HomeMy WebLinkAboutCAG-20-065 - Duvall - Change Order 9 4
Change Order No. 09
44e%
Backup
Documentation
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating, Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
Attachments:
Backup Documentation
• Field Directive
® Equitable Adjustment Determination
• Determination of Additional Working Days
® Engineer's Estimate of Change Order Cost
® Engineer's Calculation of Additional Working Days
® Contractor's Quote
111 Project Labor List
El Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement
❑ Summary of invoices for rented equipment
❑ Summary of invoices for materials
Change Order No. 09 Sidewalk-Wall Footing
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 1 of 1
Equitable Adjustment Determination - CO No 9
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:3/16/22
New Contract Item Cost
New
Contract Quantity
Item No. Description Change Unit Unit Price Total
9-A105 Sidewalk-Wall Footing 1,455 LF $15.41 $22,421.55
New Contract Item Cost $22,421.55
ESTIMATED CHANGE ORDER COST I $22,421.55
Narrative:
The Contractor met with the City and CM team on 3/10/22 and related difficulties in getting a
concrete subcontractor under contract for the reinforced cement concrete walls because a por-
tion of the wall footing rebar extends into the sidewalk payment limits.
On 3/14/22, the Contractor sent a proposal to the City for $22,428.00 to pay the sidewalk sub-
contractor to also construct the rebar and a portion of the adjoining wall footing for wall typical
sections A and B as shown on the plans sheet WD1. The Contractor states that his wall bid
item unit price did not include this work.
The engineer's estimate for the length of walls that have the integral sidewalk and wall footing
(sections A and B as shown on the plan sheet WD1) is estimated to be 1,455 LF
The City reviewed the proposal. The unit price bid by the Contractor even with this increase is
well below other bids received for the work. An equitable adjustment of$15.41/LF as measured
along the back of sidewalk with the adjoining wall was agreed to for an estimated total of
$22,421.55.
Determination of Aaaitional Working Days
A determination of zero additional working days was made.
Engineer's Estimate of Chz ! Order Cost
City of Renton-Duvall Ave NE,CAG 20-065
Engineer's Estimate
Date:3/16/22
Qty Estimated
Item No. Description Change Unit Price Amount
A42 Conc.Class 4000 for Retaining Wall 3A 0 SY $200.00 $0.00
A82 Cement Conc.Sidewalk 0 SY $60.00 $0.00
C09-A105 Sidewalk-Wall Footing 1455 LF $15.41 $22,421.55
Total $22,421.55
Conc.Class 4000 for Retaining Wall with Exposed Exposed
Sidewalk Footing Limits from RD Sheets(FT)see Avg Height Area of Sidewalk Exposed Area Area of Wall
Plan Sheet construction note 10 (FT) Wall(SY) Width(FT) of SW(SY) plus SW(SY)
RD1 0 0 0 0.00 0.00
RD2 31 1 3.44 6.00 20.67 24.11
RD3 35 1 3.89 6.00 23.33 27.22
35 1.5 5.83 6.00 23.33 29.17
40 2 8.89 6.00 26.67 35.56
45 3 15.00 6.00 30.00 45.00
135 1.5 22.50 6.00 90.00 112.50,
40 1 4.44 6.00, 26.67 31.11
80 1 8.89 6.00 53.33 62.22
RD4 80 1 8.89, 6.00 53.33 62.22
80 1 8.89 6.00 53.33 62.22
RD5 210 1 23.33 6.00 140.00 163.33
10 1 1.11 5.00 5.56 6.67
51 1.5 8.50 5.00 28.33 36.83
RD6 0 0.00 5.00 0.00 0.00
RD7 276 1 30.67 5.00 153.33 184.00
100 4 44.44 5.00 55.56 100.00
27 1 3.00 5.00 15.00 18.00
67 1 7.44 5.00 37.22 44.67
RD8 78 1 8.67 5.00 43.33 52.00
27 2 6.00 5.00 15.00 21.00
8 1.5 1.33 5.00 4.44 5.78,
RD9 0 0.00 5.00 0.00 0.00
RD10 0.00 5.00 0.00 0.00
Total 41. 225 898 1123.61
Reduction in BI A82= -898 SY
Exposed Exposed
Conc.Class 4000 for Retaining Wall 3A Limits Avg Height Area of Area of SW
Plan Sheet from RD Sheets(FT)see construction note 16 (FT) Wall(SY) (SY)
RD7 2 6.71 20.13 15
RD8 33 2 7.33 18.33
Total 33
eduction in BI A42= -217 SY
back check original BI A42 quantity= 259 SY OK
1,455 LF of wall per
typical detail A and B
on sheet WD 1, that
is adjacent to back of
sidewalk @ $15.41/
LF = $22,421.55
Engineer's Calculatio. . ,.f Additional Working Days
No new work is added so a determination of zero working days has been made.
Contractor's Quote
REEDS Change Order Proposal #12 2207 Inter Ave,Ste.A
Puyallup,WA 98372
TRUCKING&EXCAVA77NG Office:(253)841-4837
�...,.u. c...e.. .» w� Fax:(253)841-4816
GC/Owner: City of Renton JSS#: 12
Reed Job No: 156 Project: Duvall Ave NE Date: 3/14/2022
Description: Increase to add foundation and rebar to walk with adjoining wall
Subcontractor: Concrete Services,Inc.
Labor Costs
Regular Overtime Amount
Craft Employee Name Hours Rate Hrs Rate* Regular Overtime
$ - $ - S - 5
$ - $ - $ - $
$ - $ - $ - $
S - 5 - $ - $ -
5 - $ - S - S
S $ - $ - $ -
5 - $ - S - $
$ - $ - S - $
*Including Fringe Benef Labor Subtotal $ - $ -
Labor Total $ -
Equipment Costs
Equip. Regular Standby Amount
# Equipment Hrs Rate Hrs Rate* Regular Standby
$ - $ - $ - 5
$ - $ - $ - $ -
S - $ - $ - $ -
$ - $ - $ - $
S - $ $ - S
$ - $ - $ - $
$ - $ - $ - $
$ - $ - $ - 5 -
Equipment Subtotals $ - $
Equipment Total $0.00
Material Costs
Supplier Material Invoice(s) Quantity Price Amount
$0.00
$0.00
$0.00
$0.00
Materials Total $0.00
Subcontractor Costs
Subcontractor Scope Invoice(s) Quantity Price Amount
Concrete Service Concrete Increase-per SY for Bid Items#A82 900 $22.25 $20,025.00
$0.00
$0.00
$0.00
REED c ry Subcontractor Total $20,025.00
Cost Summary
TRUCKING 6 EXCAVAnP Total Labor $ -
o..«...,.0.1 c....... *.1 w a
31% Labor Mark-up $ -
Total Equipment $0.00
Date: 21% Equipment Mark-up $0.00
Total Materials $0.00,
21% Material Mark-up $0.00
Contractor Foreman /Superintendent Total Subcontractors $20,025.00
12% Sub Markup up to$25K $2,403.00
10% Sub Markup$25K-$100K $0.00
Date: 7% Sub Mark-up Over$100K $000
Subtotal $ 22,428.00
$
Engineer TOTAL $ 22,428.00
RWVUO 4 CI iveiviJe Iu.DC I L' l rG-uuul,-4l,Al,M-0I,uJ-4VUCOM4VD I UI
CAG-20-065, CO 9-22
Change Order No. 9
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
® Ordered by Engineer
❑ Proposed by the Contractor (VECP)
❑ Unilateral
Amount Working Days _
Original Contract: 260
$5,218,171.95
Current Contract: $5,308,225.95 262
Net Change This Order: $22,421.55 0
New Contract: $5,330,647.50 262
Prepared By: Iss y:
MO — 3-13'ZZ 11442
e•,den . MEW Date Engineer(city of Renton ransponatlon Date
Design Manager)
Reviewed By: Consent By:
--k'\ e"'" 3/21/22 N 1 A
Engineer of Record Date Surety( an 25%cost and/or 20% Date
t' crease)
Reviewed By: Endorsed By: .�
e / 3/21/2022tab - -� t 3 -lam Oa
f Renton Project Manager Date Contractor Date
Reviewed By: r—DocuSigned by:
Approved by Cheryl Beyer via 3/11/2022 email Martin Pastucha 4/11/2022 1 7:43 PM F
- --- ------ 1/4-8B8131FD98B449D...
City Attorney Date City of Renton Public Works Date
Administrator/Mayor
Change Order No. 9
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 1 of 4
uul.u01y !CI IVCIUpa IL).DC I UL/rL-uUul,-,+LA. i-OI,uJ-4UUCOl-WLID/JI
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
• Add the following unit price item to the contract:
o Unit Price Item No. 9-A105 SIDEWALK-WALL FOOTING
Quantity= 1,455 LF, Unit Price =$15.41 per linear foot.
This new contract item provides for construction of the wall footings for Typical
Sections A and B as shown on plan sheet WD1,to be constructed as part of the
sidewalk construction.
Add the following Special Provisions to the contract:
6-11.4 Measurement
(*****)
This Section is supplemented with the following:
Measurement for SIDEWALK-WALL FOOTING will be by the linear foot along the back of
sidewalk that is directly adjacent to wall sections A and B as shown on plan sheet WD1
and as further shown on the plans or directed in the field by the Engineer.
6-11.5 Payment
(*****)
This Section is supplemented with the following:
"SIDEWALK-WALL FOOTING", per linear foot.
All costs in connection with furnishing and installing that portion of the retaining wall,
reinforcement and footing as show in sections A and B on sheet WD1, that is located
below the optional horizontal construction joint,together with the rebar in the sidewalk
and rebar extending from the sidewalk vertically as shown on wall sections A and B,
furnishing and installing Class 4000 concrete, casting, curing, protecting, premolded
joint filler, excavation, foundation preparation, form liners, footing drains and all work
described in Section 6-11 of the Contract Provisions shall be included in the unit
Contract price per linear foot for "Sidewalk-Wall Footing".
Change Order No. 9
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 2 of 4
i'Vl:UOitpl CI IVCIVpe IU.DC I UL/I L-UVUV-4l'l+M-OIJ1-00-4VOCOMYVD I J/
Payment for BI A42 "Conc. Class 4000 for Retaining Wall 3A" per square yard shall
include all costs in connection with furnishing and installing Class 4000 concrete for the
retaining walls and footings for all walls shown on the plans, excavation, foundation
preparation, forms, form liners, furnishing and placing concrete, rebar, casting curing,
protecting, surface finish,joints, weep holes, premolded joint material, footing drains,
pigmented sealer, anti-graffiti coating, fall protection and/or fencing including anchors,
barricades, end sections, protecting the work from damage until accepted by the
Contract Agency and all Work described in Section 6-11 of the Contract Provisions
needed for a complete wall with chain link fence, except for the work to be paid
separately in the unit contract item "Sidewalk-Wall Footing".
Reason for Change:
The work required for some of the retaining wall footings extends into the payment limits for
the sidewalk. This caused confusion for the Contractor when bidding the project.
Materials:
No changes.
Plans:
No changes to the Plans.
Adjustment:
This Change Order includes changes as defined in 1-04.4. Specifically, the altering of
Special Provisions. Specifically, the altering of Special Provisions to include a unit price
contract item. The adjustment shall be made with the unit price for the new unit price
item for 9-A105 SIDEWALK-WALL FOOTING. The estimated cumulative cost of this
change is $22,421.55.
The equitable adjustment determination is attached.
Extension of Time:
The Time for Completion is extended 0 Working Days.
Change Order No. 9 _
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 3 of 4
LJUUU. IIJ.I I CI IVCIUpC IU DC I LJL r L-LJULJU-4LA,M-OL.VJ-VUUCOMVUO I"JI •
Equitable Adjustment:
This Change Order does not include an equitable adjustment, per Section 1-09.4 of the
2021 WSDOT/APWA Standard Specifications.
Payment will be measured and paid under the Unit Price Item No. 9-A105 SIDEWALK-
WALL FOOTING Estimated Quantity = 1,455 Linear Foot, Unit Price = $15.41 per Linear
Foot.
The attached Equitable Adjustment Cost table lists the unit contract item that is added
due to this change. The unit contract item quantity is an estimate;the Contractor will
be paid based on the actual quantities installed.
Sections 1-04.4 and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
E Plans
Equitable Adjustment Determination
Change Order No. 9
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 4 of 4
.4UUUJ0.�f,.I CI IVCIUpe IU.DC IUL/ /U/
Equitable Adjustment Determination - CO No 9
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:3/16/22
New Contract Item Cost
New
Contract Quantity
Item No.. Description Change Unit Unit Price Total
9-A105 Sidewalk-Wall Footing 1,455 LF $15.41 $22,421.55
New Contract Item Cost $22,421.55
ESTIMATED_CHANGE ORDER OST : $22 42155