HomeMy WebLinkAboutCAG-20-065 - Duvall - Change Order 8 Change Order No. 08
Backup
Documentation
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating, Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
Attachments:
Backup Documentation
❑ Field Directive
® Equitable Adjustment Determination
® Determination of Additional Working Days
® Engineer's Estimate of Change Order Cost
® Engineer's Calculation of Additional Working Days
® Contractor's Quote
❑ Project Labor List
❑ Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement
• Summary of invoices for rented equipment
• Summary of invoices for materials
Change Order No. 08 Cement Conc Price Adj WZA and
WZC
Contract Title: Duvall Avenue NE
Contract No. CAG -20-065
Page 1 of 1
Equitable Adjustment Determination - CO No 8
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:3/14/22
New Contract Item Cost
New
Contract Estimated
Item No. Description Quantity Unit Unit Price Total
8-A104 Cement Concrete Price Adjustment for Work Zones A and C 213.55 CY $84.29 $18,000
ESTIMATED CHANGE ORDER COST I $18,000
Narrative:
The Contractor met with the City on 3/10/22 and related that cement concrete mix material prices are in-
flated compared to when he bid the project due to the ongoing concrete workers strike. The upcoming
critical path item work in Work Zones C and A involves cement concrete curb and gutter. There was dis-
cussion related to allowing the Contractor to move to other work in another work zone, but the Contractor
would like to continue with his current schedule to complete the work in work zones C and A.
The City requested documentation from the Contractor to back up the price increase for the cement con-
crete material for review.
On 3/11/22 the Contractor submitted documentation of current cement concrete pricing and his original
quote, in the form of an invoice and quote. The contractor proposal included a 21% markup for materials
for the concrete subcontractor along with a 12% markup on subcontactor. The proposed unit price for the
concrete price adjustment was $101.99/CY. The City reviewed the documentation and negotiated down
the price adjustment to $84.29/CY for work zones A and C only, while the concrete worker strike affects
the cement concrete material prices.
The engineer's estimate for the volume of cement concrete in work zones A and C was prepared on 3/12/
22, estimated to be approx 213 CY.
Determination of I iitional Working Days
A determination of zero additional working days was made.
Engineer's Estimate of Oh, e Order Cost
City of Renton-Duvall Ave NE,CAG 20-065
Field Directive No 10
Engineer's Estimate
Date:3/14/22
Work Zone
C
Qty
Item No. _Description Change Unit Price Adj/CY Amount
A73 Cement Conc.Traffic Curb and Gutter 53.65 CY $ 84.29 $ 4,522.16
A82-A84 Cement Conc.Sidewalk and curb ramps 106.37 CY $ 84.29 $ 8,965.93
A42 Conc.Class 4000 for Retaining Wall 34.44 CY $ 84.29 $ 2,902.95
Total Work
Zone C $16,391.03
Work Zone
A
Qty
Item No. Description Change Unit Price Adj/CY Amount
A73 Cement Conc.Traffic Curb and Gutter 6.29 CY $ 84.29 $ 530.18
A82-A84 Cement Conc.Sidewalk and curb ramps 11.43 CY $ 84.29 _ $ 963.25
A42 Conc.Class 4000 for Retaining Wall 0 CY $ 84.29 $ -
Total Work
Zone A $1,493.43
Total Estimated Price Adjustment for Work Zone A plus Work Zone C= $17,884.46
Round up to $213.55
CY for an even
$18,000
Engineer's Calculation of Additional Working Dayz
No new work is added so a determination of zero working days has been made. The Con-
tractor has requested an extension of time for the concrete workers but has not provided the
requested and required backup in the form of a schedule showing impact to the critical path.
Contractor's Quote
REED Change Order Proposal #11 2207 Inter Ave.,Ste.A
Puyallup,WA 98372
TRUCKING 6 EXCAVATING Office:(253)841-4837
Fax:(253)841-4816
GC/Owner: City of Renton JSS#: 11
Reed Job No: 156 Project: Duvall Ave NE Date: 3/11/2022
Description: Concrete Price Increase Due to Concrete Strike.
Cost increase is$75.26 plus subs mark up at 21%equals$91.06 CY
Labor Costs
Regular Overtime Amount
Craft Employee Name Hours Rate Hrs Rate* Regular Overtime
$ - $ - $ - S -
$ - $ - $ - $
$ - $ - $ - $
$ - $ - $ - $
$ - $ - $ - $
*Including Fringe Benef Labor Subtotal $ - $ -
Labor Total $ -
Equipment Costs
Equip. Regular Standby Amount
# Equipment Hrs Rate Hrs Rate* Regular Standby
$ - $ - $ - $ -
$ - $ - $ - 5 -
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ $ -
$ - $ - $ - $
$ - $ - $ - $
Equipment Subtotals $ - $ -
Equipment Total $0.00
Material Costs
Supplier Material Invoice(s) Quantity Price Amount
$0.00
$0.00
$0.00
$0.00
Materials Total $0.00
Subcontractor Costs
Subcontractor Scope Invoice(s) Quantity Price Amount
CSI Cost increase 100 $91.06 $9,106.00
$0.00
$0.00
$0.00
REED c ry Subcontractor Total $9,106.00
Cost Summary
TRUCKING 6 EXCAVATING Total Labor $ -
*. . .i.Civil c....,l..ur.wag
31% Labor Mark-up $ -
Total Equipment $0.00
Date: 21% Equipment Mark-up $0.00
Total Materials $0.00
21% Material Mark-up $0.00
Contractor Foreman /Superintendent Total Subcontractors $9,106.00
12% Sub Markup up to$25K $1,092.72
10% Sub Markup$25K-$100K $0.00
Date: 7% Sub Mark-up Over$100K $0.00
Subtotal $ 10,198.72
This equates to $
Engineer $101.99/CY, the unit TOTAL - 10,198.72
price was negotiated
down to $84.29/CY
I
INVOICE
400 Valley Ave NE
ihTigi
Puyallup,WA 98372-2516 riiii INER N'0 w; „t DATE 4,l INVOICE NOr .A 3INGEr1
MILES 253-833-3705 055600 02/08/2022 1914468 1
SAND&GRAVEL .
TYEE CONCRETE CONSTRUCTION INC
11403 58TH AVE E
PUYALLUP, WA 98373
��,/'
r
„ , aI„. : Srg;iO ..306 ER`'`'�. N1tl0t% riti* DDA S, -tl 7 .44aid .ls, W'"1,im' `i ' ?ems" 4+. s; Ja `�wxCY+.�}zyi1F i`
DATE t. t "a hu PRiCE T/QUC t OT1tL
r H o TI oi.000 ' to 'rf 1? U 0M ot! vAi QCRI4 C �A etc 3 a fA a . ::.
00023 ! NE 16TH & JEFFERSON AVE E RENTON
PO NUMB.`R: JEFFERSON ST
02/08 202-270 95 10 .25 CY 0442A 115 . 000 117 . 88 1296 .63
02/08 202-270 95 10 .25 CY WI► •- - PERFORMANCE (NOV 4 . 000 4 . 10 45 . 10
02/08 202-2703 • - 10 .25 'UT OF AREA CHARGE 46 . 000 47. 15 518 . 65
02/08 202-270395 . 00 LD FUEL SURCHARGE-READY MI 15 . 000 1 . 50 16 .50
02/08 202-270395 10.25 CY ENVIRONMENTAL COMPLIANC 5 . 000 5 . 13 56 .38
02/08 202-270402 11. 00 CY 0442A 115 . 000 126 . 50 1391 . 50
02/08 202-270402 11. 00 CY WINTER PERFORMANCE (NOV 4 . 000 4 .40 48 .40
02/08 202-270402 11. 00 CY OUT OF AREA CHARGE 46 . 000 50. 60 556 . 60
02/08 202-270402 1. 00 LD FUEL SURCHARGE-READY MI 15 . 000 1. 50 16 . 50
02/08 202-270402 11. 00 CY ENVIRONMENTAL COMPLIANC 5 . 000 5 . 50 60 . 50
02/08 202-270409 10 . 75 CY 0442A 115 . 000 123 . 63 1359 . 88
02/08 202-270409 10 . 75 CY WINTER PERFORMANCE (NOV 4 . 000 4 . 30 47 . 30
02/08 202-270409 10 . 75 CY OUT OF AREA CHARGE 46 . 000 49 .45 543 . 95
02/08 202-270409 1. 00 LD FUEL SURCHARGE-READY MI 15 . 000 1. 50 16 . 50
02/08 202-270409 10. 75 CY ENVIRONMENTAL COMPLIANC 5 .000 5 . 38 59 .13
02/08 202-270417 10.25 CY 0442A 115 . 000 117. 88 1296 .63
02/08 202-270417 10 .25 CY WINTER PERFORMANCE (NOV 4 . 000 4 . 10 45 . 10
02/08 202-270417 10 .25 CY OUT OF AREA CHARGE 46 . 000 47 . 15 518 . 65
02/08 202-270417 1. 00 LD FUEL SURCHARGE-READY MI 15. 000 1 . 50 16 . 50
02/08 202-270417 10 .25 CY ENVIRONMENTAL COMPLIANC 5 . 000 5 . 13 56 . 38
JOB TOTAL LINE 7966 . 78
PRODUCT RECAP
42 .25 0442A 0442A
42 . 25 5350 WINTER PERFORMANCE (NOV-MAR)
42 .25 5040 OUT OF AREA CHARGE
4 . 00 5401 FUEL SURCHARGE-READY MIX
42 .25 5300 ENVIRONMENTAL COMPLIANCE - RM
i '--)CI VO4 71r. ; Zry,ZS y -, 12'8. - c, rr)iteS
\ \3.30 celL.( f3cL
05TX y I/Kr44$2. *7 5• 2-- lic•
AMOUNT DUE ► 7966 . 78
Remit Payment to 400 Valley Avenue NE, Puyallup, WA 98372-2516
Miles Sand & Gravel Company
WWW.MILES.ROCKS
RL'Il
AL f 3 k, 9
0
CONCRETE&MATERIALS
Dispatch: 253.891.6680 P.O. Box 487 Sumner, WA 98390
QUOTE ID CUSTOMER NAME CUSTOMER CONTACT INFO
6627 CONCRETE SERVICES INC
PROJECT NAME PROJECT ADDRESS
DUVALL AVE IMPROVEMENTS DUVALL AVE Er NE 12TH RENTON
*ALL MIXES ARE SUBJECT TO A$6.00 PER YARD ENVIRONMENTAL CHARGE
PRODhICT ; DESCRIPTION "BEST PRICE APPLICATIONa ,'
C1601ACB CLASS 3000 SLIPFORM CURB $97.00/CY3000 MACHINE CURB
C1601A COMMERCIAL CLASS 3000 W/AIR 3000 HAND CURB/WALKS
C4000A COMMERCIAL CLASS 4000 W/ R $98.00/CY CLASS 4000 W/AIR
ADDITIONALFEES
--..
11000330 READYMIX ENVIRONMENTA $5.00/C / PER YARD
CHARGE
NOTES sK;y A z.4 to
PW-YES = /rv3
l TY //c1? O w
TERMS4b •
CO,1�1 1 t f, r '�' ` � N : ;*. x;,
�"jj�MS1 7 aa`ii �' 4 d t o 1�'' 4 AA,.✓a�& a sya�� 4 :" 1�
1 t»Eg,{IMr YAbe sUbstltUtGd prRl �r'77+rash - L�4"1.A. '''.••fn vr� e: t, 6f�� )4. t
2 IASI h dl ja .1 al 0r0.0,0.c:c11iAi,0 ' 7, � x,b "r -,.' �r a+ k li
3 rgesf of I W r<tEd'uersai Ube Subject to I.,5?�interest r rnonth,o talt unpatdrbalanc,s;,A}o+��� : ' t.#a
4 QUbtedtPiice ptl g�K-pc pits,$ I,e ted A t�adciitiorai products purchased otp,4%etl(K41dde(i ,ft�kbei } ryed at prices ins effect at tyre tine of,purchase;!' -
5 0lfs4Si a gbtffett�ofr,i ii i 4 ttr0Oaleti Tax unless aempttg, ara app leab ,��Pgeih 1 oesrt• a sales q others ltcable taxes
6 t„041:t'FT, It k, d l o" i i t t r, v r:, pp
y 9� nt Y f Rts mire th n.T rn;nutes ertcub(c yardl �llQlle"t (t�edr�tlpotb tlJtea ales.
7 r9,I40110 0, l$d gpplled asrfolloWs.<A-'C/Y $300 00 4 70*,4%$ i++N$ j O I 4s t Kx k,'
4 �H lit V,W^,�"+(P 9�' f �'1� �SJ 9 �a(�y+t
tit; t:es g�u"rot Wf�Je * e/I " 0 a through r,lday between 004404 `t P` k r 0 ` '
,,t,:„,
x, r leix 11- �R ,0 .aQ l pE41 a gey0eor dQ:FM
91y 0.nsu e`fhpmel"�rdeti�e f� nerete all f,nrn orders Lust aeconflrmedtw� 0 laeonc e dl's a,tch t�h 4B�b� s'�nohce Lessa ran�24-nours.ts s iti ect
tox Ilaotfe�et',rr� ,n 1
10:r., " delrve t`,500,0ttl> S• � erj ont^,is quote as,.ve!)as the extension �aty amount of credit by Co liss Resources Inc is'subject to and contingent
sUPonte �14ro grvc110h,amouorn�ajterms',as vie“as s isronier I rtu uledge lit. a°t4t ley aretir compllance with all Washington State laws and4
0 $>@ontrac tor. f T,, i �P. t `u,r'+' :,,. • fr
•P1�''C6Rtraet jo,notify Cor iss Resources 1nc.of Prevailing Wage Requirement;tiniest stated orrces,do tp mctude Prevar log Wage or Davis Haconr r '
112n. .ii414e fe l+surchargeaubject to change without notice.
13 Coniraetat;to'-provide or[-alto washout area or cco-pan,unless other arrangements are made nor to Job corn ncncinq
14 Unless bherwrse stated prices,are valid for 30 days from the date listed on signature line
15 Does no include any add tional.necessary hgating or cooling of ready mix concrete,untourttes previously arranged.
16 Ceontrabtorgesponstble ror presiding safiviii ss,,0440ess,on Job l*Ahd!W}ila€be responsible for towIna bill if necessary
17lt eItss,ResOj Itac reserves the rigtiMtot"¢iSargeii,a*trfee for credit cat Kt`t'ter ts.
laj del{tser,1`jjgteptdtsposingco;ail+ "�,��S with Corliss Pesources Irr,irheit9'Ur'ittomer specified to this quote•acknowledges weOriffofrand eq_es to be bot7nthby thetefppsTand condtkiflopi�li'.t-dfitg all representations and'warranties.ihe'reurtder)the Cleah Soil Acceptance Ag ee Ylentapcovldeci todhe.customer,which is alao•available`at'the'following address:httus,//corllssco:com/soil/: .
Expires 12/31/2021
Steve Valenta 253-405-0165 6/22/2021
stevevOiCortissCo.com Date Authorized Customer Representative Date
Sales Representative
Must be returned signed and dated not later than seven(7)business days from date recorded by Corliss Resources,Inc.Sates
Representative.If returned later than seven days,Corliss has the right to reprice the Quoted Price.Customer agrees to all terms and
conditions as outlined above.
L:U(:U. tO"CI IVCIUF.JC IU.LC(JOCJ 1-4 I UIi +DOD-MU/M-DLDMI..I r ILL/CO
CAG-20-065, CO #8-22
Change Order No. 8
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
® Ordered by Engineer
❑ Proposed by the Contractor(VECP)
❑ Unilateral
Amount Working Days
-Origfl1 ltbntract: _ , 260
$5,218,171.95
Current Contract: $5,290,225.95 262
Net Change This Order: $18,000.00 0
New Contract: $5,308,225.95 262
Prepared By: Is a By:
3-1 V-ZZ Dfiv>rflsti 4/l0 2
4ent inee Date ngineer (city of t Transportation D e
Design Manager)
Reviewed By: Consent By:
3/17/2022 N/A
Engineer of Record Date Surety(Gres %cost and/or 20% Date
cease)
Reviewed By: Endorsed By:
3/18/2022 c)- 3-
of Renton Project Manager Date Contractor Date
Reviewed By: ,—DocuSigned by:
Approved by Cheryl Beyer via 3/22/2022 email Martin Pastucha 4/11/2022 I 7:44 PM PE
'"-8B8131F098B449D...
City Attorney Date City of Renton Public Works Date
Administrator/Mayor
Change Order No. 8
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 1 of 4
UOLu.DIyII CI IvCIOpC IL#.GC I OOCJ I-4 I OL.-4DO0-MO I M-OLDl L.I r ILUCO
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
• Add the following unit price item to the contract:
o Unit Price Item No. 8-A104 CEMENT CONCRETE PRICE ADJUSTMENT FOR WORK
ZONES A AND C,
Quantity = 213.55 CY, Unit Price = $84.29 per cubic yard.
Provide a cement concrete price adjustment of$75.26/CY plus a 12% increase
per Section 1-09.6 item 6 for a Contractor's markup on a Subcontractor's cement
concrete work in Work Zones A and C. The cement concrete price adjustment
for these work zones will be removed when concrete strike issues are over.
Add the followingSpecial-Provision-s-to the contract:
6-02.4 Measurement
(*****)
This Section is supplemented with the following:
Measurement for CEMENT CONCRETE PRICE ADJUSTMENT FOR WORK ZONES A AND C
will be by the cubic yard to the neat lines of the Structures in Work Zones A and C, as
shown on the plans.
6-02.5 Payment
This Section is supplemented with the following:
"CEMENT CONCRETE PRICE ADJUSTMENT FOR WORK ZONES A AND C", per cubic yard.
All cement concrete in Work Zone A and Work Zone C will be paid at the various lump
sum and unit Contract prices per unit as shown in the Proposal —Schedule of Prices. In
addition, all costs in connection with furnishing the cement concrete in Work Zone A
and Work Zone C, during the cement concrete worker's strike, shall be included in the
unit Contract price for "CEMENT CONCRETE PRICE ADJUSTMENT FOR WORK ZONES A
AND C". The price adjustment shall be terminated upon resolution of the cement
concrete worker's strike.
Change Order No. 8
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 2 of 4
LluLuoIy11,CI IveIupe IL,.LC/OOC)I-L I OL-'4CO0.11V/M-DLOMI.I r I LUCID
Reason for Change:
The price to furnish cement concrete,for Work Zones A and C, is escalated due to the cement
concrete worker's strike.
Materials:
No changes.
Plans:
No changes to the Plans.
Adjustment:
This Change Order includes.changes as defined in 1-04.4. Specifically,the altering of
Special-Provisions. pec`ificaliy,the altering of Special.Provisions to include a price
adjustment. The adjustment shall be made with the unit price forthe new unit price
item for 8 A104 CEMENT CONCRETE PRICE ADJUSTMENT FOR WORK ZONES A AND C.
The estimated cumulative cost of these changes is$18,000.
The equitable adjustment determination is attached.
Extension of Time:
The Time for Completion is extended 0 Working Days.
Equitable Adjustment:
This Change Order does not include an.equitable adjustment, per Section 1-09.4 of the
2021 WSDOT/APWA Standard Specifications.
Payment will be measured and paid under the Unit Price Item No.8-A104 CEMENT
CONCRETE PRICE ADJUSTMENT FOR WORK ZONES A AND C, Estimated Quantity=
213.55 Cubic Yard, Unit Price=$84.29 per Cubic Yard.
The attached Equitable Adjustment Cost table lists the unit contract item that is added
due to this change. The unit contract item quantity is an estimate;the Contractor will
be paid based on the actual quantities installed.
Change Order No. 8
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 3 of 4
UVI:uOlyII CI IVCIVpc IL/.LC/JOCJ 1-4 I OI..-4DOD-11V/11-DLDl-w..I r ILVCO t+. . .t.
Sections 1-04.4 and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern
this Change Order.The Work of the referenced Contract is modified to include the changes
detailed herein.The payment provided for herein shall constitute the complete and final
settlement for all costs of labor,equipment, materials,overhead, profit,permit fees,and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
❑ Plans
® Equitable Adjustment Determination
Change Order No. 8
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 4 of 4
VVUUJII'/I.GI ivCIUpC ILJ.LC/UOCJ I-L IUL *DUD-MU/M-DLDNL,Ir I LUCO
Equitable Adjustment Determination - CO No 8
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:3/14/22
New Contract Item Cost
New
Contract Estimated
Item No. Description Quantity Unit Unit Price Total
8-A104 Cement Concrete Price Adjustment for Work Zones A and C 213.55 CY $84.29 $18,000
ESTIMATED CHANGE ORDER COST ( $18,000