HomeMy WebLinkAboutCAG-20-065 - Duvall - Change Order 31 • R - Change Order No. 31
Backup
Documentation
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating, Inc.
Contract No. : CAG -20-065
Federal Aid No. : N/A
Attachments:
Backup Documentation
r Field Directive
® Equitable Adjustment Determination
® Determination of Additional Working Days
® Engineer's Estimate of Change Order Cost
® Engineer's Calculation of Additional Working Days
❑ Contractor's Quote
❑ Project Labor List
• Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement
❑ Summary of invoices for rented equipment
❑ Summary of invoices for materials
Change Order No. 031 Restake Monument
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 1 of 1
City of Renton
Field Directive No: 34
Project Name: Duvall Ave NE
Contractor: Reed Trucking and Excavating,Inc.
Contract No: CAG-20-065 ,-
Federal Aid No: N/A By. J i
TIB No: N/A Date:
MIL....hc.H./
Construction Manager: Tani Stafford •;,111
The following is documentation of the oral order given by the Resident Engineer per WSDOT Std Spec 1-04.4
The Contractor is directed to do the following changed work:
Restake the new monument to be installed at the intersection of NE 10th Street and Duvall Avenue NE.
The revised coordinates for the monument at NE 10th Street and Duvall Avenue NE are:
Sta 906+30.2, 1.0'LT
Northing: 184946.7041
Easting: 1313335.3242
BI A119 Restake Monument-1 LS
Cost Adjustments:
Additional cost for new contract item:
BI A119-Restake Monument-1 Lump Sum @ TBD
A Change Order covering this Field Directive will follow immediately.
Contractor Date
Equitable Adjustment Determination - CO No 31
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:04/21/23
Contract Item Changes
Bid Item Quantity
No. Description Change Unit Unit Price Cost ,
31-A119 Restake Monument 1 LS $1,185.41 $1,185.41
Contract Item Cost $1,185.41
CHANGE ORDER COST $1,185.41
Narrative:
FWD No 34 was issued on 03/29/23 directing the Contractor stake the monument at NE 10th Street and Duvall Avenue
NE at a new location.The Contractor's surveyor had already staked the monument per the plans. There will be another
trip required by the surveyor to restake the monument in the new location.
The Engineer's estimate was prepared on 3/21/23 for a total estimated cost of$1,720. The Contractor quoted
$1,185.41,which was reviewed and accepted for an equitable adjustment of$1,185.41
Determination of Additional Working Days
A determination of zero additional working days was made.
Engineer's Estimate
City of Renton-Duvall Ave NE,CAG 20-065
Field Directive No 34
Engineer's Estimate
Date:3/21/23
Item No. Description Unit LS Price Total
A119 Restake Monument LS $ 1,720.00 $ 1,720.00
Total(rounded) $ 1,720.00
Description:
Restake the Monument Control for the Monument at NE 10th Street and Duvall Ave NE
Date
TBD
Prime contractor Labor:(Reed Trucking) Hours Rate Total
Foreman 4 $86.42 $345.68
Labor Cost $345.68
Markup(31%) $107.16
Subtotal Labor Cost $452.84
Prime contractor Equipment: Hours Reg Rate Total
Service Truck 4.0 $40.00 $160.00
Equipment Cost $160.00
Markup(21%) $33.60
Subtotal Equipment Cost $193.60
Subcontractor Labor:(W.E.Coates) Hours Rate Total
Two Man Crew 4 $139.00 $556.00
Labor Cost $556.00
Markup(31%) $172.36
Subtotal Labor Cost $728.36
Subcontractor Equipment: Hours Reg Rate Total
Service Truck 4.0 $40.00 $160.00
Equipment Cost $160.00
Markup(21%) $33.60
Subtotal Equipment Cost $193.60
Subcontractor Material: Qty Invoice Total
Nails 3 $10.00 $30.00
Material Cost $30.00
Markup(21%) $6.30
Subtotal Subcontractor Material Cost $36.30
Total Subcontractor Cost $958.26
Markup(12%) $114.99
Total Cost: $1,719.69
Engineer's Calculation of Additional Working Days
See CO No 28, this work falls within the critical path work for the additional days in that change
order.
Contractor Quote
REED Change Order Proposal #41 2207 Inter Ave.,Ste.A
Puyallup,WA 98372
TRUCKING 6 EXCAVATING Office:(253)841-4837
,......»...0.1 Co..........1991 Fax:(253)841-4816
GC/Owner: City of Renton JSS#: 41
Reed Job No: 156 Project: Duvall Ave NE Date: 4/20/2023
Description: Re-Stake Revised monument location
Subcontractor: WE Coates
Labor Costs
_ Regular Overtime Amount
_ Craft Employee Name Hours Rate Hrs Rate* Regular Overtime
$ - $ - $ - $
$ - $ - $ - $ -
$ - $ - $ - $
$ - $ - $ - $ -
$ - _ $ - $ - $ -
*Including Fringe Benef Labor Subtotal $ - $ -
Labor Total $ -
Equipment Costs _
Equip. Regular Standby Amount
# _ Equipment Hrs Rate Hrs Rate* Regular Standby
$ - $ - $ - $ -
$ - $ - $ - $
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
$ $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
Equipment Subtotals $ - $ -
Equipment Total $0.00
Material Costs
Supplier Material Invoice(s) Quantity Price Amount
$0.00
$0.00
$0.00
$0.00
Materials Total $0.00
Subcontractor Costs _
Subcontractor Scope Invoice(s) Quantity Price Amount
WE Coates Re-Stake Revised monument location 2188 1 $1,058.40 $1,058.40
$0.00
$0.00
$0.00
REED c ry Subcontractor Total $1,058.40
Cost Summa
TRUCKING 6 EXCAVATING Total Labor $ -
,.NIMr.I.0.II C....WI»Jr.IKt
31% Labor Mark-up $ -
Total Equipment $0.00
Date: 21% Equipment Mark-up $0.00
Total Materials $0.00
21% Material Mark-up $0.00
Contractor Foreman /Superintendent Total Subcontractors $1,058.40
12% Sub Markup up to$25K $127.01
10% Sub Markup$25K-$100K $0.00
Date: 7% Sub Mark-up Over$100K $0.00
Grand Total $ 1,185.41
Pay Estimate Date
Engineer Bid Item Number
9IAaie4427#t7
Wei::
9825 Glory DR SE • Olympia, WA 98513 • wecoatesC'comcast.nei • 360 4 13-051 0 • FAX: 360-584-9914
INVOICE#: 2188 4/20/2023
BILL TO:
Reed Trucking & Excavation Inc.
2207 Inter Ave Suite A
Puyallup,WA 98372
PROJECT NAME: Duvall Avenue NE
JOB NUMBER: 21-16
FOR SURVEYING SERVICES: EWO
DATE DESCRIPTION & PERCENTAGE COMPLETED AMOUNT
4/6/2023 Extra Work Order 4-6-23 1,058.40
DUE DATE: 5/20/2023 $1,058.40
1\1-j
* g
EXTRA WORK ORDER
W. E. COATES SURVEYING, LLC.
9825 Glory Dr.S.E.
Olympia,Wa 98513
Mobile 253-677-3049 Office 360-413-0510
Date: IL-1 CI- 2_00
Contractor's Name (Ri j) 7YL0e.4.4 6-
Project Name DtAV64/.- AV-
DESCRIBE EXTRA WORK: I) a!<S7 £E-vt5CD , Doke' •
HOURS RATE AMOUNT
PLS/CALS(REG)
PLS/CALCS(O.T.)
FIELD CREW(REG) -i Zio' .('0 I lOST.t[o
FIELD CREW(O.T.)
DTM/CAD SERVICES _
TOTAL(This amount will appear on your next invoice) tt ( 0 Si? .40
Pursuant to our contract, we must agree upon these additional charges for extra services
above the contracted amount. Signing below constitutes an acceptance of charges,
regardless of whether the contractor is reimbursed by the owner.
W.E.COATES SURVEYING CONTRACTOR'S REPRESENTATIVE
DATE: O''/DC/Z 4 DATE: 61 ' 77-_,Z.GA3
CamS canner
DocuSign Envelope ID:03D94223-BFF0-45F7-962_ =C83F823168F ' •
CAG-20-065, CO #31-23
+ ok
T° Change Order No. 31
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking and Excavating, Inc.
Contract No.: CAG 20-065
Federal Aid No.: N/A
Ordered by Engineer 0 Force Account
❑ Proposed by the Contractor.(VECP) 0 Bid Item
❑ Unilateral lg< Lump Sum
I Amount Working Days
•
Original Contract: $5,218,171.95 260
Current Contract: • $5,905,076.50 277
Estimated Net Change This Order: +$1,185.41 0
New Contract: $5,906,261.91 277
Prepared By: iss
s 4/21/23
esident En 'Weer• - Date ngineer(ci to ransportation D to •,%?
Design Manager)
Reviewed By: Consent By:
4/25/23 N/A
Engineer of.Record Date Surety(Great 5%.costand/or 20% Date
Nm ase)
Reviewed By: Endorsed By:
4/26/2023 -�„� 'y-a r-23
• Renton Project Manager Date Contractor Date
Reviewed By: DoeuSignetl by:
Approved by Cheryl Beyer via 4/28/2023 CMartin Pastucha 5/9/2023 i 5:06 PM PDT
_ 888131FD988449D...
City Attorney Date City of Renton Public Works Date
Administrator/Mayor
Change Order No. 31 '
Contract Title: Duvall Ave NE
Contract No. CAG 20-065
Page 1of2
DocuSign Envelope ID:03D94223-BFF0-45F7-96E B3F823168F
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
As required in FWD 34-The Contractor is directed to do the following changed work:
Restake the new monument to be installed at the intersection of NE 10th Street and Duvall
Avenue NE.The revised coordinates for the monument at NE 10th Street and Duvall Avenue NE
are Sta 906+30.2, 1.0'LT
Northing: 184946.7041
Easting: 1313335.3242
Reason for Change:
There is an existing sanitary sewer manhole casting at the location of the proposed monument
so it has been shifted to the south to avoid the conflict.The Contractor's surveyor needs to
make another trip to the project site in order to stake the revised monument location.
Affects DBE Work: ❑ Yes ® No
No changes to DBE work.
Materials:
No changes.
Plans:
No changes.
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2021
WSDOT/APWA Standard Specifications.
See the attachment.
Extension of Time:The Time for Completion is extended 0 Working Days.
Sections 1-04.4 and 1-04.5 of the 2021 WSDOT/APWA Standard Specifications shall govern
this Change Order.The Work of the referenced Contract is modified to include the changes
detailed herein.The payment provided for herein shall constitute the complete and final
settlement for all costs of labor,equipment, materials,overhead,profit,permit fees,and all
other claims that may be made by the Contractor as a result of this change.
To be attached to Change Order:
❑ Plan
Change Order No.; 31
Contract Title: Duvall Ave NE
Contract No. CAG 20-065
Page 2 of 2
DocuSign Envelope ID:03D94223-BFF0-45F7-9 C83F823168F
Equitable Adjustment Determination - CO No 31
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:04/21/23
Contract Item Changes
Bid Item Quantity
No. Description Change Unit Unit Price Cost
31-A119 Restake Monument 1 LS $1,185.41 $1,185.41
Contract Item Cost $1,185.41
CHANGE ORDER COST I $1,185.41
DocuSign Envelope ID:03D94223-BFF0-45F7-961 83F823168F
Change Order No. 31
Backup
Documentation
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating, Inc.
Contract No. : CAG -20-065
Federal Aid No. : N/A
Attachments:
Backup Documentation
® Field Directive
® Equitable Adjustment Determination
• Determination of Additional Working Days
® Engineer's Estimate of Change Order Cost
® Engineer's Calculation of Additional Working Days
❑ Contractor's Quote
❑ Project Labor List
O Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement
❑ Summary of invoices for rented equipment
O Summary of invoices for materials
Change Order No. 031 Restake Monument
Contract Title: Duvall Avenue NE
Contract No. CAG-20-065
Page 1 of 1
DocuSign Envelope ID:03D94223-BFF0-45F7-91 C83F823168F
City of Renton
Field Directive No: 34 =R
Project Name: Duvall Ave NE
Contractor: Reed Trucking and Excavating,Inc.
Contract No: CAG-20-065
Federal Aid No: N/A By:
TIB No: N/A
Date:
Construction Manager: Tani Stafford
The following is documentation of the oral order given by the Resident Engineer per WSDOT Std Spec 1-04.4
The Contractor is directed to do the following changed work:
Restake the new monument to be installed at the intersection of NE 10th Street and Duvall Avenue NE.
The revised coordinates for the monument at NE 10th Street and Duvall Avenue NE are:
Sta 906+30.2, 1.0'LT
Northing: 184946.7041
Easting: 1313335.3242
BI A119 Restake Monument-1 LS
Cost Adjustments:
Additional cost for new contract item:
BI A119-Restake Monument-1 Lump Sum @ TBD
A Change Order covering this Field Directive will follow immediately.
Contractor Date
DocuSign Envelope ID:03D94223-BFF0-45F7-961 83F823168F
Equitable Adjustment Determination - CO No 31
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:04/21/23
Contract Item Changes
Bid Item Quantity
No. Description Change Unit Unit Price Cost
31-A119 Restake Monument 1 LS $1,185.41 $1,185.41
Contract Item Cost $1,185.41
CHANGE ORDER COST I $1,185.41
Narrative:
FWD No 34 was issued on 03/29/23 directing the Contractor stake the monument at NE 10th Street and Duvall Avenue
NE at a new location.The Contractor's surveyor had already staked the monument per the plans. There will be another
trip required by the surveyor to restake the monument in the new location.
The Engineer's estimate was prepared on 3/21/23 for a total estimated cost of$1,720. The Contractor quoted
$1,185.41, which was reviewed and accepted for an equitable adjustment of$1,185.41
DocuSign Envelope ID:03D94223-BFF0-45F7-9E D83F823168F
Determination of Additional Working Days
A determination of zero additional working days was made.
DocuSign Envelope ID:03D94223-BFF0-45F7-961 :83F823168F
LI I uI Ili S_,I J I_JtIJ I IUN.,
City of Renton-Duvall Ave NE,CAG 20-065
Field Directive No 34
Engineer's Estimate
Date:3/21/23
Item No. Description Unit LS Price Total
4119 Restake Monument LS $ 1,720.00 $ 1,720.00
Total(rounded) $ 1,720.00
Description:
Restake the Monument Control for the Monument at NE 10th Street and Duvall Ave NE
Date
TBD
Prime contractor Labor:(Reed Trucking) Hours Rate Total
Foreman 4 $86.42 $345.68
Labor Cost $345.68
Markup(31%) $107.16
Subtotal Labor Cost 5452.84
Prime contractor Equipment: Hours Reg Rate Total
Service Truck 4.0 $40.00 $160.00
Equipment Cost $160.00
Markup(21%) $33.60
Subtotal Equipment Cost $193.60
Subcontractor Labor:(W.E.Coates) Hours Rate Total
Two Man Crew 4 $139.00 $556.00
Labor Cost $556.00
Markup(31%) $172.36
Subtotal Labor Cost $728.36
Subcontractor Equipment: Hours Reg Rate Total
Service Truck 4.0 $40.00 $160.00
Equipment Cost $160.00
Markup(21%) $33.60
Subtotal Equipment Cost $193.60
Subcontractor Material: Qty Invoice Total
Nails 3 $10.00 $30.00
Material Cost $30.00
Markup(21%) $6.30
Subtotal Subcontractor Material Cost $36.30
Total Subcontractor Cost $958.26
Markup(12%) $114.99
Total Cost: $1,719.69
DocuSign Envelope ID:03D94223-BFF0-45F7-9E C83F823168F
Engineer's Calculation of Additional Working Days
See CO No 28, this work falls within the critical path work for the additional days in that change
order.
DocuSign Envelope ID:03D94223-BFFO-45F7-961 .83F823168F
REED Change Order Proposal #41 2207 Inter Ave,Ste.A
Puyallup,WA 98372
TRUCKING&FJCCAVATING Office:(253)841-4837
.........ow wr..«..• ...a. Fax:(253)841-4816
GC/Owner: City of Renton JSS#: 41
Reed Job No: 156 Project: Duvall Ave NE Date: 4/20/2023
Description: Re-Stake Revised monument location
Subcontractor: WE Coates
Labor Costs
Regular Overtime Amount
Craft Employee Name Hours Rate Hrs Rate* Regular Overtime
$ - $ - $ - $ -
$ - $ - $ $ -
$ - $ - $ - 5 -
$ - $ - $ - $
$ - $ - $ - $
*Including Fringe Benef Labor Subtotal $ - $ -
Labor Total $ -
Equipment Costs
Equip. Regular Standby Amount
# Equipment Hrs Rate Hrs Rate* Regular Standby
$ - $ - $ - $ -
$ - $ - $ - $
$ $ - $ - $ -
$ - $ - $ - $ -
$ $ - $ - $
$ - $ - $ - $ -
$ - $ - $ - $ -
$ - $ - $ - $ -
Equipment Subtotals $ • $ -
Equipment Total $0.00
Material Costs
Supplier Material Invoice(s) Quantity _ Price Amount
$0.00
$0.00
$0.00
$0.00
Materials Total $0.00
Subcontractor Costs
Subcontractor Scope Invoice(s) Quantity Price Amount
WE Coates Re-Stake Revised monument location 2188 1 $1,058.40 $1,058.40
$0.00
$0.00
$0.00
REED c ry Subcontractor Total $1,058.40
Cost Summary
TRUCKING&EXCAVATING Total Labor $ -
31% Labor Mark-up $ -
Total Equipment $0.00
Date: 21% Equipment Mark-up $0.00
Total Materials $0.00
21% Material Mark-up $0.00
Contractor Foreman /Superintendent Total Subcontractors $1,058.40
12% Sub Markup up to$25K $127.01
10% Sub Markup$25K-$100K $0.00
Date: 7% Sub Mark-up Over$100K $0.00
Grand Total $ 1,185.41
Pay Estimate Date
Engineer Bid Item Number
DocuSign Envelope ID:03D94223-BFF0-45F7-9( �83F823168F
I f�llV
9825 Glory DR SE • Olympia, WA 98513 • wecoates(@comcast.net • 360-413-0510 • FAX: 360-584-9914
INVOICE #: 2188 4/20/2023
BILL TO:
Reed Trucking & Excavation Inc.
2207 Inter Ave Suite A
Puyallup, WA 98372
PROJECT NAME: Duvall Avenue NE
JOB NUMBER: 21-16
FOR SURVEYING SERVICES: FAN()
DATE DESCRIPTION & PERCENTAGE COMPLETED AMOUNT
4/6/2023 Extra Work Order 4-6-23 1,058.40
DUE DATE: 5/20/2023 $1,058.40
frit
� J
DocuSign Envelope ID:03D94223-BFF0-45F7-961 83F823168F
EXTRA WORK ORDER
W. E. COATES SURVEYING, LLC.
9825 Glory Dr. S.E.
Olympia,Wa 98513
Mobile 253-677-3049 Office 360-413-0510
Date: /-442i"!Cr/740
Contractor's Name 12 i D
Project Name DIA-v4L4- QVi-
DESCRIBE EXTRA WORK: I) (ZE STD U-vtSCD rwAC47?"
L 0C43:1 IOD L)/ a c F- PD«'t a-- D wv
HOURS RATE AMOUNT
PLS/CALS (REG)
PLS/CALCS(O.T.)
FIELD CREW(REG) Z iOy IiO I 1 C)S .it o
FIELD CREW(O.T.)
DTM/CAD SERVICES
TOTAL(This amount will appear on your next invoice) t 0 S g .'4.
Pursuant to our contract, we must agree upon these additional charges for extra services
above the contracted amount. Signing below constitutes an acceptance of charges,
regardless of whether the contractor is reimbursed by the owner.
W.E. COATES SURVEYING CONTRACTOR'S REPRESENTATIVE
DATE: O`f/DC/ZA)Z.3 DATE: LI - 'I-
gpCamScanner