HomeMy WebLinkAboutChange Order - 3840
CAG-22-163, CO #38-25
Change Order No. 38
Contract Title: Rainier Ave S Corridor Improvements — Phase 4
Contractor: Pivetta Brothers Construction, Inc.
Contract No.: CAG-22-163
Federal Aid No.: STPUL-1615(OOS)
® Ordered by Engineer
® Force Account
❑ Proposed by the Contractor (VECP)
❑ Bid Item
❑ Unilateral
❑ Bid Item Price Adjustment
❑ Lump Sum
If yes, must receive concurrence from Local Programs
Affects DBE Work: ❑ No ®Yes
prior to execution.
Amount
Working Days
Original Contract:
$28,284,172.90
500
Current Contract:
$3S,625,581.85
654
Estimated Net Change This Order:
$57,252.00
0
New Contract:
$35,682,833.85
654
tr e By:
Resi ent Engineer Date
Reviewed By:
4/1/2025
Engineer of Record Date
Reviewed By:
4/2/2025
City of Rento Project Manager Date
Iss B
� ZS
ngineer (city of Renton Transportation Date
Design Manager)
Consent By:
Surety (Greater than 25% cost and/or 20% Date
time increase)
Endorsed By:
Digitally signed by Bill Adams
Bill Adams Date: 2025.04.1018:48:18-07'00' 4/10/2025
Contractor Date
Reviewed By: Executed By:
Approved by Cheryl Beyer via email 4/2/2025 4/30/2025
City Attorney Date City of Renton Public Works Date
RE"r° Administrator /Mayor
Attest: �
Jason Seth, City Clerk ,°'
Change Order No. 38
Contract Title: Rainier Ave S. Corridor Improvements — Phase 4
Contract No. CAG-22-163
Page 1 of 14
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
The Contractor encountered an existing PSE vault and conduit at STA 38+33 LT that was in
conflict with the proposed Joint Utility Trench. The Contractor was required to relocate the
vault and conduit.
Additionally, the Contractor discovered live wires inside conduits designated for removal,
which conflicted with proposed storm excavation at STA 28+85 LT, proposed sewer
excavation at STA 39+88 LT, the proposed hydrant at STA 24+24 LT, and proposed luminaire
foundations for poles 32/P49 at STA 38+06 LT, PS2 at STA 38+70 LT, 34/P54 at STA 39+33
LT, and P56 at STA 40+07 LT.
PSE is unable to address the conflicts at the storm and sewer locations quickly enough to
prevent impacts on the proposed work. Therefore, the Contractor shall proceed with
reasonable care to protect the conduits while continuing storm and sewer installations until
PSE can deactivate and remove the wires.
Conduit with live PSE wires is in direct conflict with the proposed hydrant at STA 24+24 LT,
preventing hydrant installation. The Contractor shall postpone the hydrant installation until
PSE has deactivated and removed the wires.
The live PSE wires in conflict with luminaire foundations between STA 37+7S LT to STA
40+46 LT must remain active. The Contractor shall trench and install new conduit from STA
37+7S LT to STA 40+46 LT to house the PSE wires and install a new handhole at STA 37+80
LT per Field Directive #80.
Proposal Schedule of Prices:
ADD the following to Schedule D:
38-D76 — Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault, 1
EST @ $10,000.00 = $10,000.00
38-1377 — Resolution of Utility Conflicts With Live PSE Wires, 1 EST @ $42,000.00 =
$42,000.00
Specification and/or Special Provision:
ADD the following Section 8-26.3(1):
The Contractor shall coordinate with PSE to relocate the existing PSE vault and conduit
at STA 38+33 outside of the proposed Joint Utility Trench.
Change Order No. 38
Contract Title
Contract No.
Rainier Ave S. Corridor Improvements — Phase 4
CAG-22-163
Page 2 of 14
ADD the following Section 8-26.3(2):
The Contractor shall install the proposed storm and sewer pipes at STA 28+85 LT and
STA 39+88 LT. The additional work required to install the proposed storm and sewer
while maintaining the existing conduits will be addressed as part of the item added part
of this Change Order "Resolution of Utility Conflicts With Live PSE Wires."
The Contractor shall defer installation of the hydrant at STA 24+24 LT until such time
that PSE has deenergized and removed the active wires.
The Contractor shall trench and install new conduit from STA 37+75 LT to STA 40+46 LT
to house the wires that PSE could not remove and install a new handhole at STA 37+80
LT per Field Directive #80.
Description:
None.
Materials:
None.
Measurement:
ADD the following to 8-26.4:
"Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault," force
account.
"Resolution of Utility Conflicts With Live PSE Wires," force account.
Payment:
ADD the following to 8-26.5:
"Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault," by force
account.
"Resolution of Utility Conflicts With Live PSE Wires," by force account.
Materials Specifications:
None.
Change Order No. 38
Contract Title: Rainier Ave S. Corridor Improvements — Phase 4
Contract No. CAG-22-163
Page 3 of 14
Plans:
DELETE Sheets 150, 151, 158, 159, and 244.
REPLACE with Sheets 150, 151, 158, 159, and 244.
Reason for Change:
During the installation of the Joint Utility Trench at approximately STA 38+33 LT, the
Contractor discovered a live PSE vault in conflict with the proposed trench. Coordination
with PSE determined that the vault needed to remain active and would have to be relocated
outside the trench. This vault was not identified in the information provided by PSE.
While excavating for storm at STA 28+85 LT, sewer at STA 39+88 LT, hydrant installation at
STA 24+24 LT and luminaire foundations between STA 37+75 LT to STA 40+46 the
Contractor discovered conduits containing live PSE wires within an existing duct bank
designated for removal. These wires were part of the utility conversion plan and were to be
deactivated and removed by PSE, but these locations had not been addressed. As a result,
the presence of live wires created conflicts with the installation of the proposed
infrastructure.
This Change Order is necessary to create items to compensate the Contractor for costs
incurred due to these conflicts and additional work required to resolve the conflicts.
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2022
WSDOT/APWA Standard Specifications. See attached.
Estimated Cost: $ 57,252.00
Extended Overhead: $ 0.00
Force Account Time Related Damages per 1-09.6.6.d: $ 0.00
Total: $ 57,252.00
38-1376 — Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault
An independent estimate was prepared for the cost to resolve conflicts between the
proposed JUT and existing PSE vault. This cost was calculated to be $7,676.52 and has
been rounded to an estimated cost of $10,000.00.
Change Order No. 38
Contract Title: Rainier Ave S. Corridor Improvements — Phase 4
Contract No. CAG-22-163
Page 4 of 14
r.
38-D77 — Resolution of Utility Conflicts With Live PSE Wires
An independent estimate was prepared for the cost of resolving conflicts with live PSE
wires. This cost was calculated to be $41,157.92 and has been rounded to an estimated
cost of $42,000.00.
Extension of Time: The Time for Completion is extended 0 Working Days.
Affects DBE Work:
Yes.
Sections 1-04.4 and 1-04.5 of the 2022 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
To be attached to Change Order:
® 1-Estimated Change Order Cost
® 2-Plans
® 3-Field Directive/Request for Information Response
❑ 4-Change Order Quotation
❑ 5-Project Labor List
❑ 6-Force Account Equipment Rate Request (DOT Form 422-010 EF)
❑ 7-Equitable Adjustment Determination
O 8-Additional Working Days Calculation
Change Order No. 38
Contract Title: Rainier Ave S. Corridor Improvements — Phase 4
Contract No. CAG-22-163
Page 5 of 14
PSE Live Wire Conflicts - Estimated Change Order Cost
Change Order Cost (Equitable Adjustment) Change Order No. 38
Project Name: Rainier Ave S Corridor Improvements - Phase 4
Contractor: Pivetta Brothers Construction, Inc.
Contract No: CAG-22-163
Federal Aid No: STPUL-1615(005) By: Shannon Tremper
Construction Manager: Perteet Date: 2/11/2025
Item No. Description I Quantity Unit Unit Price Estimated Cost
Independent Cost Estimate
38-D76
Resolution of Utility Conflicts Between Proposed JUT and
Existing PSE Vault
REG OT
REG OT
Labor Pivetta (Foreman)
4
Hours
$ 96.00
$ 384.00
Labor - Pivetta(Operator)
4
Hours
$ 92.00
$ 368.00
Labor - Pivetta(Operator)
4
Hours
$ 92.00
$ 368.00
Labor • Pivetta (Operator)
4
Hours
$ 92.00
$ 368.00
Labor - Pivetta(Operator Truck Driver)
4
Hours
$ 92.00
$ 368.00I
Labor - Pivetta(Laborer)
4
Hours
$ 75.00
$ 300.00
Labor -Golden Gate (Electrician Foreman)
4
Hours
$ 110.00
$ 440.00
Labor -Golden Gate (Electrician)
4
Hours
$ 109.00
$ 436.00
Labor -Golden Gate (Apprentice Electrician)
4
Hours
$ 51.00
$ 204.00
Labor -Golden Gate (Apprentice Electrician)
4
Hours
$ 51.00
$ 204.00
1Labor
Markup (Pivetta)
$ 2,156.00
Cents/Dollar I
$ 0.31
$ 668.36
Labor Markup (GGE)
$ 1,284.00
Cents/Dollar
$ 0.31
$ 398.04
Equipment - Pivetta (Pickup Truck)
4
Hours
$ 30.00
5 120.00
Equipment Pivetta (Dump Truck)
4
Hours
$ 92.00
$ 368.00
Equipment Pivetta (Excavator)
4
Hours
$ 110.00
$ 440.00
1Eguipment
- Pivetta (Excavator)
4
Hours
I $ 110.00
$ 440.00
Equipment - Pivetta (Loader)
4
Hours
I $ 110.00
1 $ 440.00
Equipment - Golden Gate (Pickup Truck)
4
Hours
I $ 46.00
I $ 184.00
Equipment - Golden Gate (Pickup Truck)
4
Hours
$ 30.00
$ 120.00
Equipment - GoldenGate(BobcatExcavator)
4
Hours
$ 68.00
$ 272.00
Equipment Markup (Pivetta)
$ 1,808.00
Cents/Dollar
$ 0.21
$ 379.68
Equipment Markup (GGE)
$ 576.00
Cents/Dollar
1 $ 0.21
$ 120.96
Subcontractor Markup
$ 2,379.00
Cents/Dollar
I $ 0.12
$ 285.48
CALCULATED TOTAL:
ESTIMATED TOTAL:
$ 7,676.52
$ 10,000.00
38.077
Resolution of Utility Conflicts With Live PSE Wires
HOURS
RATE
(Labor- Pivetta (Foreman)
I 14
I 8
Hours
$ 96.00 I
$ 127.00
I $ 2,360.00 I
Labor - Pivetta(Operator)
14
I 8
Hours
$ 92,00
1 $ 123.00
I $ 2,272,00
Labor - Pivetta(operator)
I 14
i 8
Hours
I $ 92.00
i $ 123.00
I $ 2,272.00
Labor - Pivetta (Operator)
14
I 8
Hours
$ 92.00
1 $ 123.00
I $ 2,272.00
Labor - Pivetta(Operator Truck Driver)
14
8
1 Hours
$ 92.00
$ 123.00
$ 2,272.00
Labor - Pivetta(Laborer)
I 14
1 8
1 Hours
I $ 75.00
1$ 123.00
1 $ 2,034.00
1
1Labor-Golden Gate (Electrician Foreman)
I 4
I 8
I Hours
I$ 110.00
1$ 152.00
I$ 1,656.00
Labor - Golden Gate (Electrician)
4
8
1 Hours
$ 109.00
$ 152.00
I $ 1,652.00
1
(Labor - Golden Gate (Apprentice Electrician)
( 4
8
1 Hours
1$ 51.00
1$ 72.00
$ 780.00
1
1Labor -Golden Gate (Apprentice Electrician)
I 4
l 8
Hours
1$ 51.00
1$ 72.00
I$ 780.00
1
Labor Markup(Pivetta)
$ 13,482.00
I Cents/Dollar
1 $ 0.31
$ 4,179.42
1
Labor Markup (GGE)
I $ 4,868.00
I Cents/Dollar
1 $ 0.31
I $ 1,509.08
1
(Equipment Pivetta (Pickup Truck)
I 22
1 Hours
I $ 30.00
I $ 660.00
1
Equipment - Pivetta(Dump Truck)
I 22
1 Hours
1 $ 92.00
I $ 2,024.00
1
Equipment Pivetta (Excavator)
I 22
I Hours
1 $ 110.00
I $ 2,420.00
1Equlpment Pivetta(Excavator)
22
Hours
I $ 110.00
1 $ 2,420.00
1
Equipment - Pivetta(Loader)
I 22
Hours
$ 110.00
I $ 2,420.00
1
Equipment -Golden Gate (Pickup Truck)
12
Hours
I $ 46.00
1 $ S52.00
1
Equipment - GoldenGate(PickupTruck)
12
1 Hours
I $ 30.00
$ 360.00
Equpmcnt Gold- Gatc IBobwt Excawtorl
12
Hours
I $ 68.00
I $ 816.00
Equipment Golden Gate (Material Handlet)
12
Hours
I $ 52.00
$ 624.00
Equipment -Golden Gate (Lowboy Trailer)
12
Hours
I $ 40.00
$ 480.00
1Eguipment Markup (Pivetta)
I $ 9,944.00
1 Cents/Dollar
1 $ 0.21
$ 2,088.24
Change Order #38, Page 6 of 14
PSE Live Wire Conflicts - Estimated Change Order Cost
Change Order Cost (Equitable Adjustment) Change Order No. 38
Project Name: Rainier Ave S Corridor Improvements - Phase 4
Contractor: Pivetta Brothers Construction, Inc.
Contract No: CAG-22-163
Federal Aid No: STPUL-1615(005) By: Shannon Tremper
Construction Manager: Perteet Date: 2/11/2025
Item No.
I Description
Quantity
Unit
Unit Price
Estimated Cost
Equipment Markup (GGE)
$ 2,832.00
Cents/Dollar
$ 0.21
$ 594.72
(Materials - Pivetta (Shoring)
I 1
I LS
I $ 40000
i $ 400 00
Materials Markup
I $ 400.00
I Cents/Dollar
I $ 0.21
$ 84.00
ISubcontractorMarkup1
$ 9,803.80
1 Cents/Dollar
I $ 0.12
$ 1,176.46
CALCULATED TOTAL:
ESTIMATED TOTAL:
$ 41,157.92
$ 42,000.00
Item Change
38-D76
Resolution of Utility Conflicts Between Proposed JUT and
Existing PSE Vault
1
EST
5 10,000.00
$ 10,000.00
38-D77
Resolution of Utility Conflicts With Live PSE Wires
1
EST
$ 42,000.00
$ 42,000.00
Estimated Change Order Cost Without Sales Tax (Schedule D)
$ 52,000.00
Sales Tax Schedule D 110.10%
5,252.00
TOTAL CHANGE ORDER COST
I $ S7,252.00
Summary of Contractors Quotes:
Item Quote Location Quoted Cost
N/A N/A
Total Quoted Added Cost:
Change Order #38, Page 7 of 14
PSE Live Wire Conflicts - DBE Change Order Table
Change Order DBE Participation Tracking (LAG 26.35)
Project name: Rainier Ave. Corridor Improvements - Phase 4
CAG Number. CAG-22-163
Date: 3/21/2025
New COA DBE
Current COA DOE
COA DBEs
Bidltem
Change
Contract COA
Change Order
Net Change Order
Participation by
Commitment (may
Description
Amount Assigned
Number
Order
Commitment
Amount
Subcontractor and
be changed by
Sub -contractor name
to COA DBE
Bid Item
WSDOT)
Golden Gate Electric
Fiber Optic Sizing
4
$6,975,974.00
$38,616.76
$9,651+60
$6,985,625.60
$6,975,974.00
Change to Schedule80
5
$6.975.974.00
$174,913.80
$148.411.10
$7,134,036.70
$6,975,974.00
Procure JUT Materials
7
$6.975,974.00
$99,090.001
$45,000.00
$7.179,036 70
$6.975,974,001
Overhead Added Days for JUT Material Delivery
8
$6,975,974.00
$231,454.421
$27.000.00
$7,206.036 70
$6,975.974.00
Victoria Sch 80 Conduit
9
$6.975,974.00
$103,853.141 $22,406.40
$7,228,443 10
$6.975,974.00
Removal of Private Lumianues & Business Sign in
14
$6,975,974.00
$26,00000 E13,00000
$7.241,443.10
$6,975.974.01
ROW
CMP for Foundations
16
$6.975,974.00
$38,225.001 $29.581.00
$7,271,024 10
$6,975,974 Oil
Resolution of Conflicts for Signal & Illumination
17
$6,975.974.00
$50,000.00j $25,000.00
$7,296,024 10
$6,975,974.0
Electrical Service Connections
21
$6,975.974.00
$195,000 001 $143,913 71
$7,439,937 81
$6,975,974.00
JUT Dewatenngand Utility Conflicts Impacts
22
$6,975,974 00
$146,498271
$130,593 72
$7,570,531 53
$6,975,974 00
Additional Electrical Connection
26
$6,975.974.00
$3,800001
$3,392 86
$7,573.924 39
$6,975.974.00
Install Corrugated Metal Pipe at Signal Pole
34-A198
Foundations, 5-foot
34
$ 6.975.974 00
$ 9,828.00
$ 8,775.00
$ 8,775.00
$ 6,975,974.00
Install Corrugated Metal Pipe at Lummaue Pole
34-A199
$ 4.00000
$ 3,575.00
$ 3,575.00
I $ 6,975,974.00
Foundations, 4-Foot
Install Corrugated Metal Pipe at Luminane Pole
34-A200
Foundations, 8-Foot
$ 1,200.00
$ 1,075.00
$ 1,075.00
$ 6,975,974.00
Install Corrugated Metal Pipe at Luminave Pole
34-A201
$ 7,00000
$ 6,25000
$ 6.250 00
$ 6,975,974.00
Foundations, 10-Foot
Previous Change Order Totals:
$6,975,974.00
$1,129,479.48
$617,625.39
$7,593,599.39
$6,975,974.00
Resolution of Utility Conflicts Between Proposed
38-D76
38
$ 6,975,974 00
$ 10,000.00
$ 2,500.00
$ 2.500.00
$ 6,975,974.00
JUT and Existing PSE Vault
Resolution of Utility Conflicts With Live PSE
38-D77
$ 30,000.00
$ 10,000.00
$ 10,000.00
$ 6,975,974.00
Wires
Cumulative
$ 6,975,974.00
$1,169,479.48
$ 630,125.39
$7,606,099.39
$ 6,975,974.00
Totals
$ 6,975,974.00
$ 1,169,479.48
$ 630,125.39
$ 7,606,099.39
$ 6,975,974.00
Non-COA DBEs
Bid Item
Number
Description
Change
Order
Original Contract
Amount
Change Order
Amount (+/-)
Original Contract
amount Assigned
to non-COA DBE
Net Change Order
Amount Assigned to
non-COA DBE
New non-COA DBE
Status by
subcontractor and
bid item
$
$
$
E
$
$
$
$
E
$
$
is
$
$
$
$
Cumulative
-
$ -
$ -
$
$ -
Totals $ . $ $ $ $
Current Contract COA DBE Participation $ 7,606,099.39
Available Current Contract Non-COA DBE Participation $ -
Current Contract COA plus non-COA DBE Participaton $ 7,606,099.39
Amount of COA plus non-COA DBE Participation Applied to COA Commitment (may be changed by WSDOT) $ 6,975,974.00
4 " l " // 14- 0321 2025
Yu Hong Wu, President Date
Golden Gate Electric & Construction LLC
Change Order #38, Page 8 of 14
' PSE Live Wire Conflicts - Estimated Change Order Cost
FIELD DIRECTIVE
Protect Name Federal Aid N Contract No.
Rainier Ave S Corridor Improvements -
Phasc 4 (5 3rd ST to NW 3rd PL) STPUL-1615(005) CAG-22-163
F IC d Dircctwv Dcscnption � �F,,I Il Q,—t,gg No.
PSE Conduits with Wire 080
Contractor
Ptvetta Brothers Construction
The following is documentation of on oral order given by the Engineer per WSDOT Specification 1-04.4
P PERTEET
8012nd Avenue. Suite 302, Seattle, WA98104I P206.436.0515
Date
The Contractor shall replace sheets 150,151, 158,159, and 244 with the attached updated sheets 150, 151, 158, 159, and 244.
This work will be tracked by force account and paid as port of o future change order
Protect Engineer (or Representative)
Jordon Howe
Date
10/3R024
10/4/2024
J
Change Order #38, Page 9 of 14
�:aa•Isu�=��a�R�a?
£I�
w
8g
_
r�
W S
'i F) RIP
a
UEl ; 2 N
S pS Q z f7
N N N
}
um
_ � r
ISI 133M 00+6C r15 W WjvR ® '
0 I -.; ! I I •a.
21' I �I �I• I z
a I I I w
m�
O ! \I
o �71r,
I a
o> j W ` 5 - ea4�
rn a 3S E[a
zxi ( I aNa o
o I
r r
Q J
I
r'
a
S
1`
w r—
�'�
J 6*1 1331G OS+W V15 31M1 1Mvm
W
fn
a
J
J'
O
U
d'
{pg�j
O
w
x�
i
W
6
C
��yy
y�y�yy
m
s
z
k
Wd SZ Y KOUf/01 ew LOliwtwy,\,�on�\anuw�NN�¢30\wa
rn
ry
h
gg
d
�
�h
•-
g
�p o
s
0
ZS6 �b8� i tu
0 El
aZ
occ
U N Z Q
z
W <-
W Z �
V �
r
Q O
a a F F
5
W
o rc
U _W F
Z
U
oui
1 I I3y1 3
i
_iI g Z��5
E
Id ONE MN u+68g (001
— _j '•r, .
I
C ,3
a C I
0
CD
LJ
L�I IOSI 133H5 DO�6L v1S 3NL1 VK)1VN -
a
.d 9l 9 rjoZ/L/0, s.p LolIY-Yi90r�\1mn�J\a6uwd�WJK30\r44
�
w
J
�
r
r
LLL
N
11
3e
s
ii Y
s
is
Sd
p
Y
� z
4
vi
Z
2
Z
Z
_
W
I(yKy'�
M
691 133N6 00+K y1S 3Nn loiym
W
S
g
. u111!
P
R
I,
IL
i
K
w^ ;C S mz/C/o. D. ionwso 1f
N
a
yy oW
0.
a ¢ �67
asp WMI I I I ICI ICI ¢�_
N
�Z U
2
o,1'
a
00 S n
> r
a Z
S
2
w
Z
w �
zr
a
> r
to
a a F
o�
G 6
o
LU
J 1:1N jii ~
Z
g li III m o
LD -a „ t,1E ❑
so
t.f
I I
Id ON£ MN I -
._.__
ra
I� 11 i I�
d III I
uwi I - 95t t335 00+6f v1S $1n Iglrw
a -
n, ,c 9 .zozlcJ01 .caa.r.KL,, .._ .
a
yy oW
0.
a ¢ �67
asp WMI I I I ICI ICI ¢�_
N
�Z U
2
o,1'
a
00 S n
> r
a Z
S
2
w
Z
w �
zr
a
> r
to
a a F
o�
G 6
o
LU
J 1:1N jii ~
Z
g li III m o
LD -a „ t,1E ❑
so
t.f
I I
Id ON£ MN I -
._.__
ra
I� 11 i I�
d III I
uwi I - 95t t335 00+6f v1S $1n Iglrw
a -
n, ,c 9 .zozlcJ01 .caa.r.KL,, .._ .
a
NI B
o a 3� M
F #
Z
YY y
J cc
Z w �N
to3= 3
z �a �o a oc
� 00000®®®O 2.RW SNo
N J 0 S Q
aapp J J
S < W a
d'
S W w
� F N W
W W
a w
N Q O Z
z
N z
3
7
O
F
;G
s a
J d
u
Set 133N5 00+6t r15 An N31vw
W
CAI a4
s�
Nxy1gW
u
�4
4
r
— aI F i J>
O ®
UI ii S :t F .`
0 1 I a- Q `7
sR j
>
11J fK 13345 OS+SC r15 3Nf1 431rw
� R
a
l
w, rs c �rnan/a. n.o F'osr.�eor���nn�o��:ew.�.un ai�im„w — .Wo. - ,re,, ,