed required for the 24-inch diam storm
pipe.
e. Concrete costs for WZE, Reed to provide backup for any
proposed adjustments review.
f. If unsuitable subgrade conditions are encountered for the
pavement construction, there will be over excavation and
installation of crushed surfacing
9. Inspector's Report Phil—no recent testing. CSTC testing upcoming
after curb line wheel roll. Cylinders on next set of curb install.
10.Environmental Compliance Report— No update.
11. Public Outreach —
• B&G Property Maintenance for Argo Investments parcel (Albertsons)
to look at the illuminated sign at Albertsons/Starbucks. Phil-
Unsure why it's not illuminated...been out for 6 months (before our
project was there). Meter box photocell next to light....doesn't
appear to work. Meter has power but not using electricity. Nothing
to do with Reed Trucking.
• There is a request for help with cut-through traffic Request by
property manager to add signs. Phil - motorcycle cops giving out
tickets last Friday.
• South of 8th Homeowners association broken irrigation
issue...Dustin/Jordan investigating.
Page 5 of 9
11R
4 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Justin got call from Albertsons manager...asking to be directed to
City's project website. Flora to talk with Manager of Albertsons.
12.Submittals/Documentation
a. Review ROM —
b. Submittals under review: Single tap service & equipment rates
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — Mfg. Cert. of Compliance for B9
Additional Ductile Iron Fittings included in PP # 7
13. RFIs— RFI 24 regarding depth of cover of FO and power conduit in
trench — no changes, stay with the plan per previous email.
14. FWD/ Change Orders—
• FWD21- FH relocation at NE 10th Street — was issued
• FWD23 — Storm pipe removal in lieu of CDF abandonment was issued
• CO 13 —for school frontage revisions/culvert removal —sent to City
for final signatures
• CO 14 —for storm revisions at MH 33 and at 12th — drafted and in
review
• CO 15 —for proof roll acceptance of pulverized HMA backfill — drafted
and in review
• CO 16 - for water connection at north end and CDF removal —
drafted and in review
Page 6 of 9
G\SY O
1.s
+ 4
CITY OF RENTON
4)F1,1T0‘' DUVALL AVE NE
CAG-20-065
• CO 17 —for FH at 10t1' — in the works
• CO XX — Supplemental RPM's/Traffic Arrows — in the works
15. Subcontractor Status— all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls —
Pro3resa Pavweat Nos(Apra) Prowess Paym.0 N.6(May) Progress Payment No 7(June)
1),.h.r.F mh...Oa: 9-Apr 16-Apo 23-Apo 30-Apr 7-May 14.Mov 21-May 2S-May 6J.. 11-J.. 19-J.. 25J.. 2J.1
Rccd T.o ko, 18-Apr 22-Ape 28-Apr 4-May 16-May 20-M.y 27-May 6-Jw 7-Jvo 16Jmr
WE Coates I 4-Apr 22-Apr No Work 6-May No Work 24-May 31-Mry 3-Jon 8-Jon No Work X X
Totem Electra --- _s Apr 27-Apr No Work No Work 13-May 20-Mary 24.May 6-J.. 6-Jo. 16-Jm
PoD Logging NIlikand X X X No Work 13-Jo. No Work No Work No Work X X X
'..Pager Coomorrmo No Work No Work No Work No Work No Work No Work 6-Jon No Work 6-he No Work No Work X
IC.oQae Sasiees 25-Apr 25-Apr 3-May No Work No Work No Work No Work No Work No Work No Work X X
Traraportarioo Systems X X 3-May 5-May 27-May 31-May 27.May No Work No Wodc X X X
Evergreen Sawcarting X X X 9-Mry No Work No Work No Work No Work No Work No Work No Work X
Cnoo.d Up X X X 3-May 20-May No Watt No Wort No Work No Work No Work No Work X
Legacy Tapp..g X X X 29-Ay No Work No Work No Work No Work No Work No Work No Work X
Lakendge prig X X X X 21-May No Work No Weak No Work No Wodc No Work No Work X
Page 7 of 9
R4 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor.+Subcontractor is on the job site,payroll required_ '"(#12)indicates payroll number"
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required _ _ _ _
Payroll Resubrnittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 7 — cutoff was June 30th. Documentation
needed by the City July 7th
18. Other Items:
Dustin requests flange elevation for hydrant relocation at 10th. PMX to provide.
Use 2% and carry all way back to hydrant location. 2 inches from bottom of nut.
FWD needed to remove WZE illumination? Bob—email is sufficient.
Page 8 of 9
,,,,R
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 1 � )
WZA-Feb-May 2022
7-1
WZB&E-Mar-Aug 22,2022 J Ws Irmo Z
WZD-Sept-Nov 14,2022 °x • i
WZF(Medians)-Nov-Jan 8,2023 ��_' 1 t
4F L
�° - P• 187 — 1 ' , L_
LOCATION 1 i
y �� REDUCE• INE1j,
N
is
.......
Z : .,..btZC
_Ai.,
rip.. 5,1riti,L,,_.,7
�► -- `
yzy- NE6THSr ,,.
r' 4 dill z
NE am Sr
PR•IE _Lt —
LOCATION
14Adak UCHEDVLE
(§
fr WATER MAIN IMPROVEMENTS
N -SCHEDULE 8
VICINITY MAP UNDERGROUND IMPROVEMENTS
Nor tp SCALE -SCHEDULE C
City of Renton- Duvall Ave NE, GAG 20-065
Page 9 of 9
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JUNE 28, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener &
& Excavating Inc. Assoc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District x
Dustin Weller, PSE Dennis Booth, PSE
Jesse Patjens, Lumen
2. Safety Report —
Traffic control issues— None
3. Prior Meeting Minutes — Comments/Acceptance — Accepted
Page 1 of 8
5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending June 27, 2022
Days Expired: 112.5
Days Remaining: 149.5
July 4th Holiday next Monday
5. Schedule Progress
Contractor's Look Ahead Schedule— see attached
Move north of 12th. 10"x6" wet tap per FWD 21
Curbs on the west side scheduled for the 13th, to be completed in one
day.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice
Needed for curb installations per Dustin.
Any intersection closures? 72 hour notice
PCMS Boards Required:
10 day in advance of Intersection closure - Intersection will have 1
lane around them per Dustin.
2 day in advance of driveway closure (flatwork and paving)
Expected materials that are coming out on-site — CDF? - CDF for
storm lines.
6. Utility Coordination
a. COR Water Department —
• FH Pumper Ports on backorder. A notification to the
Renton Regional Fire Authority chief needs to be made
to let them know that once the new 16-inch main is
live, the fire hydrants between NE 7th Street and Sunset,
west side of Duvall, will not have Storz adapters as a
temporary condition. Storz adaptor are on a national
Page 2 of 8
if? CITY OF RENTON
DUVALL AVE NE
CAG-20-065
backorder, ETA unknown. Dustin to check if removal of
ex hydrant thread can be used for new hydrant, will
check the thread type of hydrants. Only one can be
used. Dustin will notify City which hydrants can be
reused. Dustin noted this work would be done by
supplier.
G&O asked if hydrants in WZC can be unbagged. 3
hydrants per Phil. Wet taps done. Abdoul requested to
unbag them, and noted foot valve should be on. Dustin
will provide City info on threads of these hydrants (these
hydrants don't have Storz yet). City will notify Fire
Department.
• FH at 10th — FWD in review by City for after District
abandons their water main. G&O has received verbal
notice form District that WM is abandoned. G&O will
request written notice. Once received G&O will forward
FWD to Reed.
• Water Main Testing Schedule: 10x16 vs 16x16shown
on plan. Need retaining wall there. New CB just west of
ramp on SW corner of 10th installed per Phil.
1. Verbal confirmation that purity samples passed
their testing received 6/27/22. City waiting on
email confirmation.
2. Tie-ins on 6-28 (Starbucks and apartments) and 6-
30-22 (remainder), thrust blocking to be placed on
6-28-22 and 6-30-22.
3. City will activate the main after the 3-day cure on
the thrust blocks.
• Water fitting needed for 8" connection. Dustin already
picked lip parts.
b. PSE Power
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Schedule for PSE JUT crossings in WZE — PSE did not
attend.
• PSE vault P2 install in WZE — can this hold for WZD and
remaining JUT work? Unknown.
c. Lumen Lumen did not attend.
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT
• Existing buried telephone to be relocated by Lumen at
Filterra Vaults in WZD, Sta 918+45 RT and 916+45 RT
d. City Illumination conduit WXE—Flora to ask for Eric's
attendance. Question on if City's splicing could happen in one
day.
• Between the Albertson and Starbucks driveways, the
existing City illumination conduit was exposed and
above sidewalk subgrade. City to lower conduit at
three driveways, coordinating with Contractor. Phil
noted that driveways have not been fully cut to
subgrade. Additional grading required which will
further expose conduits.
• Does the City want expansion joint around j-boxes that
go in the sidewalks? (WZD)
7. RSD Elementary School 16 Coordination
a. Conduit crossing at NE 10th Street— needs to be completed
before July— in the works
b. Curb and gutter return on NE 10th Street - needs to be
completed prior to paving (tentative mid-August)
c. Michael Sippo noted updated Plans have been sent out with
comments including Traffic.
Page 4 of 8
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
8. Engineer's Report
a. Reviewed method for filling storm pipe with CDF with Reed
Trucking. Discuss added breaks in pipe. Will make it happen,
per Dustin
b. What is the schedule for the street light install in WZC? Totem
provided updated schedule— Week of 7/18 for delivery of
luminaire pole arms.
c. Street Light L25 conflict resolved. Wire confirmed in the field
to be dead.
d. Street light L18 (WZD) has a conflict with other buried utilities.
Future pothole to determine if a shallow footing is needed.
G&O to send info to PMX.
e. Lamping in lieu of mandrel test is OK on the 24-inch diam
storm pipe. Dustin preferred to lamp. Question on if TV
inspection can be waved. City to provide response.
f.Concrete costs for WZE, Reed to provide backup for any
proposed adjustments review. Reed anticipates there will be
additional cost and has requested info from supplier and will
forward for review.
9. Inspector's Report 16-inch tie-in happening now. Jordan to do wheel
roll for subgrade for curb placement.
10.Environmental Compliance Report— Widener did not attend. No
update.
11. Public Outreach —
12.Submittals/Documentation
a. Review ROM — No update
b. Submittals under review: None
Page 5 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. RAMs that need to be submitted: Single tap service
requested
d. Non-Material Submittals that need to be submitted: none
e. Material Documentation — In good shape
13. RFIs — none
14. FWD/ Change Orders —
• FWD21- FH relocation at NE 10th Street— in review by City
• FWD22 —Shift Filterra unit to curb at NW corner of 12th was issued
• CO 13 —for school frontage revisions/culvert removal — sent to
Contractor
• CO 14 —for storm revisions at MH 33 and at 12th — in the works
• CO 15 —for proof roll acceptance of pulverized HMA backfill
• CO XX—for FH at 10th — HOLD for FWD
• CO XX —Supplemental RPM's/Traffic Arrows — in the works
• CO 16 - for water connection at north end and CDF removal - in the
works
15. Subcontractor Status — all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
Page 6 of 8
IR
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls-
- -- Ts Parme.l No 5( fPr. eas Paym..t No 6(Mar) Pr.p. .l ss Pay mom No 7(Juno)
11..-,4,F.��,Iint,O. 9-Apr6-Apr 23-Apr 38.Apr 7-May 14-Mav 21-1May 28-May /J� 11-Jo. I 1sJ.. 25i.. 24.1
18-Ap2-Ace 28-Ape 4-May 16-May 20-May 27-}fay 6-km 7-Jun 16-Jun
- I4-Ap2-Apr No Wak 6-May No Work 24 May 31-May 3-Jun 8-Jun No Work X X
T--em Elemk _ A 27-Apr No Work Na Work 13-May 20-May 24.May 6-km 6-km _16-Joo
PO Loggag _ X X X No Work 13-Jm No Work No Work No Work X X X
;Puget Como-macs No Work No Work No Work No Work No Work No Wale 6-km No Work 6-Jar No Work No Work X
'Concrete Ser.ices 25-A$ 25-Ap 3-May No Work No Work No Wak No Work No Work No Work No Work X X `
Traaspararion Systems _ X X 3-May 5-Noy 27 May 31-May 27-May No Work No Work X X X
Evacreon Saw vmg X X X 9-May No Work No Nook No Wools No Work No Work No Work No Work X
Ground 1:p X X X 4-May 10-May No Work No Wodc No Work No Work No Work No Work X
Legacy Tapping X X X 29-Apc No Work No Work No Work No Work No Work No Wolk No Work X
,Lakeridge Paving X X X X 24-May No Work No Work No Wodc No Work No Work No Work X
Week Contractor/Subcontractor is on the job site,payroll required **( 12)indicates payroll number"`*
iiii
X Subcontractor was not on-site this week. "No Work Performed'payroll required-
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final payroll
17. Progress Payment —
• Progress Payment No 7 — cutoff is June 30tt' Documentation
needed by the City July 7th
Page 7 of 8
IR
; CITY OF RENTON
DUVALL AVE NE
CAG-20-065
18. Other Items:
WZA-Jan-May 2022 — � _
WZA-Feb-May 2022
WZB&E-Mar-Aug 22,2022 �-r 1 i
WZD-Sept-Nov 14,2022 f ZCU -`"
WZF Medians -Nov-Jan 8,2023 ' i I i
t
•
i NE 12TH
s�° __ PR�J —� — LL
LOCATION
-sc ECu�E• _ I Nc sr . ___
r bi-
4.1 lii
mir
IIIIN ii_1
;Nip5 wd am.c 74
1I N ri 04011 0
a JNE 4TH t' 5
ST ` S
PR*JE — — ;—
s ss LOCATION —
0►4 HENLE%
. -1-1 - 2) U4 —
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
•
REEDC. Date:06/25/22-07/15/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
IMO
June July
Sched
ID Work Description S S M T W T FSSM TWT FSSM T W T F Notes/Resources
25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 19 11 12 13 14 15
water tie ins X X X X
Roadway ex X X X X X X X X X
Base rock X X X X X X X X X X X X
CSTC X X X X X
Illumination system X X X X X X X X X X X X X X
psis install X X
Cd9 fill storm X X
Curb prep and install X X X X X
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JUNE 21, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc. x
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton.
Renton School District
Dustin Weller, PSE Dennis Booth, PSE
2. Safety Report— No issues.
Traffic control issues — No issue with No left turns onto driveways for NB
Duvall which may have been confusing for lefts allowed at Sunset per
Phil.
3. Prior Meeting Minutes — Comments/Acceptance — No comments.
Page 1 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending June 20, 2022
Days Expired: 107.5
Days Remaining: 154.5
Will there be any change on work hours with the longer daylight? —max
out at 10 hr/day per Dustin
5. Schedule Progress
Contractor's Look Ahead Schedule—
Next 2 weeks is water testing/tie-ins. Then onto roadway ex./base
rock installation for curb/gutter on July 13. Totem doing illumination
and fiber optics.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice None
Any intersection closures? 72 hour notice
PCMS Boards Required:
10 day in advance of Intersection closure
2 day in advance of driveway closure (flatwork and paving)
Expected materials that are coming out on-site — nothing new
6. Utility Coordination
a. COR Water Department—
• FH Pumper Ports on backorder. A temp solution via use
of available NST threaded ports/temp re-use of Seattle
thread from existing FH when abandoned. No
information on arrival. Dustin can get temporary fittings
for pumper ports. City wants standards met,for
permanent installation. Phil explained three options:
1- Do nothing
2 —Move Storz adapter from one existing FH to one new
FH
Page 2 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
3 —Purchase and use temporary non-City standard Storz
adapters.
Bob said to notify Fire District that the new hydrants are
not fitted with Storz adapters for an interim timeframe.
• FH at 10th — FWD in review by City for after District
abandons their water main.
• Water Service relocate schedule on SE corner of 12th
and Duvall complete.
• Water Main Testing Schedule:
1. Poly pigging was completed
2. Contractor pretest water for hydro static pressure
test on 6-20-22
3. If pretest is successful, then hydro static test on 6-
21-22
4. If hydro static test passes on 6-21-22 then
chlorinate the new water main on 6-22-22
Pre-testing today
5. Take chlorine residuals on 6-23-22
6. If residuals are good flush water main on 6-23-22
7. Take samples for purity tests on 6-24-22
8. Purity samples should be back by 6-28-22 (subject
to the lab).
9. Tie ins on 6-29 and 6-30-22, can all thrust
blocking be placed on 6-30-22? Need info from
Abdoul on if lines can be charged without thrust
blocks
•Tie in lengths - Per WSDOT 7-09.3(23)A, a distance of 18
feet max is allowed.
b. PSE Power
• Schedule for PSE JUT crossings in WZE -
• PSE vault P2 install in WZE —can this hold for WZD and
remaining JUT work?
Page 3 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Lumen
• Existing telephone vault to be relocated or adjusted by
Lumen at WZD, Sta 919+40 RT
• Existing buried telephone to be relocated by Lumen at
Filterra Vaults in WZD, Sta 918+45 RT and 916+45 RT
• G&O to invite Jesse to Meetings.
d. City Illumination conduit
• Between the Albertson and Starbucks driveways, the
existing City illumination conduit was exposed and
above sidewalk subgrade. Contractor claiming a
changed condition — via verbal and email notification.
• Does the City want expansion joint around jboxes that
go in the sidewalks? (WZD) City to provide answer.
7. RSD Elementary School 16 Coordination
a. Conduit crossing schedule at NE 10th Street— needs to be
completed before July— Electrician working on 10th today per
Ed
b. Curb and gutter return on NE 10th Street - needs to be
completed prior to paving (tentative mid-August) School
District in communication with Reed. Ed will confirm. Don't
want new patches.
c. FWD—revises the school frontage work(deleting trench drains,
curb/gutter modifications, based from drawings from May
11th ) Ed to confirm. Phil requested contact info. Kyle Cundy
(425.275.1299) is superintendent for school's general
contractor Cornerstone per Ed.
Page 4 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
8. Engineer's Report
a. Discuss status of swapping out 3 Filterra vaults that will go on
the east side of Duvall for correct plumbing. Contech has
picked up 3 filterras today. No cost info has been provided to
Dustin.
b.The City OK'd plan revision to shift Filterra at NW corner of
Duvall and NE 12th Street to the curb line to avoid PSE conduit
conflicts.
c. Parametrix sent out north and south elevations for Filterra unit
finished grades.
d. Reviewed method for filling storm pipe with CDF with Reed
Trucking. Discuss added breaks in pipe. Plans show 5 breaks
north of 12th. CDF fill after Water. Fill pipe and abandon CBs
before installation of curb per Phil.
e. What is the schedule for the street light arms procurement?
Next week per Fred.
f. Street Light L25 has conflict with unknown conduit. Argo
Investments to review with their property manager.
g. Street light L18 (WZD) has a conflict with other buried utilities.
Is a shallow foundation possible, and how deep would it be?
City would allow a spread footing.
h. Reed trucking requested permission to lamp 57 LF storm run
on 24-inch diam storm pipe in lieu of mandrel test. Flora to
provide reply.
i. Concrete costs for WZE Dustin assumes cost adjustment
needed for WZE. Costs have gone up due to cement shortage
as well as concrete strike. Miles is the only supplier taking
orders per Dustin. City will review per Bob.
9. Inspector's Report water trench 5/8 minus compaction test good.
Employee interviews good.
10.Environmental Compliance Report— Near 10th, make sure to empty
socks. Right across from Starbucks, make sure CB's are plugged off/not
socks. Need infiltration/concrete PH concern per Jordan.
Page 5 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11. Public Outreach — G&O contacted Argo Investments regarding
unknown conduit at street light L25 Stay tuned.
12.Submittals/Documentation
a. Review ROM — ROM uploaded last week per David
b. Submittals under review: force account equipment rates review.
Back from City today.
c. RAMs that need to be submitted: Single tap service Saddle
marked rejected
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
13. RFIs— RFI 23 response issued regarding Contractor request to shut
down of 3 street lights on west side of Duvall, north of NE 12th Street.
Temp lighting required per the Contract.
Contractor tracking changes
14. FWD/ Change Orders —
• FWD21- FH relocation at NE 10th Street— in review by City
• FWD22—Shift Filterra unit to curb at NW corner of 12th
• CO XX—for FH at 10th — HOLD for FWD
• CO XX— Supplemental RPM's/Traffic Arrows — in the works
• CO 13 —for school frontage revisions/culvert removal — in the works
• CO XX—for proof roll acceptance of pulverized HMA backfill
• CO XX—for storm revisions at MH 33 and at 12th — in the works
• CO XX - for water connection at north end and CDF removal
Page 6 of 9
G0 Y Q.r r+ +
CITY OF RENTON
� Nz°� DUVALL AVE NE
CAG-20-065
15. Subcontractor Status — all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls—
Program Nimrod N.5(Apra) Progress Payton*No 6(lam) Progress Payment No 7(J..a)
WeakE.di{O.: 9-Apr 16-Ap. 23-Apr 30-Apr 7-May 11-Mav 21-Mav 28-Nov 4Jou 11Jou 13-Jaa 25Jaz 2Jd
+.Reed Tow-kilo In-Apr 22-Ape 28-Ape 4-May 16-May 20-May 27-May 6-Jo. 7-Jun 16-Am
1 W.E.Coates W.-Apr 22-Apr No Wade 6-May No Wodc 24.Me). 31-May 3-Am 8-Jim No Work X
1 Totem Electric 25-Apr 27-Ape No Work No Work 13-May 20-May 24-May 6-Am 6-Am 16-Jon
'.PoD Logging No Wg#141 X X X No Work 13-km No Work No Work No Work X X
1 Puget Construction No Work No Work No Work No Work No Work No Work 6-Jun No Wait 6-Am No Work X
t'ICorsrctr.Srnacn 25-Apr 25-Apr 3-May No Work No Work No Work No Work No Work No Work No Work X
i&Traapostenon Systems X X 3-May 5-May 27-May 31-May 27-May No Wadc No Work X X
i',Evagreea Sov vottiog X X X 9-May No Work No Work No Wok No Work No Work No Work X
+':CaormdUp X X X 4-May 20-May No Work No Work No Work No Work X X
I'..L egacy Tapping X X X 29-Apr No Work Nowodc No Work No Wok No Work X X
3'..Lakeridge Paving X X X X 24-May No Wok No Wok No Work No Work X X
Page 7 of 9
71 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor Subcontractor is on the job site,payroll required. **(#1_7!)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed'payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
'` yu I Apprenticeship doe's required _ - - - -
-Payroll Resubmittal
No Work Received"No Work Performed payroll
15-Feb "Final'payroll
17. Progress Payment —
• Progress Payment No 7 — cutoff is June 30th. Documentation
needed by the City July 7th
18. Other Items:
Page 8 of 9
G,•f Y Q���+ +
CITY OF RENTON
6-N1° ' DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022
WZA-Feb-May 2022 kEs __
WZB&E-Mar-Aug 22,2022 BIVO Z
WZQ-Sept-Noy 74,2022 �-' 6 i -
WZF(Medians}-Nov-Jan 8,2023 T
9�` r P VJC41 —\ II 1ALOCATION _ ` 1
MEDDLE• — [NE 11.111S7
lANII
lir
N
wwrza.c
Irk
WZ 1 !`--17TH
„, ; , viki
iIr
.
C -
NEMSr N
C -_ . .W
r R z_ 1
al HE4TMn L
PR CIE r S,
LOCATION 9.
d J ,EDIJ
nitf---r-:„'-_ -1 -___ i
WATER MAIN IMPROVEMENTS
N -SCHEDULEB
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULE C
City of Renton- Duvall Ave NE, CAC 20-065
Page 9 of 9
'4 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JUNE 14, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc.
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing Abdoul Gafour, City of Renton x
Renton School District
Dustin Weller, PSE
2. Safety Report —
Traffic control issues— Short on flaggers per Phil. Talked with
Dustin/TCS to address issue.
3. Prior Meeting Minutes — Comments/Acceptance —Accepted.
4. Weekly Statement for Working Days ending June 13, 2022
Page 1 of 8
MIR CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Days Expired: 102.5
Days Remaining: 159.5
6-10-22 was an unworkable day due to weather. Discuss that sub was
on site for a half day. Please have nobody onsite on unworkable day.
Dustin has responded via email (sub was didn't receive notification on
time).
Next Monday is a non working day due to Juncteenth holiday. This not
a requirement in the WSDOT 2021 Spec however it is a City holiday.
5. Schedule Progress
Contractor's Look Ahead Schedule—
City will not be available on June 20t" per Abdoul. 10-day advanced notice
needed for connection. Tom Main will coordinate with crew once
notification. Dustin will check specs and provide official notification per
Section 7-09.3(19).
3-week look ahead may change due to 10 day notice needed per spec.
Illumination, roadway ex. (subgrade and base wrap), half street crossings
and PSE vault.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice
Any intersection closures? 72 hour notice
None identified.
PCMS Boards Required:
10 day in advance of Intersection closure
2 day in advance of driveway closure (flatwork and paving)
Expected materials that are coming out on-site—
6. Utility Coordination
a. COR Water Department—
Page 2 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• FH Pumper Port backorder status? On back order.
• Pothole data at 10" or hold for WD90 abandonment of
water main. District to let us know when they have
completed the 5 water service transfers. Still ongoing.
Phil reached out to WD 90 and is waiting for their
completion schedule. Phil will follow up with all when
schedule is available. Phil noted, less than 4 feet
horizontal distance between two mains; 6.5 feet
clearance needed to assemble due to drill motor, so
main needs to be out of the way. Pothole data not
needed since WD90 main will need to be removed.
• Water Service relocate schedule on SE corner of 12'
and Duvall —Abdoul gave 6/15 date, will take 2.5 hours.
Informed Dustin that alternating traffic control is
needed. Jordan is aware from discussion with Greg.
b. PSE Power
• Existing PSE power conduit to remain in place on the
west side of Duvall is in conflict with proposed Filterra
unit, NW corner of Duvall and 12' — Reed to pothole to
confirm if the Filterra unit can move forward to curb
line. Confirming whether ex. conduit to remain in place
near Filterra could move, with the Filterra moving to
curb. Potholing to take place after Totem takes out ex.
service cabinet. Date unknown, but told to do it ASAP.
Phil noted, power has been disconnected so Service
Cabinet can be moved now.
• PSE Power disconnect at NE 12th St was completed on
Friday 6-10-22
• Schedule for PSE JUT crossings in WZE —for PSE
inspection. Jordan has reached out to previous
Inspector. Dennis Booth wanted clarification on half
street trench. Dustin would like to do them 20th/215T but
waiting for Jordan to schedule with inspector.
Page 3 of 8
_..1"�")
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination and WSDOT Coordination
a. Conduit crossing schedule at 10th: Dustin has communicated
with Cornerstone, need it done before curbs go down (before
July).
b. WSDOT notified City of emergency repairs at Sunset/Duvall.
WSDOT to coordinate. Should be night work between June
2022 and September 2022.
c. Lumen service to Church broken. School contractor requested
fix.
8. Engineer's Report
a. Discuss Contractor idea on starting WZF early. Work in
progress.
b. Discuss status of swapping out 3 Filterra vaults that will go on
the east side of Duvall for correct plumbing. No word per
Dustin. Requested timeframe and estimate.
9. Inspector's Report Phil had MTC out for two watermain tests which
passed. Waiting for dirt to be removed from main for the wheel load
test for storm trench. All caught up on wage rate interviews.
10.Environmental Compliance Report—Jordan notified Flora that dirt piles
need to be covered and to remove sock debris. Dustin is planning to
remove piles in next day or two.
11. Public Outreach — Nothing beyond the Lumen/Church issue.
12.Submittals/Documentation
a. Review ROM —New ROM uploaded today.
b. Submittals under review: Additional info needed for force
account equipment rates review. Some discussion on equipment
Page 4 of 8
5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
rates. Dustin requested info (axles, capacity, etc.)from outdated
EquipmentWatch printout be used to establish similar rates for
their equipment. No further/additional info can be provided by
Reed.
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —All in good shape.
13. RFIs — RFI 21 and 22 issued regarding PSE to do remaining work in one
phase and schedule for power disconnect at HAWK signal.
14. FWD/ Change Orders—
• FWD X in the works for FH relocation at 10th
• CO 11 —for Multi Stem Tree Removal — City processing
• CO 12 —Sunset Blvd TC Modifications — City processing
• CO XX—for FH at 10th — HOLD for FWD
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
• CO 13—for school frontage revisions/culvert removal — in the works
• CO XX—for proof roll acceptance of pulverized HMA backfill
• CO XX—for storm revisions at MH 33 and at 12th — in the works
• CO XX - for water connection at n end and CDF removal
Page 5 of 8
Y n1111
.c
,, CITY OF RENTON
'9FN10 DUVALL AVE NE
CAG-20-065
15. Subcontractor Status — all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
16.Certified Payrolls—
Progress Payment No 5(April) Progress Payment No 6(SG,) Progress Payment No 7(Just)
n eci.l mll"e Out 9-Apr 16-Apr 23-Apr 30-Apr 7-]lay 14-May 21:May 23-M.y 4-J.. 11-Jo. 1S-Ju 25Jo 24.1
Reed Trucking _ IS-Apr 22-Apr 29-Apr d-May 16-May 20-May 27-May 6-Jun 7-Jon
W E.Coma 14-Apr 22-Apr No Work 6-May No Wok 23-May 31-May 3-le" S-Jm X
Totem Electric 23- 27-Apr No Wak No Work 13-May 20-Nay 2.1-Mo, 6-Im 6-tic
PnD Logging A X 7i X No Wmk-N.24
o Work No Work No Work X
'Puget Cooso.coco _ No Work No Wok No Work No Work No Work No Week 6-Jno No Work 6-Jon X
Concrete Services _ 23-Ayr 23-Apr 3-May No Work No Work No Work No Work No Work No Work X
Transportation Systems _ X X 3-May 5-May 27-May 31-May 27-May No Work No Wok X
Evergreen Sauntering X X X 9-Mar No Wok No Wok No Wok No Work No Work X
Gourd l'p X X X 4-May 20:May No Work No Wok No Work No Work X
Legacy Tapping X X X 29-Apr No Work No Work No Work No Work No Work X
Lakeridge Pain X X X X 24-May No Work No Wok No Work No Work X
Week Contractor/Subcontractor is on the job site,payroll required **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
{ Apprenticeship doe's required
- - - - -
Payroll Resubinittal
No Work Received"No Work Performed"payroll
15-Feb "Final'payroll
Page 6 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
17. Progress Payment—
• Progress Payment No 6— City processing
• Progress Payment No 7—cutoff is June 30th. Documentation
needed by the City July 7th
18. Other Items: Phil asked, since arms will arrive on the 27th, will Totem put
up lights in Sch. C? Totem to check.
Page 7of8
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 -,,. N----is _ (i_i
'Nork7or
WZA-Feb-May 2022
1 WZB&E-Mar-Aug 22,2022 7- kEsur„ a"VD i -
..1111111)
1 WZD-Sept-Nov 14,2022 °z -^�
WZF(Medians)-Nov-Jan 8,2023 r i
izrN ' _
st, ` 'Pi.-
i
frq
LOCATION �
IjEDULE NE 1;�`,* ST6.1
a .111 ,
iro IV - ay, _____
,-,
, N,,7,.
goo
1LN
r iNik
All
T
4
p- -Z--- NE6THSi
m
.)i '4001 1410 2 .
z
3 + I HE anE Sr `
PROJECT — - — _- —
Ss LOCATION
\icP9rr,, . I-
. n \1, i ll/ f-taf:.,
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NTOscal -SCHEDULE
OT
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
•
REEDC. Date:06/11/22-07/01122 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
June
Sched
ID Work Description SSM TWT F SS M T W T F SS M T W T F Notes/Resources
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1
Water system install X X X X
Water testing X X X X X
water tie ins X X X X
Illumination system X X X X X X X X X X X X X X X
pse install X X
Roadway ex X X X X X X X X X
Base rock X X X X X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
JUNE 7, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc.
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating x
Assoc. to Water Imp.
Ed Thompson, Representing Abdoul Gafour, City of Renton x
Renton School District
Dustin Weller, PSE
2. Safety Report—
Traffic control issues— None
3. Prior Meeting Minutes — Comments/Acceptance —Accepted
4. Weekly Statement for Working Days ending June 6, 2022
Days Expired: 98.5
Page 1 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Days Remaining: 163.5
Back on original schedule. Dustin would love to accelerate and finish
early, to get paving done, if possible.
5. Schedule Progress
Contractor's Look Ahead Schedule —
Water this week and next week. Thrust blocks next Tuesday. Totem is
doing work on 12th and illumination system. Will start
subgrade/roadway ex./prep. Week of 20th feasible for pressure
testing on Saturday.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice None
Any intersection closures? 72 hour notice None
PCMS Boards Required:
10 day in advance of Intersection closure None
2 day in advance of driveway closure (flatwork and paving)
Expected materials that are coming out on-site —
Thrust Block—Miles Concrete
6. Utility Coordination
a. COR Water Department —
• FH Pumper Port order status? No updates. They're
backordered.
• Pothole data at 10th — Hasn't happened yet. City's crew
completed all 5 water services. Watermain
abandonment forthcoming. City only installed new
meters per Abdoul. District crew will do connection from
supply line to meters.
• Water Service relocate on SE corner of 12th and Duvall —
Done by City, prior to week of 20th
Page 2 of 8
_bp0
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Flex Ring DI Pipe — Reed submitting information on this,
it is acceptable
• Discuss insert the 16-inch polypig in the north end of
the new pipe before installing the temporary end cap
and blow-off assembly and temporary blocking.
Retrieve the polypig through the vertical 16" cross to be
placed on the south end the line. Dustin's preference is
doing as discussed in last meeting. Waiting for polypig
to arrive. Set pig in pipe before end cap per Abdoul. Will
push North to South. Dustin already has a cross so
doesn't need it from City. Further discussion with
Abdoul/Phil/Dustin regarding shutting main down
during work to remove thrust block. Discussion of
restrained joint pipe not being necessary,just restrained
joint fittings.
• New hydrant can be moved 3 feet north to be out of
way of other improvements. Discussion of vertical bends
of hydrant runs.
b. PSE Power
• Existing PSE power conduit to remain in place on the
west side of Duvall is in conflict with proposed Tree
Box, NW corner of Duvall and 12' Checking on conflict.
Centered in the middle of vault. Parametrix to review if
Filterra can move east, west, or to another CB in front of
the church.
• Schedule for the disconnect service for HAWK signal at
12th and Duvall, cannot finish the removal with live
power
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination and WSDOT Coordination
a. Conduit crossing schedule at 10th: July—September
b. WSDOT notified City of emergency repairs at Sunset/Duvall.
WSDOT to coordinate. Should be night work.
Eastbound SR 900
One lane closed with traffic shifted to the opposite lane maintaining on lane in each
direction:
Sunday 8:00 p.m.to Monday 5:00 a.m.
Monday 8:00 p.m.to Tuesday 5:00 a.m.
Tuesday 8:D0 p.m.to Wednesday 5:00 a.m.
Wednesday 8:00 p.m.to Thursday 5:00 a.m.
Thursday 8:00 p.m.to Friday 5:00 a.m.
Saturday 8:00 p.m.to Sunday 8:00 a.m.
Weekend closures may be allowed with the coordination of City of Renton Traffic.
8.The number of days and/or nights the noise will occur(no changes shall be made after-
acceptance of application submittal)
WSDOT is requesting 8 non-consecutive nights.
10.The time period(include start date and end date)for which the variance is requested(no
changes shall be made after acceptance of application submittal)
Within the City of Renton,the emergency night work is estimated for 8 nights along SR 900
between MP 18.10-MP 18.12 and MP 19.83.MP 19.86. Construction window is anticipated
between the inclusive dates of June 2022 thru September 2022.
Flora Lee,PE,PTOE
Principal Civd Engineer—Project Manager/Operations Signal Engineer
8. Engineer's Report
a. Discuss Contractor idea on starting WZF early. No update.
b. Discuss status of swapping out 3 Filterra vaults that will go on
the east side of Duvall for correct plumbing. Supplier
contacted. Have not heard back.
Page 4 of 8
'4 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
9. Inspector's Report French drain near 925+00—4"perf pipe w/drain
rock coming from apartments per Phil. 2 feet(shallow) below grade.
May be damaged when grind/overlay takes place. MTC out to do
compaction testing for water trench.
10.Environmental Compliance Report— None
11. Public Outreach — None.
12.Submittals/Documentation
a. Review ROM — Updated last week.
b. Submittals under review: RAM 033B Flex Ring Joint Pipe —
additional info needed. 033C reviewed and approved. Additional
info needed for force account equipment rates review.
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted: All good.
e. Material Documentation —
13. RFIs — RFI 20 issued confirming HAWK signal pole 1 foundation
dimensions. Design per plan.
14. FWD/ Change Orders—
• FWD 20 issued water connection at north end and CDF removal
• FWD X in the works for FH relocation at 10th
Page 5 of 8
TR0
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 11 —for Multi Stem Tree Removal — City processing
• CO 12 —Sunset Blvd TC Modifications — City processing
• CO XX—for FH at 10th — HOLD for FWD
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
• CO XX—for school frontage revisions/culvert removal — in the works
• CO XX—for proof roll acceptance of pulverized HMA backfill
• CO XX—for storm revisions at MH 33 and at 12th — in the works
• CO XX - for water connection at n end and CDF removal
15. Subcontractor Status — all SOl's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
16.Certified Payrolls—
Page 6 of 8
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Progress Payment No 5(April) Pr ress Payment No 6(May)
Week Ending On: 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jan
Reed Trucking 18-Apr 22-Apr 28-Apr 4-May 16-May 20-May 27-May 6-Jun
WE.Coates 14-Apr 22-Apr No Work 6-May No Work 24-May 31-May 3-Jun X
Totem Electric 25-Apr 27-Apr No Work No Work 13-May 20=Ma• 24-May X
ND Logging No Work X X X No Work No Work X X
Puget Construction No Work No Work No Work No Work No Work No Work X X X
Concrete Services 25-Apr 25-Apr 3-May No Work No Work No Work X X X
Transportation Systems X X 3-May 5-May 27-May 31-May 27-May No Work No Work
Evergreen Sawcutting X X X 9-May No Work No Work No Work X X
Ground Up X X X 4-May 20-May No Work X X X
(Legacy Tapping X X X 29-Apr No Wok No Work No Work X X
'..Lakeridge Paving X X X X 24-May • No Wodr No Work No Work No Work
Week ContractoriSubcontractor is on the job site,payroll required **(#12)indicates payroll number**
X Subcontractor was not on-site this week "No Work Performed"payroll required-
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll ResubinittaI
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 6 — cutoff was May 31, 2022.
Documentation needed by the City today—Additional MOH is
being confirmed.
18. Other Items:
TV for storm —flash drive to Joey Wed. or Thurs.
Page 7 of 8
IR; CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 r L' 1_J
WZA-Feb-May 2022
WZB&E-Mar-Aug 22,2022 Pf6 _ Tsum a_I ~ ww
1 WZD-Sept-Nov 14,2022 r ~ —
WZF(Medians)-Nov-Jan 8,2023
ixrE�
t6.9
� � �.�E - _ -1 [ — L
LOCATION I
�� EWLE — INEL 5T i
r M — J 1 __,,,_
,„ ..,,,..41.. -,„
;N
Z I,,_,. „. T f T T T T
Ware 2aeC
••• AIIIIIIIP 1111111171. , LI%ill :.1 "liel
, -mei !m o
o - z- NE 6Rfsi N
c
R ilL;
di
HE MIST
r041 Illit i
t �plir U
ss LOCATION
t+E I / 1 • CHEDI,ILE
■ J cal u ' L 11-1:-_ 7
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO Y..ALE -SCHEDULE C
City of Renton - Duvall Ave NE, GAG 20-065
Page 8 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MAY 31, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc.
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton x
Renton School District
Dustin Weller, PSE x
2. Safety Report —
Traffic control issues— No issues.
3. Prior Meeting Minutes — Comments/Acceptance — Accepted.
4. Weekly Statement for Working Days ending May 30, 2022
Days Expired: 93.5
Page 1 of 8
O¢o
CITY OF RENTON
• DUVALL AVE NE
CAG-20-065
Days Remaining: 168.5
Memorial Day is a non-working day.
5. Schedule Progress
Contractor's Look Ahead Schedule — Finishing up storm
today/possibly tomorrow, then install watermain. Totem is working
on HAWK and illumination. Have not heard PSE confirmation of
shutting down HAWK, but it is currently shut off
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice
Any intersection closures? 72 hour notice
Intention is to keep 12' open as much as possible.
PCMS Boards Required:
10 day in advance of Intersection closure
2 day in advance of driveway closure (flatwork and paving)
Not needed now.
Expected materials that are coming out on-site — Watermain fittings
arriving today.
6. Utility Coordination
a. COR Water Department —
• FH Stortz Adaptors installed? No, pumper port is on
back order, FH's bagged. New ones are not active but
existing ones are still active.
• Pothole data at 10th — vac truck coming out this week.
• Water Service relocate on SE corner of 12th and Duvall —
Figure out next week. 2 weeks out for removing copper
from west side. Dustin asked about what to do for
thrust blocking. Abdoul informed Dustin that they would
be doing 1-2 tie-ins per day. Dustin Proposed u-cart (tiny
concrete truck on a trailer/holds one yard) instead of
Page 2 of 8
0
;75iN CITY OF RENTON
DUVALL AVE NE
CAG-20-065
bringing a truck in. Abdoul did not want the u-cart
because it does not meet spec.
Tie-ins to be installed prior to testing. Stub toward tie in
within 20'and test. Abdoul—explained reasoning based
on Sheet 58. Discussion specifically at 919+72.80. 45
degree bends blocked before water connection need to
be horizontal/vertical. Use 4x4 wedges as temp until
thrust block is cured. Need to verify existing water line
elevation & location prior to connection. Dustin Would
like to stay out of traffic for testing and deal with TC on
testing day. Abdoul will check with crew as date gets
closer. Would like his staff onsite with Contractor. Phil
has question about cross & blowoffs, also 12-inch
plug/with 12-inch main? Abdoul noted 16"pig required
per plans/details. City to check on availability of 16"
cross. Discussed that pig must be removed prior to
chlorination.
b. PSE Power
•JUT in WZE schedule—two conduit crossings — Will be
completed one at a time. Dustin Weller—needs to know
schedule.
• Disconnect service for HAWK signal at 12th and Duvall —
Dustin Weller- Working with Potelco. Will be done
shortly.
• Dustin Wright: needs to understand what he
can/cannot do as part of this work zone. Dustin Weller
to set up meeting with Dustin Wright and Dennis Booth.
Include Phil.
• Trench (do half street/west side), vault and conduit
work on west side
Page 3 of 8
•
ifaRRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination
a. Conduit crossing schedule at 10th: Ed: Cornerstone is
coordinating with Reed. Conduit will be installed prior to
flatwork.
8. Engineer's Report
a. Discuss surface restoration schedule in the different work
zones as the project progresses. There is no plant
establishment period. Dustin looking into getting landscaper
out for two center islands in front of WZB and WZC to get
them scheduled and started. Coordinating with two subs. City
not receiving citizen complaints yet. Anything that can be
done to move towards paving this year is Bob's
recommendation.
b. Discuss how to plumb the 3 Filterra vaults that will go on the
east side of Duvall. Is plumbing around the back OK per PMX
recommendation? Discussed bringing 4 inch drain
around/under sidewalk to connect. Bob wants to check with
supplier/manufacturer to see if they are willing and can fix
vaults. Dustin estimates 8-10 weeks to replace vaults, based
on original delivery of vaults. Dustin to check with Mfg. on
time frame and if any additional costs.
c. 2nd set of cut sheets for tree pits received, PMX checked
Another cut sheet sent for vault/street lights.
d. Additional existing storm pipe to be removed in lieu of CDF
where in conflict with proposed utilities or sidewalk subgrade
In the way, so it needs to move.
e. Discuss 4-inch stubs and trench drain —will Contractor furnish
or can the order be cancelled? Trench Drain has been deleted.
9. Inspector's Report
a. Material testing. Will do wheel roll for compaction for
backfill for storm.
10.Environmental Compliance Report— No update.
Page 4 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11. Public Outreach —
Verbal outreach to businesses for —15 min dwy closures — nothing new.
12.Submittals/Documentation
a. Review ROM — updated ROM on CMS this morning.
b. Submittals under review: all are returned.
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — G&O to review if any certs are missing
for Progress Payment.
13. RFIs —
14. FWD/ Change Orders—
• FWD 19 issued for School Frontage Revisions
• FWD No 18 issued for storm revisions at NE 12th Street
• FWD X in the works for FH relocation at 10th
• CO 11 —for Multi Stem Tree Removal — City processing
• CO 12 — Sunset Blvd TC Modifications — City processing
• CO XX—for FH at 10th — HOLD for FWD
• CO XX—Supplemental RPM's/Traffic Arrows — in the works
• CO XX—for school frontage revisions/culvert removal — in the works
• CO XX—for proof roll acceptance of pulverized HMA backfill
• CO XX—for storm revisions at MH 33 and at 12th — in the works
Page 5 of 8
, o .
+
CITY OF RENTON
,pE � DUVALL AVE NE
CAG-20-065
15. Subcontractor Status — all SOI's are received
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction,Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls —
Page 6 of 8
+
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Progress Payment No 5(AFril) Progress Payment No 6(May)
Week Ending On: 4-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 29-May
Reed Trucking 18-Apr 22-Apr 28-Apr 4-May 16-May 20-May
W.E-Coates 14-Apr 22-Apr No Work 6 May No Work 24-May X X
Totem Electric 25-Apr 27-Apr No Work No Work 13-May 20-May 24-May X
PnEtLogging No Work, X X X No Work No Work X
Puget Construction No Work No Work No Work X No Work No Work X X
Concrete Services 25-Apr 25-Apr 3-May No Work No Work No Work X X
Transportation Systems X X 3-May 5-May X
Evergreen Sawcutting X X X 9-May No Work No Work No Work X
Ground Up X X X 4-May 20-May No Work X X
Legacy Tapping X X X 29-Apr No Work No Work No Work X
Lakeridge Paving X X X X 24-May No Work No Work X
Week Contractor/Subcontractor is on the job site,payroll required- **(#12)indicates payroll number**
X Subcontractor was not on-site this week. 'No Work Performed"payroll required-
15-Feb Date certified payroll was recieved
MICorrections to payroll required
Apprenticeship dot's required
-
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final'payroll
17. Progress Payment —
• Progress Payment No 6—cutoff is May 31, 2022. Documentation
needed by the City on June 7—
18. Other Items:
• Phil asked is Abdoul would be setting up onsite meeting. Abdoul
had left the meeting, Flora will follow up with Abdoul. Dustin
noted he is clear on all water main issues.
• Bob stated that if the current project budget allows for payment of
Change Orders, prior to being fully executed, Flora should notify
Tani so that payment can be included in the Progress Payment.
Page 7 of 8
,,
RI CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 L)
et. -LI.,
WZA-Feb-May 2022
1 WZB&E-Mar-Aug 22,2022 �`' 4* ®tNb 2 -; 4aom.Z«m0
WZD-Sept-Nov 14,2022 - �° y
WZF(Medians)-Nov-Jan 8,2023 ' j — �__
V i N 12111 7 .._I_
N P'OJE - : t
---s,. Kill Tipp
LOCATION ____14. i r
Kyr _____ . ,
i$ '!
NE Gni sr
. ,:' %Idle ''.--
....,./ye. '',. ifilk 3
1 lowLj NE.sT
PROJECT -- _' _E-.� �_._._,
kfir A
LOCApITJION
E L J
1 •_rT t (t1 Fa -. -1--
WATER MAIN IMPROVEMENTS
N -SalEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MAY 24, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc.
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer-Rogstad, x Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & x Tom Main, City of Renton relating x
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District x
2. Safety Report —
Traffic control issues— Patching and paving at WZC to happen before
this weekend.
3. Prior Meeting Minutes — Comments/Acceptance — Accepted.
4. Weekly Statement for Working Days ending May 23, 2022
Days Expired: 89.5
Page 1 of 7
mA CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Days Remaining: 172.5
Memorial Day next Monday is a non-working day.
5. Schedule Progress
Contractor's Look Ahead Schedule—
Continuing on storm...Totem will get started next Tuesday with
illumination and HAWK Signal, then onto water main installation.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice
Any intersection closures? 72 hour notice
No closures needed at this time
PCMS Boards Required:
10 day in advance of Intersection closure
2 day in advance of driveway closure (flatwork and paving)
Expected materials that are coming out on-site — None
6. Utility Coordination
a. COR Water Department—
• FH Stortz Adaptors installed? Not yet.
• Pothole data at 10th — not yet.
• City Water Dept to furnish and install three irrigation
meters and setters for the irrigation system, schedule
TBD Dustin will have update shortly.
1. W21005898- 1" setter 830 Duvall Ave NE
2. W21005900- 1" Drop in Irrigation Meter 830
Duvall Ave NE
3. W21005901- 1" setter 920 Duvall Ave NE
4. W21005902- 1" Drop in Irrigation Meter 920
Duvall Ave NE
5. W21005907- 1" setter 1060 Duvall Ave NE
6. W21005908- 1" Drop in Irrigation Meter 1060
Duvall Ave NE
Page 2 of 7
;R CITY OF RENTON
DUVALL AVE NE
CAG-20-065
City must call for locate themselves per Abdoul. City
forces to install meter and Reed to install double
check valves. If median strip is roughly graded,
meter boxes can usually set at right elevation. Dustin
says that'll be November on Schedule if no issues
b. PSE Power Undergrounding WZE —Just two crossings and vault
and intersect work near 12th. Dustin to coordinate with Daniel
Aguirre from PSE. Tani to invite PSE to future Meetings.
7. RSD Elementary School 16 Coordination
a. Gas crossing status: Completed
b. Conduit crossing schedule at 10t": Work in progress. Ed to
make sure School's Contractor coordinates with Reed so that
conduits are installed prior to flatwork.
Still waiting on wetland agreement approval from City.
8. Engineer's Report
a. Mandrel and TV inspection only on 24-inch storm pipe
b. Discuss set up for CDF placement in storm pipe to be
abandoned — Dustin...typically grout in a blowoff at each end
and pump it from one end to the other. Reed to submit a
flowable CDF. CDF to be placed prior to curb placement, so
within next month.
c. Discuss surface restoration in the different work zones as the
project progresses. There is no plant establishment period.
Conduit is stubbed under driveway at WZA. Dustin believes
conduit work is done and ready for surface restoration. Dustin
to work on coordinating with landscapers. More conduit to put
in on WZA per Phil. All conduit work is done in WZB and WZC.
d. Pothole data received from Reed on 5/19/22 - Minor revisions
to storm pipe slopes to clear existing water pipe at Sta 920+87
e. Water service for driveway @ 916+95 RT
f. Cut sheets for tree pits received today—Parametrix
Page 3 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
9. Inspector's Report
g. Material testing. Compaction testing is not passing on the
asphalt planning/pulverized HMA. Tani has sent email to MTC
to see if that proctor is bad. Proof roll for compaction on
recycled HMA backfill acceptable.
h. 3 tree boxes built incorrectly on east side with orifices on right
hand side rather than left hand side per Dustin. Discussed
options of sending back to manufacturer, putting on other side
of catch basin, tying into storm main, or boring into side.
Parametrix to look at options.
i. Water meter for property on SE corner...need to find a way to
tap in. Currently tapped off 8 inch main. Abdoul's crew will tap
to 16 inch main. Parametrix to verify if utility easement
exists...if not, Abdoul will find a location within ROW.
j. Notification to school went well...less kids trying to cross.
k. Wage rates up to date.
I. No complaints from Albertson's and Starbucks.
m. Tree fell in windstorm. Potential conflict with contractor ditch
work. Dustin to send price for hauling away.
n. Can we make multiple tree cut a bit better?Dustin will look for
opportunities to whittle away.
10.Environmental Compliance Report - All looked good on Ross's
Sunday visit...some silt fence issue that Jordan will send communication
about.
11. Public Outreach -
Verbal outreach to businesses for -15 min dwy closures -
12.Submittals/Documentation
a. Review ROM -
b. Submittals under review: RAM 49B Stoneway concrete for
foundations-G&O to review.
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. RAMs that need to be submitted: CDF.
d. Non-Material Submittals that need to be submitted: None
e. Material Documentation —
13. RFIs — none
14. FWD/ Change Orders —
• FWD X in the works for School Frontage Revisions
• FWD No 17 send out for Storm Revisions MH 33 to CB 31
• FWD X in the works for FH relocation at 10th
• CO11 —for Multi Stem Tree Removal — signed by Reed, PMX & G&O
• CO 12 —Sunset Blvd TC Modifications —signed by Reed, PMX & G&O
• CO XX—for FH at 10th —HOLD for FWD
• CO XX— Supplemental RPM's and Traffic Arrows — in the works
• CO XX—for school district revisions/culvert removal — in the works
15. Subcontractor Status — all SOl's are received
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company, LLC $706,900.00
5. Stripe Rite, Inc. $42,778.60
6. C&P Fencing $2,177.70
Page 5 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. W.E. Coates $61,500.00
8. Legacy Tapping, Inc. $20,150.00
9. PnD Logging $10,000_00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transporation Systems, Inc $48,110.00
13. Evergreen Concrete Cutting, Inc $3,000.00
16.Certified Payrolls—
G&O to send updated payroll tracking sheet. Payrolls for
Transportation Systems and Lakeridge Paving.
Week Contractor!Subcontractor is on the job site,payroll required_ **(=12)indicates payroll number**
X Subcontractor was not on-site this week. 'No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment —
• Progress Payment No 6— cutoff is May 31, 2022. Documentation
needed by the City on June 7— a few are missing.
18. Other Items:
Totem ready to work on HAWK. Dustin asked if power could be turned off while
they perform their work. If crossing is closed, can turn off HAWK per Bob.
Dustin to give PSE call to shut off power to transformer.
Page 6 of 7
5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
June 27t"for pole arms from Totem. Totem will have all other items at that time
to begin street light installation.
Water meter box at approx. STA 919+30 RT appears to be out of ROW. Cindy to
look into it. Bob concerned about encroachment onto private property, but
Abdoul not worried.
WZC-Jan-May 2022
WZA-Feb-May 2022 -WZB&E-Mar-Aug 22,2022 k-f _kw) i -
I WZD-Sept-Nov 14,2022 --7 ��\
WZF(Medians)-Nov-Jan S.2023 ' _ `jil _
Ilk f , N izTM sr E 1
f till p•.,E ' - 7.-
t LOCATION r
Ria MEDIAE• NE 1 ST E
r4cl1,1 a 1
4 pillAPI
I!'
__
-A illl 2
MB ,.,ph mom
%d
; ., 4,d.
F" '
1 _ NE 6TH ST N
W
flia) a 0
a 1 a
NE LHH ST `
PR•JE `F _ __
ssoss LOCATION
i
HE AEA
7
II ►.uu Oil 1
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TOSC4E -SCHEDULEC
City of Renton- Duvall Ave NE, CAG 20-065
Page 7 of 7
REEDC. Date:05/22/22-06/11/22 3 Week Look-Ahead Schedule
TRUCIONG&EXCAVA77A/G Name: Duvall Avenue
May
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/Resources
21 22 23 34 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
Storm system X X X X X
Illumination X X X X X X X X X
PSE Underground X X X X X
Water X X X X X X X X X
_Holiday _ —_
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MAY 17, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc.
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District _
Michael Sippo, City of Yong Qui, City of Renton
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & x Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing x Abdoul Gafour, City of Renton x
Renton School District
2. Safety Report—
Traffic control issues—split phase at Sunset Signal — No issues. There is
a call in to the School regarding pedestrian traffic and pedestrians
following the detour.
3. Prior Meeting Minutes — Comments/Acceptance —Accepted.
Page 1 of 8
Pt
i
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending May 16, 2022
Days Expired: 84.5
Days Remaining: 177.5
5. Schedule Progress
Contractor's Look Ahead Schedule— Dustin to forward Look Ahead
Schedule by end of day.
Storm installation for next two weeks along with Illumination. Start
water sytem after storm.
Notifications to Public Required:
Any lengthy driveway closures? 72 hour notice small closures - half
width (trenching)
Any intersection closures? 72 hour notice small closures - half street
for 12th (trenching)
PCMS Boards Required:
PCMS boards were removed after lane shift/signal mod for WZE
Notification needed for driveway closure (flatwork and paving) — 2
days in advance. Half at a time
Expected materials that are coming out on-site— None.
6. Utility Coordination
a. COR Water Department —
i. FH stub testing. Per Phil - wrong threads on hydrants
which will need to be replaced. Storz Adapters ok.
City requested Pothole on north side of 10th to confirm
horizontal and vertical distance between district and
City owned systems. City suggested Reed check with
legacy tapping on for tapping clearance. Reed will have
Vactor truck onsite tomorrow.
Page 2 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. PSE Power Undergrounding WZE —Jordan researching power
on that side...may add to schedule next week.
7. RSD Elementary School 16 Coordination
a. Water crossing work update: complete within ROW
b. Gas crossing schedule: happening now
c. Conduit crossing schedule at 10th: Work to be done
d. Site work: Started Clearing Site, logging and importing
material. Activities slow due to weather.
8. Engineer's Report
a. Storm Revisions at MH 33 and between CB 32 and CB 31
b. Recycled PZB may be used per the WSDOT Specs (recycled
concrete). Reed's preference is to use recycled concrete for
PZB. Abdoul is ok with this, would rather not do a CO for
change in material (for future projects Abdoul will look into
drafting spec for sand or crushed aggregate for PZB).
c. Discuss surface restoration in the different work zones as the
project progresses. Dustin assumes the surface restoration
will be performed at end of project, but will verify with
landscapers. Add hydroseed in the interim? Will surface
restoration sit uncompleted? Dustin will reach out to the
landscapers to see if he can make something happen.
9. Inspector's Report
a. Material testing — Waiting to get more storm in before MTC out
to test pulverized asphalt in trench. Wage interviews is caught up.
Good on concrete breaks
10.Environmental Compliance Report — Ross —looked good on
Sunday...will go back out on Wednesday when rain comes back. Did
Reed see any issues after Sunday's rain? No issues, road is pulverized
and soaks up rain.
Page 3 of 8
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11. Public Outreach —
Verbal outreach to businesses for —15 min dwy closures — Reed to do
Email outreach to Church - G&O completed—no issues yet. Do have two
evening services after work hours and Sunday service.
Email outreach to Hazen HS in the works re ped detour— G&O sent out
ped detour map
12.Submittals/Documentation
a. Review ROM — none. Updated ROM is on CMS
b. Submittals under review:
c. RAMs that need to be submitted: Will Totem use Stoneway
concrete for foundations? If so provide concrete submittal (RAM
049 resubmittal)
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — looking good
13. RFIs — none outstanding
14. FWD/ Change Orders —
• FWD No 16—Signal Modification Assistance sent out last week
• FWD X in the works for School Frontage Revisions
• FWD No 17 in the works for Storm Revisions MH 33 to CB 31
• FWD X in the works for FH relocation at 10t". Need pothole data to
issue FWD.
• CO XX —for FH at 10th Waiting for pothole data
• CO XX— Supplemental RPM's and Traffic Arrows — in the works
Page 4 of 8
..01"N O .
* Q ± i+
CITY OF RENTON
‘4
''z° DUVALL AVE NE
CAG-20-065
• CO XX —for school district revisions and culvert removal — in the
works
• CO XX — for Multi Stem Tree Removal — draft sent to City for review
• CO XX— Sunset Blvd TC Modifications — draft sent to City for review
15. Subcontractor Status — all SOI's are received
REQUEST
NO. SUBCONTRACTOR AMOUNT
1. Ground Up Road Construction, Inc. $25,575.00
2. Green City, Inc. $139,480.00
3. Totem Electric of Tacoma, Inc. $734,636.80
3a. Integrity Networks(Lower Tier) $22,432.15
4. Lakeridge Paving Company,LLC $706,900.00
5. Stripe Rite,Inc. $42,778.60
6. C&P Fencing $2,177.70
7. W.E. Coates $61,500.00
8. Legacy Tapping,Inc. $20,150.00
9. PnD Logging $10,000.00
10. Concrete Services $192,934.00
11. Puget Construction Services, Inc. $15,000.00
12. Transportation Systems,Inc $48,110.00
13. Evergreen Concrete Cutting,Inc $3,000.00
16.Certified Payrolls—
Reed Trucking _ _ 18-Apr 22-Apr 28-Apr 4-May
W.E. Coates 14-Apr 22-Apr No Work 6-May X
Totem Electric 25-Apr 27-Apr No Work No Work
PnD Logging No Work X X X X
Puget Construction No Work No Work No Work X X
Page 5 of 8
s
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Concrete Services 25-Apr 25-Apr 3-May No Work X
Transportation Systems X X 3-May 5-May
Evergreen Sawcutting X X X 9-May No Work
Ground Up X X X 4-May
Legacy Tapping X X X 29-Apr X
Lakeridge Paving X X X X
Week Contractor/Subcontractor is on the job site,payroll required. **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required
- - - -
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final'payroll
17. Progress Payment —
• Progress Payment No 6 — cutoff is May 27, 2022. Documentation
needed by the City on June 1
18. Other Items: Phil asked Abdoul.... talked with Tom main. Potholed water
service to Starbucks. Comes over 24 inch and was in CDF. Abdoul doesn't
want CDF over copper piping. Use typical backfill for service.
Page 6 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
STA 926+78.0, 40.1'L(3 Mk
4'x4' OFFLINE TBBU �-/ (11
cCB#32 EX felg33 00
927+0Q
Page 7 of 8
ifeCITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC-Jan-May 2022 U _I
q-
WZA-Feb-May 2022 Y..YV�
WZ5&E-Mar-Aug 22,2022 }- MEs OLV0 i-j -
WZD-Set-Nov 14,2022 z° �r _qs.L: r.:
WZF 1 : ,,,I.
(Medians)-Nov-Jan 8,2023 r -_Y 1
p /141
• NE lYfll . _ ! r.JEZ�` — L L�� CATIONI Iy- � hEDUIE A NE 1 I
III glIl
, 414go
. ..,,,,.
,)
Mlm�2ms C
-,ii 1
l �i ern
,,,iiir ridiaLlillik Ali
a—
a i NE ERi Sr .0
0 a < 1.
e
TL _ ! F1 L
HE aH si ► S
PROJECT
----- -hr — _/Apr LOCATION
....„
�E I
lir
Lfi.,, _
WATER MAIN IMPROVEMENTS
N -SCHEDULE&
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT 105Cb1E -SCHEDULE
City of Renton- Duvall Ave NE, CAG 20-065
Page 8 of 8
REEDC. Date:05/14/22-06/03/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATWG Name: Duvall Avenue
May
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/Resources
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
Storm system X X X X X X X X X X
Illuminrtion X X X X X
PSE Underground X
Water X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MAY 10, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan Widener, Widener & Assoc. X
& Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc. X
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Ross Widener, Widener & Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing X Abdoul Gafour, City of Renton
Renton School District X
2. Safety Report —
Traffic control issues Phil—2 spotters at 12th per TCP...has seen kids
disobey the detour...crossing over at driveway further north. When it's
applicable...let them cross where they normally cross instead? Will be
moot issue when more SW is removed.
Any changes to channelization at Sunset/Duvall? — City looking at
splitting NB and SB phase for traffic and adding a green left turn arrow
below westerly circular red on SE corner mast arm for NB approach.
Page 1 of 8
;A CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Tani- does the traffic lane need to shift? Leave temp traffic
channelization as is. Phil...traffic seems to be flowing well.
No Left Turn sign at Church Driveway—installed.
Ped Detour OK? Dustin hasn't heard of issues....kids were using the
detour. No wheelchairs that he's seen. Flora— use plywood on gravel if
WC needs to be included. But would a WC even get there...through the
woods? Flora — City is considering providing WC access at this crossing.
Ed recommends contacting the HS to see if WC/ADA compliancy is
needed. Flora will look into it. Is it doable to add plywood?Dustin
concerned about WC's being caught in elevation differentials. Phil
suggested possibly using non-skid sheets for rent. Does the City want
the plywood ramp to be in place over night? Flora to confirm.
3. Prior Meeting Minutes—Comments/Acceptance — No comments;
accepted.
4. Weekly Statement for Working Days ending May 9, 2022
Days Expired: 79.5
Days Remaining: 182.5
5. Schedule Progress
Contractor's Look Ahead Schedule-
REED�' 3 Week l01
Date:05/07/22-05/27/22
TRUCKING 6 EXCAVATING Name: Duvall Avenue
NeY
ache
ID Work Description SSMTWT FSSM T W T F SS M T W T F
7 9 9 10 11 12 13 14 15 19 17 IC 19 20 21 22 23 24 25 29 27
Form and pour walls X X X X X
nlurr2r lion X X X X X
high vis fence X
demo X X
,lam x x x x x x x x x x x x x
Storm upcoming...driveway closures for Church, Albertsons and
Starbucks upcoming....need notifications. Dustin: Starbucks will be
Thurs/Friday, will maintain one lane. Monday— Wed—other
Page 2 of 8
IN
F CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Albertson's driveway. Back driveway is delivery use only but
notification needed. Church appears to not have activity during
week. Phil wants pastor contact info — Ed to pass contact info on. Ed
was told Church is used 5x per week. Some weekdays/some weekend
days. Must be off hours use?Ed will send church manager info to
Tani. Per Dustin...church driveway is at least a week out (it's south of
12rh). Ed—perhaps used gated driveway in back as alternate access?
Notifications to Public Required:
Any driveway closures? 72 hour notice See above.
Any intersection closures? 72 hour notice
PCMS Boards Required:
Notification needed for driveway closure— 2 days in advance. Can
utilize for dwy closures but currently utilized for no left turn....just put
the driveway closure info on the PCMS board at Sunset.
Will board stay up during detour?
Expected materials that are coming out on-site — Planing tailings for
trench backfill. Ex structure 33...lots of verbiage about providing
things...but no information for them to work with. Adjust ex structure
MH 33...partial replacement. Dustin needs more info...starting CB 32
first and proceeding south. 4'48 inch section with knockout(s) and
flat top...can get...shop drawings really needed? Dustin will know
more info after potholing. Dustin to send his idea for review.
6. Utility Coordination
a. COR Water Department—
i. FH stub testing. City has received satisfactory purity test
results. Pressure test to follow.
b. PSE Power Undergrounding WZE —
Page 3 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination
a. Water crossing work update: Ed: completed by Contractor.
City doing tie-ins today. Patching back today.
b. Gas crossing schedule: Rescheduled...waiting for new date,
within next 2 weeks. Dustin received call and ok'd request to
perform work on Monday (5/9) however PSE didn't show.
c. Conduit crossing schedule at lath: TBD once electrical
contractor is out on site.
8. Engineer's Report
a. Planing Tailings may be used for trench backfill and Mixed
with CSTC per spec. MTC has picked up sample for testing.
Dustin doesn't forsee enough tailings available for use as
CSTC. Abdoul needs to see approval for water main
trench..does not believe it meet spec for watermain backfill
(20% asphalt max)—do not use for water trench —it will
corrode the pipe. Abdoul says native is not suitable...use
import for gravel borrow. Tani says it can be used under
Section 5-04 for backfill (doesn't say which)...use for storm,
but not water. Abdoul says bid item for trench backfill is
import. Recycled asphalt is not considered import. Bedding
will cover top 6 inches of pipe...can use recycled concrete
above bedding? But do not use native for bedding. MTC says
planing tailings are water sensitive for backfill...may be
getting high water content....can use nuclear gauge to test
compaction.
b. Existing ROW or Perm Easement Sta and Offsets requested
from PMX. —not needed clearing offsets received.
c. Station/offset received for clearing limits in WZE for field
check. Phil—all good.
Page 4 of 8
;-AN CITY OF RENTON
DUVALL AVE NE
CAG-20-065
9. Inspector's Report
a. Material testing — completed to date.
b. Wage Interviews — last one was Lakeridge paving...all caught up.
Subs all covered(except landscape and chann)? Phil will double
check.
10.Environmental Compliance Report— Jordan has performed site
inspection. The silt fence north of 9th on the east side starting to fall
down. Please put back up. Please pick up chunks of concrete at fire
hydrant installations. Rain predicted for Thursday....be ready.
11. Public Outreach — Driveway closures. Flora received complaint at
10th...cars directed to her plat. Cannot sleep at night...not sure of her
plat.
12.Su bmitta is/Documentation
a. Review ROM — uploaded to CMS
b. Submittals under review: None.
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
• For hydrants installed for WD 90/tie-ins, need Cert. of
Compliance for gaskets, mega lugs, and field lock gaskets.
Certs for One lock and fast grip reviewing with City.
13. RFIs — RFI 19 response regarding L9 and L11 was sent out last week
Sent out.
Page 5 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
14. FWD/ Change Orders-
• FWD No 13 sent last week - More Channelization Devises and
Construction Signs
• FWD No 14 sent last week - FH shift at Sta 901+25 LT. Will be
included in a CO.
• FWD No 15 sent last week - Multi-Stem Tree Removal WZB. Will be
included in a CO.
• FWD X in the works for School Frontage Revisions
• FWD X in the works for FH relocation at 10th
• FWD X in the works for natural or native PZB for water pipe
• CO XX-for FH at 10th and natural PZB
• CO XX - Supplemental RPM's and Traffic Arrows - in the works
• CO XX-for school district revisions and culvert removal - in the
works
• CO XX -for Multi Stem Tree Removal - in the works
• CO XX-for Added Chan Devices and Construction Signs - in the
works
15. Subcontractor Status - all looks good.
Original Ccnttact Amount(w'o tax): S5,t69,69750 Date of intent
PERCENT OF TOTAL CONTRACT Request To Pay
REQUEST THIS PREVIOUS SUBLET Reed to Sublet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ground Up Road Construction,Inc. S25,575.00 0.49% 0.00% 0.49% 8/11/2021 8'12'2021 N 8.272021
2. Green City,Inc. S139,480.00 2.70% 0.49% 3.19% 8111'2021 8'12.'2021 Y 8131/2021
3. Totem E ectric of Tacoma,Inc. S734,636.80 14.21% 3.19% 17.39% 8/12,2021 8/12.2021 N 817/2021
3a. Integrity Networks(Lower Titer) 522,432.15 a 3.05% 0 00% 3.059E 12/152021 12;15,2021 N 8131,2021
4_ Luketidge Paving Company,LLC S706,900 00 13.67% 17 39% 31 07% 8116'2021 8117.'2021 N 8/30;2021 _
5. Stripe Rite,Inc. S42.778.60 0.83% 31.07% 31.89%81161021 8'17.2021 N 8/24/2021
6. C&PFen®g $2,177.70 0.04% 31.89% 31.94% 8.202021 8.'23:2021 N 8.'262021
77_ W_E.Coates S61,500.00 1 19% 31.94% 33.13%12/152021 12 152021 F 11;152021
8. Legacy Tapping,Inc. S20,150.00 039°. 33.13% 33 52% 1/27/2022 1/272022 N L27:2022
9. PnD Logging S10,000.00 0.19% 33.52% 33.71% 2'16/2022 21177.12022 N 2/16;2022
10. Concrete Services $192,934.00 3.73% 33.71% 37.44% 3'17,2022 3/17'2022 N 3.'232022
11. Puget Construction Services,Inc. $15,000.00 0.29% 37 44% 37.73% 3/18;2022 3/18'2022 N 41122022
12. Transporation Systems,Inc 548,110 00 0 93% 37 73% 38.66% 3.21,2022 3.2112022 N 3/18/2022
13. Evergreen Concrete fig.Inc 33,000.00 0.06% 38.66% 38.72% 4/15'2022 4/15.'2022 N 4115/2022
14. 0.00% 38.72% 38.72%
15. 0.00% 38.72% 38.72%
Page 6 of 8
o
• CITY OF RENTON
DUVALL AVE NE
CAG-20-065
16.Certified Payrolls-
- Progress Payment No 5(A Progress Pavmeat No 6(May)
Week Ending Oo: 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 29-May d-Joa
Reed Trucking 1S-Apr 22-Apr 25-Apr 4-May
W.E.Coates 14-Apr 22-Apr No Work X X
Totem Electric 25- 27-Apr No Work No Work X
ND Logging l X X X X X X X X
Puget Construction No Work No Work No Work X X
Concrete Services 25-Apr 25-Apr 3-May No Work X
Transportation Systems X X 3-May 5-May
Evergreen Sawcuttiogg X X X X
Ground lip X X X 4-May X _
Legacy Tapping X X X 29-Apr X
Lakeridge Paving X X X X
Week Contractor/Subcontractor is on the job site,payroll required- **(=12)indicates payroll number**
X Subcontractor was not on-site this week "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship dot's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 5 —submitted to City.
• Progress Payment No 6—cutoff is May 31, 2022. Documentation
needed by the City on June 1 (not feasible) or June 16. Change to
May 27t". Abdoul just needs a courtesy copy.
• Need to move the quantities shown in item B4 Select Imported
Trench Backfill to A27 Gravel Borrow, for material used to fill the
void for the WD 90 pipe removal.
• Corrections needed on BI B11 and BI 12 for cut and cap District
Line, should have been paid as 2 EA under B12 Cut and Cap Exist
Water Line. Abdoul is okay with holding off on making the
adjustments on the Progress Payment, to avoid negative sales tax.
Will be flagged for future payment.
18. Other Items: none.
Page 7 of 8
„.„,R
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
WZC Jan May 2022 1/4 __, ___, �U�
WZA-Feb-May 2022 _
WZB&E-Mar-Aug 22,2022 } MEs one Z J _-- Vidati,Za,,..
WZD-Sept-Nov 14,2022 / i
WZF(Medians)-Nov-Jan 8,204 N.r.l. iiir23 / ' —
l off �1( [ -
N 12TM
µS.- PROJE • -
LOCATION
SCHEDULE '— (7NE1 ST I E
I=
-ir
r �► IN,�
i j _ IL T C
Z I Want C
Al171041.11—
q 'Kiwi 7TH
z g
W
lir
t
lik - _ NE NE STH ST N
0 L t y
f
,,..)/Pri ,—0:41 , 0
li i
f 1 NE.4TH ST E O
r Atto._
PR Ed- -
—
s
LOCATION
CHEDUEE J 4
. 1
,4 !11 i , __ --
WATER MAIN IMPROVEMENTS
rN -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
City of Renton - Duvall Ave NE, CAG 20-065
Page 8 of 8
•
REEDC. Date:05/07/22-05/27122 3 Week Look-Ahead Schedule
TRUCKING£EXCAVATING Name: Duvall Avenue
May
Sched
ID Work Description SSM T W T F SS M T W T F SS M T W T F Notes/Resources
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Form and pour walls X X X X X
Illumination X X X X X
high vis fence X
demo X X
Storm X X X X X X X X X X X X X
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MAY 03, 2022
Comments made during the Meeting are shown in italics.
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan Widener, Widener & Assoc.
& Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric X Dmitri Suslikov, Parametrix Inc. X
Ross Widener, Widener & X Tom Main, City of Renton relating
Assoc. to Water Imp.
Ed Thompson, Representing X Abdoul Gafour, City of Renton
Renton School District X
2. Safety Report — Traffic control issues: Supplier is unable to deliver
PCMS boards to project today. Additional paddles are need for flaggers.
3. Prior Meeting Minutes — Comments/Acceptance — minutes are
accepted
4. Weekly Statement for Working Days ending May 2, 2022
Days Expired: 75
Page 1 of 7
5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Days Remaining: 187
5. Schedule Progress
Contractor's Look Ahead Schedule — Reed noted two more pours to
complete walls in current Work Zone.
Notifications to Public Required: Any driveway closures? Dustin
would like to close the driveways to Albertson's and Starbucks.
Discussed using pulverized material at driveways. City is ok with use
of grindings, which may have 4"-5"chunks, at the driveways. 72 hour
notice for temporary driveway closure required,follow the Contract
Provisions. Flaggers required for driveway closures. Temporary
Intersection closure at 12th St will require notifications per the
Contract Provisions. City to prepare internal notification by
Wednesday for Monday's report—if possible the City would like to
provide as much notice for internal report/lane closure notifications.
PCMS Boards Required: Notification needed for driveway closure —2
days in advance. City will required use of PCMS boards when closing
2 lanes (it was noted last week that boards would not be required for
single lane closures). PCMS boards are needed on Monday the 9th for
storm work. City may have boards available if Reed has issues with
getting boards. Dustin doesn't anticipate issues have boards onsite
tomorrow.
Expected materials that are coming out on-site— HMA,fire hydrants
and stockpiled 20'sticks of HP pipe will be swapped out for 13'sticks.
Due to cold weather, 20'sticks are not rebounding/straightening
when released from straps (pipe is bowed and bent).
6. Utility Coordination
a. COR Water Department—
i. FH stub testing. Dustin noted the City requirements,for
FH installation, that have been relayed to him: swab,
construct and install, chlorinate, bake, do purity test,
Page 2 of 7
75 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
and then a visual inspection for leaks. Backfill cannot be
done until all of this is completed—approx. a week
duration. Phil noted that the 16"main has 65 psi at this
location, based on readings during tapping. On other
City projects Contractor has been allowed to backfill to
spring line—Phil to revisit this issue with Tom Main.
Abdoul stated that Reed could connect to the main,
swab the spool,flush hydrant, then do purity sample.
Then do visual test for leakage at the bonnet/flange.
Backfill of trench is ok.
ii. FH at 10th. City checking with WD90 if water main at
10th is or will be abandoned. Placing FH on other side of
10th will require 40ft of pipe and wall. City noted field
lock gaskets are not an option. Since there is an issue
with shackle rod availability, City is ok with use of
megalugs with repair sleeves.
iii. FH bedding - use suitable native of natural CSTC.
b. PSE Power Undergrounding WZE — No PSE rep at meeting.
7. RSD Elementary School 16 Coordination
a. Water crossing work update: in purity test now, City to
perform tie in next week.
b. Gas crossing schedule: will receive 24-48 hour notification
when scheduled.
c. Conduit crossing schedule at 10th: no schedule update.
Electrician is not on site yet.
S. Engineer's Report
a. Reed to Provide invoice support for cement concrete price
adjustment once per month. Reed noted next pours are a
few months out, will look at pricing at that time.
b. Discuss proposed road closure at 12th. Reed will pulverize
and grade with pulverized material—no road closure at 12th
Page 3 of 7
0
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Discuss requirements for ped crossing at 10th and 12th. Keep
ped crossing at 10th. Reed will assist pedestrians at 12th (to
follow detour, not cross at 12th). Reed ask what's the last day
of school-June 17th
d. Temp HMA — EZ Street allowed for travel lanes
9. Inspector's Report
a. Material testing — MTC onsite for HMA compaction testing. Dustin
asked if MTC could pick up sample of planing tailings for use in
Trench Backfill. Special Provisions 5-04.3(14)states tailings can be
used for Trench Backfill. G&O & City to discuss use of tailings for
backfill.
b. Wage Interviews — Lakeridge interviews complete.
c. Phil will not be onsite tomorrow. Construction activities are
stripping forms on walls. Tom Main will be onsite to observe
water main improvements. City will ask Tom to complete IDR in
Phil's absence.
10.Environmental Compliance Report—
Environmental review has been performed by Jordan Widener. Care
with concrete pours and monitor pH levels.
11. Public Outreach — City has updated Project Website. Notifications sent
to emergency services, school and Metro for temp closure at 9tn
12.Submittals/Documentation
a. Review ROM —posted on CMS dated 4/26.
b. Submittals under review: Ped TCP and 12th Closure Detour
submittal. Per above discussion, G&O will strike the road closure
components and forward to the City for review.
c. RAMs that need to be submitted:
Page 4 of 7
Ample
;F CITY OF RENTON
DUVALL AVE NE
CAG-20-065
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
• For hydrants installed for WD 90/tie-ins, need Cert. of
Compliance for gaskets, mega lugs, and field lock gaskets.
Comments have been sent to Reed via email—CMOs
provide do not contain quantity or specification being
affirmed. Note, Cert. of Material Origin (CMO) on WSDOT
form 350-109 is not required for this project. Cert. of
Compliance shall include product name, mfg., quantity,
specification being affirmed and provide supporting
documentation (any test results during mfr/fabrication).
13. RFIs —
14. FWD/ Change Orders—
• FWD X in the works for School Frontage Revisions
• FWD X in the works for FH relocation at 10th
• FWD X in the works for natural or native PZB for water pipe
• CO XX—for FH at 10th and natural PZB
• CO XX—Supplemental RPM's and Traffic Arrows — in the works
• CO XX—for school district revisions and culvert removal — in the
works
Page 5 of 7
o ,
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
15. Subcontractor Status- Evergreen SOI needed -has been received.
Ongral Contact Amount(svo tag): S5,169.69730 Date of Intent
PERCENT OF TOTAL CONTRACT Request To Pap
REQUEST THIS PREVIOUS SUBLET Reed to Sublet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ground Up Road Coosucoo,Inc. $25,575.00 0.49% 0.00% 0.49% 8/11/2021 8112/2021 N 8.27,2021
2. Green City,Inc. $139,480.00 2 70% 0.49% 3.19% 8/11/2021 8,1212021 Y 8,'312021
3. Totem Electric of Tacoma,Inc. S734,636.80 14.21% 3.19% 17.39%8/122021 812/2021 N &27/2021
3a. Integrity Networks(Lower Tier) S22,432.15 a 3.05% 0.00% 3.05%12/15/2021 12'152021 N &31/2021
4. Lakeridge Paving Company,LLC $706,900.00 13.67% 17.39% 31.07% 8/162021 8172021 N 8302021
5. Stripe Rite,Inc. S42,778.60 0.83% 31.07% 31.89% 816/2021 8/17/2021 N 8/24,2021
6. C&PFenciog S2,177.70 0.04% 31.89% 31.94%8202021 823,2021 N 826/2021
7. WE.Coates 861 500.00 1.19% 31.94% 33.13%12115,2021 12,152021 Y 1 111 5/202 1
8. Legacy Tapping,Inc_ S20,140.00 0.39% 33.13% 33.52% 1/27.2022 1/272022 N 127.2022
9. PnD Logging $10,000.00 0.19% 33.52% 33.71% 2116'2/2 '21712022 N 2'16/2022
10. ConcreteSennces $192,934.00 3.73% 33.71% 37.44% 3/17.1 rr 1 1''2022 N 3/23/2022
11. Puget Construction Services,Inc. $15,000.00 0.29% 37.44% 37.73% 3;18202 2 318,2022 N 4/122022 1
12. Transporation Systems,Inc $48,110.00 0.93% 37.73% 38.66% 3/212022 3/21/2022 N 3/18/2022
13. Evergreen Concrete Cutting,Inc S3,000.00 0.06% 38.66% 38.72% 4/15/2022 4/15/2022 N
14. 0.00% 38.72% 38.72%
15 0.00% 38.72% 38.72%
16.Certified Payrolls- Does Reed foresee any issues providing the missing
payrolls? Tiffani noted that some subcontractors might be doing payroll
this week for previous week's work. Tiffani will confirm and let G&O
know.
Progress Payment No 5 (April)
Week Ending On: 9-Apr 16-Apr 23-Apr 30-Apr
Reed Trucking 18-Apr 22-Apr
W.E. Coates 14-Apr 22-Apr X X
Totem Electric 25-Apr 27-Apr No Work X
PnD Logging No Work X X X
Puget Construction No Work No Work No Work X
Concrete Services 25-Apr 25-Apr X
Transportation Systems X X
Evergreen Sawcutting X X X
Ground Up X X X
•
Page 6 of 7
Milt
'M CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor/Subcontractor is on the job site,payroll required. '*'(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
a is Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment —
• Progress Payment No 5 —April 29 cut off; May 4th documentation
to be submitted to City for processing.
18. Other Items: none.
Schedule 51*
-_..•_J — LUJWork Zone C-Jan-March 25 2022Styr) =JlLV 'Work Zone A-Feb 25 to March 25 2022
Work Zone B&E-March 28 to Aug 22.2022
Work Zone F(Medians)-Nov 9 to Dec 20 2022 Ill —,
J.
TIPTL4:A
lP'(SECT - (T Li
LOCATION J .1 lEDUI.E riviNE A I --
4p
INN N 1114
Irk
i
3
w(2.7_,..,
,i 1 itoge ,_ . ` NE crosr u.
o -a
4
kr r _ L J
NE I7N ST
PROM _ —
L \M.5`O�CATION
.4111111k.
• -1" .. J _
w---..-; - . _ _
---T- 7
WATER MAIN IMPROVEMENTS
-SCHEDULE B
N
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
Page 7 of 7
•
REEDC. Date:04/30/22-05/20/22 3 Week Look-Ahead Schedule
TRUCKING&EXCAVATING Name: Duvall Avenue
May
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/Resources
30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Forrn and pour walls X X X X X
Clean up and restoration WZC and A X X X X X
Paving X X
Install hydrants X X X
Set up WZB and X
Remove asphalt on WZB and E X X
Demo X X
Storm WZE X X X X X X X X
;R CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
APRIL 26, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman Sanchez, G&O
Renton
Dustin Wright, Reed Trucking x Jordan and Ross Widener, Widener x
& Excavating Inc. & Assoc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Sam Comer, Cornerstone GCI Daniel Aguirre, PSE Power
Ed Thompson, Representing x Abdoul Gafour, City of Renton x
Renton School District
Kyle Cundy, Cornerstone Gerard Boulanger, Cornerstone
Tom Main, City of Renton Glenn Helton, PSE Gas
relating to Water Imp.
2. Safety Report — Dustin Questions if gravel surface at 9th is acceptable
until paving, noting that 2"drop is legal. Section 2-02.3(3)states HMA
patching is required. Dustin states this is not feasible. City/G&O will
provide recommendation.
Page 1 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
3. Prior Meeting Minutes— Comments/Acceptance — accepted
4. Weekly Statement for Working Days ending April 25, 2022
Days Expired: 70
Days Remaining: 192
5. Schedule Progress
Contractor's Look Ahead Schedule— wa//s & clean up. Then WZ B&E.
Wet taps on Thursday.
Expected materials that are coming out on-site— Tapping tee
sleeves on Thursday.
6. Utility Coordination
a. COR Water Department—4 FH hot taps — coordinated already.
b. PSE Power WZE — schedule for next undergrounding phase (2
conduit crossings around 12th — Dustin looking into it
7. RSD Elementary School 16 Coordination
a. Water crossing work update: South crossing completed.
Finishing north crossing today and tomorrow.
b. Gas crossing schedule: there will be 24-48 hour notice from
PSE.
c. Conduit crossing schedule at 10th: Nothing set. Precon
Thursday
8. Engineer's Report
a. Filterra edge on 5 units that will be installed behind the
sidewalk.
9. Inspector's Report
a. Material testing — last concrete pour finished
b. Traffic Control issues —See Safety Report
Page 2 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
APRIL 19, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan and Ross Widener, Widener x
& Excavating Inc. & Assoc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Sam Comer, Cornerstone GO Daniel Aguirre, PSE
Ed Thompson, Representing x Abdoul Gafour, City of Renton
Renton School District x
Kyle Cundy, Cornerstone Gerard Boulanger, Cornerstone
Tom Main, City of Renton
relating to Water Imp.
2. Safety Report — Bob noted high speed traffic going through work zone.
Reed is aware of traffic speed.
3. Prior Meeting Minutes — Comments/Acceptance — no comments
Page 1 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending April 18, 2022
Days Expired: 65
Days Remaining: 197
5. Schedule Progress
Contractor's Look Ahead Schedule—
Pulverize. Leave intersection at 10th. Discussed that ped crossing at
12th will not be safe during construction.
Expected materials that are coming out on-site — HMA and some
waterline fittings. No info yet on light poles. Poles may be delivered
along with poles for Lake Washington Loop Trail Project. Fred to
check. Poles to be stored at Totem's yard when delivered.
6. Utility Coordination
a. COR Water Department— FH hot taps - four hot taps will be
done in WZB. Taps scheduled for 29th by Legacy
b. PSE Power— schedule for next undergrounding phase— Work
Zone E. Work at corner of 12th
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: Status of partial release of permit
for frontage improvement plans: Partially Released
b. Water crossing work update: To be finished this week.
Working on extending hydrant locations on west side. West
lane closed. Bob mentioned steel plates in place with no
warning to motorcycles. Phil mentioned the warning signs were
out last he checked. Perhaps knocked over. Warning signs to be
in place.
c. Temp HMA patch for water crossings? Haven't heard if City
will allow. Ed will confirm.
d. Gas crossing schedule/ permit status: Has been issued
e. Conduit crossing schedule: To be done by School
Page 2 of 6
;R CITY OF RENTON
DUVALL AVE NE
CAG-20-065
f. G&O requested Permit/Final frontage improvement drawings.
Cornerstone will provide once received from the City.
8. Engineer's Report
a. How will ADA route be provided at 12th during construction? —
Close at 12th and reroute down Sunset...Dustin to put together
ped plan and submit to City.
b. Street lights —to be staged at Totem Electric's yard.
c. Concrete worker's Strike — Corliss not delivering to Renton at
this time due to after effects of strike— Check on Stoneway or
other supplier availability. Reed to confirm pricing with
tomorrow's concrete invoices.
d. Temp edge line on WZC until median is installed? Temporary
tape. Reed to hold off on permanent striping and do all at once
e. Multiple tree removal at Sta 904+10 LT— Remove the multiple
tree and pay as one tree removal
f. Street light install sequence WZC, WZB&E, WZD per submitted
schedule?All street lights to be installed at WZC at once.
g. Retaining Wall— tapers? Bob: Yes.
9. Inspector's Report
a. Material testing — Concrete pours...all good.
b. Traffic Control issues — None. Other than rush hour speeding.
Phil noted no issues with 2 work zones at school frontage.
c. Wage Interviews — TSI Done
10.Environmental Compliance Report— Toe into slope, unless there's grass
at end of 4th
11. Public Outreach - City working with business at 4th. No issues
12.Submittals/Documentation
a. Review ROM — updated ROM posted to CMS.
Page 3 of 6
73 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Submittals under review: Anti-Graffiti under review.
c. RAMs that need to be submitted:
• A'-2.10 Anti Graffiti Coating
• B18.04 — 3/4-Inch Diam. Cor-Ten Steel Shackle Rods
• B18.13 — 3/4-Inch Cor-Ten Tie Rod
• B18.13 —Tapping Sleeve and Valve
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
• For hydrants installed for WD 90/tie-ins, need Cert. of
Compliance for gaskets, mega lugs, and field lock gaskets.
13. RFIs —
RFI 17—Thrust blocks at FH — response sent
14. FWD/ Change Orders —
• FWD 11 issued for the addition of supplemental RPM's
• FWD 12 issued for removing 2 culverts in WZE
• CO 7 —for storm imps at 9th —fully executed
• CO 8 - price adj. of conc. in WZ A and C - fully executed
• CO 9 — Wall Footing —fully executed
• CO 10 — Relocate Street Light L12 — sent to City for signatures
• CO 11 — Supplemental RPM's — in the works
• CO 12—for school district revisions and culvert removal — in the
works
15. Subcontractor Status —
Page 4 of 6
IR
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Origami Contract Amount KO Guy S2,169.69230 Date of latent
PERCENT OF TOTAL CONTRACT Request To Pay
REQUEST THIS PREVIOUS SUBLET Ree'd to Sublet Prevailing '
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ground Up Road Construction,Inc. $25,575.00 0.494E 0.00% 0.49% 8111,2021 8112'2021 N 8.27.2021
2. Green City,Inc. S139,480.00 2.70% 0.49% 3.19%8112021 8/12/2021 Y 8/31/2621
3. Totem Electric of Tacoma,Inc. S734,636.80 14.21% 3.19% 17.39% 8112/2021 8/122021 N 82712021
3a integrity Netwodcs(Lower Tier) $22,432.15 a 3.05% 0.00% 3.05%12/152021 12/152021 N 81312021
4. Lak 8 a Pavia Company,LLC S706,900.00 13.67% 1739% 31.07%%8/162021 8/17/2021 N 8/302021
� 8 �.
5. Snipe Rite,Inc. 542,778.60 0.83% 31.07% 31.89% 8116'2021 8/17/2021 N 81242021
6. C&P Fendng $2,177.70 0.04% 31.89% 31.94% 820/2021 823!2021 N 81262021
7. W.E.Coates 561,500.00 1.19% 31.94% 33.13%12/15/2021 12/152021 Y 11/1512021
8. Legacy Tapping.Inc. S20,150.00 0.39% 33.13% 33.52% 1.272022 1127.'2022 N 1127.2022
9. PoD Logging $10,000.00 0.19% 33.52% 33.71% 2/16/2022 217/2022 N 2/16/2022
10. Concrete Services S192,934.00 3.73% 33.71% 37.44% 3/17/2022 3/17/2022 N 3232022
11. Puget Coast uctioa Services,Inc. S15,000.00 0.29% 37.44% 37.73% 3//82022 3/18/2022 N _
12. Transpo,aiion Systems,Inc S48,110.00 0.93% 37.73% 38.66% 3 212022 3/21:2022 N 3/182022
13. Evergreen Concrete Cutting,Inc S3,000.00 0.06% 38.66% 38.72% 4/15/2022 N
14. __ 0.004. 38.72% 38.72%
J 15. 0.00% 38.72% 38.72%
16.Certified Payrolls-
' Cert�ed P.wolk
- - -- - - Progress Payment No I(December)
Week Ending O., 25-Sap 2-On 9-On 16-On 23-On 30-O.t 6-Nov 13-Nov 20-Nov 27-Nov 4-Dee 11-Dee 11-Dee 25-Dee
Read Tmcl'ng X X X X X X X X X X X X X X
Progres.,P.ymrar No 2(I.a.ry Progress Paysadd No 3(February) Progress Papaw.No 4(.March)
' Week lading O.: I1.. 8-Jan 15-Jan 22J10 291en 5-Feb 12-Feb 19-Feb 26-Feb 8-Mar 12-Mar 19-Mar 26-Mr 2-Apr
i,Revd Trading 4-Jan 18-Jan 25-Irs 28-In 4-Feb 10•Fob 1-Mar I•Mar 4-Mr 14-Mr 22-Mar 25-Mr 4-Apr 8-Apr
W.E.Coates X 18-aria 28-Jon No Work No Work No Work No Work 1-Mr No Work 14-Mar 24-Mr 24-Mar No Work X
'Tote Electric X X 28-ion 28-laa No Work No Work I-Mr I-Mar 4-Mr 18-Mar IS-Mar 25-Mr 4-Apr 8-Apr
i PoD Logging X X X X X X X 1-Mr No Work No Work No Work X X X
1 Puget Continence X X X X X X X X X X X X X
:Concrete Sereicn X X X X X _ X X X X X X X X
Proper Parsed No 5(April) Progress Payment No 6(May) Progress Payment No 7(J..e)
•
Week Ending Or. 9-Apr 16-Apr 23-Apr 30-Apr 7-3Aav 14-May 2I-M.y 28 May 4-Jun II-Jaa 104.. 28-J.. 21d
r;'Reed Trucking
'I:W.E.Coates
-!Totem Electric
•PoD Logging X
r Puget Construction X '
Concrete Senioea
Week Contractor/Subcontractor is on the job site,payroll required_ **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
im.Corrections to payroll required
Apprenticeship doe's required
Payroll Resubrnittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment-
• Progress Payment No 5 -April 29 cut off; May 4th paper work to be
submitted to City for processing.
• MOH - Need certs for Filterra units. Dustin to consider if MOH will
be requested for storm structures - Certs will also be required.
Page 5 of 6
'D0 -4 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
18. Other Items:
Schedule yy�y�r4in j �U
Work Zone C-Jan-March 25 2022 NE f's'
Work Zone A-Feb 25 to March 25 2022 sitT eC�d x o J D
Work Zone B 8 E-March 28 to Aug 22,2022 g �.rr
Work Zone F(Medians)-Nov 9 to Dec 20 2022 �) _,
sol: L
1,1
LOCATION _ I
( Li.-
� TT , EtiEDUIE� NE 10'L!ST �tN}))r�i I�- _.-
1 1
in , III, tiki
.1.
'�\ ; Irmi4;ato gii____„:„_ - $1
Wat Ear C
2
i
Z---,_ N
F.
u' _ NE 6THST
. 10--, 2 t--- 54
7
i
NElTHST ` g
ir
PROJE _ f E_ __ —
LOCATION
'\...rn J Fr----51's . ___i_____,
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SOME -SCHEDULEC
Page 6 of 6
REEDC. Date:04/16/22-05/6/22 3 Week Look-Ahead Schedule
TRUCOG rs C EXCAVATING Name: Duvall Avenue
YON
April
Sched
ID Work Description SSM TWT F SSM T W T F SS M T W T F Notes/Resources
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6
5 prep to pave X X
8 form and pour walks X X X
Storm WZB X X X X X X X X X
Form and pour walls X X X X X X X X
9 Clean up and restoration WZC and A X X X X X
10 plainning WZA and C X
11 Paving X X
12 SetupW2BandE
13 Remove asphalt on WZB and E X X
14
15
16
17
18
19
20
21
"F CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
APRIL 12, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan and Ross Widener, Widener
& Excavating Inc. Qom.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Jordan, Reed Trucking & Michael Ballard, G&O
Excavating Inc.
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc. X
Sam Corner, Cornerstone GCI Daniel Aguirre, PSE
Ed Thompson, Representing X Dustin Weller, PSE
Renton School District
Kyle Cundy, Cornerstone Gerard Boulanger, Cornerstone
Tom Main, City of Renton Matt Maynard, PSE Intolight
relating to Water Imp.
Traci Brewer-Rogstad, X Abdoul Gafour, City of Renton X
Renton School District
2. Safety Report — no issues to report
Page 1 of 6
rtY .nc
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
3. Prior Meeting Minutes— Comments/Acceptance
Prior minutes are accepted
4. Weekly Statement for Working Days ending April 11, 2022
Days Expired: 60
Days Remaining: 202
5. Schedule Progress
Contractor's Look Ahead Schedule — see the attachment. Dates for
planning are tentative —Reed is coordinating with Lakeridge for
planning. Dates shown for wall are for pour all walls in WZC.
Expected materials that are coming out on-site — Filterra vaults
arrive on Wed and Friday, more storm structures arriving on Wed.
6. Utility Coordination
a. PSE schedule for wire and cut overs in work zone C—started 4-
11-22 and 5-6 working days duration — They will finish today
b. PSE-Intolight schedule for Existing PSE Street light at the SE
corner of Duvall and 9th removal — this was completed
yesterday
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: Status of frontage improvement
plans: the School is waiting on a permit for the school site.
There may be a partial release of the permit soon which would
include the frontage improvements on Duvall Ave.
b. Water crossing work update: water stub out tie-ins are
hopping today
c. Gas crossing schedule: City to check on status of permit
d. Conduit crossing schedule: In the shop drawings and submittal
phase
Page 2 of 6
if? CITY OF RENTON
DUVALL AVE NE
CAG-20-065
e. Discussed two existing culverts that are shown to be removed
on the school plans, along the Duvall Ave frontage. Reed
Trucking to do this work instead.
8. Engineer's Report
a. Staging Area Alternatives — no notifications received on the
existing staging area from the City
• Vacant commercial lot north of Sunset — no new
contact with the property owner achieved.
• ROW in a lane closure
• Hazen Reservoir Site.
b. Driveway profile at 4th Street driveway was revised
c. Planing time limitations in advance of paving—can they be
waived when the planing is within a lane closure? The City will
work with the Contractor regarding waiving the time limitations
—contractor to provide adequate signage.
d. Planing limits in WZC —should we extend 1 foot to the west to
match into previous pavement joint? Will be within the lane
closure. City would like the planing limits extended to the joint
e. Concrete worker's Strike— the strike is over but Reed Trucking is
unable to purchase concrete from Cadman (Corliss) Reed to
provide documentation of same.
9. Inspector's Report
a. Material testing — concrete testing done for street light
foundation pours
b. Traffic Control issues — traffic cone issues being dealt with
c. Wage Interviews — up to date
10.Environmental Compliance Report -
Jordan was not present. Phil said that she had met on site earlier in the
week and discussed use of check dams in the ditch near the church in
WZE
Page 3 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11. Public Outreach
Nothing to report
12.Submittals/Documentation
a. Review ROM — updated ROM posted to CMS.
b. Submittals under review:
c. RAMs that need to be submitted:
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
• For hydrants installed for WD 90/tie-ins, need Cert. of
Compliance for gaskets, mega lugs, and field lock gaskets.
13. RFIs —
RFI 15 — HMA depth in 2-foot patch along curb — sent
14. FWD/ Change Orders—
• CO 7—for storm improvements at 9th — City processing
• CO 8 - price adjustment of concrete in work zones A and C— City
processing
• CO 9 — Wall Footing — sent to City for signatures
• CO 10 — Relocate Street Light L12 —sent to City for signatures
• CO X —for school district revisions— in the works
• G&O to issue FWD for removing culverts
15. Subcontractor Status—
Page 4 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
PERCENT OF TOTAL CONTRACT
REQUEST THIS PREVIOUS SUBLET
( NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE
1. Ground Up Road Construction,Inc. S25,575.00 0.49% 0.00% 0.49% £
2. Green City,Inc_ S139,480.00 2.70% 0.49% 3.19% £
3. Totem Electric of Tacoma,Inc. S734,636.80 14.21% 3.19% 17.39%
3a. Integrity Networks(Lower Tier) S22,432.15' 3.05% 0.00% 3.05% 1
4. Lakeridge Paving Company,LLC S706,900.00 13.67% 17.39% 31.07% f
5. Stripe Rite,Inc. S42,778.60 0.83% 31.07% 31.89% f
( 6. C&P Fencing $2,177.70 0.04% 31.89% 31.94%10 f
7. W.E.Coates S61,500.00 1.19% 31.94% 33.13% 1
8. Legacy Tapping,Inc. $20,150.00 0.39% 33.13% 33.52% 1
9. PnDLogging $10,000.00 0.19% 33.52% 33.71%
I 10. Concrete Services $192;934.00 3.73% 33.71% 37.44%
I I1. Puget Construction Services,Inc. $15,000.00 0.29% 37.44%1 37.73%
12. Transporation Systems,Inc $48,110.00 0.93% 37.73% 38.66%
16.Certified Payrolls-
Progress Nyman No 2(Jemmy) Pro ress Peymnt No 3(February) Progress Payment N.4(Maack)
Week Ending On: IJa. BJ.s 15J.. 22Jan 29J.a 5-Feb 12-Feb 19-Fab 26-Feb 5-Mar 12 Mar 19-.Mar 26-Mar 2-Apr
Reed Tmekiug 4-Jan 18Jan 25-Jan 2S-Jau 4-Feb 10-Feb 1-Ma 1-Ma 4-Mar 14-Mr 22-Mar 25-Mar 4-Apr
W.E.Coons X IBJan 28-Jan No Work No Wok No Work No Work 1-Mr No Work I4-Mr 24-Mr 24-Mar No Work X
Totem Ekcmc X X 28-Jao 28-Jan No Work No Work 1-Mar 1-Mr 4-Ma 18-Mr 18-Mar 25.Mr 4•Apr X
PoD Loaning X X X X X X X I-Mr No Work No Wok No Wok X X _ X
Rrger Cortsuuction X X X X X X X X X X X X X
Concrete Serocer X X X X X X X X X X X X X
Progress Payment No 5(Apra) Progren Payment No 6(May) Progress Payment No 7(June)
]Peek Eodlag On: 9-Apr VS-Apr 23-Apr 10-Apr 7-May M-May 21-May 2$-Ma. 4-3a. 11Jm 18J.. 25Ju. 2J.1
,Reed Tracking
W.E.Coomr
•
Totem Electric _
PoDLoggurg X
Puget Coroom,8o,r X
Concrete Services
Week Contractor/Subcontractor is on the job site,payroll required_ **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment-
• Progress Payment No 4- in processing.
Page 5 of 6
_EDO
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Progress Payment No 5 —April 29 cut off May 4th documentation
due, should we consider a different cutoff date to allow more
time for reviews. Contractor prefers to keep existing cut off date.
• Fuel Price adjustments and Asphalt Cost Price Adjustments will
be added retroactively on the next progress payment
•
18. Other Items:
The Contractor wants to know if there are options for the fire hydrant
thrust blocks on the 16-inch diameter water main. They will submit an
RFI requesting options.
Schedule
Work Zone C-Jan-March 25 2022 5Z--l � 'Work Zone A-Feb 25 to March 25 2022BCVo la
-71111,I I•
Work Zone B&E-March 28 to Aug 22.2022 II _Work Zone F(Medians)-Nov 9 to Dec 20 2022 t 1 _
J NE IIf119f
CEP i givirppl..�� l L ` t— E
Akir LOCATION L
MAE
k . , _„
,__Lai sr : ---
won zorcr
001 40711
"ta I I 1 b FA ,. a• =NE nH
::
"hilt
a.
.--i--jz-.--
_..__ NE ETHST
) ,°
INEaTNST $
PR•1E —
LOCATION —1
( figJ Lki__ — T.
WATER MAIN IMPROVEMENTS
-SCHEDULE B
N
VICINITY MAP UNDERGROUND IMPROVEMENTS
Nnira SCALE -SCHEDULEC
Page 6 of 6
•
REED 3 Week Look-Ahead Schedule
Date:04/09/22-04/29/22
TRUCKING&EXCAVAT7T Name: Duvall Avenue
April
Sched
ID Work Description S S M T W T , F SS M T W T F SS M T W T F Notes/Resources
9 10 11 12 13 14 15 16 17 18 19 29 21 22 23 24 25 26 27 28 29
2 sidewalk prep X X X
5 prep to pave X X X X
6 Clear and grub WZ B and E X X X
silt fence X X X X
7 Pour sidewalk X _ X
8 form and pour walls X X X X X X X X X X
Storm WZB X X X X X
9 Clean up and restoration WZC and A X X X X X
10 plainning WZA and ?
11 Paving ? ? ?
12
13
14
15
16
17
18
19
20
21
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
APRIL 5, 2022
Comments made during the Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan and Ross Widener, Widener X
& Excavating Inc. & Assoc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Jordan, Reed Trucking & X Michael Ballard, G&O X
Excavating Inc.
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric X Dmitri Suslikov, Parametrix Inc. X
Sam Corner, Cornerstone GO Daniel Aguirre, PSE X
Ed Thompson, Representing X Dustin Weller, PSE
Renton School District
Kyle Cundy, Cornerstone Gerard Boulanger, Cornerstone
Torn Main, City of Renton Matt Maynard, PSE-Intolight
relating to Water Imp.
2. Safety Report —no issues at this time.
3. Prior Meeting Minutes— Comments/Acceptance —
4. Weekly Statement for Working Days ending April 4, 2022
Page 1 of 6
off' ,
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Days Expired: 55
Days Remaining: 215
5. Schedule Progress
Contractor's Look Ahead Schedule —Sidewalk Forms, Pouring 12th 4th
Expected materials that are coming out on-site — Class 4000P on
Friday.
6. Utility Coordination
a. PSE schedule for wire and cut overs in work zone C - start
4/12/22 and 5-6 working days duration — Dustin stated all
sidewalk will be poured at once . Asked if 4/12 date could be
pushed up? PSE/Potelco crews are busy with outages. Dustin
and PSE to coordinate for poles in sidewalk and walls.
b. PSE-Intolight schedule for Existing PSE Street light at the SE
corner of Duvall and 9th removal — End of week
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: updated plans are in review by the
City. The School District Contractor may use the Duvall Ave TCP
with deference to Reed Trucking.
b. Water crossing permit has been issued, TCP comments were
sent to the School — Permit is issued, on hold for TCP, submittal
of parts
c. Gas crossing schedule —The permit been submitted by PSE
d. Conduit crossing schedule- School waiting on construction
permits.
e. School Borings planned 4/4 —4/6 Completed 4/4
8. Engineer's Report
a. PCMS timeframes were clarified last week. Not needed for lane
closures.
Page 2 of 6
;R CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Staging Area —pulverized material may be stored in ROW on a
lane closure. Use of lane closure along Work Zone C doesn't
seem feasible. Hazen reservoir site would require extensive
restoration. Dustin asked if the City had a working relationship
with Ace or Safeway to use their parking lots. Also available is
the vacant commercial lot however Dustin noted it is expensive
since it is a commercial lot. It is anticipated the lot would be
needed for 5-6 months. Dustin to talk to owner to is if price can
come down.
c. Staging area for street lights — may be at Hazen Water Tank site
if Reed Trucking needs it. Tani asked for delivery update and if
street lights are ready to be installed. Totem stated the delivery
schedule is the same - Beginning of May. Additional work on
circuit required prior to installation. Staging area at Hazen
reservoir site would be good for street lights, Flora to arrange
d. Cut sheets for curb/gutter — G&O requests Reed to submit these
one week in advance of curb pour so there is time to review.
e. TCP approved for right lane closure in WZB and WZE
f. Shine issue with wall footings. Shine at back of walk adjacent to
walls. Since there isn't a form at the back of walk it will be
difficult to get a straight edge. Bob stated shine is not required
at these locations.
9. Inspector's Report
a. Material testing — Concrete testing. Compaction testing on CSTC.
b. Traffic Control issues—
c. Wage Interviews — CSI
10.Environmental Compliance Report -
New CBs located north of NE 7th St need cb socks. For foundation pour
on Friday, water at bottom of foundation needs to be pumped to pond
or filter.
11. Public Outreach
Page 3 of 6
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor./Subcontractor is on the job site,payroll required. **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
I. :Apprenticeship dot's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 4 — March 31st was the cutoff, all paperwork
submitted to the City by April 6th for April 15 check run.
Schedule I
Work Zone C-Jan-March 25 2022 NE —
Work Zone A-Feb 25 to March 25 2022 ! -Elio ;—' -- 20.o
,73
Work Zone B S E-March 28 to Aug 22.2022 k -' 1
Work Zone F(Medians) Nov 9 to Dec 20 2022 r
-
E'E4 PR 1EZT^ \ ^ I. 1
I
Li_
A !ihh11!
LOCATION _ L �
-SCHEDULE6 wEw' r rr sr .
—
.g,i .44
- - ]
NE 7rH
--,,, gitii.,,, ,
2,�V`�
,, iii
�yIZ__ _ HE 6TH 5T N
z
NEarnsr J
E ` JIL1l
1LJ LOCATION
`l Eot--'
NE ,fir - 7
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP i UNDERGROUND IMPROVEMENTS
MOT 10 SCAIE -SCHEDULE C
Page 6 of 6
REEDc Date:04/02/22-04/22/22 3 Week Look-Ahead Schedule
TRUCKING 8 EXCAVA77NG Name: Duvall Avenue
...«......<,w<...,...«......w. March
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/Resources
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
2 sidewalk prep X X X X X . X
5 Demo workzone A X X
6 Clear and grub WZ B and D X X X X X X X X
7 Pour sidewalk X X
8 form and pour walls X X X X X X X
9 Clean up and restoration WZ C and A X X X X X
10
11
12
13
14
15
16
17
18
19
20
21
o,c'
4 + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MARCH 29, 2022
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O
x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking xlarda-rs-a-n-€1-Ress-W-iclener-TWideReF
& Excavating Inc. Q.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Michael Ballard, G&O x
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc. x
Sam Corner, Cornerstone GO Daniel Aguirre, PSE x
Ed Thompson, Representing x
Renton School District
Kyle Cundy, Cornerstone Gerard Boulanger, Cornerstone
Tom Main, City of Renton x Matt Maynard, PSE Intolight
relating to Water Imp.
2. Safety Report— No issues
3. Prior Meeting Minutes — Comments/Acceptance —
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending March 28, 2022
Days Expired: 50
Days Remaining: 220
Reed Trucking requesting change to 10-hour work days, for weekdays, is
approved - 7:30 am to 5:30 pm, then shift to 7:00 am to 5:00 pm closer
to summer.
5. Schedule Progress
Contractor's Look Ahead Schedule— 8:30 on Wed, concrete is coming
on site, other than that the look ahead is similar to last week's, will
move to Work Zone 8 and E in the next 2 weeks. CM team to provide
spec clarification on PCMS requirements.
Expected materials that are coming out on-site— concrete mix and
rebar
6. Utility Coordination
a. PSE schedule for wire and cut overs in work zone C - start
4/12/22 and 5-6 working days duration — Daniel says that
Potelco may be able to move in earlier. Daniel will coordinate
with Phil and Dustin if crew is available at an earlier date.
b. PSE guy wire in WZA may get covered with some fill material —
G&O to send Daniel an email with a photo
c. Existing PSE Street light at the SE corner of Duvall and 9th to be
disconnected and removed by PSE-IntoLight
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: updated plans are in review by the
City. City is still commenting, may issue a limited work permit
in the next 2 weeks
Page 2 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Water crossing permit has been created — The School
contractor may do the work under the Duvall Avenue NE permit
if needed. The TCP plan is under review. The City water crew is
2-3 weeks out for the tie-ins.
c. Gas crossing schedule— Has permit been submitted by PSE?
The City confirmed that PSE did apply last Monday,for a one
day cut-in connection.
d. Conduit crossing schedule- School waiting on construction
permits.
e. School Borings planned 4/4 —4/6. For subgrade info.
8. Engineer's Report
a. ADA pre-activity meeting was held — March 28 on site.
b. Culvert removal at driveway in Zone A is approved in lieu of
abandon in place with CDF at contractor's option.
c. Added TC signs are upon Sunset Boulevard? — will be up today
d. PCMS sign schedule for next work zone— discussed that PCMS
boards for lane closures will not be needed. They will be used for
driveway closures, if any, and to warn public in advance of
paving. G&O to send an email to confirm this. Therefore PCMS
boards can be picked up once the supplemental signs are up on
Sunset.
e. Staging Area — discuss pulverized material and street lights —
Reed may store the pulverized material within R-O-W along lane
a closure subject to coordination with the City. Street lights may
be stored at the Hazen Water Tower site, with coordination of
the City. Contractor has not had word from City Permitting
department regarding staging area.
f. TV Inspections for Storm — They just completed the last run.
g. Who will supply concrete, Cadman or Miles? From which plant?
Miles will be the concrete supplier. Dustin needs submittal
review ASAP.
9. Inspector's Report
Page 3 of 7
CITY OF RENTON
, To DUVALL AVE NE
CAG-20-065
a. Material testing — 2 compaction tests last week, tomorrow at
8:00 MTC will be on site for concrete testing.
b. Traffic Control issues — Will need flogger on site for concrete pour
c. Wage Interviews — CS/ will be done tomorrow
d. Potholing — completed for WZA and WZC
10.Environmental Compliance Report -
Jordan sent word that the silt sock in the C8 at the NE corner of NE
10th/Duvall needs to be cleaned out.
11. Public Outreach
Nothing to report
12.Submittals/Documentation
a. Review ROM —
b. Submittals under review:
• RAM 084E— Miles concrete for curbs — G&O to expedite the review
• RAM 086 —Tracer wire & wire sleeves
• FA rates for Totem Electric
c. RAMs that need to be submitted:
• BI 10. 01.03 —Tie rods for anchor blocks -
d. Non-Material Submittals that need to be submitted:
e. Material Documentation —
• For hydrants installed for WD 90/tie-ins, need Cert. of
Compliance for gaskets, mega lugs, and field lock gaskets.
13. RFIs —
RFI 14 — regarding Magnolia Stellata is in review— will have a
response soon
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
14. FWD/ Change Orders-
• CO 7-for storm improvements at 9th - City processing
• CO 8 - price adjustment of concrete in work zones A and C-City
processing
• CO 9 -Wall Footing -sent to City for signatures
• CO 10- Relocate Street Light L12 -sent to City for signatures
• CO X-for school district revisions-in the works
15. Subcontractor Status-
PERCENT OF TOTAL CONTRACT
:REQUEST THIS PREVIOUS SUBLET
NO. SUBCONTRACTOR AJIOUIT REQUEST REQUESTS TO DATE
1_ Ground Up Road Construction,Inc. S25,575.00 0.49°o 0.00% 0.49% £
2. Green City,Inc_ S139,480.00 2.70% 0.49% 3.19%
3. Totem Electric of Tacoma.Inc $734,636.80 14.21% 3.19°0 17.39% £
3a. Integrity Networks(Lower Tier) S22,432.15' 3.05% 0.00°o 3.05% 1
4. Lakeridge Paving Company:LLC $706,900.00 13.67% 17.39°o 31.07% £
5. Stripe Rite,Inc. S42,778.60 0.83% 31.07% 31.89% £
6. C&P Fencing S2,177.70 0.04% 31.89% 31.94% £
7. W.E.Coates S61,500.00 1.19% 31.94% 33.13% 1
8. Legacy Tapping,Inc. S20,150.00 0.39% 33.13% 33.52°o :
9. PnD Logging $10,000.00 0.19% 33.52% 33.71°o :
10. Concrete Services S192,934.00 3.73% 33.71% 37.44%
11. Puget Construction Services,Inc. S15,000.00 0.29% 37.44% 37.73%
12. Transporation Systems:Inc $48,110.00 0.93% 37.73% 38.66%
16.Certified Payrolls-
Page 5 of 7
`t a
CITY OF RENTON
��"T°� DUVALL AVE NE
CAG-20-065
Stdtdyv.oJI k Pa ��
Proven Pgvnt No 1(December)
N Week E" qr.O 25Sep 2-Oct 9-Oet 16-Or 23-0es 31)-Oct 4-Nov 13-Nov 20-Nov 27-Nov 4-Dee 11-Dee 18-Der 25-Dee
Reed Tnckio8 X X X X X X X X X X X X X X
Provers P.reoo No 2(Joaaory) Per/Leer Payne No 3(Febn;) Provers Pryeae No 4(.Marti)
Reek EndY8 0n 1-lea iJu If 214n 29Jaa 5-Feb 12-Feb 19-Feb 26-Feb 8-Mr 12-Mar 19-Mar 26-Mar 2-Apr
Reed Tramp 4-Jan 18-Jn 25Jn 28-7n 4-Feb 10-Feb 1-Mr 1-Mr 4-Mr 14-Mr 22-Mr
W E.Cones X 18-laa 28-Jan No Work No Work No Wad( No Work I-Mr No Work 14-Mar 24-Mr 24-Mr X
Torn Ekc"ic X X 28-Jan 28-Jn No Work No Work 1-Mr 1-Mr 4-Mr 18-Mar 18-Mr X
P"O Loper X X X X X X X 1-Mar No Work No Work No Work X X
Week Contractor/Subcontractor is on the job site,payroll required. **(=121 indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
lApprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 4— March 31st is the cutoff, all paperwork
submitted to the City by April 6th for April 15 check run.
18. Other Items—
Page 6 of 7
ic'� CITY OF RENTON
4-
DUVALL AVE NE
CAG-20-065
Schedule ---J
Work Zone C-Jan-March 25 2022 I ME '
Ova
Work Zone A-Feb 25 to March 25 2022 — i 1_J
11111,1 .
Work Zone 8 8 E-March 28 to Aug 22.2022
Work Zone F(Medians)-Nov 9 to Dec 20 2022 111 _.
1111
1
—Q TT_ ', l•al .N
. . sr
I .. , �i
114410111101 111'
.1‘ irmitop sisio .
; Ali
17 NE 4TH�__ ( 1
:I: PROAE
LOCATION —
alp
1140111111 LICTEDILE t", —__
' (14
WATER MAIN IMPROVEMENTS
N -SCrrDULE a
VICINITY MAP UNDERGROUND IMPROVEMENTS
Nor1OSCAIF -St Fit DUIEI
Page 7 of 7
ife
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MARCH 22, 2022
Comments made during Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O
x
Flora Lee, City of Renton x Tani Stafford, G&O
x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan and Ross Widener, Widener x
& Excavating Inc. & Assoc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
James Cohn, Comcast x Michael Ballard, G&O x
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric x Dmitri Suslikov, Parametrix Inc.
Sam Corner, Cornerstone GCI Daniel Aguirre, PSE
Ed Thompson, Representing x Dennis Booth, PSE
Renton School District
Kyle Cundy, Cornerstone Gerard Boulanger, Cornerstone
Tom Main, City of Renton Rawley Robins
relating to Water Imp. , PSE-pole management
2. Safety Report— None.
3. Prior Meeting Minutes—Comments/Acceptance —Accepted
Page 1 of 7
� CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending March 21, 2022
Days Expired: 45
Days Remaining: 215
Reed Trucking requesting change to 10-hour work days - 7:30 to 5:30,
then 7:00 to 5:00 closer to summer. Dustin to send email request for City
consideration. No earlier than 7:00 am start, due to noise per Bob.
5. Schedule Progress
Contractor's Look Ahead Schedule — Prepping for wall, sidewalk
subgrade, prep for curb, clean & TV the storm on 3/23-24. Go into
Zone A, and do prep work as well. ADA Precon on 3/28. Pour Curbs on
3/30. Hoping storm can be done in a day at 4th
Bob notified Dustin to discourage semi-trucks from turning right on
4th. Additional signs will be up and ready tomorrow. Leave PCMS up
until new signs are up.
Expected materials that are coming out on-site — None.
6. Utility Coordination
a. Comcast— cut over work is complete - yes
b. PSE schedule for wire and cut overs in work zone C — PSE
absent from meeting.
c. PSE guy wire in WZA may get covered with some fill material
d. Existing PSE Street light at the SE corner of Duvall and 9th to be
disconnected and removed by PSE-IntoLight, not part of Sch
74 work.
e. G&0 asked Totem, when light poles could be installed? Anchor
bolts delivered at the end of the month. Poles scheduled for
first week of April. (Note: this was later updated to first week
of May)
Page 2 of 7
a
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: updated plans are in review by the
City. Per Ed, no updates, waiting for permits from City. Phil
noted TC plans do not include plan for full width crossings.
b. Water crossing schedule/availability of DI pipe- Permit created.
Stub crossing to fire hydrant.
c. Gas crossing schedule — City has not seen permit app yet, Ed to
check.
d. Conduit crossing schedule-
e. School Borings planned 4/4 —4/6.
8. Engineer's Report
a. Time extension due to concrete workers strike requires updated
schedule. Does Contractor want to pursue this? Dustin will send
updated schedule if Reed wants to pursue this.
b. Schedule ADA meeting prior to first curb pour — March 28 on
site at 10:00 AM @ 9th and Duvall
c. Storm pipe material change for lateral in WZA and for remaining
3 laterals on the project may be changed from 12" DI to 12" PP
pipe. The Proposal quantity for 12" PP pipe is sufficient for the
change.
d. Added TC signs going up on Sunset Boulevard
e. Barhudarian Claim —going through the process
9. Inspector's Report
a. Material testing — Compaction for curb subgrade —MTC
compaction testing Thursday between 1 & 3. One at 4', 2 at 7th to
9th and 2 at 9th to 10t`'. Potholing showed gas as mislocated.
Storm stretch at 4th should be able to go in per plan.
b. Traffic Control issues —Sidewalk closed sign up at 1st cross-street
heading south from 4th, Phil will forward pictures to determine if
additional signage is needed.
c. Wage Interviews — will do concrete subs when they come out on
site
d. Potholing — gas and water in WZA
Page 3 of 7
o�
+ CITY OF RENTON
4)
�N1 DUVALL AVE NE
CAG-20-065
e. Concern about CDF in culvert across driveway at 4ih. Blockage
preventing drainage also prevents pumping CDF. Dustin wants
Reed to remove it instead. Phil to find out material type.
10.Environmental Compliance Report -
Rain forecast. Keep in mind with water pumping, treatment, etc...
11. Public Outreach
12.Submittals/Documentation
a. Review ROM — updated ROM sent out last week.
b. Submittals under review: RAM 083 Cadman concrete for curbs,
RAM 084 Miles concrete for curbs, and RAM 085 Miles concrete
for retaining walls
c. RAMs that need to be submitted:
• BI 10. 01.03 —Tie rods for anchor blocks -
d. Non-Material Submittals that need to be submitted: FA rates for
Totem Electric
e. Material Documentation —
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket. — For hydrants installed for WD90, any
fittings/gaskets, mega lugs, etc. need COC's. Phil noted,
field lock gaskets were used at the tie-ins.
13. RFIs —
RFI 14 — regarding Magnolia Stellata is in review -Jordan is checking
nurseries — Is City ok with different height of the Magnolia or prefer a
different species, Flora to check with Ian.
Page 4 of 7
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
14. FWD/ Change Orders-
• FWD 10- relocate street light L12 -issued
• CO 2, 3, 4 and 6-fully executed
• CO 5 -for trench backfill and dealing with water- City processing
• CO 7-for storm improvements at 9th - City processing
• CO 8 - price adjustment of concrete in work zones A and C-City
processing
• CO 9-Wall Footing -sent to City for signatures
• CO 10- Relocate Street Light L12 -sent to City for signatures
• CO X-for school district revisions- in the works
15. Subcontractor Status-
PERCENT OF TOTAL CONTRACT
REQUEST THIS PREVIOUS SUBLET
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE
1_ Ground Up Road Constriction,Inc. $25,575.00 0.49% 0.00% 0.49% E
2. Green City,Inc. $139,480.00 2.70% 0.49% 3.19% E
3. Totem Electric of Tacoma,Inc. $734,636.80 14.21% 3.19% 17.39% E
3a Integrity Netwocks(Lower Tier) $22,432.15 3.05% 0.00% 3.05% 1
4. Lakeridge Paving Company,LLC $706,900.00 13.67% 17.39% 31.07% E
5_ Stripe Rite.Inc. $42,778.60 0.83% 31.07% 31.89% E
6. C&P Fencing $2,177.70 0.04% 31.89% 31.94% E
7. W.E.Coates $61,500.00 1.19°0 31.94% 33.13°0 1
8. Legacy Tapping,Inc. $20,150.00 0.39°,0 33.13% 3352°0 1
9. PnD Logging S10,000.00 0.19% 33.52% 33.71%
I; 10. Concrete Services $192,934.00 3.73°0 33.71% 37.44%
11. Puget Construction Services,Inc. $15,000.00 0.29% 37.44%• 37.73%
12. Transporation Systems,Inc $48,110.00 0.93% 37.73% 38.66%
Page 5 of 7
+
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
16.Certified Payrolls—
••,•••u• Provers Payment No I(December)
Reek Ending Oa: 25Sep 2-00 9-Ors 16-0ct 23-Oct 36-0er 6-Nov 13-Nov 20-Nov 27-Nov 4-Der 11-Dec 18-Dec
Reed Trucking X X X X X X X X X X X X X
Progress Pa;teat No 2(J.a.ary) Provers Payment No 4(March)
Week E.dla 1J.. Wu 15J.a 22Ja. 26-Jam 5-Pro 12Fe 1p-Feb2r'Feb 5-Mar I2-Mar I9 Mor 26-Mae
Reed Trucking 4-7ao 18-1a. 254ai 28Jao 4-Feb 10-Feb I-Mar 1-Mar J-MIar 14-Mar
W.E.Coat. X 18-Jan 18-Jan No Work No Work No Work No Work 1-Mar No Work 14-Mar X X
Tam Elaine X X 2114au 28J® No Work No Work 1-Mar I-Mar 4-Mar
PoD lagging X X X X X X X 1-Mir X X X X
Week Contractor/Subcontractor is on the job site,payroll required. **(=12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"pa'.Toll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 4— March 31st is the cutoff, all paperwork
submitted to the City by April 6th for April 15 check run.
Tiffani-payrolls for subs may have issue since they do payroll on the 8'
Tani, noted will need to consider to not include work performed by
subcontractor(with missing payrolls) or push PP No. 4 to next check run
date.
18. Other Items—
• Nothing new to report regarding the staging area.
• Reed is responding to Barhudarian claim
Page 6 of 7
RCITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule
Work Zone C-Jan-March 25 2022
Work Zone A-Feb 25 to March 25 2022 4
Work Zane B 8 E-March 2$to Aug 22.2022 1 tl,,, ( —
Work Zone F(Medians)-Nov 9 to Dec 20 2022 , tnH —
° ANIL PR�1EC1
LOCATION
— _�
F
-stwDutE a --�� --I
t M 'E1�-
�� mil i I W ' T TTTTT
I Wock Zona C
libilapli l'
I1 r 1 --0
7
400,
t
1____
HE[THST
_., 5
PRO1E Fr.../..„ F__ 1 11,
LOCATION
a n A __4
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCALE -SCHEDULEC
Page 7 of 7
REEDC. Date:03/19/22-04/08/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall A
...«�.....,<.�<.,........,. ... March
Sched
ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/Resources
19 20 21 22 23 24 25 26 27 28 209 30 31 1 2 3 4 5 6 7 8
2 Illumination X X X X X
5 Roadway E. X X X X X
6 CSTC Curb Grade X X X
7 Workzone A
8 erosion control X X
9 demo X X
10 storm X X
11 Roadway Ex X
12 CSTC Curb Grade X
13 Curb prep Zone A and X X X
ADA Pre con X
14 Pour curb X X
15 sidewalk prep X X X X X X X
16 Sidewalk pour X X X
17
18
19
20
21
IR, CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING Minutes
MARCH 15, 2022
Comments made during Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O
x
Flora Lee, City of Renton x Tani Stafford, G&O
x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan and Ross Widener, Widener x
& Excavating Inc. & Assoc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O
Renton School District _ x
Michael Sippo, City of x Yong Qui, City of Renton x
_ Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Sam Corner, Cornerstone GCI Daniel Aguirre, PSE x
Ed Thompson, Representing Dennis Booth, PSE
Renton School District
Katie Pond, Hoarch James Cohn, Comcast x
Torn Main, City of Renton Gerard Boulanger, Cornerstone
relating to Water Imp.
Kyle Cundy, Cornerstone
Page 1 of 7
CITY OF RENTON
' DUVALL AVE NE
CAG-20-065
2. Safety Report— PCMS board at south end is not operating. Batteries
were stolen.
3. Prior Meeting Minutes—Comments/Acceptance —Accepted
4. Weekly Statement for Working Days ending March 14, 2022
Days Expired: 40
Days Remaining: 220
Asked for extension...need to provide additional information.
5. Schedule Progress
Contractor's Look Ahead Schedule—Same as previous....Reed
requesting extension due to concrete strike & bad weather. Concrete
sub 3 weeks out.
Expected materials that are coming out on-site— No.
6. Utility Coordination
a. Comcast— schedule for cable cut over is this Friday 3/18/22 —
No Change. Day work Scheduled...Steel sheet to be pulled off
b. PSE - City has requested a change order to their contract with
PSE for the undergrounding work to allow for phasing the
work in two phases: Work zone C and Work zone D/E —sent
3/8/22
c. PSE schedule for wire and cut overs in work zone C— 1 % -2
weeks out, 4-5 days for pulling. Only PSE wires are on poles.
d. Existing PSE Street light at the SE corner of Duvall and 9th to be
disconnected and removed by PSE — Daniel will follow up
internally.
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: updated plans are in review by the
City.
b. Water crossing schedule/availability of DI pipe-
Page 2 of 7
tY OT
+ Mite +
CITY OF RENTON
N10 DUVALL AVE NE
CAG-20-065
c. Gas crossing schedule—
d. Conduit crossing schedule-
e. School Borings planned 4/4—4/6. Should not interfere with
Reed's work.
8. Engineer's Report
a. Received request for time extension due to Concrete Strike—
City requests back up of schedule showing how the strike
impacted the critical path.
b. Price adjustment for concrete in work zones A and C during
concrete strike— Will revisit price adjustment. Dustin unsure of
price changes, will ask for a locked in price from CSI.
c. Reed Trucking may provide a wall measurement and payment
revision for consideration — Dustin proposes changes to clarify
sidewalk/wall line. Face of wall measurement removed to come
up with 1130. The dollar amount will be sidewalk with rebar
sticking up. Phil has reviewed stacking along 7th to 9t" it doesn't
appear any of the wall can be deleted in this section.
OWNER MP,_,
NI"111011101,010 t, r
IOMTF1gt PER 3TG SfO it h•.. 6' i
TiAAfr t 4
PUN
AND WTYFR._.. ' V A 1S"_
wasi� DTP
K!1'-11' OPTID
.._. w!sm.NOO[ ._'` CON41
4*CSTCPEA
S1O.Pt,AN
d. Schedule ADA meeting prior to first curb pour — 3 weeks out.
e. Barhudarian Claim —the City of Renton's risk management
has/will send Reed Trucking the Tender letter/Claim for
regarding the cracking wall/4704 NE 7th PI property— Flora
forwarded PDF copy to Reed and has been sent via USPS certified
mail.
Page 3 of 7
}
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
f. Staging area.... not received formal statement to move. Potential
Issue with storage of upcoming asphalt pulverization and reuse
as base rock. Dustin stated, if different staging area is needed,
preference on area at water town near Hazen High School. Bob
—as long as they give notice to property owner and Reed...notice
cannot only be sent to City.
Ross—outside of ordinary high-water mark so not a CWA issue.
Code enforcement has not red tagged property. Bob will talk
over with Martin who can talk to Chip. Email from code
enforcement stating a Temporary Use Permit is not required for
staging area.
9. Inspector's Report
a. Material testing —Subgrade
b. Traffic Control issues — PCMS Board. Any road closures coming
up? None.
c. Wage Interviews —
d. Potholing—
10.Environmental Compliance Report -
Monitor Totem, and be careful where pumping near open catch basins.
Socks at 10th getting full.
11. Public Outreach
• PCMS boards are up in advance of moving to Work Zone A
12.Submittals/Documentation
a. Review ROM — no updates to the ROM since last week
b. Submittals under review: RAM 046A Metal form
c. RAMs that need to be submitted:
• BI 10. 01.03 —Tie rods for anchor blocks -
d. Non-Material Submittals that need to be submitted:
Page 4 of 7
COY OA,
+ t
CITY OF RENTON
4), DUVALL AVE NE
CAG-20-065
e. Material Documentation —
• HMA documentation —Toxicity Testing and Cert. of Toxicity
Characteristics for RAP.
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket.
13. RFIs —
RFI 14 — regarding Magnolia Stellata is in review - Jordan is checking
nurseries
RFI 15 —flashing beacon relocation with foundation has been
responded to
14. FWD/ Change Orders—
• FWD 11 — relocate street light L12 — in the works
• CO 2 - FO Termination Panel change— signed by Bob
• CO 3 —Triple Tree Removal —signed by Bob
• CO 4— Remove requirement for Tier 2 on CS from recycled pits —
signed by Bob
• CO 5 —for trench backfill and dealing with water — Signed by Bob
• CO 6 — Changes to Storm line CB 2 and CB 6 —signed by Bob
• CO 7 —for storm improvements at 9th — Signed by Bob
• CO 8 - price adjustment of concrete in work zones A and C — in the
works
• CO X—for school district revisions — in the works
CO 2 thru CO 7 to be included in Progress Payment No 4.
Page 5 of 7
Y °A
CITY OF RENTON
4)E"T0"‘ DUVALL AVE NE
CAG-20-065
15. Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR
1. Ground Up Road Construction, Inc.
2. Green City, Inc.
3. Totem Electric of Tacoma, Inc.
3a. Integrity Networks(Lower Tier)
4. Lakeridge Paving Company, LLC
5. Stripe Rite,Inc.
6. C&P Fencing
7. W.E. Coates
8. Legacy Tapping, Inc.
9. PnD Logging
16.Certified Payrolls—
Cee11Md P..rolla
Progress Payment No 1(Deeember)
Week Eodlq O. 25-Sep 2-0rt 9-Ott 111-O0 23-Oct 39-Oct 4No, 13-No. lb-Nov 17-Nor 4-D"r 11-IM 14pc 23-Dec
Reed Tn.ckmt X _ X _ X X X X _ X X X X X X X X
Progress Payment No 2(J.00.ry) Molar Payment No 3(Feb.oa7) Prowess Payment No 4(Marsh)
Week Ending Om Ilan Sloe 15-J.o 22-Jon 29-Jon 5-Fek 12-Feb 19-Feb 26-Feb S-Mr 12-Mar 19-Mar 26-M.r 2-Apr
Raad Tnrkkn4 4-1m 18-Jan 27-Jan .18-Jan 4-Feb 10-Fab 1-Mr 1-Mm e-Mor
W.E.Coemr X Man 28-Jo No Work No Work No Week No Work 1-Mar No Work X X
Toter Electric X X 28-Jan :8 ion No Wok No Wok 1-Mor 1-Mar 3.61ar
PuD Lowing X X X X X X X 1-Ma X X X
Week Contractor Subcontractor is on the job site,payroll required **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required
15-Feb Date certified payroll was recieved
Corrections to payroll required
(� _ _ Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final'payroll
17. Progress Payment—
• Progress Payment No 3 — processed
• Progress Payment No 4— March 315t
Page 6 of 7
.,,,,R
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule :_.ram -.�1 _r .LJ)
Work Zone C-Jan-March 25 2022 ME i — -I
ork Zone A-Feb 25 to March 25 2022
W k�D J
'Work Zone B 8 E-March 28 to Aug 22.2022 ..� }
W
Work Zone F(Medians)-Nov 9 to Dec 20 2022
\4 ? J=-� y P'61IECT - I
`
2
LOCATION I NE rift_T
DutE +
NT
.iIII'� _ s, l .,
,. .
i_ • O
ITIOL°.-- 71 ___ ..qc:_iior.
' ` d ._- _ NE 6TH ST .. s
)44, klii
z i
ME RTH ST I
PROJE -
LOCATION
mil. 4,Licir°`t_.-/
I f ■■ 1 } I
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TO SCARE
-SCHEDULE
Page 7 of 7
REEDC. Date:03/12/22-04/01/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
s..«......<..<...�.....,...«. March
Sched
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/Resources
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
2 Illumination X X X X X
5 Roadway Er X X X
6 CSTC Curb Grade X X X
7 Workzone A
8 erosion control X
9 demo X
10 storm X X
11 Roadway Er X X
12 CSTC Curb Grade X X
13 Curb prep Zone A and C X X
14 Pour curb X X
15
16
17
18
19
20
21
G\�Y o .
CITY OF RENTON
‘1. DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MARCH 08, 2022
Comments made during Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O
x
Flora Lee, City of Renton x Tani Stafford, G&O
x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc. x
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc. x
Traci Brewer Rogstad, Michael Ballard, G&O x
Renton School District
Michael Sippo, City of x Yong Qui, City of Renton x
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Sam Comer, Cornerstone GCI Daniel Aguirre, PSE x
Ed Thompson, Representing Dennis Booth, PSE x
Renton School District x
James Cohn, Comcast x
Tom Main, City of Renton Gerard Boulanger, Cornerstone
relating to Water Imp.
Dennis Booth, PSE x Kyle Cundy, Cornerstone
Page 1 of 7
Y
(_ C T
+ +0CITY OF RENTON
�e N 7"� DUVALL AVE NE
CAG-20-065
2. Safety Report— None.
3. Prior Meeting Minutes—Comments/Acceptance—Accepted
4. Weekly Statement for Working Days ending March 7, 2022
Days Expired: 35
Days Remaining: 225
5. Schedule Progress
Contractor's Look Ahead Schedule—
REED c. Data:03105122•03125122
3 Week Look•Ahead Schedule
H
IR4. XAYQ a EXCAIIITIMG Name: Oswalt Avon..
.._...r.....—r..._.... Yard.
soma
ID Work Description SIM TWT FSISM TWT F S $ M T W T F Notes I Resources
a e X I e II 11 I] 13 11 13 16 1] Itl 1a M i1 t7 ]] to 21
2 x x x x x XXXXX
a ndartlonat aa.m oa un x x
6 awd.,y E. X x x
6 CSnc cure G,d. X X X
7 uer.xene a
8 eromen contra X
0 demo X
10 slonn X x
11 pwdve5G — X X
12 OTC C8.3,4de X X
U roprep:me4antic X X
to war uak X X
15
Hold ADA meeting before curb. PCMS is up for shift to Zone A.
Expected materials that are coming out on-site— None
6. Utility Coordination
a. Comcast— schedule for cable —lames—90% complete. Used
existing conduit. Cutover next week.
b. PSE - schedule for wire and cut overs —Looked at Phase C, can
be done independently, but remainder of phases need to be
one mobilization. Change Order for additional mob on Phase C
required. $15k-$30k anticipated cost. PSE crews 2-3 weeks
out.
Dustin needs PSE there ASAP if City elects not to have PSE
demob/mob again. Cutover needs to happen before curb is
Page 2 of 7
R'� * CITY OF RENTON
nr'
DUVALL AVE NE
CAG-20-065
placed in 2 weeks. Are there service conversions? Pole at gth
only has PSE on it. PSE to send CO estimate to City and
schedule of their removal work. PSE suggested a separate
meeting between PSE, City and CM team to discuss phasing
and contractual obligations.
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: Ed: Working on getting contract
approved by school board. Contract signed within 2 weeks.
Contractor working with subs for meters for crossings.
Permitting from City is needed for crossing permit.
b. Water crossing schedule
c. Availability of DI pipe for same
d. Gas crossing schedule — Possibly trench for the gas
e. Conduit crossing schedule
8. Engineer's Report
a. Standby time claim for 2-3/4-22 will be accepted. Will send
formal response.
b. Trench patch second review (RFI 9 Response) — City states that
trench patches are shown in the plans and covered under the
bid item BI A37 HMA Cl. % In. PG 64-22.
c. Wall revisions per FWD No 07 have been deleted.
d. Transition to Work Zone A — PCMS boards are up and truck
detour signage in the works
9. Inspector's Report
a. Material testing — No issues
b. Traffic Control issues — No issues
c. Wage Interviews — No issues
d. Potholing — No issues
10.Environmental Compliance Report - Jordan —JUT South of 9th is open
right now. Grade shoulder to keep work zone water off roadway.
Page3of7
%
CITY OF RENTON
"T°a DUVALL AVE NE
CAG-20-065
11. Public Outreach
• A second round of outreach was performed for 3/7/22 temp road
closure on 9th
12.Submittals/Documentation
a. Review ROM — David sent this out.
b. Submittals under review: RAM 005A Original Paint submittal —
was returned. Received culvert pipes.
c. RAMs that need to be submitted:
• BI 10. 01.03 —Tie rods for anchor blocks -
d. Non-Material Submittals that need to be submitted: none
e. Material Documentation —
• HMA documentation —Toxicity Testing and Cert. of Toxicity
Characteristics for RAP.
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn. for March 2022 - received& approved
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mtn -- received& approved
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket.
• DI water main material on hand —certs are required for
payment on Progress Estimate.
13. RFIs—
RFI 14— regarding Magnolia Stellata is in review
14. FWD/ Change Orders—
Page 4 of 7
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 2 - FO Termination Panel change— 3 sig's sent to City
• CO 3 —Triple Tree Removal — 3 sig's sent to City
• CO 4— Remove requirement for Tier 2 on CS from recycled pits — 3
sig's sent to City
• CO 5 —for trench backfill and dealing with water— 3 sig's sent to
City
• CO 6— Changes to Storm line CB 2 and CB 6 —3 sig's sent to City
• CO 7—for storm improvements at 9th — 3 sig's sent to City
• CO X—for school district revisions — in the works
• CO 8—for walls — DELETED
15. Subcontractor Status—
REQUEST
NO. SUBCONTRACTOR
1. Ground Up Road Construction, Inc.
2. Green City, Inc.
3. Totem Electric of Tacoma, Inc.
3a. Integrity Networks(Lower Tier)
4. Lakeridge Paving Company,LLC
5. Stripe Rite,Inc.
6. C&P Fencing
7. W.E. Coates
8. Legacy Tapping,Inc.
9. PnD Logging
16.Certified Payrolls—
Cert ed Payrolls
Progress Pr t No 1 bye
Week Ending Out 25-Sep 2-Oct 9-0el 16-0et 23-0et 30-OttNov (Die
20-Nov 27-Nov 4-Dee 12-Dec 10-Dee
Reed Tntckin2 X X X X X XX X X X X X X
PP Na 1 Progress Payment No 2(January) Progress Payment Na 3(February)
Week Ending Om 25-Dee 1-Jan 0-Jan 15-Jan 22Ju 29Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar
Reed Trucking 4-Jan 4-Jan 18-Jan 25-Jen 28-Jan 4-Feb 10-Feb 1-Mr I-Mar 4-Mar
W.E.Coates X X 18Jen 28-Jan No Work No Work No Work No Work 1-Mar No Work X
Totem Electric X X X 28-Jan 28-Jan No Work No Work 1-Mar 1-Mar 4-Mar
PuD Long X X X X X X X X 1-Mar X X
Page 5 of 7
_I a 01 b
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Week Contractor Subcontractor is on the job site,payroll required_ **( 12)indicates payroll number**
X Subcontractor was not on-site this week "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubnuttal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
17. Progress Payment—
• Progress Payment No 3 — in the works. PP No 3 was submitted to
the City yesterday.
18.Revisit retaining wall discussion —
Discussed walls and options such as modular block wall and sloping to
eliminate need for walls.
Concrete sub on Sunset Lane (CO for a luminaire) was Caliber Concrete.
Check in field where walls may not be needed.
Bob: City will assist Contractor in deeming what is buildable but there
should be no cost increase. $200 per SY.
Page 6 of 7
G j,,
IR+ CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule _ . / —'
C
Work Zone C-Jan-March 25 2022 NE
Work Zone A-Feb 25 to March 25 2022 Iwo Z__I }
Work Zone B 8 E-March 28 to Aug 22.2022 T ,t
Work Zone F(Medians)-Nov 9 to Dec 20 2022
*\ 2
,
LOCATION — ; _
INT
• INElOT<LILST
a um
nall ir,,,,„
J
4,-Ah'ill , iliko
r
1 =NW
1 5 2L _ fl' :
‘111 ;
1 __ r.
PROJECT — —
LOCATION
1�� I Ii-
5CHIOULL A
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
-
NOT InKAIl Sr HI UUIE(.
Page 7 of 7
REEDc Date:03/05/22-03/25/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
r..« March
Soled
ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/Resources
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
2 Illumination X X X X X X X X X X
4 Additional storm on 9th X X
5 Roadway Ex X X X
6 CSTC Curb Grade X X X
7 Workzone A
8 erosion control X
9 demo __ _ X
10 storm X X
11 Roadway Ex X X
12 CSTC Curb Grade X X
13 Curb prep Zone A and C X X
—14 Pour curb __ _-- X X
15
16
17
18
19
20
21
%
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
MARCH 01, 2022
Comments made during Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O
X
Flora Lee, City of Renton X Tani Stafford, G&O
X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan Widener, Widener & Assoc. X
& Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc. X
Traci Brewer Rogstad, Michael Ballard, G&O X
Renton School District
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Sam Corner, Cornerstone GO Daniel Aguirre, PSE X
Ed Thompson, Representing Gary Bradley, PSE
Renton School District X
Katie Pond Hoarch James Cohn, Comcast
Tom Main, City „f Renton Gerard Boulanger, Cornerstone
relating to Water Imp.
Kelsey Marshall, City of ,
men
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report— Totem put boards over metal pipe used for street
light foundation forms, no safety issues.
3. Prior Meeting Minutes—Comments/Acceptance — no comments.
4. Weekly Statement for Working Days ending February 28, 2022
Days Expired: 30. Monday was an unworkable day due to rain.
Days Remaining: 230
5. Schedule Progress
Contractor's Look Ahead Schedule—
REED c 7 Week Look-Ahead Schedule
Dale:02126R2-07118J22
TRUCKING A EXCAVATING Name: Duvet Avenue
Febu
sow
ID Work Detaipaon SIIMTWT F S $ N T W T FISSM T W T F Notes l Resources
1 iuravaurc i.nuanon R X
2 mmialx X X X % X X X X X X X X X X
I roSJng o nwii X X X X
6 ndonw on sm+ X X
5 enae061 ra X X X X
li (STC Curb Gadx X X X X
7 WOry pp A
C eoaon coma %
9 c nv X X
0 X X X
„ al ea X
12 CStC Curb Gie4. X
1]
Dustin: Finishing work on JUT
Tani: PCMS signs will need to go up 10 days before switching to Work
Zone A. PCMS to be placed by end of week.
CO 7—sent out for SW work done at 9th
Soonest in-road work is Thursday for road closures. Friday preferred
due to rain. Send out notifications once date is solidified.
Expected materials that are coming out on-site— none from Reed.
Page 2 of 7
V4
�Z v
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
6. Utility Coordination
a. Corncast — did not attend. Per Phil: out there with SFENCO,
replaced and installed 2"conduit sweeps. Waiting for pole
connection.
b. PSE - Daniel joined later on. Daniel to discuss schedule for
wire pull with Potelco.
Per Phil:Approved conduit on Friday. Installed new 2-inch run
from P02 to pole. Potential interference with crossing on
Duvall (Totem may be trenching) on Wed/Thurs per Dustin.
Phil asked for easement on 9th and Duvall....should get it
today.
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: Ed— bid opening 3/2. Will be
checking on availability of D.I. Pipe.... want water installed
ASAP. Updated drawing in addenda with matching stationing
between projects to be provided.
8. Engineer's Report
a. The stormwater diversion work on 2-9-22 determined not
eligible as FWD No 5 work. Will send formal response.
b. Standby time claim for 2-3/4-22 will be accepted. Can this be
included in CO No 5 force account payments since it is water
related. Will send formal response.
c. Plastic Line for bid items A88 and A89 is not going to be included
in the project in lieu of the paint line. Bob: Provide explanation
why MMA will not be used, and note spec WSDOT standards in
submittal review.
d. Anchor bolt lengths are going back to original plan length. Will
send formal submittal.
e. Expanded grind and overlay per FWD No 6 will not be
constructed. Will not be done. Use limits on plans
Page 3 of 7
i
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
f. Trench patch second review (RFI 9 Response) — City to send a
formal response. Underway.
g. Water double check valve/meter contact sent to Reed —
scheduled to be picked up by Jordan. Dustin will let us know if
there are any issues.
9. Inspector's Report
a. Material testing — none
b. Traffic Control issues — none
c. Wage Interviews — Completed for Totem
d. Potholing—Pothole for Telephone near 9th
10.Environmental Compliance Report -Jordan Weidner—stockpile is
creeping. There's another pile of sand at 9th, should be removed today.
If not, make sure ditch line is back open. Also using dewatering through
pond again. Turbidity test results are acceptable.
11. Public Outreach
• Temp Road Closure - Doorstep fliers went out to neighbors of
9th/Duvall - CO 7 work...may need to redo date. Dustin will confirm on
date.
• Email notification went out on 2/25 to Emergency Services, Transit,
Postmaster
• Email notification went out to School Dist 2/25
12.Submittals/Documentation
a. Review ROM —sent out...updates to include recent approved
submittals.
b. Submittals under review: RAM 73B Anchor Bolts, underway. Paint
resubmittal required
Page 4 of 7
Oc
IRM * CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. RAMs that need to be submitted:
• BI 10. 01.03 —Tie rods for anchor blocks
d. Non-Material Submittals that need to be submitted:
e. Material Documentation — David sent some emails to Tiffani/Reed
for these:
• HMA documentation —certification letter, Toxicity Testing
and Cert. of Toxicity Characteristics for RAP.
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn. for March 2022
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mtn
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket.
• DI water main material on hand—certs are required for
payment on Progress Estimate.
13. RFIs —
RFI 13 —confirmation that A88 and A89 will be paint line, not plastic
14. FWD/ Change Orders—
• FWD 6 - deleted. The overlay will not be expanded at 9th
• FWD 4A— 12" polypropylene storm pipe at 9th was sent out
• CO 2 - FO Termination Panel change— 3 sig's sent to City
• CO 3 —Triple Tree Removal — 3 sig's sent to City
• CO 4— Remove requirement for Tier 2 on CS from recycled pits — 1
sig, sent to Reed for signature
• CO 5 —for trench backfill and dealing with water — in the works
• CO 6 — Changes to Storm line CB 2 and CB 6 — in the works
• CO 7—for storm improvements at 9th — in the works
• CO X—for school district revisions — in the works
Page 5 of 7
S _r,
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 8—for walls —in the works
4-7 have been sent to Reed, and are under review.
15. Subcontractor Status— need SOI for PnD Logging
REQUEST
NO. SUBCONTRACTOR
1. Ground Up Road Construction, Inc.
2. Green City, Inc.
3. Totem Electric of Tacoma, Inc.
3a. Integrity Networks(Lower Tier)
4. Lakeridge Paving Company, LLC
5. Stripe Rite,Inc.
6. C&P Fencing
7. W.E. Coates
8. Legacy Tapping, Inc.
9. PnD Logging
16.Certified Payrolls—
PP No 1 Proves,Payment No 2(January) Prowess Payment No 3(February)
Reek Ending On: 25-Dee 1-Jan 6-Jan 15-Jan 22Jae 29Jan S-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar
Reed Tmvckin2 4-Jan 4-Jan Wan 25Jan 28-Jan 4-Feb 10-Feb
W.P.Coate, X X 1S-Joe 28-]an No Work No Wode No Wort X X
Totem Electric X X X 28Jan 28Jan No Work No Wort X
Pun Losing X X X X X X X X X
Week Contractor-Subcontractor is on the job site,payroll required **(#12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
-
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final payroll
17. Progress Payment—
• Progress Payment No 3 —cut off is 2/28/22 — rain day.
Other items discussed—PMX to review control information at 4th
Page 6 of 7
lr
,IR
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Phil to visit Totem yard to inspect material on hand
Schedule _ --I
L Work Zone C-Jan-March 25 2022 I'NE RYA
Work Zone A-Feb 25 to March 25 2022 Q J
Work Zone B 8 E-March 28 to Aug 22.2022 g
Work Zone F(Medians)-Nov 9 to Dec 20 2022 _
.0o aLOCATION\ —4: TT_ tilP, -• MU
---4— 1 - —
1 all 111 all ____.._ 1
, lirir
_ .kj 1 N -• • --
1
4'pETM
<I
4 4 Iti* i A
I - —:111ifir /41.1*1 . a5 warm ST
NEITHST
PR�JEC'T -
joppril LOCATION
.." 11.1111\air
1"..I as 6 F:,- i
- i
WATER MAIN IMPROVEMENTS
N -SCHEDULE 8
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT TOSCMF -SCHEDULE
Page 7 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
February 22, 2022
Comments made during Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan Widener, Widener &Assoc. X
& Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc. X
Traci Brewer Rogstad, Michael Ballard, G&O X
Renton School District
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric X Dmitri Suslikev, Parametrix Ins
Sam Corner, Cornerstone GO Daniel Aguirre, PSE X
Ed Thompson, Representing X Gary Bradley, PSE
Renton School District
James Cohn, Comcast
Tom Main, City of Renton X Gerard Boulanger, Cornerstone X
relating to Water Imp.
Kelsey Marshall, City of X Kyle Cundy, Cornerstone X
Renton
Page 1 of 8
;MIN CITY OF RENTON
DUVALL AVE NE
CAG-20-065
2. Safety Report— Staging yard had vehicle break in (per Phil). Over the
weekend or Monday(holiday). Totem's pickup truck had passenger
window broken, and tried to start/move equipment.
3. Prior Meeting Minutes—Comments/Acceptance -Accepted
4. Weekly Statement for Working Days ending February 21, 2022
Days Expired: 26
Days Remaining: 234
5. Schedule Progress
Contractor's Look Ahead Schedule—sent out prior to meeting.
Working on JUT and illumination (2 weeks, give or take), next storm
crossing at Duvall& Storm change at 9th. TV inspection to be
completed.
Expected materials that are coming out on-site— Culvert Pipe.
Short on 3 inch conduit by PSE—Daniel—stub out to future fiber vault
FV1 (not onsite yet). Fiber team will excavate and install vault. PSE
can get conduit on site quickly. Fiber contact provided by Daniel:
Dennis Libadia Dennis.Libadia@pse.com
Puget Sound Energy
Advisor Fiber Transport Engineer
9515 Willows Rd NE
Redmond, WA.
425 223-2108 cell
6. Utility Coordination
a. Comcast— not discussed
b. PSE - HH issue at 7th...Daniel is working with ROW person to
know if HH can go in easement. If no easement...could shift
into sidewalk(has non-skid lid). Bob: It should be a bit below
finished grade and adjusted accordingly. BOW elevation to be
provided by Parametrix or shifted slightly towards end of ramp
where elevation already known.
Page 2 of 8
•
.zy
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Totem needs power source for service relocation at 12th
Relocated service on sheet E6 is likely powered by vault along
12th to west of project. Daniel to verify.
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: Ed Thompson —School will be
starting construction soon —access provided off of 12th
Construction entrances on Duvall on the 4th. Access but no work
on Duvall. Tani—Reed will be moving to Workzone E(along
school frontage) tentatively April. Access through Duvall will
require coordination and be inaccessible at times. 105 days
(end of August). Ed—requesting 2 lanes open for Duvall. Dustin
- CL to back of sidewalk will be taken up for construction. Kyle:
Access to 12th off of Sunset would be ideal. Michael agrees.
Michael working on getting water& gas permits going...so Kyle
can get going ASAP. Conflict with water main construction
between 10th & 12th
b. Reed Trucking confirmed street lights have been ordered,
anticipated end of May 2022.
8. Engineer's Report
a. Long lead-time items —Streetlights have been ordered, and
going back to the original bolts. Anchor bolts not ordered yet
b. City looking into relocation of HH1, to the north to avoid the
need for a wall —Already discussed earlier. FH may need a small
wall...ped curb possibly. Phil to do some measurements.
c. Reviewing the stormwater diversion work on 2-9-22 to see if it is
eligible as FWD No 5 work. Still working on it.
d. Standby time claim for 2-4-22 in review. 3' & 4th
• Resident Engineer's review says this day was an
unworkable day due for the critical path item of storm
trench excavation due to the wet shoulder conditions
without a proposed solution agreed to remove the
water for the morning of 2/4/22. Dustin —It was
Page 3 of 8
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
Thursday/Friday(resolution mid-morning). Tani—hours
match the 3rd. Dustin—labor hours are for 3rd. Equipment
hours are for 3rd. Standby time is also for the 4th. G&O to
verify with City and provide response.
• The standing water in the shoulder was observed to be
present after 2 weeks of dry weather.
• The Contractor submitted his Proposal for dealing with
the water on 2/3/22 —3:00 PM and again provided
additional information at 'r5:00 PM as requested.
• The City was not able to confirm that the Contractor's
proposed method of disposal was allowable that
evening so an unworkable day was granted for the
following day of 2/4/22.
• The City obtained consensus on the proposed water
disposal method and gave direction to proceed with the
proposed water disposal mid-day on 2/4/22.
• The Contractor has submitted a claim for standby time
for 2/4/22. 3rd& 4th
e. A new wall detail in the works for the 2' high wall near Sta.
917+78 RT Parametrix is working on it.
f. Junction boxes for street lights to be set within sidewalk, Reed
to refresh centerline offset to assist with field direction for
placement. JB's to be within sidewalk areas where walls are
proposed. Prefer to keep out of walk but okay within walk if no
other place to go. Back of walk is back of JB.
g. Direction given that FWD No 5 trench backfill restriction is not in
affect with drier conditions. Noted.
h. Received word from City Water Dept (Abdoul) that they do not
want to waive the requirement for thrust or anchor blocks.
i. Trench patch second review (RFI 9 Response) — Resident
Engineer's interpretation is that all permanent HMA mix work
required is covered under the "HMA Cl. 1/2 In PG 64-22" bid item
in the Proposal, per the payment item description in 5-04.5 of
the Special Provisions. City Reviewing. City, G&D and Parametrix
Page 4 of 8
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
agree that it is covered under the HMA pay item under 5-04.
Dustin disagrees—patch across 9th. Illumination, irrigation and
water are Dustin's argument, not SD. Potential for abandoned
water pipe to be used for sleeve for new street light illumination.
Bob: check with utilities group.
j. Have Anchor Bolts been ordered/fabricated. No. City would like
to go back to the design length.
k. City reconsidering need for plastic—vs-paint —Noted. CO will
stay on hold.
9. Inspector's Report
a. Material testing — OK for compaction testing
b. Traffic Control issues — Haven't seen any. Need flaggers for cross
street impacts.
c. Wage Interviews — P&D logging
d. Potholing - Staking to be done ahead of work-provides time to
see if potholes needed. Tani asked Reed for staking control for
offsets to CL alignment.
e. Water—school will need to cross all the way to the east for
connection —coordination needed. Our watermain improvements
are 12th to Sunset on west side.
10.Environmental Compliance Report
Jordan —stockpile at 9th to be covered if sitting 3+ days, or provide straw
wattles, or move it.
Not planning to jet out storm until sidewalks/curb/gutter in - clear out
bottom of manholes beforehand. City crews were mowing...crews moved to
keep grass-lined ditches. Phil has concerns about mowing through stakes.
Bob—mowers are relocated.
Pond overflow went into ditch that is no longer there.... Phil thinks the
overflow can sheet flow over sidewalk to new CB's. Bob defers to Phil.
Page 5 of 8
°,c
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11.Submittals/Documentation
a. Review ROM —
b. Submittals under review: RAM 73B Anchor Bolts, FA Equipment
Rate Resubmittal of 2-15-22 has been reviewed
c. RAMs that need to be submitted:
• BI 10. 01.03 — Tie rods for anchor blocks
d. Non-Material Submittals that need to be submitted:
e. Material Documentation
• HMA documentation — certification letter, Toxicity Testing
and Cert. of Toxicity Characteristics for RAP.
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn. for March 2022
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mtn
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket.
12. RFIs—
RFI 11- Station and offset and back of sidewalk elevations given for
JUT utility vaults
RFI 12 — Light Pole 8 foundation in review
13. FWD/ Change Orders—
• FWD 6 for expanding grind limits at 9th St —sent out
• FWD 8 for CB 2 to CB 6 revision —sent out
• FWD 9 for triple tree removal —sent out
Page 6of8
jnraisk
iN
75 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 2— Plastic Line—City reconsidering
• CO 3 - FO Termination Panel change— in the works
• CO X— Remove requirement for Tier 2 on Crushed Surfacing from
recycled pits - in the works
• CO X—for trench backfill and dealing with water— in the works
• CO X—for storm improvements at 9th— in the works
• CO X—for school district revisions—in the works
• CO X—for walls — in the works —need new wall detail from PMX
and then need quote from Dustin.
14. Subcontractor Status— need SOI for PnD Logging
REQUEST
NO. SUBCONTRACTOR
1. Ground Up Road Construction, Inc.
2. Green City, Inc.
3. Totem Electric of Tacoma, Inc.
3a. Integrity Networks(Lower Tier)
4. Lakeridge Paving Company, LLC
5. Stripe Rite,Inc.
6. C&P Fencing
7. W.E. Coates
8. Legacy Tapping,Inc.
9. PnD Logging
15.Certified Payrolls—
Pevrdle
PreOs sl Net L Wed/Fr{Ob 23-X&P 2-Oct 1-X0
e1 1LXO el 2YXO d 3RXO d� X.. Dc3-X w 2•XN e 27-N ee 4-DXe e 11X ee 1SXDee
ReedDOdeq PPNe 1 Pewees Psmeet Ns 2 Jmmme) Peered Paned N.3(Febeeme1
Week Fe`{Ow 23-Dee Ili LJ.e 16Jen 2-. 25J.e SFd 12-F0 le-Feb 24.Fe 3-Mr 12-M0
Reedmdd8 440 4-1m 18-Jo 25-Jo 23-70 4-Feb 10-Feb
W.F.Coates X X 13-Jon 214o No Week No Week No Work X X
Totem Electric X X X 23-Jm 211d0 No Week No Work X X
W.E.Codes `
FeD Lopdmk _.
Page 7 of 8
G
+ +iiii
CITY OF RENTON
�E.Arro DUVALL AVE NE
CAG-20-065
Week Contractor Subcontractor is on the job site,payroll required_ **(=121 indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doe's required _ - - -
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16. Progress Payment—
• Progress Payment No 2 — Has Reed received the payment? Yes.
• Progress Payment No 3 —cut off will be 2/28/22
Schedu•e ctvo
szow `Work Zone C-Jan-March 25 2022 Mrst,n
Work Zone A-Feb 25 to March 25 2022 z "
ill
Work Zone B&E March 28 to Aug 22.2022
}
Work Zone F(Medians)-Nov 9 to Dec ZO 2022 l —,
mit
. 4 cir''`. ',
L.3 •N - IV -lit i .,_—
ini
our.
i al
*ape1 :7rH
Z
) IF ie LA e7-- , I.4 ... tit snisr g
.111 i Nr♦TH ST
( ...., .g. --i.
I\1111111111111117:1
LOtCATTIION,WI
IFy
�� SU WATER MAIN IMPROVEMENTS
N -SCHEDULE 8
VICINITY MAP UNDERGROUND IMPROVEMENTS
NW IUSCA1k -4(-H )UIF[.
Page 8 of 8
REEDC. Date:02/19/22-03/11/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall A
Feburary
Sched
ID Work Description SS M T W T F SS M TWT F SS M T W T F Notes!Resources
19 20 21 22 23 24 25 28 27 28 1 2 3 4 5 6 7 8 9 10 11
1 JUT&Vault Installation X X X X X X X
2 Illumination X X X X X X X X X X X X X X
3 storm crossing on dwall X X
4 Additional storm on 9th? X X
5 Roadway Es _ X X X
6 CSTC Curb Grade X X X
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
C
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
February 15, 2022
Comments made during Meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton I X Phil Van Earwage, G&O X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan Widener, Widener & Assoc. X
& Excavating Inc.
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc. X
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O X
Renton School District
Michael Sippo, City of X Yong Qui, City of Renton X
Renton
Fred Duke, Totem Electric Dmitri Suslikov, Parametrix Inc.
Sam Corner, Cornerstone GO Daniel Aguirre, PSE
Ed Thompson, Representing X Gary Bradley, PSE
Renton School District
Katie Pend Hearch James Cohn, Comcast
Tom Main, City of Renton
relating to Water Imp.
2. Safety Report — No concerns.
Page 1 of 9
IN
5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Bob—there was a claim about device going into tire.... team was
unaware what that was about. Bob responded that they did not believe
it was from our Contractor.
SUMMARY&DESCRIPTION MEDIA
Other
Drove along Duvall this afternoon and there was a lot of
road debris from the construction.Unfortunately caused
a flat tire that needed to be thrown away
Reported by:Renton,WA Neighbor 02/01/2022-02:45PM '
II
t.
TIMESTAMP INTERNAL COMMENT COMMENTER
February 01,2022 14:45 Renton,WA assigned this issue to Mayor's Office Renton.WA
Plus sheetrock cracking on house issue was discussed. Claim for damages
for cracked sheetrock...but if they didn't have pre-construction photos of
uncracked sheetrock, they cannot prove it was our construction that
caused the cracking. Phil said it was sheetrock cracking...interior walls.
Usually caused by piers settlement under the floor joists. House has
crawls pace. Was not caused by our work. Dustin may have pictures as well
but here's Phil's picture. No action taken on this for now. Wait for claim to
City..to Contractor...to Contractor's insurance to provide response. Flora
Page 2 of 9
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
has claims forms to share with Phil, if citizens ask for it, he can give it out.
11111114111
3. Prior Meeting Minutes—Comments/Acceptance - Accepted
4. Weekly Statement for Working Days ending February 14, 2022
Days Expired: 22
Days Remaining: 238
5. Schedule Progress
Contractor's Look Ahead Schedule - From Dustin today—RFI out
asking for vault Sta/Offset by Wednesday. Surveyor scheduled to be
onsite on Friday.
REEDDate:02I1 2122.03104122 3 Week Look Ahead Schedule
MUCOOI1IO a EXCAVATING Name: Duvall Avee uc
Fame
seaaa
p l Work Oscripn on 5 5 M T W T F a a M T N T ! M T W i F NOteS/RBSOUfCeS
t smm x x x x x
2 IIWa.wvetwwlMar X X X' X x X X X X x
Also be on lookout for sand submittal.
Expected materials that are coming out on-site: Comcast conduit &
vaults are there, waiting on sand.
6. Utility Coordination No utility representation, so skipped items.
a. Comcast —
Page 3 of 9
9 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. PSE -
7. RSD Elementary School 16 Coordination
a. Cornerstone coordination: Ed—it's quiet until end of month.
Moving construction trailer last week Feb/15t week March.
Shouldn't affect Duvall Ave project.
Some details about adding streetlighting...City's work versus
school work. Some Civil coordination needed— working through
it.
b. G&O noted Stating for start/stop of driveway curb cuts along
frontage improvements are needed.
ACTION ITEM: Dustin to verify if streetlights have been ordered.
8. Engineer's Report
a. Long lead-time items - Street lights are long lead item...Fred has
enough info to order anchor bolts.
b. Tom Main, is assigned to help coordination for the City of
Renton's water department and may be on site. Phil is still the
project inspector and Tom will coordinate with Phil and G&O for
scheduling or any issues that may come up relating to City of
Renton's Water Improvements. Tom will not direct the
Contractor. Bob stated Tom does not have the authority to stop
work. Do not stop work.
c. Reviewing the stormwater diversion work on 2-9-22 to see if it is
eligible as FWD No 5 work. Stay tuned for City's answer.
d. Submit Traffic Control Plans directly to Flora with City of Renton
TCP application. There is a separate review process for them.
9. Inspector's Report
a. Material testing —compaction testing this week —hoping recycled
rock will be good enough but enough CSTC in case. Paving towards
end of week.
b. Traffic Control issues — No concerns
Page 4 of 9
'5 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Wage Interviews — Up to date.
Phil recommends potholing for new hydrant locations across the
street to get correct height.
10.Environmental Compliance Report
Jordan —NE 10r" east of street...make sure pile is stabilized every 3 days.
Plus make sure extra materials are picked up by end of day(DEF fluid
example) to avoid spills. Need secondary containment.
Dewatering.... will we need to do this in the future? Dustin...hoping we're
finished with it.
11.Submittals/Documentation
a. Review ROM - updated sent out
b. Submittals under review: none
c. RAMs that need to be submitted:
• BI 10. 01.03 —Steel for anchor blocks
d. Non-Material Submittals that need to be submitted: none
outstanding
e. Material Documentation
• HMA documentation —certification letter, Toxicity Testing
and Cert. of Toxicity Characteristics for RAP. Paving
anticipated end of this week.
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn. Certs provided via CMS are outdated.
Send latest one. Tiffani—it will be updated in March.
Tiffani via Zoom chat—Squak doesn't have 2021 Scale Cert.
Squak working on getting WSDOT pit#.
Page 5 of 9
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mt
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket.
• DI Pipe for Water Main, did it make it onsite?Phil—yes, it's
at their staging yard. Phil took photo of lot#. David to
review and request Certs.
12. RFIs—
RFI 9 —Trench Patch in review - response provided on CMS—Dustin
would like to discuss—he disagrees that anything in 5-04 talks about
trench restoration patchwork. Doesn't see where it's reference
anywhere. Pavement repair section is mentioned but not related to
trench patch restoration. Doesn't agree with response. Patchwork is
handwork. It's small and will cost more. Lakeridge doesn't have
handwork. Tani: 1 —in the appendix there is a trench restoration
detail which references trench patch details. And 2 - COR standard
plans in their entirety are included in the specs intro. Tani& Dustin
are in disagreement with interpretation of HMA trench definition and
whether it was covered in 5-04 description. ACTION ITEM - Dustin will
officially provide a response.
RFI 10—Steel for Water Blocking in review - response provided on
CMS—there are none on thrust blocks, shackle rods required for
anchor blocks. Dustin- can't get concrete so asking if blocks are
needed on fully restrained system. Can they be deleted on this one?
Bob— water dept. demands it so yes, needs to be installed. Dustin
concerned about getting concrete to site. Bob—others have been
using Miles, but they are very busy. Work will take place tentatively in
June. ACTION ITEM—City will wait until it's close to June and will
engage Abdoul if it's still a concern.
13. FWD/Change Orders—
• FWD 6 for expanding grind limits at 9th St—in the works
Page 6 of 9
2.,FeCITY OF RENTON
DUVALL AVE NE
CAG-20-065
• FWD 7 issued for Wall Revisions - Dustin has question -CO...City
asked for revised price for new walk/sidewalk combo, which
reduces quantity for remaining wall for 25%...250 SY down to 33
SY. Can't build at current unit prices. City is reviewing.
• FWD 5-will be coming their way
• CO 2 - Plastic Line- draft sent to City for review
• CO X - FO Termination Panel change- Quote requested.
• CO X- Remove requirement for Tier 2 on Crushed Surfacing from
recycled pits in the works -in the works
• CO X-for trench backfill and dealing with water- in the works
• CO X-for storm improvements at 9th - Dustin sent DI estimate.
Tani to check.
• CO X-for school district revisions -in the works
• CO X-for walls - in the works -need quote from Dustin.
14. Subcontractor Status- looks good
Original Contract amount(t„u). S5,169,697.50 Date of Intent
PERCENT OF TOTAL CONTRACT Request To Po
REQUEST THIS PREVIOUS SUBLET Reed to Saki Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (appevd) DBE Wages
1. Grouted Up Road Construction.Inc. $25,575.00 0.49% 0.00% 0.49% 8:11.2021 8/122021 N 8 2-2021
2. Green City,Inc. 5139,480.00 2.70% 0.49% 3_I9''e 8%11;2021 81122021 Y 831,2021
3. Totem Ekctrk of Tacoma,Loc. S734,636.80 14.21% 3.19% 17.39% 8/12/2021 8 122021 N 8272021
38_ Integrity Networks(Lower Tier) S22,432.15' 3.05% 0.00% 305.12/15/2021 I2/152021 N 8/312021
4. Lakaidge Pasiog Company,LLC $706,900.00 13.67% 17.39% 31.07% 8/16/2021 8/17/2021 N 8/30/2021
5. Stripe Rite,Inc_ S42,778.60 0.83% 31.07% 31.89% 8/162021 8/17/2021 N 8/24,2021
6. C&PFencing S2,177.70 0.04% 31.89% 31.94% 8/20/2021 8/23/2021 N 8/26/2021
7. W.E.Coates S61,500.00 1.19% 31.94% 33.13%12/15.2021 12/15/2021 Y 11/15/2021
8. Legacy Tappug,Inc. S20,150.00 0.39% 3313% 33.52% 1272022 127/2022 N 1/27/2022
9. 0.00% 33.52% 33.52%
10. 0.00% 3352% 33.52%
11. 0.00% 33.52% 33.52%
12. 0.00% 33.52% 33.52%
13. 0.00% 33.52% 33.52%
14. 0.00% 33.52% 33.52%
15. 0.00% 33.52% 33.52%
15.Certified Payrolls- looks good
Page 7 of 9
iFtCITY OF RENTON
DUVALL AVE NE
CAG-20-065
City oMMootoa Coofrart\o.CAI:-36965 - IhnY1 Avrme M.
credited P.m&
Progress Parent No 1(December)
Work Eadla{Oa: 233q 2-Oct 9-Oct 1190et 23-Oct 30-Oct &Noe 13-No, 20-Nw 27-Now 4-Der Il-Dee 1/1-Dee
Reed Tncckkt X X X X X X X X X X X X X
_._
IR No i Progress Payment No 2(Amoy) Progress Paymrat No S(February)
Week Eadlaj Om 23-Dec IJan BJaa 19-Jm 22Jao 29Jn 5-Feb 12-Feb 19-Feb 2-Feb 5-Mar 12-MMar
Reed Truchas 4-Jw 4-Jen _ 18-Im 25Jo 28-]o. 4-Fob 10-Feb
W.E.Costa X X 18Jao 284as No Wart No Wort No Wok X _
Totem Elcctnc X X X 28-1au 28-Jam No Wort No Work X
Week Contractor'Subcontractor is on the job site,payroll required- **(u12)indicates payroll number** _l-
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved i
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received'No Work Performed"payroll
ma
15-Feb "Final"payroll
16. Progress Payment—
• Progress Payment No 2 —submitted to City
• Progress Payment No 3 — cut off will be 2/28/22
Page 8 of 9
if? CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule --- -- `—/
Work Zone C-Jan-March 25 2022 NE a[Yp 6 J
Work Zone A-Feb 25 to March 25 2022
Work Zone B 8 E-March 28 to Aug 22.2022
Work Zone F(Medians)-Nov 9 to Dec 20 2022 r
iop c!..c,i_ [ (....,, 3iTr(1 _
l
L
LOCATION )
„L‘
IIir* riir ....
T
/r: Ili' N
••• ,.,
i.._ =um
i mid
'i' '... _.A.c.I k 1 ■ ���
7 1 1 ,
N(,TI/5T I
PROJECT ; IIIIIIIw---
LOCATION� 1
T
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
Nnrinxrue -Sp1E0UIE(
OTHER: Phil—look at larger tree branches that hang over site...do we want
to take these down? Madrona hangs over up 25 feet or so. But hangs over
lane/second part of lane. Bob— up to Arborist but if not in our way, don't do
anything. Not part of the purpose of the project.
Phil and Jordan have clear understanding of trees to be removed in Work
Zone C.
Page 9 of 9
REEDc Date:02/12/22-03/04/22 3 Week Look-Ahead Schedule
TICKING 6 EXCAVATING Name: Duvall Avenue
,�� m Foburary
Schell
ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/Resources
12 13 14 15 18 17 18 18 20 21 22 23 24 25 28 27 28 1 2 3 4
1 Storm install X X X X X
2 JUT&Vauk Installation X X X X X X X X X X
3
4
6
7
8
9
10
11
12
13
14
15
16
18
19
20
21
II
Ors
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
February 8, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking Jordan Widener, Widener & Assoc. x
& Excavating Inc. x
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Traci Brewer Rogrtad, Michael Ballard, G&O x
Renton School District
Michael Sippo - City of x Yong Qui, City of Renton x
Renton
Gerard Boulanger x Dmitri Suslikov, Parametrix Inc. x
Ed Thompson — Gary Bradley, PSE x
Representing Renton School x Daniel Aguirre, PSE x
District
Katie Pond Hoarch James Cohn, Comcast
2. Safety Report—
Phil noted that Storz adapters installed. Additional reflectors needed for
the turn pocket at 7th.
3. Prior Meeting Minutes —Comments/Acceptance
Comment that the response to RFI No 8 had not yet been sent.
Response for RFI No 8 sent
Page 1 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending February 7, 2022
Days Expired: 17
Days Remaining: 243
5. Schedule Progress
Contractor's Look Ahead Schedule - Start of JUT has been pushed
out one week. Loss of production due to dewatering.
City asked is compaction was achieved on trench backfill material.
Phil noted that material is going in better. Compaction test will be
scheduled for next week.
Expected materials that are coming out on-site: 16" DI Pipe
obtained. Kangley aggregate material.
6. Utility Coordination
a. Comcast— No update
b. PSE - Daniel Aguirre to replace Gary. Confirm PSE inspector
fulfills electrician requirement or will PSE require conduit to be
installed by an electrician.
c. Water District 90— Painting hydrant and placing concrete pads
to be completed
Utility Reps dismissed
7. RSD Elementary School 16 Coordination
a. School Contractor coordination:
School contractor: Cornerstone.
April 4th scheduled time for installing construction site
entrances—2 entrances. Further coordination required since
Reed will take roadway down to dirt, as first order of work.
School to provide update on storm improvement projects
within the next week.
Page 2 of 7
C O�
♦ ilFe
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
G&O asked, who will install the water tie-ins? SD waiting on
bid opening for civil site work— will provide update next week.
RSD rep dismissed
8. Engineer's Report
a. Long lead-time items - None at the moment
b. Intersection at 9th —a FWD in the works to expand the grind and
overlay
c. Upcoming on-site preconst meeting for CB adjustments - Rocky
can be onsite this Wednesday
d. Trenching — a FWD has been issued to address backfill and water
in trench area
e. Field work directive for walls to be issued. The FWD will include
a revised wall section detail and revised payment. A quote from
Reed will be needed. G&O anticipates sending draft FWD to
Parametrix and City today and providing the FWD to Reed this
week.
9. Inspector's Report
a. Material testing — Samples from Icon and Sumner pits received.
Schedule compaction testing for next week to allow the trench to
dry. Phil noted the import material is going in tighter/better. Scale
certification performed on yearly basis for Squak Mountain. .
b. Traffic Control issues — Reflective striping at 7th
c. Wage Interviews — New operator and flogger
10.Environmental Compliance Report
9th/10th —Silt fence around culvert inlet and existing culvert. Straw wattle
or additional rockery may be needed. Prevent discharge to wetland.
Reed's sweeper has been removed from job site. Another sweep needs to
be brought in to continue the street sweeping.
City to provide key for storm pond north of 9'for Reed for use in
construction storm water management. Reed prefers to use pond at 9th
sooner than later.
Page 3 of 7
O,c
y 4
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
11.Submittals/Documentation
a. Review ROM -
b. Submittals under review:
• Force Account equipment list and labor rates. Equipment
list under review
c. RAMs that needs to be submitted:
• BI 10. 01.03 — Reinforcing Steel for thrust and anchor blocks
d. Non Material Submittals that need to be submitted:
e. Material Documentation
• HMA documentation —certification letter, Toxicity Testing
and Cert. of Toxicity Characteristics for RAP.
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn. Certs provided via CMS are outdated.
Need newer one within 6 months. G&O requested latest
Scale Cert. since the one received is from 2020.
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mt
• DI Fittings Cert of Compliance for fire hydrant and water
main fittings, gasket.
12. RFIs —
RFI 8 response in the works regarding walls Response sent
13. FWD/ Change Orders —
• FWD No 5 sent for trench backfill and dealing with construction
zone water
• FWD for expanding grind limits at 9th St will be provided
Page 4 of 7
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 2 for plastic line and FO Termination Panel change — Quote
requested. Reed will check on quote for electrical items.
• CO 3 — Remove requirement for Tier 2 on Crushed Surfacing from
recycled pits in the works
• CO X —for trench backfill and dealing with water — in the works
• CO X —for storm improvements at 9th — in the works
• CO X —for school district revisions — in the works
• CO X—for walls — in the works
14. Subcontractor Status —
Oneul Canvas Amount'a o to S5.169.69'.56 1 Date of latent
PERCENT OF TOTAL CONTRACT Request To Pay
REQUEST THIS PREVIOUS SUBLET Rec'd to Sublet Prevailing
NO. SUBCONTR4CTOR SIOLNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ground Up Road Construction,lac. 325,575.00 0.49`. 0.00% 0.49% 8/11.2021 8122021 N 8:27:2021
2. Green Cty,Inc. S139,48000 2.70% 0 49% 3.19% &'112021 812I2021 Y 8512021
3. Tot®Fknoe ofTacama,Lc. S734,636.80 1421% 3.19% 1739% 8:122021 8122021 N 8'27!2021
3a lregiiy Networlcs(Lawer Tier) 522,432.15 t 305% 0.00% 3 05%12.45,2021 12.152021 N 1312021
4. Laicadge Paving Company,LLC S706,900.00 13.67% 1739% 31.07% &162021 8;172021 N 8.302021
S. Salve Rite.Inc. S42,778.60 0.83% 31.07% 3189% &762021 6172021 N 8/242021
6. C&PFencag $2,177.70 0.04% 31.89% 31.94%8/20.2021 8/232021 N 8.262021
7. W E.Coates 161,500.00 119% 3194% 3313%12)15+2021 12/1512021 Y 11115.2021
8. Legacy Tapping,lac. $20,150.00 039% 33.13% 33.52% 1:272022 1.272022 N
15.Certified Payrolls —
Week Contractor Subcontractor is on the job site,payroll required a'"(o12)indicates payrod number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required_
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmmal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16. Progress Payment—
• Progress Payment No 2 — in the works for work through 1/31/22
Signed/submitted to City. PP No. 2 includes CO #1, Material on
Hand, and work performed in January.
Page 5 of 7
', CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule ,TL _I 1, I
ZaM E
Work Zone C-Jan-March 25 2022 N[wN �atvo J
Work Zone A-Feb 25 to March 25 2022 z lipr
Work Zone 5&E-March 28 to Aug 22.2022 i lo ,„
Work Zone F(Medians)_Nov 9 to Dec 20 2022 I r
51 '
EN
LOCATION I di
l• �
14 �`. ,r 4 -7
41•0411ITHPIE s'IST 7 C
yriAll
la aDIST If s
PROJECT ='1111."' :
LOCATION
IA
,Lio,„_,
. . ,„ , 7- i
WATER MAIN IMPROVEMENTS
N -204EDULE 8
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT 1Osuat -SCHEDULEC
Poured-in-place wall may increase for sidewalk tie in to wall
Widener and COR permitting staff dismissed.
Attendees for remainder of Meeting include Flora, Bob, Joey, G&O,
Parametrix and Barcott.
17. Force Account Tracking for Dewatering discussion
Reed will use their FA forms to track dewatering activities. Phil will
track on COR FA forms.
Phil and Reed to compare forms at end of day, if in agreeance, both
forms will be signed.
For first day of dewatering, FA forms will show time for driving the
truck to the jobsite (from Puyallup yard), digging the sump, and
operating the pump.
Page 6 of 7
.
G O�
CITY OF RENTON�
F" DUVALL AVE NE
CAG-20-065
For daily dewatering activities, FA forms will show labor hours for
moving the truck (when required), setting/adjusting the pump.
Reed requested regular rate, not the standby rate, be used for the
Water Truck when pump is being operated. Dustin noted their quote
was set up this way, assuming 2 hours of operating the Water Truck
(at regular hourly rate) each day.
Reed anticipates dewatering might be required for JUT installation. It
is uncertain if dewatering will be required for storm installation in the
next Work Zone.
If uncertain if dewatering will still be needed, Bob requested G&O
calculate which is more cost effective: demob Water Truck or keep on
jobsite and pay standby time.
18. Potential revisions to Street Lighting
City may add additional Street Lights near the Church Property at 12th
Street. Flora mentioned that Chris had considered looking at
purchasing material and having School District install as part of their
project. Bob noted that need to discuss with CED that poles along the
School's frontage improvements will need a 14ft lamp (dual lights)
over sidewalk since there is a planter.
Installation of the additional street lights under the Duvall Ave project
will require remove/replace existing rockery at corner of 12th St. Bob
asked Reed what their preferred method on reinstalling wall. Reed
indicated pour in place wall, similar to all other walls and would be
covered with an increase in quantity.
Flora requested Parametrix provide the City with previous preliminary
design of street light/foundation/restoration plans at this location.
Page 7 of 7
•
REEDc Date:02/05/22-02/25/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall A
Feburary
ached
ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/Resources
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 Storm install X X X X X X X X X X lost days due to dewatering discussion
2 JUT&Vault Installation X X X X X downtime and anticipated loss of production
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
-A CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Wage Interviews - Evergreen interviewed.
10.Environmental Compliance Report- No issues.
11. Public Outreach - Will need if 12th is allowed to be closed.
12.Submittals/Documentation
a. Review ROM - Recently Uploaded to CMS.
b. Submittals under review: RAM 91 Anti-Graffiti under review.
c. RAMs that need to be submitted:
• B18.04 - 3/4-Inch Diam. Cor-Ten Steel Shackle Rods -
resubmittal
• B18.13 - 3/4-Inch Cor-Ten Tie Rod - resubmittal
d. Non-Material Submittals that need to be submitted: Ped detour
plan for 12th crossing.
e. Material Documentation -
• For hydrants installed for WD 90/tie-ins, need Cert. of
Compliance for gaskets, mega lugs, and field lock gaskets.
13. RFIs-
14. FWD/ Change Orders-
• FWD 13 in the works for School Frontage Revisions
• CO 10 - Relocate Street Light L12 -sent to City for signatures -
Fully executed.
• CO 11 - Supplemental RPM's and Traffic Arrows - in the works
• CO 12 -for school district revisions and culvert removal - in the
works
Page 3 of 6
•
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
15. Subcontractor Status- Evergreen statement of intent required.
Oeynal Cuo0act Amount(ay o tax): 55,169,697.i0 Date of _Intent
• PERCENT OF TOTAL CONTRACT Request To Fay
REQUEST THIS PREVIOUS SUBLET Rec'd to Sublet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ground Up Road Construction,Inc. S25,575.00 0.49% 0.00% 0.49 u 8/11.2021 8i122021 N 827,2021
2. Green City,Inc. S 139,480.00 2 70% 0.49% 3.19% 8/11.2021 81122021 Y 8/312021
3. Totem Electric of Tacoma,Inc. 3734,636.80 14.21% 3.19% 17.39% 8/12/2021 8/12t20a1 N 8/2712021
3a Integrity Networks(Lowe.Tier) S22,432.15. 3.05% 0.00% 3.05%12/15/2021 12'15/2021 N 8531/2021
4 Lakeridge Paving Company,LLC $706,900.00 13.67% 17.39% 31.07% 8'162021 811712021 N 8302021
5. Stripe Rite,Inc. S42,778.60 0.83% 31.07% 31.89%81162021 8/17/2021 N 824/2021
6. C&PFaris S2,177.70 0.04% 31.89% 31.94%81202021 8292021 N 8262021
7. W.E.Coxes S61.500.00 1.19% 31.94% 33.13%12'152021 12/15/2021 Y 11,1512021
8. Legacy Tapping,Inc. S20,150.00 0.39% 33.13% 33 52% 12712022 1272022 N 1/27/2022
9. PnD Logging S10,000.00 0.19% 33.52% 33.71%2/162022 2/172022 N 2'1612022
10. Conaete Services S192,934.00 3.73% 33.71% 37.44%31172022 3/1712022 N 3/232022
11. Puget Construction Services,Inc. S15,000.00 0.29% 37.44% 37.73%3/182022 3118,2022 N 4/122022 j
12. Ttansporation Systems,Inc S48,110.00 0.93% 37.73% 38.66%32112022 3i21?2022 N 3/18/2022
13. Evergreen Concrete Cutting,Inc S3,000.00 0.06% 38.66% 38.72%4/1512022 4/152022 N
14. 0.00% 38.72% 38.72%
15. 0.00% 38.72% 31172%
16.Certified Payrolls- Not up to date.
_ Progress Payment No 2(January) Progresss,Po.me"r No 3(February) Progress Payment No 4(Morels)
_ Week Ending On: 1.-.La SJm 15daa 22Jan 29Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12.Mar 19-Mar 26-Mar 2-Apr
Read Trucking 4-Jar 18-1ao 25-Jar 28-Jon 4-Feb 10-Feb 1-Ntar t-Mar 1-Mar 14-Moo ::Mar 25-Mar 4-Apr 8-Apr
WY.Coates X 18.1e" 28-Jon No Work No Work No Wort No Work 1-Mar No Work 14-Mar 24-Mar 24-Mar,No Work 11-Apr
!Totem Electric X X 28-1m 28-Jan No Work No Work I-Mar I-Mar 4-Ma, 19-Mor IS-Mar 23-Min 4-Apr 8-Apr
PoD Logging X X X X X X X 1-Mar No Work No Work No Work No Work No Work No Watt
Paget Construction X X X X X X X X X X X X X
Comore Senior* X X X X X X X X X X X X X
Progress Payment No 5(AorO) Progress Payment No 6(May) k Progms Payment No 7(Jane)
Week Ending On: 9-Apr 16-Apr 23-Ape 38 Apr 7-May 14-May 21-May 23-May 4-Jo. 11-Jun 13.ho 25-lan 2-Jul
Reed Trucking 18-Apr 22-Apr
W.E.Coates 14-Apr 22-Apr X
Totem Electric X
Pap Logging No Work X X X X X X X X X X X X
Puget Commrnwa X X X
Concrete Semen
Potdco X X
'Transportation Spotam X X
Week Contractor/Subcontractor is on the job site,payroll required_ **( 12)indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"payroll required.
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship floc's required
Payroll Resubmittal
No Work Received"No Work Performed''payroll
I5-Feb "Final"payroll
17. Progress Payment-
Page 4 of 6
;ARCITY OF RENTON
DUVALL AVE NE
CAG-20-065
• Progress Payment No 5 —April 29 cut off; May 4th documentation
to be submitted to City for processing.
• MOH — Fred Duke received poles without arms. Unsure of lights.
Phil needs pictures before progress payment by the 29th. Fred to
verify after meeting.
18. Other Items:
Recycled Pavement section is ok for full depth repair sections shown at 10th
& 12th.
Proposed closure of 12th at Duvall- In order to close 12th, action needed by
City Council. There is an argument for an emergent safety situation. There is
an estimated 4 months of construction at 12th- Dustin to determine if
schedule can be reduced with the closure of 12th. Bob ok with proposed
closure. Coordinate with Fire Department. Approach to be kept open and
have movable temporary barricades for emergency vehicles that can get
through. Dustin needs answer by May 5th or 6th (pulverizing on the
schedule), can delay to May 12. Outreach to church, apartments, and
Albertson's people. Reed to put together a TCP plan for a detour
(incorporate on ped plan he's already working on).
Page 5 of 6
... .
_ . ._
4ii,
4R,
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule . ` J (�
-NjilligIN-1--
Work Zone C-Jan-March 25 2022su
Work Zone A-Feb 25 to March 25 2022 arm) z J
0
Work Zone B&E-March 28 to Aug 22.2022 §
Work Zone F(Medians)-Nov 9 to Dec 20 2022JIL
NEurNSr —
. t)el" *IP\
LI P•61ECT~ —
LOCATION y I -
(
'SCF,EDUIE l -' INES ST
�N..
...,,,,1 cm *moil
j -NE 7rH
z
�
p i-- NE 6TH ST IN
W
1 = H 4
t NE�TNST
PROIEC'Tlilmw" 1.
a LO7CADTUION
IE liLEd
'-----) MN J _
Fr:. _ i , , \11 ,7,
WATER MAIN IMPROVEMENTS
it -SCHEDULE B
VICINITY MAP A UNDERGROUND IMPROVEMENTS
NorioscxE -SCHEDULE C
Page 6 of 6
•
REEDc Date:04/23/22-05/13/22 3 Week Look-Ahead Schedule
7RUCI =s EXCAVA7 NG Name: Duvall Avenue
April
Sched
ID Work Description SSMT W T F SS M T W T F SS M T W T F Notes/Resources
23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13
Form and pour walls X X X X X
Clean up and restoration WZC and A X X X X X X X X X X
plainning WZA and C X
wet taps and hydrants X X X
paying X X
Set upWZBandE X
Remove asphalt on WZB and E X X
Storm WZE X X X X X
•
` =1
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
February 1, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc. x
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogrtad, Michael Ballard, G&O x
Michael Sippo - City of x Yong Qui —City of Renton x
Renton
Ed Thompson —Representing Gary Bradley, PSE x
Renton School District x
Katie Prond — H march James Cohn, Comcast
2. Safety Report— Same from last week...need storz adapters on Fire
Hydrants at 7th and 9th
3. Prior Meeting Minutes —Comments/Acceptance
Heading to be revised to be revised from "Agenda" to "Minutes"
Minutes accepted
4. Weekly Statement for Working Days ending January 31, 2022
Page 1 of 7
•
co;
CITY OF RENTON
�"T°`" DUVALL AVE NE
CAG-20-065
Days Expired: 14
Days Remaining: 246
5. Schedule Progress
Contractor's Look Ahead Schedule - Dustin - Started on storm
installation, will take roughly next 2 weeks, JUT start date on 2/14,
give or take.
Expected materials that are coming out on-site: Dustin: don't have
any on schedule, DI Pipe may ship soon to lock on price. 16" water
and other DI Pipe.
David: Cert. of Compliance for 16"DI Pipe required
6. Utility Coordination
a. Comcast — No attendees. Comcast has provided material (per
Phil). Inspector not needed onsite during installation. Assume
Totem to install conduit. If installation not required by
electrician, Reed would rather install themselves.
David to check requirements for installation (electrician
needed or not)
b. PSE - Gary— inspector required onsite. Looking at 2-3 weeks
before inspector can come out. Need updates ASAP if change
in schedule. Dustin —pretty secure on 2/14 start date; weather
pending. Will reach out to PSE for Conduit
Phil asking if Fred Duke with Totem has everything finalized
with meter cabinet at 12th...unsure of current status. Dustin to
let G&O know if PSE (Fred) needs anything else.
c. Water District 90— No attendees. Work completed except for 2
Storz adapters. David to check with Flora if City needs
anything else.
7. RSD Elementary School 16 Coordination
a. School Contractor: construct water xings, coordinate gas
crossing, provide conduit and j-boxes to Reed
Page 2 of 7
\T\
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Reed Trucking: add conduit crossings/j-boxes at 10th
intersection on 3 approaches, add block outs for future
driveways on west side between 10th and 12th, delete SL 12
G&O will provide info on driveway block outs to Dustin, and
possibly adding illumination north and south of school as
change order. Question on timing....the Renton School District
could do work during WZ B, D & E(Staying out of way of
Dustin).
Dustin - what is ingress/egress for their work? Duvall and/or
12th? Ed - most likely on Duvall (south entry); also looked at
12th. Dustin —foresee some times of delay and/or severe
coordination.
Engineer plans show two construction entrances, versus one.
Dustin recommends two for flexibility in coordinating work.
School breaks ground mid-April.
8. Engineer's Report
a. Staging Area- two reservoir sites available: Hazen and Highlands
as per email Dustin — haven't heard anything regarding existing
area. City has two alternate sites. Tani requests that Dustin
select which one is preferable so City can get them ready,just in
case.
b. Long lead-time items - No update
c. Intersection at 9th — a FWD in the works to add storm imp,
expanding the grind and overlay is under consideration In review
for now.
d. Upcoming on-site preconst meeting for CB adjustments Dustin
to give heads up when CB adjustment takes place.
e. Trench dewatering —testing Icon & Sumner pit as alternate
aggregate sources. Dustin had switched to Icon already. Still
running recycled backfill material—cost difference to change.
Phil—failing compaction tests for Squak Mountain recycled
material for storm pipe. Worse test results the more it was
compacted...leaning towards getting back out for another test.
Consider switching product if it doesn't pass (no rain lately).
Page 3 of 7
CITY OF RENTON
NTO DUVALL AVE NE
CAG-20-065
David to get MTC out there to retest.
Tani— is it worth just using Icon? Dustin has good results with
Icon.
Waiting for MTC results.
9. Inspector's Report
a. Material testing —Samples from Icon and Sumner pits. See above
b. Traffic Control issues — No issues.
c. Wage Interviews — Done.
d. Precon photos done.
10.Environmental Compliance Report
Jordan —Site looks good...only comment from 9' to 10' with
Type 2 CB - make sure it's our connection point and make sure
we have rock/fabric to catch turbidity & sediments. Clean out
before it's up and running.
11.Submittals/Documentation
a. Review ROM David— ROM posted update last week.
b. Submittals under review: 3 electrical reviewing, Anchor bolts
(73A) will be returned with revisions with Field Work Directive #3
shortly. 80 & 81 are approved.
• RAM 054B—Switches
• RAM 078 —AC DC Power Supply
• RAM 067A — FO Components
• RAM 073A — Anchor Bolts. Bolts for Hawk and Luminaire
poles will be revised via FWD No. 3.
• RAM 80 — Sumner Pit aggregate
• RAM 81 — Icon Pit aggregate
c. RAMs that needs to be submitted:
• BI 10. 01.03 — Reinforcing Steel for thrust and anchor blocks please
provide submittal if it's included.
Page 4 of 7
c
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
d. Non Material Submittals that need to be submitted:
• Force Account equipment list and labor rates noted.
e. Material Documentation
• HMA documentation —certification letter, Toxicity Testing
and Cert. of Toxicity Characteristics for RAP, Scale Cert for
plant noted.
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn. Certs provided via CMS are outdated.
Need newer one within 6 months
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mt Noted
• DI Fittings Cert of Compliance ficor wateriFe main fittings,
gasket.
12. RFIs—
RFI 8 responses issued regarding walls Sent to Dustin. Some
coordination regarding how it's paid and design change to make
sidewalk thicker.
13. FWD/ Change Orders—
• FWD No 3 in the works for anchor bolt extra length Sent today.
Need cost.
• FWD No 4 in the works for Storm at 9th Sent today. Some DI Pipe
proposed; need bid item. Other items pay by bid item?
• CO 2 for plastic line and FO Termination Panel change — in the
works. —Quote requested
• CO 3 — Remove requirement for Tier 2 on Crushed Surfacing from
recycled pits
• CO X—for storm improvements at 9th
• CO X —for school district revisions — in the works —
Page 5 of 7
vCITY OF RENTON
DUVALL AVE NE
CAG-20-065
14. Subcontractor Status — Looks good.
Onginat Contract Amount(a o tat): 55,16949'9 1 Date of INeot
PERCENT OF TOTAL CONTRACT Request To Pay
REQUEST THIS PREVIOUS SUBLET Rec'd to Sublet Prevailing
NO. SUBCONTRACTOR _MOU.T REQUEST REQUESTS TO DATE RTS (awed) DBE Wages
1. Groaadtip Road Construction,loc. 525.575.00 0.49% 0.00% 0.49% 831:2021 8;122021 N 18127.2021
2. Green City,Inc. 5139480.00 2-70% 0 49•L 3.19% W11./2021 8/1212021 Y 8r31.2021
3. Team Ekcbc of Tacoma,loc. S734,636.80 14.21% 3.19% 1739% 81122021 8/12'2021 N 8/27.!2021
3t keep*Ydworks(LowrrTier) 522,43215 3.05% 0.00% 3,05X1215202112152021 N 8131r2021
4. Labeidg Paving Company,LLC S706,900.00 13.67% 1739% 31.07% 8/162021 V17/2021 N 8/30/2021
5. Stipe Rite,lee S42,778.60 0.83% 31.07% 31 89% 8/162021 81172021 N 8/24/2021
6. C&PFeoc>.8 S2,177.70 0.04% 31.89% 31.94% 1202021 823,2021 N 8.262021
7. W.E Coatis S61,50000 119% 31-94% 33 13%1215,2021 1215.2021 Y 11;15,2021
8._ �e ay Tapping,Inc. S20,150.00 039% 33.13% 33.52% 1,27 2022 127/2022 N
15.Certified Payrolls— Tiffani putting up on CMS. All marked in yellow to
go in with documentation to City.
PP No 1 Progress Payment No 2(January)
Week Ending On: 25-Dec 1-Jan 8-Jan 15-Jan 22-Jan 29-Jan
Reed Trucking 4-Jan 4-Jan 18-Jan 25-Jan
W.E.Coates X X 18-Jan X X
Totem Electric X X X X X
Week Contractor Subcontractor is on the job site,payroll required. **(=12t indicates payroll number**
X Subcontractor was not on-site this week. "No Work Performed"pat.Toll required
15-Feb Date certified payroll was recieved
Corrections to payroll required
Apprenticeship doc's required
Payroll Resubmittal
No Work Received"No Work Performed"payroll
15-Feb "Final"payroll
16. Progress Payment—
• Progress Payment No 1 — check cut 1/31/22 Dustin not paid
yet,- Tani to check status. Joey updated—it went electronically
yesterday but can take up to 24 hours. Dustin to check his
bank account to verify.
• Progress Payment No 2 — in the works for work through 1/28/22
Page 6 of 7
IR
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule ( ` -- 1 I 1
Work Zone C-Jan-March 25 2022 NE• amp Si
-- �/
Work Zone A-Feb 25 to March 25 2022
Work Zone B&E-March 28 to Aug 22.2022 Work Zone F(Medians)-Nov 9 to Dec 20 2022 , t —
Lrt
01:46
i° , _
PR•) _ '
Kil'I'
LOCATION �r
4.,. . ii.
ii..,,.
tri,
.,., � .
g .,„
,,
1 ` IN
wit tnr sr yt
5
t wE.rN n 3$
PROJE -
:. JAW"
LOCATION
{ WATER MAIN IMPROVEMENTS
N -SUIEOULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
for TOSCCNE -SCNEOULEC
Page 7 of 7
REEDC. Date:01/29/22-02/18/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall A
....�,...,..,�..,�._....,.._....... January Feburary
Sched
ID Work Description SSMTWT F 8 S M T W T F SS M T W T F Notes/Resources
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 18 17 18
1 Storm Install X X X X X X X X X X
2 JUT&Vault Installation X X X X X
3
4
5
6
7
8
9
10
11
12
13 -
14
15
16
17
18
19
20
21
G
+ CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Curb line to stay per design with block outs for future
driveways
8. Engineer's Report
a. Staging Area- permitting issue — Critical Areas Code does not
make exception. City GIS does not show setbacks on the staging
yard property. Bob stated to wait for official notice from
enforcing department which should include timeframe for
vacating property. Discussed that Reed might make a claim
against the project for vacating property/relocating staging
area. The Hazen water reservoir north of 12' may be an
alternate site, or church JCLDS north of 8th(Reed willing to move
if needed). Dustin to check on workability.
b. Discuss long lead-time items that have submittal reviews
outstanding? Anchor bolt questions received from Reed. Reed
to provide resubmittal. — Dim. On std. plan — minimum, City
would like submittal reviews to show that anchor bolts shall be
12" out of ground. G&O asked if the anchor bolts had been
ordered, Reed to confirm with Totem.
c. Intersection at 9th — looking at adding CB structures
d. Clearing and fill behind sidewalk OK in swath of property in front
of rock wall between 7th and 9"), east side
e. Upcoming on-site preconst meeting for CB adjustments
f. Discuss Foam and CDF for utility conflicts
g. CSTC from Squak Mtn Pit to be approved via CO
h. Contractor would like to discuss wall bid item —
Look at pay limits to back of wall for sidewalk. Discussed revising
pay structure with sidewalk included as part of wall foundation.
SW 6" thickness required when part of wall foundation. Create
Change Order for redesign of wall. City requested a formal RFI
for this issue.
9. Inspector's Report
a. Material testing — compaction test to be completed
Page 3 of 6
i 0,
CITY OF RENTON
DUVALL AVE NE
N
CAG-20-065
b. Traffic Control issues — truck driver issue corrected
c. Wage Interviews — up to date
10.Environmental Compliance Report
Preparing for rain,forecast shows approx. % inch of rain next
week. Jordan W. will be onsite tomorrow to review BMPs.
11.Public Outreach
a. Businesses — to be updated. City has updated their website.
12.Submittals/Documentation
a. Review ROM
• G&O to update with response to RAM 029B - Mortar and
rods marked "Approval Withheld." The foam is acceptable.
• G&O to update with response to RAM 074 & 075 — Franklin
pit Ballast approved for use as Gravel Borrow. —Scalemans
report not required
b. Submittals under review:
• RAM 054B — Switches
• RAM 078 —AC DC Power Supply
• RAM 067A— Electrical Components
c. RAMs that needs to be submitted:
• BI 10. 01.03 — Reinforcing Steel for thrust and anchor blocks
• BI 17.12/18.12 —Temp HMA—proposed use for each item
requiring temp HMA patch. Reed inquired,for areas that
will receive a grind and overlay, ok to install permanent
patch? Small amount of amount of HMA would be wasted
from grind.
d. Non Material Submittals that need to be submitted:
• Request to Sublet for Legacy Tapping (water main wet tap). — Force
Account equipment list and labor rates requested from Reed.
Page 4 of 6
G\T Y O*
+ + CITY OF RENTON
N111,4,NTO
DUVALL AVE NE
CAG-20-065
e. Material Documentation
• Scale Certification (semi-annual calibration of commercial
scale) for Squak Mtn
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mt
• DI Fittings Cert of Compliance
13. RFIs—
RFI 6 and 7 responses issued regarding gutter slope and PSE power
source
14. FWD/ Change Orders—
• FWD No 1 issued regarding plastic line
• FWD No 2 issued regarding Elec components
• CO 2 for plastic line and FO Termination Panel change — in the
works. — Need quotes. G&O to send draft to Reed.
• CO 3 — Remove requirement for Tier 2 on Crushed Surfacing from
recycled pits
• CO 4—for school district revisions — in the works — May delete
SL12
15. Subcontractor Status —
PERCENT OF TOTAL CONTRACT Requecr To Pap
REQUEST THIS PREVIOUS SUBLET Rec'd to Sublet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
' 1. Ground Up Road Construction,lac. S25.575.00 0.49% 0 00°n 0.49% 8/11.2021 812'2021 N 82'.2:,21
2. Green City.Inc S139.480.00 2 70°° 0 49°b 3.19% 811.2021 812/2021 Y 831 2021
3. Totem Electncof Tacoma Inc. S734,636.80 14.21°a 3.19% 17.39% 8/122021 8112/2021 N 8/27.2021
3a. Integrity Networks(Lower Tier) S22,432 15 t 3.05°° 0 00% 3.05%12/152021 12/1512021 N 831/2021
4. Lakaidge Paring Company,LLC S706,900.00 13.67% 17.39% 31.07% 8/162021 8/17/2021 N 8/30/2021
5. SlMe Rite,Inc. S42,778.60 0.83% 31.07% 31.89% 8/16/2021 8117/2021 N 8/24/2021
6. C&PFencing S2,177.70 0.04% 31.89% 31.94% 8202021 823/2021 N 826/2021
7. WE Coates S61,500.00 1.19% 31.94% 33.13%12/152021 12/15/2021 Y 11115/2021
Page 5 of 6
o,c
• ''y + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
16.Certified Payrolls—
17. Progress Payment—
• Progress Payment No 1 — check to be cut 1/31/22
• Progress Payment No 2 — last working day of January, 1/28/22
Schedule
IIII
Work Zone C-Jan-March 25 2022 l• .
Work Zone A-Feb 25 to March 25 2022 &�
Work Zone B 8 E-March 28 to Aug 22.2022 ' 1 lililli r Ill
ork Zone F(Medians)-Nov 9 to Dec 20 2022i II
' til, ( I9- 1111.11 11111° I
I\ „.40,411 LOCATION ' ii "JI
iii
ii,,,"4„.....g%.
ii!
1 I mit .. .
....!„ .
i 1
Pr/ill ' 2
fijejlifilli
Alpfi, Plts E 1.11111.1111 1
LOCATION mi
�` lid . t _ II
i
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT 10 SCMI -SCHEDULE
Page 6 of 6
REEDC. Date:01/22/22-02/11122 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVATING Name: Duvall Avenue
tam wr.
January Feburary
Schell
ID Work Description SSMTJWT T W T F SS M I TWT F Notes/Resources
22 23 24 25 29 27_28 29 30 31 1 2 3 4 5 9 7 8 9 10 11
1 Remove wrtermain X X_ X X X
2 Storm install X X—X X X X X X X X X
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Get
+ ife CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
January 25, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O x
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc. x
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc.
Traci Brewer Rogstad, Michael Ballard, G&O x
Michael Sippo - City of x Joshua Drummond, KCWD 90
Renton
Matt Fcldmcycr Renton Gary Bradley, PSE x
School District
Katic Pond Hoarch Yong X Jamcs Cohn, Comcast
Qui—City of Renton
2. Safety Report— Safety complaint received regarding no flaggers and
street blocked off at Duvall Ave and 121st (7th?) on Sunday (no work
taking place) — One lane during construction. No significant issues. City
to follow up if further action needed.
Phil reminded truck drivers to confirm tail gate is closed.
3. Prior Meeting Minutes —Comments/Acceptance
Minutes Accepted
Page I of 6
\!Y o
+ 16" + CITY OF RENTON
DUVALL AVE NE
4)A,
CAG-20-065
4. Weekly Statement for Working Days ending January 24, 2022
Days Expired: 9
Days Remaining: 251
5. Schedule Progress
Contractor's Look Ahead Schedule - See the attached schedule
Expected materials that are coming out on-site: storm items on site.
nothing new
6. Utility Coordination
a. Comcast — materials delivered to the staging area last week
b. PSE - Materials delivered? No curb and gutter requirements in
advance of JUT on PSE's end. Materials delivered, Reed to
send PSE confirmation of what was received. Issue regarding
power source, Reed Trucking to send emails to Gary Bradley if
needed.
c. Water District 90— Storz Adapters needed. Replace 3-1/2"
part. G&O asked if the City needs any documentation from
WD 90 stating work completed to their standards.
7. RSD Elementary School 16 Coordination
a. School Contractor to construct water xings, coordinate gas
crossing— Conduit crossing at 10th may be added. Discussed
that Reed is ok with school contractor to do this work, however
it may take place in stops and starts. Discussed idea of school
to deliver conduit for Reed to install along with junction boxes
for school district conduit. Reed to find out if street lights
ordered as SL 12 may be deleted.
b. Reed Trucking change order to add conduit crossing at 10th
yes
Page 2 of 6
7 CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
January 18, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton x Phil Van Earwage, G&O
x
Flora Lee, City of Renton x Tani Stafford, G&O
x
Josef Harnden, City of David Roman-Sanchez, G&O
Renton x x
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc.
& Excavating Inc. x
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc. x
Trucking & Excavating Inc. x
Michael Ballard, G&O x
& Excavating, Inc.
Ross Widener, Widener & ,
Assoc.
Dmitri Suslikov, Darametrix Gary Bradley, PSE and Brent Olson,
} }E P.-SEx
James Cohn, Comcast x
2. Safety Report— no issues
3. Prior Meeting Minutes — Comments/Acceptance
Comment - Correct 2021 to 2022 on the date, minutes accepted with
the correction
Page 1 of 7
CAI
o
+ + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
4. Weekly Statement for Working Days ending January 17, 2022
Days Expired: 4
Days Remaining: 256
1/17/22 was a non-working day to the MLK holiday
5. Schedule Progress
Contractor's Look Ahead Schedule — see the attached 3-weed look
ahead schedule. KCWD90 FH connections this week and water main
shut down scheduled for Thursday, then will begin water main
removal
Expected materials that are coming out on-site: FH materials, storm
materials and gravel borrow
6. Engineer's Report
a. Discuss long lead-time items that have submittal reviews
outstanding? RAM 58B Anchor bolt questions received from
Reed
b. Tree removal at 903+55 RT —just remove the one tree that is
noted on the plans, within the ROW and try to protect the
neighboring tree. Grind stump to finished grade per the
Specials — Phil suggested that other trees in question be looked
at in the field
c. Intersection at 9th — standing water in inner travel lane
d. Upcoming on-site preconst meeting — CB's —this preconst
meeting will hold until the Contractor is ready to adjust CB
structures
Page 2 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
e. Potholing — discussed that if there is a possible utility conflict
shown on the plans and no elevations shown on the plans for
the existing utility then Engr may request a pothole, or the
Contractor may request a pothole per Contract Provisions
f. Wet area noted near 9" Street intersection - discussed that it
may be a water main leak and if so then when the water main
is abandoned we will know...or it may be groundwater.
g. Tuff Curb — was removed and salvaged to ease right turning
movement from 7th, temp striping has been placed— keep an
eye on it to keep it up during construction
h. Discussed foam for utility conflicts —check with Abdoul to see if
CDF can be used in lieu of foam for close separation between
utilities per plans.
7. Utility Coordination
a. Comcast - Comcast would like a set of plans sent, G&O to send
a link. Comcast will deliver their conduit to the staging yard
ASAP. They are interested in undergrounding across Duvall at
10th if that is added to the project. This is not shown on the
plans at this time, only undergrounding under 10t" on the east
approach of Duvall.
b. PSE - Materials anticipated to be delivered to the staging area
on the 24t". Contractor asked if there are curb and gutter
requirements in advance of JUT on PSE's end. PSE to respond.
c. Water District 90 — District staff not present but Tani received
an email that everything is good on their end. Restrained joint
fittings submittal sent to District for review.
8. Inspector's Report
a. Material testing - Gradation and Proctors for aggregate —
samples taken from Franklin Pit.
Page 3 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
b. Traffic Control issues — One change made on sidewalk closed
signage at 10th
c. Wage Interviews — Reed Trucking interviews complete
d. Preconstruction Photos — started
e. TCP submittal for 7' was submitted and approved, Flora to see
if it can be expanded for 10th
9. Environmental Compliance Report
Jordan shared photos taken near 9' of road runoff drained to
construction area, reiterated need for sandbags or temp HMA
to keep road runoff separate from the construction area.
Jordan stated the roadway is staying swept.
10.Public Outreach
a. School District - City to meet with School Dist. regarding
coordination of projects on 1/21/22
b. Businesses — no issues known.
11.Submittals/Documentation
a. Review ROM. — ROM to be shared later
b. Submittals under review:
• RAM 029B — Speedcrete and Plank Foam Mortar for Storm
Structures and Shackle Rods for FH
• RAM 036B — COC for Valves (will confirm Heat # shown on
COC is same as stamped on valves brought on site) — on
hold waiting for the material to show up on site and
compare
• RAM 058B — Radar Signs/School Beacons. Has been
returned to Reed via CMS. Radar Sign is acceptable. School
Beacon components not approved since City prefers
relocating existing School Beacons.
• RAM 074 and RAM 075 — Franklin Pit — waiting on test
results
Page 4 of 7
ICITY OF RENTON
DUVALL AVE NE
CAG-20-065
• RAM 076 — Gasket — sent to WD 90 for review
• RAM 077 — Mueller gate valve — Returned to Reed via CMS.
Gate Valves are acceptable.
• NMS 12- TCP to add one lane closure with flagging and
alternating traffic for side streets etc. — Contractor has
submitted directly to City for approval
• Anchor bolt questions on RAM 073 Review
c. RAMs that needs to be submitted:
• BI 10. 01.03 — Reinforcing Steel for thrust and anchor blocks
• BI 17.06.03/18.06.03 Valve Extension (if needed)
• BI 17.08/18.08 — Blue RPM
• BI 17.11/18.11 — Class 4000 for Curb/Gutter &
Sidewalk/concrete pad for hydrant — this will be done by
sidewalk subcontractor. City verified that concrete pad
needed as shown on plans for KCWD hydrants
• BI 17.12/18.12 — Temp HMA
• BI 18 — Tapping Sleeve and Valve
d. Non Material Submittals that need to be submitted:
• Request to Sublet for Legacy Tapping (water main wet tap).
• Mobilization Plan & Work Plan for City water connections
(SP 7-16.1(1))
e. Material Documentation
• Scale Certification (semi-annual calibration of commercial
scale) for an-Squak Mtn
• Scale certification (semi-annual) and scalcsman reports for
Franklin pit. Scaleman's Reports are not required for Gravel
Borrow.
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mt
• DI Fittings Certifications and Storm Pipe Cert of Compliance
12. RFIs —
Page5of7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
RFI 6 in review regarding gutter cross slope
13. FWD/ Change Orders —
• FWD No 1 issued regarding plastic line
• FWD No 2 issued regarding Elec components
• CO 1 for Retainage —fully signed
• CO 2 for plastic line and FO Termination Panel change.
• CO 3 —for school district revisions —
14. Subcontractor Status —
PERCENT OF TOTAL CONTRACT Request To Pay
REQUEST THIS PREVIOUS SUBLET Rec'd to Sablet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
I. Ground Co Road Construction,Inc $25,575.00 0.49% 0.00% 0.49% 8/11/2021 8/12/2021 N 1'27;2021
2. Green Cly,Inc. _ 5139,480.00 2.70% 0.49% 3.19% 8/11/2021 8/12/2021 Y 8/31,2021
3. Totem Electric of Tacoma,Inc. $734,636.80 14.21% 3.19% 1739% 8/12/2021 8/12/2021 N 8/272021
3a Integrity Networks(Lower Tier) $22,432-15 3.05% 0.00% 3.05%12/15/2021 12/15/2021 N 8/31/2021
4_ Lakeridge Paving Company,LLC S706,900.00 13.67% 17 39% 31.07% 8/16/2021 8/17/2021 N 8/30/2021
5. Stripe Rite.Inc. $42,778.60 0.83% 31.07% 31.89% 8/162021 8/17/2021 N 8/24/2021
6. C&P Feoring $2,177.70 0.04% 31.89% 31.94% 8/20/2021 8/23/2021 N 8/26/2021
WE.Coates 561.500.00 1.19% 31.94•a 33.13%12/15/2021 12/15,2021 Y 11/15/2021
15.Certified Payrolls — Contractor uploading to CMS
16. Progress Payment —
• Progress Payment No 1 —
• Progress Payment No 2 — last working day of January, 1/28/22
Page 6 of 7
IR CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule "` I U t
Work Zone C-Jan-March 25 2022 flrE _/
Work Zone A-Feb 25 to March 25 2022 4Yp 4J Work Zone B 8 E-March 28 to Aug 22.2022 z i I. 'I
Work Zone F(Medians)-Nov 9 to Dec 20 2022 f
1 r _
T_
;imi (
f iii
... i,4
ll I
-- i _T
1 LOCATION
�w -SCIEDIJIE NE? 1� -
lam
\\I all e II
illai� _ C-1II, ilt -
A * VW
i .
W. NE ETH ST
,;,:f Ole 1[- c_.1 . 1 2- � HSf -.E1 PROJECT NE R =
LOCATION
1 L_.1
Url r1 I r
WATER MAIN IMPROVEMENTS
N -SCHEDULER
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT to KAtf -SCHFDUIE(-
Page 7 of 7
REEDc Date: 01/15/22 -02/04/22 3 Week Look-Ahead Schedule
TRUCKING& EXCAVATING Name: Duvall Avenue
January Feburary
Sched
ID Work Description S S M T W T F S S M T W T F SS M T W T F Notes / Resources
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
1 erosion control X
2 Clear and grub X X
3 Make edge of rd fills X X
4 install hydrants and cap main X X X
5 remove water main X X X X X X
6 install Storm X X X X X X X X X X
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
J v `e --
)2L c c. 71c q 'Bn211
,r)21\7 120 'W U/YJ n!1 d r " "U Igo
'TV \ 'MG\
ry \GIck_ks 30 -rvtpirNO 7)np<2.id (74- kpuv
L,1,1/)I lIl l/U/l 1 t l ��✓�I V Y✓ �
?n ri bus vim - 1 0
-n o°1 12 U Ls -vvv p ley Lt3 Z l --i l
5-ciLt^�-� cun0 Z -7)n2V1 L 11,G, IN 10Q"•Q1g —
- 44epu -n tle,t -mod t a
s � � '''- G.Arai prIlw cg sad (-
"v
j i Q s�u0 t , Sum 1104 a ' ! s
'),t7 t , Of I Ctow _171,1452) sw0 LfzpIA/19.3. ° gA)147AC
v» I ov p P wl)4. CU •
2rj el(y)L; t2►� fi �u�ru �� �2' (�
lb2 pco° L , --lp Ud iq �' ,S 5 2�
');g1
�� e , 1��n4 � /5Uv1.�-wa 4srcnq
2I - I atrY) •
APUVD
cia.9
4 I/v)
ztou
a,ttd-o
-P c -c?C ON
J p„(p --�sa
° °t2j C24- 710 ttrn j\-).241
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
January 11, 2022
Comments made during the meeting are shown in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O x
x _ _
Flora Lee, City of Renton x Tani Stafford, G&O x
Josef Harnden, City of x David Roman-Sanchez, G&O x
Renton
Dustin Wright, Reed Trucking x Jordan Widener, Widener & Assoc. x
& Excavating Inc.
Tiffani Barquist, Reed x Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Shawn Reed, Reed Trucking Michael Ballard, G&O x
& Excavating, Inc.
Ross Widener, Widener & Joshua Drummond, KCWD 90 x
Assoc.
Dmitri Suslikov, Parametrix Gary Bradley, PSE and Brent Olson, x
Inc. x PSE
2. Safety Report— no issues
3. Prior Meeting Minutes — Comments/Acceptance
Prior minutes are accepted
4. Weekly Statement for Working Days ending January 10, 2022
Days Expired: 1
Days Remaining: 259
Page 1 of 6
O`r
ti
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule —see the attached schedule
Overall Schedule Update in Review -has been reviewed and posted
Expected materials that are coming out on-site:
• Storm pipe—need cert of compliance uploaded to CMS
• Silt Fence, CB Socks
• Water system parts
6. Engineer's Report
a. Discuss long lead-time items that have submittal reviews
outstanding? Paint Chips, RAM 58B
b. Warning beacons — City does not believe they need to be
replaced — City to review in the field, more to come.
c. PCMS boards timeframes:
a. 2 PCMS boards for 10 calendar days min, before a lane
closure or business driveway closure (page SP-41...) the
2 PCMS boards may come down now for Zone C
b. 2 PCMS boards are to be up for 2 week advance notice
prior to paving operations (Page SP-60) and
recommended they stay up through the paving
operation. PCMS boards to be used as per the Contract
c. PCMS boards for work zone C have been up for 3 weeks,
shall we have Reed take them down? Yes
7. Utility Coordination
a. Comcast -
b. PSE -Jan 24' PSE will be delivering material to the
Contractor's yard. Need 3 week notification for PSE
inspection. JUT anticipated to start mid Feb. Robert Sanborne
from PSE meeting on site tomorrow to discuss service
relocation.
Page 2 of 6
116
jai"
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
c. Water District 90— The FH on 7' may need to be shifted to
avoid guy anchor. District OK with this if clearance is
provided. May need back of walk staked out in order to shift.
The District may supply the valve can tops for the District valve
boxes.
8. Inspector's Report
a. Material testing - Gradation and Proctors for aggregate—
samples requested from Kangly and Squak Mtn pits. Kangley
sample test reports are in review. Squak Mtn samples have
been picked up, no reports yet. Kangly pit samples look to be
good for all but wall backfill.
b. Traffic Control issues — No issues
c. Wage Interviews —None taken yet, waiting on more workers
on site.
d. Preconstruction Photos — started, waiting on locates
9. Environmental Compliance Report
Site walk through completed last week with WES, Contractor
and Phil, BMPs are going in. There are no problems to report.
Care emphasized near MH 33 (creek).
10.Public Outreach
a. School District - City to meet with School Dist regarding
coordination of projects
b. Businesses — no issues known
c.
11.Submittals/Documentation
a. Review ROM. — update will be posted
b. Submittals under review:
• RAM 029B—Speedcrete and Plank Foam Mortar for Storm
Structures and Shackle Rods for FH
• RAM 030A —Trench Drain
• RAM 031A— DI Pipe Gasket
Page 3 of 6
meeker"44' CITY OF RENTON
,a
DUVALL AVE NE
CAG-20-065
• RAM 036B— COC for Valves (will confirm Heat # shown on
COC is same as stamped on valves brought on site)
• RAM 058B — Radar Signs/School Beacons
• RAM 066—Squak Mountain CSBC (need Sand Equivalent
test result for review of Bank Run Gravel for Trench Backfill)
Contractor's first choice is Squak Mtn Pit and second is
Kangly/Black River Pit — will review test data from MTC
• RAM 067 — Mule Tape and various electrical components
• RAM 072 —Thrust Block
• RAM 073 —Anchor Bolt — checking on sizes of bolts in the
field
• NMS 5C — LS Breakdown
• NMS 8A — Schedule
• NMS 10A— Confined Space Plan
• NMS 11 — Paint Color
c. RAMs that needs to be submitted:
• BI 10. 01.03 — Reinforcing Steel for thrust and anchor blocks
• BI 16.01 — 16-Inch Gate Valve
• BI 17.06.01/18.06.01 — FH Valve
• BI 17.06.03/18.06.03 — Valve Extension (if needed)
• BI 17.08/18.08 — Blue RPM
• BI 17.11/18.11 — Class 4000 for Curb/Gutter &
Sidewalk/concrete pad for hydrant
• BI 17.12/18.12 —Temp H M A
• BI 18 —Tapping Sleeve and Valve
d. Non Material Submittals that need to be submitted:
• Request to Sublet for Legacy Tapping (water main wet tap).
• Mobilization Plan & Work Plan for City water connections
(SP 7-16.1(1))
e. Material Documentation
• Scale Certification (semi-annual calibration of commercial
scale) for and Squak Mtn
• Toxicity Testing and Cert. of Toxicity Characteristics for
aggregate material from Squak Mt
Page 4 of 6
•
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
f. Discussed field meeting will be scheduled when first CB is
constructed to show the method for construction of manhole
adjustments and CB adjustments. Build adjustments per plan, mix
mortar per manuf directions, do not use wood lath for spacers.
12. RFIs—
RFI 1 to RFI 5 responses sent
13. FWD/ Change Orders —
• No FWD issued yet — G&O working on FWD No 1 for CO No 2
items
• CO 1 for Retainage—fully signed
• CO 2 for plastic line and FO Termination Panel change.
• CO 3 —for school district revisions —
14. Subcontractor Status—
PERCENT OF TOTAL CONTRACT Request To Pap
REQUEST THIS PRECIOUS SUBLET Rec'd to Sublet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ge000dUp Road Construction,Inc. $25.575.00 049% 0.00% 0.49% 8%11;2021 8,12,2021 N 8/272021
Green City,Inc. $139:480.00 2.70% 0.49% 3.19% 8,11.2021 8.12_021 Y 8/31'2021
3. Totem Electric of Tacoma,Inc. S734,636.80 14.21% 3.19% 17.39% 8122021 81212021 N 8'2712021
3a_ Integrity Networks(LowerTier) S22432.15e 3.05% 0.00% 3.05%12'152021 1215.l2021 N 8;'31:2021
4. LakeridgePaving Company,LLC S706,900.001 13.67% 17.39% 31.07% 816;2021 8,172021 N &30.'2021
5. She Rite,Inc_ S72,778.601 0.83% 31.07% 31.89% 8(162021 8172021 N 8(24:2021
6. C&PFencing $2477_701 0.04% 31.89% 31.94% 8120;2021 823/2021 N 8/262021
7. WE.Coates S61,500.001 1.19%1 31.94% 33.13%1215,2021 12215/2021 Y 11115.•2021
15.Certified Payrolls— upload to CMS when they come in
16. Progress Payment—
• Progress Payment No 1 — City processing/routing
• Progress Payment No 2 — last working day of January, 1/28/22
Page 5 of 6
R
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule i Y f
Work Zone C-Jan-March 25 2022 ME et.Vp Z J
Work Zone A-Feb 25 to March 25 2022 o y'y
Work Zone B&E-March 28 to Aug 22,2022 - y
Work Zone F(Medians)-Nov 9 to Dec 20 2022 .111 ! _
L l .� 12TN ram._._.II
tit, r' J..
xtp� 1....,
JP'O1E ' 4 r
7_� lip, / LOCATION III— _,,
_ t EouEE 1 NE I
y . I� , ill
_ _ II 1
4,414N
i
2
momsa 4x"NFL
z
a iii W "' o
NE 6TH Sr
�S 2 Q W
Wit0 -a— 1
III r1NE4114ST + ` 8
'm APR*IECT —
LOCATION
C LEA/I-
L 1 �t
.. e, _J
WATER MAIN IMPROVEMENTS
N -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
NOT To SCME -SCHEDULEC
Page 6 of 6
REEDc Date:01/08/22-01/28/22 3 Week Look-Ahead Schedule
MUCKING&EXCAVATING Name: Duvall Avenue
January
Sched
ID Work Description S SMT W T F SS M T W T F SS M T W T F Notes/Resources
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 Set up Workzonec X
2 locates X
3 survey X X
4 erosion control X X X
5 Clear and grub X X X X
6 Make edge of rd fills X X X X
7 install hydrants and cap main X X X
8 remove water main X X X X X X X
9 install Storm X X X X X
10
11
12
13
14
15
16
17
18
19
20
21
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
January 04, 2021
Comments made during the meeting are in italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O X
X
Flora Lee, City of Renton X Tani Stafford, G&O X
Josef Harnden, City of X David Roman-Sanchez, G&O X
Renton
Dustin Wright, Reed Trucking X Jordan Widener, Widener & Assoc. X
& Excavating Inc. _
Tiffani Barquist, Reed X Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Shawn Reed, Reed Trucking X Michael Ballard, G&O
& Excavating, Inc.
Ross Widener, Widener & Joshua Drummond, KCWD 90 X
Assoc.
Dmitri Suslikov, Parametrix Ken, KCWD 90 X
Inc. X
2. Safety Report
No issues
3. Prior Meeting Minutes — Comments/Acceptance
Prior minutes accepted
4. Weekly Statement for Working Days ending January 3, 2022
Days Expired: 0
Days Remaining: 260
Non-working days due to weather on Mon and Tues this week.
Page 1 of 7
o'NSF + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
5. Schedule Progress
Contractor's Look Ahead Schedule — see the attachment.
Contractor is waiting for utility locates. His survey sub could not find
the control, perhaps due to snow on the ground. Phil and Dustin to
walk the project tomorrow and see if they can find the control after
meeting with Jordan.
Contractor to change the PCMS sign to "Right Lane Closed Ahead"
when the lane closure is put in place. City requested advanced notice
prior to any lane closure for notifications to the Mayor's office and
City Council.
City has requested an updated project schedule that shows the
critical path and addresses the comments. Non-working days will be
granted when critical path activities are impacted.
City may put up the work zone map at the end of these minutes on
their project page. Friday this week is tentative for lane closure.
Expected materials that are coming out on-site:
• Project Sign. Reed has signs in their yard and will install when
they are onsite.
• TESC items
• Fire Hydrants, thrust block
• Aggregate
• Storm Pipe
• Catch Basins
Page 2 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
6. Engineer's Report
a. Coordination with School Project— changes in work zone E
are in the works — City to schedule a meeting with School Dist
to review.
b. Electrical Permit — load calcs sent to contractor for permit
c. Storm System cleaning —the City crews have cleaned out the
existing storm system the week of Dec 20th
d. Has Contractor received the storm pipe?—not yet but expect
next Monday.
e. Are there any long lead-time items such as illumination, Filterra
and Signal items that have submittal reviews outstanding?
Filterra and luminaire poles submittals have been returned to
Reed. G&O reviewing RAM 067 with cable and misc. electrical
components.
7. Utility Coordination
a. Comcast -
b. PSE -
c. Water District 90— Joshua and Ken from KCWD90 sat in on
the meeting. Contractor asked if an ecology block can be used
for a temp thrust block. The District needs a few days notice
for notification to customers of water line shut down.
KCWD90 Inspector to be onsite for work on WD's water main.
KCWD90 to witness swabbing. G&O to send approved water
submittals to District. Discussed that there may be more
District work required, District is reviewing plans.
8. Inspector's Report
a. Material testing - Gradation and Proctors for aggregate—
samples requested from Kangley and Squak Mtn pits.
b. Traffic Control issues — none
c. Wage Interviews —none
d. Preconstruction Photos — Phil to do
e. Confirmed MOH - completed
Page 3 of 7
a r,�
CITY OF RENTON
. } DU VALL AVE NE
CAG-20-065
9. Environmental Compliance Report
a. Jordan meeting with Phil and Dustin on Wed to walk
project— meet at 8:30 at the staging yard. Discussed
gravel pad. Jordan mentioned that Honeydew Creek
runs under the project in a culvert to the north of 12th
Street.
10.Public Outreach
a. School District - City to meet with School Dist regarding
coordination of projects
b. Businesses — City sending out mailers this week
11.Submittals/Documentation
a. Review ROM.
b. Submittals under review:
• RAM 028B/08C— MH Ring and Cover
• RAM 036B — COC for Valves (will confirm Heat # shown on
COC is same as stamped on valves brought on site)
• RAM 058B— Radar Signs/School Beacons (need CO pricing)
• RAM 065 —Squak Mountain CSTC (Approval Withheld — not
a Tier 2 facility) 5/8-In is OK for trench backfill and PZB
• RAM 066— Squak Mountain CSBC (need Sand Equivalent
test result for review of Bank Run Gravel for Trench Backfill)
Contractor's first choice is Squak Mtn Pit and second is
Kangly/Black River Pit
• RAM 067— Mule Tape and various electrical components
c. RAMs that needs to be submitted:
• BI 43.02 to 48.02 — Dense Foam (if needed)
• BI 49.03/50.03/51.03/52.03/53.03 — Mortar for storm structures
• BI 52.07/53.03 —Storm Pipe Connector (Kor-N-Seal) — G&O
to check to see if sand collar is needed for connect to
existing, and confirm what is needed for connect to existing.
Page 4 of 7
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• BI 10.01.01 — Concrete Class 4000 (for Thrust Blocking)
• BI 10. 01.03 — Reinforcing Steel, Shackle Rods, Clamp Assembly
• BI 10.02 — Polyethylene Plastic Wrap
• BI 16.01 - 16-Inch Gate Valve
• BI 17.04/18.04— Hydrant Restraints
• BI 17.06.01/18.06.01 — Shut-off Valve
• BI 17.06.03/18.06.03 — Valve Extension (if needed)
• BI 17.08/18.08— Blue RPM
• BI 17.09/18.09 —Washed Drain Rock
• BI 17.11/18.11 — Class 4000 for Curb/Gutter &
Sidewalk/concrete pad for hydrant
• BI 17.12/18.12 —Temp H M A
• BI 18 —Tapping Sleeve and Valve
d. Non Material Submittals that need to be submitted:
• Request to Sublet for sub performing existing water main wet tap.
Reed indicated Legacy Tapping is working on paperwork.
• Confined Space program (SP 1-07.1)
• Hydrant meter permit from City (SP 7-09.3(23)) Dustin or
Tiffani has received this from the City
• Mobilization Plan & Work Plan (SP 7-16.1(1)) Discussed
that this is the plan for the City water system work.
e. Material Documentation
• Scale Certification (semi-annual calibration of commercial
scale)for Kangley/Black River and Squak Mtn
• Toxicity Testing and Cert. of Toxicity Characteristics for
Kangley/Black River (under review, please upload to CMS)
12. RFIs —
RFI 1 to RFI 4 responses sent
Page 5 of 7
•
• fz,z, CITY OF RENTON
DUVALL AVE NE
CAG-20-065
13. FWD/ Change Orders—
• No FWD issued yet —
• CO 1 for Retainage—fully signed
• CO 2 for plastic line and FO Termination Panel change. Tani to
prepare FWD
• CO 3 —for school district revisions— in review by G&O and City
14. Subcontractor Status—
PERCENT OF TOTAL CONTRACT Request To Pas
REQUEST THIS PREVIOUS SUBLET Rec'd to Sublet Prevailing
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (apprvd) DBE Wages
1. Ground Up Road Construction,Inc. S25,575.00 0.49% 0.00% 0.49% 8/11/2021 8;12,2021 N 827.'2021
2. Green City,Inc. 3139,480.00 2.70% 0 49% 3.19% 811172021 8+122021 Y 831;2021
3. Totem Electric of Tacoma,Ioe. S734,636.80 14.21% 2,.19% 17.39% 811112021 8111'2021 N 8272021
3a Integrity Nehraics(Lower Tier) S22,432.15 a 3.05% 0.00% 3 05%12/15/2021 12/152021 N 831/2021
4. Lakeridge Paving Company,LLC S706,900.00 13.67% 17.39% 31.07% 8/16.2021 8/17/2021 N 8+30/2021
5. Stripe Rue,Inc. S42,778.60 0.83% 31.07% 31.89%8/162021 0117.2021 N 82412021
6 C&P Fencing S2,1 77 70 0.04% 31.89% 31.94% 81202021 8232021 N 8/26/2021
7. W.E.Coates S61,500.00 1.19% 31.94% 33.13%12115/2021 12115/2021 Y 11%15_021
Legacy Tapping to be added
15.Certified Payrolls— upload to CMS when they come in
16. Progress Payment —
• Progress Payment No 1 —for CO #1 and MOH. City processing
• Progress Payment No 2 — last working day of January, 1/28/22
Page 6 of 7
liz CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Schedule (-� J -—
Work Zone C-Jan-March 25 2022
Work Zone A-Feb 25 to March 25 2022 r —_rl IBtvp 2
Work Zone B&E-March 28 to Aug 22,2022 m
Work Zone F(Medians)-Nov 9 to Dec 20 2022 _,
a —-
•
,, I. -\ -' NE 17IN i
TyEP P'•JE ' - l
� T� LOCATION 1
iln
�, EDULE• INE,1 5T I_
rI 1.
:fq-, . .
�, ` - Z 1 Nak 2aaC
NI7rM
K
,� •
':1 ir MP ; '�zl--_. NE 6TH ST N
us
111 i
NE!TN ST
PRclE a ` X—
¢ LOCATION I
''tiiik. ` -?EDUCE ,
.. L�J• - F 7
WATER MAIN IMPROVEMENTS
Nisi -SCHEDULE B
VICINITY MAP UNDERGROUND IMPROVEMENTS
Nor TO SOUS 'SCHEDULE C
Page 7 of 7
REEDc Date:01/01/22-01/21/22 3 Week Look-Ahead Schedule
TRUCKING 6 EXCAVA77NG Name: Duvall Avenue
,�� `wc••�w ... January
Sc bed
ID Work Description S SMT W T F SS M T W T F SS M T W T F Notes/Resources
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Class a signs X
2 locates X X X X X
3 survey X X X
4 Set up Workzonec X
5 erosion control X X X
6 Clear and grub X X X
7 install hydrants and cap main X X
8 remove water main X X X X X
9 install Storm
10
11
12
13
14
15
16
17
18
19
20
21
,
iRCITY OF RENTON
DUVALL AVE NE
CAG-20-065
CONSTRUCTION MEETING MINUTES
December 28, 2021
Comments made during the meeting are shown in red italics
1. Meeting Attendees
Bob Hanson, City of Renton Phil Van Earwage, G&O
Flora Lee, City of Renton Tani Stafford, G&O
Josef Harnden, City of David Roman-Sanchez, G&O
Renton
Dustin Wright, Reed Jordan Widener, Widener & Assoc.
Trucking & Excavating Inc.
Tiffani Barquist, Reed Cindy Clark, Parametrix Inc.
Trucking & Excavating Inc.
Shawn Reed, Reed Trucking Michael Ballard, G&O
& Excava}in
Ross Widener, Widener&
Assoc.
2. Safety Report
None yet.
3. Prior Meeting Minutes — Comments/Acceptance
No prior minutes
4. Weekly Statement for Working Days ending January 1, 2022
Days Expired: 0
Days Remaining: 260
5. Schedule Progress
Page 1 of 6
°C Y C�c
+ + CITY OF RENTON
DUVALL AVE NE
CAG-20-065
Contractor's Look Ahead Schedule — Project resumes 1/3/22
pending weather — Dustin will provide 3-week look ahead. Weather
pending...Dustin hoping Class A signs ready this week (weather
pending), PCMS boards are up, notifications out, work zone C set up,
lane, survey, TESC, Clear/Grub, contract water (set 2 hydrants,
decommission water main) — waiting for call back from WD 90. Take
water out, storm installation....
Expected materials that are coming out on-site:
• Project Sign, TC signs, PCMS - Flora to send Phil out to take
pics of proposed project signs locations.
• TESC items — out at staging area...good to go.
• Fire Hydrants, thrust block— David: a few submittals waiting
for comments on from City.
• Aggregate
• Storm Pipe
• Catch Basins
6. Engineer's Report
a. Coordination with School Project —frontage improvements —
curb further to west (location of CB's and Filterra may move a
bit)....and signal at 10r'....one year out. Would it make sense for
Reed to do some work to avoid future trench across new road?
b. Electrical Permit — working on load talcs.
c. Coordination with Ecology— no special coordination needed so
far, Flora to follow up.
d. Coordination with MTC - Materials testing (MTC) needs to get
samples for testing. Dustin stated Squawk Mountain doesn't
have a WSDOT Pit ID number. David—Squawk Mtn. is Reed's
second source for recycled aggregate material. Per WDOT spec
top course needs to be from QPL pit for recycled concrete
Page 2 of 6
•
CITY OF RENTON
DUVALL AVE NE
LnrT0�
CAG-20-065
aggregate but for backfill doesn't need to be. Top course may
not be approved but gravel borrow may be.
G&O to check if Kangley Rock will meet gradation for gravel
borrow....
7. Utility Coordination
a. Comcast - UG
b. PSE - UG
c. Water District 90— water lines
Need staging areas when time comes for these utilities. Current
staging area is on Sunset right off of McDonald's.
8. Inspector's Report no updates from Phil....will take pictures.
a. Material testing - Gradation and Proctors for aggregate —
b. Traffic Control issues —
c. Wage Interviews —
9. Environmental Compliance Report
Jordan/Ross —SWPPP documentation making sure we're in compliance —
want timeframe Dustin — silt fence/silt socks in staging area. Waiting for
straw wattles...first order of work. Reed has copy of SWPPP.
10.Public Outreach/Notifications
a. Abutting Properties with driveway access to Duvall — confirmed
these have been sent (all the properties that have TCE's &
emergency services, postmaster, SD perhaps). Flora can pass it
along to SD if they were not notified...Tani will check on SD and KC
Metro.
b. School District -
c. Emergency Services —
d. Postmaster -
11.Submittals/Documentation
a. Review ROM.
Page 3 of 6
+ CITY OF RENTON
'�` DUVALL AVE NE
CAG-20-065
b. Submittals under review:
• RAM 033A — DI Pipe (City review) — looked good; a couple
of comments. Needs double thick cement lining & seal coat.
• RAM 036A — COC for valves & gasket material (City review)
— looked good. Initial review of several fittings noted that
the gaskets material shall be neoprene. G&O will follow up
with Reed via email, will neoprene be used for all gaskets?
• RAM 039A — Hydrant & bolts (City review) — looked good
• RAM 039B/064 — Storz adaptor (City review) looked good
• RAM 041A — Meter Setter (City review) looked good
• RAM 053B — Pole, Arm & anchors (City review) — pole & arm
looked good, anchors —since reusing ex. standards, bolt
pattern etc needs field verification by Reed or Totem. Flora
is checking with Eric.
• RAM 058B — Radar Signs/School Beacons (need CO pricing)
— email to Tiffani— additional cost?Supplier and Totem
wanting to completely replace. Dustin will follow up with
Totem on pricing. Flora is checking with Eric. Can solar
panels be reused?
• RAM 065 — Squak Mountain CSTC (need WSDOT Pit #) — see
previous notes
• RAM 066 — Squak Mountain CSBC (need WSDOT Pit #)— see
previous notes
c. RAMs that needs to be submitted:
• BI 43.02 to 48.02 — Dense Foam (if needed)
• BI 43.03 to 48.03 — Pipe Bedding. Will CSTC from Kangley
be used for storm pipe PZB (RAM 060)? Dustin — correct.
David will note on ROM that no submittal is needed.
• BI 49.03/50.03/51.03/52.03/53.03 — Mortar for storm structures
• BI 52.02 — MH Ring and Cover
• BI 52.07/53.03 — Storm Pipe Connector (Kor-N-Seal)
• BI 10.01.01 — Concrete Class 4000 (for Thrust Blocking)
• BI 10. 01.03 — Reinforcing Steel, Shackle Rods, Clamp Assembly
Page 4 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• BI 10.02 — Polyethylene Plastic Wrap
• BI 16.01 — 16-Inch Gate Valve
• BI 17.04/18.04 — Hydrant Restraints
• BI 17.06.01/18.06.01 — Shut-off Valve
• BI 17.06.03/18.06.03 — Valve Extension (if needed)
• BI 17.08/18.08 — Blue RPM
• BI 17.09/18.09 — Washed Drain Rock
• BI 17.11/18.11 — Class 4000 for Curb/Gutter &
Sidewalk/concrete pad for hydrant
• BI 17.12/18.12 —Temp HMA — Dustin will look into where it
was submitted from, normally us 1/2"from local supplier.
G&O confirmed a material submittal is required for Temp
HMA.
• BI 18 — Tapping Sleeve and Valve
d. Non Material Submittals that need to be submitted:
• Request to Sublet for sub performing existing water main wet tap
• Confined Space program (SP 1-07.1)
• Hydrant meter permit from City (SP 7-09.3(23)) — will need
this to check out meter from City. Flora will ask Holly.
• City is processing permit for new irrigation meter services.
• Mobilization Plan & Work Plan (SP 7-16.1(1))
e. Material Documentation — per submittal response to RAM 060
and 062, need Toxicity Testing and Cert. of Toxicity Characteristics.
Email was sent to Tiffani requesting this documentation. G&O
requested documents be upload to CMS.
12. RFIs —
RFI 1 to RFI 4 responses sent — no outstanding RFI's
13. FWD/ Change Orders —
• No FWD issued yet — discuss plastic line and FO Termination Panel
in Signal Cabinet change — Will Flora need one? City to decide. It's
a Change Order. Tani to send email to Flora.
Page 5 of 6
CITY OF RENTON
DUVALL AVE NE
CAG-20-065
• CO 1 for Retainage -signed by G&0, PMX and Reed, to City for
signatures — with Martin for approval
• CO 2 for plastic line and FO Termination Panel change. — in the
works. May have one for Flashing Beacon change.
• CO 3 —for school district revisions— may have one eventually.
14. Subcontractor Status —
PERCENT OF TOTAL CONTRACT Request To Pay
REQUEST THIS PREVIOUS SUBLET Reel to Sublet Prevviug
NO. SUBCONTRACTOR AMOUNT REQUEST REQUESTS TO DATE RTS (appnd) DBE Wages
I. Ground Up Road Construction,Inc. S25 575.00 0.49% 0.00% 0.49% 8'11'2021 8:12'2021 N 8272021_
2. Green City,Inc. S139,480.00 2.70% 0.49% 3.19°. 8'112021 8122021 Y 8131.2021
3. Totem Electric of Tacoma,Inc. S734,636.80 14.21% 3.19% 17.39°'e 812 2021 812.2021 N 8'27 2021
3a_ Integrity Networks(Lower Tin) S22,432.15 3.05% 0.00% 3.05°•.1215 2021 1215,2021 N 8/312021
4 Lakeridge Paving Company;LLC S706,900.00 13.67% 17.39% 31.07°4 8 16 2021 8117,2021 N 8/30,2021
5. _Stripe Rite,Inc. S42.778.60 0.83% 31.07% 31.89% 8162021 81171021 N 8'24:2021
6. CAP Fencing 52.177.70 0.04% 31.89% 31.94% 8.200'2021 8123/2021 N 8262021
7. W_E.Coates S61,500.00 1.19% 31.94% 33.13%12,15.-2021 12.'152021 Y 111512021
15.Certified Payrolls —
Use CMS.
16. Progress Estimate —
• Progress estimate No 1 —for CO #1 and MOH. Sent to Reed for
sig- Dustin to give contact info for confirming MOH at Totem
Electric's shop.
• Progress estimate No 2 — last working day of January, 1/28/22
Page 6 of 6