CAG-20-065 -Duvall - Schedule
REEDC. Date: 4/29/23 5/19/23 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue April May Sched ID Work Description SSM TWT F SS M T W T F SS M T W T F Notes / Resources 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Illumination critical path X X X X landscaping criticalpath Seeding window begins 3/1 also P g wanting illumination complete prior to X X final restoration thermoplastic Critical path ? ? ? Scheduled long wait list! Fencing X X Monuments X Punchlist work X X X Suspension for Thermoplastic X X X X X X X X X X X REEDC. Date: 4/08/23-4/28/23 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue April Sched ID Work Description SSMTWT FSSMTWTFSSM TWT F Notes / Resources 8 9 10 11 12 13 14 15 16 17 18_ 19 20 21 22 23 24 25 26 27 28 L08 foundation Modification X X _ Illumination critical path X X X X X X X Seeding window begins 3/1 also landscaping critical path wanting illumination complete prior to X X X X final restoration thermoplastic Critical path ? ? ? Scheduled long wait list! Monuments X X Punchlist work X X X X X Suspension for Thermoplastic X REED N Date: 3/25/23 -4/14/23 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue _IMarch April Sched ID Work Description SSMTWT FSSMTWT FSSM T W T F Notes / Resources 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 _ L08 foundation Modification X � I - Illumination critical path --5-1—^ I I X X X Seeding window begins 3/1 also landscaping critical path / I wanting illumination complete prior to ( X X X > final restoration Grind and overlay 14 day cure prior to thermo,Critical Path for plastic thermoplastic Critical path X X X Monuments X X REEDG Date: 3/11/23 -3/31/23 3 Week Look-Ahead Schedule TRUCKING&EXCAVATING Name: Duvall Avenue •...��..,. C,.,u c....«...,..,...,...loon March Sched ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes / Resources 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 LO8 foundation Modification X X Illumination critical path X X X X X X Seeding window begins 3/1 also landscaping critical path wanting illumination complete prior to X X X final restoration Grind and overlay 14 day cure prior to thermo,Critical Path for plastic X X thermoplastic Critical path X X X Monuments X X REEDc Date: 3/11/23-3/31/23 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue 111.III.M.In Clvll CMr.-sw AIM-199O March Sched ID Work Description SSMTWT FSSM TINT F S S M T W T F Notes/ Resources 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 L08 foundation Modification X X Illumination critical path X X X X X X landscaping critical path Seeding window begins 3/1 also wanting illumination complete prior to X X X final restoration Grind and overlay 14 day cure prior to thermo,Critica. Path for plastic X X thermoplastic Critical path X X X Monuments X X REEDC. Date: 2/4/23-2/24/23 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue IFebuary Schad ID Work Description SSM T W T F SS M T W T F SS M T W T F Notes / Resources 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Illumination critical path Waiting on Pole Mods Finish wall and backfill,Critical Path for landscape X X X X Wall cure time so we can backfill,Critical Path X X X X Raise iron X X landscaping Grind and overlay thermoplastic Temp Suspension for electrical,paving,landscape and thermoplastic X X X X X X X X X REEDc Date: 1/28/23 -2/17/23 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue January Sched ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes/ Resources 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Illumination critical path Waiting on Pole Mods Finish wall and backfill X X X X X landscaping X X X X Raise iron X X X X X _ Fiber X X X Permenant signs X Suspension allowed to work on non critical items X X X X X X X X X X X X X REEDG Date: 1/14/23 -2/03/23 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue (..N.w..+r cwu c.....S...:.sr 1991 January Sched ID Work Description SSMTWT FSSM T W T F S S M T W T F Notes I Resources 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 Illumination ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? Waiting on Pole Mods Form wall X X X X X X X X X X X X X walls X X X X Waiting on Schedule Irigation and landscaping X X X X X X X X X X X X X X X Raise iron X X X X Fiber ? ? ? ? ? waiting on schedule confirmation REEDc Date: 1/07/23 -1/27/23 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue �aa�1�Mf�Iw CIVU CM4MW1<M Mrs.1991 January Sched ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources 7 8 9 10 11 12 13 14 105 16 17 18 19 20 21 22 23 24 25 26 27 Illumination ? ? ? ? ? ? ? ? ? ? Waiting on Pole Mods Form wall X X X X X X X X walls X Waiting on Schedule Irigation and landscaping X X X X X X X X X X X X X X X Raise iron X X X X X X X X X REEDcr. Date: 12/10/22-12/30/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue December Sched ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/ Resources 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Illumination X X X X X Form wall X X X X walls X Irigation and landscaping X X X X X X X X X Raise iron X X X X X Signs X X X X X Punchlist items X X X X X X X REEDC. Date: 12/03/22-12/23/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue December Sched ID Work Description SSMTWT F SS M T W T F SS M TWT F Notes / Resources 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17_18 19 20 21 22 23 Illumination X X X X X hawk signal X X Form wall ? ? ? ? ? pour walks ? ? ? ? ? walls ? ? ? ? ? Demo islands X X X Irigation services X Pour Island curb ? ? ? ? Weather suspension X X X X X X X X X X REEDC. Date: 11/19/22-12/09/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue November December Sched ID Work Description SSM T W T F SS M T W T F SS M T W T F Notes / Resources 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 Illumination X X X X X X X X X X X X X hawk signal X X X X X X X X X X grade sidewalk X X X X Form wall X X pour walks X X walls X X X X X X X Set up WKZ F X X Saw cut Islands X X Demo islands X X Irigation services X Pour Island curb X X X X Raise iron X X X REEDc Date: 11/12/22 -12/02/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue October November Sched - 1 ID Work Description SSMTWT F S S M T W T F S S M TWT F Notes / Resources 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 Illumination X X X X X X X X X X X X X hawk signal X X X X X X X X grade sidewalk X X X X X X X X pour wall footing X X pour walks X X walls X X X 1D raise iron X X X X Lumen Ped is in the way of this pour REEDIV c Date: 10/22/22 -11/11/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue 19911 September October Sched ID Work Description S S M T W T F SS M TWT F SS M T W T F Notes I Resources 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 CSBC and CSTC X X X Illumination X X X X X X X X X X X X X Sidewalk and curb prep X X X X X X Flatwork and curb pour X Paving X X X PSE X X X X X X X X X X X X X X REEDitt c. Date: 10/15/22-11/04/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue September October Sched ID Work Description S S. M T W T F S S4 M T W T F S S M T W T F Notes/ Resources 15 161 17 18 19 20 21 22 231 24 25 26 27 28 ,29 30 31 1 2 3 4 CSBC and CSTC �' X X X X X 4, X X X X X X Illumination IX X X X X X X X X X X Sidewalk and curb prep 1 X X X X 1 T Flatwork and curb pour 't x X 1 Paving 'I . X X 7 X PSE 1 _ 1 -; X X X X 1 H la REEDDate: 10/08/22- 10/28/22 3 Week Look-Ahead Schedule TRUCICINGB EXCAVATNYIG Name: Duvall Avenue September October Sched ID Work Description SSMTWT FSSM TWT F SS M T W T F Notes/Resources 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 roadway ex X X X X X CSBC and CSTC X X X X X X X X Illumination X X X X X X X X X X X X X Storm testing X X JUT proofing X Flatwork and curb X X Paving X X PSE ??7? Flatwork Tr?? Walls REEDC. Date:09/24/22-10/14/22 3 Week Look-Ahead Schedule TRUCKING&EXCAVATING Name: Duvall Avenue f..........c...l c....rw..as..we.Iwo September October Sched ID Work Description S SI M T W T F S S M T W T F S S M T W T F Notes/ Resources 24 251 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 JUT IX X X X X roadway ex • X X X X X CSBC and CSTC `' X X X X X X X X X X ' X X X X X Illumination X X X X X X X X X + X X X X X Storm testing X Curb and gutter X X Flatwork form and grading X X X X flatwork pour X Walls X X X X X 1 FEEDDate:09117/22-10/07/22 3 Week Look-Ahead Schedule TRUCKING&EXCAVATING Name: Duvall Avenue f...u..+..c...�c+..ww..«.,..c.ews September Sched ID Work Description SSM TWT F MTWTFSSM T W T F Notes/ Resources 17 18 19 20 21 22 23 26 27 28 29 30 1 2 3 4 5 6 7 JUT X X X X X X X X X X roadway ex X X X X X X X X X X Mi CSBC and CSTC X X X X X X X X X X Illumination X X X X X X X Curb and gutter X X X X X X Flatwork form and grading X X X flatwork pour ;; X REEDc Date:09/03/22-09/23/22 3 Week Look-Ahead Schedule TRUCI N'G&EXCAVATING Name: Duvall Avenue f�.�Mwr� w C•r.l CMww�•w r•1•4r 199i September Sched - - ID Work Description SSMTWT F S M T W T F SS M T W T F Notes/ Resources 3 4 5 6 7 8 9 10 1r 12 13 14 15 16 17 18 19 20 21 22 23 Clear and grub X roadway ex X X X X X X X X X Storm X X X X X X X X JUT X X X X X Illumination X X X X X REEDI. Date:08/13/22-09/02/22 3 Week Look-Ahead Schedule muctario&EXCAVATING Name: Duvall Avenue 11a Olw.... ..nt.Iron August Sched ID Work Description MTWT F S S,. M TWTFSSM T W T F Notes/ Resources 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 31 1 2 Paving X X X X Raise utilities X X OX X X X Illumination X X X X X X Pour flume lids X X switch WKZ X Asphalt pulverization X X X Clear and grub if, I x x REEDDate: 08/06/22 -08/26/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue July August Schell - ID Work Description S S M T W T F S S M T W T F SS M T W T F Notes/ Resources 6 7 8 9 10 11 12 13 14( 15 16 `17 18 19 '20 21 22 23 24 25 26 Grade 10th intersection I X X X X p X CSTC ! X X X X X i X pour walls X X X t _ pour walls X X form and pour Filterra flumes X Plaining _ _ X Paving X X X X X Illumination ' X X X _ X X Raise utilities X X X X X Cleanup t X X X X X 1 Li REEDC. Date:07/30/22-08/19/22 3 Week Look-Ahead Schedule TRUCKING&EXCAVATING Name: Duvall Avenue 1.4Nb...ow Car d cowa.,r,...saw..Iro11 August Sched r - ID Work Description M T W T F M T W T F k M TWTF Notes/ Resources 1 2 3 4 5 8 9 10 11 12 15 16 17 18 19 Sidewalk prep X Pour flat work X Cstc X X X X X Hydrant on loth X X plaining X Grade 10th intersection X X X X X X X X pour walls X X X X X form and pour Filterra flumes X X X X X Paving X X X X X REEDC. Date:07/16/22 08/05/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue �.y+IN.w.�,w;ra GwH4wa:w.:w(w 104f July August Sched 4 ID Work Description SSMTWT F SS 3 M T W T F SS M T W T F Notes/ Resources 16 17 . 18 19 20 21 22 23 2 r 25 26 27 28 29 30 31 1 2 3 4 5 Sidewalk prep X X X X X X X X X X Pour flat workIlX X extend water blow off X set pse vault x X 'y roadway ex X X X ' X X X X X Base rock X X X X X X X X Cstc I °. X X X X X pour walls I I X X X X X form and pour Filterra flumes I IX X X X X Install Hydrant on 10th T �a X X REEDc Date: 06/25/22-07/15/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue +tNf•••M Gird G•wdMw••• iwte ITV{ June July Sched ID Work Description S S M T W T F r -' M TWTFSSM T W T F Notes I Resources 25 2:} 27 28 29 30 1 4 5 6 7 8 9 10 11 12 13 14 15 water tie ins "r X X X X Roadway ex IIX X X X X X X X X Base rock X X X X X i X X X X X X X MiliX X _ X X X • ltialtil X X X X X X X X X pse install ' X X Cdf fill storm X X Curb prep and install ; X X , X X X , . a f REEDc. Date:06/11/22-07/01/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue •.r.11..... n C..l[.w.+w+....,rnc.1996 June Sched ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 Water system install X X X X Water testing X X X X X water tie ins X X X X Illumination system X X X X X X X X X X X X X X X pse install X X Roadway ex X X X X X X X X X Base rock X X X X X X X X X REEDc Date: 05122/22-06/11/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue � �II.I.M w C,v.l ConNn.(.r .w♦\VV6 May Sched ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources 21 22 23 34 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 Storm system X X X X X 1 Illumination X X X X X X X X X PSE Underground X X X X X Water 4 X X X X X X X X X IIIIIINHoliday REED 3 Week Look-Ahead Schedule c Date:05/14/22 06/03/22 TRUCKING 6 EXCAVATING Name: Duvall Avenue May Sched - ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes/ Resources 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 Storm system X X X X X X X X X X Illumination X X X X X PSE Underground X Water X X X X X REEDC. Date: 05/07/22-05/27/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue �...u.«...c.i co.ww....,....ace May Sched - ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Form and pour walls X X X X X Illumination X X X X X high vis fence X demo X X _ Storm X X X X X X X X X X X X X REED C Date: 04/30/22-05/20/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue May Sched ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Form and pour walls X X X X X Clean up and restoration WZC and A X X X X X Paving X X Install hydrants X X X Set upWZBandE X Remove asphalt on WZB and E X X Demo X X Storm WZE X X X X X X X X REED c Date: 04/23/22 -05/13/22 3 Week Look-Ahead Schedule TRUCKING&EXCAVATING Name: Duvall Avenue April Sched ID Work Description SSM TWT F SS M T W T F SS M T W T F Notes/ Resources 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 Form and pour walls X X X X X Clean up and restoration WZC and A X X X X X X X X X X plainning WZA and C X wet taps and hydrants X X X Paving _ X X Set upWZBandE X Remove asphalt on WZB and E X X Storm WZE X X X X X REEDc Date:O4/16/22-O5/6/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue ....U.wr.m C....l Cswww,•....M•,99. April Sched ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes/ Resources 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 5 prep to pave X X 8 form and pour walks X X X Storm WZB X X X X X X X X X Form and pour walls X X X X X X X X 9 Clean up and restoration WZC and A X X X X X 10 plainning WZA and C X 11 Paving X X 12 Set up WZBandE 13 Remove asphalt on WZB and E X X 14 15 16 17 18 19 20 21 REEDC. Date:04/09/22 -04/29/22 3 Week Look-Ahead Schedule TRUCKING 6 EXCAVATING Name: Duvall Avenue a...u..,. c....,...........wa• April Sched - ID Work Description SSMTWT FSSM TINT F SS M T W T F Notes I Resources 9 10 11 12 13 14 15 16_ 17 18 19 20 21 22 23 24 25 26 27 28 29 2 sidewalk prep X X X 5 prep to pave X X X X 6 Clear and grub WZ B and"E X X X silt fence X X X X 7 Pour sidewalk X X 8 form and pour walls X X X X X X X X X X Storm WZB X X X X X 9 Clean up and restoration WZC and A X X X X X 10 plainning WZA and C 11 Paving ? ? ? 12 13 14 15 16 17 18 19 20 21 REEDC. Date:04/02/22-04/22/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue March Sched ID Work Description SS M TWT F SS M T W T F SS M T W T F Notes/ Resources 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 2 sidewalk prep X X X X X X 5 Demo workzone A X X 6 Clear and grub WZ B and D X X X X X X X X 7 Pour sidewalk X X 8 form and pour walls X X X X X X X 9 Clean up and restoration WZ C and A X X X X X 10 11 12 13 14 15 16 17 18 19 20 21 REEDc Date:03/19/22 04/08/22 3 Week Look-Ahead Schedule TRUCKING&EXCAVATING Name: Duvall Avenue March Sched ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes/ Resources 19 20 21 22 23 24 25 26 27 28 209 30 31 1 2 3 4 5 6 7 8 2 Illumination X X X X X 5 Roadway Ex X X X X X 6 CSTC Curb Grade X X X 7 Workzone A 8 erosion control X X 9 demo X X 10 storm X X 11 Roadway Ex X 12 CSTC Curb Grade X 13 Curb prep Zone A and C X X X ADA Pre con X 14 Pour curb X X 15 sidewalk prep X X X X X X X 16 Sidewalk pour X X X 17 18 19 20 21 REEDC. Date: 03/12/22-04/01/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue March Sched ID Work Description SSMT W T F SS M T W T F SS M T W T F Notes / Resources 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 Illumination X X_ X X X 5 Roadway Ex X X_ X 6 CSTC Curb Grade X _X_ X 7 Workzone A 8 erosion control X 9 demo X 10 storm _ X X 11 Roadway Ex X X 12 CSTC Curb Grade X X 13 Curb prep Zone A and C X X 14 Pour curb X X 15 16 17 18 19 20 _ 21 REEDC. Date: 03/05/22 -03/25/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue March Sched ID Work Description SSMTWT F SSM T W T F SS M T W T F Notes / Resources 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 2 Illumination X X X X X X X X X X 4 Additional storm on 9th X X 5 Roadway Ex X X X 6 CSTC Curb Grade X X X 7 Workzone A 8 erosion control X 9 demo X 10 storm X X 11 Roadway Ex X X 12 CSTC Curb Grade X X 13 Curb prep Zone A and C X X 14 Pour curb X X 15 16 17 18 19 20 21 REED3 Week Look-Ahead Schedule c Date: 02/26/22 03/18/22 TRUCKING& EXCAVATING Name: Duvall Avenue R.•.•.+.•n c u Ccnwvaa.«a ana.fri Feburary Sched ID Work Description SSMTWT F SS M T W T F SS M T W T F Notes / Resources 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 _ 1 JUT&Vault Installation R X _ 2 Illumination X X X X X X X X_ X X X X X X 3 storm crossing on duvall X X X X 4 Additional storm on 9th? X X 5 Roadway Ex X X X X 6 CSTC Curb Grade X X X X 7 Workzone A 8 erosion control X 9 demo X X 10 storm X X X 11 Roadway Ex X 12 CSTC Curb Grade X 13 14 _ 15 16 17 18 19 _ . _20 - 21 REED c Date: 02/19/22 -03/11/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue Feburary Sched r ID Work Description SSMTWT F SSM T W T F SS M T W T F Notes / Resources 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 1 JUT&Vault Installation X X X X X X X 2 Illumination X X X X X X X X X X X X X X 3 storm crossing on duvall X X 4 Additional storm on 9th? X X -5 Roadway Ex X X X 6 CSTC Curb Grade X X X 7 _ 8 9 10 11 12 13 14 15 16 17 18 _ 19 20 21 REED . Date:02/12/22 03/04/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue Feburary Sched ID Work Description S S M T W T FSSM T W T F SS M T W T F Notes I Resources 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 1 Storm install X X X X X 2 JUT&Vault Installation X X X X X X X X X X 3 4 5 6 7 • 9 10 11 12 13 14 15 16 17 18 19 20 21 REEDC. Date: 02/05/22-02/25/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue I•..Ib... n C,.J C.w...w..r..wo ligt Feburary Sched - ID Work Description SSMTWT FSSMTWTFSSM T W T F Notes / Resources 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 1 Storm install X X X X X X X X X X lost days due to dewatenng discussion • 2 JUT&Vault Installation X X X X X downtime and anticipated loss of production 3 4 5 6 7 9 10 11 12 13 14 15 16 17 18 19 20 21 REEDc Date: 01/29/22 02118/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue January Feburary Sched ID Work Description SSMTWT F SSM T W T F SS M T W T F Notes / Resources 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 Storm install X X X X X X X X X' X 2 JUT&Vault Installation X X X X X 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 REEDc. Date:01/22/22 02111122 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue January Feburary Sched ID Work Description SSMTWT FSSM TWTFSSM T W T F Notes / Resources 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 _ 9 10 11 1 Remove watermain X X X X X 2 Storm install X X X X X X X X X X X 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 REEDc Date:01/15/22 -02/04/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue n,.u.«.a.ca.,c...w..««.....199i January Feburary Sched ID Work Description SSMTWT FSSM TWT F S S M T W T F Notes / Resources 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 1 erosion control X Clear and grub X X 3 Make edge of rd fills X X 4 install hydrants and cap main X X X 5 remove water main X X X X X X 6 install Storm X X X X X X X X X X 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 REED c Date: 01/08/22 -01128122 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue January Sched ID Work Description SSMTWT F SSM T W T F SS M T W T F Notes / Resources 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 Set up Workzone c - X _ locates X - survey X X 4 erosion control X X X 5 Clear and grub X X X X 6 Make edge of rd fills X X X X 7 install hydrants and cap main _ X X X 8 remove water main X X X _ X X X X 9 install Storm _ X X X X X 10 11 12 13 14 15 16 17 18 19 20 21 REEDG Date:01/01/22 -01/21/22 3 Week Look-Ahead Schedule TRUCKING& EXCAVATING Name: Duvall Avenue January Sched - - ID Work Description SSMTWT FSSM T W T F SS M T W T F Notes / Resources 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 Class a signs X _ locates X X X X X I survey X X X _' 4 Set up Workzone c X 5 erosion control X X X 6 Clear and grub X X X 7 install hydrants and cap main X X 8 remove water main X X X X X 9 install Storm 10 11 12 13 14 15 16 17 18 19 20 21 - --ji _ (, -.) 1 ewo Q n I/ 17b- 7 I; 4 Li C`A4 "_. arm gr r 14 9 POO1ETION _ a- i: \- \ililirdlilooripli Shit 5CEpUE , NE J r -F- Z. 1 4 "(Ire C W O" t ` 1' Z - .�, ° -__ NE 6TH ST bt 1.11,1 No ; g d I „ = 4 NE 4Trr sr PROJE — - I �, ,f _ �1.g LOCATION .illik. °`Li (c� r WATER MAIN IMPROVEMENTS N -SCHEDULE B VICINITY MAP UNDERGROUND IMPROVEMENTS NOT TO SLArr -SCHEDULE C City of Renton - Duvall Ave NE, CAG 20-065 . WZC-Jan - May 2022 `1 ) WZA- Feb- May2022 .,� +► WZB &E- Mar-Aug 22, 2022 s. PIE. aLVD Z,� 4 ii -L rt .,:' WZD-Sept- Nov 14, 2022 gFh'$ WZF (Medians)- Nov-Jan 8, 2023 ' _ 47/ Ir ` , I p• . 1 . iii,w LOCATION I 1 ,411141 EDULE . NE e .5T _ - VAP MINI II iArg11111111101111111111t:i z iiii ) litlir mon a a ,. Irif'" Ira a HE 6TH 5T u / I� °` z L. —a— --�--' d Nip 3 s A0111 ' /'.f! '4THST ..1 plipir PR* € A .Mt".: z 1. LOCATION win# r.ED41 . \MS . -----) :‘,..rn , Fr://:: — ---1 I WATER MAIN IMPROVEMENTS N -SaIEDULE S A 1lt+CINITYMAP UNDERGROUND IMPROVEMENTS NOT TO SCALE -SCHEDULE C City of Renton - Duvall Ave NE, CAG 20-065 NMS 008A -Project Schedule 0 Mode Successors 21 I Qtr 1,2022 Qtr 2,2022 Qtr 3,2022 I Qtr 4,2022 .Qtr 1 2023 ID 1 Duvall Avenue Ne 1Durabon Start IFinis��n023,due to Holidays _. N_ov 1._.Dec ,r } .yew Mar 1--_Appr. May...j.. Jun ;......--Jul__.1 Aug L....5Cp.._.._o I Nov__„t ,,.__....Jan_._1 Feb _ 1 t1 260 days Mon 1/10/22 Fri l- - I 2 PCMS 275 days Mon 12/20/21 Fri t1/13/2023 I 3 { 1 Owner/Resident/Emergency notification 1 day Mon 12/20/21 Mon 12/20/21 4 Traffic control 260 days Mon 1/10/22 Fri 1/6/23 5 "" Mobilization 2 days Mon 1/3/22 Tue 1/4/22 6 21P. Class A Signs 2 days Mon 1/3/22 Tue 1/4/22 7 it Workzone C Construction 60 days Mon 1/10/22 Fd 4/1/22 43 IIIMIMIL 8 fr Survey 2 days Mon 1/10/22 Tue 1/11/22 (I 9 * erosion control 3 days Tue 1/11/22 Thu 1/13/22 ' I 10 fr sawcutting 2 days Wed 1/12/22 Thu 1/13/22 11 SUBMITTAL REVIEW r, clear and grub 4 days Fri 1/14/22 11/20/22 I 12,14,13 1/11/22=HOiaay Ili No Exceptions Taken In demo 2 days Thu 1/20/22 Fri 1/21/22 15 x Make Corrections Noted 13 I as% Water shutdown and thrust Block notification 1 day Thu 1/20/22 Thu 1/20/22 1 _ Amend&Resubmit Rejected-See Remarks 14�' �,, Pothole Utilities 2 days Thu 1/20/22 Fri 1/21/22 IMPORTANT NOTICE:This review 15 in install new hydrants 2 days Mon 1/24/22 Tue 1/25/22 16 does not relieve the ContraQor from �16 , Removal of Structures and obstructions 5 days Wed 1/26/22 Tue 2/1/22 18,17 responsibility to comply&conform 17 S Storm Precon 1 day Wed 2/2/22 Wed 2/2/22 I with the Plans,Specifications,and 18 ari storm system SO days Wed 2/2/22 Tue 2/15/22 20,21,19 Contract Documents. 19 se. Fiber Optic notification pays Wed 2/16/22 I1/17/2021 I 1 1166 20 in Underground utilities 20 days Wed 2/16/22 I3/16/22 I Gray**Osborne'Lac. CONSULTING ENGINEERS 21 ma illumination 20 days Wed 2/16/22 13/16/22 I 22 Roadway Excavation and subgrade 5 days Wed 2/23/22 Tue 3/1/22 23,29 E, By: TLS Date 1/10/22 23 0 of'. CSTC 4 days Wed 3/2/22 Mon 3/7/22 25,39,24 24 E. ADA and Sidewalk Pre con 1 day? Tue 3/8/22 Tue 3/8/22 25 E. Curb and Gutter 2 days Tue 3/8/22 Wed 3/9/22 26 26 Sidewalk,Ramps,DW and High walls inonst'd Dwyicxiuns 13 days Thu 3/10/22 Mon 3/28/22 27,41 '.. 27 W Planning weather pending 2 days Tue 3/29/22 Wed 3/30/22 28,42 28 mitt hma weather pending 2 days Thu 3/31/22 Fri 4/1/22 29 tea Workzone A Construction 22 days? Wed 3/2/22 Thu 3/31/22 30 tt►a Survey 1 day Wed 3/2/22 Wed 3/2/22 1 Ea Erosion control 1 day Wed 3/2/22 Wed 3/2/22 1 mr, sawcutting 1 day Wed 3/2/22 Wed 3/2/22 33 33 art Clear and grub 1 day Thu 3/3/22 Thu 3/3/22 34,35 34 l.. Demo 1 day Fri 3/4/22 Fri 3/4/22 36 35 In Pothole Utilities 1 day? Fri 3/4/22 Fri 3/4/22 36 in Storm system 1 day Mon 3/7/22 Mon 3/7/22 37 s. 37 II.i* Roadway Excavation and subgrade 2 days Tue 3/8/22 Wed 3/9/22 38 38 •a CSTC 2 days Thu 3/1o/22 Fri 3/11/22 i I Task-Critical Project Summary r'-- -I Manual Task I I Start-only C Deadline i Project:Duvall ave. Project Sch Split Inactive Task Duration-only Finish only3 Progress Date:Mon 1/10/22 Milestone ♦ Inactive Milestone Manual Summary Rollup External Tasks IIIIIOIIIIIIIIIIIIIIIIIINIII Manual Progress Summary 1�'" '"' • Inactive Summary I 1 Manual Summary r'"'"'' '' l External Milestone 0 Page 1 ITaID Task© MID ode J Curb Gutter _.. Duration !Start Finish '''.Successors 121 T I Qtr 1,2022 Qtr 2,2022 Qtr 3,2022 Qtr 4,2022 .Qtr 1,2023 II' .....___ _. ' Noy .I.Dec ._...Jan �Fe _i_1d4r I Apr.. I May_i.fin L---__WI tugL Sep I Oct ! Nov I '.Dec ...r lenL Feb 39 tr 1 day Tue 3/8/22 Tue 3/8/22 40 40 Mr Sidewalk 1 day Wed 3/9/22 Wed 3/9/22 I 41 In Planning weather pending 1 day Tue 3/29/22 Tue 3/29/22 42 M Hma weather pending 1 day Thu 3/31/22 Thu 3/31/22 I 43 / Workzone B and E Construction 106 days Mon 4/4/22 Mon 8/29/22 67 P 4. 44 * Survey 2 days Mon 4/4/22 Tue 4/5/22 g 45 2r Sawcutting 1 day Tue 4/5/22 Tue 4/5/22 1 46 2► Erosion control 3 days Tue 4/5/22 Thu 4/7/22 47 47 wit Clear and grub 2 days Fri 4/8/22 Mon 4/11/22 48 48 In Pulverize and remove asphalt 2 days Tue 4/12/22 Wed 4/13/22 49 l; Removal of Structures and obstructions 7 days Thu4/14/22 Frl 4/22/22 50 In Demo 2 days Mon 4/25/22 Tue 4/26/22 51 51 In Pothole Utilities 2 days Wed 4/27/22 Thu 4/28/22 52 52 3 Storm system 25 days Fri 4/29/22 6/4/22 53,58,57 5/31/22=Holiday 53 lin Water System Incl.notiticatios 15 days Fri 6/3/22 Thu 6/23/22 55,56,60 54 2I Cdf Fill Storm 2 days Fri 6/17/22 Mon 6/20/22 55 n Underground utilities 40 days Fri 6/24/22 1815n2_ _ I 7/4=Holiday 56 In illumination 40 days Fri 6/24/22 I6/19/22 I 59 57 04 Electrical system material procurement 1 day Fri 6/3/22 Fri 6/3/22I'MI —58 Kit Electrical system Complete incl.sakiage notification 57 days Fri 6/3/22 Mon 8/22/22 59 W.a Signal turn on notification 5day Fri 8/19/22 Ian sin I 1 60 n Roadway Excavation and subgrade 20 days Fri 6/24/22 Thu 7/21/22 61 61 0% Place Recycled Asphalt , 5 days Fri 7/22/22 Thu 7/28/22 62 62 ter y CSTC 3 days Frl7/29/22 Tue 8/2/22 63 ', 63 we. Curb and Gutter 3 days Wed 8/3/22 Fri 8/5/22 64 64 arm Sidewalk,Ramps,DW !incl.2W closure notirutions I 8 days Mon 8/8/22 Wed 8/17/22 65 65 S CSTC 3 days Thu 8/18/22 Mon 8/22/22 66 66 M; Hma 5 days Tue 8/23/22 Mon 8/29/22 67 Workzone D Construction 56 days Mon 8/29/22 Mon 11/14/22 86 or 68 r► Survey 2 days Mon 8/29/22 Tue 8/30/22 1 Sawcutting 1 day Tue 8/30/22 Tue 8/30/22 1 2r Erosion control 2 days Tue 8/30/22 Wed 8/31/22 71 i r I a►� Clear and grub 2 days Thu 9/1/22 Fri 9/2/22 72 1 72 ter Pulverize and remove asphalt 2 days I9/6/22 I Tue 9/6/22 73,74 I9/5/22=Holiday 1 ill , 73 W. Removal of Structures and obstructions 2 days Wed 9/7/22 Thu 9/8/22 75 74 M1 Pothole Utilities 2 days Wed 9/7/22 Thu 9/8/22 75 W. Storm system 5 days Fri 9/9/22 Thu 9/15/22 76 76 a►y Water System I incl.notifications I 1 day Fri 9/16/22 Fri 9/16/22 77,78,79 Task-Critical Project Summary I I Manual Task Start-only I Deadline i Project:Duvall ave. Project Sch Split Inactive Task Duration onlyFinish-only 3 Progress Date:Mon 1/10/22 Milestone ♦ Inactive Milestone Manual Summary Rollup mmimmilimmim External Tasks 111111111111111111111111111111111 Manual Progress Summary 11 Inactive Summary I Li Manual Summary 11 External Milestone <> Page 2 ID (Task Task Name Duration Start Finish Successors 21 Qtr 1,2022 Qtr 2,2022 Qtr 3,2022 I Qtr 4,2022 Qtr 1,2023 tw 0 Mode e I Feb___!_L1ar I Ayr-1_May- I Jun NI J -nuo Se 1_QG I N 1Dec_ tan I Feb 77 in Underground utilities 15 days Mon 9/19/22 Fri 10/7/22 78 in illumination 15 days Mon 9/19/22 Fri 10/7/22 79 on Roadway Excavation and subgrade 20 days Mon 9/19/22 Fri 10/14/22 80 80 i, Place Recycled Asphalt 5 days Mon 10/17/22 Fri 10/21/22 81 81 tr, CSTC 3 days Mon 10/24/22 Wed 10/26/22 82 82 11,4 Curb and Gutter 2 days Thu 10/27/22 Fri 10/28/22 83 83 n Sidewalk and walls 3 days Mon 10/31/22 Wed 11/2/22 84 t ' 84 �.i CSTC 3 days Thu 11/3/22 Mon 11/7/22 85 i 85 I, hma weather pending 5 days Tue 11/8/22 g11/1s/22 I I11/11/22=Holiday I A 86 Workzone F Construction 30 days Tue 11/15/22 Mon 12/26/22 97 n Survey 1 day Tue 11/15/22 Tue 11/15/22 88,91 111 n Sawcutting 1 day Wed 11/16/22 Wed 11/16/22 89 89 m, Roadway Excavation and subgrade 3 days Thu 11/17/22 Mon 11/21/22 90 90 n Extruded Curb 3 days Tue 11/22/22 I11/28/22 I 92,94 11/24adn 11/15/22=Hodiays 91 tom, irragation install notification I10day 1 111/02/22 I Wed 11/16/22 L 92 I S, Irrigation 20 days (11/28/22 I 112/23/22 I 93 ® I, Topsoil 20 days I11/28/22 I 112/23/22 I 9.4 a plant delivery notification 17 day I 111/21/22 I I11/28/22 I 1 95 In 0, Landscaping 20 days I22/2s/22 I 112/23/22 I 96 96 W. Hydroseeding 2 days Fri 12/23/22 I1/03/23 I 12/26/22-1/2/23 are non-working days 97 or, Pavement days 8 Signs and Markings I1/03/23 I I1/12/23 I due to Christmas,the week after 9Christmas and New Years Day 98 ., paint line Layout notification L4 day I12/20/22 I 112/23/22 I I 99 W, Permanent Signing 8 days 11/3/2023 I 11/12/za23 I IN 100 ils, Remove Markings 8 days 11/3/2023 I 11/12/2023 I Ill 101 O, Paint Lines 8 days 11/3/2023 I 11/12/2023 I 102 ot, Plastic markings 8 days 11/3/2023 I 11/12/2023 I 103 f 103 /, Substantial Completion 1 day I1/13/2023 I 11/13/2023 I 101 APunchlst 6days I1/14/2023 I 1/19/2023 J{" 105 ''.. 71*9 106 71g 109 )t 110-_-1 M Task-Critical — Project Summary I I Manual Task 1111111111111111111111111111111111111111 Start-only I Deadline 4 Project:Duvall ave. Project Sch Split .................. Inactive Task Duration-only 1111111111111111111111111111111111W Finish-only 3 Progress Date:Mon 1/10/22 Milestone ♦ Inactive Milestone Manual Summary Rollup ammommammot. External Tasks "' .. Manual Progress Summary 1— " 1 Inactive Summary Manual Summary I— 1 External Milestone • Page 3 r MD askTask Name Duration Start Finish Predecessors 0 5 day written notice b OW t,2e22 Qtr L 2022 0012022 Qtr a.2022 Qtr t,2p1 1 Mode i Oper1y OwnterSlreaideftl34 _ t- Ian I _Feb I Mar 1. Aq 1 May 1 tin lul ! Aug 1 Sep Oct ! NOV I pcc_.. Jan t p► Duvall Avenue Ne rior to commencement of 260 days Mon 1/3/22 Fri 12/30/22 p -v Y YY Y YYYY"YY YYYYY\` 2 Mobilization the work 4 days Mon 1/3/22 Thu 1/6/22 Phase identity the Oddest Path activities ,3 3 >* Class A Signs 2 days Mon 1/3/22 Tue 1/4/22 _A 2,,x- 4 fr Workzone C Construction 60 days Mon 1/3/22 Fri 3/25/22 3 5 OP Traffic control 60 days Mon 1/3/22 Fri 3/25/22 — —Y-Y 1— Y Y Tor am Worlaonss,PCMS shall provide notice 10 days 6 JO MS 10 ds s or u 60 days Mon 1/3/22 Fri 3/25/22 • • ,. J. closures. . , start date as needed.oli g for Work tu i 2 days Tue 1/4/22 Wed 1/5/22 - orhe C erosion control 2 hour written notice to 3 days Wed 1/5/22 Fri 1/7/22 9 i 1 sawcutting` mergency personnel for 2 days Thu 1/6/22 Fri 1/7/22 M. YY'Y-Y Y`4—,4- 1 e closure(all Workzones) 14 day notice prior clear and grub 4 days Mon 1/10/22 Thu 1/13/22 9 Plasm nets,balers holidays am aonworking days(MOOT 148.6). 4 Mater main shutoff required? Mast dualism of sclivRla as rlasdsd. nenarg FO emo 2 days Fri 1/14/22 Mon 1/17/22 10 4 f so,provide 10 day notice of shutoff t-0s-s Time lot eompledon t install new drants 2 days Tue 1/18/22 Wed 1/19/22 11 'all Workzones.as required) I 13 TM Co .r5e rw ra Work pinskar Contract ork et,.the Mantel a•.ottatr 1 { emoval of Str es and obstructions 5 days Thu 1/20/22 Wed 1/26/22 12 W [tap'stated nOwCc mar es,r.tsoraseemnodt,theErgneerinarcora,2ew.h 14 . ms system 1 Working Day notice for Thrust Block seaan1-0E8 E. vday II be moroNasa'.vn.ng Darr.aces.is n a nmw+c-e Oa, y5 Thu 21/10/22 Wed 32/9/22 13 1 1 man Earmnca,Yraoyneda•.Wdsaba m,A'coon rUnt day s definer/as a Saewn. 4 Storm nstallation. 1 WDnoticeforbaekfill asu.tday.ae.+saeorhrrea,e.,.hchthecnna,:tspecr�fa,rrhbitsWorkondu Underground utilities inspection required) Thu 2/10/22 Wed 3/9/22 14 1 1 r Preconstruction P (all Workzones,as rmc r,amuupcere,>Asa,pt.eaawlessschtwl.ottr,earhe;r,weays Field Meeting illumination c +ary uueyt Thu Wed3/9/22 I I 1t.M er e .rar-«y w e4Jaur,.11.et�td.a:.e,rylrm, ..d wy,,, y.Stn e sly a.Labor Day Waenoery 1rsana,8••ne ow the day after II...i re_rd Roadway Excavation and subg 4 hour notice for Thu 2/17/22 Wed 2/23/22 I4 [Mamas Day.wh m a en a these hmna,n tar co a stm n ,.Ow lolI a earn a,aay ma, a ledrical Inspector(all to counted a noM«ass,a m,Wheer des.aeay fats debt a Saluda,.en we<mre rrda„ 18 CSTC T u2/24/22 Tue 1/22 17 snot m<a.alodantr,as:aye day.lit nasSettee Derrynlaa BaN aatatrt was orkzares,as required) day notice for a.a�d as nav t deli mn 19 p► Curb and Gutter .,.,.h /2/22 18 i riveway closure(all A.A A A ' 20 I l/ /Eldewalk,Ramps,DW and High walls 13 days o ) /21/22 19 ADA Ramps / Planning weather ng days Tue 3/22/22 Wed 3/23/22 20 Preconstruction idewalk Preconstruction field meeting lima weather pending ling and door days Thu 3/24/22 Fri 3/25/22 21 SUgN11TTAL REVIEW ,. Workzone A Construction ngers(all Workzones) 0 days Fri 2/25/22 Thu 3/24/22 24 f Traffic control 0 days Fri 2/25/22 Thu 3/24/22 No Exceptions Taken Make Corrections Noted 25 JP PCMS 20 days Fri 2/25/22 Thu 3/24/22 X Amend&Resubmit 26 fr Survey 1 day Fri 2/25/22 Fri 2/25/22 1 Rejected-See Remarks 27 a Erosion control 1 day Fri 2/25/22 Fri 2/25/22 1 IMPORTANT NOTICE:This review 28 .# Sawcutting 1 day Fri 2/25/22 Fri 2/25/22 $ does not relieve the Contractor from 29 pt Clear and grub Potholing for Work 1 day Mon 2/28/22 Mon 2/28/22 28 responsibility to comply&conform 30 J Demo i� -Zone A with the Plants.Speaficaoons,and 1 day Tue 3/1/22 Tue 3/1/22 29 I ,1 Storm system 1 day Wed 3/2/22 Wed 3/2/22 30 Contract Documents. 111151) 2 P Roadway Excavation and subgrade 2 days Thu 3/3/22 Fri 3/4/22 31 �'l,&y HrOaboa�,Lam 33 fr CSTC 2 days Mon 3/7/22 Tue 3/8/22 32 6nNSIA1II EDrGfeER6 34 fr Curb and Gutter 1 day Wed 3/2/22 Wed 3/2/22 18 117 35 it Sidewalk 1 day Thu 3/3/22 Thu 3/3/22 34 By: TLS/DRS Date: 12/28/21 36 fr Planning weather pending 1 day Tue 3/22/22 Tue 3/22/22 20 r 37 Hma weather pending 1 day Thu 3/24/22 Thu 3/24/22 21 1 38 I if Workzone B and E Construction 106 days Mon 3/28/22 Mon 8/22/22 37 .. -t Task 111111111111111111111111111.11111t Project Summary 1 I Manual Task 1 I Start-only 1 Deadline a Project:Duvall ave. Project Sch Split . i Inactive Task Duration-only Finish-only ] Progress Date:Fri 12/10/21 Milestone ♦ Inactive Milestone Manual Summary!Runup External Tasks Manual Progress - -- Summary 1-1 Inactive Summary 1 I Manual Summary 1--1 External Milestone O Page 1 ID - trask Task Name Duration !Finish 'Predecessors Qtr1,2022 {Qtr 2,2022 Qtr 3,2022 Qtr 4,2022 Qtr 1,20 e Mode { 1 Dec Jan I Feb I Mar • Apr ' May I I Jun _Jd I Aug I Sep Oct Noe { Dec Jan 39 1► Traffic control 4 day notice to 105 days Mon 3/28/22 Fri 8/19/22 1 rrmenramil 40 Ji PCMS 'ntenance Shop for 105 days Mon 3/28/22 Fri 8/19/22 1 .entletil � 41 * Survey '"ivory of salvaged 2 days Tue 3/29/22 Wed 3/30/22 I Potholing for Work Sawcutting tonal I day Wed 3/30/22 Wed 3/30/22 i Zone B and E f Erosion contro 'Working Days notice 3 days Wed 3/30/22 Fri 4/1/22 U • signal tum on 44 • A Clear and gr . 2 days Mon 4/4/22 Tue 4/5/22 43 45 I .0 Pulverize a :r- ove asphalt 2 days Wed 4/6/22 Thu 4/7/22 44 I+ 46 t A' Removal• uctures and obstructions 7 days Fri 4/8/22 Mon 4/18/22 45 itl. 47 A Demo 2 days Tue 4/19/22 Wed 4/20/22 46 x1 48 . Cdf Fil -•rm 2 days Thu 4/21/22 Fri 4/22/22 47 (. bandon storm for• em 25 days Mon 4/25/22 Fri 5/27/22 48 ter new storm is instructed W. System 15 days Mon 5/30/22 Fri6/17/22 49 ,1 >r 7.ergroundutilities 40 days Mon 6/20/22 Fri8/12/22 50 1 52 ! umination 40 days Mon 6/20/22 Fri 8/12/22 50 :> t 53 i 4" Electrical system Complete 57 days Mon 5/30/22 Tue 8/16/22 49 s 54 ' Fr Roadway Excavation and subgrade 20 days Mon 6/20/22 Fri 7/15/22 50 55 ; 1 Place Recycled Asphalt 5 days Mon 7/18/22 Fri 7/22/22 54 56 ,40. CSTC 3 days Mon 7/25/22 Wed 7/27/22 55 i 57 . >r Curb and Gutter 2 days Thu 7/28/22 Fri 7/29/22 56 T 58 I 1 Sidewalk,Ramps,DW and High walls 8 days Mon 8/1/22 Wed 8/10/22 57 Td 59 4 f CSTC 3 days Thu 8/11/22 Mon 8/15/22 58 if 60 ,f Hma 5 days Tue 8/16/22 Mon 8/22/22 59 i high walls are in I 61 i Worlaone D Construction ones g and 56 days Tue 8/23/22 Tue 11/8/22 60 f1 4 62 + Traffic Control ,see work zone 55 days Tue 8/23/22 Mon 11/7/22 ruq 63 •r PCMS 55 days Tue 8/23/22 Mon 11/7/22 rMM 64 Survey 2 days Wed 8/24/22 Thu 8/25/22 1 65 A Sawcutting 1 day Thu 8/25/22 Thu 8/25/22 il 66 t' ' Erosion control 2 days Thu 8/25/22 Fri 8/26/22 g, 67 , r Clear and grub 2 days Mon 8/29/22 Tue 8/30/22 66 ri 68 Jr Pulverize and remove asphalt 2 days Wed 8/31/22 Thu 9/1/22 67 ft A9 ' t Removal of Structures and obstructions 2 days Fri 9/2/22 Mon 9/5/22 68 D t Storm system 5 days Tue 9/6/22 Mon 9/12/22 69 at 1 Water System 1 day Tue 9/13/22 Tue 9/13/22 70 il+ Potholing for Work 72 r Underground '•.es ne D 15 days Wed 9/14/22 Tue 10/4/22 71 i 1 73 • illumination 15 days Wed 9/14/22 Tue 10/4/22 71 1 74 Roadway Excavation and su de Wails in advance 20 days Wed 9/14/22 Tue 10/11/22 71 IT i 75 Place Recycled Asphalt pf Utility 5 days Wed 10/12/22 Tue 10/18/22 74 1'f, 76 CSTC rgro 3 days Wed 10/19/22 Fri 10/21/22 75 IT vaults Task 411111111111111111111111111111111t Prayect Summary I "•1 Manual Task Start-only C Deadline i Project:Duvall ave. Project Sch Split Inactive Task Duration-only _ - - finish-only ] Progress Date:Fri 12/10/21 Milestone ♦ Inactive Milestone Manual Summary Ratup External Tasks Manual Progress Summary P--1 Martine Summary I 1 Manual Summary r"--1 External Milestone O Page 2 ID I Task Task Name Duration tart '.Finish !Predecessors 0 Mode tiv 1.2022 Qtr 2,2022 ptr 3.2022 Qu 4,2022 001.20 Dec /an I Feb 1 Mar I Am I May I Jsrn I )e I ors 1 Sep I Oct 1 Nary 1 nsc I_I 77 yh Curb and Gutter 1 day Mon 10/24/22 Mon 10/24/22 76 iri 78 A Sidewalk 3 days Tue 10/25/22 Thu 10/27/22 77 II 79 fr CSTC 3 days Fri 10/28/22 Tue 11/1/22 78 di 80 A hma weather pending 5 days Wed 11/2/22 Tue 11/8/22 79 81 A Workzone F Construction 30 days Wed 11/9/22 Tue 12/20/22 80 82 1♦ Traffic Control 30 days Wed 11/9/22 Tue 12/20/22 83 { PCMS 30 days Wed 11/9/22 Tue 12/20/22 Invlltlubs I 84 Survey 1 day Thu 11/10/22 Thu 11/10/22 F. 85 fr Sawcutting 1 day Fri 11/11/22 Fri 11/11/22 84 11 10 calendar day 86 A Roadway Excavation and subgrade otice prior to 3 days Mon 11/14/22 Wed 11/16/22 85il 7 40 f Extruded Curb rrigation installation 2 days Thu 11/17/22 Fri 11/18/22 86 Irrigation week notice prior to 20 days Mon 11/21/22 Fri 12/16/22 87 r 1 i 89 2► Topsoil lant material delivery 20 days Mon 11/21/22 Fri 12/16/22 IF I 90 )1 Landscaping 20 days Mon 11/21/22 Fri 12/16/22 I. I. 91 fr Ftydroseeding 2 days Man 12/19/22 Tue 12/20/22 90 i, 92 A Pavement Markings and Signs 7 days Wed 12/21/22 Thu 12/29/22 91 93 fr Traffic control 7 days Wed 12/21/22 Thu 12/29/22 1 94 fr PCMS 2 day notice for 7 days Wed 12/21/22 Thu 12/29/22 I. driveway closure(all 95 0 Permanent Sign --I— Workzones) 7 days Wed 12/21/22 Thu 12/29/22 I 96 A Remove Markings 7 days Wed 12/21/22 Thu 12/29/22 I" 97 fr Paint Lines 7 days Wed 12/21/22 Thu 12/29/22 98 0 Plastic markings 8 hour notice prior to 7 days Wed 12/21/22 Thu 12/29/22 . 1 h 99 7, Substantial Completion -mark 1 day Fri 12/30/22 Fri 12/30/22 98 100 hannelization 101 it — 102 , 103 {A 104 1kv 105 A 106 At, 1111 Task Project Summary I I Manual Tam 21141118111111111111M01 Start-only C Deadline i Project Duvall ave. Project Sch Split ,,,,,,,,,,,,,, ,,, Inactive Task Duration-only fillieRMIIIMIXRIE Finish-only 7 Progress Date:Fri 12/10/21 milestone • Inactive Mdesaone Manual Summary Rollup immmm External Tasks s...: Manual Progress Summary 1 ".."'"...."'"-1 Inactive Summary I I Manual Summary I1 External Milestone @ Page 3 ID Task Task Name Duration Start Finish PAllredecessors Qtr 4,2021 Qtr 1,2022 Qtr 2,2022 Qtr 3,2022 0 Mode Sep Od Nov Dec Jan Feb Mar May tun Jul Aug Sep 1 BE En Duvall Avenue Ne 260 days Mon 9/20/21 Fri 9/16/22 2 miP 4 Mobilization 4 days Mon 9/20/21 Thu 9/23/21 0 3 EP 4 Class A Signs 2 days Mon 9/20/21 Tue 9/21/21 4 A Workzone C Construction 60 days Mon 9/20/21 Fri 12/10/21 3 5 A Traffic control 60 days Mon 9/20/21 Fri 12/10/21 6 * PCMS 60 days Mon 9/20/21 Fri 12/10/21 ____7 0 Survey 2 days Tue 9/21/21 Wed 9/22/21 8 A erosion control 3 days Wed 9/22/21 Fri 9/24/21 III 9 A sawcutting 2 days Thu 9/23/21 Fri 9/24/21 10 7r clear and grub 4 days Mon 9/27/21 Thu 9/30/21 9 11 J demo 2 days Fri 10/1/21 Mon 10/4/21 10 iiteMie1111 12 ,0 install new hydrants 2 days Tue 10/5/21 Wed 10/6/21 11 13 ,r Removal of Structures and obstructions 5 days Thu 10/7/21 Wed 10/13/21 12 14 fr storm system 10 days Thu 10/14/21 Wed 10/27/21 13 15 7r Underground utilities 20 days Thu 10/28/21 Wed 11/24/21 14 16 A illumination 20 days Thu 10/28/21 Wed 11/24/21 III 17 fr Roadway Excavation and subgrade 5 days Thu 11/4/21 Wed 11/10/21 18 1 CSTC 4 days Thu 11/11/21 Tue 11/16/21 17 19 A Curb and Gutter 1 day Wed 11/17/21 Wed 11/17/21 18 I 20 * Sidewalk, Ramps, DW and High walls 13 days Thu 11/18/21 Mon 12/6/21 19 21 1 Planning weather pending 2 days Tue 12/7/21 Wed 12/8/21 20 l 22 hma weather pending 2 days Thu 12/9/21 Fri 12/10/21 21 23 0 Workzone A Construction 20 days Fri 11/12/21 Thu 12/9/21 —_ 24 A Traffic control 20 days Fri 11/12/21 Thu 12/9/21 25 AnPCMS 20 days Fri 11/12/21 Thu 12/9/21 I MI 26 fr Survey 1 day Fri 11/12/21 Fri 11/12/21 1 1 27 0 Erosion control 1 day Fri 11/12/21 Fri 11/12/21 28 * Sawcutting 1 day Fri 11/12/21 Fri 11/12/21 29 * Clear and grub 1 day Mon 11/15/21 Mon 11/15/21 28 , 30 A Demo 1 day Tue 11/16/21 Tue 11/16/21 29 31 * Storm system 1 day Wed 11/17/21 Wed 11/17/21 30 1 32 fr Roadway Excavation and subgrade 2 days Thu 11/18/21 Fri 11/19/21 31 1 33 A CSTC 2 days Mon 11/22/21 Tue 11/23/21 32 34 A Curb and Gutter 1 day Wed 11/17/21 Wed 11/17/21 18 h 35 Sidewalk 1 day Thu 11/18/21 Thu 11/18/21 34 36 0 Planning weather pending 1 day Tue 12/7/21 Tue 12/7/21 20 1 37 Hma weather pending 1 day Thu 12/9/21 Thu 12/9/21 21 h, 38 0 Workzone B and E Construction 106 days Mon 12/13/21 Mon 5/9/22 37 7 Task .-- -_— _.-.. Project Summary C C Manual Task I I Start-only C Deadline 4- Project: Duvall ave. Project Sch Split Inactive Task Duration-only Finish-only ] Progress Date: Fri 7/9/21 Milestone ♦ Inactive Milestone Manual Summary Rollup External Tasks -' Manual Progress Summary Inactive Summary Manual Summary External Milestone Page 1 ID p (Task Task Name ,Duration Start Finish Predecessors Qtr4,2021 Qtr 1,2022 Qtr 2,2022 Qtr 3,2022 IV (Mode , Seo Oct Nov Dec Jan Feb Mar Apr I May i; Jun ; Jul . Aug Sep 39 ]r Traffic control 105 days Mon 12/13/21 Fri 5/6/22 40 A- PCMS 105 days Mon 12/13/21 Fri 5/6/22 41 ,' Survey 2 days Tue 12/14/21 Wed 12/15/21 42 A' Sawcutting 1 day Wed 12/15/21 Wed 12/15/21 1 43 A` Erosion control 3 days Wed 12/15/21 Fri 12/17/21 44 A' Clear and grub 2 days Mon 12/20/21 Tue 12/21/21 43 45 Jr Pulverize and remove asphalt 2 days Wed 12/22/21 Thu 12/23/21 44 46 A- Removal of Structures and obstructions 7 days Fri 12/24/21 Mon 1/3/22 45 47 A' Demo 2 days Tue 1/4/22 Wed 1/5/22 46 48 A' Cdf Fill Storm 2 days Thu 1/6/22 Fri 1/7/22 47 49 A' Storm system 25 days Mon 1/10/22 Fri 2/11/22 48 i \leeiMMIUMI- 50 7r Water System 15 days Mon 2/14/22 Fri 3/4/22 49 1 51 A' Underground utilities 40 days Mon 3/7/22 Fri 4/29/22 50 52 A illumination 40 days Mon 3/7/22 Fri 4/29/22 50 53 A' Electrical system Complete 57 days Mon 2/14/22 Tue 5/3/22 49 54 A Roadway Excavation and subgrade 20 days Mon 3/7/22 Fri 4/1/22 50 55 A- Place Recycled Asphalt 5 days Mon 4/4/22 Fri 4/8/22 54 56 A CSTC 3 days Mon 4/11/22 Wed 4/13/22 55 57 A Curb and Gutter 2 days Thu 4/14/22 Fri 4/15/22 56 58 ' Sidewalk, Ramps, DW and High walls 8 days Mon 4/18/22 Wed 4/27/22 57 59 ,' CSTC 3 days Thu 4/28/22 Mon 5/2/22 58 60 A' Hma 5 days Tue 5/3/22 Mon 5/9/22 59 61 A Workzone D Construction 56 days Tue 5/10/22 Tue 7/26/22 60 P' 62 A' Traffic Control 55 days Tue 5/10/22 Mon 7/25/22 INIIIINIMIIIIMIIIMI 63 Jr PCMS 55 days Tue 5/10/22 Mon 7/25/22 64 A' Survey 2 days Wed 5/11/22 Thu 5/12/22 65 A' Sawcutting 1 day Thu 5/12/22 Thu 5/12/22 1 66 A Erosion control 2 days Thu 5/12/22 Fri 5/13/22iiiiiiilL 67 A Clear and grub 2 days Mon 5/16/22 Tue 5/17/22 66 68 )r Pulverize and remove asphalt 2 days Wed 5/18/22 Thu 5/19/22 67 i 69 A' Removal of Structures and obstructions 2 days Fri 5/20/22 Mon 5/23/22 68 70 ,' Storm system 5 days Tue 5/24/22 Mon 5/30/22 69 71 ' Water System 1 day Tue 5/31/22 Tue 5/31/22 70 72 A' Underground utilities 15 days Wed 6/1/22 Tue 6/21/22 71 73 ,' illumination 15 days Wed 6/1/22 Tue 6/21/22 71 74 A' Roadway Excavation and subgrade 20 days Wed 6/1/22 Tue 6/28/22 71tit-, 75 A' Place Recycled Asphalt 5 days Wed 6/29/22 Tue 7/5/22 74 1/ 76 A' CSTC 3 days Wed 7/6/22 Fri 7/8/22 75 Ir. j Task 1111111MINIMIl Project Summary C I; Manual Task 1 1 Start-only E Deadline ♦ Project: Duvall ave. Project Sch Split Inactive Task Duration-only Finish-only J Progress Date: Fri 7/9/21 Milestone • Inactive Milestone Manual Summary Rollup External Tasks Manual Progress Summary Inactive Summary Manual Summary External Milestone C Page 2 ID Task Task Name Duration Start Finish Predecessors Qtr4,2021 Qtr 1,2022 'Qtr 2,2022 Qtr 3,2022 0 'Mode Curb and Gutter 1 day Mon 7/11/22 Mon 7/11/22 76 Oct O I Nov I Dec Jan I Feb I Mar � Apr I May I Jun T Jul I Aug I Sep 77 78 ,r Sidewalk 3 days Tue 7/12/22 Thu 7/14/22 77 t 79 yr CSTC 3 days Fri 7/15/22 Tue 7/19/22 78 ■11 i 80 ,r hma weather pending 5 days Wed 7/20/22 Tue 7/26/22 79 i. 81 ,r Workzone F Construction 30 days Wed 7/27/22 Tue 9/6/22 80 ilil 82 ,r Traffic Control 30 days Wed 7/27/22 Tue 9/6/22 83 ,r PCMS 30 days Wed 7/27/22 Tue 9/6/22 84 ,r Survey 1 day Thu 7/28/22 Thu 7/28/22 1� 85 ,r Sawcutting 1 day Fri 7/29/22 Fri 7/29/22 84 •L 86 fr Roadway Excavation and subgrade 3 days Mon 8/1/22 Wed 8/3/22 85 lit... 87 ,r Extruded Curb 2 days Thu 8/4/22 Fri 8/5/22 86 88 ,r Irrigation 20 days Mon 8/8/22 Fri 9/2/22 87 89 ,r Topsoil 20 days Mon 8/8/22 Fri 9/2/22 90 ,r Landscaping 20 days Mon 8/8/22 Fri 9/2/22 =INN, 91 ,a+r Hydroseeding 2 days Mon 9/5/22 Tue 9/6/22 90 I1 92 ,r Pavement Markings and Signs 7 days Wed 9/7/22 Thu 9/15/22 91 Ili 93 Jr Traffic control 7 days Wed 9/7/22 Thu 9/15/22 94 ,r PCMS 7 days Wed 9/7/22 Thu 9/15/22 95 2r Permanent Signing 7 days Wed 9/7/22 Thu 9/15/22 Itil 96 ar Remove Markings 7 days Wed 9/7/22 Thu 9/15/22 I,. 97 ,r Paint Lines 7 days Wed 9/7/22 Thu 9/15/22 NO 98 yr Plastic markings 7 days Wed 9/7/22 Thu 9/15/22 99 ,r Substantial Completion 1 day Fri 9/16/22 Fri 9/16/22 98 illr Task 11.111111 Project Summary I' Manual Task I I Start-only C Deadline Project: Duvall ave. Project Sch Split Inactive Task Duration-only Finish-only ] Progress Date: Fri 7/9/21 Milestone ♦ Inactive Milestone Manual Summary Rollup i=mimilm External Tasks Manual Progress Summary Inactive Summary Manual Summary External Milestone C Page 3