HomeMy WebLinkAboutPN_Project_Narrative_250508_v1
Project Narrative
Rolling Hills Creek Pipe Rehabilitation Project
SWP-27-4297
PROJECT OBJECTIVE
Repair 340 LF of 42” CMP and 66 LF of concrete pipe via CIPP Lining.
PROJECT BACKGROUND & DESCRIPTION
The City of Renton Surface Water Utility has identified three segments of pipe that have been damaged
or are starting to fail due to age. The Surface Water Utility has setup a CCTV review program that
videos stormwater pipes. CCTV of assets 128514, 118951, and 128467 have been reviewed for pipe
deterioration and cracking. Each of these damaged sections convey water from Rolling Hills Creek.
The Rolling Hills Creek Pipe Rehabilitation Project is a maintenance project to ensure that further
deterioration is stopped by inserting a CIPP liner into each pipe. This liner extends the life of the
existing pipe by sealing the cracks and other damages of the pipe.
FACILITY CONFIGURATION
CIPP Lining of 340 LF of 42” CMP Pipe and 66 LF of 24” Concrete Pipe adjacent Talbot Rd S.
Easements: No easement is required due to the work being entirely in the City of Renton right-of-way.
Surveying and Geotechnical Investigation: No survey was conducted. Information for design drawings
were based on City of Renton GIS data. No geotechnical report has been generated and is not required
because the project is lining existing 24” and 42” pipes and will not be impacting the soil.
Design: The City of Renton Surface Water Utility has completed the design of the project internally.
Design elements included construction plans, specifications, and engineer’s cost estimate.
Environmental Review Permits: This project requires an HPA from WA Department of Fish and Wildlife
because the pipe being repaired conveys Rolling Hills Creek. A Critical Areas Exemption permit is being
requested. Lastly, this project is categorically exempt from SEPA because this is a maintenance project
per WAC 197-11-800 (3).
Construction: There are three segments (manhole to manhole) of pipe lining. A total of 66 LF of 24”
concrete pipe and 340 LF of 42” CMP to be lined. Each segment should take approximately 1 day to
complete for a total of 3 days of lining work. The work will consist of setting up at the upstream and
downstream structure and installing the new liner. Challenges will include access to the structures and
traffic/pedestrian control.
PRELIMINARY COST ESTIMATE
Engineer’s Cost Estimate: $342,500
FUNDING SOURCE
Page 2 of 2
https://cityofrentonwa.sharepoint.com/sites/DEPT_PW_Admin/Shared Documents/Surface Water Engineering/SW CIP Projects/27-4297
Rolling Hills Creek and Rolling Hills Ave SE/080 Permitting/City/CRIT AREAS/RH Creek/27-4232 Project-Proposal-Panther Creek.doc
The Surface Water Utility has allocated funding for the design and construction of this project through
the Small Scale Stormwater Projects budget (427.475015).
PROJECT SCHEDULE
Permitting Complete by June 27, 2025
Final Design Complete by June 2, 2025
Construction July 1, 2025 - August 30, 2025
STAKEHOLDER ENGAGEMENT
Community: The Rolling Hills Creek Lining project will have limited impact to nearby
residents/community members due to project location and time required to complete project. Lining
the pipes should only take a couple days. When lining work is to be performed the City of Renton
project manager and inspector will work with the contractor to notify all residents and community
members impacted. They will also ensure the adequate access to properties are maintained.
Other Agencies: City of Renton - Maintenance, City of Renton – CED, WA Department of Fish and
Wildlife
Private Utilities: There are no anticipated impact private utilities. No excavation or underground work
will be conducted. Project is lining an already existing 42” and 24” pipe. Utility locates will be
responsibility of contractor to ensure that their method of accessing the project site and performing
lining of pipe will not impact other utilities.
STAFFING
Project Management: The project manager is Jared McDonald, Surface Water Utility.
Mapping: Based on City GIS.
Geotechnical Investigations: Not required.
Design Engineer: The design engineer is Jared McDonald from the Surface Water Utility.