THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
Description:
The contractor iHtirected in the field to utilize a vactor truck as a less invasive excavation
method around the seven unidentified conduits discovered during the installation of the storm
system on Park Ave N.
Proposal Schedule of Prices:
Add the following to schedule A: A97 Vactor and Excavation
Specification and/or Special Provision:
Materials:
Measurement :
The new bid item "A97 Vactor and Excavation" shall be measured by Lump Sum.
Payment:
The new Bid Item "A97 Vactor and Excavation" shall be paid as a lump and shall cover
the complete cost of providing all labor, materials, tools, equipment required to
complete the Work.
Plans:
Reason for Change:
During the storm system installation along Park Avenue North, seven unlocated conduits were
discovered. Due to their proximity to the old Boeing Duct Bank system, both the Contractor and
the City were concerned that these conduits might be electrical. A vactor truck was therefore
used to excavate around the unidentified conduits as a less invasive method of excavation. This
was decided in the field.
Change Order No.
Contract Title:
Contract No.
Page 2 of 4