ERC Meeting Date: March 17, 2025
Project File Number: PR25-000012
Project Name: Williams ADU/Garage
Land Use File Number: LUA25-000025, ECF, SSDP, MOD
Project Manager: Jill Ding, Senior Planner
Owner/Applicant: Jamie Williams, 13411 SE 151st St, Renton, WA, 98058
Contact: Patty Thuman, 13411 SE 151st St, Renton, WA 98058
Project Location: 13411 SE 151st St, Renton, WA 98058 (APN 2223059112)
Project Summary: The applicant is requesting a Shoreline Substantial Development Permit,
Environmental (SEPA) Review, and a height modification for the construction of
a two (2) story 1,012 square foot detached accessory dwelling unit (ADU). The
project site is a 37,744 square foot lot within the Residential-4 (R-4) zone that
is currently developed with a single-family home and associated accessory
structures. The site is currently accessed via a residential driveway off of SE
151st St. A height modification is requested to allow the proposed ADU to
exceed the height of the existing single family residence. According to the City
of Renton Maps (COR Maps), the project site is mapped with a Wellhead
Protection Area Zone (Zone 2, Maplewood Wellfield), Special Flood Hazard
Areas (100 year flood, FEMA Zone-AE), Moderate to Severe Channel Migration
Zone Hazards, Regulated Shoreline High Intensity Environmental Designation,
Regulated Shoreline: CR-C Cedar River Reaches Jurisdiction, High Seismic
Hazards, Regulated Slopes, and High Erosion Hazards.
Exist. Bldg. Area SF: 1,470 sq. ft. Proposed New Bldg. Area
(footprint):
Proposed New Bldg. Area (gross):
1,012 sq. ft.
2,024 sq. ft.
Site Area: 37,744 sq. ft.
(0.87 acres)
Total Building Area GSF: 3,494 sq. ft.
STAFF
RECOMMENDATION:
Staff Recommends that the Environmental Review Committee issue a
Determination of Non-Significance - Mitigated (DNS-M).
Docusign Envelope ID: 22A8539B-6B4F-45E9-B44D-17C2E5317108
City of Renton Department of Community & Economic Development
Williams ADU/Garage
Staff Report to the Environmental Review Committee
LUA25-000025, ECF, SSDP, MOD
Report of March 17, 2025 Page 2 of 4
ERC_WI~1
ENVIRONMENTAL REVIEW
In compliance with RCW 43.21C.240, the following environmental (SEPA) review addresses only those
project impacts that are not adequately addressed under existing development standards and environmental
regulations.
A. Environmental Threshold Recommendation
Based on analysis of probable impacts from the proposal, staff recommends that the Responsible
Officials:
Issue a DNS-M with a 14-day appeal period
B. Mitigation Measures
1. The applicant shall submit an Inadvertent Discoveries Plan prepared by a qualified professional
with the building permit for review and approval by the Current Planning Project Manager prior to
permit issuance.
C. Exhibits
Exhibit 1: Environmental Review Committee (ERC) Report
Exhibit 2: Site Plan
Exhibit 3: Accessory Dwelling Unit (ADU) Building Plan Set
Exhibit 4: Channel Migration Study, prepared by DCG Watershed, dated October 18, 2023
Exhibit 5: Wetland and Stream Assessment, prepared by J. S. Jones and Associates, Inc.,
dated November 20, 2021
Exhibit 6: Duwamish Tribe Comment Letter, dated January 30, 2025
Exhibit 7: City Response to Duwamish Comments, dated January 30, 2025
Exhibit 8: SEPA Environmental Checklist, prepared on December 26, 2024
Exhibit 9: Advisory Notes
D. Environmental Impacts
The Proposal was circulated and reviewed by various City Departments and Divisions to determine
whether the applicant has adequately identified and addressed environmental impacts anticipated to
occur in conjunction with the proposed development. Staff reviewers have identified that the proposal is
likely to have the following probable impacts:
1. Water
Impacts: The applicant submitted a Channel Migration Study, prepared by DCG Watershed, dated
October 18, 2023 (Exhibit 4) and a Wetland and Stream Assessment, prepared by J. S. Jones and
Associates, Inc., dated November 20, 2021 (Exhibit 5) with the project application materials. The
project site is located along the Cedar River, which is a Shoreline of the State. The site is located within
Reach C of the Cedar River, Special Flood Hazard Areas (100-year flood, FEMA Zone-AE), Moderate
to Severe Channel Migration Zone Hazards, and is within the Shoreline High Intensity Designation.
The proposed work would occur within the designated moderate channel migration zone. The
moderate hazard area is located between the outer boundary of severe hazard and the maximum
probable limits of future migration. No work is proposed within the severe channel migration zone.
Work proposed within the 100-year flood plain would be limited to the installation of posts for an
upper level deck.
Docusign Envelope ID: 22A8539B-6B4F-45E9-B44D-17C2E5317108
City of Renton Department of Community & Economic Development
Williams ADU/Garage
Staff Report to the Environmental Review Committee
LUA25-000025, ECF, SSDP, MOD
Report of March 17, 2025 Page 3 of 4
ERC_WI~1
The Channel Migration Study concluded that the proposed ADU location would not be in an area
subject to surface erosion or channel migration following major floods. The new construction
proposed within this area would be unlikely to require new shoreline stabilization or other structural
flood hazard reduction measures.
The Wetland and Stream Assessment concluded that there were no wetlands present on the subject
property. The Cedar River is classified as a Shoreline of the State and would be subject to the City’s
adopted Shoreline Master Program and would not be subject to the City’s Critical Areas Regulations.
The subject property has a lot depth of approximately 345 feet.
According to the Shoreline Master Program, residential lots with a lot depth greater than 170 feet
would be required to provide a 50-foot vegetation conservation buffer and a 15-foot building setback.
The proposed ADU would be constructed approximately 180 feet from the ordinary high water mark
(OHWM) of the Cedar River, which would exceed the 65-foot combined vegetation conservation
buffer and building setback required.
It is anticipated that the City’s currently adopted erosion control, construction, and drainage
regulations would adequately mitigate for any impacts that could result from the proposed
construction of the ADU; therefore, no further mitigation is recommended.
Mitigation Measures: No further mitigation recommended.
Nexus: Not Applicable.
2. Historic and Cultural Preservation
Impacts: Staff received comments from the Duwamish Tribe (Exhibit 6), requesting that an
Inadvertent Discovery Plan be followed in the case that archeological deposits are discovered during
construction activities. To ensure that any archeological deposits are managed appropriately, staff
recommends as a SEPA mitigation measure that the applicant submit an Inadvertent Discoveries
Plan prepared by a qualified professional with the building permit for review and approval by the
Current Planning Project Manager prior to permit issuance.
Mitigation Measures: The applicant shall submit an Inadvertent Discoveries Plan prepared by a
qualified professional with the building permit for review and approval by the Current Planning Project
Manager prior to permit issuance.
Nexus: State Environmental Policy Act (SEPA) Regulations; City of Renton Comprehensive Plan Goals
and Policy, L-AA, L-44, and LU-45; RCW 27.53 Archeological Sites and Resources; and RCW 27.44
Indian Graves and Records; and Duwamish Tribe Comment Letter, dated January 30, 2025.
E. Comments of Reviewing Departments
The proposal has been circulated to City Department and Division Reviewers. Where applicable, their
comments have been incorporated into the text of this report and/or “Advisory Notes to Applicant”
(Exhibit 9).
✓ Copies of all Review Comments are contained in the Official File and may be attached to this
report.
The Environmental Determination decision will become final if the decision is not appealed within the
14-day appeal period (RCW 43.21.C.075(3); WAC 197-11-680).
Environmental Determination Appeal Process: Appeals of the environmental determination must be
filed in writing on or before 5:00 p.m. on March 31, 2025. Appeals must be submitted electronically to the
City Clerk at cityclerk@rentonwa.gov or delivered to City Hall 1st floor Lobby Hub Monday through Friday. The
Docusign Envelope ID: 22A8539B-6B4F-45E9-B44D-17C2E5317108
City of Renton Department of Community & Economic Development
Williams ADU/Garage
Staff Report to the Environmental Review Committee
LUA25-000025, ECF, SSDP, MOD
Report of March 17, 2025 Page 4 of 4
ERC_WI~1
appeal fee, normally due at the time an appeal is submitted, will be collected at a future date if your appeal
is submitted electronically. The appeal submitted in person may be paid on the first floor in our Finance
Department. Appeals to the Hearing Examiner are governed by RMC 4-8-110 and additional information
regarding the appeal process may be obtained from the City Clerk’s Office, cityclerk@rentonwa.gov.
Docusign Envelope ID: 22A8539B-6B4F-45E9-B44D-17C2E5317108
ERC_WI~1
CITY OF RENTON
DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT
STAFF REPORT TO THE ENVIRONMENTAL REVIEW COMMITTEE
EXHIBITS
Project Name:
Williams ADU/Garage
Land Use File Number:
LUA25-000025, ECF, SSDP, MOD
Date of Meeting
March 17, 2025
Staff Contact
Jill Ding
Senior Planner
Project Contact/Applicant
Patty Thuman
13411 SE 151st St, Renton,
WA 98058
Project Location
13411 SE 151st St, Renton, WA
98058 (APN 2223059112)
The following exhibits are included with the ERC Report:
Exhibit 1: Environmental Review Committee (ERC) Report
Exhibit 2: Site Plan
Exhibit 3: Accessory Dwelling Unit (ADU) Building Plan Set
Exhibit 4: Channel Migration Study, prepared by DCG Watershed, dated October 18, 2023
Exhibit 5: Wetland and Stream Assessment, prepared by J. S. Jones and Associates, Inc.,
dated November 20, 2021
Exhibit 6: Duwamish Tribe Comment Letter, dated January 30, 2025
Exhibit 7: City Response to Duwamish Comments, dated January 30, 2025
Exhibit 8: SEPA Environmental Checklist, prepared on December 26, 2024
Exhibit 9: Advisory Notes
Docusign Envelope ID: 22A8539B-6B4F-45E9-B44D-17C2E5317108