Fire Station 15
1404 N 30th St, Renton, WA
Technical Information Report
September 22, 2017
Prepared by:
LPD Engineering, PLLC
1932 1st Avenue
Suite 201
Seattle, WA 98101
Contact: Laurie J. Pfarr, P.E.
(206) 725-1211
Prepared for:
Schreiber Starling Whitehead
Architects
901 5th Avenue #3100
Seattle, WA 98164
Contact: Keith Schreiber, AIA
(206) 682-8300
Fire Station 15
Technical Information Report
September 22, 2017
FIRE STATION 15
TABLE OF CONTENTS
Section 1 – Project Overview ...................................................................................................................................... 1
Section 2 – Conditions and Requirements Summary ............................................................................................ 2
Section 3 – Offsite Analysis .......................................................................................................................................... 4
Section 4 – Flow Control and Water Quality Facility Analysis and Design .................................................... 6
Section 5 – Conveyance Systems Analysis and Design ......................................................................................... 9
Section 6 – Special Reports and Studies ..................................................................................................................10
Section 7 – Other Permits ..........................................................................................................................................10
Section 8 – CSWPPP Analysis and Design .............................................................................................................10
Section 9 – Bond Quantities, Facility Summaries, and Declaration of Covenant ........................................11
Section 10 – Operations and Maintenance Manual ..............................................................................................11
FIGURES
Figure 1: TIR Worksheet
Figure 2: Vicinity Map
Figure 3: Soils Map
Figure 4: Existing Conditions
Figure 5: Proposed Conditions
Figure 6: Downstream Drainage Course
APPENDICES
Appendix A – Design Drawings
Appendix B - Design Calculations
Appendix C - Stormwater Pollution Prevention and Spill Plan Report
Appendix D – Operations and Maintenance Manual
Page 1
Fire Station 15
Technical Information Report
September 22, 2017
FIRE STATION 15
PRELIMINARY TECHNICAL INFORMATION REPORT
SEPTEMBER 22, 2017
SECTION 1 – PROJECT OVERVIEW
This Technical Information Report (TIR) is for the construction the new fire station 15 for the City of
Renton. Refer to Figure 1: TIR Worksheet for basic site information. The project is west of I-405,
located at 1404 N 30th Street on parcel #3342103245. The site is in Section 32, Township 24, Range 5,
Willamette Meridian. Refer to Figure 2- Vicinity Map.
The City of Renton has adopted the 2016 King County Surface Water Design Manual (KCSWDM)
with the City’s 2016 Surface Water Design Manual Amendment (RSWDMA). According to Figure
1.1.2.A of the RSWDMA, Flow Chart for Determining Type of Drainage Review Required, the project
is subject to a “Full Drainage Review” because the project results in greater than 2,000 SF of new plus
replaced impervious surface, and it is not a large project or single family residential project. Per the
“Full Drainage Review” requirements in Table 1.1.2.A, the TIR addresses Core Requirements #1-9
and Special Requirements #1-5 of the 2016 RSWDMA.
The current property is proposed to be subdivided into two lots. The northern lot will be for the
development of a new water storage reservoir serving the 320-pressure zone. The project in the
northern lot will be on a similar timeline for design and construction and will be permitted separately.
The southern lot will be the extent of the proposed project improvements addressed in this report.
Existing Site
The total existing parcel area is 47,538.4 SF (1.09 acres). The project limit of work within the
southernmost subdivided lot totaling 31,173 SF (0.72 acres). The site and bounded by two gas stations
to the east and west, single-family residences to the north, and N 30th St to the south. The property is
located in the Kennydale neighborhood on a vacant, city-owned parcel. See Figure 4 – Existing
Conditions.
Topographically the site generally slopes downward from northeast to southwest, a vertical elevation
change of 12.5 feet. According to the USDA Natural Resources Conservation Service, the site soils in
the project area are mapped as Indianola loamy sand (InC) with 5 to 15 percent slopes. Refer to Figure
3 – Soils Map. HWA GeoSciences, Inc. prepared a preliminary study for the northern portion of the
parcel dated November 10, 2016. Field investigation included three boring samples. In general, the
borings indicated one to two feet of topsoil underlain with recessional outwash to approximately 5-feet
in depth. Underneath the recessional outwash is medium dense silty sand. In the geotechnical
engineer’s preliminary study, it was determined that the soils underneath the first 5-feet form finished
grade may be suitable for infiltration. However, none of the boring locations were within the proposed
on-site stormwater management facilities on the project site and HWA will need to conduct a PIT test
to determine the infiltration rate. In this preliminary TIR drainage report, LPD has assumed the existing
soils are no conducive for infiltration until further investigation has been conducted by the geotechnical
engineer.
A survey of the site has been prepared by Duane Hurtmant & Associates, Inc. on October 21st, 2016.
According to the survey, there are no existing drainage facilities on the property. It appears the
Page 2
Fire Station 15
Technical Information Report
September 22, 2017
majority of the stormwater runoff from the project site sheet flows southwest towards an existing inlet
within in N 30th St. There is a 12-inch public storm main flowing west within the north portion of N
30th Street. The site is located in the East Lake Washington drainage basin.
According to the City of Renton GIS maps, the site is located within a Wellhead Protection Area Zone
2. Along the eastern property line of the site, a relatively small area has been designated as a regulated
slope (>15% and ≤ 25%). There do not appear to be any other critical areas on the site.
Proposed Site Improvements
Proposed improvements include a new fire station with 11 standard parking stalls on-site and one ADA
stall with ADA accessible walkways to the front entrance. An asphalt drive access will be constructed
along the west side of the property to be shared with the northern subdivided water reservoir lot. A
second drive on the eastern portion of the property that will be for fire truck exit only out of the 2-bay
garage. Runoff from the pollution generating surfaces will be treated via a permeable pavement facility
as well as StormFilter cartridges. On-site stormwater management will be implemented via a
bioretention pond and the permeable pavement facility. The majority of the project site run-off will be
routed to a shallow detention facility before discharging from the site. Refer to Section 4 – Flow
Control and Water Quality Analysis and Design for further information on the storm drainage design.
Also refer to Figure 5 – Proposed Conditions.
Improvements will be made to the frontage along N 30th Street to accommodate the two proposed drive
entrances per City of Renton standards. An 11-foot dedication along the site frontage has been
requested by the City to allow for future right-of-way (ROW) expansion to N 30th Street.
SECTION 2 – CONDITIONS AND REQUIREMENTS SUMMARY
This section addresses the Core Requirements (Section 1.2) and Special Requirements (Section 1.3)
requirements set forth by 2016 RSWDMA.
Core Requirement 1 - Discharge at the Natural Location (1.2.1)
The proposed conditions will maintain the natural drainage patterns within its basin. All stormwater
runoff will be routed to the existing catch basin inlet within N 30th Street discharging to the 12-inch
public storm main.
Core Requirement 2 - Off-site Analysis (1.2.2)
An offsite analysis is required for this project and can be referred to in Section 3 below. A field
investigation and assessment will be conducted for the final draft of this report.
Core Requirement 3 – Flow Control (1.2.3)
Per the City of Renton Flow Control Application Map, Reference 15-A in the RSWDMA., the project
site is located within a Peak Rate Flow Control Standard (Existing Site Conditions) area. Therefore,
flow control facilities must be provided to match the existing site’s peak discharge rates for the 2- year,
10-year, and 100- year return periods at the point of discharge from the site. Per the RSWDMA, flow
control facilities must mitigate the runoff from the target surfaces which include new impervious
surfaces and new pervious surfaces not fully dispersed. For further information regarding the flow
control design, refer to Section 4 of this report.
Page 3
Fire Station 15
Technical Information Report
September 22, 2017
Core Requirement 4 - Conveyance System (1.2.4)
A preliminary conveyance design analysis for the project has been completed and is included within
Section 5 of this Report.
Core Requirement 5 - Erosion and Sedimentation Control (1.2.5)
A Temporary Erosion and Sediment Control (TESC) plan for the project is included with this
submittal. The TESC plan will be considered the minimum for anticipated site conditions. The
Contractor will be responsible for implementing all TESC measures and upgrading as necessary. The
TESC facilities will be in place prior to clearing, grubbing, or construction of proposed improvements.
Core Requirement 6 - Maintenance and Operations (1.2.6)
The maintenance and operations guidelines for all of the proposed stormwater facilities will be
included with the final drainage report.
Core Requirement 7 – Financial Guarantees and Liability (1.2.7)
Financial guarantees and liability are not anticipated to be required since the Owner is a public agency.
Core Requirement 8 – Water Quality (1.2.8)
The project proposes more than 5,000 SF of pollutant generating impervious surface (PGIS) and
therefore requires the project to provide water quality treatment. Basic WQ Treatment of the pollution
generating impervious surfaces will be provided with a proprietary cartridge treatment system and
permeable pavement surfaces. For further information regarding the water quality design requirements,
refer to Section 4 of this report.
Core Requirement 9 – On-site BMP’s (1.2.9)
The project is required to provide onsite flow control best management practices (BMP’s) to mitigate
the impacts of stormwater runoff generated by the new plus replaced impervious surface to the
maximum extent feasible. Per section 1.2.9.2 of the 2016 RSWDMA, the project is larger than 22,000
SF; therefore, the project will apply the large lot BMP requirements. For further information regarding
the on-site BMP’s, refer to Section 4 of this report.
Special Requirement 1 – Other Adopted Area-Specific Requirements (1.3.1)
• Master Drainage Plans (MDPs) – Project is not within an area covered by an approved
Master Drainage Plan.
• Basin Plans (BPs) – The project is located in the East Lake Washington drainage basin.
The Renton Municipal Code does not provide any more stringent flow control or water
quality requirements than that of the current code.
• Salmon Conservation Plans (SCPs) – The applicable SCP is the Water Resource
Inventory Area (WRIA) 8 for the Lake Washington/Cedar/Sammamish Watershed.
Within the large watershed, our project is in the Lake Washington. The SCP does not
appear to have stormwater management requirements more stringent than Renton
Municipal Code.
• Stormwater Compliance Plans (SWCPs) – The project is not within an area governed by a
SWCP.
Page 4
Fire Station 15
Technical Information Report
September 22, 2017
• Flood Hazard Reduction Plans (FHRPs) –The project site is not within a designated flood
hazard area.
• Shared Facility Drainage Plan (SFDPs) – The proposed project is not within an area with
a SFDP.
Special Requirement 2 – Flood Hazard Area Delineation (1.3.2)
The project site is not located within or adjacent to a designated flood hazard area
Special Requirement 3 – Flood Protection Facilities (1.3.3)
The project does not rely on an existing flood protection facility, nor will a new flood protection
facility be constructed; therefore, this requirement is not applicable.
Special Requirement 4 – Source Control (1.3.4)
In the proposed conditions, there will be no applicable activities matching those listed within the 2016
King County Stormwater Pollution Prevention Manual (KCSPPM) that will require the use of source
control measures.
Special Requirement 5 – Oil Control (1.3.5)
The project will not have high-use site characteristics, nor is it an existing high-use site.
Special Requirement 6 – Aquifer Protection Area (1.3.6)
Per the city of Renton Aquifer Protection Area (APA) map, the project site is within Zone 2, which
may require some open flow control and water quality treatment facilities as well as open conveyance
systems to be constructed with a liner. The proposed does not include these facilities.
SECTION 3 – OFFSITE ANALYSIS
The following is the Level 1 downstream analysis for the proposed project. Refer to Figure 6 -
Downstream Drainage Map. The following resources have been reviewed for the project area:
Basin Summary
King County’s Watershed Map locates the project site in the East Lake Washington – Renton
drainage basin.
Floodway Map
A FEMA flood insurance rate map (53033C0664F) is included in Appendix B, illustrating the
FEMA flood zone designations for the site. The site is located within zone X, which are areas
outside the 0.2% annual chance floodplain.
Sensitive Areas
The sensitive areas within one-mile upstream and downstream of the subject property were
examined using the King County iMAP application. According to iMAP, the following are the
sensitive area designations for the project site and within one mile downstream of the site:
Page 5
Fire Station 15
Technical Information Report
September 22, 2017
SAO Erosion Hazard – The project site is not located within an erosion hazard area. There
is an erosion hazard area identified on iMAP approximately 900 LF east of the site which is
not downstream of the site.
SAO Seismic Hazard – There are no seismic hazard areas on the site on within one mile of
the site.
SAO Landslide Hazard – There are no landslide hazard areas on the site on within one mile
of the site.
SAO Coal Mine –There are no known coal mines on the site or within one mile of the site.
SAO Stream – There are no sensitive streams located within the project site or within a mile
downstream of the project site.
SAO Wetland – There are no wetlands located within the project site or within one mile
downstream of the project site.
Groundwater Contamination – The project area is not located within an area designated as
being susceptible to groundwater contamination.
Sole Source Aquifer – The project area is not within a sole source aquifer area.
Channel Migration Hazard – There are no channel migration hazards for the site.
Topographic Map
The Topographic information for the project area is shown on the Design Drawings in
Appendix A of this report.
Drainage Complaints
According to King County’s iMap program, there have been no drainage complaints within
the last 10 years within the project site, upstream area, or downstream area.
King County Soils Survey
As stated previously, according to the USDA Natural Resources Conservation Service, the site
soils in the area of proposed work are mapped as Indianola loamy sand (InC). Refer to Figure
3: Soils Map.
Migrating River Studies
According to King County’s iMAP program, the project site is not located within a channel
migration hazard.
303d List of Polluted Waters
According to Washington State Department of Ecology’s Water Quality Assessment map, the
project site does not contain any polluted water. The southeast area of Lake Washington, the
immediate receiving water for the downstream system, is designated as a Category 5-303d
water for bacteria (Listing ID 12193). There are no Water Quality Improvement Projects
identified as part of the 303d listing.
Water Quality Problems
According to King County’s iMAP program, the project site is not within a designated King
County water quality problem area.
Page 6
Fire Station 15
Technical Information Report
September 22, 2017
Field Inspection and Problem Descriptions
A field inspection will be conducted for the final draft of the TIR drainage report.
Drainage System Description
As stated previously, there are no existing drainage facilities on the property. It appears the majority of
the stormwater runoff from the project site sheet flows southwest towards existing inlet within in N 30th
Street. Refer to Figure 6 – Downstream Drainage Course for the continuation of the downstream flow
path. The remaining downstream course is as follows:
1. The flow continues west within the 12-inch system along N 30th Street for approximately
1,000 feet.
2. The system continues west through 18-inch line in N 30th Street, between Park Ave N and
Burnett Ave N, about 300 feet before crossing the ¼-mile point downstream from the site.
3. Stormwater discharges into existing catch basin located at the intersection of N 30th Street and
Burnett Ave N. Flow continues north through 18-inch pipe to an existing catch basin near the
intersection of Burnett Ave N and N 33rd Street.
4. A 24-inch storm line exits the existing catch basin and continues north for about 530 feet to a
catch basin at the intersection of Burnett Ave N and N 34th Street.
5. Flow continues west before discharging to existing catch basin at the intersection of Lake
Washington Blvd N and N 34th Street.
6. A 24-inch storm line exits the catch basin and continues southwest for about 120 feet.
7. The system continues west through 24-inch line, eventually outfalling to Lake Washington.
SECTION 4 – FLOW CONTROL AND WATER QUALITY FACILITY ANALYSIS
AND DESIGN
Existing Site Hydrology
Please refer to Section 1- Project Overview and Section 3- Off-site Analysis of this report for a
description of the existing hydrology.
Proposed Site Hydrology
Please refer to Section 1- Project Overview and the Flow Control System section below in this report
for a description of the proposed hydrology.
Performance Standards
Please refer to Section 2- Conditions and Requirements Summary, Section 5 – Conveyance Systems
Analysis, and the Flow Control System, Water Quality, and On-site BMP sections of this report for a
brief description of the required standards applicable to this report.
Flow Control System
As stated in Section 3 of this report, the project site is located within a Peak Rate Flow Control
Standard (Existing Site Conditions) area. Therefore, flow control facilities must be provided to match
the existing site conditions peak discharge rates for the 2- year, 10-year, and 100- year return periods at
the point of discharge.
Based on the RSWDMA definition, the ‘existing site conditions’ are those that existed at the site prior
to May 1979 as determined from aerial photographs, unless a drainage plan for land cover changes has
Page 7
Fire Station 15
Technical Information Report
September 22, 2017
been approved by the city since May 1979 as a part of a city permit or approval. Based on the city’s
records, there have been no drainage plans for permitted land cover changes by the City since 1979.
Based on available historical aerials from King County’s map vault, a 1954 and 1965 map show two
residential building with a gravel driveway and grassed-landscape on-site. Based on Renton’s record
documents, the previous owners sold the deed of the property to the City in 2001. In the year 2005 the
house was demolished according to Google aerial maps. Currently, the site is a grassed vacant lot with
a few large trees. For the modeled pre-developed conditions, instead of calculating the amount of
existing impervious area constructed before 1979 based on aerial photos, the redeveloped area will be
considered as “grass” for conservative flow calculations. Please refer to Figure 4 – Existing Conditions
for the referenced aerial images has been included in Appendix B.
For the stormwater threshold analysis, MGSFlood was used to model the pre-developed and developed
conditions within the project site area. A summary of areas for the site can be found in Appendix B of
this report and are also referred in Figure 5 – Proposed Conditions. The project proposes approximately
20,835 SF of new plus replaced impervious surface. The majority of the site which includes the asphalt
access drive, walkways, and roof will be modeled to route directly to the detention facility and are
considered to be 100% impervious surfaces. For the purposes of this preliminary report, the permeable
pavement facility within the parking lot will be under-drained and considered 100% impervious until
further infiltrative testing has been conducted. The surfaces considered pollution-generating will be
treated by a water quality facility preceding the detention system. For more information, see the Water
Quality section below in this report.
A portion of the roof will be routed to a bioretention cell west of the proposed fire station building,
which will be credited as an on-site BMP for stormwater mitigation. The target surfaces within the 11-
foot dedication area associated with the ROW cannot physically be routed to the detention facility and
will be modeled as target surfaces bypassing the detention facility in the developed conditions. The
bypass areas on site will sheet flow the northern gutter line along N 30th Street into the existing inlet
where the detention facility will also connect to before discharging into the existing 12-inch public
main. The MGSFlood output for the peak flow rates for the developed project area are included in
Table 1 below, and in Appendix B of this report.
Table 1 – Net Peak Flow Rates for Discharge from Project Work Area
Peak Runoff Rates for Project Work Area
Storm Event Existing Conditions Proposed Conditions Delta
2-yr 0.0671 cfs 0.0655 cfs 0.0016 cfs
10-yr 0.169 cfs 0.187 cfs 0.018 cfs
100-yr 0.365 cfs 0.302 cfs 0.063 cfs
The required storage volume of detention facility totals 1,100 CF of live storage. The detention facility
is a Brentwood StormTank Module system that will consist of approximately 200 polypropylene
modules with a total dimension of 42-feet long by 21-feet wide and 2-feet deep. A 12-inch layer of
angular stone backfill will cover all sides of the facility and separated from the subgrade by geotextile
fabric. The overall dimensions of the facility will be 44-feet long by 23-feet wide and 3-feet deep. The
facility will outflow to a flow control structure located west of the facility to restrict the flows entering
the public storm system.
Page 8
Fire Station 15
Technical Information Report
September 22, 2017
On-site BMPs
Flow Control BMPs have been applied in accordance with Section 1.2.9 of the RSWDMA. The project
site proposed more than 2,000 SF of new plus replaced impervious surfaces which will require an
evaluation of BMP feasibility for all target surfaces. The project site is more than 22,000 SF and will
have an impervious coverage greater than 65% on the buildable portion of the site. Therefore, the site
is categorized under the Large Lot BMP Requirements and on-site BMPs will be applied to at least
20% of the target impervious surfaces. Based upon the site size, the total area required to be mitigated
by BMP facilities is 4,170 SF. Refer to Figure 5 – Proposed Conditions and Area Summary
spreadsheet for the calculated impervious coverage and area calculations for BMP implementation. Per
the following summary, the total area mitigated is currently greater than what is required due to the
potential to infiltrate. If infiltration is not feasible, the permeable pavement surface may be eliminated
and the water quality aspect of the facility replaced with an additional StormFilter.
Full dispersion is not feasible to be used as BMP due to the limited downstream vegetative flow path.
The use of infiltration facilities has not yet been determined, the final drainage report will reflect the
results of site infiltration testing that will conducted by the geotechnical engineer. Per Requirement #3
of Section 1.2.9.2.2 of the RSWDMA, the following is a list of BMPs that have been evaluated and
applied to the proposed target surfaces:
• Bioretention: Approximately 4,975 SF of roof will be directed to a bioretention cell west of
the proposed building. Per the King County Rainfall Regions map, the project site falls within
the rainfall region Seatac 1.0. In outwash soils, the bioretention volume is based on 0.1 inches
of equivalent storage depth by the square footage of the target surface area serve. Therefore,
the required storage volume of the bioretention pond is 42 CF of required storage. The project
proposes a 6-inch ponding bioretention cell with a total designed volume of 122 CF. The
bioretention area consists of 18-inches of bioretention soil mix underlain by 18-inches of drain
rock over the native subgrade. A 6-inch slotted underdrain will extend the entire length of the
bottom of the bioretention area.
• Permeable Pavement: Permeable asphalt pavement has been proposed for the parking area
located north of the proposed fire station. The permeable pavement facility will include a 6-
inch layer of sand filter media to address water quality treatment requirements referred to in
the Water Quality System section of this report. The total permeable pavement area proposed
for the project is approximately 4,180 SF.
Water Quality System
The project proposes approximately 8,965 SF of pollution-generating impervious surfaces and
therefore requires the project to provide water quality treatment for the proposed access drive and
parking lot. The driveway on the southeast side of the proposed building and the drive apron on the
north side of the building are restricted to fire truck access only are not considered pollution-generating
surfaces.
Page 9
Fire Station 15
Technical Information Report
September 22, 2017
Stormwater runoff from the asphalt access drive will be treated by a Stormfilter catch basin system. A
Stormfilter analysis will be conducted by Contech Stormwater Solutions for the final drainage report,
using the project’s flow rates calculated in MGSFlood stormwater modeling. The StormFilter structure
will have ZPG media (zeolite, perlite, granular activated carbon). Per Section 6.5.5.1 of the KCSWDM
manual, the Stormfilter sizing is based on water quality design flow and a mass loading method. The
water quality design flow is based on 35% of the developed two-year peak flow rate, modeled with 15-
minute time steps when the facility is preceding the detention. The resulting size of StormFilter
Structure is estimated to be (2) 18-inch cartridge in a catch basin structure. The MGSFlood output for
the water quality analysis and the calculations by Contech for the StormFilter will be provided for the
final draft of the drainage report.
The parking lot will be constructed with a heavy-duty concrete permeable pavement designed for fire
truck loading. Stormwater runoff will percolate through the permeable surface layer into the free-
draining base and storage reservoir. These aggregate layers will be underlain with 6-inch of sand filter
med to be treated for water quality.
SECTION 5 – CONVEYANCE SYSTEMS ANALYSIS AND DESIGN
The proposed conveyance system will be designed to convey the 25-year peak flow rate of the
developed site. The system is allowed to overtop during the 100-year peak flow provided that it does
not create or aggravate a severe flooding problem.
The entire project site was considered 100% impervious for conservative calculations. A conveyance
analysis was performed for one pipe run. The 8-inch storm line is the ultimate discharge point,
receiving flow from the entire site at a minimum 0.5% slope. The tributary flows were calculated using
MGS Flood with the 158-year, 5-minute time series and were compared to the full flow capacity of the
conveyance pipe calculated by the Manning’s equation. The pipe analyzed was determined to have
adequate capacity to convey the 25-year peak flow for the tributary area. Attached is the complete
output from MGS Flood and Conveyance Analysis Spreadsheet.
Page 10
Fire Station 15
Technical Information Report
September 22, 2017
SECTION 6 – SPECIAL REPORTS AND STUDIES
There are no additional special reports or studies associated with this project. The final geotechnical
report will be provided under separate cover.
SECTION 7 – OTHER PERMITS
An NPDES permit from the Washington State Department of Ecology will not be required for the
project disturbs less than one (1) acre of land. There are no additional permits required from other
agencies for this project.
SECTION 8 – CSWPPP ANALYSIS AND DESIGN
An Erosion Sediment Control (ESC) plan has been prepared for the project and is included within the
Design Drawings included in Appendix A of this report. The construction storm water pollution
prevention plan (CSWPPP) consists of the site preparation plan and a Stormwater Pollution Prevention
and Spill (SWPPS) plan (to be provided in the final report). The Contractor will be responsible for
implementing all TESC measures and upgrading as necessary. The TESC facilities will be in place
prior to any clearing, grubbing or construction. Anticipated minimum ESC and stormwater pollution
prevention measures are as follows:
• Mark Clearing Limits/Minimize Clearing – Clearing limits will be defined by erosion control
components and areas of proposed grading. Clearing will be minimized to the maximum extent
practicable. No existing trees will be removed.
• Minimized Sediment Tracked Offsite – A stabilized construction entrance for vehicle access to
minimize the tracking of public roads. The temporary construction access is shown on the ESC
plan. If necessary, sediment shall be removed from roads by shoveling or pickup sweeping and
shall be transported to a controlled sediment disposal area.
• Install Sediment Controls – Runoff from disturbed areas must pass through a sediment control
measures to prevent the transport of sediment downstream until the disturbed area is fully
stabilized. Sediment will be controlled using perimeter siltation control which includes silt fencing.
In addition catch basin inlet protection will be installed on any existing catch basin within and
surrounding the project area.
• Stabilize Exposed Soils –It is possible that some of the earthwork and grading may occur in wet
weather conditions. The site must be stabilized and no soils will be allowed to remain unstabilized
for more than two days between October 1 and April 30. From May 1 through September 30,
cover measures must be installed to protect disturbed areas that will remain unworked for seven
days or more. By October 8, seed all areas that will remain unworked from October 1 through
April 30. Mulch all seeded areas. Exposed slopes will be protected by DOE-approved coverage
measures, such as mulching, nets and blankets, plastic covering, seeding, and sodding per Section
C.3 of the KCSWDM will be used to stabilize onsite soils during construction. See Erosion and
Sedimentation Control Notes on the plans in Appendix A
• Control Pollutants – Sediment is the only pollutant expected from the proposed project. Limiting
the duration of disturbance of the site soils provides the first level of protection for pollution
control, and perimeter measures on the edges of the disturbed areas will mitigate the remaining
pollutants.
Page 11
Fire Station 15
Technical Information Report
September 22, 2017
• Control De-watering – De-watering is not expected to be required. If perched groundwater is
encountered and de-watering is necessary, a temporary pump will be used to remove water from
the trenches. Pumped water will be routed to perimeter undisturbed areas or other approved
location prior to discharge from the project site.
• Maintain BMPs – The BMPs will be maintained regularly in accordance with the Erosion and
Sedimentation Control Plan and Notes.
• Manage the Project – The Contractor will maintain a daily presence on the site and will assign a
contact person for erosion and sedimentation control issues.
SECTION 9 – BOND QUANTITIES, FACILITY SUMMARIES, AND DECLARATION
OF COVENANT
A Bond Quantities Worksheet is not expected to be required since the owner is the City of Renton,
which is a public agency; no bonding is required. A Facility Summary and Declaration of Covenant
will be provided in the final drainage report submittal.
SECTION 10 – OPERATIONS AND MAINTENANCE MANUAL
The operations and maintenance guidelines will be provided in the final drainage report submittal.
Fire Station 15
Technical Information Report
September 22, 2017
FIGURES
Figure 1: TIR Worksheet
Figure 2: Vicinity Map
Figure 3: Soils Map
Figure 4: Existing Conditions
Figure 5: Proposed Conditions
Figure 6: Downstream Drainage Course
engineering pllc
1932 1st Ave,
Suite 201,
Seattle, WA 98101
p. 206.725.1211
f. 206.973.5344
www.lpdengineering.com
FIRE STATION 15
2VICINITY MAP
engineering pllc
1932 1st Ave,
Suite 201,
Seattle, WA 981041
p. 206.725.1211
f. 206.973.5344
www.lpdengineering.com
FIRE STATION 15
3SOILS MAP
MAP UNIT SYMBOL
KING COUNTY AREA, WASHINGTON (WA633)
InC Indianola Loamy Sand, 5% to 15% slopes
MAP UNIT NAME
PROPERTY AREA
1932 1st Ave,Suite 201,Seattle, WA 98101p. 206.725.1211f. 206.973.5344www.lpdengineering.comengineering pllc2017 LPD Engineering PLLC©FIRE STATION 154EXISTING CONDITIONS
1932 1st Ave,Suite 201,Seattle, WA 98101p. 206.725.1211f. 206.973.5344www.lpdengineering.comengineering pllc2017 LPD Engineering PLLC©FIRE STATION 155PROPOSED CONDITIONS
engineering pllc2017 LPD Engineering PLLC©FIRE STATION 1561932 1st Ave,Suite 201,Seattle, WA 98101p. 206.725.1211f. 206.973.5344www.lpdengineering.comDOWNSTREAMDRAINAGE MAPPROPERTYAPPROXIMATELY 1/4 MILEDOWNSTREAM FROM SITEAPPROXIMATE LOCATION OFLAKE WASHINGTON OUTFALLDISCHARGE POINTFROM PROPERTY12" SD SYSTEM18" SD SYSTEM24" SD SYSTEM
Fire Station 15
Technical Information Report
September 22, 2017
APPENDIX A
Design Documents
(To Be Provided in Final Drainage Report)
Fire Station 15
Technical Information Report
September 22, 2017
APPENDIX B
Design Calculations
Fire Station 15 Area Summary 9/22/2017
Existing Areas (SF) (AC)
North Subdivided Lot 16,495 0.38
South Subdivided Lot 31,045 0.71
Grand Total Area 47,540 1.091
On‐Site to Bio Pond (SF) (AC)
Roof 4,975 0.114
Total On‐Site to Bio 4,975 0.114
On‐Site Driect to Vault (SF) (AC)
PGIS 4,135 0.095
Fire Access Only 2,440 0.056
Pervious Pavement 4,180 0.096
Walk 755 0.017
Roof 2,780 0.064
Landscape 2,420 0.056
Total Impervious On‐Site to Vault 14,290 0.328
Total Pervious On‐Site to Vault 2,420 0.056
On‐Site Bypass Area (SF) (AC)
PGIS 650 0.015
Fire Access Only 400
Walk 520 0.012
Landscape 7,790 0.179
Total Impervious On‐Site 1,570 0.036
Total Pervious On‐Site 7,790 0.179
Total Target Impervious 20,835 0.478
Total Pervious 10,210 0.234
Total Basin Modeled 31,045 0.713
Percentage of Target Impervious 67.11%
20% of Target Surface 4,167
Proposed Areas
—————————————————————————————————
MGS FLOOD
PROJECT REPORT - FLOW CONTROL ANALYSIS
Program Version: MGSFlood 4.40
Program License Number: 201410003
Project Simulation Performed on: 08/21/2017 6:38 PM
Report Generation Date: 08/21/2017 6:38 PM
—————————————————————————————————
Input File Name: DD Detention with approx. bypass.fld
Project Name: FS 15
Analysis Title: Detention
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Climatic Region Number: 0
Full Period of Record Available used for Routing
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 0.713 0.707
Area of Links that Include Precip/Evap (acres) 0.000 0.006
Total (acres) 0.713 0.713
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Pre-dev Basin ----------
-------Area (Acres) --------
Till Grass 0.713
----------------------------------------------
Subbasin Total 0.713
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 3
---------- Subbasin : Direct to Det ----------
-------Area (Acres) --------
Till Grass 0.050
Impervious 0.328
----------------------------------------------
Subbasin Total 0.378
---------- Subbasin : Bypass ----------
-------Area (Acres) --------
Till Grass 0.179
Impervious 0.036
----------------------------------------------
Subbasin Total 0.215
---------- Subbasin : Roof to Bio ----------
-------Area (Acres) --------
Impervious 0.114
----------------------------------------------
Subbasin Total 0.114
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: New Copy Lnk1
Link Type: Copy
Downstream Link: None
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 3
------------------------------------------
Link Name: Det Systm
Link Type: Structure
Downstream Link Name: New Copy Lnk2
Prismatic Pond Option Used
Pond Floor Elevation (ft) : 100.00
Riser Crest Elevation (ft) : 103.00
Max Pond Elevation (ft) : 103.50
Storage Depth (ft) : 3.00
Pond Bottom Length (ft) : 20.0
Pond Bottom Width (ft) : 18.0
Pond Side Slopes (ft/ft) : L1= 0.00 L2= 0.00 W1= 0.00 W2= 0.00
Bottom Area (sq-ft) : 360.
Area at Riser Crest El (sq-ft) : 360.
(acres) : 0.008
Volume at Riser Crest (cu-ft) : 1,080.
(ac-ft) : 0.025
Area at Max Elevation (sq-ft) : 360.
(acres) : 0.008
Vol at Max Elevation (cu-ft) : 1,296.
(ac-ft) : 0.030
Massmann Infiltration Option Used
Hydraulic Conductivity (in/hr) : 0.00
Depth to Water Table (ft) : 100.00
Bio-Fouling Potential : Low
Maintenance : Average or Better
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 18.00
Common Length (ft) : 0.000
Riser Crest Elevation : 103.00 ft
Hydraulic Structure Geometry
Number of Devices: 2
---Device Number 1 ---
Device Type : Circular Orifice
Control Elevation (ft) : 100.00
Diameter (in) : 0.95
Orientation : Horizontal
Elbow : No
---Device Number 2 ---
Device Type : Circular Orifice
Control Elevation (ft) : 102.15
Diameter (in) : 0.85
Orientation : Vertical
Elbow : No
------------------------------------------
Link Name: New Copy Lnk2
Link Type: Copy
Downstream Link: None
------------------------------------------
Link Name: Bio Pond
Link Type: Bioretention Facility
Downstream Link Name: Det Systm
Base Elevation (ft) : 100.00
Riser Crest Elevation (ft) : 100.50
Storage Depth (ft) : 0.50
Bottom Length (ft) : 100.0
Bottom Width (ft) : 2.5
Side Slopes (ft/ft) : L1= 3.00 L2= 3.00 W1= 3.00 W2= 3.00
Bottom Area (sq-ft) : 250.
Area at Riser Crest El (sq-ft) : 567.
(acres) : 0.013
Volume at Riser Crest (cu-ft) : 316.
(ac-ft) : 0.007
Infiltration on Bottom and Sideslopes Selected
Soil Properties
Biosoil Thickness (ft) : 1.50
Biosoil Saturated Hydraulic Conductivity (in/hr) : 2.50
Biosoil Porosity (Percent) : 30.00
Maximum Elevation of Bioretention Soil : 102.00
Native Soil Hydraulic Conductivity (in/hr) : 0.00
Underdrain Present
Orifice NOT Present in Under Drain
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 6.00
Common Length (ft) : 0.000
Riser Crest Elevation : 100.50 ft
Hydraulic Structure Geometry
Number of Devices: 0
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 1
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 3
Number of Links: 3
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Pre-dev Basin 87.136
Link: New Copy Lnk1 0.000
_____________________________________
Total: 87.136
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Direct to Det 6.111
Subbasin: Bypass 21.876
Subbasin: Roof to Bio 0.000
Link: Det Systm Not Computed
Link: New Copy Lnk2 0.000
Link: Bio Pond Not Computed
_____________________________________
Total: 27.986
Total Predevelopment Recharge is Greater than Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.551 ac-ft/year, Post Developed: 0.177 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
********** Link: New Copy Lnk1 **********
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 143.39
Inflow Volume Including PPT-Evap (ac-ft): 143.39
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 143.39
Secondary Outflow To Downstream System (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered)/Total Volume: 0.00%
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 3
********** Link: New Copy Lnk2 **********
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 264.07
Inflow Volume Including PPT-Evap (ac-ft): 264.07
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 264.07
Secondary Outflow To Downstream System (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered)/Total Volume: 0.00%
***********Compliance Point Results *************
Scenario Predeveloped Compliance Link: New Copy Lnk1
Scenario Postdeveloped Compliance Link: New Copy Lnk2
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 6.708E-02 2-Year 6.558E-02
5-Year 0.115 5-Year 0.146
10-Year 0.168 10-Year 0.186
25-Year 0.256 25-Year 0.218
50-Year 0.331 50-Year 0.275
100-Year 0.363 100-Year 0.293
200-Year 0.400 200-Year 0.358
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
Fire Station 15 9/22/2017
Conveyance Analysis Spreadsheet
Gravity Discharge
Pipe Run Size Mannings N Plan
Slope Qfull Tributary Basins Tributary
Area Impervious Grass Qtrib
(25yr-5min)
% Full
(25yr)
#(inches)(ft/ft)(cfs)(acres)(acres)(acres)(cfs)
1 Pipe Connecting to Point of
Discharge 8 0.011 0.005 1.01 Entire Project Site 0.716 0.716 0.000 0.687 68%
—————————————————————————————————
MGS FLOOD
PROJECT REPORT- CONVEYANCE ANALYSIS
Program Version: MGSFlood 4.40
Program License Number: 201410003
Project Simulation Performed on: 08/21/2017 5:48 PM
Report Generation Date: 08/21/2017 5:49 PM
—————————————————————————————————
Input File Name: Conveyance Calcs.fld
Project Name: FS 15
Analysis Title: Conveyance
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 5
Extended Precipitation Time Series Selected
Climatic Region Number: 0
Full Period of Record Available used for Routing
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 0.713 0.713
Area of Links that Include Precip/Evap (acres) 0.000 0.000
Total (acres) 0.713 0.713
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Pre-dev Basin ----------
-------Area (Acres) --------
Till Grass 0.713
----------------------------------------------
Subbasin Total 0.713
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Subbasin 1 ----------
-------Area (Acres) --------
Impervious 0.713
----------------------------------------------
Subbasin Total 0.713
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: New Copy Lnk1
Link Type: Copy
Downstream Link: None
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 0
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 1
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
Number of Links: 0
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Pre-dev Basin 87.076
Link: New Copy Lnk1 0.000
_____________________________________
Total: 87.076
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Subbasin 1 0.000
_____________________________________
Total: 0.000
Total Predevelopment Recharge is Greater than Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.551 ac-ft/year, Post Developed: 0.000 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
********** Link: New Copy Lnk1 **********
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 143.41
Inflow Volume Including PPT-Evap (ac-ft): 143.41
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 143.41
Secondary Outflow To Downstream System (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered)/Total Volume: 0.00%
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 0
***********Compliance Point Results *************
Scenario Predeveloped Compliance Link: New Copy Lnk1
Scenario Postdeveloped Compliance Subbasin: Subbasin 1
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 8.601E-02 2-Year 0.333
5-Year 0.159 5-Year 0.437
10-Year 0.214 10-Year 0.535
25-Year 0.326 25-Year 0.687
50-Year 0.427 50-Year 0.836
100-Year 0.559 100-Year 1.034
200-Year 0.570 200-Year 1.134
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
Fire Station 15
Technical Information Report
September 22, 2017
APPENDIX C
Stormwater Pollution Prevention and Spill Plan (SWPPS)
(To Be Provided in Final Drainage Report)
Fire Station 15
Technical Information Report
September 22, 2017
APPENDIX D
Operations and Maintenance Manual
(To Be Provided in Final Drainage Report)