HomeMy WebLinkAboutChange Order - 36Docusign Envelope ID: B2ABBA57-D0A4-4893-ADE8-60078FA469DF
Contract Title:
Change Order No. 36
Rainier Ave S Corridor Improvements -Phase 4
Contractor: Pivetta Brothers Construction, Inc.
Contract No.: CAG-22-163
Federal Aid No.: STPUL-1615(005)
181 Ordered by Engineer 181 Force Account □Proposed by the Contractor (VECP)181 Bid Item □Unilateral □Bid Item Price Adjustment□Lump Sum
Affects DBE Work: 181 No □Yes If yes, must receive concurrence from Local Programs
Original Contract:
Current Contract:
Estimated Net Change This Order:
New Contract:
Reviewed By: d�� E¼f �Record =---.....
Reviewed By:
City Attorney
36
prior to execution.
Date
1/20/2025
Date
1/23/2025
Date
Date
Amount Working Days
$28,284,172.90 500
$35,470,373.43 654
$67,773.42 0
$35,538,146.85 654
��Bv.:J� �� �1,iz�
Engineer (City of Renton Transportation Date
Design Manager)
Consent By:
Surety (Greater than 25% cost and/or 20%
time increase)
Endorsed By:
Bill Adams
Contractor
Executed By:
Digitally signed by Bill Adams
Date: 2025.03.05 11:46:12-08'00'
City of Renton Public Works
Administrator/ Mayor
Armondo Pavone
Date
3/5/2025
Date
Date
Change Order No.
Contract Title: Rainier Ave S. Corridor Improvements -Phase 4
Contract No. CAG-22-163
Page 1 of 13
CAG-22-163, CO #36-25
3/18/2025
Approved by Cheryl Beyer via email 3/6/2025
Attest:_______________________________
Jason A. Seth, City Clerk
Docusign Envelope ID: B2ABBA57-D0A4-4893-ADE8-60078FA469DF
materials. The Contractor may need to excavate additional test pits during the course of
work to assess tainted soils which would need to be exported. This Change establishes pay
items for the work to excavate test pits for the evaluation of tainted soils.
Because petroleum tainted material cannot be accepted at standard export sites or
disposed of under the original unit prices in the proposal, a new unit price has been
established to cover the costs associated with the disposal of petroleum-tainted soils.
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2022
WSDOT/APWA Standard Specifications. See attached.
Estimated Cost: $ 67,773.42
Extended Overhead: $ 0.00
Force Account Time related $ 0.00
damages per 1-09.6.6.d:
Total: $ 67,773.42
36-A202 -Excavation of Test Pits for Tainted Soils and Water for Storm Sewer
An independent estimate was prepared for the cost to excavate test pits to identify the
extent of tainted soils and water for storm sewer. This cost was calculated to be
$21,657.60. The Contractor's quote of $40,000.00 is rejected because of overestimated
quantity. The estimated cost of excavation of test pits for tainted soils and water for
storm sewer is $22,000.00.
36-A203 -Disposal of Petroleum Tainted Materials Incl. Haul for Storm Sewer
An independent estimate was prepared for the cost to dispose of tainted soils and water
for storm sewer. This cost was calculated to be $34,245.69. The Contractor's quote of
$63.46 per ton is accepted, and the estimated cost to dispose of tainted soils and water
for storm sewer is $25,384.00.
36-B43 -Excavation of Test Pits for Tainted Soils and Water for Water
An independent estimate was prepared for the cost to excavate test pits to identify the
extent of tainted soils and water for water. This cost was calculated to be $3,248.64.
The Contractor's quote of $5,000.00 is rejected because of overestimated quantity. The
estimated cost of excavation of test pits for tainted soils and water for water is
$3,000.00.
36-B44 -Disposal of Petroleum Tainted Materials Incl. Haul for Water
An independent estimate was prepared for the cost to dispose of tainted soils and water
for water. This cost was calculated to be $4,236.62. The Contractor's quote of $63.46
Change Order No.
Contract Title:
Contract No.
36
Rainier Ave S. Corridor Improvements -Phase 4
CAG-22-163
Page 4 of 13
202
203
Docusign Envelope ID: B2ABBA57-D0A4-4893-ADE8-60078FA469DF
Tainted Soils Sch. A, B, and C -Change Order Quotation
related constituents, petroleum fuels (gasoline, diesel, etc.) and other waste oil
related contaminants in soil. Material testing above MTCA Method A Soil
Cleanup Levels for Unrestricted Land Uses will be evaluated for payment under
this section. At.' ot/:ler eHEe�•etefl meter.ie.' wif..' be t,JRfler t/:le geRere.' eHEe�•et.ioR
2.Measurement:
SP 8-35.4 Measurement is supplemented as follows:
No specific unit of measurement shall apply to the force account item of
"Excavation of Test Pits for Tainted Soils and Water for Joint Utility Trench".
3.Payment:
SP 8-35.5 Payment is supplemented as follows:
"Excavation of Test Pits for Tainted Soils and Water for Joint Utility Trench", by
force account as provided in Section 1-09.6.
4.Reason for Change: The Contractor encountered tainted soils while excavating
for the joint utility trench. Disposing of contaminated soils exceeding the MTCA
Method A Soil Cleanup Levels for Unrestricted Land Uses is relatively more
expensive than that for tainted soils. To minimize the quantity of soils disposed
as contaminated soils and therefore save project funds, a series of five test pit
sites was identified, excavated, and tested.
5.Affects DBE Work:□Yes � No
6.Materials: N/ A
7.Plans: A plan sheet is attached showing the locations of the test pits.
8.Equitable Adjustment: This Change Order includes an equitable adjustment per
Section 1-09.4 of the 2022 WSDOT/APWA Standard Specifications. The
estimated increase is $40,000.00.
9.Extension of Time: The additional Time for Completion including for the work for
this entire Change Order is included in section H. of this Change Order.
B.Structure Excavation Class B Incl. Haul for Joint Utility Trench
1.Description of Change:
Change Order No.
Contract Title:
Contract No.
19
Rainier Ave S Corridor Improvements -Phase 4
CAG-22-163
Page 3 of 92
Change Order #36, Page 11 of 13