HomeMy WebLinkAboutChange Order - 3840 CAG-22-163, CO #38-25 Change Order No. 38 Contract Title: Rainier Ave S Corridor Improvements — Phase 4 Contractor: Pivetta Brothers Construction, Inc. Contract No.: CAG-22-163 Federal Aid No.: STPUL-1615(OOS) ® Ordered by Engineer ® Force Account ❑ Proposed by the Contractor (VECP) ❑ Bid Item ❑ Unilateral ❑ Bid Item Price Adjustment ❑ Lump Sum If yes, must receive concurrence from Local Programs Affects DBE Work: ❑ No ®Yes prior to execution. Amount Working Days Original Contract: $28,284,172.90 500 Current Contract: $3S,625,581.85 654 Estimated Net Change This Order: $57,252.00 0 New Contract: $35,682,833.85 654 tr e By: Resi ent Engineer Date Reviewed By: 4/1/2025 Engineer of Record Date Reviewed By: 4/2/2025 City of Rento Project Manager Date Iss B � ZS ngineer (city of Renton Transportation Date Design Manager) Consent By: Surety (Greater than 25% cost and/or 20% Date time increase) Endorsed By: Digitally signed by Bill Adams Bill Adams Date: 2025.04.1018:48:18-07'00' 4/10/2025 Contractor Date Reviewed By: Executed By: Approved by Cheryl Beyer via email 4/2/2025 4/30/2025 City Attorney Date City of Renton Public Works Date RE"r° Administrator /Mayor Attest: � Jason Seth, City Clerk ,°' Change Order No. 38 Contract Title: Rainier Ave S. Corridor Improvements — Phase 4 Contract No. CAG-22-163 Page 1 of 14 THE CONTRACT IS MODIFIED AS FOLLOWS: Description of Change: The Contractor encountered an existing PSE vault and conduit at STA 38+33 LT that was in conflict with the proposed Joint Utility Trench. The Contractor was required to relocate the vault and conduit. Additionally, the Contractor discovered live wires inside conduits designated for removal, which conflicted with proposed storm excavation at STA 28+85 LT, proposed sewer excavation at STA 39+88 LT, the proposed hydrant at STA 24+24 LT, and proposed luminaire foundations for poles 32/P49 at STA 38+06 LT, PS2 at STA 38+70 LT, 34/P54 at STA 39+33 LT, and P56 at STA 40+07 LT. PSE is unable to address the conflicts at the storm and sewer locations quickly enough to prevent impacts on the proposed work. Therefore, the Contractor shall proceed with reasonable care to protect the conduits while continuing storm and sewer installations until PSE can deactivate and remove the wires. Conduit with live PSE wires is in direct conflict with the proposed hydrant at STA 24+24 LT, preventing hydrant installation. The Contractor shall postpone the hydrant installation until PSE has deactivated and removed the wires. The live PSE wires in conflict with luminaire foundations between STA 37+7S LT to STA 40+46 LT must remain active. The Contractor shall trench and install new conduit from STA 37+7S LT to STA 40+46 LT to house the PSE wires and install a new handhole at STA 37+80 LT per Field Directive #80. Proposal Schedule of Prices: ADD the following to Schedule D: 38-D76 — Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault, 1 EST @ $10,000.00 = $10,000.00 38-1377 — Resolution of Utility Conflicts With Live PSE Wires, 1 EST @ $42,000.00 = $42,000.00 Specification and/or Special Provision: ADD the following Section 8-26.3(1): The Contractor shall coordinate with PSE to relocate the existing PSE vault and conduit at STA 38+33 outside of the proposed Joint Utility Trench. Change Order No. 38 Contract Title Contract No. Rainier Ave S. Corridor Improvements — Phase 4 CAG-22-163 Page 2 of 14 ADD the following Section 8-26.3(2): The Contractor shall install the proposed storm and sewer pipes at STA 28+85 LT and STA 39+88 LT. The additional work required to install the proposed storm and sewer while maintaining the existing conduits will be addressed as part of the item added part of this Change Order "Resolution of Utility Conflicts With Live PSE Wires." The Contractor shall defer installation of the hydrant at STA 24+24 LT until such time that PSE has deenergized and removed the active wires. The Contractor shall trench and install new conduit from STA 37+75 LT to STA 40+46 LT to house the wires that PSE could not remove and install a new handhole at STA 37+80 LT per Field Directive #80. Description: None. Materials: None. Measurement: ADD the following to 8-26.4: "Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault," force account. "Resolution of Utility Conflicts With Live PSE Wires," force account. Payment: ADD the following to 8-26.5: "Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault," by force account. "Resolution of Utility Conflicts With Live PSE Wires," by force account. Materials Specifications: None. Change Order No. 38 Contract Title: Rainier Ave S. Corridor Improvements — Phase 4 Contract No. CAG-22-163 Page 3 of 14 Plans: DELETE Sheets 150, 151, 158, 159, and 244. REPLACE with Sheets 150, 151, 158, 159, and 244. Reason for Change: During the installation of the Joint Utility Trench at approximately STA 38+33 LT, the Contractor discovered a live PSE vault in conflict with the proposed trench. Coordination with PSE determined that the vault needed to remain active and would have to be relocated outside the trench. This vault was not identified in the information provided by PSE. While excavating for storm at STA 28+85 LT, sewer at STA 39+88 LT, hydrant installation at STA 24+24 LT and luminaire foundations between STA 37+75 LT to STA 40+46 the Contractor discovered conduits containing live PSE wires within an existing duct bank designated for removal. These wires were part of the utility conversion plan and were to be deactivated and removed by PSE, but these locations had not been addressed. As a result, the presence of live wires created conflicts with the installation of the proposed infrastructure. This Change Order is necessary to create items to compensate the Contractor for costs incurred due to these conflicts and additional work required to resolve the conflicts. Equitable Adjustment: This Change Order does include an equitable adjustment per Section 1-09.4 of the 2022 WSDOT/APWA Standard Specifications. See attached. Estimated Cost: $ 57,252.00 Extended Overhead: $ 0.00 Force Account Time Related Damages per 1-09.6.6.d: $ 0.00 Total: $ 57,252.00 38-1376 — Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault An independent estimate was prepared for the cost to resolve conflicts between the proposed JUT and existing PSE vault. This cost was calculated to be $7,676.52 and has been rounded to an estimated cost of $10,000.00. Change Order No. 38 Contract Title: Rainier Ave S. Corridor Improvements — Phase 4 Contract No. CAG-22-163 Page 4 of 14 r. 38-D77 — Resolution of Utility Conflicts With Live PSE Wires An independent estimate was prepared for the cost of resolving conflicts with live PSE wires. This cost was calculated to be $41,157.92 and has been rounded to an estimated cost of $42,000.00. Extension of Time: The Time for Completion is extended 0 Working Days. Affects DBE Work: Yes. Sections 1-04.4 and 1-04.5 of the 2022 WSDOT/APWA Standard Specifications shall govern this Change Order. The Work of the referenced Contract is modified to include the changes detailed herein. The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change. To be attached to Change Order: ® 1-Estimated Change Order Cost ® 2-Plans ® 3-Field Directive/Request for Information Response ❑ 4-Change Order Quotation ❑ 5-Project Labor List ❑ 6-Force Account Equipment Rate Request (DOT Form 422-010 EF) ❑ 7-Equitable Adjustment Determination O 8-Additional Working Days Calculation Change Order No. 38 Contract Title: Rainier Ave S. Corridor Improvements — Phase 4 Contract No. CAG-22-163 Page 5 of 14 PSE Live Wire Conflicts - Estimated Change Order Cost Change Order Cost (Equitable Adjustment) Change Order No. 38 Project Name: Rainier Ave S Corridor Improvements - Phase 4 Contractor: Pivetta Brothers Construction, Inc. Contract No: CAG-22-163 Federal Aid No: STPUL-1615(005) By: Shannon Tremper Construction Manager: Perteet Date: 2/11/2025 Item No. Description I Quantity Unit Unit Price Estimated Cost Independent Cost Estimate 38-D76 Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault REG OT REG OT Labor Pivetta (Foreman) 4 Hours $ 96.00 $ 384.00 Labor - Pivetta(Operator) 4 Hours $ 92.00 $ 368.00 Labor - Pivetta(Operator) 4 Hours $ 92.00 $ 368.00 Labor • Pivetta (Operator) 4 Hours $ 92.00 $ 368.00 Labor - Pivetta(Operator Truck Driver) 4 Hours $ 92.00 $ 368.00I Labor - Pivetta(Laborer) 4 Hours $ 75.00 $ 300.00 Labor -Golden Gate (Electrician Foreman) 4 Hours $ 110.00 $ 440.00 Labor -Golden Gate (Electrician) 4 Hours $ 109.00 $ 436.00 Labor -Golden Gate (Apprentice Electrician) 4 Hours $ 51.00 $ 204.00 Labor -Golden Gate (Apprentice Electrician) 4 Hours $ 51.00 $ 204.00 1Labor Markup (Pivetta) $ 2,156.00 Cents/Dollar I $ 0.31 $ 668.36 Labor Markup (GGE) $ 1,284.00 Cents/Dollar $ 0.31 $ 398.04 Equipment - Pivetta (Pickup Truck) 4 Hours $ 30.00 5 120.00 Equipment Pivetta (Dump Truck) 4 Hours $ 92.00 $ 368.00 Equipment Pivetta (Excavator) 4 Hours $ 110.00 $ 440.00 1Eguipment - Pivetta (Excavator) 4 Hours I $ 110.00 $ 440.00 Equipment - Pivetta (Loader) 4 Hours I $ 110.00 1 $ 440.00 Equipment - Golden Gate (Pickup Truck) 4 Hours I $ 46.00 I $ 184.00 Equipment - Golden Gate (Pickup Truck) 4 Hours $ 30.00 $ 120.00 Equipment - GoldenGate(BobcatExcavator) 4 Hours $ 68.00 $ 272.00 Equipment Markup (Pivetta) $ 1,808.00 Cents/Dollar $ 0.21 $ 379.68 Equipment Markup (GGE) $ 576.00 Cents/Dollar 1 $ 0.21 $ 120.96 Subcontractor Markup $ 2,379.00 Cents/Dollar I $ 0.12 $ 285.48 CALCULATED TOTAL: ESTIMATED TOTAL: $ 7,676.52 $ 10,000.00 38.077 Resolution of Utility Conflicts With Live PSE Wires HOURS RATE (Labor- Pivetta (Foreman) I 14 I 8 Hours $ 96.00 I $ 127.00 I $ 2,360.00 I Labor - Pivetta(Operator) 14 I 8 Hours $ 92,00 1 $ 123.00 I $ 2,272,00 Labor - Pivetta(operator) I 14 i 8 Hours I $ 92.00 i $ 123.00 I $ 2,272.00 Labor - Pivetta (Operator) 14 I 8 Hours $ 92.00 1 $ 123.00 I $ 2,272.00 Labor - Pivetta(Operator Truck Driver) 14 8 1 Hours $ 92.00 $ 123.00 $ 2,272.00 Labor - Pivetta(Laborer) I 14 1 8 1 Hours I $ 75.00 1$ 123.00 1 $ 2,034.00 1 1Labor-Golden Gate (Electrician Foreman) I 4 I 8 I Hours I$ 110.00 1$ 152.00 I$ 1,656.00 Labor - Golden Gate (Electrician) 4 8 1 Hours $ 109.00 $ 152.00 I $ 1,652.00 1 (Labor - Golden Gate (Apprentice Electrician) ( 4 8 1 Hours 1$ 51.00 1$ 72.00 $ 780.00 1 1Labor -Golden Gate (Apprentice Electrician) I 4 l 8 Hours 1$ 51.00 1$ 72.00 I$ 780.00 1 Labor Markup(Pivetta) $ 13,482.00 I Cents/Dollar 1 $ 0.31 $ 4,179.42 1 Labor Markup (GGE) I $ 4,868.00 I Cents/Dollar 1 $ 0.31 I $ 1,509.08 1 (Equipment Pivetta (Pickup Truck) I 22 1 Hours I $ 30.00 I $ 660.00 1 Equipment - Pivetta(Dump Truck) I 22 1 Hours 1 $ 92.00 I $ 2,024.00 1 Equipment Pivetta (Excavator) I 22 I Hours 1 $ 110.00 I $ 2,420.00 1Equlpment Pivetta(Excavator) 22 Hours I $ 110.00 1 $ 2,420.00 1 Equipment - Pivetta(Loader) I 22 Hours $ 110.00 I $ 2,420.00 1 Equipment -Golden Gate (Pickup Truck) 12 Hours I $ 46.00 1 $ S52.00 1 Equipment - GoldenGate(PickupTruck) 12 1 Hours I $ 30.00 $ 360.00 Equpmcnt Gold- Gatc IBobwt Excawtorl 12 Hours I $ 68.00 I $ 816.00 Equipment Golden Gate (Material Handlet) 12 Hours I $ 52.00 $ 624.00 Equipment -Golden Gate (Lowboy Trailer) 12 Hours I $ 40.00 $ 480.00 1Eguipment Markup (Pivetta) I $ 9,944.00 1 Cents/Dollar 1 $ 0.21 $ 2,088.24 Change Order #38, Page 6 of 14 PSE Live Wire Conflicts - Estimated Change Order Cost Change Order Cost (Equitable Adjustment) Change Order No. 38 Project Name: Rainier Ave S Corridor Improvements - Phase 4 Contractor: Pivetta Brothers Construction, Inc. Contract No: CAG-22-163 Federal Aid No: STPUL-1615(005) By: Shannon Tremper Construction Manager: Perteet Date: 2/11/2025 Item No. I Description Quantity Unit Unit Price Estimated Cost Equipment Markup (GGE) $ 2,832.00 Cents/Dollar $ 0.21 $ 594.72 (Materials - Pivetta (Shoring) I 1 I LS I $ 40000 i $ 400 00 Materials Markup I $ 400.00 I Cents/Dollar I $ 0.21 $ 84.00 ISubcontractorMarkup1 $ 9,803.80 1 Cents/Dollar I $ 0.12 $ 1,176.46 CALCULATED TOTAL: ESTIMATED TOTAL: $ 41,157.92 $ 42,000.00 Item Change 38-D76 Resolution of Utility Conflicts Between Proposed JUT and Existing PSE Vault 1 EST 5 10,000.00 $ 10,000.00 38-D77 Resolution of Utility Conflicts With Live PSE Wires 1 EST $ 42,000.00 $ 42,000.00 Estimated Change Order Cost Without Sales Tax (Schedule D) $ 52,000.00 Sales Tax Schedule D 110.10% 5,252.00 TOTAL CHANGE ORDER COST I $ S7,252.00 Summary of Contractors Quotes: Item Quote Location Quoted Cost N/A N/A Total Quoted Added Cost: Change Order #38, Page 7 of 14 PSE Live Wire Conflicts - DBE Change Order Table Change Order DBE Participation Tracking (LAG 26.35) Project name: Rainier Ave. Corridor Improvements - Phase 4 CAG Number. CAG-22-163 Date: 3/21/2025 New COA DBE Current COA DOE COA DBEs Bidltem Change Contract COA Change Order Net Change Order Participation by Commitment (may Description Amount Assigned Number Order Commitment Amount Subcontractor and be changed by Sub -contractor name to COA DBE Bid Item WSDOT) Golden Gate Electric Fiber Optic Sizing 4 $6,975,974.00 $38,616.76 $9,651+60 $6,985,625.60 $6,975,974.00 Change to Schedule80 5 $6.975.974.00 $174,913.80 $148.411.10 $7,134,036.70 $6,975,974.00 Procure JUT Materials 7 $6.975,974.00 $99,090.001 $45,000.00 $7.179,036 70 $6.975,974,001 Overhead Added Days for JUT Material Delivery 8 $6,975,974.00 $231,454.421 $27.000.00 $7,206.036 70 $6,975.974.00 Victoria Sch 80 Conduit 9 $6.975,974.00 $103,853.141 $22,406.40 $7,228,443 10 $6.975,974.00 Removal of Private Lumianues & Business Sign in 14 $6,975,974.00 $26,00000 E13,00000 $7.241,443.10 $6,975.974.01 ROW CMP for Foundations 16 $6.975,974.00 $38,225.001 $29.581.00 $7,271,024 10 $6,975,974 Oil Resolution of Conflicts for Signal & Illumination 17 $6,975.974.00 $50,000.00j $25,000.00 $7,296,024 10 $6,975,974.0 Electrical Service Connections 21 $6,975.974.00 $195,000 001 $143,913 71 $7,439,937 81 $6,975,974.00 JUT Dewatenngand Utility Conflicts Impacts 22 $6,975,974 00 $146,498271 $130,593 72 $7,570,531 53 $6,975,974 00 Additional Electrical Connection 26 $6,975.974.00 $3,800001 $3,392 86 $7,573.924 39 $6,975.974.00 Install Corrugated Metal Pipe at Signal Pole 34-A198 Foundations, 5-foot 34 $ 6.975.974 00 $ 9,828.00 $ 8,775.00 $ 8,775.00 $ 6,975,974.00 Install Corrugated Metal Pipe at Lummaue Pole 34-A199 $ 4.00000 $ 3,575.00 $ 3,575.00 I $ 6,975,974.00 Foundations, 4-Foot Install Corrugated Metal Pipe at Luminane Pole 34-A200 Foundations, 8-Foot $ 1,200.00 $ 1,075.00 $ 1,075.00 $ 6,975,974.00 Install Corrugated Metal Pipe at Luminave Pole 34-A201 $ 7,00000 $ 6,25000 $ 6.250 00 $ 6,975,974.00 Foundations, 10-Foot Previous Change Order Totals: $6,975,974.00 $1,129,479.48 $617,625.39 $7,593,599.39 $6,975,974.00 Resolution of Utility Conflicts Between Proposed 38-D76 38 $ 6,975,974 00 $ 10,000.00 $ 2,500.00 $ 2.500.00 $ 6,975,974.00 JUT and Existing PSE Vault Resolution of Utility Conflicts With Live PSE 38-D77 $ 30,000.00 $ 10,000.00 $ 10,000.00 $ 6,975,974.00 Wires Cumulative $ 6,975,974.00 $1,169,479.48 $ 630,125.39 $7,606,099.39 $ 6,975,974.00 Totals $ 6,975,974.00 $ 1,169,479.48 $ 630,125.39 $ 7,606,099.39 $ 6,975,974.00 Non-COA DBEs Bid Item Number Description Change Order Original Contract Amount Change Order Amount (+/-) Original Contract amount Assigned to non-COA DBE Net Change Order Amount Assigned to non-COA DBE New non-COA DBE Status by subcontractor and bid item $ $ $ E $ $ $ $ E $ $ is $ $ $ $ Cumulative - $ - $ - $ $ - Totals $ . $ $ $ $ Current Contract COA DBE Participation $ 7,606,099.39 Available Current Contract Non-COA DBE Participation $ - Current Contract COA plus non-COA DBE Participaton $ 7,606,099.39 Amount of COA plus non-COA DBE Participation Applied to COA Commitment (may be changed by WSDOT) $ 6,975,974.00 4 " l " // 14- 0321 2025 Yu Hong Wu, President Date Golden Gate Electric & Construction LLC Change Order #38, Page 8 of 14 ' PSE Live Wire Conflicts - Estimated Change Order Cost FIELD DIRECTIVE Protect Name Federal Aid N Contract No. Rainier Ave S Corridor Improvements - Phasc 4 (5 3rd ST to NW 3rd PL) STPUL-1615(005) CAG-22-163 F IC d Dircctwv Dcscnption � �F,,I Il Q,—t,gg No. PSE Conduits with Wire 080 Contractor Ptvetta Brothers Construction The following is documentation of on oral order given by the Engineer per WSDOT Specification 1-04.4 P PERTEET 8012nd Avenue. Suite 302, Seattle, WA98104I P206.436.0515 Date The Contractor shall replace sheets 150,151, 158,159, and 244 with the attached updated sheets 150, 151, 158, 159, and 244. This work will be tracked by force account and paid as port of o future change order Protect Engineer (or Representative) Jordon Howe Date 10/3R024 10/4/2024 J Change Order #38, Page 9 of 14 �:aa•Isu�=��a�R�a? £I� w 8g _ r� W S 'i F) RIP a UEl ; 2 N S pS Q z f7 N N N } um _ � r ISI 133M 00+6C r15 W WjvR ® ' 0 I -.; ! I I •a. 21' I �I �I• I z a I I I w m� O ! \I o �71r, I a o> j W ` 5 - ea4� rn a 3S E[a zxi ( I aNa o o I r r Q J I r' a S 1` w r— �'� J 6*1 1331G OS+W V15 31M1 1Mvm W fn a J J' O U d' {pg�j O w x� i W 6 C ��yy y�y�yy m s z k Wd SZ Y KOUf/01 ew LOliwtwy,\,�on�\anuw�NN�¢30\wa rn ry h gg d � �h •- g �p o s 0 ZS6 �b8� i tu 0 El aZ occ U N Z Q z W <- W Z � V � r Q O a a F F 5 W o rc U _W F Z U oui 1 I I3y1 3 i _iI g Z��5 E Id ONE MN u+68g (001 — _j '•r, . I C ,3 a C I 0 CD LJ L�I IOSI 133H5 DO�6L v1S 3NL1 VK)1VN - a .d 9l 9 rjoZ/L/0, s.p LolIY-Yi90r�\1mn�J\a6uwd�WJK30\r44 � w J � r r LLL N 11 3e s ii Y s is Sd p Y � z 4 vi Z 2 Z Z _ W I(yKy'� M 691 133N6 00+K y1S 3Nn loiym W S g . u111! P R I, IL i K w^ ;C S mz/C/o. D. ionwso 1f N a yy oW 0. a ¢ �67 asp WMI I I I ICI ICI ¢�_ N �Z U 2 o,1' a 00 S n > r a Z S 2 w Z w � zr a > r to a a F o� G 6 o LU J 1:1N jii ~ Z g li III m o LD -a „ t,1E ❑ so t.f I I Id ON£ MN I - ._.__ ra I� 11 i I� d III I uwi I - 95t t335 00+6f v1S $1n Iglrw a - n, ,c 9 .zozlcJ01 .caa.r.KL,, .._ . a yy oW 0. a ¢ �67 asp WMI I I I ICI ICI ¢�_ N �Z U 2 o,1' a 00 S n > r a Z S 2 w Z w � zr a > r to a a F o� G 6 o LU J 1:1N jii ~ Z g li III m o LD -a „ t,1E ❑ so t.f I I Id ON£ MN I - ._.__ ra I� 11 i I� d III I uwi I - 95t t335 00+6f v1S $1n Iglrw a - n, ,c 9 .zozlcJ01 .caa.r.KL,, .._ . a NI B o a 3� M F # Z YY y J cc Z w �N to3= 3 z �a �o a oc � 00000®®®O 2.RW SNo N J 0 S Q aapp J J S < W a d' S W w � F N W W W a w N Q O Z z N z 3 7 O F ;G s a J d u Set 133N5 00+6t r15 An N31vw W CAI a4 s� Nxy1gW u �4 4 r — aI F i J> O ® UI ii S :t F .` 0 1 I a- Q `7 sR j > 11J fK 13345 OS+SC r15 3Nf1 431rw � R a l w, rs c �rnan/a. n.o F'osr.�eor���nn�o��:ew.�.un ai�im„w — .Wo. - ,re,, ,