Contract Title:
Change Order No. 35
Rainier Ave S Corridor Improvements -Phase 4
Contractor: Pivetta Brothers Construction, Inc.
Contract No.: CAG-22-163
Federal Aid No.: STPUL-1615(005)
181 Ordered by Engineer 181 Force Account □Proposed by the Contractor (VECP)□Bid Item□Unilateral □Bid Item Price Adjustment□Lump Sum
Affects DBE Work: 181 No □Yes If yes, must receive concurrence from Local Programs
prior to execution.
Original Contract:
Current Contract:
Estimated Net Change This Order:
New Contract:
Reviewed By:
,/�-� _,,
� �Egineer/4iRecord
Reviewed By:
1/20/2025
Date
' 1/23/2025
Reviewed By:
City Attorney
ject Manager Date
Date
35
Amount Working Days
$28,284,172.90 500
$35,464,868.43 654
$5,505.00 0
$35,470,373.43 654
Design Manager)
Consent By:
Surety (Greater than 25% cost and/or 20%
time increase)
Endorsed By:
Contractor
Date
3/5/2025
Date
Executed •vr:0�••••" "
�artin Pastucha 3;11;202s 1 3:46 PM PD.
City of Renton Pt1\3H[W�4�k� Date
Administrator/ Mayor
Change Order No.
Contract Title: Rainier Ave S. Corridor Improvements -Phase 4
Contract No. CAG-22-163
Page 1 of 8
CAG-22-163, CO#35-25
Approved by Cheryl Beyer via email 3/6/2025
Change Order No. 35
Contract Title: Rainier Ave S. Corridor Improvements Phase 4
Contract No. CAG 22 163
Page 2 of 8
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
The Contractor shall perform excavation south of the 12 In. water main connection at STA
15+65 RT where they shall expose the three existing 12 In. gate valves and one 12 In. tee.
The Contractor shall support the Citys water department in the removal of the three
existing 12 In. gate valves and 12 In. tee, and the installation and connection of a new, City
provided 12 In. MJ x MJ gate valve to a live watermain.
Proposal Schedule of Prices:
ADD the following to Schedule B:
35 B42 Excavate to Expose STA 15+65 RT Valve Cluster and Support Additional City
Water Department Work, 1 EST @ $5,000.00 = $5,000.00.
Specification and/or Special Provision:
SP 7 09.3(19)A is supplemented with the following:
The Contractor shall perform excavation south of the 12 In. water main connection at
STA 15+65 RT where they shall expose the three existing 12 In. gate valves and one 12
In. tee. The Contractor shall support the Citys water department in the removal of the
three existing 12 In. gate valves and 12 In. tee, and the installation of a new, City
provided 12 In. MJ x MJ gate valve.
Description:
None.
Materials:
None.
Measurement:
SP 7 09.4 is supplemented with the following:
Excavate to Expose STA 15+65 RT Valve Cluster and Support Additional City Water
Department Work, per force account.
Payment:
SP 7 09.5 is supplemented with the following:
Excavate to Expose STA 15+65 RT Valve Cluster and Support Additional City Water
Department Work, force account.
Change Order No. 35
Contract Title: Rainier Ave S. Corridor Improvements Phase 4
Contract No. CAG 22 163
Page 3 of 8
Materials Specifications:
None.
Plans:
None.
Reason for Change:
During the water main connection at STA 15+65 RT, the City utilized the open trench to
remove the gate valve cluster and tee located immediately south of the connection, and
install a new 12 In. gate valve and connect to the live watermain. With the City water crew
already on site, this presented an opportunity to perform the infrastructure adjustments at
the point of connection with reduced impact to the project.
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1 09.4 of the 2022
WSDOT/APWA Standard Specifications. See attached.
Estimated Cost: $ 5,000.00
Extended Overhead: $ 0.00
Force Account Time related
damages per 1 09.6.6.d:
$ 0.00
Total: $ 5,000.00
35 B42 Excavate to Expose STA 15+65 RT Valve Cluster and Support Additional City Water
Department Work
An independent estimate was prepared for the cost to excavate around the valve cluster
and tee south of STA 15+65 RT and support the Citys crew with the removal of the gate
valves and tee, and installation of a new 12 In. gate valve. The calculated cost is
$4,763.34 and has been rounded to an estimated cost of $5,000.00.
Extension of Time:The Time for Completion is extended 0 Working Days.
Affects DBE Work:
No.
Change Order No. 35
Contract Title: Rainier Ave S. Corridor Improvements Phase 4
Contract No. CAG 22 163
Page 4 of 8
Sections 1 04.4 and 1 04.5 of the 2022 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
To be attached to Change Order:
1 Estimated Change Order Cost
2 Plans
3 Field Directive/Request for Information Response
4 Change Order Quotation
5 Project Labor List
6 Force Account Equipment Rate Request (DOT Form 422 010 EF)
7 Equitable Adjustment Determination
8 Additional Working Days Calculation
EST
Docusign Envelope ID: B5E53622-26DA-42A2-961A-C8A575962D37
R \,Y�ter r.rew_at �TA 1�+65 (Wendy's)- RFI #267 anrl Official Resoonse Pivetta Broi:hers Consfruct1on;1nc. "Pro1ect: 20�2-�.JlrRaimer""Ave S Phase 4
1812 Pease Avenue,
Sumner, Washington 98390
P: (800) 748-3882
Renton, Washington
RFI #267: STA 15+65 Wendy's Water Connection Revision by Renton Water
Department
Status
To
Date Initiated
Location
Cost Impact
Spec Section
Drawing Number
Linked Drawings
Received From
Copies To
Activity
Question
Official Response
Closed on 07/17/24
Jordan Howe (Perteet)
Feb 23, 2024
Yes (Unknown)
122,139
Kyle MacDonald (Pivetta Brothers Construction,
Inc.)
Bill Adams (Pivetta Brothers Construction, Inc.),
Zach Brader (Pivetta Brothers Construction, Inc.),
Jordan Howe (Perteet), Kyle MacDonald (Pivetta
Brothers Construction, Inc.), Joe Nerlfi (City of
Renton), Russell Owen (Pivetta Brothers
Construction, Inc.), Austin Roth (Pivetta Brothers
Construction, Inc.), William Schroeder (Pivetta
Brothers Construction, Inc.), Andrea Schultz
(Perteet), Anthony Trail (Pivetta Brothers
Construction, Inc.)
From
Due Date
Project Stage
Schedule Impact
Cost Code
Reference
Russell Owen (Pivetta Brothers Construction, Inc.)
201 S 3rd St
Renton, Washington 98057
Feb 27, 2024
Course of Construction
Yes (Unknown)
Question from Russell Owen Pivetta Brothers Construction, Inc. on Friday, Feb 23, 2024 at 11:06 AM PST
Pivetta and City of Renton Water Department had a scheduled water connection at STA 15+65 (Final Connection 3 Detail) per
sheet 139 for night shift of 2/22/2024. During 2/22/24 night shift Pivetta foreman was directed by the City of Renton inspector
and City of Renton Water Department to dig further south than required for City of Renton to make changes to the valve south
of the planned connection. These changes are summarized in the attached email. Pivetta dug further as directed but did not
install any water parts that were not per plan. City of Renton Water Department installed additional parts south of connection
themselves.
Please confirm these changes for the project record and provide clarification on payment for Pivetta's tracked force account
extra work to demo and excavate further south than required for the planned water connection.
Attachments
2024.02.22 FA Ticket for added gate valve.pdf
Response from Jordan Howe Perteet on Wednesday, Jul 17, 2024 at 07:58 AM PDT
A change order is being prepared for this work. This work will be paid by force account as part of a new item which will be
added as part of the change order.
Jordan Howe -7/17/2024
Pivetta Brothers Construction, Inc. Page 1 of 2