CAG-20-065 - Duvall - Change Order 16
.11016 Change Order No. 16 Backup Documentation Contract Title: Duvall Avenue NE Contractor: Reed Trucking& Excavating, Inc. Contract No. : CAG-20-065 Federal Aid No. : N/A Attachments: Backup Documentation ® Field Directive ® Equitable Adjustment Determination ® Determination of Additional Working Days ® Engineer's Estimate of Change Order Cost © Engineer's Calculation of Additional Working Days ❑ Contractor's Quote ® Project Labor List 11 Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement • Summary of invoices for rented equipment ❑ Summary of invoices for materials Change Order No. 014 Storm Revs at MH33 and NE 12th St Contract Title: Duvall Avenue NE Contract No. CAG-20-065 Page 1 of 1 City of Renton Field Directive No: 20 ;IR Project Name: Duvall Ave NE Contractor: Reed Trucking and Excavating,Inc. Contract No: CAG-20-065 By. �"ME► Federal Aid No: N/A TIB No: N/A Date: Construction Manager: Tani Stafford 6/1/2022 The following is documentation of the oral order given by the Resident Engineer per WSDOT Std Spec 1-04.4 The Contractor is directed to do the following changed work: Remove and dispose of existing CDF on top of and around the existing water main pipe as required to confirm existing water main locations and as required for water main connections. Revise the water main connection at Sta 926+81.70 to include removal of the existing 16"x8"Tee and blocking, per plan revision 1 on sheet WA6-060122.The actual removal of the existing tee and valve will be done by City forces as part of the final connection. Note that there is a thrust block on the south side of the 16"tee near the Starbucks driveway that cannot be disturbed during the removal of the CDF until the final connection when the main line valve is shut-off at Sunset/Duvall intersection. BI B22-Water Main Conflict Resolution-new contract item to be measured and paid via force account methods. Rough Cost Estimate,WSDOT Construction Manual 1-04.4,Changes. Cost Adjustments: Approx change for BI B22-Water Main Conflict Resolution-new contract item-1 FA,cost TBD A Change Order covering this Field Directive will follow immediately. Contractor Date Equitable Adjustment Determination - CO No 16 Project Name:Duvall Avenue NE Contractor:Reed Trucking&Excavating Inc. Contract No:CAG 20-065 By: Tani Stafford Construction Manager: Tani Stafford,PE Date:6/27/22 Contract Item Cost Contract Quantity Item No. Description Change Unit Unit Price Total 16-B22 Water Main Conflict Resolution 1.0 FA $1,500.00 $1,500.00 • Contract Item Cost $1,500.00 Sales Tax @ 10.1% $151.50 ESTIMATED CHANGE ORDER COST I $1,651.50 Narrative: An equitable adjustment of +$1,651.50 including sales tax has been determined based anticipated force account work. The actual amount will be determined by force account calculations. FWD No 20 was issued on 6/1/22 directing the Contractor to perform additional work to include removal of an existing CDF backfill around the point of connection at the water main connection point at the north end of the project, and to make changes to the point of connection on the existing 16-inch diameter water main. The Engineer's Estimate for FWD No 20 is +$1,500, not including sales tax. _ y Determination of Ad zonal Working Days A determination of zero additional working days was made. a Engineer's Estima ', City of Renton Duvall Avenue NE G&O 20593 Engineer's Estimate FWD No 20 Description: FWD No 20-Water Main Connection and FA work for CDF removals-assume 3 hours Dates: TBD Prime Contractor Labor: (Reed) Hours Rate Total Foreman 3 $86.42 $259.26 Operator 3 $84.38 $253.14 Laborer 3 $61.59 $184.77 Labor Cost $697.17 Markup (31%) $216.12 Subtotal Labor Cost $913.29 Prime Contractor Equipment: Hours Reg Rate Total Ford F450 FT03 3 $53.55 $160.65 Komatsu PC88 EX04 3 $90.70 $272.10 Equipment Cost $432.75 Markup(21%) $90.88 Subtotal Equipment Cost $523.63 Subcontractor Service Unit Unit Price Total Service Cost $0.00 Markup(12%) $0.00 Subtotal Service Cost $0.00 Total Estimated Cost, Rounded: $1,500.00 Engineer's Calculation ,f Additional Working Days The changed work will not result in a reduction or addition of working days. The net added work included removal of cdf encasement and is estimated to take less than a half day of work. ..• , . DocuSign Envelope ID:19EA56FC-3219-4979-S" ',0B4A572DDF5 ! i . . CAG-20-065, CO#16-22 -.. BEIR ‘ ..lsrilD . Change order'Nz 161 ,,......,........-- . toritract;Title:-, Duvall Avenue:4E' Contractor' Reed Trucking ipdtxcaavting-,Inc; _............. .._ ... _ ...,... . - ..... . _. .. ..,.._ ... .... ......... . __,. .. - • ---- -. - -. __ • • .. _,. _____,.__ . . ..._ ____ _.... Contract No;',:. _t:Aq2a ___ .. :004, _ _. _ , __... .: _i-,,. _ ,_ . - - Federal Attixo.::. . .. _ , ... Ordered by Engineer tgi: Force Account CI: NVP.c1.4..0*.the-.00.0401.'(VUP). a OW kgfri., ,Cl 00.11.0014. La: Ltimititirr. , „ ., . . .... ., _. .... ! i Amount W,oiltitpoys. coginacoritract:, . ..., :$3.)12A1,171-...§$ f .:./Pre. . ._ . Current tOiitii4i - -- - .$:5ii8i.. $1,-j$ : .262 ‘ : Estimated Net Change This arder,;..; _ :ii,"$:1-;651;5.0. _ i .0':. ' , i_NOtTsCpntrAct: _._ lss. -"i',•!•14.: . ..-. .. -....--'711-: 7:-..:"i'.l4'. 71 / i100itEngineer Date rgiteerAcitotietoiTrarspatgia Date. i-.:'2:... :.i IfiesignManagef.)! . . • RitireAiliedali: 'tonsent. 70/2'.2, .... g..e.igreleot:4f.R4:04 - . - . - .-6.-..t.4 $U1101101: ":' .., ReilleViett O.": . tildorsedly; fe:„.....-- 7/26%2022 - --- - ' .' --- - - - 5C)t.'1,•;-1: —.-- - --- ' . ,..f.,,..z...,. Ci i p enton Peoject•M'anagef 'riat.4 .Ctititiaatii,' Date -- R.dideiniett.B9:: . Om:Signed by: Approved by Cheryl Beyer via 7/20/2022 email Martin Pastucha 7/27/2022 I 5:16 'PM PDT - - ' 8B8131FD9813449p... . - . 1_ - OW-At:to-Po Date City of Refiteirf,Ribljtr,vork , )06 Mmirpt9r,/MPS:or . ..._ _. ... . . . diaZige-Ciiiit;go:: 16.. qtr.q.44Tift.: Duvall Ave NE, • • • ..•tpniraeata.- .t:A, :1040; . - Pange J.tif3'• . . • DocuSign Envelope ID:19EA56FC-32194979-1 `,A0B4A572DDF5 THE CONTRACT i$,MODiFiEbM,FoLLOW& D6Crititiontif'Change: As reddired fri FlAID,NO 20—The Cotterorilditetted to'do the;;IcilldWingrehanged work: RernoVe anti tlispOSeofeXiSting CDF":-OntOb:Of and a 60nd thekiSting Water- min pipe as required to:.confirm existing water-maMikafiOn5erKI as required forWaterfnain dohnettiOns: • Reviserthe-water main connection at Sta.020+400 tolholude removal of the eAstingil6N8"Tee and blbekihg,,Oer plan revision 1 on she-et WA0-:060122:The at tot removal Ofthee5,4Stinnea and Valv-evili O-e.4000 bs•KCity fo-reeS-iaSfiart:cif theling,connection. • There:Is-A:thrust block.on the south side of theU'itee near the 4tarbigkS drivewaythat cannot be disturbed during the removal of the(Orpritil!thefinat OnnettiOn when the Mein line Valve iS,Shitt-OffetSUnSet/DbVall intersection. The 4uantity fOr then&•contractitem 16-822—Water Main torifliettResolkition will be measured.byforce a(count Meth.O.dS and lSeStithated to be$1,500.00 The additional Wifirk Will be:Oaid,Via the folldWing hew.Contract ltéñ,aS determined by -force account methods; o Bid Item NO,16-1322—WATER MAIN CONFLICT RESQLOTION.=.:1,FA, Estimated Quantity Is$1,500.00bluS 10.1%:SaleS-Tak", Reason forthafige: There were existing: backfill surroundingrthe existing water main at the.connection point The cbilneetion pOintwas shifted northtlightly to allow forthe removal of an existing 1.6"x8"Tee that IS 0001004ed:. Affeett:DBE Work: 0 Yes E4 No No 00.'00s td OBE Work. Materialai. No changes. Changeflrder No. 16; Contract Duvall Ave N E Contract No CAG 207005' Page :4tif 3 DocuSign Envelope ID:19EA56FC-3219-4979-B 7,0B4A572DPF5 Plans: Plan Sheet WA6-060122 Equitable Adjustment: This work is an unforeseen change and therefore the Change Order does include an equitable adjustment per Section 1-09.4 of the 2021 WSDOT/APWA Standard Specifications.See attached. Extension of Time: The Time for Completion is extended 0 Working Days. Sections 1-04.4 and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern this Change Order.The Work of the referenced Contract is modified to include the changes detailed herein.The payment provided for herein shall constitute the complete and final settlement for all costs of labor,equipment,materials,°overhead, profit, permit fees,and all other claims that may be made by the Contractor as a result of this change. To be attached to Change Order: Z Plans Change Order No. 16 Contract Title: Duvall Ave NE Contract No.. CAG 20-065 Page 3 of 3 • 6'0. DOCPS ig n Envelope ID:19EA56FC-3215-4979-E .40,134A572DDF5 . . Equitable - . • _ . Adhigthielit Dëtérnijnatibñ-CO'NO.10 Fi.rojetihamezii.uvairAvenueAi CO-ktraktoilli0:4 Te);(010g-'4.E3A01410t1c, tooe. -d tantStattord Construction Manager Taiii•staffOr4,,Pg: Data:027/22. COrittactlt0i* pat contract: Quantity kern NO. . Destription Change Unit Ptiee• „ total 16-022 Wat&Maki CooflictRafolutioti 1:0 rA, $1;stiix • Cb-eitra0 iterii.rcist Salps:.Thit 010;i6A ftITCVIATEDICHAINGE(000(00SIT,:24 : '..4:11aWttit,t): • 0 0 0 CO rn - CD 0 0. :CD ia •1 _________ _ - 1. ii-ii•*kill-,A -„,..s. -0,614,4-07.! _._ ...e..c.i.. .WW1!. .1 k / •/ =VII°35PLAIr' "!' 12 . r'ocru tow.mu= "..,... M Mita .. '' Ill 3V1010*(YE0)1,i474 ...----- rN: 7 -., • - MeV, \ . . . 'firi4sigi.ciiciaA . T. rAtiPitc on Exsiy,,Grass '1-10 . - \ . - „.„.....-----. 14.1,..1.7.tittur"Ai'' 1.4:9ta...?,!,- --,.....,., . 1 .43 n) InOsTiG*0:2'40.0.tal.• \ \ :. ililrio2;sixEyEgtuAiNA. ..... I , =wpm imranaimfrui. imicai ici ,. . cf, (1)16•457116316046111 constarwkrui. '",,,, . , . 10 e-tr silitmi.iii) N to Ow-mum int ..:).- .1/ iiItel-amastMtPAlluo" co ,--i _ , . • , ant.Dioa _--. / 93 r.upty . .4v4vvo t 1 '•,, oorAvochtle,may; N.. '. mum.ok r I r ,I, `, paninorigmotww, il ):04.11.CCK" . . ._ - ---, 1 :. 11 5 co- tl 1 casree301,C WO LUJI 100c 'a 4— ,› - MoSillaae(XIS 70 WW1 Cii gptene,vALvgnoTu, V n) g 0 icoi*Ecn*Artikaik_ 0)#,TikdnottiTfriAeiiiiiia: ii)-iiriiiiiikiiiii ii4:54.iii, 'm r DETAIL- f"-,N. , ',DETAIL ?I...A DETAIL _ , 1 40 50LE. DM W.•"‘ Mc),St!'LE -V-5' 4.. 14,4140364%1041i-W6e. / 43,10,...........srmprcnotant-... .. -- . - ..'1..'n / Atswi.r.war croacartgr.w.ru, - . - . , REMOVE EXISTING 1,2)(8"TEE AND:8"VLAYE AND, / , - - COAINEOT TT,GEXIS.TIM 1_6`7NPIPE.WIT10'.$1:1.EVE(Rj)' E , #:. ,it 4111TOSt / - ... .. Rein oval of the watlhy tee and valywIll beAone-by,tIty feirces a's,Part - - of the..A , .. . .. . . . .. • - ' . . - _ ; ? . . . aiiiiiiii.- qq.10-0 INS1,14 r tAID GPM WSJ rw' " . - 1,, N 'PEW:telli4 EE,•, c i , , currp,t1c.rlirwmi, 1 .16.1100/400941eatt)CX S i "fatIVESTEaREY.1510,NS'Br CITY OF RENTON WAMFULfraltr . .. 1 Ktia-mai-huakiniOnma f, ' by ABDOUL GAFOUR..06/P1/22' 4. DasnlialitrITENirp2x.ailatavi trWATERTOTEEWITg Wanyg It4D9' il. pRolir DIVA VOW. 1., ,. :il, 'torciiicnoilATaTivi#14-0.70 A DETAIL ?Ts,. I .• HP*Az %vs V *00.:-Ol22 N. •- , h wmnq..., art OF.RENTON ouyio.tmEyc, 0.04.1.3 lIV.A6' ... ... , _. ... - ,4:61W •• ' • BID DOCUMENT rumucwoctioirassioq .50.Wp0,,n107.11. t . ' Ilk -.4) 4#0.#4. . ', Parametrbc 'SUBMITTAL ,ptwec••••mot•cr,o•• :111.101R0 tORMSTIMIXN iiiikrin 61E'ali:S. -8/Dat.O. 69P. ru. z4' „a..1: i OOP?t'la P.;WM,R MINICTION 4 IV TI.S'... :VIM'i , .\. — • 'escuiaar ci.C: .M..."*.•V.r, '61.IEETS0, ' .......I •sremarnattsunctl I ft ril mt.I•.Dili '''---"L '•.4.•F. ' .toninimioo4.44 " - iiiiividec14016gIckig pk;:ti§n**:iiir.:.r pc,.Yeit tioao.,..pittoytio64-.Agrci..e,r,Ojig.orkirei?0,41.t4iE-0!-.?aieY.,,i,g'2Y90.f.kr.,59,s;