Change Order No. 03
Backup
Documentation
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating, Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
Attachments:
Backup Documentation
® Field Directive
® Equitable Adjustment Determination
® Determination of Additional Working Days
® Engineer's Estimate of Change Order Cost
® Engineer's Calculation of Additional Working Days
® Contractor's Quote
• Project Labor List
• Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement
El Summary of invoices for rented equipment
• Summary of invoices for materials
Change Order No. 03 Triple Tree Removal
Contract Title: Duvall Avenue NE
Contract No. CAG -20-065
Page 1 of 1
• r
City of Renton
Field Directive No: 9
Project Name: Duvall Ave NE
Contractor. Reed Trucking and Excavating,Inc.
Contract No: CAG-20-065
Federal Aid No: N/A By'
TIB No: N/A
Construction Manager: Tani Stafford Date: 7/2022,
The following is documentation of the oral order given by the Resident Engineer per WSDOT Std Spec 1-04.4
The Contractor is directed to do the following additional work:
Remove a triple maple at approximately Sta 895+23 RT in lieu of 1 each 12-inch maple tree at the this location
The extra tree removal will be paid via a new contract item at the lump sum price based on the invoice recieved
for a total of$3,339.00
Rough Cost Estimate,WSDOT Construction Manual 1-04.4,Changes.
Cost Adjustments: 3-A100
The added work will be paid at a new contract item-F302 Triple Tree Removal for the lump sum price of
$3,339.00.
A Change Order covering this Field Directive will follow immediately.
Contractor Date
\1
Equitable Adjustment Determination - CO No 3
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:2/20/22
New Contract Item Cost
New
Contract Quantity
Item No. Description Change Unit Unit Price Total
3-A100 TRIPLE TREE REMOVAL 1 LS $3,339.00 $3,339.00
New Lump Sum Contract Item Cost $3,339.00
LUMP SUM CHANGE ORDER COST I $3,339.00
Narrative:
The equitable adjustment for removing a triple maple tree at Sta 895+23 RT in lieu of a 12-inch tree as
shown on the plans is determined to be$3,339.00 lump sum
The Engineer's estimate of$3,400 was prepared 2/17/2022, based on unit prices for•similar work on a recent
bid tab.
FWD No 9 was sent out on 2/17/22.
The Contractor sent a quote for the work on 2/16/22, based on quotes received from the logging
subcontractor. The Contractor's quote was reviewed and accepted, it was less than the Engineer's Estimate.
Determination of Additional Working Days
A determination of zero additional working day was made.
Engineer's Estimate.
City of Renton-Duvall Ave NE,CAG 20-065
Field Directive No 09
Engineer's Estimate
Date:2/17/22
Qty Estimated
Item No. Description Change Unit Price Amount
Added Cost to remove group of 3 trees-vs-1
** tree 1 LS $3,400.00 $3,400.00
Total(rounded) $3,400.00
Used tree removal bid from SeaTac project Remove 12"tree= $ 1,696.13 per EA
2 extra trees= $ 3,392.25 LS
., A
t588a85a88855a858888888881888888888858888888 a 5858885855858e88a888888888188888 ka
8saassalgsaasssaasasa!ast
gii?1,§144§111111AgAWMA.IMO!MV40§!!1,1§ ! ;a0aaga5a4alala!lallailalagiaa5Railaalmaafaitpaavagal
.aaamgmaggpaagiaamagaag.50-mamagaag 4.aaEaE a Eau3,:,aliss.,aart.c,.al EsE..ss "EsEE. Es*SsEaE.A..,..U.ssal
i' sass S8Si 8 a 8 esesesa2 38888 at sta ersaseass a seas sess8 sasassasassasa 88$28 aaa.18 38E18 seas 8E1388888 88 8888
FaIIIIEE2.31143R13:431VIR2.9 g(I) itAgAggilif!IMEIHRIPPIR'ilinkPlAWigla!!!!!Ngq!!
11,.3....,,ii al.,- -a a - -. -- - ....... ,,aaa a aa a u 3
VE
iseassassaseass;sassassassaassaasesassesaass a sassassesassassassasasasasesassassassasasassassessaassas
iRFliiMali..791i111§CEViJiEA!IEEAill ! AERMEKEEE,M.SIEgAbli1RWIEUEMAEONESOIRE'EiMUIE6211
ZE5s agagsaga4aagamaligaa5a5mmape3 aamagga . 412.443.i2"5E!"Qi* Ea 32 mgamaam ammmm5aamamaamamgmqg
li
i 88888888V58I ' 5!55=5585WI558518g81585A; 8 8:88-T8*88885;::4.1888;5*148;888855:;I88;588;5;885!;8;
0
gliMilliiiiiiiillIMMINI!!!!!!P ! Iiiiiiiii!iiii!iliqiiilliWIN!!!!!!!!!!!!iiiiiiii
i.-
IP
8 8818$8888a8p tpasa888@aaassa8a8888888888 8 88aaaalssaasaassaaaaaasssaapassasHs§aasssaeassasaaaa88
t g Haalaglaaaaaaaaallgjaammam.ialaig..gagfaligagrlagaalagaa
aR
.18888488888888888888888888888888888888888585 s 8818888118888888828888881111988181111888gW8s5*I58;88;
101M11111§1pattpium§0§piili@gpp§fl I 5taalaga.aptala5kg/1.1A,_ lda.,,a I ..40... n „ _ , ,
aR232EldIE1:-4.g.51...:7461Pga7,1211a;A af; E°.g . .45.25mm.mmm.agummam amamm- mm asEas !"1-....-233- E-s-111
g5
r88888e8858888 8 ssasasassasassasasssassassa a 88s8ea88a888888888888888888888888888889888888888888888a8
1,1440liaalaaa5 azaaaaaamgaggma5magmggualaa a apaalaaafaaaaalaglagatmmgalailaagaarillaaagaMMMI4
!.... '3 .
118885
11118
1115888118118911111511188.85885I8 8 8811198558118i181188S
2
l8
85588
*55838
5
8
5
8
8801811111;111
g,:,'AP. !gmamagaxi mamamaaama gmma5a5g mg PCIE g iPfi"iE 1"IFF mmag"9=5 mm mmamaam Y.Iss-aaa-RsEas4 "11
iq
!: ll ass2sseess !34!3$83;sears!88838$18!!BW; 5 !1 ?",$6E$ARAsasega!a882:81:!,,11,pts,g,,!,,s,Lislipl,1;
g,31114,E ,E 43ftaa1-.Ells,111A-4EsaE.12112L! I alVIIMAIR31111.11-2,1 -3-. 2•. 1.-aa2a23212,,1 2 3
r„am E:i.a aal a agaaasa dal N a . R "" ' l;
R
a88888888884888885a58e888858g885.v88885888 8 8888888!818888888888188.9884888881818888:11113888555s8
i §§14§§§A§kg&AMWRIX12§M§IFii1M210 8kg:',4Z2It3-§832,01MA 00,—.2:. 32§FIRA - - 3 5,G 0
11
I
u ""s""Ssss 885885e88885s885233,I8:885:: , :8888188.1188885I88888s8855511,558t,1111488I88I8888g81
bril!!!!ITI1 -sEsssss-E!!!"" .s EaEasaa s agnaalPaINEE-5aai 1! g mi-mmfa - .. 231 1 ,-.2. ii
4
; ;l PVIMI;;;;;Inli;;;;;aG123EfWilP123a2'8F.F.2.2.3.1a%Uai6a1 aimmmaa a aamammamgmatimmmam2. ammm3"mm.maai-‘11 mmmaaamigaama mmggE
8888888888888 i 888828888883888883888 a seasalessissesssaaswassRe2sasx.2scassagsamastassassesgss$.155aiamtairia gaggiaiimmamaimagmggaiiii i agpaairagginagtawaiimmgmaiaaaagtaaagiaaagailt55w,g1
388888888888888888838888888888888888883888 1 883s58e85*8il5e88888888888588g888s8a888s888888q8888888888
Pil§1§1§§4§§11414.1E1W1§11§1M§MP!§/§§ ?i §gAM11111111§§gAkrTAMIlilFqkkMAIVTOM§§
aaf. ", EgiP1M33. ".!-°' -42::"aEaaa aVi'ma 5amamma amaiammma "m P.m" m m iaa ammm-aagm. B2 a'322g1
A888888888888 wass!aas8asssa888888818aassa 8 easa88846R888S3assassaaag$8838agags88898@aaSea8SaSsauges
,tFialataaataaa aagmga...amaagamaamagmggigaig a afaa§g§IIIIIIIIE9WRII"PIIIIII1,-.51PHIIIIIIIIIIEWM ai --.--R- .RA - -. . auaaaa l5ka. a. . 5 ..... . rig
5
1 888881888888883888458g885885a8588888s558aa 8 88sasessagassaaaaaa888888Fasiaaasaasagsaassaaaaalaaassa
g§t4M4441§1§;§§11§P§A111§1134W1A11141 ! =§!!!f!18Mill§gg.flAMPA$211 !E!g!IIIMA;!!!!!,,!!!! /1!!§!
immmaigdIN.gueagamgag.atamgmmaaa.gmmgaama. a ag-.mg. m-aiammmag .-.-mm 3 a2rJP 85.1-a.. n-w. -46
1 11_ 8
_
S ``141;1;";;;;Wt;itgigttalt;;IlttitttiNt t INIUMMIWINitiittittgMilMtnigNAIINAiiii
a 1 .
; a
' I I a ,c14-aFall.a-*-1P4.ggSa.Baaaa g ,a....,'-----------0,==--am..,.W—qw,...m.E.,...!,
1 g
1 a Er2mnn*nagn,.542r„:1inn6aattacnlraarnErr,annn n nn;,1:561:564 ;Zt4nnnaas;; Innnaggnsta;444n;;snn
i
; 1i
.111
i 1 i a
al 3 I
1 1 j_ja ! A 1) na 1 J
: . 3 i ll]
2 1 1 3 ; . .41 2 ; „Iiiiil ]
i 0
lipl 1 JIN I,
1 i• ' 1 yr 311,1,11qp_i ,lid3F,;4 111-;!ifig , ;;0111 oj .111 1 1 b. tiAigi him ii
po- 1 ,4,4111-.,illig. :qh.1„W-1 r -a=is,il 11111Ar!(.2 j I, ; IA H _„; mill ....0.1
i i eft c 1 ;1/110Plil;lil viiji.d'l4,11 1 -100-'-r4"14P11111 j,i' ;1111 11111;0411.1111
7' ' -"II kgrilliiiiPirillit'1111113 A "14"41j "AIMIIITP l'"i"1"1111 P)11111111111';° i Haig i . 18_1 a__ ii AD,,,,i ii—_,Aa01.4l,llflaliiii / ./1 i 011.1l4.li ll—Aiia/a3- --, ll
' pw20.“'"-.5.gUll2XXMIM ;ltIllMIMM.g .1 MeeePPMMA7.7.77alassass!222221fli!..........1155-111:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
Engineer's Calculatio Additional Working Days
The Engineer calculates zero added days.The Contractor has kept to their original schedule with the added tree
removal work.
REEDS Change Order Proposal #9 2207 Inter Ave,Ste.A
Puyallup,WA 98372
TRUCKING 6 EXCAVATING Office:(253)841-4837
..,.w....c.a c»wn»...,... w. Contractor Quote Fax:(253)841-4816
GC/Owner: CITY OF Renton JSS#: 9
Reed Job No: 156 Project: Duvall Ave Date: 2/16/2022
Description: cost difference to remove 30'tree with 3 legs vs 12'tree as called out on the plans
Subcontractor:
Labor Costs
Regular Overtime Amount
Craft Employee Name Hours Rate Hrs Rate* Regular Overtime
FM Jordan Ausbun 3 $ 86.42 $ 129.63 $ 259.26 $ -
$ - $ - $ - $ -
$ - $ - $ - $
$ $ - $ - $ -
$ - $ - $ - $
*Including Fringe Benef Labor Subtotal $ 259.26 $ -
Labor Total $ 259.26
Equipment Costs
Equip. Regular Standby Amount
# Equipment Hrs Rate Hrs Rate* Regular Standby
FT03 2020 FORD F-450 3 $ 55.00 $ 27.50 $ 165.00 $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
Equipment Subtotals $ 165.00 $ -
Equipment Total $165.00
Material Costs
Supplier Material Invoice(s) Quantity Price Amount
$0.00
$0.00
$0.00
$0.00
Materials Total $0.00
Subcontractor Costs
Subcontractor Scope Invoice(s) Quantity rice Amount
P and D logging tree removal 1 \\\\$2,500.00 $2,500.00
$0.00
$0.00
$0.00
REED C. $80.37 Subcontractor Total $2,500.00
Cost Summary `'--
TRUCKING 6 EXCAVATING Total Labor $ 259.26
31% .� 29% Labor Mark-up 75.19
Total Equipment $165.00
Date: 21% Equipment Mark-up $34.65
Total Materials $0.00
21% Material Mark-up $0.00
Contractor Foreman /Superintendent Total Subcontractors $2,500.00
12% Sub Markup up to$25K $300.00
10% Sub Markup$25K-$100K $0.00
Date: 7% Sub Mark-up Over$100K $0.00
Grand Total $ 3,334.10
P e Date
Engineer Bid Item Number
$3,339.00
Combined Cutting Contractors, Inc. MEMBER of Lima PROPOSAL
•D.B.A. P&D Tree Service Better
\pv_gd- (425)432-7636 1-877-7664882 Fax(425)413-7991 Business Ask about our low impact
Lic.#CCPNDLOLT867QQ • UBI 601-439-180
Bureau crane removal program!
• www.panddtreeservice.com Visa/Mastercard
panddlogging@comcast.net Fully Insured and Bonded
ustomer Name: 1Zek, TA,citAA E?(6(WA DATE:
ADDRESS: HOME PHONE:
8-6 1 DU Mil Ave_ N
CITY/ZIP: WORK PHONE:
IZZ)7T-0
MAIL: CE3LL: - FAX:
60 .701 ' Oiq .)
COMMENTS: ' •
0•45 -1‘11
We hereby submit specifications and estimate for:
..
,ttsf.a.3. lyet. wovIcl 7'
3) Cbel 1 00 0
5). s A rsc,k.„.v1 / / e--4- a frx.
6). etts,/-- 1-Le loofe ,s 0 "124)_- 1-0 ciJ evro 0
7).
8). 51—c,vle
9). •
10).
12).
13).
•
14).
(
Definitions:Permits are the responsibility of the customer,and shall hold P&D Tree Service harmless.Removal means taking of
something down,never does it refer to hauling or stump grinding. Stump grinding and wood removal are separate charges.
Firewood means rounds; to be left where cut-up.Any moving would be additional charges.If logs are taken,firewood means
..anything too small to go on the truck and too big for the chipper.
credit card processing fee.Full payment upon completion of job,unless other arrangements have been made.20%interest charge
after 30 days.Coupon not to be combined with Visa or MasterCard.All material is guaranteed to be as specified.All work to be
completed in a workmanlike manner according to standard practices.Any alteration or deviation from above specification will become
an extra charge over and above the estimate.All agreements contingent upon strikes,accident or delays beyond our control.Homeowner
to mark trees if away from work site,and will not hold C.C.C.I.responsible for errors.Any timber tax to be paid by the homeowner.The
above prices specifications are hereby accepted.You are authorized to do the work as specified.Payment will be made as outlined above.
...Signature Date
Please see terms and conditions on back REV 01/21
DocuSign Envelope ID:628262B7-AAA2-4BD1-B 6E660BAFDFF
CAG-20-065,CO#3-22
�a s
Change Order No. 3
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking&Excavating Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
Z Ordered by Engineer
❑ Proposed by the Contractor (VECP)
❑ Unilateral
Amount Working Days
Original Contract: 260
$5,218,171.95
Current Contract: $5,220,756.95 260
Estimated Net Change This Order: $3,339.00 0
New Contract: $ 5,224,095.95 260
Prepared By: I e By:
Re ide ngineer ) Date ngineer city o Renton Transportation [Sate
� / Design Manager)
Reviewed By: Consent By:
2/24/22
Engineer of Record Date Surety(Gre an 25%cost and/or 20% Date
_i ai easel
Reviewed By: Endorsed By:
Project Manager 2/24/2022 ,S''c r rrrL .4 2/23/2022
f Re Proj er Date Contractor 6 Date
g
Reviewed By: xec ul4By.:
Approved by Cheryl Beyer via 2/28/2022 email Martin Pastucha 3/10/2022 I 9:37 AM PST
City Attorney Date bty o'lkeng Public Works Date
Administrator/ Mayor
Change Order No. 3
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 1 of 3
DocuSign Envelope ID:628262B7-AAA2-4BD1- -36E660BAFDFF
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
• Add the following lump sum item to the contract:
o Lump Sum Item No. 3-A100 TRIPLE TREE REMOVAL,
Quantity= 1 L.S., Unit Price= $3,339.00 per L.S.
Special Provision
• 2-01.4 Measurement
o The removal of 1 each triple tree,greater than 12-inches, shall be measured by
lump sum.
• 2-01.5 Payment
o This section is supplemented with the following:
"Triple Tree Removal", per lump sum.
Reason for Change:
There was a changed condition. The plans called for the removal of one 12-inch tree at Sta.
895+23 RT. There was found to be a triple maple tree,greater than 12-inches that needed to
be removed at this location. As required per Field Work Directive No 9:the Contractor was
directed to do the following additional work:
• 1 each triple tree for removal at approximately Sta. 895+23 RT in lieu of 1 each 12-inch
tree noted on the plans for removal at this location shall meet the requirements in
special provision section 2-01.
Materials:
No change.
Plans:
No change.
Adjustment:
This Change Order includes changes as defined in 1-04.4. Specifically,the altering size of
specifications (i.e. the tree to be removed at Sta. 895+23 RT). The adjustment shall be
made with the unit price for the new lump sum item.The lump sum cost of this change
is $3,339.00.
Extension of Time:
The Time for Completion is extended 0 Working Days.
Change Order No. 3
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 2 of 3
DocuSign Envelope ID:628262B7-AAA2-4BD1-E 16E660BAFDFF
Equitable Adjustment:
This Change Order includes an equitable adjustment in the unit price of the new lump sum
item.The unit price for the new lump sum item is as follows:
• Lump Sum Item No. 3-A100,TRIPLE TREE REMOVAL, Unit Price=$3,339.00 per L.S.
See attached equitable adjustment determination.
Sections 1-04.4 and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern
this Change Order.The Work of the referenced Contract is modified to include the changes
detailed herein.The payment provided for herein shall constitute the complete and final
settlement for all costs of labor,equipment, materials,overhead,profit, permit fees,and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
❑ Plans
® Equitable Adjustment Determination
Change Order No. 3
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 3 of 3
a
DocuSign Envelope ID:628262B7-AAA2-4BD1-1 '136E660BAFDFF
Equitable Adjustment Determination - CO No 3
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:2/20/22
New Contract Item Cost
New
Contract Quantity
Item No. Description Change Unit Unit Price Total
3-A100 TRIPLE TREE REMOVAL 1 IS $3,339.00 $3,339.00
New Lump Sum Contract Item Cost $3,339.00
LUMP SUM CHANGE ORDER COST I. $3,339.00