HomeMy WebLinkAboutCAG-20-065 - Duvall - Change Order 17 Change Order No. 17 MIRBackup Documentation Contract Title: Duvall Avenue NE Contractor: Reed Trucking& Excavating, Inc. Contract No. : CAG -20-065 Federal Aid No. : N/A Attachments: Backup Documentation ® Field Directive ® Equitable Adjustment Determination ® Determination of Additional Working Days ® Engineer's Estimate of Change Order Cost ® Engineer's Calculation of Additional Working Days X Contractor's Quote El Project Labor List El Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement El Summary of invoices for rented equipment El Summary of invoices for materials Change Order No. 017 FH at NE 10th Contract Title: Duvall Avenue NE Contract No. CAG -20-065 Page 1 of 1 City of Renton Field Directive No: 21 Project Name: Duvall Ave NE Contractor: Reed Trucking and Excavating,Inc. Contract No: CAG-20-065 Federal Aid No: N/A By: W � TIB No: N/A • Date: Construction Manager: Tani Stafford 6/28/2022 The following is documentation of the oral order given by the Resident Engineer per WSDOT Std Spec 1-04.4 The Contractor is directed to do the following changed work after the abandondment of the existing King County Water District Main on NE lath Street: Construct a 10"x6"Tee and 6"gate valve on the City of Renton 10-inch diam.water main on NE 10th Street per COR Standard Plan 310.1 and construct the long fire hydrant stub with megalug restraints to the south per the attached detail. The fire hydrant to be located at approx Sta 906+12,53'LT. Remove and dispose of a section of the abandoned King County Water District water main that conflicts with the 6-inch fire hydrant stub and cap each end. Construct cement concrete wall per Drawing WD1,Section D,at back of fire hydrant to provide clearance per COR 310.1 as needed. BI B6-Furnish and Install 8-inch Cl.52 Water Main with Restrained-Joint Fittings and Polyethylene Encasement to pay for the additional 32 LF of 6-inch diameter fire hydrant stub=32 LF BI B12-Cut and Cap Existing Water Main and Abandon Existing Water Facilities=2 EA BI A25-Removing Asphalt Conc.Pavement=21.5 SY BI A42-Conc Class 4000 for Retaining Wall 3A=3.33 SY BI A105-Sidewalk-Wall Footing=5 LF BI A104-Cement Concrete Price Adjustments for Work Zones A and C=2.7 CY BI B22-New Item for Additional Contractor Survey for FH and Wall at NE 10th St=1 LS Rough Cost Estimate,WSDOT Construction Manual 1-04.4,Changes. Cost Adjustments: Approximate increase for BI B6-Furnish and Install 8-Inch Cl.52 Water Main with Restrained-Joint Fittings and Polyethylene Encasement=32 LF @$140/LF=$4,480 Approximate increase for BI B12-Cut and Cap Existing Water Main and Abandon Existing Water Facilities=2 EA @$650/EA=$1,300 Approximate increase for BI A25-Removing Asphalt Conc. Pavement=21.5 SY @$25/SY=$537.50 Approximate increase for BI A42-Conc Class 4000 for Retaining Wall 3A=3.33 SY @$200/SY=$666.00 Approximate increase for BI A104-Cement Concrete Price Adjustment for Work Zones A and C=2.7 CY @ $84.29/LF=$227.58 Approximate increase for BI A105-Sidewalk-Wall Footing=5 LF @$15.41/LF=$77.05 Now Item R77..Ariditinnal enntrartnr Sunray fnr FH and Wall at NF lnth St=1 I S Cnct TRr1 A Change Order covering this Field Directive will follow immediately. Contractor Date Equitable Adjustment Determination - CO No 17 Project Name:Duvall Avenue NE Contractor:Reed Trucking&Excavating Inc. Contract No:CAG 20-065 By: Tani Stafford Construction Manager: Tani Stafford,PE Date:7/22/22 Contract Item Cost Sch A Bid Item Quantity No. Description Change Unit Unit Price Estimated Cost A25 Removing Asphalt Conc Pavement 21.5 SY $25.00 $537.50 Estimated Bid Item Cost Sch A $537.50 Bid Item and New Contract Item Changes Sch B Bid Item Quantity No. Description Change Unit Unit Price Estimated Cost Furnish and Install 8-Inch Cl.52 Water Main with Restrained- B6 Joint Fittings and Polyethylene Encasement 32 LF • $140.00 $4,480.00 • Cut and Cap Existing Water Main and Abandon Existing Water B12 Facilities 2 EA $650.00 $1,300.00 17-BI23 Modular Block Wall and Survey for FH 1 LS $6,000.00 $6,000.00 Subtotal Costs Sch B $11,780.00 Sales tax @ 10.1% $1,189.78 Estimated Contract Item Cost Sch B $12,969.78 ESTIMATED CHANGE ORDER COST I 513,507.28 Narrative: An equitable adjustment of +$13,507.28 including sales tax has been determined based estimated quantities for unit price bid items and based on agreed upon quotes for additional work. The actual amount will be determined by quantities installed for the unit price items. FWD No 21 was issued on 6/28/22 directing the Contractor to perform additional work to include installation of the fire hydrant on the SW corner of NE 10th Street, rather than on the NW corner. The added work includes a longer fire hydrant stub, additional pavement removals, removal and capping of an existing abandoned water line, an added modular block wall and additional survey. The Engineer's Estimate for FWD No 21 is +$9,721 including sales tax, which assumed the construction of reinforced concrete walls at unit prices. It was later determined that a modular block wall would be a better choice within the tight space and it was also confirmed that removal and replacement of a fence section may be required. The•Contractor provided a quote on 7/22/22 for the revised work that increased the price to $13,507.28. This quote was reviewed and agreed to by the City. Determination of Adc anal Working Days A determination of zero additional working days was made. Engineer's Estimate Engineer's Estimate FWD No 21 Project Name:Duvall Avenue NE Contractor:Reed Trucking&Excavating Inc. Contract No:CAG 20-065 By: Tani Stafford Date:6/15/22 Bid Item Changes Sch A Bid Item Quantity No. Description Change _ Unit Unit Price Estimated Cost A25 Removing Asphalt Conc Pavement 21.5 SY $25.00 $537.50 A42 Conc.Class 4000 for Retaining Wall 3A 3.33 SY $200.00 $666.00 A104 Cement Concrete Price Adjustments for Work Zones A and C 2.7 CY $84.29 $227.58 A105 Sidewalk-Wall Footing 5 LF $15.41 $77.05 Estimated Bid Item Cost Sch A $1,508.13 Bid Item Changes Sch B Bid Item Quantity No. Description Change Unit Unit Price Estimated Cost Furnish and Install 8-Inch Cl.52 Water Main with Restrained- B6 Joint Fittings and Polyethylene Encasement 32 LF $140.00 $4,480.00 Cut and Cap Existing Water Main and Abandon Existing Water B12 Facilities 2 EA $650.00 $1,300.00 BI22 Additional Contractor Survey for FH and Wall at NE 10th St 1 LS $1,680.00 $1,680.00 Subtotal Costs Sch B $7,460.00 Sales tax @ 10.1% $753.46 Estimated Bid Item Cost Sch B $8,213.46 Total $9,721.59 Wall and Survey= $2,820.31 Engineer's Calculatior, Additional Working Days The changed work will not result in a reduction or addition of working days. The Contractor has been allowed to work expanded hours and has kept up to the original base schedule. . Contractor Quote Tani Stafford From: Dustin Wright <DWright@reedtrucking.com> Sent: Friday,July 22, 2022 11:53 AM To: 'Tani Stafford';Tiffani Barquist; Shawn Reed Cc: 'Flora Lee'; 'Cindy Clark'; 'David Roman-Sanchez' Subject: RE: Renton - CAG 20-065 draft CO 17 FH at 10th -for quote The wall I'II do for 5000.00 REEDC. TRUCKING & EXCAVATING 'EXCELLENCE IN CIVIL CONSTRUCTION SINCE t998' Dustin Wright Vice President (360) 701-0997 From:Tani Stafford [mailto:tstafford@g-o.com] Sent:Thursday,July 21, 2022 4:02 PM To: Dustin Wright<DWright@reedtrucking.com>;Tiffani Barquist<tbarquist@reedtrucking.com>; Shawn Reed <SReed@reedtrucking.com> Cc: 'Flora Lee' <flee@rentonwa.gov>; 'Cindy Clark'<cclark@parametrix.com>; 'David Roman-Sanchez'<droman- sanchez@g-o.com> Subject: Renton -CAG 20-065 draft CO 17 FH at 10th -for quote Dustin—here is a draft of CO 17 for your use in preparing a quote for the additional modular block wall and survey. The City is reviewing it as well. The City would like to use existing bid items where possible for this work, so those are shown in the draft change order and in the equitable adjustment. Several bid items have sufficient quantities that no additions are required to the Proposal Quantity,so those are shown in red on the Equitable Adjustment, and they will not appear as an "additions"on the change order. We have added some language in the change order that a road closure of NE 10th and Duvall will be allowed to expedite the work. This assumes that Reed submits a TCP with a detour and signage that would be acceptable to the City, per our last weekly meeting. Thanks Tani Tani Stafford,P.E. / 206.284.0860 office / 206-498-2888 cell /206.283.3206 fax Gray&Osborne,Inc. I 1130 Rainier Avenue South,Suite 300,Seattle, WA,98144 Alik kWAPlease consider the environment before printing this email. 1 Tani Stafford From: Tani Stafford <tstafford@g-o.com> Sent: Friday,July 22, 2022 4:10 PM To: 'Dustin Wright' Cc: 'Flora Lee'; 'David Roman-Sanchez'; 'Cindy Clark' Subject: RE: Duvall Ave - CO No 17 FH at 10th - 1 sig for Reed review and signature Attachments: CO 17 CAG 20-065 FH at 10th - 2022-07-22 - 1 sig.pdf Dustin used your earlier phone quote of$1K for surve .nd modified the change order and got the OK from the City for this amount. -- - ' •--- • - ' : -view and signature. Thanks Tani Original Message From: Dustin Wright<DWright@reedtrucking.com> Sent: Friday,July 22, 2022 2:56 PM To: 'Tani Stafford'<tstafford@g-o.com> Subject: FW: Told you to . o 1000.00 plus our markup on subs Thank you [cid:image001.jpg@01D86133.CCOA8EE0] Dustin Wright Vice President (360) 701-0997 From:Trent Coates [mailto:trentcoates@wecoatessurveying.com] Sent: Friday,July 22, 2022 2:54 PM To: Dustin Wright<DWright@reedtrucking.com> Subject: Re: Would we be coming out to stake just that one item? If so it would be 4 hour minimum @ $250 per hour rate ($1,000). Trent Coates Project Manager W.E. Coates Surveying (253)677-3092 From: Dustin Wright<DWright@reedtrucking.com<mailto:DWright@reedtrucking.com>> Sent: Friday,July 22, 2022 11:44:47 AM To:Trent Coates<trentcoates@wecoatessurveying.com<mailto:trentcoates@wecoatessurveying.com» Subject: Trent 1 Can you give me a price to survey this on hydrant? Flange elevation to follow [cid:image001.jpg@01D86133.000A8EE0] Dustin Wright Vice President (360) 701-0997 2 DocuSign Envelope ID:F2722081-F4A1-424E-B01 7A3745E240 CAG-20-065,CO#17-22 Change Order No. 17 Contract Title: Duvall Avenue NE Contractor: Reed Trucking and Excavating,Inc. Contract No. : CAG 20-065 Federal Aid No. : N/A ® Ordered by Engineer ❑ Force Account X Proposed by the Contractor(VECP) ® Bid Item ❑ Unilateral ® Lump Sum Amount Working Days Original Contract: $5,218,171.95 260 Current Contract: $5,340,608.78 262 Estimated Net Change This Order: +$13,507.28 0 New Contract: $5,354,116.06 262 Prepared By: ;" Is By: l� ► 8-1-7Z 2_ _ Resdent,En'ineer / Date ngineer(City of enton Transportation Date ( Design Manager) Reviewed By:' Consent By: C -iiv\ —' 8/1/2022 N/A- Engineer of Record Date Suret reater than 25%cost and/or 20% Date --rime increase) Reviewed By: Endorsed By: 8/1/2022 CD-e,— L.- g - �2 f Renton Project Manager Date Contractor Date Reviewed By: 1-DocuSigned by: Approved by Cheryl Beyer via 8/11/2022 email Martin Pastucha 8/24/2022 16:38 AM PDT - -8B8131FD988449D... City Attorney Date City of Renton Public Works Date Administrator/Mayor Change Order No. 17 Contract Title: Duvall Ave NE Contract No. CAG 20-065 Page 1 of 4 DocuSign Envelope ID:F2722081-F4A1-424E-B 177A3745E240 THE CONTRACT IS MODIFIED AS FOLLOWS: Description of Change: As required in FWD No 21—The Contractor is directed to do the following changed work after the abandonment of the existing King County Water District Main on NE 10th Street: • Construct a 10"x6"Tapping Tee and 6"gate valve on the City of Renton 10-inch diam.water main on NE 10th Street per COR Standard Plan 310.1 and construct the long fire hydrant stub with Megalug restraints to the south per the attached detail and Drawing WA2-061522. The fire hydrant to be located at approximate Sta 906+12, 53' LT. • Remove and dispose of a section of the abandoned King County Water District water main that conflicts with the 6-inch fire hydrant stub and cap each end. • Construct modular block wall with compact blocks at back of fire hydrant to provide clearance per COR 310.1 and per the attached Modular Block Wall Exhibit. The quantity for BI 86- Furnish and Install 8-inch Cl. 52 Water Main with Restrained- Joint Fittings and Polyethylene Encasement(to pay for the additional 32 LF of 6-inch diameter fire hydrant stub) is estimated to increase by 32 LF. The quantity for BI B12-Cut and Cap Existing Water Main and Abandon Existing Water Facilities is estimated to increase by 2 EA. The quantity for BI A25 -Removing Asphalt Conc. Pavement is estimated to increase by 21.5 SY. Change Order No. 17 Contract Title: Duvall Ave NE Contract No. CAG 20-065 Page 2 of 4 DocuSign Envelope ID:F2722081-F4A1-424E-Bt r7A3745E240 Modify the Special Provisions as follows: 7-16.1 Measurement and Payment (*****) This section is supplemented with-the following: 7-16.1(16)'Modular Block Wall for Fire Hydrant to include Surveying There will be no specific unit of measure for the lump sum item "Modular Block Wall for Fire Hydrant to include Surveying" The-lump sum contractiprice for"Modular Block Wall and Survey for EH"shall be full pay-for all work required for the following:additional construction staking for fire hydrant, excavation,waste haul and disposal of existing soil and vegetation.required to excavate to subgrade for the fire hydrant pad and modular block wall,grading,wall foundation preparation,furnishing and installing the compact modular block retaining wall per the manufacturer's recommendations,furnishing and installing cap blocks,end blocks and connection to the existing block wall, removal and replacement of existing wood fence above the wall,crushed surfacing top course for wall foundation and backfill,for a complete modular block wall installation. The quantity for the new contract item 17-BI 823—Modular Block Wall and Survey for FH, will-be measured-by lump sum. The lump sum amount is determined to be $6,000.00 plus 10.1%sales tax. Reason for Change: There was a conflict with an existing 4-inch diameter natural gas line and the fire hydrant stub to the north. The fire hydrant will be relocated to the south to avoid the conflict. Affects DBE Work: ❑ Yes ►:f No No changes to DBE work. Change Order No. 17 Contract Title: Duvall Ave NE Contract No. CAG 20-065 Page 3 of 4 - DocuSign Envelope ID:F2722081-F4A1-424E-B1 77A3745E240 Materials: Keystone modular block, BroadStone—6"Tri-Plane ST compact block or Contracting Agency approved equal,gray finish,approximately 6-inches in height x 18-inches in width, x 12-inches in depth. Plans: • Plan Sheet WA2-061522 and Modular Block Wall Exhibit. Equitable Adjustment: This Change Order does include an equitable adjustment per Section 1-09.4 of the 2021 WSDOT/APWA Standard Specifications.See attached. Extension of Time: The Time for Completion is extended 0 Working Days. Sections 1-04.4.and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern this Change Order.The Work of the referencedContract is modified.to include the changes detailed herein.The payment provided for herein shall constitute the complete and final settlement for all costs of labor,equipment, materials,overhead, profit,permit fees,and all other claims that may be made by the Contractor as a result of this change. To be attached to Change Order: ® Plans Change Order No. 17 Contract Title_: Duvall Ave NE Contract No. CAG 20-065 Page 4 of 4 DocuSign Envelope ID:F2722081-F4A1-424E-BO '7A3745E240 Equitable Adjustment Determination -CO No 17 Project Name:Duvall Avenue NE Contractor:Reed Trucking&Excavating Inc. Contract No:CAG 20-065 By: Tani Stafford Construction Manager: Tani Stafford,PE Date:7/22/22 Contract Item Cost Sch A Bid Item Quantity No. Description Change Unit Unit Price Estimated Cost A25 Removing Asphalt Conc Pavement 21.5 SY $25.00 $537.50 Estimated Bid Item Cost Sch A $537.50 Bid Item and New Contract Item Changes Sch B Bid Item Quantity No. Description _ Change Unit Unit Price Estimated Cost Furnish and Install 8-Inch Cl.52 Water Main with Restrained- B6 Joint Fittings and Polyethylene Encasement 32 LF $140.00 $4,480.00 Cut and Cap Existing Water Main and Abandon Existing Water B12 Facilities 2 EA $650.00 $1,300.00 17-8123 Modular Block Wall and Survey for FH 1 LS $6,000.00 $6,000.00 Subtotal Costs Sch B $11,780.00 Sales tax @ 10.1% $1,189.78 Estimated Contract Item Cost Sch B $12,969.78 E5 i IMATEL1LHANGE ORDER-CO51 ( 513,507.28 DocuSign Envelope ID:F2722081-F4A1-424E-Bt 77A3745E240 0 N 5 1 INCH=5 FT. r.my4 r,----- 'VMS N r• •earoawu a Mod r cxJYdll•I ilmpg 1 . / 1 _ _1��, ,\ ,, com rt 6lotks ,mrc«..r -5 '��,( - ,� \\.n^,mar u+,.,,..�] 1/ i �. «tee• V � STA 906+11.77,52.631T 4.a •�+x-' � _ _ti Concrete Pad El•f37.W ' T-- `t 1 FM Fla nge El=437.77 �, I ,,+7,,f Modular Block Wall Exhibit- SW corner of NE 10th Street - and Duvall Ave NE DocuSign Envelope ID:F2722081-F4A1-424E-BC '7A3745E240 INSTALLATION OF LONG HYDRANT RUN(OVER 18 TO 20 FEET OR 1 FULL PIPE LENGTH)JSING • MEGAUIG RESTRAINT GLANDS AND PLAIN END D.,.PIPE-NO SHACKLE RODS REQUIRED SKETCH 8Y:A0D0Ut GAFOUR-RENTON WATER UN I TY-04/29/22 r f {MEGALLIG PETAlNE1 - T';' . l 40 ft o16"D.I �� 1 4. :�1. r I IWEPD ro cur orr FIEF +I } ( ) BELL ENO OF tilt7 I /ft T TVTON JOINT PIPE 2.6'SLEEVES WITH 0611,GALLIO RETAINER GLANDS s,c 1Yton joint pipes come in 18 ft or 20 ft length �• • - 18 Fr J( y .A ,...„.....,'me "gib I". (' Ifr iI MI" CIS 4M 'OfNs tsf t a na fa •w Ili los US 11`—/ A L 6" L V WITH MEGALLIG RESTRAINT . DocuSign Envelope ID:F2722081-F4A1-424E-BC r7A3745E240 GMEMI NOTES, . a...n w.a..n.wurr arena cowuwsPir.:wi uum.n w.`.niw r.w r:r.�:. u,vwr+ 3 .n Mt _ _ ..e el ii M • // r.a n��.•~i.y r.a p� • M• ,YNW M..W'NN....a DUY�LL AK WE NE '�M,.r...p a.4.tai.r.,o • • 4. 1 7' Ir ' _ ._ _..�--—��— z .wun�r%.ua.ww..,..r11,1, Iw / 3 ...WV al vs...,«avrr..v.....n to saramarwarom am RAMO T TA-miaow..r -I - .0 Villiffeler II/a[en. aat I. I ..,«. I run - rrr...VIT•IO .aro o.l..omwo w., ,A.w.M..,.w,fN .O.M WM I ,e.,,,.rl.u«.wu .wi►.a...m..aa..r.svrw.P.. I i OK nw ar.o..a uuslsu.a.u]w w I I r.r..l7,wy ..,W� r.. 5 QQQ I. ...I. ra M.n'��V..II AYE MUE NE ,wa , 11.? St' MC WOOS we 1yy i .u.n.w.w..irwn w'• 3 ., W.w u.nns 1rs -7 A 1. f' -- •- -- — - .•-• M hIN �r 'r .wy.a ...— CITY Of R[NTON MOM N(YE W1V _ ! ..... ... ..r ��w. CO/MOItlYO SIT a '----- ,... wAmn,w 111•MTO Imo) 'r• ..w .r.l �T"rT) .. •r r...•w...l..ice ram✓/ '.o Y411.1016