Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutRS_Drainage_Technical_Information_Report_250117_V1.pdfcoterra
6413 Phinney Ave N
Seattle, Washington 98103
206.596.7115
TECHNICAL INFORMATION REPORT
POST PERMIT REVISION
Project: Homestead
Willowcrest Townhomes PH II
Edmonds Ave NE
Renton, WA 98056
Prepared For: Homestead
412 Maynard Ave S #201
Seattle, WA 98104
Prepared By: Henry Stefan, PE
Reviewed By: Peter Apostol, PE
Date: December 13, 2024
ENGINEERING PLLC
TABLE OF CONTENTS
Section No. Subject Page No.
SECTION I PROJECT OVERVIEW.....................................................................1
SECTION II CONDITIONS AND REQUIREMENTS SUMMARY.....................9
SECTION III OFFSITE ANALYSIS......................................................................12
SECTION IV FLOW CONTROL AND WATER QUALITY
FACILITY ANALYSIS AND DESIGN..........................................18
SECTION V CONVEYANCE SYSTEM ANALYSIS AND DESIGN................23
SECTION VI SPECIAL REPORTS AND STUDIES.............................................23
SECTION VII OTHER PERMITS ...........................................................................23
SECTION VIII EROSION AND SEDIMENT CONTROL ......................................23
SECTION IX BOND QUANTITIES AND
DECLARATION OF COVENANTS...............................................24
SECTION X OPERATIONS AND MAINTENANCE MANUAL.......................24
LIST OF FIGURES
FIGURE 1 VICINITY MAP.................................................................................4
FIGURE 2 TIR WORKSHEET ............................................................................5
FIGURE 3 EXISTING SITE SOILS.....................................................................6
FIGURE 4 EXISTING LAND COVER ...............................................................7
FIGURE 5 DEVELOPED LAND COVER ..........................................................8
FIGURE 6 OFF-SITE DRAINAGE SYSTEM...................................................16
FIGURE 7 WATER QUALITY TREATMENT AREA ....................................22
LIST OF APPENDICIES
APPENDIX A CIVIL PLANS
APPENDIX B FLOW CONTROL/DETENTION CALCULATIONS
APPENDIX C WATER QUALITY CALCULATIONS
APPENDIX D GEOTECHNICAL REPORT
APPENDIX E OPERATIONS AND MAINTENANCE
APPENDIX F BOND QUANTITIES WORKSHEET (INCLUDED IN FUTURE
SUBMITTAL)
APPENDIX G CONVEYANCE CALCULATIONS (INCLUDED IN FUTURE
SUBMITTAL)
APPENDIX H DRAINAGE REVIEW FLOWCHART
APPENDIX I DECLARATION OF COVENANTS (INCLUDED IN FUTURE
SUBMITTAL)
Willowcrest Townhomes Project Phase 2 Page 1 Project No. 21011
Renton, WA Coterra Engineering PLLC
SECTION I – PROJECT OVERVIEW
General Description:
The proposed Homestead Willowcrest Townhomes Project Phase 2 includes the
construction of five townhome buildings, consisting of four townhomes each, on a
proposed 0.955 acre lot located off of Edmonds Ave NE in the City of Renton (see Figure
1 for vicinity map). The site is bordered by developed parcels to the east (Willowcrest
Phase 1 Townhomes), Edmonds Ave NE to the west, and developed parcels to the north
and south. The site is proposed to be subdivided for this townhomes project and
Edmonds Ave NE frontage improvements. The total area of the project site: the
Willowcrest Townhomes Phase 2 lot; and the front improvements total 1.067 acres. The
frontage improvements will include construction of new curb, gutter, bioretention planter,
and sidewalk. 270 feet of right-of-way will be dedicated along the site’s frontage on
Edmonds Ave NE.
The proposed project has been designed to meet the requirements of the 2022 City of
Renton Surface Water Design Manual (SWDM). A summary of the project data is
provided in the TIR worksheet (see Figure 2).
Site Soils:
The NRCS map (see Figure 3) of the site shows “Ragnar-Indianola” soils located within
the project area. Additional information on the site’s soils is provided in a geotechnical
report prepared by GeoEngineers, Inc., and dated Nov 18, 2024. The findings of the
report are based on soil samples taken from test pits that were excavated on-site. In
general, the results of the test pit data uncovered about one foot of topsoil mixed with
loose fill underlain by a 2-3.5 foot thick layer of silty sand that was underlain by
impermeable glacial till soil. For more information, see the geotechnical report included
in Appendix D.
Predeveloped Conditions:
The existing site consists of vegetation sloping to the west towards Edmonds Ave NE. A
steep asphalt driveway accessing Edmonds Ave NE as well as an existing rockery wall
ranging from 5’ to 15’.
Existing grades on the project site are generally 3% - 10% with stormwater runoff
draining overland from east to west towards Edmonds Ave NE. On the west margin of
the site, the previously improved street, Edmonds Ave NE, slopes from north to south at
approximately 7% slope along the frontage of the project site.
The existing land coverage of each section of the project site is presented in the table
below. The existing site is presented graphically in Figure 4 which follows this section.
The downstream path of stormwater runoff is described in the offsite analysis in Section
III.
Willowcrest Townhomes Project Phase 2 Page 2 Project No. 21011
Renton, WA Coterra Engineering PLLC
Table 1 – Existing Site Land Coverage (Acres)
Rooftop
(Acres)
Cem.
Conc.
(Acres)
Gravel
(Acres)
ACP
(Acres)
Pervious
(Acres)
Total
(Acres)
Basin A – Project
Site - - 0.025 - 0.895 0.920
Basin B – Offsite
Improvements - 0.036 0.010 - 0.078 0.124
Developed Conditions:
The area of proposed improvements include five townhouse buildings – consisting of
three to four connected townhomes in each building; an access drive; residential parking
stalls; pedestrian walkways; and associated storm drainage, utility, and landscape
improvements. The following table quantifies the areas of the proposed land coverage.
The proposed site is presented graphically in Figure 5 which follows this section.
Table 2 – Developed Site Land Coverage (Acres)
Rooftop
(Acres)
Cem.
Conc.
(Acres)
Gravel
(Acres)
ACP
(Acres)
Grass/
Landscape
(Acres)
Total
(Acres)
Basin A – Project
Site 0.298 0.213 - 0.161 0.248 0.920
Basin B – Offsite
Improvements - 0.0359 - 0.010 0.0781 0.124
The existing site topography will not be dramatically altered in the proposed condition.
In general, the site will continue to drain from east to west towards the Edmonds Ave NE
right-of-way as it currently does in the existing condition.
The proposed improvements within the project site (Basin A) described above and
delineated in Table 2 trigger both flow control and water quality mitigation per the City
of Renton Surface Water Design Manual.
Stormwater runoff will be collected by roof drains, catch basins, and area drains. Per
Core Requirement #4 of the 2017 City of Renton Surface Water Design Manual, the
proposed conveyance system will be designed to convey runoff resulting from the peak
rates resulting from the 25-year storm event. The proposed flow control facility is a
detention tank located at the west edge of the project site within a Tract, which will
discharge to the existing storm drainage main in Edmonds Ave NE to the west.
A bioretention planter with vertical concrete walls located at the west – and low end – of
the Phase 1 project site will provide water quality treatment to meet the City of Renton’s
Enhanced Basic Treatment requirement. Runoff from targeted pollution-generating
impervious surfaces will sheet flow or be captured by catch basins and flow into the
bioretention planter before entering the detention tank.
Willowcrest Townhomes Project Phase 2 Page 3 Project No. 21011
Renton, WA Coterra Engineering PLLC
See Section IV for a detailed description of the design of the flow control and water
quality facilities.
Willowcrest Townhomes Project Phase 2 Page 4 Project No. 21011
Renton, WA Coterra Engineering PLLC
FIGURE 1 – VICINITY MAP
Willowcrest Townhomes Project Phase 2 Page 5 Project No. 21011
Renton, WA Coterra Engineering PLLC
FIGURE 2
CITY OF RENTON
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
CITY OF RENTON SURFACE WATER DESIGN MANUAL
2022 City of Renton Surface Water Design Manual 6/22/2022
8-A-1
REFERENCE 8-A
TECHNICAL INFORMATION REPORT (TIR)
WORKSHEET
Part 1 PROJECT OWNER AND
PROJECT ENGINEER Part 2 PROJECT LOCATION AND
DESCRIPTION
Project Owner _____________________________
Phone ___________________________________
Address __________________________________
_________________________________________
Project Engineer ___________________________
Company _________________________________
Phone ___________________________________
Project Name __________________________
CED Permit # ________________________
Location Township ________________
Range __________________
Section _________________
Site Address __________________________
_____________________________________
Part 3 TYPE OF PERMIT APPLICATION Part 4 OTHER REVIEWS AND PERMITS
Land Use (e.g., Subdivision / Short Subd.)
Building (e.g., M/F / Commercial / SFR)
Grading
Right-of-Way Use
Other _______________________
DFW HPA
COE 404
DOE Dam Safety
FEMA Floodplain
COE Wetlands
Other ________
Shoreline
Management
Structural
Rockery/Vault/_____
ESA Section 7
Part 5 PLAN AND REPORT INFORMATION
Technical Information Report Site Improvement Plan (Engr. Plans)
Type of Drainage Review
(check one):
Date (include revision
dates):
Date of Final:
Full
Targeted
Simplified
Large Project
Directed
__________________
__________________
__________________
Plan Type (check
one):
Date (include revision
dates):
Date of Final:
Full
Modified
Simplified
__________________
__________________
__________________
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
6/22/2022 2022 City of Renton Surface Water Design Manual
8-A-2
Part 6 SWDM ADJUSTMENT APPROVALS
Type (circle one): Standard / Blanket
Description: (include conditions in TIR Section 2)
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
Approved Adjustment No. ______________________ Date of Approval: _______________________
Part 7 MONITORING REQUIREMENTS
Monitoring Required: Yes / No
Start Date: _______________________
Completion Date: _______________________
Describe: _________________________________
_________________________________________
_________________________________________
Re: SWDM Adjustment No. ________________
Part 8 SITE COMMUNITY AND DRAINAGE BASIN
Community Plan: ____________________________________________________________________
Special District Overlays: ______________________________________________________________
Drainage Basin: _____________________________________________________________________
Stormwater Requirements: _____________________________________________________________
Part 9 ONSITE AND ADJACENT SENSITIVE AREAS
River/Stream ________________________
Lake ______________________________
Wetlands ____________________________
Closed Depression ____________________
Floodplain ___________________________
Other _______________________________
_______________________________
Steep Slope __________________________
Erosion Hazard _______________________
Landslide Hazard ______________________
Coal Mine Hazard ______________________
Seismic Hazard _______________________
Habitat Protection ______________________
_____________________________________
REFERENCE 8-A: TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
2022 City of Renton Surface Water Design Manual 6/22/2022
Ref 8-A-3
Part 10 SOILS
Soil Type
______________________
______________________
______________________
______________________
Slopes
________________________
________________________
________________________
________________________
Erosion Potential
_________________________
_________________________
_________________________
_________________________
High Groundwater Table (within 5 feet)
Other ________________________________
Sole Source Aquifer
Seeps/Springs
Additional Sheets Attached
Part 11 DRAINAGE DESIGN LIMITATIONS
REFERENCE
Core 2 – Offsite Analysis_________________
Sensitive/Critical Areas__________________
SEPA________________________________
LID Infeasibility________________________
Other________________________________
_____________________________________
LIMITATION / SITE CONSTRAINT
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
Additional Sheets Attached
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet
per Threshold Discharge Area)
Threshold Discharge Area:
(name or description)
Core Requirements (all 9 apply):
Discharge at Natural Location Number of Natural Discharge Locations:
Offsite Analysis Level: 1 / 2 / 3 dated:__________________
Flow Control (include facility
summary sheet)
Standard: _______________________________
or Exemption Number: ____________
Conveyance System Spill containment located at: _____________________________
Erosion and Sediment Control /
Construction Stormwater Pollution
Prevention
CSWPP/CESCL/ESC Site Supervisor: _____________________
Contact Phone: _________________________
After Hours Phone: _________________________
Maintenance and Operation Responsibility (circle one): Private / Public
If Private, Maintenance Log Required: Yes / No
Financial Guarantees and Liability Provided: Yes / No
REFERENCE 8: PLAN REVIEW FORMS AND WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
6/22/2022 2022 City of Renton Surface Water Design Manual
8-A-4
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet
per Threshold Discharge Area)
Water Quality (include facility
summary sheet)
Type (circle one): Basic / Sens. Lake / Enhanced Basic / Bog
or Exemption No. _______________________
On-site BMPs Describe:
Special Requirements (as applicable):
Area Specific Drainage
Requirements
Type: SDO / MDP / BP / Shared Fac. / None
Name: ________________________
Floodplain/Floodway Delineation Type (circle one): Major / Minor / Exemption / None
100-year Base Flood Elevation (or range): _______________
Datum:
Flood Protection Facilities Describe:
Source Control
(commercial / industrial land use)
Describe land use:
Describe any structural controls:
Oil Control High-Use Site: Yes / No
Treatment BMP: _________________________________
Maintenance Agreement: Yes / No
with whom? _____________________________________
Other Drainage Structures
Describe:
REFERENCE 8-A: TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
2022 City of Renton Surface Water Design Manual 6/22/2022
Ref 8-A-5
Part 13 EROSION AND SEDIMENT CONTROL REQUIREMENTS
MINIMUM ESC REQUIREMENTS
DURING CONSTRUCTION
Clearing Limits
Cover Measures
Perimeter Protection
Traffic Area Stabilization
Sediment Retention
Surface Water Collection
Dewatering Control
Dust Control
Flow Control
Control Pollutants
Protect Existing and Proposed
BMPs/Facilities
Maintain Protective BMPs / Manage
Project
MINIMUM ESC REQUIREMENTS
AFTER CONSTRUCTION
Stabilize exposed surfaces
Remove and restore Temporary ESC Facilities
Clean and remove all silt and debris, ensure
operation of Permanent BMPs/Facilities, restore
operation of BMPs/Facilities as necessary
Flag limits of sensitive areas and open space
preservation areas
Other _______________________
Part 14 STORMWATER FACILITY DESCRIPTIONS (Note: Include Facility Summary and Sketch)
Flow Control Description Water Quality Description On-site BMPs Description
Detention
Infiltration
Regional
Facility
Shared
Facility
Other
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
Vegetated
Flowpath
Wetpool
Filtration
Oil Control
Spill Control
Other
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
Full Dispersion
Full Infiltration
Limited Infiltration
Rain Gardens
Bioretention
Permeable
Pavement
Basic Dispersion
Soil Amendment
Perforated Pipe
Connection
Other
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
_____________
Willowcrest Townhomes Project Phase 2 Page 6 Project No. 21011
Renton, WA Coterra Engineering PLLC
FIGURE 3 – EXISTING SITE SOIL CONDITIONS
co
t
e
r
r
a
32
1
3
r
d
A
v
e
n
u
e
S
o
u
t
h
,
S
u
i
t
e
4
0
6
Se
a
t
t
l
e
,
W
a
s
h
i
n
g
t
o
n
9
8
1
0
4
20
6
.
5
9
6
.
7
1
1
5
c
o
t
e
r
r
a
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
EN
G
I
N
E
E
R
I
N
G
P
L
L
C
co
t
e
r
r
a
32
1
3
r
d
A
v
e
n
u
e
S
o
u
t
h
,
S
u
i
t
e
4
0
6
Se
a
t
t
l
e
,
W
a
s
h
i
n
g
t
o
n
9
8
1
0
4
20
6
.
5
9
6
.
7
1
1
5
c
o
t
e
r
r
a
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
EN
G
I
N
E
E
R
I
N
G
P
L
L
C
Willowcrest Townhomes Project Phase 2 Page 9 Project No. 21011
Renton, WA Coterra Engineering PLLC
SECTION II – CONDITIONS AND REQUIREMENTS SUMMARY
The proposed project is subject to a Full Drainage Review per the 2022 City of Renton
Surface Water Design Manual and is therefore subject to all nine core requirements and
all six special requirements. These requirements are listed below along with a discussion
of their applicability to this project. See Appendix H for drainage review type flow chart.
Core Requirements:
Req. #1 Discharge at Natural Location:
Existing discharge locations will be maintained.
Req. #2 Offsite Analysis:
See Section III below.
Req. #3 Flow Control:
The project is required to meet the Peak Rate Flow Control Standard.
The proposed improvements within Phase 1 exceed the threshold of 5,000 sf of
new and replaced impervious surface, therefore triggering the requirement of a
flow control facility and on-site flow control BMPs.
A detention tank is proposed to meet the Peak Rate Flow Control Standard
requirement. Onsite BMPs are also required as part of the project and are
discussed below in Core Requirement #9.
For further details see Section IV.
Req. #4 Conveyance System:
The new conveyance system has been designed to meet and exceed the
requirement to convey the 25-year peak flow from the developed site conditions.
Req. #5 Erosion and Sediment Control:
Construction erosion and sediment control systems shall be implemented per the
Temporary Erosion and Sediment Control plan.
Willowcrest Townhomes Project Phase 2 Page 10 Project No. 21011
Renton, WA Coterra Engineering PLLC
Req. #6 Maintenance and Operations:
A Declaration of Covenant is required for this project and will be submitted for
review by City of Renton staff before recording. The proposed facilities will be
owned and maintained by Homestead.
Req. #7 Financial Guarantees:
A financial guarantee will be necessary for this project. Bonding will be required
for the construction of improvements and will be obtained prior to construction.
Req. #8 Water Quality:
The proposed improvements located on the project site exceed 5,000 sf of new
and replaced Pollution-Generating Impervious Surface (PGIS), therefore
triggering the requirement of a water quality facility.
Based on the proposed site usage, multi-family housing, Enhanced Basic Water
Quality treatment is required per Core Requirement #8 of the 2022 City of Renton
Surface Water Design Manual for targeted PGIS.
A vertical-walled bioretention planter is proposed to meet the requirements of the
Enhanced Basic Water Quality requirement within the SWDM.
For further details see Section IV.
Req. #9 On-Site BMPs:
The proposed improvements exceed the threshold of 5,000 sf of new and replaced
impervious surface, therefore triggering the requirements of Core Requirement #9
to implement on-site flow control facilities to the maximum extent feasible.
Following the City of Renton SWDM required list method for implementing on-
site BMPs to comply with Core Requirement #9, all listed BMPs were determined
to be infeasibly for Phase 1 of the proposed project site.
Despite infeasibility determinations for listed on-site BMP facilities, the proposed
project plans to implement perforated pipe on all roof drain connections from the
four proposed townhouse buildings per the recommendation of the City of Renton
SWDM.
Willowcrest Townhomes Project Phase 2 Page 11 Project No. 21011
Renton, WA Coterra Engineering PLLC
Additionally, the project will implement compost-amended topsoil per SWDM
requirement for all new and replaced landscape areas to aid surface water
drainage.
For further details see Section IV.
Special Requirements:
Req. #1 Area Specific Requirements:
No area specific requirements are applicable to this project.
Req. #2: Floodplain/Floodway Delineation
This project is not adjacent to any floodplains or floodways. Therefore no
delineation is necessary.
Req. #3 Flood Protection Facilities:
This project is not adjacent to any applicable areas and will not affect any
applicable facility.
Req. #4 Source Controls:
This project is a multi-family project and will provide appropriate source controls.
Req. #5 Oil Control:
No oil control requirements are applicable to this project.
Req. #6 Aquifer Protection Area
The proposed project is within Zone 2 of the APA. The contractor will be
required to obtain imported fill material from a Washington Department of
Transportation approved source. There are no open flow control or water quality
facilities which will introduce stormwater to ground water given the project soil
conditions.
Willowcrest Townhomes Project Phase 2 Page 12 Project No. 21011
Renton, WA Coterra Engineering PLLC
SECTION III – OFFSITE ANALYSIS
Task 1 – Study Area Definition and Maps
Maps of the project site and surrounding area were obtained from the King County GIS
website. Topographical site information is from the topographical survey for the project.
Storm drainage system maps were compiled from City of Renton GIS maps and as-built
plans. Aerial images were obtained from Google Earth.
Task 2 – Resource Review
The City of Renton Public Works Department was contacted regarding the resources
listed in section 2.3.1.1 of the 2022 City of Renton Surface Water Design Manual. The
following is a summary of the resource review:
Adopted Basin Plans
o King County Basin Name: East Lake Washington (per King County
iMap)
Basin Reconnaissance Summary Reports
o None completed to our knowledge.
Floodplain/Floodway (FEMA) Maps
o The site is not within a floodplain or floodway per FEMA mapping.
Other Offsite Analysis Reports
o Other Offsite Analysis Reports were not available.
Environmentally Sensitive Areas Map
o There are no Environmentally Sensitive areas mapped within the vicinity
of the site.
USDA Soils Survey
o A geotech report has been completed and site soils are primarily silty sand
that was underlain by impermeable glacial till soil.
Wetlands Inventory Maps
o There are no Wetlands mapped within the vicinity of the site.
Downstream Water Quality Problems Requiring Special Attention
o Per Section 1.2.2.1.2 of the SWDM, possible downstream water quality
issues that have been identified by the local, state, or federal jurisdiction
must be reviewed as part of the Downstream Analysis.
Per the EPA’s Clean Water Act, states must identify impaired waterways
and identify the pollutants causing impairment. These waterways or
waterbodies are listed on what is known as the 303(d) list. The eventual
downstream conveyance system for the proposed project site is John’s
Willowcrest Townhomes Project Phase 2 Page 13 Project No. 21011
Renton, WA Coterra Engineering PLLC
Creek, which outfalls into Lake Washington. The last reaches of John’s
Creek are identified by the Washington State Department of Ecology as
303(d) impacted based on the following parameters which are identified as
Category 5, which lists the waterbody on the 303(d) list:
-Bacteria
-Temperature
-Dissolved Oxygen
The portions of John’s Creek which are identified as 303(d) impacted
waterways at the final reaches of John’s Creek as it outfalls to Lake
Washington. These sections are beyond ¼ mile from the piped-
conveyance system which the proposed project site discharges to in
Edmonds Ave NE.
o Per Section 1.2.2.3 of the SWDM, based on the criteria listed above for
the 303(d) listed waterway(s) for the downstream conveyance from the
project site, the following mitigation measures must be considered as part
of the proposed project:
-Bacteria
The proposed project does not drain to a bacteria problem
located within one quarter mile/15% distance downstream
from the site discharge point; therefore no further
mitigation measures are required beyond Core
Requirements #1 - #9 and Special Requirements #1 - #6
from the 2017 City of Renton Surface Water Design
Manual. The location of the impacted 303(d) waterway was
determined from Washington State DOE’s online Water
Quality Atlas Mapping system.
-Temperature
The proposed project does not drain to a temperature
problem located within one quarter mile/15% distance
downstream from the site discharge point; therefore no
further mitigation measures are required beyond Core
Requirements #1 - #9 and Special Requirements #1 - #6
from the 2017 City of Renton Surface Water Design
Manual. The location of the impacted 303(d) waterway was
determined from Washington State DOE’s online Water
Quality Atlas Mapping system.
-Dissolved Oxygen
The proposed project does not drain to a Dissolved Oxygen
problem located within one quarter mile/15% distance
downstream from the site discharge point; therefore no
further mitigation measures are required beyond Core
Willowcrest Townhomes Project Phase 2 Page 14 Project No. 21011
Renton, WA Coterra Engineering PLLC
Requirements #1 - #9 and Special Requirements #1 - #6
from the 2017 City of Renton Surface Water Design
Manual. The location of the impacted 303(d) waterway was
determined from Washington State DOE’s online Water
Quality Atlas Mapping system.
Task 3 – Field Inspection
A Level 1 downstream analysis was performed on 12/18/2018. Weather conditions
during the downstream analysis consisted of overcast skies. Periodic rainfall occurred in
the week prior to the analysis.
On-site landuse and topography was confirmed, and the downstream conveyance was
identified. This section is complemented by the information found in Figure 6 and the
Off-site Analysis Drainage System Table which follow this section.
Stormwater runoff originating from the project site sheet flows to the west across the
adjacent undeveloped parcel which is primarily vacant and heavily vegetated. Grades
within this parcel slope to the west at approximately 10%-15%. Sheet flow patterns
persist in a westerly direction until flowing onto Edmonds Ave NE. A piped conveyance
system in Edmonds Ave NE collects runoff from the project site and conveys flows to the
south. Due to heavy traffic conditions, the piped conveyance system was not inspected.
Based on review of City of Renton GIS Utility Mapping, the piped conveyance continues
to the south in Edmonds Ave NE to NE Sunset Blvd, where larger diameter conveyance
piping flows west towards Lake Washington beyond ¼ mile downstream from the site.
No open drainage complaints are associated with the downstream conveyance system.
Task 4 – Drainage System Description and Problem Description
There are no known problems with the downstream system.
Task 5 – Mitigation of Existing or Potential Problems
Based on the observations made during the field inspection and the requirements for the
design of the proposed drainage systems, no negative impacts to the systems downstream
of the project site are anticipated.
Existing Upslope Drainage Areas
Portions of the adjacent property to the east – the previously developed Glennwood
Townhomes drain to the west based on topography to the proposed Phase 1 project site.
The areas of the adjacent off-site, upstream area that drains to the Willowcrest site are
fully-established pervious landscape areas or previously undeveloped pervious areas.
Based on on-site observations during the Offsite Analysis, no upstream run-on was
observed. Based on current landcover, site layout, and grading, minimal offsite run-on is
expected onto the Willowcrest site.
Willowcrest Townhomes Project Phase 2 Page 15 Project No. 21011
Renton, WA Coterra Engineering PLLC
To mitigate any upstream overland or subsurface run-on, a perforated interreceptor storm
drain line is proposed at the eastern project margin of the Phase 1 property to collect any
upstream flows from the Glennwood Townhomes site and route it around the proposed
project improvements on the Willowcrest site. The proposed upstream drainage
collection system – consisting of a French drain – and tightline routing is intended to
maintain the existing drainage patterns of any upstream runoff from the adjacent property
and convey it to the existing municipal storm drainage system in Edmonds Ave NE.
18"
SD
18"
SD
24"
SD 24"SD
2
4"
S
D
3
0"
S
D
30"SD
36"SD
3 6 "S D
3 6 "S D
3 6 "S D 3 6 "S D
36"SD
CB (TYP)
PROJECT
SITE
SHALLOW CONCENTRATED
SURFACE FLOW
PIPED CONVEYANCE
CATCH BASIN
DIRECTION OF
FLOW INDICATED
BY ARROW
SHEET FLOW
co
t
e
r
r
a
32
1
3
r
d
A
v
e
n
u
e
S
o
u
t
h
,
S
u
i
t
e
4
0
6
Se
a
t
t
l
e
,
W
a
s
h
i
n
g
t
o
n
9
8
1
0
4
20
6
.
5
9
6
.
7
1
1
5
c
o
t
e
r
r
a
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
EN
G
I
N
E
E
R
I
N
G
P
L
L
C
1/1/05
OFF-SITE ANALYSIS DRAINAGE SYSTEM TABLE
SURFACE WATER DESIGN MANUAL, CORE REQUIREMENT #2
Basin: Subbasin Name: Subbasin Number:
Symbol Drainage
Component Type,
Name, and Size
Drainage
Component
Description
Slope Distance
from site
discharge
Existing
Problems
Potential
Problems
Observations of field
inspector, resource
reviewer, or resident
see map Type: sheet flow, swale,
stream, channel, pipe,
pond; Size: diameter,
surface area
drainage basin, vegetation,
cover, depth, type of sensitive
area, volume
% ¼ ml = 1,320 ft. constrictions, under capacity, ponding,
overtopping, flooding, habitat or organism
destruction, scouring, bank sloughing,
sedimentation, incision, other erosion
tributary area, likelihood of problem,
overflow pathways, potential impacts
Willowcrest Townhomes Project Phase 2 Page 18 Project No. 21011
Renton, WA Coterra Engineering PLLC
SECTION IV – FLOW CONTROL AND WATER QUALITY FACILITY
ANALYSIS AND DESIGN
Flow Control
The project site is located in a Peak Flow Control Standard area per the 2022 City of
Renton Surface Water Design Manual. This standard requires that the developed site
discharge rates match the existing site conditions discharge rates for the 2-, 10-, and 100-
year return periods. The proposed improvements will create more than 2,000 SF of new
plus replaced imperious surfaces, therefore the project is required to meet the flow
control standard and implement on-site flow control BMPs. Based on the engineer’s on-
site visits to the proposed property and analysis of current aerial photography, the
existing site conditions within the project site is assumed to be 25% forested land cover
and 75% pasture land cover.
MGS Flood stormwater modeling program – utilizing a continuous hydrologic model –
was implemented to size a detention facility which matched the existing site discharge
rates for the 2-, 10-, and 100-year return events. At this preliminary stage of design, a
detention vault was sized in MGS Flood to meet the flow control requirement. As the
project stormwater design is refined, the type of detention structure on the project may be
revised.
Based on the MGS Flood analysis, a detention tank was sized to detain Basin A of the
proposed project. The proposed detention volume is 3,731 cubic feet. The MGS Flood
calculations are included in Appendix B of this report. The proposed detention tank was
designed per the City of Renton SWDM requirements including 0.5’ sediment storage
(dead storage). Sizing details are shown on the Storm Drainage Plan, sheet 4.0 of the civil
plan set, as well as the civil details.
On-Site Flow Control BMPs
The proposed site is classified as a Small Subdivision Project. Implementation of On-
Site Flow Control BMPs is therefore required per Core Requirement #9.
On-site BMPs are evaluated for targeted surfaces, per the list from section 1.2.9.3.1 for
Small Subdivision Projects in the 2022 City of Renton Surface Water Design Manual.
Analysis of feasibility of the on-site BMPs from the SWDM list follow in order per
SWDM feasibility determination instructions.
Full Dispersion: Infeasible. Per on-site BMP infeasibility criteria in section C.2.1.1,
the total area of impervious surfaces plus non-native pervious surfaces on the project
site exceed 35% of the total site area.
Full Infiltration: Infeasible. Per criteria outlined in section 5.2 of the SWDM, in order
for infiltration to be implemented on a site, “The applicant must demonstrate through
infiltration testing, soil logs, and the written opinion of a geotechnical professional
that sufficient permeable soil exists at the proposed facility location to allow
construction of a properly functioning infiltration facility.” Per the SWDM, the
Willowcrest Townhomes Project Phase 2 Page 19 Project No. 21011
Renton, WA Coterra Engineering PLLC
geotechnical engineer shall obtain soil logs for possible infiltration system locations
on the proposed site. Soils collected in on-site test pits per Geotechnical Engineering
Services report prepared by GeoEngineers, Inc., dated 11/18/2024, are classified as
“SM” or “silty sands, sand – silt mixtures” at the depth of typical on-site infiltration
facilities or infiltration BMPs. The report continues, “Based on our analysis, it is our
opinion that the on-site native glacial till soils have a very low infiltration capacity.”
And finally they conclude, “Due to the density, high fines content, and relative
impermeability of the glacial till, infiltration should be assumed to be very low when
designing infiltration systems.” Based on the geotechnical engineer analysis of the
existing site soils, full infiltration is not feasible.
Bioretention: Infeasible For On-Site Flow Control BMPs. Bioretention is proposed to
provide water quality treatment on the project site. The bioretention planter has been
designed to meet the requirements of Enhanced Basic Water Quality treatment. Due
to the very low infiltration capacity of the existing onsite soils, the bioretention
planter has been designed utilizing an underdrain as allowed by the SWDM for water
quality treatment.
But, bioretention with underdrains is not allowed to meet Core Requirement #9, per
the SWDM; therefore bioretention is infeasible for on-site flow control BMPs.
Permeable Pavement: Infeasible. Per section C2.7, permeable pavement shall not be
installed on slopes steeper than 5% for porous asphaltic concrete. Project proposes
asphalt paving for access drives. Based on existing topography and proposed site
layout, majority of access drive grades exceed 5%. Proposed areas of grading less
than 5% in access drive would exceed maximum run-on limit ratio for PGIS of 2:1.
Limited Infiltration: Per SWDM section 1.2.9.2.2, which then references section
C.2.3 for feasibility of Limited Infiltration, “Where geotechnical evaluation and
approval is required for limited infiltration that proposes to discharge towards or is
within described setbacks of a steep slope hazard area, erosion hazard area, landslide
hazard, or slopes greater than 15%, limited infiltration is considered infeasible and
not required.” Existing and proposed grades down gradient from proposed project site
exceed 15% grade; therefore, limited infiltration is infeasible.
Basic Dispersion:
o Splash blocks: Infeasible. Required 50’ vegetated flow path is infeasible
based on proposed site design.
o Rock pads: Infeasible. Required 50’ vegetated flow path is infeasible
based on proposed site design.
o Gravel-filled trenches: Infeasible. Per section C.2.4.4, setbacks of at least
10’ from buildings and 5’ from property line are required. Proposed site
layout cannot accommodate 25’ flowpath with required setbacks.
o Sheet flow: Infeasible. Required 10’ vegetated flow path located on the
project property is infeasible based on proposed site design.
Other BMPs: Per criteria set forth in section 1.2.9.2.2 of the SWDM, for projects that
will result in an impervious surface coverage 45-65% on the buildable portion of the
Willowcrest Townhomes Project Phase 2 Page 20 Project No. 21011
Renton, WA Coterra Engineering PLLC
site/lot, on-site BMPs must be applied to 50% of target impervious surfaces reduced
by 1.5% for each 1% of impervious surface coverage above 45%.
The proposed project site developed condition consists of 63% impervious surfaces.
Based on the above formula, 23% of the site’s targeted impervious surfaces must be
mitigated by onsite BMPs (63%-45%=18%; 18*1.5=27; 50%-27%=23%). Of the
19,689 SF of new impervious surfaces, 4,528 SF are required by the SWDM to be
mitigated by onsite BMPs.
When the previously listed onsite stormwater BMPs are not feasible, projects shall
evaluate the implementation of the following BMPs:
o Reduced Impervious Surface Credit: Currently proposed townhome
footprints total 20% of proposed Phase I lot. Townhomes have been
designed to maximize building lot area for the benefit of providing
maximum number of housing units allowed by zoning on this site.
Reduced Impervious Surface Credit would decrease size of proposed
townhomes and limit the project goals of providing as much low-income
housing as possible with the highest site density. To meet BMP area
target, proposed townhomes would need to decrease by over 50% of
proposed footprint. This is infeasible for this project.
o Native Growth Retention Credit: This BMP credit requires retention of
existing forested portions of the site at a 3.5 to 1 ratio for credit. To meet
BMP target goal, 15,850 SF of site area would need to be retained as
native growth. That is over one third of proposed site area and would not
make development of site possible to the desired density to meet project
goal of providing maximum number of low-incoming housing units.
Additionally, this BMP is infeasible due to, “The donor area must not
slope more than 15%.” – existing and proposed onsite grades exceed 15%.
o Tree Retention Credit: 4 Significant Trees are proposed to be retained as
part of the proposed project to meet land use code requirements. These
trees are shown on the Tree Retention Plan within the landscape plans. To
meet the onsite BMP area target (tree retention credit can only account for
up to 25% of required target mitigation area), 11,320 SF of deciduous tree
canopy or 5,660 SF of evergreen tree canopy would need to be retained on
the project site and within 20’ of ground-level hardscape. Based on
proposed site layout to maximize housing units, it is infeasible to meet the
onsite BMP target mitigation area requirement with tree retention.
Soil Amendment: Feasible. New and replaced pervious surfaces within the project
limits will implement soil amendment per the soil quality and depth requirements of
section C2.13. Soil amendment will be implemented in all onsite disturbed areas
which will be landscape area in the developed condition. See Landscape sheet 3.01
for additional details.
Willowcrest Townhomes Project Phase 2 Page 21 Project No. 21011
Renton, WA Coterra Engineering PLLC
Despite infeasibility for listed on-site BMPs per the SWDM criteria, perforated pipe
connections from roof drain leaders from each of the three proposed buildings, upstream
of detention, are proposed. These perforated pipe connections are shown on the current
Utility Plan.
From the initial geotechnical investigation, it was determined that the subsurface soils on
the project site are composed of several feet of fill soil laying over glacial till which
inhibits any practical infiltration potential for possible stormwater mitigation on the
project site. Therefore, the use of large-scale infiltrative flow control facilities and on-site
BMPs are not shown on the current preliminary plans.
Water Quality
The proposed new and replaced pollution-generating impervious surfaces (PGIS) on the
project site trigger the requirement for water quality treatment of targeted surfaces. Per
the City of Renton SWDM, the project site is within the Basin Water Quality Area; but
the proposed site land use of multi-family housing triggers the Enhanced Basic Water
Quality Menu.
The proposed project will provide treatment of targeted PGIS as outlined by the
Enhanced Basic Water Quality Menu. This will be provided by a single bioretention
planter with vertical concrete walls located at the west side of the Phase 1 project area.
Runoff from targeted PGIS will generally sheet flow towards the bioretention planter
where it will be captured first by a Type 1 catch basin with an outlet pipe fitted with a
downturn elbow and discharging onto cobbles to slow the velocity of the tributary flows
and provide some measure of pre-treatment to the bioretention facility.
The bioretention facility was sized using MGS Flood software to treat a minimum of 91%
of the total runoff volume from the tributary targeted surfaces flowing to the facility. The
targeted water quality surfaces for the project are shown on Figure 7 which follows.
Based on the MGS Flood calculations, a 10’x12’ interior dimension bioretention planter
is proposed, with a total of 120 square feet of bottom area. The bioretention cell will have
vertical walls constructed from concrete due to the grading limits near the project tract
line. The 144 square foot bioretention planter will treat at least 91% of all tributary flows
to the facility. 6” of ponding depth is proposed and a 6” underdrain will be installed
under the bioretention soil mix because of the poorly-draining soils existing on the site.
Sizing calculations are provided in Appendix C.
co
t
e
r
r
a
32
1
3
r
d
A
v
e
n
u
e
S
o
u
t
h
,
S
u
i
t
e
4
0
6
Se
a
t
t
l
e
,
W
a
s
h
i
n
g
t
o
n
9
8
1
0
4
20
6
.
5
9
6
.
7
1
1
5
c
o
t
e
r
r
a
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
EN
G
I
N
E
E
R
I
N
G
P
L
L
C
Willowcrest Townhomes Project Phase 2 Page 23 Project No. 21011
Renton, WA Coterra Engineering PLLC
SECTION V – CONVEYANCE SYSTEM DESIGN AND ANALYSIS
The new conveyance system has been designed to convey, per SWDM requirements, at
least the 25-year peak flow rate from the developed site. Conveyance capacity
calculations are included in Appendix G which show that onsite conveyance can
accommodate the 100-year peak flow for the full developed site in addition to upstream
tributary area.
SECTION VI – SPECIAL REPORTS AND STUDIES
A geotechnical analysis of the project site was performed and is included in Appendix D.
Additionally, specifications are provided by manufacturer to show that the proposed
detention tank can accommodate at least H-20 loading per City of Renton comments.
SECTION VII – OTHER PERMITS
In addition to the PPUD permit, a Civil Construction Permit from the City of Renton is
required.
SECTION VIII – EROSION AND SEDIMENT CONTROL
ESC Measures are being addressed as follows:
Clearing Limits: Clearing limits are being delineated by perimeter silt fencing and
chain link fencing.
Cover Measures: Temporary cover shall be installed if an area is to remain
unworked for more than seven days during the dry season (May 1 to September
30) or for more than two consecutive working days during the wet season
(October 1 to April 30). Any area to remain unworked for more than 30 days shall
be seeded or sodded, unless the City of Renton determines that winter weather
makes vegetation establishment infeasible.
Perimeter Protection: Perimeter protection will be implemented by silt fencing
around the site perimeter where drainage paths require.
Traffic Area Stabilization: A stabilized construction entrance will be built for
construction traffic.
Sediment Retention: Catch basin protection has been provided and is shown on
the projects TESC plans.
Surface Water Control: Surface water will be collected and conveyed via swales
with check dams as necessary.
Dust Control: Dust control, if required, will be provided through the limited use
of water trucks.
Willowcrest Townhomes Project Phase 2 Page 24 Project No. 21011
Renton, WA Coterra Engineering PLLC
SECTION IX – BOND QUANTITIES AND DECLARATION OF COVENANTS
A bond quantity worksheet for the proposed improvements is included with this
submittal.
There are three Declaration of Covenants which are required for the proposed project:
- one for inspection and maintenance of proposed stormwater facilities
- one for the inspection and maintenance of the proposed on-site BMPs.
- one for the prohibition on the use of leachable metals on the property.
The covenants for inspection and maintenance of stormwater facilities and on-site BMPs
are provided as one document as allowed by the City of Renton. A draft version of the
required covenants are provided in Appendix I.
Covenants must be signed and notarized prior to recording.
SECTION X – OPERATIONS AND MAINTENANCE MANUAL
An Operation and Maintenance Manual is provided in this submittal in Appendix E. The
maintenance of the stormwater facilities will by be performed by Homestead.
Appendix A
Civil Plans
C1.0
NW 1/4, SEC. 9, TWP. 23N, RGE. 5E, W.M.
IN COMPLIANCE WITH CITY OF RENTON STANDARDS
EDMONDS AVE NE, RENTON, WA
WILLOWCREST TOWNHOMES IIcoterra
6413 Phinney Ave North
Seattle, Washington 98103
ph 206.596.7115
coterraengineering.com
ENGINEERING PLLC
WI
L
L
O
W
C
R
E
S
T
T
O
W
N
H
O
M
E
S
I
I
MA
S
T
E
R
S
I
T
E
P
L
A
N
R
E
V
I
E
W
PR
:
LU
A
:
C:
’
’
’
C1.1
IN COMPLIANCE WITH CITY OF RENTON STANDARDS
EDMONDS AVE NE, RENTON, WA
WILLOWCREST TOWNHOMES IIcoterra
6413 Phinney Ave North
Seattle, Washington 98103
ph 206.596.7115
coterraengineering.com
ENGINEERING PLLC
WI
L
L
O
W
C
R
E
S
T
T
O
W
N
H
O
M
E
S
I
I
MA
S
T
E
R
S
I
T
E
P
L
A
N
R
E
V
I
E
W
PR
:
LU
A
:
C:
IN COMPLIANCE WITH CITY OF RENTON STANDARDS
EDMONDS AVE NE, RENTON, WA
WILLOWCREST TOWNHOMES IIcoterra
6413 Phinney Ave North
Seattle, Washington 98103
ph 206.596.7115
coterraengineering.com
ENGINEERING PLLC
WI
L
L
O
W
C
R
E
S
T
T
O
W
N
H
O
M
E
S
I
I
MA
S
T
E
R
S
I
T
E
P
L
A
N
R
E
V
I
E
W
PR
:
LU
A
:
C:
C2.0
IN COMPLIANCE WITH CITY OF RENTON STANDARDS
EDMONDS AVE NE, RENTON, WA
WILLOWCREST TOWNHOMES IIcoterra
6413 Phinney Ave North
Seattle, Washington 98103
ph 206.596.7115
coterraengineering.com
ENGINEERING PLLC
WI
L
L
O
W
C
R
E
S
T
T
O
W
N
H
O
M
E
S
I
I
MA
S
T
E
R
S
I
T
E
P
L
A
N
R
E
V
I
E
W
PR
:
LU
A
:
C:
C3.0
IN COMPLIANCE WITH CITY OF RENTON STANDARDS
EDMONDS AVE NE, RENTON, WA
WILLOWCREST TOWNHOMES IIcoterra
6413 Phinney Ave North
Seattle, Washington 98103
ph 206.596.7115
coterraengineering.com
ENGINEERING PLLC
WI
L
L
O
W
C
R
E
S
T
T
O
W
N
H
O
M
E
S
I
I
MA
S
T
E
R
S
I
T
E
P
L
A
N
R
E
V
I
E
W
PR
:
LU
A
:
C:
C3.1
IN COMPLIANCE WITH CITY OF RENTON STANDARDS
EDMONDS AVE NE, RENTON, WA
WILLOWCREST TOWNHOMES IIcoterra
6413 Phinney Ave North
Seattle, Washington 98103
ph 206.596.7115
coterraengineering.com
ENGINEERING PLLC
WI
L
L
O
W
C
R
E
S
T
T
O
W
N
H
O
M
E
S
I
I
MA
S
T
E
R
S
I
T
E
P
L
A
N
R
E
V
I
E
W
PR
:
LU
A
:
C:
C4.0
Appendix B
Flow Control/Detention Calculations
Basin B - ExistingBasin B - Existing
EX CP
Basin A - Proposed
Basin B - Proposed
Basin A - Detention Pipe
PR CP
Detention Pipe Volume Calculator
Blue Indicates Data Entry Cells, the rest are calculated.
Storage Volume Provided by Horizontal Pipe of Diameter d
Pipe Diameter (d)6.0 ft
Pipe Length 300 ft
Overflow Elevation:296.00 ft
Pond Volume at Overflow (cu ft):8482
Target Volume from MGSFlood:700
Note: Volume is increased by 1 for Elevations Greater than Pipe Diameter
Pond Volume Table Because Routing Routine Requires Increasing Pond Volume
Circular Section Geometry Read from CircularSections Tab *** Copy Table below to MGSFlood Program Elevation Volume Input Screen
elev.Wetted Area storage storage DON'T INCLUDE THE COLUMN HEADINGS!
ft y/d s.f.cu.ft.(ac.ft)ELEV (FT)Top Area (Dummy)VOLUME (CU FT)
290.00 0.000 0.000 0 0 290.00 10.0 0.0.
290.20 0.030 0.248 75 0.002 290.20 10.1 74.5.
290.40 0.070 0.871 261 0.006 290.40 10.2 261.4.
290.60 0.100 1.472 442 0.010 290.60 10.3 441.7.
290.80 0.130 2.160 648 0.015 290.80 10.4 648.0.
291.00 0.170 3.186 956 0.022 291.00 10.5 955.8.
291.20 0.200 4.025 1207 0.028 291.20 10.6 1207.4.
291.40 0.230 4.914 1474 0.034 291.40 10.7 1474.2.
291.60 0.270 6.160 1848 0.042 291.60 10.8 1847.9.
291.80 0.300 7.135 2141 0.049 291.80 10.9 2140.6.
292.00 0.330 8.136 2441 0.056 292.00 11.0 2440.8.
292.20 0.370 9.511 2853 0.066 292.20 11.1 2853.4.
292.40 0.400 10.562 3169 0.073 292.40 11.2 3168.7.
292.60 0.430 11.624 3487 0.080 292.60 11.3 3487.3.
292.80 0.470 13.057 3917 0.090 292.80 11.4 3917.2.
293.00 0.500 14.137 4241 0.097 293.00 11.5 4241.2.
293.20 0.530 15.217 4565 0.105 293.20 11.6 4565.2.
293.40 0.570 16.650 4995 0.115 293.40 11.7 4995.0.
293.60 0.600 17.712 5314 0.122 293.60 11.8 5313.6.
293.80 0.630 18.763 5629 0.129 293.80 11.9 5629.0.
294.00 0.670 20.138 6042 0.139 294.00 12.0 6041.5.
294.20 0.700 21.139 6342 0.146 294.20 12.1 6341.8.
294.40 0.730 22.115 6634 0.152 294.40 12.2 6634.4.
294.60 0.770 23.360 7008 0.161 294.60 12.3 7008.1.
294.80 0.800 24.250 7275 0.167 294.80 12.4 7274.9.
295.00 0.830 25.088 7527 0.173 295.00 12.5 7526.5.
295.20 0.870 26.114 7834 0.180 295.20 12.6 7834.3.
295.40 0.900 26.802 8041 0.185 295.40 12.7 8040.6.
295.60 0.930 27.403 8221 0.189 295.60 12.8 8221.0.
295.80 0.970 28.026 8408 0.193 295.80 12.9 8407.8.
296.00 1.000 28.274 8482 0.195 296.00 13.0 8482.3.
12/18/2024 PondPipePH2.xls
—————————————————————————————————
MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.63
Program License Number: 201510001
Project Simulation Performed on: 12/18/2024 11:00 AM
Report Generation Date: 12/18/2024 11:00 AM
—————————————————————————————————
Input File Name: Willowcrest PH 2- Prelim Sizing - Landuse.fld
Project Name: Renton - Willowcrest Phase II
Analysis Title: Peak Flow - Detention
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Full Period of Record Available used for Routing
Climatic Region Number: 15
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 3
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 1.044 1.044
Area of Links that Include Precip/Evap (acres) 0.000 0.000
Total (acres) 1.044 1.044
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 2
---------- Subbasin : Basin B - Existing ----------
-------Area (Acres) --------
Till Forest 0.224
Till Pasture 0.671
ROADS/FLAT 0.025
----------------------------------------------
Subbasin Total 0.920
---------- Subbasin : Basin B - Existing ----------
-------Area (Acres) --------
Till Forest 0.020
Till Pasture 0.059
ROADS/FLAT 0.046
----------------------------------------------
Subbasin Total 0.124
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 2
---------- Subbasin : Basin A - Proposed ----------
-------Area (Acres) --------
Till Grass 0.248
ROADS/FLAT 0.672
----------------------------------------------
Subbasin Total 0.920
---------- Subbasin : Basin B - Proposed ----------
-------Area (Acres) --------
Till Grass 0.078
ROADS/FLAT 0.046
----------------------------------------------
Subbasin Total 0.124
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: EX CP
Link Type: Copy
Downstream Link: None
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 2
------------------------------------------
Link Name: Basin A - Detention Pipe
Link Type: Structure
Downstream Link Name: PR CP
User Specified Elevation Volume Table Used
Elevation (ft) Pond Volume (cu-ft)
290.00 0.
290.20 75.
290.40 261.
290.60 442.
290.80 648.
291.00 956.
291.20 1207.
291.40 1474.
291.60 1848.
291.80 2141.
292.00 2441.
292.20 2853.
292.40 3169.
292.60 3487.
292.80 3917.
293.00 4241.
293.20 4565.
293.40 4995.
293.60 5314.
293.80 5629.
294.00 6042.
294.20 6342.
294.40 6634.
294.60 7008.
294.80 7275.
295.00 7527.
295.20 7834.
295.40 8041.
295.60 8221.
295.80 8408.
296.00 8482.
Hydraulic Conductivity (in/hr) : 0.00
Massmann Regression Used to Estimate Hydralic Gradient
Depth to Water Table (ft) : 100.00
Bio-Fouling Potential : Low
Maintenance : Average or Better
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 8.00
Common Length (ft) : 0.000
Riser Crest Elevation : 296.00 ft
Hydraulic Structure Geometry
Number of Devices: 3
---Device Number 1 ---
Device Type : Circular Orifice
Control Elevation (ft) : 290.50
Diameter (in) : 0.86
Orientation : Horizontal
Elbow : No
---Device Number 2 ---
Device Type : Circular Orifice
Control Elevation (ft) : 293.00
Diameter (in) : 1.40
Orientation : Horizontal
Elbow : Yes
---Device Number 3 ---
Device Type : Circular Orifice
Control Elevation (ft) : 294.50
Diameter (in) : 4.00
Orientation : Horizontal
Elbow : Yes
------------------------------------------
Link Name: PR CP
Link Type: Copy
Downstream Link: None
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 2
Number of Links: 1
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 2
Number of Links: 2
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin B - Existing 156.800
Subbasin: Basin B - Existing 13.665
Link: EX CP 0.000
_____________________________________
Total: 170.465
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Basin A - Proposed 30.308
Subbasin: Basin B - Proposed 9.545
Link: Basin A - Detention Not Computed
Link: PR CP 0.000
_____________________________________
Total: 39.853
Total Predevelopment Recharge is Greater than Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 1.079 ac-ft/year, Post Developed: 0.252 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
********** Link: EX CP **********
2-Year Discharge Rate : 0.052 cfs
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.02 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.01 cfs
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 160.73
Inflow Volume Including PPT-Evap (ac-ft): 160.73
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 160.73
Secondary Outflow To Downstream System (ac-ft): 0.00
Volume Lost to ET (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered+ET)/Total Volume: 0.00%
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 2
********** Link: PR CP **********
2-Year Discharge Rate : 0.047 cfs
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.03 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.02 cfs
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 387.67
Inflow Volume Including PPT-Evap (ac-ft): 387.67
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 387.67
Secondary Outflow To Downstream System (ac-ft): 0.00
Volume Lost to ET (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered+ET)/Total Volume: 0.00%
***********Compliance Point Results *************
Scenario Predeveloped Compliance Link: EX CP
Scenario Postdeveloped Compliance Link: PR CP
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 5.164E-02 2-Year 4.736E-02
5-Year 8.178E-02 5-Year 7.153E-02
10-Year 0.113 10-Year 8.836E-02
25-Year 0.188 25-Year 0.108
50-Year 0.270 50-Year 0.118
100-Year 0.331 100-Year 0.127
200-Year 0.336 200-Year 0.222
500-Year 0.340 500-Year 0.349
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
Appendix C
Water Quality Calculation
—————————————————————————————————
MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.63
Program License Number: 201510001
Project Simulation Performed on: 12/10/2024 3:16 PM
Report Generation Date: 12/10/2024 3:22 PM
—————————————————————————————————
Input File Name: Willowcrest - PH 2 WQ Bioretention.fld
Project Name: Renton Homestead - Willowcrest Townhomes
Analysis Title: Water Quality - Bioretention Cell - PH2
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Full Period of Record Available used for Routing
Climatic Region Number: 15
Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 3
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 0.331 0.328
Area of Links that Include Precip/Evap (acres) 0.000 0.003
Total (acres) 0.331 0.331
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : WQ BASIN ----------
-------Area (Acres) --------
ROADS/FLAT 0.331
----------------------------------------------
Subbasin Total 0.331
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
---------- Subbasin : PH 2 WQ BASIN ----------
-------Area (Acres) --------
ROADS/FLAT 0.328
----------------------------------------------
Subbasin Total 0.328
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: New Ecy Bio Lnk1
Link Type: Ecology Bioretention Facility
Downstream Link: None
Floor Elevation (ft) : 100.00
Riser Crest Elevation (ft) : 101.00
Storage Depth (ft) : 1.00
Bottom Length (ft) : 10.0
Bottom Width (ft) : 12.0
Bottom Slope (ft/ft) : 0.000
Side Slopes (ft/ft) : Z1= 0.00 Z2= 0.00 Z3= 0.00 Z4= 0.00
Bottom Area (sq-ft) : 120.
Area at Riser Crest El (sq-ft) : 120.
(acres) : 0.003
Volume at Riser Crest (cu-ft): 120.
(ac-ft) : 0.003
Infiltration on Bottom only Selected
Soil Properties
Layer No Soil Name Thickness (ft)
1 ASTM 100 0.250
2 SMMWW 12 in/hr (Ecol 1.500
3 GRAVEL 1.500
KSat Safety Factor: None
Native Soil Infiltration Rate (in/hr) : 0.00
Underdrain Present
Underdrain Offset (in): : 6.00
Orifice Diameter (in) : 4.000
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 6.00
Common Length (ft) : 0.000
Riser Crest Elevation : 101.00 ft
Hydraulic Structure Geometry
Number of Devices: 0
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1
Number of Links: 1
********** Link: New Ecy Bio Lnk1 ********** Link WSEL Stats
WSEL Frequency Data(ft)
(Recurrence Interval Computed Using Gringorten Plotting Position)
Tr (yrs) WSEL Peak (ft)
======================================
1.05-Year 100.656
1.11-Year 100.820
1.25-Year 100.981
2.00-Year 101.041
3.33-Year 101.056
5-Year 101.065
10-Year 101.077
25-Year 101.100
50-Year 101.121
100-Year 101.142
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: WQ BASIN 0.000
_____________________________________
Total: 0.000
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: PH 2 WQ BASIN 0.000
Link: New Ecy Bio Lnk1 0.000
_____________________________________
Total: 0.000
Total Predevelopment Recharge Equals Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.000 ac-ft/year, Post Developed: 0.000 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 0
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 1
********** Link: New Ecy Bio Lnk1 **********
Basic Wet Pond Volume (91% Exceedance): 1453. cu-ft
Computed Large Wet Pond Volume, 1.5*Basic Volume: 2179. cu-ft
2-Year Discharge Rate : 0.107 cfs
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.05 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.03 cfs
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 147.06
Inflow Volume Including PPT-Evap (ac-ft): 147.53
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 146.25, 99.13%
Primary Outflow To Downstream System (ac-ft): 147.06
Secondary Outflow To Downstream System (ac-ft): 0.00
Volume Lost to ET (ac-ft): 0.47
Percent Treated (Infiltrated+Filtered+ET)/Total Volume: 99.45%
***********Compliance Point Results *************
Scenario Predeveloped Compliance Subbasin: WQ BASIN
Scenario Postdeveloped Compliance Link: New Ecy Bio Lnk1
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 0.123 2-Year 0.107
5-Year 0.160 5-Year 0.150
10-Year 0.180 10-Year 0.173
25-Year 0.227 25-Year 0.223
50-Year 0.289 50-Year 0.270
100-Year 0.334 100-Year 0.310
200-Year 0.346 200-Year 0.342
500-Year 0.362 500-Year 0.384
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
Appendix D
Geotechnical Report
Geotechnical Engineering Services
Willowcrest Townhomes Phase II
Renton, Washington
for
Homestead Community Land Trust
November 18, 2024
17425 NE Union Hill Road, Suite 250
Redmond, Washington 98052
425.861.6000
Geotechnical Engineering Services
Willowcrest Townhomes Phase II
Renton, Washington
File No. 23656-001-01
November 18, 2024
Prepared for:
Homestead Community Land Trust
412 Maynard Avenue South, Suite 201
Seattle, Washington 98104
Attention: Eric Pravitz
Prepared by:
GeoEngineers, Inc.
17425 NE Union Hill Road, Suite 250
Redmond, Washington 98052
425.861.6000
Colton W. McInelly, PE
Senior Geotechnical Engineer
Robert C. Metcalfe, PE, LEG
Principal
CWM:RCM:tlm:atk
Disclaimer: Any electronic form, facsimile, or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy
of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record.
Homestead Community Land Trust | November 18, 2024 i
File No. 23656-001-01
Table of Contents
1.0 Introduction .................................................................................................................. 1
1.1 Project Description ........................................................................................................................ 1
1.2 Purpose and Scope ....................................................................................................................... 1
2.0 Field Explorations and Laboratory Testing ...................................................................... 1
2.1 Explorations ................................................................................................................................... 1
2.2 Laboratory Testing ........................................................................................................................ 1
2.3 Previous Explorations ................................................................................................................... 2
3.0 Site Description ............................................................................................................ 2
3.1 Surface Conditions........................................................................................................................ 2
3.2 Site Geology .................................................................................................................................. 2
3.3 Geologic Hazards .......................................................................................................................... 3
3.4 Subsurface Conditions ................................................................................................................. 3
3.4.1 Soil Conditions ................................................................................................................... 3
3.4.2 Groundwater Conditions ................................................................................................... 3
4.0 Conclusions and Recommendations .............................................................................. 4
4.1 Environmentally Critical Areas ..................................................................................................... 4
4.1.1 Landslide Hazard ECA ....................................................................................................... 5
4.1.2 Regulated (Steep) Slope Hazard ECA ............................................................................... 5
4.1.3 Alterations to ECAs ............................................................................................................ 5
4.2 Earthquake Engineering ............................................................................................................... 6
4.2.1 Seismicity ........................................................................................................................... 6
4.2.2 2021 IBC Seismic Design Information ............................................................................. 7
4.2.3 Liquefaction Potential ....................................................................................................... 7
4.2.4 Ground Rupture ................................................................................................................. 7
4.2.5 Landslides .......................................................................................................................... 7
4.3 Temporary Dewatering ................................................................................................................. 8
4.4 Excavation Support ....................................................................................................................... 8
4.4.1 Excavation Considerations ................................................................................................ 9
4.4.2 Temporary Cut Slopes ....................................................................................................... 9
4.4.3 Soldier Pile and Tieback Walls ........................................................................................ 10
4.4.4 Soil Nail Walls .................................................................................................................. 12
4.4.5 Shoring Wall Performance .............................................................................................. 15
4.5 Shallow Foundations .................................................................................................................. 15
4.5.1 Allowable Bearing Pressures .......................................................................................... 16
4.5.2 Settlement ....................................................................................................................... 16
4.5.3 Lateral Resistance ........................................................................................................... 17
4.5.4 Footing Drains ................................................................................................................. 17
4.5.5 Construction Considerations .......................................................................................... 17
Homestead Community Land Trust | November 18, 2024 ii
4.6 Slab-on-Grade Floors .................................................................................................................. 18
4.6.1 Subgrade Preparation ..................................................................................................... 18
4.6.2 Design Parameters .......................................................................................................... 18
4.6.3 Underslab Drainage ......................................................................................................... 18
4.7 Below-Grade Walls and Retaining Walls .................................................................................... 19
4.7.1 Permanent Subsurface Walls Against Temporary Shoring ........................................... 19
4.7.2 Other Cast-in-Place Walls ................................................................................................ 19
4.7.3 Wall Drainage .................................................................................................................. 20
4.8 Earthwork .................................................................................................................................... 21
4.8.1 Clearing and Site Preparation ......................................................................................... 21
4.8.2 Earthwork Subgrade Preparation ................................................................................... 22
4.8.3 Structural Fill.................................................................................................................... 22
4.8.4 Fill Placement and Compaction Criteria ......................................................................... 23
4.8.5 Weather Considerations ................................................................................................. 24
4.8.6 Utility Trenches ................................................................................................................ 25
4.8.7 Pavement Subgrade Preparation ................................................................................... 25
4.8.8 Permanent Slopes ........................................................................................................... 25
4.8.9 Sedimentation and Erosion Control ............................................................................... 26
4.9 Pavement Recommendations .................................................................................................... 26
4.9.1 Subgrade Preparation ..................................................................................................... 26
4.9.2 New Hot-Mix Asphalt Pavement ..................................................................................... 26
4.9.3 Portland Cement Concrete Pavement ............................................................................ 27
4.10 Drainage Considerations ............................................................................................................ 27
4.11 Infiltration Considerations .......................................................................................................... 27
5.0 Recommended Additional Geotechnical Services ......................................................... 28
6.0 Limitations .................................................................................................................. 28
7.0 References .................................................................................................................. 29
List of Figures
Figure 1. Vicinity Map
Figure 2. Site Plan
Figure 3. Earth Pressure Diagrams – Temporary Soldier Pile & Tieback Wall
Figure 4. Recommended Surcharge Pressure
Figure 5. Wall Drainage and Backfill
Figure 6. Compaction Criteria for Trench Backfill
File No. 23656-001-01
Homestead Community Land Trust | November 18, 2024 iii
File No. 23656-001-01
Appendices
Appendix A. Field Explorations
Figure A-1 – Key to Exploration Logs
Figures A-2 through A-7 – Logs of Test Pits
Appendix B. Laboratory Testing
Figure B-1 – Sieve Analysis Results
Appendix C. Exploration Logs from Previous Studies
Appendix D. Ground Anchor Load Tests and Shoring Monitoring Program
Appendix E. Report Limitations and Guidelines for Use
Homestead Community Land Trust | November 18, 2024 Page 1
File No. 23656-001-01
1.0 Introduction
This geotechnical engineering report presents the results of GeoEngineers, Inc.’s (GeoEngineers’)
geotechnical engineering services to support design and construction of the Willowcrest Townhomes
Phase II project located in Renton, Washington. The proposed project site is shown relative to surrounding
physical features in Figure 1, Vicinity Map and Figure 2, Site Plan.
1.1 PROJECT DESCRIPTION
GeoEngineers previously provided geotechnical engineering services during design and construction for
Phase I of the project, which is located directly east of Phase II. Our understanding of Phase II is based on
conversations with, and information provided by Caitlyn Salters with Third Place Design Co-operative Inc.
We understand the project consists of constructing five 3- to 4-unit wood-frame townhomes (Buildings A
through E) that will be three stories in height. Buildings A through C will be constructed close to existing
grades, while Buildings D and E may be cut into the hillside and may be below-grade on the east side and
daylight on the west side of the buildings. A large retaining wall will replace the existing rockery on the west
side of the site along Edmonds Avenue NE, and a retaining wall may be required along the north/northeast
side of the site. Associated improvements include a subsurface stormwater detention facility near the
southwest corner of the site, new underground utilities and access drive, sidewalks, parking area and
landscaping.
1.2 PURPOSE AND SCOPE
The purpose of our services is to evaluate soil and groundwater conditions as a basis for developing design
criteria for the geotechnical aspects of the project. Field explorations and laboratory testing were performed
to characterize subsurface conditions and to develop engineering recommendations for use in the design of
the project. Our services were performed in general accordance with our proposal dated October 11, 2024.
2.0 Field Explorations and Laboratory Testing
2.1 EXPLORATIONS
The subsurface soil and groundwater conditions were evaluated through a field exploration program that
consisted of excavating and sampling six test pits (GEI-TP-7 through GEI-TP-12). The test pits were
completed using a small track-mounted excavator at the approximate locations shown in Figure 2. The test
pits were excavated to depths ranging from 7½ to 10½ feet below the ground surface (bgs). Locations of
the test pits were determined in the field by measuring from physical features on site to the test pit
locations. Test pits GEI-TP-1 through GEI-TP-6 were completed during Phase 1. Appendix A includes the logs
of the test pits and details of the subsurface exploration program.
2.2 LABORATORY TESTING
Soil samples obtained from the test pits were transported to our laboratory and evaluated to confirm or
modify field classifications, as well as to evaluate engineering properties of the soil. Representative
samples were selected for laboratory testing consisting of moisture content and grain size distribution
(sieve analysis). The tests were performed in general accordance with test methods of the American Society
for Testing and Materials (ASTM) and other applicable procedures. A description of the laboratory testing
and the test results are presented in Appendix B.
Homestead Community Land Trust | November 18, 2024 Page 2
File No. 23656-001-01
2.3 PREVIOUS EXPLORATIONS
GeoEngineers previously provided geotechnical engineering services during Phase I of the project, which
included completing six test pits (GEI-TP-1 through GEI-TP-6) in the Phase I area. Additionally, test pits and
borings were completed by others in the Phase I and Phase II areas. The logs of selected explorations from
these previous studies were reviewed. Logs of relevant explorations reviewed for this study are presented
in Appendix C and the approximate locations of the previous explorations are shown in Figure 2.
3.0 Site Description
3.1 SURFACE CONDITIONS
The subject property is approximately 0.92 acres and consists of one King County Parcel (number
943280-0130). The site is currently occupied by a gravel surfaced parking/storage area near the middle
and a driveway off Edmonds Avenue NE that leads up to the gravel surfaced parking/storage area. The
remainder of the site is vegetated with medium to large deciduous and coniferous trees, blackberry bushes,
shrubs, ivy and other brush and grasses. Steep slopes are mapped by the City of Renton on the west side
of the parcel and are associated with a cut slope used to construct Edmonds Avenue NE. A rockery was
built along the cut slope.
Site grades descend moderately to the west/southwest from about Elevation 330 feet on the east side to
about Elevation 315 to 320 feet on the west side. Slope inclinations become steeper near the west property
line as they approach the rockery along the east side of the street. The rockery is generally about 10 feet
tall and borders the entire west side of the site, except near the driveway entrance.
Underground utilities consisting of storm drain and sanitary sewer associated with the Phase I townhome
development exist on the east side and in a 15-foot-wide sewer easement on the southern border of the
site. Power, gas, water, sewer and storm utilities are located under Edmonds Avenue NE.
3.2 SITE GEOLOGY
Published geologic information for the project vicinity includes a United States Geological Survey (USGS)
map of Seattle and the surrounding area (Mullineaux et al. 1961). Mapped units in the immediate project
vicinity consist of glacially consolidated Vashon Till deposits (glacial till). Recessional outwash is mapped
west of the site.
■ Glacial till is generally a non-sorted, non-stratified mixture of sand, gravel and silt that has been
overridden by over a thousand feet of ice. It typically has high shear strength, low consolidation and
low permeability characteristics in the undisturbed state. It typically develops a “weathered” zone
where seasonal groundwater perches on top of the relatively unweathered till and the perched
groundwater occurs as seepage following the site topography.
■ Recessional outwash is predominantly composed of stratified sand and gravel that was deposited in
meltwater streams that emanated from the terminus of the Vashon glacier as it receded northward. It
typically has low shear strength and moderate to high permeability characteristics.
Homestead Community Land Trust | November 18, 2024 Page 3
File No. 23656-001-01
Subsurface conditions encountered in the recent and existing explorations completed at the site are
consistent with the mapped glacial till unit.
3.3 GEOLOGIC HAZARDS
Our assessment of the geologic hazards at the site includes reviewing the environmentally critical area
(ECA) geographic information system (GIS) maps defined by the City of Renton and King County. These
maps identify the site for ECAs. The City of Renton identifies landslide and regulated slope hazards along
the west side of the site. King County does not identify any ECAs at the site. Further discussion on these
ECAs is presented in Section 4.1.
3.4 SUBSURFACE CONDITIONS
3.4.1 Soil Conditions
GeoEngineers’ understanding of the subsurface soil conditions is based on review of existing geotechnical
data as well as the results of our recent test pits. Figure 2 shows the approximate locations of the existing
and recent explorations completed at and within the vicinity of the site. The general subsurface conditions
consist of topsoil and fill overlying native glacial till. The subsurface conditions are summarized below:
■ Topsoil/Sod about ½ to 1½ feet thick was observed in most of the explorations and consists of silty
sand with roots.
■ Fill was encountered below the topsoil or ground surface in test pits GEI-TP-9, -10, and -12 and extends
to approximately 2 to 5 feet below the ground surface. The fill is loose to medium dense and generally
consists of silty sand with gravel and variable organic content. Fill observed at the surface of test pit
GEI-TP-10 consists of gravel with silt and sand and is associated with the gravel surfaced
parking/storage area in that area of the site. Construction debris (concrete, fabric and plastic) as well
as scattered organics were observed within the fill.
■ Weathered Glacial Till generally consisting of loose to dense silty sand with variable gravel content
was observed within most of the explorations. The weathered glacial till ranges from about 1½ to
6½ feet thick and it is often difficult to distinguish the looser weathered glacial till from the overlying
fill.
■ Glacial Till was observed below the fill/weathered glacial till and extends to the depths explored in the
explorations. The glacial till is relatively unweathered and generally consists of dense to very dense silty
sand with variable gravel content and very stiff to hard silt with variable sand content. The top of the
glacial till was observed at depths ranging from 2½ to 8 feet below existing site grades.
Cobbles and boulders were observed in some of the explorations and are commonly present in glacial
deposits.
3.4.2 Groundwater Conditions
Regional groundwater was not encountered in the explorations; however, shallow groundwater seepage
interpreted as perched groundwater was observed in several of the explorations at various depths. Based
on our experience in the project vicinity, the regional groundwater table is much deeper than planned
excavations for the project and therefore will not be encountered. However, perched groundwater and
seepage zones should be expected in the fill, weathered glacial till and relatively permeable layers of the
glacial till and perched above the relatively unweathered glacial till.
Homestead Community Land Trust | November 18, 2024 Page 4
File No. 23656-001-01
4.0 Conclusions and Recommendations
Based on the results of our review, our recently completed explorations and our experience on similar
projects, we conclude that the proposed development can be constructed satisfactorily as planned with
respect to geotechnical engineering elements. A summary of the key geotechnical considerations is
provided below. The summary is presented for introductory purposes only and should be used in
conjunction with the complete recommendations presented in this report.
■ The west side of the site is mapped as steep slope and potential slide area ECAs based on the City of
Renton GIS maps accessed online. There are development restrictions associated with these ECAs;
however, an exemption should be allowed as the ECAs are associated with past legal grading activities
during the construction of Edmonds Avenue NE.
■ The site is classified as Site Class C in accordance with the 2021 International Building Code (IBC).
■ Temporary excavations may employ temporary cut slopes or shoring consisting of soldier piles with
wood lagging or soil nail walls.
■ Shallow foundations can be constructed on the glacial till. A maximum allowable bearing pressure of
6,000 pounds per square foot (psf) may be used for footings bearing on native undisturbed dense to
very dense/very stiff to hard glacial till. An allowable bearing pressure of 3,000 psf may be used for
footings bearing on native undisturbed medium dense to dense weathered glacial till or where
structural fill is placed below footings, if needed, that extend to undisturbed and suitable medium
dense to dense glacial till. Existing fill, highly weathered glacial till or otherwise unsuitable soils should
be removed from below foundations and floor slabs prior to constructing foundations or placing
structural fill.
■ Conventional slabs-on-grade are considered appropriate and should be underlain by a 4-inch-thick layer
of capillary break consisting of clean crushed rock with negligible fines and sand content.
■ Below-grade walls and retaining structures should be evaluated using an equivalent fluid density of
35 pounds per cubic foot (pcf) provided there is a horizontal surface behind the top of the walls and
that the walls will not be restrained against rotation when backfill is placed behind them. If the walls
will be restrained from rotation, we recommend using an equivalent fluid density of 55 pcf.
■ The on-site soils generally contain a high percentage of fines (silt and clay) ranging generally from 25
to 35 percent based on laboratory tests and are highly moisture sensitive. Therefore, reuse of on-site
soils should only be planned in the normal dry season (June through September).
■ We anticipate long-term design infiltration rates will be less than 0.2 inches per hour within the native
glacial till. On-site pilot infiltration testing will be needed if infiltration facilities are being considered as
part of the project.
4.1 ENVIRONMENTALLY CRITICAL AREAS
Based on our review of the City of Renton and King County ECA GIS maps, the City of Renton identifies
landslide and regulated slope hazards on the west edge of the site. No ECAs were shown on the King County
maps.
Homestead Community Land Trust | November 18, 2024 Page 5
File No. 23656-001-01
4.1.1 Landslide Hazard ECA
The City of Renton categorizes landslide hazards into unclassified, moderate, high and very high landslide
hazards. Based on the City of Renton GIS map, the west/southwest side of the site are identified as
moderate and high landslide hazards. According to RMC 4-3-050G.5.b:
■ Moderate landslide hazards are “areas with slopes between fifteen percent and forty percent and
underlain by soils that consist largely of sand, gravel or glacial till.”
■ High landslide hazards are “areas with slopes greater than forty percent, and areas with slopes
between fifteen percent and forty percent and underlain by soils consisting largely of silt and clay.”
Per RMC 4-3-050.G.2, moderate and high landslide hazards do not have a critical area buffer and there is
no structure setback required beyond the buffer. However, the critical area buffer is “based upon the results
of a geotechnical report and/or independent review, conditions of approval for developments may include
buffers and/or setbacks from buffers” and the structure setback beyond the buffer is subject to
“the adopted building code or Building Official.”
4.1.2 Regulated (Steep) Slope Hazard ECA
The City of Renton categorizes regulated (steep) slope hazards into sensitive and protected slope types.
Based on the City of Renton GIS map, the west edge of the site is identified as sensitive and protected
slopes. According to RMC 4-3-050G.5.a:
■ Sensitive slopes are defined as “a hillside or portion thereof characterized by: (a) an average slope of
twenty five percent to less than forty percent as identified by the City of Renton Steep Slope Atlas or in
a method approved by the City; or (b) an average slope of forty percent or greater with vertical rise of
less than fifteen feet as identified in the City of Renton Steep Slope Atlas or in a method approved by
the City; (c) abutting an average slope of twenty five percent to forty percent as identified in the City of
Renton Steep Slope Atlas or in a method approved by the City.”
■ Protected slopes are defined as “a hillside or portion thereof characterized by an average slope of forty
percent or greater grade having a minimum vertical rise of fifteen feet as identified in the City of Renton
Steep Slope Atlas or in a method approved by the City.”
Per RMC 4-3-050G.2, sensitive and protected slopes do not have a critical area buffer associated with
them. Sensitive slopes do not have a structure setback required beyond the buffer, while protected slopes
have a 15-foot structure setback required beyond the buffer. However, the critical area buffer is “based
upon the results of a geotechnical report and/or independent review, conditions of approval for
developments may include buffers and/or setbacks from buffers” and the structure setback beyond the
buffer is subject to “the adopted building code or Building Official.”
4.1.3 Alterations to ECAs
Per RMC 4-3-050J.1.a.i, an applicant may request the administrator grant a modification to allow “regrading
of any slope which was created through previous mineral and natural resource recovery activities or was
created prior to adoption of applicable mineral and natural resource recover regulations or through public
or private road installation or widening and related transportation improvements, railroad track installation
or improvement, or public or private utility installation activities.”
Homestead Community Land Trust | November 18, 2024 Page 6
File No. 23656-001-01
Based on our review of the ECA map and our understanding of the site, construction of Edmonds Avenue NE
roadway created cut slope conditions along the east side of the road (west side of the site) in which
rockeries were used to face the steep cut slope. Based on just mapping tools, the cut for the roadway and
existing rockery can be interpreted as landslide hazard/steep slope conditions, although this was a
permitted man-made cut slope. Therefore, the existing rockeries along the east side of Edmonds Avenue NE
that border the west side of the project were designed and permitted through the City of Renton as part of
the roadway extension.
Subsurface conditions present across the site consist of shallow fill underlain by competent glacial till. The
roadway extension (cut) likely removed fill soils during construction such that the rockery was excavated in
competent glacial till. In our opinion, the mapped steep slope is a permitted man-made stable cut and is
likely a very low landslide hazard risk. Provided that the contractor completing the construction work uses
construction practices consistent with local and state regulations, and the recommendations provided in
this report, GeoEngineers takes no exception to the planned work along the west edge of the site as they
relate to encroaching within the mapped landslide hazard and regulated (steep) slope hazard ECAs.
GeoEngineers should be on site during construction to provide construction observation services during
earthwork activities.
4.2 EARTHQUAKE ENGINEERING
4.2.1 Seismicity
The Puget Sound area is located near the convergent continental boundary known as the Cascadia
Subduction Zone (CSZ), which extends from mid-Vancouver Island to Northern California. The CSZ is the
zone where the westward advancing North American Plate is overriding the subducting Juan de Fuca Plate.
The interaction of these two plates results in two potential seismic source zones: (1) the Benioff source
zone and (2) the CSZ interplate source zone. A third seismic source zone, referred to as the shallow crustal
source zone, is associated with the north-south compression resulting from northerly movement of the
Sierra Nevada block of the North American Plate.
Shallow crustal earthquakes occur within the North American Plate to depths up to 15 miles. Shallow
earthquakes in the Puget Sound region are expected to have durations ranging up to 60 seconds.
Four magnitude 7 or greater-known shallow crustal earthquakes have occurred in the last 1,100 years in
the Cascadia region; two of these occurred on Vancouver Island and two in Western Washington.
The southeast end of the east-west trending Seattle fault zone is mapped approximately 1½ miles north of
the site.
The Benioff zone is characterized as being capable of generating earthquakes up to magnitude (M) 7.5.
The Olympia 1949 (M = 7.1), the Seattle 1965 (M = 6.5) and the Nisqually 2001 (M = 6.8) earthquakes
are considered to be Benioff zone earthquakes. The recurrence interval for large earthquakes originating
from the Benioff source zone is believed to be shorter than for the shallow crustal and CSZ source zones;
on average, damaging Benioff zone earthquakes in Western Washington occur every 30 years or so.
The CSZ is considered as being capable of generating earthquakes of magnitudes 8 to 9. No earthquakes
on the CSZ have been instrumentally recorded; however, through the geologic record and historical records
of tsunamis in Japan, it is believed that the most recent CSZ event occurred in the year 1700. Recurrence
intervals for CSZ interplate earthquakes are thought to be on the order of 400 to 600 years.
Homestead Community Land Trust | November 18, 2024 Page 7
File No. 23656-001-01
4.2.2 2021 IBC Seismic Design Information
For the site, we recommend the 2021 IBC parameters for Site Class C, mapped risk-targeted
maximum-considered earthquake (MCER) spectral response acceleration at short period (Ss), mapped
MCER spectral response acceleration at 1-second period (S1), short period site coefficient (Fa), long period
site coefficient (Fv), design spectral acceleration at 0.2-second period (SDS) and the design spectral
acceleration at 1.0-second period (SD1). Table 1 summarizes recommended values for these parameters.
TABLE 1. 2021 IBC SEISMIC PARAMETERS
2018 IBC PARAMETER1 RECOMMENDED VALUE
Site Class C
Mapped MCER Spectral Response Acceleration at Short Period, Ss (g) 1.432
Mapped MCER Spectral Response Acceleration at 1-second period, S1 (g) 0.49
Short Period Site Coefficient, Fa 1.2
Long Period Site Coefficient, Fv 1.5
Design Spectral Acceleration at 0.2-second period, SDS (g) 1.146
Design Spectral Acceleration at 1.0-second period, SD1 (g) 0.49
Notes:
1 Parameters developed based on latitude 47.5019 and longitude -122.1851 using the Applied Technology Council (ATC) Hazards
online tool (https://hazards.atcouncil.org/).
4.2.3 Liquefaction Potential
Liquefaction is a phenomenon where soils experience a rapid loss of internal strength as a consequence
of strong ground shaking. Ground settlement, lateral spreading and/or sand boils may result from soil
liquefaction. Structures supported on liquefied soils could suffer foundation settlement or lateral
movement that could be severely damaging to the structures.
Conditions favorable to liquefaction occur in loose to medium dense, clean to moderately silty sand, which
is below the groundwater level. Based on our evaluation of the subsurface conditions observed in the
explorations, it is our opinion that potentially liquefiable soils are not present at the project site.
4.2.4 Ground Rupture
Ground rupture from lateral spreading is associated with liquefaction. Lateral spreading involves lateral
displacements of large volumes of liquefied soil, and can occur on near-level ground as blocks of surface
soils displace relative to adjacent blocks. In our opinion, ground rupture resulting from lateral spreading at
the site is unlikely because potentially liquefiable soils are not present at the site as discussed above.
Because of the thickness of the Quaternary sediments below the site, which are commonly more than
1,000 feet thick, the potential for surface fault rupture is considered low.
4.2.5 Landslides
As discussed in Sections 3.3 and 4.1, steep slopes are mapped on the west edge of the site; however, they
are associated with a rockery that was built during construction of Edmonds Avenue NE. We understand
that the existing rockery will be replaced with an engineered retaining wall. Provided the retaining wall is
designed in accordance with the recommendations of this report, it is our opinion that there will be no risk
of earthquake induced landsliding as a result of strong ground shaking.
Homestead Community Land Trust | November 18, 2024 Page 8
File No. 23656-001-01
4.3 TEMPORARY DEWATERING
Perched seepage zones should be expected in permeable layers within the shallow fill, weathered glacial
till and more permeable layers of the glacial till. We anticipate that the contractor will be able to use sumps
and pumps located within excavations for required temporary dewatering to control perched groundwater
seepage.
Sump pumping involves removing water that has seeped into an excavation by pumping from a sump that
has been excavated at one or more locations in an excavation. Drainage ditches that lead to the sump are
typically excavated along the excavation sidewalls at the base of an excavation. The excavation for the
sump and discharge drainage ditches should be backfilled with gravel or crushed rock to reduce the amount
of erosion and associated sediment in the water pumped from the sump. In our experience, a slotted casing
or perforated 55-gallon drum that is installed in the sump backfill provides suitable housing for a
submersible pump.
For planning purposes, perched groundwater flow rates of up to 5 gallons per minute (gpm) can be assumed
for site excavations. Surface water from rainfall will contribute significantly to the volume of water that
needs to be removed from the excavation during construction and will vary as a function of season and
precipitation. Disposal of soil and water pumped from excavations should be in compliance with any
environmental handling requirements for excavations in these areas.
4.4 EXCAVATION SUPPORT
Excavations will be required to replace the existing rockery on the west side of the site, to facilitate
installation of possible retaining walls on the north/northeast side of the site, to install underground utilities
and to construct Buildings D and E that may be cut into the hillside and may be below-grade on the east
side and daylight on the west side of the buildings. Subsurface conditions support the use of temporary cut
slopes where possible. Where temporary shoring is required, soldier piles and tiebacks or soil nails with
full-depth vertical elements may be used.
If soil nailing is used, the soil nail wall design should consider the upper fill and looser weathered glacial
soils, and utilities located in close proximity to the wall alignment. We recommend implementing full depth
vertical elements on soil nail shoring walls for improved deflection control, to reduce face instability and to
allow for soil nails to be located below existing utilities, as needed. Vertical elements consist of light wide
flange beams placed in drilled excavations that are backfilled full depth with lean concrete.
The City of Renton requires that shoring walls be designed to limit lateral deflections to 1 inch or less in
order to reduce the risk of damage to existing improvements. The City of Renton requires that remedial
measures be implemented when lateral deflections reach 1 inch.
An existing apartment building is located north of the site. If a retaining wall (temporary and/or permanent)
is utilized on the north edge of the site and that existing apartment building is located within a horizontal
distance equal to the height of the retaining wall, the shoring wall design earth pressures should be
increased by 1.25 to provide enhanced deformation control. This should also be considered for retaining
walls along the west side of the site adjacent to Buildings A and B.
Homestead Community Land Trust | November 18, 2024 Page 9
File No. 23656-001-01
The following sections provide design information for temporary cut slopes, soldier pile walls and soil nail
walls.
4.4.1 Excavation Considerations
The fill and glacial soils may be excavated with conventional excavation equipment, such as track hoes or
dozers. It may be necessary to rip the dense to very dense glacial till soils locally to facilitate excavation.
Cobbles and boulders typically exist within the glacial soils, and the contractor should be prepared to deal
with them. Likewise, the surficial fill may contain foundation elements and/or utilities from previous site
development, as well as debris, rubble and/or cobbles and boulders. We recommend that procedures be
identified in the project specifications for measurement and payment of work associated with obstructions.
4.4.2 Temporary Cut Slopes
For planning purposes, temporary unsupported cut slopes more than 4 feet high may be inclined at 1H:1V
(horizontal to vertical) maximum steepness within the relatively unweathered dense to very dense glacial
till soils. Temporary cuts within the fill and loose to medium dense weathered glacial till deposits may be
cut at a maximum inclination of 1½H:1V. If significant seepage is present on the cut face, then the cut
slopes may have to be flattened. However, temporary cuts should be discussed with the geotechnical
engineer during final design development to evaluate suitable cut slope inclinations for the various portions
of the excavation.
The above guidelines assume that surface loads such as traffic, construction equipment, stockpiles or
building supplies will be kept away from the top of the cut slopes a sufficient distance so that the stability
of the excavation is not affected. We recommend that this distance be at least 5 feet from the top of the
cut for temporary cuts made at 1H:1V or flatter and less than 10 feet high, and no closer than a distance
equal to one half the height of the slope for cuts more than 10 feet high.
Temporary cut slopes should be planned such that they do not encroach on a 1H:1V influence line projected
down from the edges of nearby or planned foundation elements. New footings planned at or near existing
grades and in temporary cut slope areas should extend through wall backfill and be embedded in native
soils.
Water that enters the excavations must be collected and routed away from prepared subgrade areas. We
expect that this may be accomplished by installing a system of drainage ditches and sumps along the toe
of the cut slopes. Some sloughing and raveling of the cut slopes should be expected. If excessive
groundwater is observed while making cuts, then alternative groundwater control systems will be
necessary, such as well points or wells. Temporary covering, such as heavy plastic sheeting with appropriate
ballast, should be used to protect these slopes during periods of wet weather. Surface water runoff from
above cut slopes should be prevented from flowing over the slope face by using berms, drainage ditches,
swales or other appropriate methods.
If temporary cut slopes experience excessive sloughing or raveling during construction, it may become
necessary to modify the cut slopes to maintain safe working conditions. Slopes experiencing problems can
be flattened, regraded to add intermediate slope benches or additional dewatering can be provided if the
poor slope performance is related to groundwater seepage.
Homestead Community Land Trust | November 18, 2024 Page 10
File No. 23656-001-01
4.4.3 Soldier Pile and Tieback Walls
Soldier pile walls consist of steel beams that are concreted into drilled vertical holes located along the wall
alignment, typically 8 feet on center. After excavation to specified elevations, tiebacks are installed, if
necessary. Once the tiebacks are installed, the pullout capacity of each tieback is tested, and the tieback
is locked-off to the soldier pile at or near the design tieback load. Tiebacks typically consist of steel strands
that are installed into pre-drilled holes and then either tremie or pressure grouted. Timber lagging is typically
installed behind the flanges of the steel beams to retain the soil located between the soldier piles.
Geotechnical design recommendations for each of these components of the soldier pile and tieback wall
system are presented in the following sections.
4.4.3.1 SOLDIER PILES
We recommend that soldier pile walls be designed using the earth pressure diagrams presented in Figure 3.
The earth pressures presented in Figure 3 are for full height cantilever soldier pile walls and full-height
soldier pile walls with a single level or multiple levels of tiebacks and include loading from traffic surcharge.
The earth pressures represent the estimated loads that will be applied to the wall system for various wall
heights. No seismic pressures have been included because it is assumed that the shoring will be temporary.
Additional surcharge loads (floor or foundation loads, etc.) can be evaluated using the surcharge pressures
presented in Figure 4. Other surcharge loads, such as cranes, construction equipment or construction
staging areas, should be considered by GeoEngineers on a case-by-case basis.
We recommend that the embedded portion of the soldier piles be at least 2 feet in diameter and extend a
minimum distance of 10 feet below the base of the excavation to resist “kick-out.” The axial capacity of the
soldier piles must resist the downward component of the anchor loads and other vertical loads, as
appropriate. We recommend using an allowable end bearing value of 40 kips per square foot (ksf) for piles
supported on the glacially consolidated soils. The allowable end bearing value should be applied to the
base area of the drilled hole into which the soldier pile is concreted. This value includes a factor of safety
of about 2.5. The allowable end bearing value assumes that the shaft bottom is cleaned out immediately
prior to concrete placement. If necessary, an allowable pile skin friction of 1.5 ksf may be used on the
embedded portion of the soldier piles to resist the vertical loads.
4.4.3.2 LAGGING
We recommend that the temporary timber lagging be sized using the procedures outlined in the Federal
Highway Administration’s Geotechnical Engineering Circular No. 4. The site soils are best described as
competent soils. Table 2 presents recommend timber lagging thicknesses (roughcut) as a function of
soldier pile clear span and depth. Shotcrete lagging can be used as an alternative to timber lagging,
depending upon the contractor’s preference.
TABLE 2. RECOMMENDED LAGGING THICKNESS
DEPTH (FEET)
LAGGING THICKNESS (ROUGHCUT) FOR CLEAR SPANS OF:
5 FEET 6 FEET 7 FEET 8 FEET 9 FEET 10 FEET
0 to 25 2 inches 3 inches 3 inches 3 inches 4 inches 4 inches
Homestead Community Land Trust | November 18, 2024 Page 11
File No. 23656-001-01
Lagging should be installed promptly after excavation, especially in areas where perched groundwater is
present or where clean sand and gravel soils are present and caving soils conditions are likely. The
workmanship associated with lagging installation is important for maintaining the integrity of the
excavation.
The space behind the lagging should be filled with soil as soon as practicable. The voids behind the lagging
should be backfilled immediately or within a single shift, depending on the selected method of backfill.
Placement of backfill will help reduce the risk of voids developing behind the wall and damage to existing
improvements located behind the wall. Lean concrete or controlled density fill (CDF) is a suitable option for
the use of backfill behind the walls. Lean concrete/CDF will reduce the volume of voids present behind
walls. Alternatively, lean concrete may be used for backfill behind the upper 5 to 10 feet of the excavation
to limit caving and sloughing of the upper soils, with on-site soils used to backfill the voids for the remainder
of the excavation. Based on our experience, the voids between each lean concrete lift are sufficient for
preventing the buildup of hydrostatic pressure behind the wall.
4.4.3.3 TIEBACKS
Tieback anchors can be used for wall heights where cantilever soldier pile walls are not cost-effective.
Tieback anchors should extend far enough behind the wall to develop anchorage beyond the “no-load” zone
and within a stable soil mass. The anchors should be inclined downward at 15 to 25 degrees below the
horizontal. Corrosion protection will not be required for the temporary tiebacks with a design life of less
than one year.
Centralizers should be used to keep the tieback in the center of the hole during grouting. Structural grout
or concrete should be used to fill the bond zone of the tiebacks. A bond breaker, such as plastic sheathing,
should be placed around the portion of the tieback located within the no-load zone if the shoring contractor
plans to grout both the bond zone and unbonded zone of the tiebacks in a single stage. If the shoring
contractor does not plan to use a bond breaker to isolate the no-load zone, GeoEngineers should be
contacted to provide recommendations.
Loose soil and slough should be removed from the holes drilled for tieback anchors prior to installing the
tieback. The contractor should take necessary precautions to minimize loss of ground and prevent
disturbance to previously installed anchors and existing improvements in the site vicinity. Holes drilled for
tiebacks should be grouted/filled promptly to reduce the potential for loss of ground.
Tieback anchors should develop anchorage in the glacially consolidated soils. We recommend that spacing
between tiebacks be at least three times the diameter of the anchor hole to minimize group interaction.
We recommend a design load transfer value between the anchor and soil of 4 kips per foot for the
unweathered glacial till soils and 1.5 kips per foot for fill and weathered glacial till soils. Higher adhesion
values may be developed, depending on the anchor installation technique. The contractor should be given
the opportunity to use higher adhesion values by conducting performance tests prior to the start of installing
the production tieback anchors.
The tieback anchors should be verification- and proof-tested to confirm that the tiebacks have adequate
pullout capacity. The pullout resistance of tiebacks should be designed using a factor of safety of 2. The
pullout resistance should be verified by completing at least two successful verification tests in each soil
type and a minimum of four total tests for the project. Each tieback should be proof tested to 133 percent
of the design load. Verification and proof tests should be completed as described in Appendix D.
Homestead Community Land Trust | November 18, 2024 Page 12
File No. 23656-001-01
The tieback layout and inclination should be checked to confirm that the tiebacks do not interfere with
adjacent buried utilities.
4.4.3.4 DRAINAGE
A suitable drainage system should be installed to prevent the buildup of hydrostatic groundwater pressures
behind the soldier pile and lagging wall. It may be necessary to cut weep holes through the lagging in wet
areas. Seepage flows at the base of the excavation should be contained and controlled. Drainage should
be provided for permanent below-grade walls as described in Section 4.7.
4.4.3.5 CONSTRUCTION CONSIDERATIONS
Shoring construction should be completed by a qualified shoring contractor having experience with similar
projects in the Puget Sound area.
Temporary casing or drilling fluid may be required to install the soldier piles and possibly the tiebacks where:
■ Loose fill is present;
■ The native soils do not have adequate cementation or cohesion to prevent caving or raveling; and/or
■ Groundwater is present.
GeoEngineers should be allowed to observe and document the installation and testing of the shoring to
verify conformance with the design assumptions and recommendations.
4.4.4 Soil Nail Walls
The soil nail wall system consists of drilling and grouting rows of steel bars or “nails” behind the excavation
face as it is excavated and then covering the face with reinforced shotcrete. The placement of soil nails
reinforces the soils located behind the excavation face and increases the soil’s ability to inhibit a mass of
soil from sliding into the excavation.
Soil nails typically consist of #6 to #12 threaded steel bars (¾- to 1½-inch-diameter). The steel bars are
placed in 6- to 8-inch-diameter holes drilled at angles typically ranging from 10 to 25 degrees below
horizontal. Centralizers are used to center the steel bars in the holes. Once the steel bars are installed, the
holes are grouted using cement grout or concrete.
The soils typically are required to have an adequate standup time (to allow placement of the steel wire
mesh and/or reinforcing bars to be installed and the shotcrete to be placed). Soils that have short standup
times are problematic for soil nailing.
Soil nail walls are typically constructed using the following sequence:
1. Install full-depth vertical elements into vertical drilled holes and grout each hole with lean concrete.
2. Excavate the soil at the wall face to between 1 and 3 feet below the row of soil nails to be installed.
Depending upon the soil conditions at the wall face, the excavation may be completed with a vertical
cut or with berms (native or fill).
3. Drill, install and grout soil nails.
Homestead Community Land Trust | November 18, 2024 Page 13
File No. 23656-001-01
4. Excavate berm, if present, located within about 3 feet below the elevation of the soil nail.
5. Place drainage strips, steel wire mesh and/or reinforcing bars in front of the excavated soil.
6. Install shotcrete and place steel plates and nuts over the soil nails.
7. Complete nail pullout capacity testing on approximately one out of every 20 nails in an installed row.
8. Repeat steps two through seven for each row of nails located below the completed row.
Full depth vertical elements should be used to improve deformation control, improve face stability of the
site soils and to act as a cantilever wall to meet nail clearance requirements where buried utilities are
present. Vertical elements typically consist of vertical steel beams placed in drilled holes located along the
wall alignment and backfilled with lean concrete. For vertical elements that act as a cantilever wall, we
recommend that the vertical elements be designed for the earth pressures presented in Section 4.7.2.
Face instability where clean granular soils are present can be mitigated using vertical elements or by other
means determined by the shoring contractor during shoring construction, as discussed below.
4.4.4.1 DESIGN RECOMMENDATIONS
We recommend the following for design and cost estimating purposes:
■ Full depth vertical elements installed at approximately 6 feet on center with vertical element toe
embedment of at least 3 feet below the base of excavation elevation;
■ A soil nail grid pattern of about 6 by 6 feet;
■ A soil nail length ranging up to the wall height (but not less than 10 feet), inclined at about 15 to
20 degrees from the horizontal;
■ An allowable load transfer of 1.5 kips per foot for fill and weathered glacial till, and 3 kips per foot for
the relatively unweathered glacial till for 6- to 8-inch-diameter grouted nails; and
■ Strips of drainage material installed behind the shotcrete to relieve hydrostatic pressures. Additional
drainage provisions may be necessary if significant groundwater is encountered during the excavation.
Existing fill, looser weathered glacial soils and fill associated with utilities located behind the walls will affect
the soil nail design. Typically, the soil nail spacing is tighter or the soil nails are longer, or both, where fill or
looser native soils are present compared to where competent glacially consolidated soils are present.
Difficulties associated with face stability and standup time may be experienced during construction in the
site soils. Fill soils are often loose to medium dense and, as a result, may have a shorter standup time.
Cleaner sand and gravel soils or soils located in areas with groundwater may also exhibit shorter standup
times. Spalling and raveling of the cut face may occur at these locations during soil nail wall installation.
Construction techniques used to mitigate spalling and raveling include:
■ Flash coating the cut face with 2 to 4 inches of shotcrete immediately after the cut face is excavated
to final line and the drainage material is installed. This typically provides enough standup time to allow
for the installation of the reinforcing steel and final shotcrete;
■ Excavating in half-height (2- to 3-foot) lifts, rather than full-height (6-foot) lifts;
Homestead Community Land Trust | November 18, 2024 Page 14
File No. 23656-001-01
■ Excavating leaving a 1H:1V earth berm in front of the wall. The soil nails are installed by drilling through
the soil berm. The soil berm is then removed to allow for installation of the drainage material and
reinforcing steel and shotcrete;
■ Excavating to the planned back of shotcrete facing and then placing a 1H:1V fill berm in front of the
wall. The fill berm is then removed just before placement of drainage material, reinforcement and
shotcrete;
■ Shortening the length of wall drilled and shotcreted using a staggered excavation approach; and
■ Installing closely spaced full-depth vertical soil nails or small steel beams (vertical elements) along the
wall alignment.
Contractors experienced in the soil nailing method should be able to mitigate significant spalling and
raveling conditions. Contractors should also be prepared to use techniques to address problems that occur
because of caving soils. The contractor should be made responsible for the safety of the shoring system.
Baseline assumptions for the extent of temporary casing required for soil nail installation and the use of
native/fill berms for the project are recommended to be established prior to construction.
4.4.4.2 DRAINAGE
A suitable drainage system should be installed to prevent the buildup of hydrostatic groundwater pressures
behind the soil nail walls. Drainage behind soil nail walls typically consists of prefabricated geocomposite
drainage strips, such as Mirafi G100™, installed vertically between the soil nails. The drainage strips are
typically a minimum of 16 inches wide and extend the entire height of the wall. Horizontal drainage strips
may also be used in areas where perched groundwater is observed, or for other reasons. We recommend
that drainage strips be connected to a prefabricated drainage grate and weep pipe installed along the base
of the wall that passes through the shotcrete facing, and routed to a suitable discharge point as described
below in Section 4.7.
4.4.4.3 LATERAL EARTH PRESSURES RESULTING FROM ADJACENT SURCHARGE LOADING
The diagrams of recommended surcharge pressures presented in Figure 4 can be used to estimate the
lateral earth pressures acting on below-grade walls as a result of other point, line and uniform surcharge
loading.
4.4.4.4 SOIL NAIL WALL PERFORMANCE
A soil nail wall is a passive shoring system that requires deflections for load to be applied to the soil nails.
We recommend that the soil nail be designed such that average wall deflections are limited to 1 inch and
ground surface settlements behind the wall are less than about 1 inch.
The deflections and settlements are usually highest at the excavation face and decrease to negligible
amounts beyond a distance behind the wall equal to the excavation height. Wall deflections can be reduced
by pre-stressing the upper row(s) of soil nails. Localized deflections may exceed the above estimates and
may reflect local variations in soil conditions (such as around abandoned side sewers) or may be the result
of the workmanship used to construct the wall.
Homestead Community Land Trust | November 18, 2024 Page 15
File No. 23656-001-01
4.4.4.5 CONSTRUCTION CONSIDERATIONS
Temporary casing or drilling fluid will be required to install the vertical elements, and casing will be
necessary for soil nails where:
■ Loose fill is present;
■ The native soils do not have adequate cementation or cohesion to prevent caving or raveling; and/or
■ Perched groundwater is present.
GeoEngineers should be allowed to observe and document the installation and testing of the shoring to
verify conformance with design assumptions and recommendations.
Shoring construction should be completed by a qualified shoring contractor having experience with similar
projects in the Puget Sound area.
4.4.5 Shoring Wall Performance
Temporary shoring walls typically move up to 1 inch. The deflections and settlements are usually highest at
the excavation face and decrease to negligible amounts beyond a distance behind the wall equal to the
height of the excavation. Localized deflections may exceed the above estimates and may reflect local
variations in soil conditions (such as around side sewers) or may be the result of the workmanship used to
construct the shoring wall. Given that some movement is expected, existing improvements located adjacent
to the temporary shoring system will also experience movement. The deformations discussed above are
not likely to cause structural damage to structurally sound existing improvements; however, some cosmetic
damage should be expected (for instance, cracks in drywall finishes; widening of existing cracks; minor
cracking of slabs-on-grade/hardscapes; cracking of sidewalks, curbs/gutter and pavements/pavement
panels; etc.). For this reason, it is important to complete a pre-construction survey and photo
documentation of existing buildings and improvements prior to shoring construction. Refer to Appendix D
for more detailed recommendations for shoring monitoring and preconstruction survey.
4.5 SHALLOW FOUNDATIONS
We recommend that the proposed buildings be supported on shallow spread footings founded on the dense
to very dense/very stiff to hard glacial till encountered in the explorations. Shallow spread footings may
also be supported on weathered glacial till or on properly compacted structural fill extending down to these
soils. Existing fill and unsuitable highly weathered glacial till should be removed from under the planned
building foundations.
For shallow foundation support, we recommend widths of at least 18 and 36 inches, respectively, for
continuous wall and isolated column footings supporting the proposed buildings. The design frost depth in
the Puget Sound area is 12 inches; therefore, we recommend that exterior footings for the buildings be
founded at least 18 inches below lowest adjacent finished grade. Interior footings should be founded at
least 12 inches below bottom of slab or adjacent finished grade.
The following recommendations for the building foundations are based on the subsurface conditions
observed in the explorations completed at the site.
Homestead Community Land Trust | November 18, 2024 Page 16
File No. 23656-001-01
4.5.1 Allowable Bearing Pressures
Unsuitable soils consisting of fill, topsoil and/or highly weathered glacial till will vary across the site and
must be removed from below planned footings. Based on our explorations and estimated fill depths,
unsuitable soils and fill may range from approximately 2½ to 8 feet deep. Therefore, depending on the
foundation locations and design elevations, overexcavation under the footings may be necessary for some
building foundations. For design, we recommend the following:
■ Shallow Foundations on Dense Glacial Till: Foundations extending to and bearing on competent
undisturbed dense to very dense/very stiff to hard native glacial till may be designed using a maximum
allowable soil bearing pressure of 6,000 psf for isolated spread footings and continuous footings. CDF
or lean concrete may be used below footings to support 6,000 psf, provided that it extends down to
dense to very dense/very stiff to hard glacial till. Overexcavated areas must be backfilled with CDF
having a design strength of at least 200 pounds per square inch (psi).
■ Shallow Foundations on Medium Dense Weathered Glacial Till: Foundations extending to and
bearing on competent undisturbed medium dense to dense native weathered glacial till may be
designed using a maximum allowable soil bearing pressure of 3,000 psf for isolated spread footings
and continuous footings.
■ Shallow Foundations on Structural Fill: For foundations bearing on properly placed and compacted
structural fill extending down to medium dense to very dense/ glacial till, foundations may be designed
using a maximum allowable soil bearing pressure of 3,000 psf for isolated spread footings and
continuous footings.
Where structural fill is placed below footings, the fill should extend beyond the edges of the foundations by
the depth of the overexcavation, while the CDF should extend beyond the edges of the foundations by half
the depth of the overexcavation. The allowable bearing pressures presented above apply to the total dead
and long-term live loads and may be increased up to one-third for short-term live loads such as wind or
seismic forces.
All footings near below-grade walls should be embedded to a depth that is at least below a 1H:1V line
projected up from the bottom of the closest section of wall, otherwise the below-grade walls need to be
designed for lateral loads from the footings.
4.5.2 Settlement
Post-construction settlement of shallow footings supported on native soils or on properly compacted
structural fill as recommended above should be limited to less than 1 inch, and differential settlement
between comparably loaded column footings or along a 25-foot section of continuous wall footing should
be less than ½ inch. We expect most of the footing settlements will occur as loads are applied. Loose or
disturbed soils not removed from footing excavations prior to placing concrete will result in additional
settlement.
Homestead Community Land Trust | November 18, 2024 Page 17
File No. 23656-001-01
4.5.3 Lateral Resistance
Lateral foundation loads may be resisted by passive resistance on the sides of the footings and by friction
on the base of the footings. Frictional resistance may be computed using a coefficient of friction of 0.4
applied to vertical dead-load forces. Passive resistance may be computed using an equivalent fluid density
of 350 pcf. The allowable passive resistance is for horizontal soil conditions in front of the footing and is
applicable provided that the footings are surrounded by structural fill or constructed neat against
native glacial soils. The structural fill should be compacted to at least 95 percent of the maximum dry
density (MDD) determined in accordance with ASTM D 1557. Passive pressure resistance should be
calculated from the bottom of adjacent floor slabs or below a depth of 1 foot where the adjacent area is
unprotected, as appropriate. The allowable frictional resistance and passive resistance values presented
above include a factor of safety of about 1.5.
If soils adjacent to footings are disturbed during construction, the disturbed soils must be recompacted,
otherwise the lateral passive resistance value must be reduced.
4.5.4 Footing Drains
We recommend perimeter footing drains be installed around the proposed buildings. The perimeter drains
should be installed at the base of the exterior footings, as shown in Figure 5. The perimeter drains should
consist of at least 4-inch-diameter perforated pipe placed on a 4-inch bed of, and surrounded by, 6 inches
of drainage material enclosed in a nonwoven geotextile filter fabric such as Mirafi 140N (or approved
equivalent). The perimeter drains should be provided with cleanouts. The footing drainpipe should be
installed at least 18 inches below the top of the adjacent floor slab. The drainage material should consist
of “Gravel Backfill for Drains” per Section 9-03.12(4) of the 2024 Washington State Department of
Transportation (WSDOT) Standard Specifications. We recommend the drainpipe consist of either heavy-wall
solid pipe (SDR-35 polyvinyl chloride [PVC], or equal) or rigid corrugated smooth interior polyethylene pipe
(ADS N-12, or equal). We recommend against using flexible tubing for footing drainpipes. The perimeter
drains should be sloped to drain by gravity, if practicable, to a suitable discharge point, preferably a storm
drain. We recommend the cleanouts be covered and placed in flush mounted utility boxes. Water collected
in roof downspout lines must not be routed to the footing drain lines.
4.5.5 Construction Considerations
We recommend that the excavations for the footings be completed with an excavator equipped with a
smooth-edge bucket to minimize subgrade disturbance. Immediately prior to placing concrete, all debris
and loose soils that accumulated in the footing excavations during forming and steel placement must be
removed. Debris or loose soils not removed from the footing excavations will result in increased settlement.
If wet weather construction is planned, we recommend that all footing subgrades be protected using a lean
concrete mud mat that is about 2 inches thick. The mud mat should be placed the same day that the footing
subgrade is excavated and approved for foundation support.
Homestead Community Land Trust | November 18, 2024 Page 18
File No. 23656-001-01
4.6 SLAB-ON-GRADE FLOORS
4.6.1 Subgrade Preparation
We recommend that concrete slabs-on-grade be constructed on a gravel layer to provide uniform support
and drainage, and to act as a capillary break. We expect that slab-on-grade floors can be supported on:
(1) medium dense to very dense/stiff to hard native glacial soils encountered in the explorations,
(2) properly compacted structural fill extending down to these materials, or (3) on suitable on-site soils.
Prior to placing the gravel layer, the subgrade should be evaluated and unsuitable soils should be removed
and replaced with structural fill where needed. Then the subgrade should be proofrolled as described in
Section 4.8. The exposed subgrade should be evaluated during construction and compacted to a firm and
unyielding condition.
4.6.2 Design Parameters
A 4-inch-thick capillary break layer of 1-inch minus clean crushed gravel with negligible sand and silt
(WSDOT 9-03.1(4)C, Grading No. 67) should be placed to provide uniform support and form a capillary
break beneath the slabs. For slabs designed as a beam on an elastic foundation, a modulus of subgrade
reaction of 100 pounds per cubic inch (pci) may be used for subgrade soils prepared as recommended
above.
If water vapor migration through the slabs is objectionable, the capillary break gravel layer should be
covered with heavy plastic sheeting at least 10-mil thick to act as a vapor retarder. This will be desirable
where the slabs are in occupied spaces or will be surfaced with tile or will be carpeted. It may also be
prudent to apply a sealer to the slab to further retard the migration of moisture through the floor. The
contractor should be made responsible for maintaining the integrity of the vapor barrier during construction.
Additional water proofing measures that may be needed should be evaluated during design.
4.6.3 Underslab Drainage
Groundwater could accumulate below the slab-on-grade for portions of buildings that are cut into the
hillside (i.e. Buildings D and E) and that have below-grade walls or utility connections that tie into the
building. To mitigate this condition, we recommend that the slabs of buildings with below-grade walls be
constructed with underslab drainage to collect and discharge groundwater from below the slabs. This can
be accomplished by installing a 4-inch-diameter, heavy-wall perforated collector pipe in a shallow trench
placed directly below the capillary break layer. The trench should measure about 18 inches wide by
12 inches deep and should be backfilled with the same drainage material as described in Section 4.5.4.
The drainage material should be wrapped in a nonwoven geotextile, such as Mirafi 140N. We recommend
installing a single underdrain collector pipe below the long axis of the buildings and towards the cut slope.
The collector pipe should be sloped to drain and discharge into the storm water collection system to convey
water off site. If connected to the footing drain pipe, the invert of the underslab drain pipe must be at a
higher elevation than the footing drain pipe to prevent water from flowing under the buildings from the
perimeter system. The pipe should also incorporate cleanouts, if possible. The cleanouts could be extended
through the foundation walls to be accessible from the outside or could be placed in flush mounted access
boxes cast into the floor slabs.
Homestead Community Land Trust | November 18, 2024 Page 19
File No. 23656-001-01
4.7 BELOW-GRADE WALLS AND RETAINING WALLS
We understand that below-grade retaining walls will be needed to replace the existing rockery on the west
side of the site and may be necessary for construction of Buildings D and E, as well as to support grade
transitions at the north/northeast side of the site and other site improvements. The following
recommendations should be used in design of below-grade walls that are intended to act as retaining walls
and for other retaining structures that are used to achieve grade changes.
As discussed previously, an existing apartment building is located north of the site. If a retaining wall
(temporary and/or permanent) is utilized on the north edge of the site and that existing apartment building
is located within a horizontal distance equal to the height of the retaining wall, the shoring wall design earth
pressures should be increased by 1.25 to provide enhanced deformation control. This should also be
considered for retaining walls along the west side of the site adjacent to Buildings A and B.
4.7.1 Permanent Subsurface Walls Against Temporary Shoring
Permanent below-grade walls cast against temporary shoring should be designed for the pressures
presented in Figure 3, with the addition of seismic earth pressures, which should be determined using a
rectangular distribution of 7H, where H is the wall height in feet. The rectangular distribution should be
distributed the full height of the wall. The seismic pressures should be added to the earth pressures shown
in Figure 3. Surcharge loads (floor slabs, construction surcharges, etc.) can be evaluated using the
surcharge pressure in Figure 4.
The soil pressures recommended above assume that wall drains will be installed to prevent the buildup of
hydrostatic pressure behind the walls, as described in Section 4.7.3 and tied to permanent drains to
remove water to suitable discharge points.
4.7.2 Other Cast-in-Place Walls
Conventional cast-in-place walls may be necessary against cut slopes not supported by temporary shoring.
The lateral soil pressures acting on conventional cast-in-place subsurface walls will depend on the nature,
density and configuration of the soil behind the wall and the amount of lateral wall movement that can
occur as backfill is placed.
Lateral earth pressures for design of below-grade walls and retaining structures should be evaluated using
an equivalent fluid density of 35 pcf (triangular distribution) provided that the walls will not be restrained
against rotation when backfill is placed. If the walls will be restrained from rotation, we recommend using an
equivalent fluid density of 55 pcf (triangular distribution). Walls are assumed to be restrained if top
movement during backfilling is less than H/1000, where H is the wall height. These lateral soil pressures
assume that the ground surface behind the wall is horizontal. For unrestrained walls with backfill sloping up
at 2H:1V, the design lateral earth pressure should be increased to 55 pcf, while restrained walls with a
2H:1V sloping backfill should be designed using an equivalent fluid density of 75 pcf. These lateral soil
pressures do not include the effects of surcharges such as floor loads, traffic loads or other surface loading.
Surcharge effects should be included as appropriate.
Below-grade should also include seismic earth pressures. Seismic earth pressures should be determined
using a rectangular distribution of 7H in psf, where H is the wall height in feet. The seismic pressures should
be added to the active/at-rest pressures.
Homestead Community Land Trust | November 18, 2024 Page 20
File No. 23656-001-01
If vehicles can approach the tops of exterior walls to within half the height of the wall, a traffic surcharge
should be added to the wall pressure. For car parking areas, the traffic surcharge can be approximated by
the equivalent weight of an additional 1 foot of soil backfill (125 psf) behind the wall. For delivery truck
parking areas and access driveway areas, the traffic surcharge can be approximated by the equivalent
weight of an additional 2 feet (250 psf) of soil backfill behind the wall. Other surcharge loads, such as
from foundations, construction equipment or construction staging areas, should be considered on a
case-by-case basis. Positive drainage should be provided behind below-grade walls and retaining structures
as discussed below.
These recommendations assume that all retaining walls will be provided with adequate drainage. The
values for soil bearing, frictional resistance and passive resistance presented above for foundation design
are applicable to retaining wall design. Walls located in level ground areas should be founded at a depth of
18 inches below the adjacent grade.
4.7.3 Wall Drainage
4.7.3.1 PERMANENT WALLS AGAINST TEMPORARY SHORING
Drainage behind the permanent below-grade walls is typically provided using prefabricated drainage board
attached to the temporary shoring walls. Weep pipes that extend through the permanent below-grade wall
should be installed around the perimeter of the building at the footing elevation. The weep pipes should
have a minimum diameter of 2 inches. The weep pipes through the permanent below-grade wall should be
spaced no more than 8 feet on center and should be hydraulically collected to the sump. The weep pipes
may be designed for a hard connection to the perimeter foundation drains discussed in Section 4.5.4.
The earth pressures for permanent below-grade walls assume that adequate drainage is provided behind
the wall. Prefabricated geocomposite drainage material, such as Aquadrain 15X, should be installed
vertically to the face of the lagging/behind the shotcrete. The vertical drainage material should extend a
minimum of 2 feet below the planned weep pipe locations. The weep pipes that penetrate the basement
wall should be connected to the vertical drainage material with a drain grate. For soldier pile shoring walls,
the drainage material should be installed on the excavation side of the timber lagging, with the fabric
adjacent to the timber lagging. For soil nail walls, the drainage material should be installed behind the
shotcrete, as described in Section 4.4.4.2.
4.7.3.2 OTHER CAST-IN-PLACE WALLS
To reduce the potential for hydrostatic water pressure buildup behind cast-in-place retaining walls not
constructed against temporary shoring, we recommend that the walls be provided with adequate drainage,
as shown in Figure 5. Wall drainage can be achieved by using free draining wall drainage material with
perforated pipes to discharge the collected water.
Wall drainage material may consist of Gravel Backfill for Drains per WSDOT Standard Specification
Section 9-03.12(4) surrounded with a nonwoven geotextile filter fabric such as Mirafi 140N (or approved
equivalent), or imported Gravel Borrow with less than 5 percent fines may be used in conjunction with a
geocomposite wall drainage layer. The zone of wall drainage material should be 2 feet wide and should
extend from the base of the wall to within 2 feet of the ground surface. The wall drainage material should
be covered with a geotextile separator (such as Mirafi 140N) and then 2 feet of less permeable material,
such as the on-site silty sand that is properly moisture conditioned and compacted.
Homestead Community Land Trust | November 18, 2024 Page 21
File No. 23656-001-01
A 4-inch-diameter perforated drain pipe should be installed within the free-draining material at the base of
each wall. We recommend using either heavy-wall solid pipe (SDR-35 PVC) or rigid corrugated polyethylene
pipe (ADS N-12, or equal). We recommend against using flexible tubing for the wall drain pipe. The footing
drain recommended above can be incorporated into the bottom of the drainage zone and used for this
purpose. If gravel borrow is used against the wall in conjunction with a geocomposite wall drainage layer,
then the drainage pipe at the base of the wall should be surrounded with at least 12 inches of Gravel
Backfill for Drains per WSDOT Standard Specification Section 9-03.12(4) that is wrapped with a nonwoven
geotextile filter fabric such as Mirafi 140N (or approved equivalent).
The pipes should be laid with minimum slopes of one-quarter percent and discharge into the storm water
collection system to convey the water off site. The pipe installations should include a cleanout riser with
cover located at the upper end of each pipe run. The cleanouts could be placed in flush mounted access
boxes. Collected downspout water should be routed to appropriate discharge points in separate pipe
systems.
4.8 EARTHWORK
Based on the observed subsurface soil conditions, we anticipate that the soils at the sites may be excavated
using conventional heavy-duty construction equipment. Dense to very dense glacial till with variable silt and
gravel content that was encountered in the explorations can be difficult to excavate. Glacial deposits in the
area commonly contain cobbles and boulders that may be encountered during excavation. Accordingly, the
contractor should be prepared to deal with cobbles and boulders.
The fill and native soils contain significant fines (material passing the U.S. Standard No. 200 sieve) and are
highly moisture-sensitive and susceptible to disturbance, especially when wet. Ideally, earthwork should be
undertaken during extended periods of dry weather (June through September) when the surficial soils will
be less susceptible to disturbance and provide better support for construction equipment. Dry weather
construction will help reduce earthwork costs and increase the potential for using the native soils as
structural fill.
Trafficability on the site is not expected to be difficult during dry weather conditions. However, the fill and
native soils will be susceptible to disturbance from construction equipment during wet weather conditions
and pumping and rutting of the exposed soils under equipment loads may occur and could potentially
generate significant quantities of mud if not protected.
4.8.1 Clearing and Site Preparation
Areas to be developed or graded should be cleared of surface and subsurface deleterious matter including
any debris, shrubs, trees and associated stumps and roots. Graded areas should be stripped of organic
soils. We anticipate that the average stripping depth will be about 6 inches, although stripping depth around
12 inches will be needed in heavily vegetated areas.
The organic soils can be stockpiled and used later for landscaping purposes or may be spread over
disturbed areas following completion of grading. If spread out, the organic strippings should be in a layer
less than 1-foot thick, should not be placed on slopes greater than 3H:1V (horizontal to vertical) and should
be track-rolled to a uniformly compacted condition. Materials that cannot be used for landscaping or
protection of disturbed areas should be removed from the project site.
Homestead Community Land Trust | November 18, 2024 Page 22
File No. 23656-001-01
Undocumented fill may be present in various areas of the site and will be required to be removed under
building foundations and within the upper two feet of pavement, hardscape and slab subgrade levels.
Where existing fill and looser native soils are removed, they may be reused and recompacted as structural
fill, if conditions allow.
4.8.2 Earthwork Subgrade Preparation
Prior to placing new fills, pavement base course materials or gravel below on-grade floor slabs, subgrade
areas should be proof-rolled to locate any soft or pumping soils. Prior to proof-rolling, all unsuitable soils
should be removed from below building footprints and new hardscape areas. Proof-rolling can be completed
using a piece of heavy tire-mounted equipment such as a loaded dump truck. During wet weather, the
exposed subgrade areas should be probed to determine the extent of soft soils. If soft or pumping soils are
observed, they should be removed and replaced with structural fill.
After completing the proof-rolling, the subgrade areas should be recompacted to a firm and unyielding
condition, if possible. The degree of compaction that can be achieved will depend on when the construction
is performed. If the work is performed during dry weather conditions, we recommend that all subgrade
areas be recompacted to at least 95 percent of the MDD in accordance with the ASTM D 1557 test
procedure (modified Proctor). If the work is performed during wet weather conditions, it may not be possible
to recompact the subgrade to 95 percent of the MDD. In this case, we recommend that the subgrade be
compacted to the extent possible without causing undue weaving or pumping of the subgrade soils.
Subgrade disturbance or deterioration could occur if the subgrade is wet and cannot be dried. If the
subgrade deteriorates during proof-rolling or compaction, it may become necessary to modify the proof-
rolling or compaction criteria or methods.
4.8.2.1 SUBGRADE PROTECTION
Site soils contain significant fines content (silt/clay) and will be highly sensitive and susceptible to moisture
and equipment loads. The contractor should take necessary measures to prevent site subgrade soils from
becoming disturbed or unstable.
4.8.3 Structural Fill
All fill, whether existing on-site soils or imported soil, that will support floor slabs, pavement areas or
foundations or be placed against retaining walls or in utility trenches are classified as structural fill and
should generally meet the criteria for structural fill presented below. The suitability of soil for use as
structural fill depends on its gradation and moisture content.
4.8.3.1 MATERIALS
Structural fill material quality varies depending upon its use as described below:
■ Structural fill placed below foundations designed for 3,000 psf or lower, floor slabs or as subbase
material below pavement areas may consist of suitable on-site glacial till soils (during dry weather) or
should meet the criteria for gravel borrow as described in Section 9-03.14(1) of the 2024 WSDOT
Standard Specifications.
Homestead Community Land Trust | November 18, 2024 Page 23
File No. 23656-001-01
■ CDF used to support building foundations designed for bearing pressures up to 6,000 psf should be in
accordance with 2024 WSDOT Standard Specification Section 2-09.3(1)E and should have a minimum
compressive strength of 200 psi. The mix design should be adjusted to obtain this minimum
compressive strength. Lean concrete may also be used under building foundations.
■ Structural fill placed to raise site grades below building slabs or to backfill utility trenches should meet
the criteria for common borrow as described in Section 9-03.14(3) of the 2024 WSDOT Standard
Specifications during dry weather conditions (typically June through September). Common borrow
materials are highly moisture sensitive. For wet weather construction (October through May), structural
fill placed to raise site grades or in utility trenches should meet the criteria for gravel borrow as
described in Section 9-03.14(1) of the 2024 WSDOT Standard Specifications, except that the fines
content (material passing the U.S. No. 200 sieve) should not exceed 5 percent.
■ Structural fill placed immediately outside below-grade walls (drainage zone) should consist of washed
gravel in conformance Section 9-03.12(4) of the 2024 WSDOT Standard Specifications, as shown in
Figure 5.
■ Structural fill placed as crushed surfacing base course (CSBC) below pavements should conform to
Section 9 03.9(3) of the 2024 WSDOT Standard Specifications.
■ Structural fill placed as capillary break below slabs should consist of 1-inch minus clean crushed gravel
with negligible sand or silt in conformance with Section 9-03.1(4)C, grading No. 67 of the 2024 WSDOT
Standard Specifications.
4.8.3.2 REUSE OF ON-SITE SOILS
Based on the explorations, the moisture content of the fill and the native glacial till is typically near the
optimum moisture content for compaction. However, the soils are very moisture sensitive and can be
difficult to compact during periods of wet weather or if impacted by groundwater seepage. Therefore, we
recommend that they be used as Common Borrow only during periods of extended dry weather. Soils with
high fines content, such as silt and clay will not be suitable for reuse as structural fill and should be exported
from the site or used in landscape areas if encountered during construction.
4.8.4 Fill Placement and Compaction Criteria
Structural fill should be mechanically compacted to a firm, non-yielding condition. Structural fill should be
placed in loose lifts not exceeding 12 inches in thickness if using heavy compactors and 6 inches if using
hand operated compaction equipment. The actual lift thickness will be dependent on the structural fill
material used and the type and size of compaction equipment. Each lift should be moisture conditioned to
within about 2 percent of the optimum moisture content and compacted to the specified density before
placing subsequent lifts. Compaction of all structural fill at the site should be in accordance with the
ASTM D 1557 (modified proctor) test method. Structural fill should be compacted to the following criteria:
1. Structural fill placed below floor slabs and foundations, and against foundations, should be compacted
to at least 95 percent of the MDD.
Homestead Community Land Trust | November 18, 2024 Page 24
File No. 23656-001-01
2. Structural fill placed behind below-grade walls should be compacted to between 90 to 92 percent of
the MDD. Care should be taken when compacting fill near the face of below-grade walls to avoid
over-compaction and, hence overstressing the walls. Hand-operated compactors should be used within
5 feet behind the wall. Wall backfill placed within building footprints, but under a second-floor level
should be compacted to between 90 to 92 percent of the MDD within 5 feet of the walls and to at least
95 percent of the MDD beyond 5 feet of the walls. The upper 2 feet of fill below floor slab subgrade
should also be compacted to at least 95 percent of the MDD.
3. Structural fill in new pavement and hardscape areas, including utility trench backfill, should be
compacted to at least 90 percent of the MDD, except that the upper 2 feet of fill below final subgrade
should be compacted to at least 95 percent of the MDD, see Figure 6.
4. Structural fill placed as crushed rock base course below pavements should be compacted to
95 percent of the MDD.
5. Non-structural fill, such as fill placed in landscape and planting areas, should be compacted to at least
90 percent of the MDD.
4.8.5 Weather Considerations
The on-site soils and common borrow contain a sufficient percentage of fines (silt and clay) to be highly
moisture sensitive. When the moisture content of these soils is more than a few percent above the optimum
moisture content, these soils become muddy and unstable, operation of equipment on these soils will be
difficult and it will be difficult or impossible to meet the required compaction criteria. Additionally,
disturbance of near-surface soils should be expected if earthwork is completed during periods of wet
weather. It will be preferable to schedule site preparation and earthwork activities during periods of dry
weather when the soils will: (1) be less susceptible to disturbance and (2) provide better support for
construction equipment.
The wet weather season in the Puget Sound region generally begins in October and continues through May;
however, periods of wet weather may occur during any month of the year. The optimum earthwork period
for these types of soils is typically June through September. If wet weather earthwork is unavoidable, we
recommend the following:
■ Structural fill placed during the wet season or during periods of wet weather should consist of imported
gravel borrow with less than 5 percent fines (material passing the U.S. No. 200 sieve).
■ The ground surface in and around the work area should be sloped so that surface water is directed
away from the work area.
■ The ground surface should be graded such that areas of ponded water do not develop.
■ The contractor should take measures to prevent surface water from collecting in excavations and
trenches.
■ Earthwork activities should not take place during periods of heavy precipitation.
■ Slopes with exposed soils should be covered with plastic sheeting or similar means.
Homestead Community Land Trust | November 18, 2024 Page 25
File No. 23656-001-01
■ Measures should be taken to prevent on-site soils and soils to be used as fill from becoming wet or
unstable. These measures may include the use of plastic sheeting, sumps with pumps and grading.
The site soils should not be left uncompacted and exposed to moisture. Sealing the surficial soils by
rolling with a smooth-drum roller prior to periods of precipitation will reduce the extent to which these
soils become wet or unstable.
■ The contractor should cover all soil stockpiles that will be used as structural fill with plastic sheeting.
■ Construction and foot traffic should be restricted to specific areas of the site, preferably areas that are
surfaced with materials not susceptible to wet weather disturbance.
■ Construction activities should be scheduled so that the length of time that soils are left exposed to
moisture is reduced to the extent practicable.
4.8.6 Utility Trenches
Trench excavation, pipe bedding and trench backfilling should be completed using the general procedures
described in the 2024 WSDOT Standard Specifications or other suitable procedures specified by the project
civil engineer. The glacial deposits and fill soils encountered at the site are generally of low corrosivity based
on our experience in the Puget Sound area.
Utility trench backfill should consist of structural fill and should be placed in lifts of 12 inches or less (loose
thickness) when using heavy compaction equipment or 6 inches or less when using hand-operated
equipment such that adequate compaction can be achieved throughout the lift. Each lift must be
compacted as described in Section 4.8.4 and shown in Figure 6, prior to placing the subsequent lift. Prior
to compaction, the backfill should be moisture conditioned to within about 2 percent of the optimum
moisture content, if necessary.
4.8.7 Pavement Subgrade Preparation
We recommend that the subgrade soils in new pavement areas be prepared and evaluated as described
in Sections 4.8.2 and 4.9. For cuts in medium dense to very dense glacial till, we recommend that the
exposed subgrade be proof-rolled. Where existing fill or loose to medium dense/soft to stiff native soils
exist, we recommend that the upper 12 inches of the existing site soils be compacted to at least 95 percent
of the MDD per ASTM D1557 and then proof-rolled prior to placing pavement section materials. If the
subgrade soils are loose or soft, it may be necessary to excavate the soils and replace them with structural
fill, gravel borrow or gravel base material. Based on the explorations, the majority of the subgrade soils are
expected to consist of fill, weathered native soils and relatively unweathered glacial till. Pavement subgrade
conditions should be observed and proof-rolled during construction to evaluate the presence of unsuitable
subgrade soils and the need for over excavation.
4.8.8 Permanent Slopes
We recommend that permanent cut or fill slopes be constructed at inclinations of 2H:1V or flatter. To
achieve uniform compaction, we recommend that fill slopes be overbuilt at least 2 feet and subsequently
cut back to expose properly compacted fill. Permanent slopes constructed at 3H:1V or flatter provide better
conditions for future maintenance.
Homestead Community Land Trust | November 18, 2024 Page 26
File No. 23656-001-01
To reduce erosion, newly constructed slopes should be planted or hydroseeded shortly after completion of
grading. Until the vegetation is established, some sloughing and raveling of the slopes should be expected.
This may require localized repairs and reseeding. Temporary covering, such as clear heavy plastic sheeting,
jute fabric or erosion control blankets (such as American Excelsior Curlex 1 or North American Green
SC150) could be used to protect the slopes during periods of rainfall.
4.8.9 Sedimentation and Erosion Control
In our opinion, the erosion potential of the on-site soils is low to moderate. Construction activities including
stripping and grading will expose soils to the erosion effects of wind and water. The amount and potential
impacts of erosion are partly related to the time of year that construction actually occurs. Wet weather
construction will increase the amount and extent of erosion and potential sedimentation.
Erosion and sedimentation control measures may be implemented by using a combination of interceptor
swales, straw bale barriers, silt fences and straw mulch for temporary erosion protection of exposed soils.
All disturbed areas should be finish graded and seeded as soon as practicable to reduce the risk of erosion.
Erosion and sedimentation control measures should be installed and maintained in accordance with the
requirements of the City of Renton.
4.9 PAVEMENT RECOMMENDATIONS
4.9.1 Subgrade Preparation
We recommend the subgrade soils in new pavement areas be prepared and evaluated as described in
sections 4.8.2 and 4.8.7. All new pavement and hardscape areas should be supported on subgrade soils
that have been proof rolled or probed, and approved by the geotechnical engineer. If the exposed subgrade
soils are loose or soft, it may be necessary to excavate localized areas and replace them with structural fill
or gravel base course. Pavement subgrade conditions should be observed during construction and prior to
placing the base course materials in order to evaluate the presence of zones of unsuitable subgrade soils
and the need for over-excavation and replacement of these zones.
4.9.2 New Hot-Mix Asphalt Pavement
In light-duty pavement areas (e.g., automobile parking), we recommend a pavement section consisting of
at least a 2.5-inch thickness of ½-inch hot-mix asphalt (HMA) (PG 58-22) per WSDOT Sections 5-04
and 9-03, over a 4-inch thickness of densely compacted crushed rock base course per WSDOT
Section 9-03.9(3). In heavy-duty pavement areas (e.g., truck traffic areas, materials delivery), we
recommend a pavement section consisting of at least a 4-inch thickness of ½-inch HMA (PG 58-22) over a
6-inch thickness of densely compacted crushed rock base course. The base course should be compacted
to at least 95 percent of the MDD (ASTM D 1557). We recommend that a proof-roll of the compacted base
course be observed by the geotechnical engineer of record prior to paving. Soft or yielding areas observed
during proof-rolling may require over-excavation and replacement with compacted structural fill.
The pavement sections recommended above are based on our experience. Thicker asphalt sections may
be needed based on the actual subgrade conditions, traffic data and intended use, or City of Renton
requirements.
Homestead Community Land Trust | November 18, 2024 Page 27
File No. 23656-001-01
4.9.3 Portland Cement Concrete Pavement
PCC sections should be considered for loading dock aprons, trash dumpster areas and where other
concentrated heavy loads may occur. We recommend that these pavements consist of at least 6 inches of
PCC over 6 inches of crushed rock base course. A thicker concrete section may be needed based on the
actual traffic data. If the concrete pavement will have doweled joints, we recommend that the concrete
thickness be increased by an amount equal to the diameter of the dowels. The base course should be
compacted to at least 95 percent MDD.
We recommend PCC pavements incorporate construction joints and/or crack control joints spaced
maximum distances of 12 feet apart, center-to-center, in both the longitudinal and transverse directions.
Crack control joints may be created by placing an insert or groove into the fresh concrete surface during
finishing, or by sawcutting the concrete after it has initially set-up. We recommend the depth of the crack
control joints be approximately one-fourth the thickness of the concrete; or about 1.5 inches deep for the
recommended concrete thickness of 6 inches. We also recommend the crack control joints be sealed with
an appropriate sealant to help restrict water infiltration into the joints.
4.10 DRAINAGE CONSIDERATIONS
The contractor should anticipate shallow perched groundwater conditions may exist, and seepage may
enter excavations depending on the time of year construction takes place, especially in the spring and
winter months. However, we expect this seepage water can be handled by digging interceptor trenches in
the excavations and pumping from sumps. The seepage water, if not intercepted and removed from the
excavations, will make it difficult to place and compact structural fill and may destabilize cut slopes.
All paved and landscaped areas should be graded so surface drainage is directed away from the buildings
to appropriate catch basins.
Water collected in roof downspout lines must not discharge into or be routed to the perforated pipes
intended for footing, underslab or wall drainage.
4.11 INFILTRATION CONSIDERATIONS
Sieve analyses were performed on selected soil samples collected from the test pits that were completed
as part of this study, as well as from previous explorations complete at and within the site vicinity. The soil
samples typically consisted of native weathered or relatively unweathered glacial till. The design infiltration
value described below is based on the results of the grain size analyses, the United States Department of
Agriculture (USDA) Textural Triangle, and the Washington State Department of Ecology Storm Water
Management Manual (2024). The grain size analyses are presented in Appendix B.
Based on our analysis, it is our opinion that the on-site native glacial till soils have a very low infiltration
capacity. The majority of the soils across the site contain significant fines, which limits the infiltration
capacity. The results of the sieve analyses indicated that the fines content (material passing the U.S.
No. 200 sieve) typically ranges from 25 to 35 percent. Due to the density, high fines content and relative
impermeability of the glacial till, infiltration should be assumed to be very low when designing infiltration
systems. We recommend a preliminary infiltration rate of not more than 0.2 inches per hour be used for
design of the infiltration facilities. Depending on the depth of proposed infiltration facilities, the infiltration
rate will vary; however, we recommend site specific pilot infiltration testing be performed to determine the
design infiltration rate if specific infiltration facilities are being considered.
Homestead Community Land Trust | November 18, 2024 Page 28
File No. 23656-001-01
5.0 Recommended Additional Geotechnical Services
Throughout this report, recommendations are provided where we consider additional geotechnical services
to be appropriate. These additional services are summarized below:
■ GeoEngineers should be retained to review the project plans and specifications when complete to
confirm that our design recommendations have been implemented as intended.
■ GeoEngineers should be retained to provide additional recommendations for design of stormwater
infiltration facilities, including performing pilot infiltration testing, if infiltration is being considered at
the site.
■ During construction, GeoEngineers should observe the installation and evaluate the performance of
temporary shoring (if used) and cut slopes, observe and evaluate the suitability of the wall and
foundation subgrades, observe removal of unsuitable soils, evaluate the suitability of floor slab and
pavement subgrades, observe installation of subsurface drainage measures including footing drains
and underslab drains, observe and test structural backfill including wall and trench backfill and provide
a summary letter of our construction observation services. The purposes of GeoEngineers construction
phase services are to confirm that the subsurface conditions are consistent with those observed in the
explorations and other reasons described in Appendix E.
6.0 Limitations
We have prepared this report for the exclusive use of Homestead Community Land Trust and their
authorized agents for design and construction of the proposed project. Our report, conclusions and
interpretations should not be construed as a warranty of the subsurface soil conditions.
Within the limitations of scope, schedule and budget, our services have been executed in accordance with
generally accepted practices in the field of geotechnical engineering in this area at the time this report was
prepared. No warranty or other conditions, express or implied, should be understood.
Any electronic form, facsimile or hard copy of the original document (email, text, table and/or figure), if
provided, and any attachments are only a copy of the original document. The original document is stored
by GeoEngineers, Inc. and will serve as the official document of record.
Please refer to Appendix E for additional information pertaining to use of this report.
Homestead Community Land Trust | November 18, 2024 Page 29
File No. 23656-001-01
7.0 References
ASCE 7-16, 2016, “Minimum design loads for buildings and other structures.”
Applied Technology Council, “Hazards by Location” accessed via: https://hazards.atcouncil.org/#/.
GeoEngineers, Inc., “Geotechnical Engineering Services, Sunset Crest Townhomes, Renton, Washington,”
dated November 15, 2018.
International Code Council, “International Building Code,” 2021.
Mullineaux, D.R. et al., 1961, “Preliminary Geologic Map of Seattle and Vicinity, Washington.”
Soil & Environmental Engineers, Inc., “Report of Geotechnical Investigation, Proposed Residential
Development, Edmonds and Glennwood Ave NE, Renton, Washington,” dated January 10, 2011.
U.S. Department of Transportation, Federal Highways Administration, 1999, “Geotechnical Engineering
Circular No. 4, Ground Anchors and Anchored Systems,” FHWA Report No. FHWA-IF-99-015.
Washington Administration Code, “Title 296, Chapter 296-155, Part N, “Excavation, Trenching and
Shoring,” November 2024.
Washington State Department of Transportation, Geotechnical Design Manual, 2022.
Washington State Department of Transportation. 2024. “Standard Specifications for Road, Bridge and
Municipal Construction.”
Figures
Lake Washington
Renton
Municipal
Airport
M a y C r e e k
Pa
rk
A
v
e
N
N 32nd S t
N 30th St
N 3 1st S t
N 29th St
SE
9
1
s
t
S
t
May Creek Park
- County
May Creek Park
900
H
o
u
s
e
r
Wa
y
N
NE 20th
S
t
J
o
n
e
s
A
v
e
N
E
Ga
r
d
e
n
A
v
e
N
NE
1
2
t
h
S
t
NE 1 6th St
NE 7th S t
N 8th S t
NE
9
th St
M
o
n
r
o
e
A
v
e
N
E
NE 4t h St
M
o
n
t
e
r
e
y
A
v
e
NE
R
e
d
m
o
n
d
A
v
e
NE
NE 27th St
NE
2
4
t h
S
t
NE
S
u
n
s
e
t
Blv
d
Logan
A
v
e
N
S uns e t
B
lvd
N
E
S
u
n
s
et
B
l
vd
N
E
P
a
r
k
A
v
e
N
NE 4t h S tN 4 t h S t
The Landing
Honey Creek
Open Space
Gene Coulon
Memorial Beach
Park
N
1
s
t
S
t
N E
3
r
d
S
t
N 3rd St Greenwood
Memorial Park
Cedar River
Park - Renton
May Creek
NE
6
th St
U
n
i
o
n
A
v
e
N
E
NE
1
0
t
h
St
NE
7
t
h
P
l
NE
2
4
t
h
S
t
NE 17th St
D
u
v
a
ll
A
v
e
NE
NE S uns et B lv d
May Creek
Open Space
Maplewood
Heights
Elementary
School
1
SITE
Vicinity Map
Figure 1
Willowcrest Townhomes Phase II
Renton, Washington
101
Alpine Lakes
Wilderness
Kent
Everett
Seattle 0 2,000
Feet
P:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
S
\
2
3
6
5
6
0
0
1
_
P
r
o
j
e
c
t
\
2
3
6
5
6
0
0
1
_
P
r
o
j
e
c
t
.
a
p
r
x
\
2
3
6
5
6
00
1
0
1
_
F
0
1
_
V
i
c
i
n
i
t
y
M
a
p
D
a
t
e
E
x
p
o
r
t
e
d
:
1
1
/
0
1
/
2
4
b
y
J
f
e
l
l
o
w
s
Source(s):
• ESRI
Coordinate System: NAD 1983 StatePlane Washington North FIPS 4601 Feet
Disclaimer: This figure was created for a specific purpose and project. Any use of this figure
for any other project or purpose shall be at the user's sole risk and without liability to GeoEngineers.
The locations of features shown may be approximate. GeoEngineers makes no warranty or
representation as to the accuracy, completeness, or suitability of the figure, or data contained
therein. The file containing this figure is a copy of a master document, the original of which is
retained by GeoEngineers and is the official document of record.
3
1
0
3
1
5
3
2
0
325
3
3
0
3
1
1
3
1
2
3
1
3
3
1
4
3
1
6
3
1
7
3
1
8
3
1
9
32
1
32
2
32
3
32
4
326
3
2
7
3
2
8
3
2
9
31
0
31
5
32
0
3
2
5
33
0
3
0
9
31
1
31
2
31
3
314
31
6
31
7
31
8
31
9
32
2
3
2
3
3
2
4
3
2
6
3
2
7
32
8
32
9
33
1
3
3
2
290
295
300
305
310
291
292
293
294
296
297
298
299
301
302
303
304
306
307
308
309
311
312
313
33
1
3
3
2
33
3
33333
3
33
533
1
33
2
33
3
33
4
33
6
3
3
5
3
3
6
3
3
7
33
8
34
0
341342343
3
3
5
333
3
3
3
33
4
33
4
3
3
6
3
3
7
3
3
8
33
3
335
334
330
329
331
33
2
333
30
5
3
1
0
3
1
5
3
2
0
32
5
330
30
1
30
1
30
2
30
3
30
4
30
6
30
7
30
8
30
9
3
1
1
3
1
2
3
1
3
3
1
4
3
1
6
3
1
7
3
1
8
3
1
9
3
2
1
3
2
2
32
3
32
4
3
2
6
3
2
7
3
2
8
3
2
9
29
2
29
3
294
3
0
5
31
0
3
1
5
32
0
3
2
5
33
0
3
0
3
3
0
4
3
0
6
30
7
30
8
30
9
31
1
31
2
31
3
31
4 31
6
31
7
31
8
31
9
32
1
32
2
32
3
32
4
326 32
7
32
8
32
9
3
1
0
3
1
5
32
0
3
2
5
3
0
8
3
0
9
3
1
1
3
1
2
3
1
3
3
1
4
3
1
6
31
7
31
7
3
1
7
31
8
31
9
32
1
32
2
32
3
32
4
32
6
32
7
3
3
0
3
2
9
3
3
1
3
3
2
3
3
3
Ed
m
o
n
d
s
A
v
e
N
E
Gl
e
n
w
o
o
d
A
v
e
N
E
GEI-TP-1
GEI-TP-2
GEI-TP-3
GEI-TP-4
GEI-TP-5
GEI-TP-6
B-1
B-2
TP-1
TP-2
TP-3
TP-4 TP-5
TP-6
GEI-TP-11
GEI-TP-10
GEI-TP-12
GEI-TP-8
GEI-TP-7
GEI-TP-9
Re
t
a
i
n
i
n
g
W
a
l
l
Re
t
a
i
n
i
n
g
W
a
l
l
Figure 2
Site Plan
P:
\
2
3
\
2
3
6
5
6
0
0
1
\
C
A
D
\
0
1
\
G
e
o
t
e
c
h
\
2
3
6
5
6
0
0
1
0
1
_
F
0
2
_
S
i
t
e
P
l
a
n
.
d
w
g
T
A
B
:
F
0
2
D
a
t
e
E
x
p
o
r
t
e
d
:
1
1
/
1
2
/
2
4
-
8
:
0
7
b
y
J
f
e
l
l
o
w
s
Legend
Test Pit by GeoEngineers, 2018GEI-TP-1
Boring by Soil & Environmental Engineers, 2011B-1
Test Pit by Soil & Environmental Engineers, 2011TP-1
Site Boundary
Source(s):
·Survey from Lank Tree Land Surveying, dated 11/6/24
·Proposed site features from Third Place Design Co-op, dated 9/13/24
Coordinate System: WA State Plane, North Zone, NAD83, US Foot
Disclaimer: This figure was created for a specific purpose and project. Any use of this figure for any other
project or purpose shall be at the user's sole risk and without liability to GeoEngineers. The locations of
features shown may be approximate. GeoEngineers makes no warranty or representation as to the accuracy,
completeness, or suitability of the figure, or data contained therein. The file containing this figure is a copy of
a master document, the original of which is retained by GeoEngineers and is the official document of record.Feet
0 40
N
Willowcrest Townhomes Phase II
Renton, Washington
GEI-TP-7 Test Pit by GeoEngineers, 2024 (Current Study)
Building C
FFE Varies from 325' - 332.5'
Building B
FFE = 323'
Building A
FFE = 320.5'
Building E
FFE Varies from
320' - 321'
Building D
FFE Varies from
322.5' - 324'
h1
Earth Pressure Diagrams -
Temporary Soldier Pile & Tieback Wall
Notes:
1. Active/apparent earth pressure and traffic surcharge pressure act over the
pile spacing above the base of the excavation.
2. Passive earth pressure acts over 3 times the concreted diameter of the
soldier pile, or the pile spacing, whichever is less.
3. Passive pressure includes a factor of safety of 1.5 and includes the net
pressure (difference between active and passive) below the base of
excavation.
4. Additional surcharge from footings of adjacent buildings should be included
in accordance with recommendations provided on Figure 4.
5. This pressure diagram is appropriate for temporary soldier pile and tieback
walls. If additional surcharge loading (such as from soil stockpiles,
excavators, dumptrucks, cranes, or concrete trucks) is anticipated,
GeoEngineers should be consulted to provide revised surcharge pressures.
H/5
60°
P
P= 27.H psf
2'
H
D
15'
55
psf
400.D
psf
Ground Surface
Net Allowable
Passive Pressure
Apparent
Earth
Pressure
Traffic
Surcharge
Pressure
Conventional Soldier Pile Wall with One Level of Tiebacks Conventional Soldier Pile Wall with Multiple Levels of Tiebacks
H
3
2(H-H1)
3
2.H1
3
H/5
60°
P
P= 22.H psf
2'
H
D
15'
55
psf
400.D
psf
Ground Surface
Net Allowable
Passive Pressure
Apparent
Earth
Pressure
Traffic
Surcharge
Pressure
0.2H
Not To Scale
H =
D =
Height of Excavation, Feet
Soldier Pile Embedment Depth, Feet
Maximum Apparent Earth Pressure,
Pounds per Square Foot
Design Groundwater Elevation for Drained Walls/
Passive Resistance Design
P =
T = Horizontal Load in Uppermost Ground Anchor
Distance From Ground Surface to
Uppermost Tieback, FeetH =1
Legend
No Load Zone
H1
Th1
0.2H
1 1
400
Willowcrest Townhomes Phase II
Renton, Washington
Figure 3
P:
\
2
3
\
2
3
6
5
6
0
0
1
\
C
A
D
\
0
1
\
G
e
o
t
e
c
h
\
2
3
6
5
6
0
0
1
0
1
_
F
0
3
_
E
P
D
.
d
w
g
T
A
B
:
3
D
a
t
e
E
x
p
o
r
t
e
d
:
1
1
/
1
1
/
2
4
-
1
1
:
5
8
b
y
J
f
e
l
l
o
w
s
H/2 H/2
400
400.D
psf
H
D
27.H psf 55
psf
2'
Base of
Excavation
27
1
Ground Surface
Cantilever Soldier Pile
Active
Earth
Pressure
Traffic
Surcharge
Pressure
Net Allowable
Passive Pressure
15'
1
400
Base of
Excavation
Base of
Excavation
Figure 4
P:
\
2
3
\
2
3
6
5
6
0
0
1
\
C
A
D
\
0
1
\
G
e
o
t
e
c
h
\
2
3
6
5
6
0
0
1
0
1
_
F
0
4
_
R
S
P
.
d
w
g
T
A
B
:
4
D
a
t
e
E
x
p
o
r
t
e
d
:
1
1
/
1
2
/
2
4
-
8
:
0
8
b
y
J
f
e
l
l
o
w
s
H
X= m H
X= m H
Z=nH
R
H
X= m H
Z=nH
R
σH
m R
0.1 0.60H
0.3 0.60H
0.5 0.56H
0.7 0.48H
Q P
For m ≤ 0.4
H2(0.16+n2 )3
For m > 0.4
q (psf)
0.2 · q (psf)
Section A-A'
H
Point load in pounds
Line load in pounds/foot
Excavation height below footing, feet
Lateral earth pressure from surcharge, psf
Surcharge pressure in psf
Radians
Distribution of σH in plan view
Resultant lateral force acting on wall, pounds
Distance from base of excavation to resultant lateral force, feet
H
'
m
P
R
0.2 0.78 0.59H
0.4 0.78 0.59H
0.6 0.45 0.48H
Recommended Surcharge Pressure
Fa
c
e
o
f
W
a
l
l
σH
σ
QP =
QL =
H =
σH =
q =
σ'H =
PH =
R =
σ
Notes:
1. Procedures for estimating surcharge pressures shown above are based on Manual
7.02 Naval Facilities Engineering Command, September 1986 (NAVFAC DM 7.02).
2. Lateral earth pressures from surcharge should be added to earth pressures
presented on Figure 3.
3. See report text for where surcharge pressures are appropriate.
4. Determination of surcharge factor (k). Flexible is for a system that allows small
movements (temporary shoring, retaining walls, etc.) and rigid is for a system that
does not allow small movements (permanent basement walls, below grade utility
structures, etc.). If permanent basement walls are cast/poured directly against
temporary shoring, then the lateral surcharge factor should be assumed as flexible
when analyzing lateral surcharges.
θ
θ =
PH H
Q( )
Pressures from Point Load QP
QP
PH
Lateral Earth Pressure from Point Load, QP
(Spread Footing)
QL
PH
Lateral Earth Pressure from Line Load,
QL (Continuous Wall Footing)
Uniform Surcharges,
q (Floor Loads, Large Foundation
Elements or Traffic Loads)
σH = Lateral Surcharge Pressure from
Uniform SurchargeσH= K · 0.28QPn2
H2(m2+n2 )3
σH = K · 1.77QPm2n2
σ'H = σ COS2 (1.1θ )
Resultant PH = K · 0.64QL
(m2 +1)
For m ≤ 0.4
H(0.16+n2 )2
For m > 0.4
σH = K · 0.2n · QL
H(m2+n2 )2
σH = K · 1.28m2nQL
Definitions:
Base of Excavation Base of Excavation Base of Excavation
A A'
σH
Resultant lateral force acting on wall, poundsX =
Depth of σH to be evaluated below the bottom of QP or QLZ =
Ratio of X to Hm =
Ratio of Z to Hn =
Not To Scale
Wall Type Surcharge Factor, k
Rigid 1.0
Flexible 0.5
Willowcrest Townhomes Phase II
Renton, Washington
Figure 5
P:
\
2
3
\
2
3
6
5
6
0
0
1
\
C
A
D
\
0
1
\
G
e
o
t
e
c
h
\
2
3
6
5
6
0
0
1
0
1
_
F
0
5
_
W
a
l
l
D
r
a
i
n
a
g
e
.
d
w
g
T
A
B
:
5
D
a
t
e
E
x
p
o
r
t
e
d
:
1
1
/
1
1
/
2
4
-
1
2
:
0
0
b
y
J
f
e
l
l
o
w
s
Floor Slab
4"
2' Min.
12" Min. Cover Of
Drainage Material (6"
Min. On Sides Of Pipe)
MATERIALS:
Not To Scale
May consist of "Gravel Backfill for Drains" per WSDOT Standard Specification 9-03.12(4), surrounded with a non-woven geotextile such
as Mirafi 140N (or approved equivalent). Alternatively, the wall drainage material may consist of Gravel Borrow Per WSDOT Standard
Specification 9-03.14(1) when used in combination with geocomposite drainage board.
Geotextile Filter Fabric
Temporary
Excavation Slope
Pavement Or 24"
Low Permeability Soil
Retained Soil
Sloped To Drain Away
From Structure
4" Diameter
Perforated Drain Pipe
Capillary Break
Vapor Retarder
Damp Proofing/Water Proofing
Geocomposite Drainage Board Per Others
Wall Drainage Material
Exterior Wall
Should consist of structural fill, either on-site soil or imported. The backfill should be compacted in loose lifts not exceeding 6 inches.
Wall backfill supporting building floor slabs should consist of imported sand and gravel per WSDOT Standard Specification 9-03.14
compacted to at least 95 percent ASTM D1557. Backfill not supporting building floor slabs, sidewalks, or pavement should be
compacted to 90 to 92 percent of the maximum dry density, per ASTM D1557. Backfill supporting sidewalks or pavement areas should
be compacted to at least 95 percent in the upper two feet. Only hand-operated equipment should be used for compaction within 5 feet
of the walls and no heavy equipment should be allowed within 5 feet of the wall.
Should consist of a 4-inch diameter perforated heavy-wall solid pipe (SDR-35 PVC) or rigid corrugated polyethylene pipe (ADS N-12) or
equivalent. Drain pipes should be placed with 0.25 percent minimum slopes and discharge to the storm water collection system.
Should consist of at least 4 inches of clean crushed gravel with a maximum size of 1-inch and negligible sand or fines, per WSDOT
9-03.1(4)c Grading No. 67.
A. WALL DRAINAGE MATERIAL
B. RETAINED SOIL
C. CAPILLARY BREAK
D. PERFORATED DRAIN PIPE
Wall Drainage and Backfill
Willowcrest Townhomes Phase II
Renton, Washington
Compaction Criteria
for Trench Backfill
95
90 90
95
90
Pipe
Varies
Varies
(See Note 1)
2 Feet
Varies
(Modified Proctor)
Pipe Bedding
Trench Backfill
Base Course
Concrete or Asphalt Pavement
Maximum Dry Density, by Test Method ASTM D1557
Recommended Compaction as a Percentage of
Legend
95
Not To Scale
Notes:
1. All backfill under building areas should be compacted to at
least 95 percent per ASTM D1557.
Non-structural
Areas
Hardscape Or
Pavement
Areas
Ground Surface
P:
\
2
3
\
2
3
6
5
6
0
0
1
\
C
A
D
\
0
1
\
G
e
o
t
e
c
h
\
2
3
6
5
6
0
0
1
0
1
_
F
0
7
_
C
o
m
p
a
c
t
i
o
n
C
r
i
t
e
r
i
a
f
o
r
T
r
e
n
c
h
B
a
c
k
f
i
l
l
.
d
w
g
T
A
B
:
7
D
a
t
e
E
x
p
o
r
t
e
d
:
1
1
/
1
1
/
2
4
-
1
2
:
0
0
b
y
J
f
e
l
l
o
w
s
Figure 6
Willowcrest Townhomes Phase II
Renton, Washington
Appendices
Appendix A
Field Explorations
Homestead Community Land Trust | November 18, 2024 Page A-1
File No. 23656-001-01
Appendix A
FIELD EXPLORATIONS
Subsurface soil and groundwater conditions were evaluated through a field exploration program that
consisted of excavating six test pits (GEI-TP-7 through GEI-TP-12) at the approximate locations shown on
Figure 2. Locations of the test pits were determined in the field by pacing and tape measuring distances
from the test pit locations to existing site features. Ground surface elevations were interpolated from the
site survey. Exploration locations and elevations should be considered accurate to the degree implied by
the method used.
The test pits were completed on October 24, 2024 to depths ranging from approximately 7½ to 10½ feet
below the ground surface. The test pits were completed using a track-mounted excavator owned and
operated by Kelly’s Excavating under subcontract to GeoEngineers.
The test pits were continuously monitored by staff from our firm who reviewed and classified the soils
encountered, obtained representative soil samples, observed groundwater conditions and prepared a
detailed log of each test pit.
Disturbed samples of representative soil types were obtained from the excavator bucket at representative
depths. Soils encountered in the test pits were classified in the field in general accordance with
ASTM D 2488, the Standard Practice for Classification of Soils, Visual-Manual Procedure, which is
summarized in Figure A-1. Logs of the test pits are provided in Figures A-2 through A-7.
The test pit logs are based on our interpretation of the field and laboratory data and indicate the various
types of soil and groundwater conditions encountered. The logs also indicate the depths at which these
soils or their characteristics change, although the change may be gradual.
Observations of groundwater conditions were made during the excavations. The groundwater conditions
encountered during excavation of the test pits are presented on the test pit logs. Groundwater conditions
observed during the excavation of the test pits represent short-term condition and may or may not be
representative of the long-term groundwater conditions at the site. Groundwater conditions observed
during test pit excavations should be considered approximate.
Measured groundwater level in exploration,
well, or piezometer
Measured free product in well or piezometer
Distinct contact between soil strata
Approximate contact between soil strata
Contact between geologic units
SYMBOLS TYPICAL
DESCRIPTIONS
GW
GP
SW
SP
SM
FINE
GRAINED
SOILS
SILTS AND
CLAYS
NOTE: Multiple symbols are used to indicate borderline or dual soil classifications
MORE THAN 50%
RETAINED ON
NO. 200 SIEVE
MORE THAN 50%
PASSING
NO. 200 SIEVE
GRAVEL
AND
GRAVELLY
SOILS
SC
LIQUID LIMIT
LESS THAN 50
(APPRECIABLE AMOUNT
OF FINES)
(APPRECIABLE AMOUNT
OF FINES)
COARSE
GRAINED
SOILS
MAJOR DIVISIONS GRAPH LETTER
GM
GC
ML
CL
OL
SILTS AND
CLAYS
SANDS WITH
FINES
SAND
AND
SANDY
SOILS
MH
CH
OH
PT
(LITTLE OR NO FINES)
CLEAN SANDS
GRAVELS WITH
FINES
CLEAN GRAVELS
(LITTLE OR NO FINES)
WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES
CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES
WELL-GRADED SANDS, GRAVELLYSANDS
POORLY-GRADED SANDS, GRAVELLYSAND
SILTY SANDS, SAND - SILT MIXTURES
CLAYEY SANDS, SAND - CLAYMIXTURES
INORGANIC SILTS, ROCK FLOUR,CLAYEY SILTS WITH SLIGHTPLASTICITY
INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS,LEAN CLAYS
ORGANIC SILTS AND ORGANIC SILTYCLAYS OF LOW PLASTICITY
INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS SILTY SOILS
INORGANIC CLAYS OF HIGHPLASTICITY
ORGANIC CLAYS AND SILTS OFMEDIUM TO HIGH PLASTICITY
PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTSHIGHLY ORGANIC SOILS
SOIL CLASSIFICATION CHART
MORE THAN 50%
OF COARSE
FRACTION RETAINED
ON NO. 4 SIEVE
MORE THAN 50%
OF COARSE
FRACTION PASSING
ON NO. 4 SIEVE
SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES
POORLY-GRADED GRAVELS,GRAVEL - SAND MIXTURES
LIQUID LIMIT GREATER
THAN 50
Contact between soil of the same geologic
unit
Material Description Contact
Graphic Log Contact
NOTE: The reader must refer to the discussion in the report text and the logs of explorations for a proper understanding of subsurface conditions.
Descriptions on the logs apply only at the specific exploration locations and at the time the explorations were made; they are not warranted to be
representative of subsurface conditions at other locations or times.
Groundwater Contact
Blowcount is recorded for driven samplers as the number of
blows required to advance sampler 12 inches (or distance noted).
See exploration log for hammer weight and drop.
"P" indicates sampler pushed using the weight of the drill rig.
"WOH" indicates sampler pushed using the weight of the
hammer.
Key to Exploration Logs
Figure A-1
ADDITIONAL MATERIAL SYMBOLS
SYMBOLS
Asphalt Concrete
Cement Concrete
Crushed Rock/
Quarry Spalls
Topsoil
GRAPH LETTER
AC
CC
SOD Sod/Forest Duff
CR
DESCRIPTIONS
TYPICAL
TS
No Visible Sheen
Slight Sheen
Moderate Sheen
Heavy Sheen
Laboratory / Field Tests
%F
%G
AL
CA
CP
CS
DD
DS
HA
MC
MD
Mohs
OC
PM
PI
PL
PP
SA
TX
UC
UU
VS
Sheen Classification
NS
SS
MS
HS
Percent fines
Percent gravel
Atterberg limits
Chemical analysis
Laboratory compaction test
Consolidation test
Dry density
Direct shear
Hydrometer analysis
Moisture content
Moisture content and dry density
Mohs hardness scale
Organic content
Permeability or hydraulic conductivity
Plasticity index
Point load test
Pocket penetrometer
Sieve analysis
Triaxial compression
Unconfined compression
Unconsolidated undrained triaxial compression
Vane shear
Continuous Coring
Bulk or grab
Direct-Push
Piston
Shelby tube
Standard Penetration Test (SPT)
Sampler Symbol Descriptions
Modified California Sampler (6-inch sleeve) or Dames & Moore
Rev. 03/2024
Dark brown silty sand (topsoil)
Brown sandy silt with gravel (stiff to very stiff, moist) (weathered
glacial till)
Light grayish brown silt with sand and gravel (hard, moist) (glacial till)
Light grayish brown silty fine to medium sand with occasional gravel
(very dense, moist)
TS
ML
ML
SM
1
MC
2
MC
3SA
4
5
8
9
10
Probed 0 inches
Probed 0 inches
Probed 0 inches29
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Aerial Imagery.
Da
t
e
:
1
1
/
1
4
/
2
4
P
a
t
h
:
P
:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
1
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
23656-001-01
Log of Test Pit GEI-TP-7
Figure A-2
Willowcrest Townhomes Phase II
Renton, Washington
El
e
v
a
t
i
o
n
(
f
e
e
t
)
32
0
31
9
31
8
31
7
31
6
31
5
31
4
31
3
31
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
9
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/24/2024 9.5
321
NAVD88
1306249
186101
WA State Plane North
NAD83 (feet)
JSP
Checked By SK
Groundwater not observed
Caving not observedEquipment Takeuchi TB 138 Excavator
Logged By Excavator
Dark brown silty sand with organic matter (topsoil)
Brown silty fine to medium sand with gravel (medium dense, moist)
(weathered glacial till)
Light gray silty fine to medium sand with gravel (very dense, moist)
(glacial till)
TS
SM
SM
1
MC
2MC
3
SA
4
6
7
7 29
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Aerial Imagery.
Da
t
e
:
1
1
/
1
4
/
2
4
P
a
t
h
:
P
:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
1
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
23656-001-01
Log of Test Pit GEI-TP-8
Figure A-3
Willowcrest Townhomes Phase II
Renton, Washington
El
e
v
a
t
i
o
n
(
f
e
e
t
)
32
7
32
6
32
5
32
4
32
3
32
2
32
1
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/24/2024 7.5
328
NAVD88
1306326
186093
WA State Plane North
NAD83 (feet)
JSP
Checked By SK
Groundwater not observed
Caving not observedEquipment Takeuchi TB 138 Excavator
Logged By Excavator
Dark brown silty sand with organic matter (topsoil)
Light brown silty fine to medium sand with gravel; organic matter
(loose, moist) (fill)
Light gray silty fine to medium sand with gravel (dense to very dense,
moist) (glacial till)
Gray silty fine to coarse gravel with cobbles (dense to very dense,
moist)
Grayish brown silty fine to medium sand with occasional gravel
(dense to very dense, moist)
TS
SM
SM
GM
SM
1
MC
2MC
3
4
5
5
5
Probed 10 inches
Probed 8 inches
Probed 4 inches
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Aerial Imagery.
Da
t
e
:
1
1
/
1
4
/
2
4
P
a
t
h
:
P
:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
1
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
23656-001-01
Log of Test Pit GEI-TP-9
Figure A-4
Willowcrest Townhomes Phase II
Renton, Washington
El
e
v
a
t
i
o
n
(
f
e
e
t
)
31
5
31
4
31
3
31
2
31
1
31
0
30
9
30
8
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/24/2024 8.5
316
NAVD88
1306242
185969
WA State Plane North
NAD83 (feet)
JSP
Checked By SK
Groundwater not observed
Caving not observedEquipment Takeuchi TB 138 Excavator
Logged By Excavator
Dark gray fine to coarse gravel with silt and sand; construction debris
(concrete, fabric and plastic) (loose, moist) (fill)
Brown silty fine to medium sand with gravel (dense to very dense,
moist) (weathered glacial till)
Gray silty fine sand (very dense, moist) (glacial till)
GP-GM
SM
SM
1
2
MC
3SA
4
MC
5
11
9
8
Probed 2 inches
Probed 0 inches
Probed 0 inches16
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Aerial Imagery.
Da
t
e
:
1
1
/
1
4
/
2
4
P
a
t
h
:
P
:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
1
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
23656-001-01
Log of Test Pit GEI-TP-10
Figure A-5
Willowcrest Townhomes Phase II
Renton, Washington
El
e
v
a
t
i
o
n
(
f
e
e
t
)
32
5
32
4
32
3
32
2
32
1
32
0
31
9
31
8
31
7
31
6
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
9
10
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/24/2024 10.5
326
NAVD88
1306342
185988
WA State Plane North
NAD83 (feet)
JSP
Checked By SK
Groundwater not observed
Caving not observedEquipment Takeuchi TB 138 Excavator
Logged By Excavator
Brown silty sand with organic matter (topsoil)
Brown silty fine to medium sand; organic matter (loose, moist)
(weathered glacial till)
Boulder
Light grayish brown silty fine to medium sand with occasional gravel
(dense to very dense, moist) (glacial till)
TS
SM
SM
1
MC
2MC
3MC
4
6
7
8
Probed 10 inches
Probed 10 inches
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Aerial Imagery.
Da
t
e
:
1
1
/
1
4
/
2
4
P
a
t
h
:
P
:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
1
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
23656-001-01
Log of Test Pit GEI-TP-11
Figure A-6
Willowcrest Townhomes Phase II
Renton, Washington
El
e
v
a
t
i
o
n
(
f
e
e
t
)
31
6
31
5
31
4
31
3
31
2
31
1
31
0
30
9
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/24/2024 8.5
317
NAVD88
1306253
185909
WA State Plane North
NAD83 (feet)
JSP
Checked By SK
Groundwater not observed
Caving not observedEquipment Takeuchi TB 138 Excavator
Logged By Excavator
Dark brown silty sand with organic matter (topsoil)
Brown silty fine to medium sand with gravel; organic matter
(loose, moist) (fill)
Orange Fabric
Tan silty fine to medium sand with gravel (very dense, moist)
(glacial till)
TS
SM
SM
1
MC
2MC
3
SA
4
5
6
4
Probed 6 inches
Probed 0 inches
28
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Aerial Imagery.
Da
t
e
:
1
1
/
1
4
/
2
4
P
a
t
h
:
P
:
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
1
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
23656-001-01
Log of Test Pit GEI-TP-12
Figure A-7
Willowcrest Townhomes Phase II
Renton, Washington
El
e
v
a
t
i
o
n
(
f
e
e
t
)
32
7
32
6
32
5
32
4
32
3
32
2
32
1
32
0
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/24/2024 8.5
328
NAVD88
1306363
185909
WA State Plane North
NAD83 (feet)
JSP
Checked By SK
Groundwater not observed
Caving not observedEquipment Takeuchi TB 138 Excavator
Logged By Excavator
Appendix B
Laboratory Testing
Homestead Community Land Trust | November 18, 2024 Page B-1
File No. 23656-001-01
Appendix B
LABORATORY TESTING
Soil samples obtained from the test pits were visually classified in the field before being transported to our
laboratory and evaluated to confirm or modify field classifications, as well as to evaluate index properties
of the soil samples. Representative samples were selected for laboratory testing consisting of moisture
content and grain size distribution (sieve analysis). The tests were performed in general accordance with
test methods of the ASTM International (ASTM) or other applicable procedures.
Visual Classifications
Soil samples obtained from the test pits were visually classified in the field and/or in our laboratory using
a system based on the Unified Soil Classification System (USCS) and ASTM classification methods. ASTM
test method D 2488 was used to visually classify the soil samples, while ASTM D 2487 was used to classify
the soils based on laboratory tests results. These classification procedures are incorporated in the test pit
logs shown in Appendix A.
Moisture Content
Moisture content tests were completed in general accordance with ASTM D 2216 for representative
samples obtained from the test pits. The results of these tests are presented on the test pit logs in
Appendix A at the depths at which the samples were obtained.
Grain Size Distribution
Sieve analyses were performed on selected samples in general accordance with ASTM D 6913. The wet
sieve analysis method was used to estimate the percentage of soil greater than the U.S. No. 200
mesh sieve. The results of the sieve analyses were plotted, classified in general accordance with the USCS,
and presented in Figure B-1.
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.11101001000
PE
R
C
E
N
T
P
A
S
S
I
N
G
B
Y
W
E
I
G
H
T
GRAIN SIZE IN MILLIMETERS
U.S. STANDARD SIEVE SIZE
2”
SAND SILT OR CLAYCOBBLES
GRAVEL
COARSE MEDIUM FINECOARSEFINE
Boring Number
Depth
(feet)Soil Description
GEI-TP-7
GEI-TP-8
GEI-TP-10
GEI-TP-12
4
6
4
6
Silty fine to medium sand with occasional gravel(SM)
Silty fine to medium sand with gravel (SM)
Silty fine sand (SM)
Silty fine to medium sand with gravel (SM)
Symbol
Moisture
(%)
10
7
9
4
3/8”3” 1.5”#4 #10 #20 #40 #60 #1003/4”
Fi
g
u
r
e
B
-
1
Si
e
v
e
A
n
a
l
y
s
i
s
R
e
s
u
l
t
s
Wi
l
l
o
w
c
r
e
s
t
T
o
w
n
h
o
m
e
s
P
h
a
s
e
I
I
Re
n
t
o
n
,
W
a
s
h
i
n
g
t
o
n
23656-001-00 Date Exported: 11/14/2024
Note: This report may not be reproduced, except in full, without written approval of GeoEngineers, Inc. Test results are applicable only to the specific sample on which they were
performed, and should not be interpreted as representative of any other samples obtained at other times, depths or locations, or generated by separate operations or processes.
The grain size analysis results were obtained in general accordance with ASTM D6913. GeoEngineers 17425 NE Union Hill Road Ste 250, Redmond, WA 98052
#2001”#140
Appendix C
Exploration Logs from Previous Studies
Homestead Community Land Trust | November 18, 2024 Page C1
File No. 23656-001-01
Appendix C
EXPLORATION LOGS FROM PREVIOUS STUDIES
Included in Appendix C are relevant logs from available previous studies completed in the immediate vicinity
of the project site.
■ The logs of six test pits (GEI-TP-1 through GEI-TP-6) completed by GeoEngineers, Inc., in 2018 for
Phase I of the Willowcrest Townhomes project.
■ The logs of two borings (B-1 and B-2) and six test pits (TP-1 through TP-6) completed by Soil and
Environmental Engineers, Inc., in 2010 for the Proposed Development at Edmonds Avenue NE and
Glennwood Avenue NE project.
Blackberry brambles
Dark brown fine to medium sand with silt, occasional gravel, roots
(loose, moist) (fill)
Light brown silty fine to medium sand with gravel, occasional cobbles,
trace roots (medium dense, moist) (weathered glacial till)
Gray silty fine to medium sand with gravel (very dense, moist) (glacial
till)
WD
SP-SM
SM
SM
1
SA
2
%F
3
4
4
3
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 6 inches
0.5 kg/cm2 / 4 inches
>4.5 kg/cm2 / ½ inch
>4.5 kg/cm2 / <½ inch
21
30
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Da
t
e
:
1
1
/
5
/
1
8
P
a
t
h
:
W
:
\
P
R
O
J
E
C
T
S
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
0
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-1
Sunset Crest Townhomes
Figure A-2
El
e
v
a
t
i
o
n
(
f
e
e
t
)
33
9
33
8
33
7
33
6
33
5
33
4
33
3
33
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/22/2018 8
340
NAVD88
1306462
186084
WA State Plane North
NAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Dark brown fine to medium sand with silt, roots (loose, moist) (fill)
Brown silty coarse gravel with sand and occasional cobbles, roots
(medium dense to dense, moist) (weathered glacial till)
No roots below 2 feet
Gray silty fine sand with occasional gravel and cobbles (very dense,
moist) (glacial till)
WD
SP-SM
GM
SM
1
SA
2
3
4
3
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 8 inches
1.0 kg/cm2 / 3 inches
>4.5 kg/cm2 / 1 inch
>4.5 kg/cm2 / ¼ inch
17
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Da
t
e
:
1
1
/
5
/
1
8
P
a
t
h
:
W
:
\
P
R
O
J
E
C
T
S
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
0
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit TEI-TP-2
Sunset Crest Townhomes
Figure A-3
El
e
v
a
t
i
o
n
(
f
e
e
t
)
33
9
33
8
33
7
33
6
33
5
33
4
33
3
33
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/22/2018 8
340
NAVD88
1306453
186046
WA State Plane North
NAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Dark brown fine to medium sand with silt and occasional gravel, roots
(loose, moist) (fill)
Light brown silty fine sand with gravel and occasional cobbles, roots
(loose to medium dense, moist) (weathered glacial till)
No roots below 2 feet
Light gray silty fine to medium sand with occasional gravel and cobbles
(very dense, moist) (glacial till)
Gray fine to medium sand with silt, gravel and occasional cobbles (very
dense, moist)
WD
SP-SM
SM
SM
SP-SM
1
SA
2
3
4
5
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
2.0 kg/cm2 / 3 inches
>4.5 kg/cm2 / ½ inch
>4.5 kg/cm2 / ¼ inch
32
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Da
t
e
:
1
1
/
5
/
1
8
P
a
t
h
:
W
:
\
P
R
O
J
E
C
T
S
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
0
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-3
Sunset Crest Townhomes
Figure A-4
El
e
v
a
t
i
o
n
(
f
e
e
t
)
33
9
33
8
33
7
33
6
33
5
33
4
33
3
33
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/22/2018 8
340
NAVD88
1306422
185979
WA State Plane North
NAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Dark brown fine to medium sand with silt and occasional gravel, roots
(loose, moist) (fill)
Light brown silty fine sand with gravel and occasional cobbles (loose to
medium dense, moist) (weathered glacial till)
Light gray silty fine to medium sand with gravel and occasional
cobbles; partially cemented (very dense, moist) (glacial till)
Boulder encountered at 3½ feet
WD
SP-SM
SM
SM
1
2
SA
3
4
6
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
2.25 kg/cm2 / 4 inches
>4.5 kg/cm2 / 1 inch
>4.5 kg/cm2 / ¼ inch
35
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Da
t
e
:
1
1
/
5
/
1
8
P
a
t
h
:
W
:
\
P
R
O
J
E
C
T
S
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
0
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-4
Sunset Crest Townhomes
Figure A-5
El
e
v
a
t
i
o
n
(
f
e
e
t
)
33
9
33
8
33
7
33
6
33
5
33
4
33
3
33
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/22/2018 8
340
NAVD88
1306466
185974
WA State Plane North
NAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Brown fine to medium sand with silt and occasional gravel (loose,
moist) (fill)
Light brown silty fine sand with gravel and cobbles, roots (loose to
medium dense, moist) (weathered glacial till)
Gray silty fine sand with gravel and occasional cobbles; partially
cemented (dense to very dense, moist) (glacial till)
WD
SP-SM
SM
SM
1
%F
2
3
4
8
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
1.5 kg/cm2 / 5 inches
2.5 kg/cm2 / 2 inches
>4.5 kg/cm2 / ¼ inch
26
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Da
t
e
:
1
1
/
5
/
1
8
P
a
t
h
:
W
:
\
P
R
O
J
E
C
T
S
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
0
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-5
Sunset Crest Townhomes
Figure A-6
El
e
v
a
t
i
o
n
(
f
e
e
t
)
33
9
33
8
33
7
33
6
33
5
33
4
33
3
33
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/22/2018 8
340
NAVD88
1306422
185911
WA State Plane North
NAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Blackberry brambles
Brown fine to medium sand with silt and occasional gravel (loose,
moist) (fill)
Light brown silty fine to medium sand with gravel and cobbles, roots
(loose to medium dense, moist) (weathered till)
Gray silty fine to medium sand with gravel and occasional cobbles
(dense to very dense, moist) (glacial till)
WD
SP-SM
SM
SM
1
2
SA
3
4
5
Pocket Pen / Probe Penetration
0.0 kg/cm2 / 12 inches
1.5 kg/cm2 / 5 inches
4.0 kg/cm2 / 1½ inches
>4.5 kg/cm2 / ¼ inch
33
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to ½ foot.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Da
t
e
:
1
1
/
5
/
1
8
P
a
t
h
:
W
:
\
P
R
O
J
E
C
T
S
\
2
3
\
2
3
6
5
6
0
0
1
\
G
I
N
T
\
2
3
6
5
6
0
0
1
0
0
.
G
P
J
D
B
L
i
b
r
a
r
y
/
L
i
b
r
a
r
y
:
G
E
O
E
N
G
I
N
E
E
R
S
_
D
F
_
S
T
D
_
U
S
_
J
U
N
E
_
2
0
1
7
.
G
L
B
/
G
E
I
8
_
T
E
S
T
P
I
T
_
1
P
_
G
E
O
T
E
C
_
%
F
Sheet 1 of 1Project Number:
Project Location:
Project:
Renton, Washington
23656-001-00
Log of Test Pit GEI-TP-6
Sunset Crest Townhomes
Figure A-7
El
e
v
a
t
i
o
n
(
f
e
e
t
)
33
9
33
8
33
7
33
6
33
5
33
4
33
3
33
2
De
p
t
h
(
f
e
e
t
)
1
2
3
4
5
6
7
8
Te
s
t
i
n
g
S
a
m
p
l
e
Gr
a
p
h
i
c
L
o
g
SAMPLE
MATERIAL
DESCRIPTION
Gr
o
u
p
Cl
a
s
s
i
f
i
c
a
t
i
o
n
Sa
m
p
l
e
N
a
m
e
Te
s
t
i
n
g
Mo
i
s
t
u
r
e
Co
n
t
e
n
t
(
%
)
REMARKS
Fi
n
e
s
Co
n
t
e
n
t
(
%
)
Date
Excavated
Surface Elevation (ft)
Vertical Datum
Coordinate System
Horizontal Datum
Easting (X)
Northing (Y)
Total
Depth (ft)10/22/2018 8
340
NAVD88
1306474
185878
WA State Plane North
NAD83 (feet)
AJF
Checked By MAG
Groundwater not observed
Caving not observedEquipment Takeuchi TB138FR
Logged By Excavator Kelly's Excavating, Inc.
Appendix D
Ground Anchor Load Tests and
Shoring Monitoring Program
Homestead Community Land Trust | November 18, 2024 Page D1
File No. 23656-001-01
Appendix D
GROUND ANCHOR LOAD TESTS AND SHORING MONITORING PROGRAM
Ground Anchor Load Testing
The locations of the load tests shall be approved by the Engineer and shall be representative of the field
conditions. Load tests shall not be performed until the ground anchor grout and shotcrete wall facing, where
present, have attained at least 50 percent of the specified 28-day compressive strengths.
Where temporary casing of the unbonded length of test ground anchors is provided, the casing shall be
installed to prevent interaction between the bonded length of the ground anchor and the casing/testing
apparatus.
The testing equipment shall include two dial gauges accurate to 0.001 inch, a dial gauge support, a
calibrated jack and pressure gauge, a pump and the load test reaction frame. The dial gauge should be
aligned within 5 degrees of the longitudinal ground anchor axis and shall be independently supported from
the load frame/jack and the shoring wall. The hydraulic jack, pressure gauge and pump shall be used to
apply and measure the test loads.
The jack and pressure gauge shall be calibrated by an independent testing laboratory as a unit. The
pressure gauge shall be graduated in 100 pounds per square inch (psi) increments or less and shall have
a range not exceeding twice the anticipated maximum pressure during testing unless approved by the
Engineer. The ram travel of the jack shall be sufficient to enable the test to be performed without
repositioning the jack.
The jack shall be independently supported and centered over the ground anchor so that the ground anchor
does not carry the weight of the jack. The jack, bearing plates and stressing anchorage shall be aligned
with the ground anchor. The initial position of the jack shall be such that repositioning of the jack is not
necessary during the load test.
The reaction frame should be designed/sized such that excessive deflection of the test apparatus does not
occur and that the testing apparatus does not need to be repositioned during the load test. If the reaction
frame bears directly on the shoring wall facing, the reaction frame should be designed to not damage the
facing.
VERIFICATION TESTS
Prior to production soil nail/tieback installation, at least two soil nails/tiebacks for each soil type shall be
tested to validate the design pullout value. All test nails/tiebacks shall be installed by the same methods,
personnel, material and equipment as the production anchors. Changes in methods, personnel, material
or equipment may require additional verification testing as determined by the Engineer. At least two
successful verification tests shall be performed for each installation method and each soil type. The
nails/tiebacks used for the verification tests may be used as production nails/tiebacks if approved by the
Engineer.
Homestead Community Land Trust | November 18, 2024 Page D2
File No. 23656-001-01
For soil nails, the unbonded length of the test nails shall be at least 3 feet unless approved otherwise by
the Engineer. The bond length of the test nails shall not be less than 10 feet and shall not be longer than
the bond length that would prevent testing to 200 percent of the design load while not exceeding the
allowable bar load. The allowable bar load during testing shall not exceed 80 percent of the steel ultimate
strength for Grade 150 bars or 90 percent of the steel ultimate strength for Grade 60 and 75 bars.
The allowable tieback load should not exceed 80 percent of the steel ultimate strength.
For soil nails, the design test load shall be determined by multiplying the bond length of the nail times the
design load pullout resistance (load transfer). Tieback design test loads should be the design load specified
on the shoring drawings. Verification test nails/tiebacks shall be incrementally loaded and unloaded in
accordance with the following schedule:
LOAD HOLD TIME
Alignment Load 1 minute
0.25 Design Load (DL) 1 minute
0.5DL 1 minute
0.75DL 1 minute
1.0DL 1 minute
1.25DL 1 minute
1.5DL 60 minutes
1.75DL 1 minute
2.0DL 10 minutes
The alignment load shall be the minimum load required to align the testing apparatus and should not
exceed 5 percent of the design load. The dial gauge should be zeroed after the alignment load is applied.
Nail/tieback deflections during the 1.5DL test load shall be recorded at 1, 2, 3, 5, 6, 10, 20, 30, 50 and
60 minutes.
PROOF TESTS
Proof tests shall be completed on approximately 5 percent of the production nails at locations selected by
the owner’s representative. Additional testing may be required where nail installation methods are
substandard. Proof tests shall be completed on each production tieback.
For soil nails, the unbonded length of the test nails shall be at least 3 feet unless approved otherwise by
the Engineer. The bond length of the test nails shall not be less than 10 feet and shall not be longer than
the bond length that would prevent testing to 200 percent of the design load while not exceeding the
allowable bar load. The allowable bar load during testing shall not exceed 80 percent of the steel ultimate
strength for Grade 150 bars or 90 percent of the steel ultimate strength for Grade 60 and 75 bars.
The allowable tieback load should not exceed 80 percent of the steel ultimate strength.
For soil nails, the design test load shall be determined by multiplying the bond length of the nail times the
design load pullout resistance (load transfer). Tieback design test loads should be the design load specified
on the shoring drawings. Proof test nails/tiebacks shall be incrementally loaded and unloaded in
accordance with the following schedule:
Homestead Community Land Trust | November 18, 2024 Page D3
File No. 23656-001-01
LOAD HOLD TIME
Alignment Load 1 minute
0.25 Design Load (DL) 1 minute
0.5DL 1 minute
0.75DL 1 minute
1.0DL 1 minute
1.25DL (soil nails) 1 minute
1.33DL (tiebacks) 10 minutes 1.5DL (soil nails)
The alignment load shall be the minimum load required to align the testing apparatus and should not
exceed 5 percent of the design load. The dial gauge should be zeroed after the alignment load is applied.
Nail/tieback deflections during the 1.33DL and 1.5DL test loads shall be recorded at 1, 2, 3, 5, 6 and
10 minutes.
Depending upon the nail/tieback deflection performance, the load hold period at 1.33DL (tiebacks) or
1.5DL (soil nails) may be increased to 60 minutes. Nail/tieback movement shall be recorded at 1, 2, 3, 5,
6 and 10 minutes. If the nail/tieback deflection between 1 minute and 10 minutes is greater than
0.04 inches, the 1.33DL/1.5DL load shall be continued to be held for a total of 60 minutes and deflections
recorded at 20, 30, 50, and 60 minutes.
TEST GROUND ANCHOR ACCEPTANCE
A test ground anchor shall be considered acceptable when:
1. For verification tests, a nail/tieback is considered acceptable if the creep rate is less than 0.04 inches
per log cycle of time between 1 and 10 minutes, and the creep rate is linear or decreasing throughout
the creep test load hold period;
2. For proof tests, a ground anchor is considered acceptable if the creep rate is less than 0.04 inches per
log cycle of time between 1 and 10 minutes or less than 0.08 inches per log cycle of time between
6 and 60 minutes, and the creep rate is linear or decreasing throughout the creep test load hold period;
3. The total movement at the maximum test load exceeds 80 percent of the theoretical elastic elongation
of the unbonded length; and
4. Pullout failure does not occur. Pullout failure is defined as the load at which continued attempts to
increase the test load result in continued pullout of the test ground anchor.
Acceptable proof-test ground anchors may be incorporated as production ground anchors provided that the
unbonded test length of the ground anchor hole has not collapsed and the test ground anchor length and
bar size/number of strands are equal to or greater than the scheduled production ground anchor at the
test location. Test ground anchors meeting these criteria shall be completed by grouting the unbonded
length, as necessary. Maintenance of the temporary unbonded length for subsequent grouting is the
contractor’s responsibility.
Homestead Community Land Trust | November 18, 2024 Page D4
File No. 23656-001-01
The Engineer shall evaluate the verification test results. Ground anchor installation techniques that do not
satisfy the ground anchor testing requirements shall be considered inadequate. In this case, the contractor
shall propose alternative methods and install replacement verification test ground anchors.
The Engineer may require that the contractor replace or install additional production ground anchors in
areas represented by inadequate proof tests.
Shoring Monitoring
PRECONSTRUCTION SURVEY
A shoring monitoring program should be established to monitor the performance of the temporary shoring
walls and to provide early detection of deflections that could potentially damage nearby improvements.
We recommend that a preconstruction survey of adjacent improvements, such as streets, utilities and
buildings, be performed prior to commencing construction. The preconstruction survey should include a
video or photographic survey of the condition of existing improvements to establish the preconstruction
condition, with special attention to existing cracks in streets or buildings.
OPTICAL SURVEY
The shoring monitoring program should include an optical survey monitoring program. The recommended
frequency of monitoring should vary as a function of the stage of construction as presented in the following
table.
CONSTRUCTION STAGE MONITORING FREQUENCY
During excavation and until wall movements have stabilized Twice weekly
During excavation if lateral wall movements exceed 1 inch and until wall
movements have stabilized Three times per week
After excavation is complete and wall movements have stabilized, and before
the floors of the building reach the top of the excavation Twice monthly
Monitoring should include vertical and horizontal survey measurements accurate to at least 0.01 feet.
A baseline reading of the monitoring points should be completed prior to beginning excavation. The survey
data should be provided to GeoEngineers for review within 24 hours.
For shoring walls, we recommend that optical survey points be established: (1) along the top of the shoring
walls; (2) at the curb line behind the shoring walls; and (3) on existing buildings/structures located within
100 feet of the site. The survey points should be spaced every other soldier pile for soldier pile walls, every
20 feet for soil nail walls and the points along the curb line/existing buildings should be located at an
approximate spacing of 25 feet. GeoEngineers recommends that a survey monitoring plan be developed
for GeoEngineers’ review prior to establishing the survey points in the field. If lateral wall movements are
observed to be in excess of ½ inch between successive readings or if total wall movements exceed 1 inch,
construction of the shoring walls should be stopped to determine the cause of the movement and to
establish the type and extent of remedial measures required.
Appendix E
Report Limitations and Guidelines for Use
Homestead Community Land Trust | November 18, 2024 Page E-1
File No. 23656-001-01
Appendix E
Report Limitations and Guidelines for Use1
This appendix provides information to help you manage your risks with respect to the use of this report.
Read These Provisions Closely
It is important to recognize that the geoscience practices (geotechnical engineering, geology, and
environmental science) rely on professional judgment and opinion to a greater extent than other
engineering and natural science disciplines, where more precise and/or readily observable data may exist.
To help clients better understand how this difference pertains to our services, GeoEngineers includes the
following explanatory “limitations” provisions in its reports. Please confer with GeoEngineers if you need to
know more how these “Report Limitations and Guidelines for Use” apply to your project or site.
Geotechnical Services Are Performed for Specific Purposes, Persons, and Projects
This report has been prepared for Homestead Community Land Trust and for the Project(s) specifically
identified in the report. The information contained herein is not applicable to other sites or projects.
GeoEngineers structures its services to meet the specific needs of its clients. No party other than the party
to whom this report is addressed may rely on the product of our services unless we agree to such reliance
in advance and in writing. Within the limitations of the agreed scope of services for the Project, and its
schedule and budget, our services have been executed in accordance with our Agreement with Homestead
Community Land Trust dated October 15, 2024 and generally accepted geotechnical practices in this area
at the time this report was prepared. We do not authorize, and will not be responsible for, the use of this
report for any purposes or projects other than those identified in the report.
A Geotechnical Engineering or Geologic Report is Based on a Unique Set of Project-
Specific Factors
This report has been prepared for the proposed Willowcrest Townhomes Phase II project in Renton,
Washington. GeoEngineers considered a number of unique, project-specific factors when establishing the
scope of services for this project and report. Unless GeoEngineers specifically indicates otherwise, it is
important not to rely on this report if it was:
■ Not prepared for you,
■ Not prepared for your project,
■ Not prepared for the specific site explored, or
■ Completed before important project changes were made.
For example, changes that can affect the applicability of this report include those that affect:
1 Developed based on material provided by GBA, GeoProfessional Business Association, www.geoprofessional.org.
Homestead Community Land Trust | November 18, 2024 Page E-2
File No. 23656-001-01
■ The function of the proposed structure,
■ Elevation, configuration, location, orientation or weight of the proposed structure,
■ Composition of the design team; or
■ Project ownership.
If important changes are made after the date of this report, GeoEngineers should be given the opportunity
to review our interpretations and recommendations and provide written modifications or confirmation, as
appropriate.
Subsurface Conditions Can Change
This geotechnical or geologic report is based on conditions that existed at the time the study was performed.
The findings and conclusions of this report may be affected by the passage of time, by man-made events
such as construction on or adjacent to the site, new information or technology that becomes available
subsequent to the report date, or by natural events such as floods, earthquakes, slope instability or
groundwater fluctuations. If more than a few months have passed since issuance of our report or work
product, or if any of the described events may have occurred, please contact GeoEngineers before applying
this report for its intended purpose so that we may evaluate whether changed conditions affect the
continued reliability or applicability of our conclusions and recommendations.
Geotechnical and Geologic Findings are Professional Opinions
Our interpretations of subsurface conditions are based on field observations from widely spaced sampling
locations at the site. Site exploration identifies the specific subsurface conditions only at those points where
subsurface tests are conducted or samples are taken. GeoEngineers reviewed field and laboratory data
and then applied its professional judgment to render an informed opinion about subsurface conditions at
other locations. Actual subsurface conditions may differ, sometimes significantly, from the opinions
presented in this report. Our report, conclusions and interpretations are not a warranty of the actual
subsurface conditions.
Geotechnical Engineering Report Recommendations are Not Final
We have developed the following recommendations based on data gathered from subsurface
investigation(s). These investigations sample just a small percentage of a site to create a snapshot of the
subsurface conditions elsewhere on the site. Such sampling on its own cannot provide a complete and
accurate view of subsurface conditions for the entire site. Therefore, the recommendations included in this
report are preliminary and should not be considered final. GeoEngineers’ recommendations can be
finalized only by observing actual subsurface conditions revealed during construction. GeoEngineers
cannot assume responsibility or liability for the recommendations in this report if we do not perform
construction observation.
Homestead Community Land Trust | November 18, 2024 Page E-3
File No. 23656-001-01
We recommend that you allow sufficient monitoring, testing and consultation during construction by
GeoEngineers to confirm that the conditions encountered are consistent with those indicated by the
explorations, to provide recommendations for design changes if the conditions revealed during the work
differ from those anticipated, and to evaluate whether earthwork activities are completed in accordance
with our recommendations. Retaining GeoEngineers for construction observation for this project is the most
effective means of managing the risks associated with unanticipated conditions. If another party performs
field observation and confirms our expectations, the other party must take full responsibility for both the
observations and recommendations. Please note, however, that another party would lack our project-
specific knowledge and resources.
A Geotechnical Engineering or Geologic Report Could Be Subject to Misinterpretation
Misinterpretation of this report by other design team members can result in costly problems. You could
lower that risk by having GeoEngineers confer with appropriate members of the design team after
submitting the report. Also retain GeoEngineers to review pertinent elements of the design team's plans
and specifications. Contractors can also misinterpret a geotechnical engineering or geologic report. Reduce
that risk by having GeoEngineers participate in pre-bid and preconstruction conferences, and by providing
construction observation.
Do Not Redraw the Exploration Logs
Geotechnical engineers and geologists prepare final boring and testing logs based upon their interpretation
of field logs and laboratory data. The logs included in a geotechnical engineering or geologic report should
never be redrawn for inclusion in architectural or other design drawings. Photographic or electronic
reproduction is acceptable, but separating logs from the report can create a risk of misinterpretation.
Give Contractors a Complete Report and Guidance
To help reduce the risk of problems associated with unanticipated subsurface conditions, GeoEngineers
recommends giving contractors the complete geotechnical engineering or geologic report, including these
“Report Limitations and Guidelines for Use.” When providing the report, you should preface it with a clearly
written letter of transmittal that:
■ Advises contractors that the report was not prepared for purposes of bid development and that its
accuracy is limited; and
■ Encourages contractors to conduct additional study to obtain the specific types of information they
need or prefer.
Contractors Are Responsible for Site Safety on Their Own Construction Projects
Our geotechnical recommendations are not intended to direct the contractor’s procedures, methods,
schedule or management of the work site. The contractor is solely responsible for job site safety and for
managing construction operations to minimize risks to on-site personnel and to adjacent properties.
Homestead Community Land Trust | November 18, 2024 Page E-4
File No. 23656-001-01
Geotechnical, Geologic and Environmental Reports Should Not Be Interchanged
The equipment, techniques and personnel used to perform an environmental study differ significantly from
those used to perform a geotechnical or geologic study and vice versa. For that reason, a geotechnical
engineering or geologic report does not usually relate any environmental findings, conclusions or
recommendations, e.g., about the likelihood of encountering underground storage tanks or regulated
contaminants. Similarly, environmental reports are not used to address geotechnical or geologic concerns
regarding a specific project.
Biological Pollutants
GeoEngineers’ Scope of Work specifically excludes the investigation, detection, prevention, or assessment
of the presence of Biological Pollutants. Accordingly, this report does not include any interpretations,
recommendations, findings, or conclusions regarding the detecting, assessing, preventing or abating of
Biological Pollutants, and no conclusions or inferences should be drawn regarding Biological Pollutants as
they may relate to this project. The term “Biological Pollutants” includes, but is not limited to, molds, fungi,
spores, bacteria, and viruses, and/or any of their byproducts.
A Client that desires these specialized services is advised to obtain them from a consultant who offers
services in this specialized field.
Appendix E
Operations and Maintenance Manual
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual
A-6
NO. 3 – DETENTION TANKS AND VAULTS
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Site Trash and debris Any trash and debris which exceed 1 cubic
foot per 1,000 square feet (this is about
equal to the amount of trash it would take
to fill up one standard size office garbage
can). In general, there should be no visual
evidence of dumping.
Trash and debris cleared from site.
Noxious weeds Any noxious or nuisance vegetation which
may constitute a hazard to City personnel
or the public.
Noxious and nuisance vegetation removed
according to applicable regulations. No
danger of noxious vegetation where City
personnel or the public might normally be.
Contaminants and
pollution
Any evidence of contaminants or pollution
such as oil, gasoline, concrete slurries or
paint.
Materials removed and disposed of
according to applicable regulations. Source
control BMPs implemented if appropriate.
No contaminants present other than a
surface oil film.
Excessive growth of
grass/groundcover
Grass or groundcover exceeds 18 inches
in height.
Grass or groundcover mowed to a height
no greater than 6 inches.
Tank or Vault
Storage Area
Trash and debris Any trash and debris accumulated in vault
or tank (includes floatables and non-
floatables).
No trash or debris in vault.
Sediment
accumulation
Accumulated sediment depth exceeds
10% of the diameter of the storage area for
½ length of storage vault or any point
depth exceeds 15% of diameter. Example:
72-inch storage tank would require
cleaning when sediment reaches depth of
7 inches for more than ½ length of tank.
All sediment removed from storage area.
Tank Structure Plugged air vent Any blockage of the vent. Tank or vault freely vents.
Tank bent out of
shape
Any part of tank/pipe is bent out of shape
more than 10% of its design shape.
Tank repaired or replaced to design.
Gaps between
sections, damaged
joints or cracks or
tears in wall
A gap wider than ½-inch at the joint of any
tank sections or any evidence of soil
particles entering the tank at a joint or
through a wall.
No water or soil entering tank through
joints or walls.
Vault Structure Damage to wall,
frame, bottom, and/or
top slab
Cracks wider than ½-inch, any evidence of
soil entering the structure through cracks
or qualified inspection personnel
determines that the vault is not structurally
sound.
Vault is sealed and structurally sound.
Inlet/Outlet Pipes Sediment
accumulation
Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in
inlet/outlet pipes (includes floatables and
non-floatables).
No trash or debris in pipes.
Damaged inlet/outlet
pipes
Cracks wider than ½-inch at the joint of the
inlet/outlet pipes or any evidence of soil
entering at the joints of the inlet/outlet
pipes.
No cracks more than ¼-inch wide at the
joint of the inlet/outlet pipe.
Access Manhole Cover/lid not in place Cover/lid is missing or only partially in
place. Any open manhole requires
immediate maintenance.
Manhole access covered.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016
A-7
NO. 3 – DETENTION TANKS AND VAULTS
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Access Manhole
(cont.)
Locking mechanism
not working
Mechanism cannot be opened by one
maintenance person with proper tools.
Bolts cannot be seated. Self-locking
cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to
remove
One maintenance person cannot remove
cover/lid after applying 80 lbs of lift.
Cover/lid can be removed and reinstalled
by one maintenance person.
Ladder rungs unsafe Missing rungs, misalignment, rust, or
cracks.
Ladder meets design standards. Allows
maintenance person safe access.
Large access
doors/plate
Damaged or difficult
to open
Large access doors or plates cannot be
opened/removed using normal equipment.
Replace or repair access door so it can
opened as designed.
Gaps, doesn't cover
completely
Large access doors not flat and/or access
opening not completely covered.
Doors close flat; covers access opening
completely.
Lifting rings missing,
rusted
Lifting rings not capable of lifting weight of
door or plate.
Lifting rings sufficient to lift or remove door
or plate.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual
A-8
NO. 4 – CONTROL STRUCTURE/FLOW RESTRICTOR
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Structure Trash and debris Trash or debris of more than ½ cubic foot
which is located immediately in front of the
structure opening or is blocking capacity of
the structure by more than 10%.
No Trash or debris blocking or potentially
blocking entrance to structure.
Trash or debris in the structure that
exceeds 1/3 the depth from the bottom of
basin to invert the lowest pipe into or out of
the basin.
No trash or debris in the structure.
Deposits of garbage exceeding 1 cubic
foot in volume.
No condition present which would attract or
support the breeding of insects or rodents.
Sediment
accumulation
Sediment exceeds 60% of the depth from
the bottom of the structure to the invert of
the lowest pipe into or out of the structure
or the bottom of the FROP-T section or is
within 6 inches of the invert of the lowest
pipe into or out of the structure or the
bottom of the FROP-T section.
Sump of structure contains no sediment.
Damage to frame
and/or top slab
Corner of frame extends more than ¾ inch
past curb face into the street (If
applicable).
Frame is even with curb.
Top slab has holes larger than 2 square
inches or cracks wider than ¼ inch.
Top slab is free of holes and cracks.
Frame not sitting flush on top slab, i.e.,
separation of more than ¾ inch of the
frame from the top slab.
Frame is sitting flush on top slab.
Cracks in walls or
bottom
Cracks wider than ½ inch and longer than
3 feet, any evidence of soil particles
entering structure through cracks, or
maintenance person judges that structure
is unsound.
Structure is sealed and structurally sound.
Cracks wider than ½ inch and longer than
1 foot at the joint of any inlet/outlet pipe or
any evidence of soil particles entering
structure through cracks.
No cracks more than 1/4 inch wide at the
joint of inlet/outlet pipe.
Settlement/
misalignment
Structure has settled more than 1 inch or
has rotated more than 2 inches out of
alignment.
Basin replaced or repaired to design
standards.
Damaged pipe joints Cracks wider than ½-inch at the joint of the
inlet/outlet pipes or any evidence of soil
entering the structure at the joint of the
inlet/outlet pipes.
No cracks more than ¼-inch wide at the
joint of inlet/outlet pipes.
Contaminants and
pollution
Any evidence of contaminants or pollution
such as oil, gasoline, concrete slurries or
paint.
Materials removed and disposed of
according to applicable regulations. Source
control BMPs implemented if appropriate.
No contaminants present other than a
surface oil film.
Ladder rungs missing
or unsafe
Ladder is unsafe due to missing rungs,
misalignment, rust, cracks, or sharp edges.
Ladder meets design standards and allows
maintenance person safe access.
FROP-T Section Damaged FROP-T T section is not securely attached to
structure wall and outlet pipe structure
should support at least 1,000 lbs of up or
down pressure.
T section securely attached to wall and
outlet pipe.
Structure is not in upright position (allow up
to 10% from plumb).
Structure in correct position.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016
A-9
NO. 4 – CONTROL STRUCTURE/FLOW RESTRICTOR
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
FROP-T Section
(cont.)
Damaged FROP-T
(cont.)
Connections to outlet pipe are not
watertight or show signs of deteriorated
grout.
Connections to outlet pipe are water tight;
structure repaired or replaced and works
as designed.
Any holes—other than designed holes—in
the structure.
Structure has no holes other than designed
holes.
Cleanout Gate Damaged or missing
cleanout gate
Cleanout gate is missing. Replace cleanout gate.
Cleanout gate is not watertight. Gate is watertight and works as designed.
Gate cannot be moved up and down by
one maintenance person.
Gate moves up and down easily and is
watertight.
Chain/rod leading to gate is missing or
damaged.
Chain is in place and works as designed.
Orifice Plate Damaged or missing
orifice plate
Control device is not working properly due
to missing, out of place, or bent orifice
plate.
Plate is in place and works as designed.
Obstructions to orifice
plate
Any trash, debris, sediment, or vegetation
blocking the plate.
Plate is free of all obstructions and works
as designed.
Overflow Pipe Obstructions to
overflow pipe
Any trash or debris blocking (or having the
potential of blocking) the overflow pipe.
Pipe is free of all obstructions and works
as designed.
Deformed or
damaged lip of
overflow pipe
Lip of overflow pipe is bent or deformed. Overflow pipe does not allow overflow at
an elevation lower than design
Inlet/Outlet Pipe Sediment
accumulation
Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in
inlet/outlet pipes (includes floatables and
non-floatables).
No trash or debris in pipes.
Damaged inlet/outlet
pipe
Cracks wider than ½-inch at the joint of the
inlet/outlet pipes or any evidence of soil
entering at the joints of the inlet/outlet
pipes.
No cracks more than ¼-inch wide at the
joint of the inlet/outlet pipe.
Metal Grates
(If applicable)
Unsafe grate opening Grate with opening wider than 7/8 inch. Grate opening meets design standards.
Trash and debris Trash and debris that is blocking more
than 20% of grate surface.
Grate free of trash and debris. footnote to
guidelines for disposal
Damaged or missing
grate
Grate missing or broken member(s) of the
grate.
Grate is in place and meets design
standards.
Manhole Cover/Lid Cover/lid not in place Cover/lid is missing or only partially in
place. Any open structure requires
urgent maintenance.
Cover/lid protects opening to structure.
Locking mechanism
not working
Mechanism cannot be opened by one
maintenance person with proper tools.
Bolts cannot be seated. Self-locking
cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to
remove
One maintenance person cannot remove
cover/lid after applying 80 lbs. of lift.
Cover/lid can be removed and reinstalled
by one maintenance person.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual
A-10
NO. 5 – CATCH BASINS AND MANHOLES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Structure Sediment
accumulation
Sediment exceeds 60% of the depth from
the bottom of the catch basin to the invert
of the lowest pipe into or out of the catch
basin or is within 6 inches of the invert of
the lowest pipe into or out of the catch
basin.
Sump of catch basin contains no sediment.
Trash and debris Trash or debris of more than ½ cubic foot
which is located immediately in front of the
catch basin opening or is blocking capacity
of the catch basin by more than 10%.
No Trash or debris blocking or potentially
blocking entrance to catch basin.
Trash or debris in the catch basin that
exceeds 1/3 the depth from the bottom of
basin to invert the lowest pipe into or out of
the basin.
No trash or debris in the catch basin.
Dead animals or vegetation that could
generate odors that could cause
complaints or dangerous gases (e.g.,
methane).
No dead animals or vegetation present
within catch basin.
Deposits of garbage exceeding 1 cubic
foot in volume.
No condition present which would attract or
support the breeding of insects or rodents.
Damage to frame
and/or top slab
Corner of frame extends more than ¾ inch
past curb face into the street (If
applicable).
Frame is even with curb.
Top slab has holes larger than 2 square
inches or cracks wider than ¼ inch.
Top slab is free of holes and cracks.
Frame not sitting flush on top slab, i.e.,
separation of more than ¾ inch of the
frame from the top slab.
Frame is sitting flush on top slab.
Cracks in walls or
bottom
Cracks wider than ½ inch and longer than
3 feet, any evidence of soil particles
entering catch basin through cracks, or
maintenance person judges that catch
basin is unsound.
Catch basin is sealed and is structurally
sound.
Cracks wider than ½ inch and longer than
1 foot at the joint of any inlet/outlet pipe or
any evidence of soil particles entering
catch basin through cracks.
No cracks more than 1/4 inch wide at the
joint of inlet/outlet pipe.
Settlement/
misalignment
Catch basin has settled more than 1 inch
or has rotated more than 2 inches out of
alignment.
Basin replaced or repaired to design
standards.
Damaged pipe joints Cracks wider than ½-inch at the joint of the
inlet/outlet pipes or any evidence of soil
entering the catch basin at the joint of the
inlet/outlet pipes.
No cracks more than ¼-inch wide at the
joint of inlet/outlet pipes.
Contaminants and
pollution
Any evidence of contaminants or pollution
such as oil, gasoline, concrete slurries or
paint.
Materials removed and disposed of
according to applicable regulations. Source
control BMPs implemented if appropriate.
No contaminants present other than a
surface oil film.
Inlet/Outlet Pipe Sediment
accumulation
Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in
inlet/outlet pipes (includes floatables and
non-floatables).
No trash or debris in pipes.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016
A-11
NO. 5 – CATCH BASINS AND MANHOLES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Inlet/Outlet Pipe
(cont.)
Damaged inlet/outlet
pipe
Cracks wider than ½-inch at the joint of the
inlet/outlet pipes or any evidence of soil
entering at the joints of the inlet/outlet
pipes.
No cracks more than ¼-inch wide at the
joint of the inlet/outlet pipe.
Metal Grates
(Catch Basins)
Unsafe grate opening Grate with opening wider than 7/8 inch. Grate opening meets design standards.
Trash and debris Trash and debris that is blocking more
than 20% of grate surface.
Grate free of trash and debris. footnote to
guidelines for disposal
Damaged or missing
grate
Grate missing or broken member(s) of the
grate. Any open structure requires
urgent maintenance.
Grate is in place and meets design
standards.
Manhole Cover/Lid Cover/lid not in place Cover/lid is missing or only partially in
place. Any open structure requires
urgent maintenance.
Cover/lid protects opening to structure.
Locking mechanism
not working
Mechanism cannot be opened by one
maintenance person with proper tools.
Bolts cannot be seated. Self-locking
cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to
remove
One maintenance person cannot remove
cover/lid after applying 80 lbs. of lift.
Cover/lid can be removed and reinstalled
by one maintenance person.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual
A-12
NO. 6 – CONVEYANCE PIPES AND DITCHES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Pipes Sediment & debris
accumulation
Accumulated sediment or debris that
exceeds 20% of the diameter of the pipe.
Water flows freely through pipes.
Vegetation/root
growth in pipe
Vegetation/roots that reduce free
movement of water through pipes.
Water flows freely through pipes.
Contaminants and
pollution
Any evidence of contaminants or pollution
such as oil, gasoline, concrete slurries or
paint.
Materials removed and disposed of
according to applicable regulations. Source
control BMPs implemented if appropriate.
No contaminants present other than a
surface oil film.
Damage to protective
coating or corrosion
Protective coating is damaged; rust or
corrosion is weakening the structural
integrity of any part of pipe.
Pipe repaired or replaced.
Damaged pipes Any dent that decreases the cross section
area of pipe by more than 20% or is
determined to have weakened structural
integrity of the pipe.
Pipe repaired or replaced.
Ditches Trash and debris Trash and debris exceeds 1 cubic foot per
1,000 square feet of ditch and slopes.
Trash and debris cleared from ditches.
Sediment
accumulation
Accumulated sediment that exceeds 20%
of the design depth.
Ditch cleaned/flushed of all sediment and
debris so that it matches design.
Noxious weeds Any noxious or nuisance vegetation which
may constitute a hazard to City personnel
or the public.
Noxious and nuisance vegetation removed
according to applicable regulations. No
danger of noxious vegetation where City
personnel or the public might normally be.
Contaminants and
pollution
Any evidence of contaminants or pollution
such as oil, gasoline, concrete slurries or
paint.
Materials removed and disposed of
according to applicable regulations. Source
control BMPs implemented if appropriate.
No contaminants present other than a
surface oil film.
Excessive vegetation
growth
Vegetation that reduces free movement of
water through ditches.
Water flows freely through ditches.
Erosion damage to
slopes
Any erosion observed on a ditch slope. Slopes are not eroding.
Rock lining out of
place or missing (If
applicable)
One layer or less of rock exists above
native soil area 5 square feet or more, any
exposed native soil.
Replace rocks to design standards.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual
A-40
NO. 28 – NATIVE VEGETATED SURFACE/NATIVE VEGETATED LANDSCAPE BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Site Trash and debris Trash and debris accumulated on the
native vegetated surface/native vegetated
landscape site.
Native vegetated surface site free of any
trash or debris.
Vegetation Insufficient vegetation Less than two species each of native
trees, shrubs, and groundcover occur in
the design area.
A minimum of two species each of native
trees, shrubs, and groundcover is
established and healthy.
Poor vegetation
coverage
Less than 90% if the required vegetated
area has healthy growth.
A minimum of 90% of the required
vegetated area has healthy growth.
Undesirable
vegetation present
Weeds, blackberry, and other undesirable
plants are invading more than 10% of
vegetated area.
Less than 10% undesirable vegetation
occurs in the required native vegetated
surface area.
Vegetated Area Soil compaction Soil in the native vegetation area
compacted.
Less than 8% of native vegetation area is
compacted.
Insufficient vegetation Less than 3.5 square feet of native
vegetation area for every 1 square foot of
impervious surface.
A minimum of 3.5 square feet of native
vegetation area for every 1 square foot of
impervious surface.
Excess slope Slope of native vegetation area greater
than 15%.
Slope of native growth area does not
exceed 15%.
NO. 29 – PERFORATED PIPE CONNECTIONS BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Preventive Blocking, obstructions Debris or trash limiting flow into perforated
pipe system or outfall of BMP is plugged or
otherwise nonfunctioning.
Outfall of BMP is receiving designed flows
from perforated pipe connection.
Inflow Inflow impeded Inflow into the perforated pipe is partially or
fully blocked or altered to prevent flow from
getting into the pipe.
Inflow to the perforated pipe is unimpeded.
Pipe Trench Area Surface compacted Ground surface over the perforated pipe
trench is compacted or covered with
impermeable material.
Ground surface over the perforated pipe is
not compacted and free of any impervious
cover.
Outflow Outflow impeded Outflow from the perforated pipe into the
public drainage system is blocked.
Outflow to the public drainage system is
unimpeded.
Outfall Area Erosion or landslides Existence of the perforated pipe is causing
or exasperating erosion or landslides.
Perforated pipe system is sealed off and
an alternative BMP is implemented.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual
A-42
NO. 31 – BIORETENTION BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Preventive Vegetation Vegetation to be watered and pruned as
needed and mulch applied to a minimum of
2 inches to maintain healthy growth.
Healthy vegetation growth with full
coverage as designed.
Bioretention Area Trash and debris Trash and debris in the bioretention area;
leaf drop in the fall season.
No trash or debris In the bioretention area.
Sediment
accumulation
Sediment accumulation in the bioretention
area interfering with infiltration.
Water in the bioretention infiltrates as
designed.
Excessive ponding Standing water in the bioretention area for
more than two days.
Standing water infiltrates at the desired
rate.
Inflow restricted Inflow not getting into bioretention;
debris/sediment blockage at inlet features;
native soil is exposed or other signs of
erosion damage is present.
Unobstructed and properly routed inflow
into bioretention area; inlet is stabilized and
appropriately armored.
Overflow not
controlling excess
water
Overflow water not controlled by outlet
features; native soil is exposed or other
signs of erosion damage is present.
Outlet features control overflow; overflow is
stabilized and appropriately armored.
Underdrain not freely
flowing
Underdrain is not flowing when bioretention
area has been infiltrating water.
Underdrain flows freely when water is
present.
Vegetation Poor vegetation
coverage
Plants not thriving across at least 80% of
the entire design vegetated area within the
BMP; overly dense vegetation requiring
pruning.
Healthy water tolerant plants in
bioretention area, plants thriving across at
least 80% of the entire design vegetated
area within the facility.
Insufficient vegetation Plants not water tolerant species. Plants are water tolerant.
Weeds present Weeds growing in bioretention area. No weeds in bioretention area.
Watering not
occurring
Planting schedule requires frequent
watering (approx. weekly Year 1, bimonthly
Years 2 and 3) for new facilities, and as
needed for established plantings or dry
periods
Plants are established and thriving
Pest control Signs of pests, such as wilting or chewed
leaves or bark, spotting or other indicators;
extended ponding period encouraging
mosquitoes
Plant community is pest-free when
following an approved Integrated Pest
Management plan; bioretention functioning
normally and ponding controlled as needed
for pest control
Containment Berm
and Earthen Slopes
Erosion Erosion occurring at earthen slopes or
containment berm side slope.
Erosion on the containment berm and side
slopes has been repaired and the cause of
the erosion corrected.
Voids created by
nuisance animals
(e.g., rodents) or tree
roots
Voids affecting berm integrity or creating
leaky pond condition
Voids have been repaired; facility is free of
nuisance animals following an approved
Integrated Pest Management plan.
Settlement Any part of the containment berm top has
less than 6 inches of freeboard from the
maximum pond level to the top of the
berm.
A minimum of 6 inches freeboard from the
maximum pond level to the top of the
berm.
Amended Soil Poor soil nutrients Soil not providing plant nutrients. Soil providing plant nutrients.
Bare spots Bare spots on soil in bioretention area. No bare spots, bioretention area covered
with vegetation or mulch mixed into the
underlying soil.
Compaction Poor infiltration due to soil compaction in
the bioretention area.
No soil compaction in the bioretention
area.
Appendix F
Bond Quantities Worksheet
Appendix G
Conveyance Calculations
Appendix H
Drainage Review Flow Chart
SECTION 1.1 DRAINAGE REVIEW
6/22/2022 2022 City of Renton Surface Water Design Manual
1-14
FIGURE 1.1.2.A FLOW CHART FOR DETERMINING TYPE OF DRAINAGE REVIEW REQUIRED
Appendix I
Declarations of Covenant