HomeMy WebLinkAboutCAG-20-065 - Duvall - Change Order 33 r
iR Change Order No. 33
Backup
Documentation
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking& Excavating, Inc.
Contract No. : CAG-20-065
Federal Aid No. : N/A
Attachments:
Backup Documentation
® Field Directive
° Equitable Adjustment Determination
® Determination of Additional Working Days
® Engineer's Estimate of Change Order Cost
® Engineer's Calculation of Additional Working Days
® Contractor's Quote
❑ Project Labor List
• Contractor's Equipment list including rates per AGC-WSDOT Equipment Agreement
O Summary of invoices for rented equipment
O Summary of invoices for materials
Change Order No. 033 Paint Line Final Application
Contract Title: Duvall Avenue NE
Contract No. CAG -20-065
Page 1of1
City of Renton
Field Directive No: 36
Project Name: Duvall Ave NE
Contractor: Reed Trucking and Excavating,Inc.
Contract No: CAG-20-065
Federal Aid No: N/A By:
TIB No: N/A
1")
Date:
Construction Manager: Tani Stafford 10/2023
The following is documentation of the oral order given by the Resident Engineer per WSDOT Std Spec 1-04.4
The Contractor is directed to do the following changed work:
Remobilize,clean,prep and reapply two coats of the longitudinal paint line on Duvall Avenue,as shown in the
attached schedule,over the previously applied paint lines.
The approximate added paint line quantity is 6,279 LF. The current contract quantity is 16,096 LF. The added
work is an approximate 39%increase in quantity.
Cost Adjustments:
Additional cost for contract items:
RI A121-Paint Line-Final Application. Add approx 6,279 LF @$0.77/LF=$4,835.00
A Change Order covering this Field Directive will follow immediately.
Contractor Date
r
Paint Line(White Wide Edge Line)-Estimate
Sta Sta Length(LF) Passes Total
89094 89280 186 1 186
89358 90591 1233 1 1233
90672 91931 1259 1 1259
92022 92760 738 1 738
92022 92122 100 1 100
89358 89400 42 1 42
Bid Item A88 Paint Line- Total added 3558 LF
Paint Line(White Lane Line)-Estimate
Sta Sta Length(LF) Passes Total
90672 90926 254 1 254
91300 91800 500 1 500
91800 91931 131 1 131
89358 90591 1233 1 1233
89400 89850 450 1 450
Bid Item A88 Paint Line- Total added 2568 LF
Paint Line(White Wide Lane Line)-Estimate
Sta Sta Length(LF) Passes Total
90051 90112 61 1 61
Total added 61 LF
Paint Line(White Wide Dotted Lane Line)-Estimate
Sta Sta Length(LF) Passes Total
89358 89400 42 1 42
89903 89953 50 1 50
Total added 92 LF
Equitable Adjustment Determination - CO No 33
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065 •
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:05/09/23
Bid Item Changes
Bid Item Quantity
No. Description Change Unit Unit Price Cost
A121 Paint Line-Final Application 6279 LF $0.77 $4,834.83
Bid Item Cost $4,834.83
ESTIMATED CHANGE ORDER COST(Rounded) $4,835.00
Narrative:
FWD No 36 was issued on 5/10/23 directing the Contractor to apply a final application of
paint line in various locations throughout the project.
Contractor confirmed that his subcontractor would do the added work at the unit price for
A88 Paint line, along with an added mob fee of$1064.00 on 5/9/2023.
The Engineer provided an estimate to the City on 5/9/23 for$4,835, which includes the
paint line final application at $0.77/LF for$6,259 LF of paint line. This unit price is within
the range of current projects bid.
The equitable adjustment is estimated to be $4,835.00
CO 31 added wood fence improvements to the Contract. No working days were included
in that change order because the Contractor anticipated it would be completed in tandem
with remaining illumination work. However the fence subcontractor was not available until
after this time frame, so the added work was completed on 5/2/23. One working day is re-
quired for the added work
CO 33 adds a final application of paint line. The added work was completed on 5/15/23
and 5/16/23. Two working days were required for the added work.
An adjustment of an additional 3 working days was agreed to.
Determination of Additional Working Days
A determination of three additional working days was made.
Engineer's Estimate
Duvall Avenue NE
CAG 20-065
G&O 620593
5/9/2023 OK per WSDOT Unit
FWD 36 Engineer's Estimate Bid Analysis
Bid Item ASS Paint Line= 16,096 LF
Net Change/Renegotiated Rat 6279 LF @ Cr0.77 per LF $ 4,834.83 39%increase in quantity
Paint Line(White Wide Edge Line)-Estimate
Sta Sta Length(LF) Passes Total
89094 89280 186 1 186
89358 90591 1233 1 1233
90672 91931 1259 1 1259
92022 92760 738 1 738
92022 92122 100 1 100
89358 89400 42 1 42
Bid Item A88 Paint Line- Total added 3558 LF
Paint Line(White Lane Line)-Estimate
Sta Sta Length(LF) Passes _ _ Total_
90672 90926 254 1 254
91300 91800 500 1 500
91800 91931 131 1 131
89358 90591 1233 1 1233
89400 89850 450 1 450
Bid Item A88 Paint Line- Total added 2568 LF
Paint Line(White Wide Lane Line)-Estimate
Sta Sta Length(LF) Passes Total
90051 90112 61 1 61
Total added 61 LF
Paint Line(White Wide Dotted Lane Line)-Estimate
Sta Sta Length(LF) Passes Total
89358 89400 42 1 42
89903 89953 50 1 50
Total added 92 LF i
Veld Net Clump $ 4,834.83
m�m Desert. peon_ Job ContractAD Date• Planned Quantity Low Bid {Ione Bld Third Bid
6781 L F. TEMPORARY BARRIER 22A040 009935 1/23/2023 460.00 $84.00 $78.00 3100.32
NWR AVERAGE LOW BID is $58.13
STATE AVERAGE LOW BID is $26.58
6783 L.F. RAISING EXISTING BEAM GUARDRAIL 22A038 009932 1/9/2023 470.00 $18.00 $20.00 $17.00
6783 L.F. RAISING EXISTING BEAM GUARDRAIL 22A048 009954 2/272023 4.158.00 $7.00 $7.50 $0.00
NWR AVERAGE LOW BID is $8.12
STATE AVERAGE LOW BID is$9.54
6784 L.F. REMOVING AND RESETTING EXISTING PERMANENT BARRIER 20A039 009850 6/6/2022 250.00 524.82 $20.00 $30.00
NWR AVERAGE LOW BID is $24.82
STATE AVERAGE LOW BID is $20.12
6806 L.F. PAINT LINE 22A012 009846 5/31/2022 636 DO $11 15. $10.00 S0 00
6806 L.F. PAINT LINE 20A039 009850 6/6/2022 10.110.00 $1.00 $1.10 $1.40
6806 L.F. PAINT LINE 22A007 009864 8/1/2022 350.00 $50.00 $20.00 51550
6806 L.F. PAINT LINE 22A022 009885 10/3/2022 70.00 $15.00 $20.00 $22.00
6806 L.F. PAINT LINE 22A008 009887 10/3/2022 680.00 $7.50 $6.00 $0.00
6806 L.F. PAINT LINE 22A018 009894 10/24/2022 5.000.00 $2.50 $2.40 $8.00
6806 L.F. PAJNT LINE 22A021 009896 10/24/2022 430.00 $9.00 $0.00 $0.00
5806 L.F. PAINT LINE 22A036 009924 12272022 2.748.00 $2.50 $1.50 $3.20
NWR AVERAGE LOW BID is $3.20
STATE AVERAGE LOW BID is $0.22
Engineer's Calculation of Additional Working Days
The added work requires three additional working days to complete.
The number of working days required to install the final application of paint line is two working
days.
The number of working days required to install the wood fence per CO 31 is one working day.
The original schedules shows the fence work being completed
A
r
3 Week Look-Ahead Schedule
REEDc Date:4/29/23 5/19123
TRUCKING 6 EXCAVATING Name: Illumination critical Duvall Avenue
s ....,.Civil C.. .v....�..wa path work shifted to
5/4/23 and 5/9/23
April May
Sched
ID Work Description S S M Ti W T F S S M T W T F S S M T Notes/Resources
29 30 1 �• 3 4 5 6 7 8 9 10 11 12 13 14 15 16
l^
Illumination critical path X X 0 X O
Seeding window begins 3/1 also
landscaping critical path wanting illumination complete prior to
' X final restoration
thermoplastic Critical path p Scheduled long wait list!
Fencing 0 X
Monuments X
Punchlist work X X
Suspension for Thermoplastic X X X X X X X X
CO No 31 fence work work completed on
5/2/23 and it became critical path work CO No 33 Paint line
since the illumination work did not take reapplication added
—
place that day as planned. work takes place on
5/15/23 and 5/16/23
Contractor Quote
Tani Stafford
From: Dustin Wright <DWright@reedtrucking.com>
Sent: Tuesday, May 9, 2023 12:07 PM
To: Tani Stafford; Flora Lee
Cc: Tiffani Barquist;Shawn Reed
Subject: Duvall.
Tani.
Stripe rite says they can honor the paint line bid price but they require an additional mobe fee of 1064.00 dollars.Will
this be acceptable?
Also I'm hearing Friday or Monday for thermo.
Last thing.The wall needs to dry.There will be no work performed on the wall until Monday The 15th.
Please place the project back in suspension after today until thermo plastic.
Thank you
Sent from my iPhone
1
DocuSign Envelope ID:AC692699-B961-4CF2-81 15D3154585C
G\tY 0.4,,
® j
. —NTa� ,
Change Order No. 33
Contract Title: Duvall Avenue NE
Contractor: Reed Trucking and Excavating,Inc.
Contract No. : CAG 20-065
Federal Aid No.: N/A
® Ordered by Engineer ❑ Force Account
El Proposed by the Contractor(VECP) ® Bid Item
El Unilateral .. ❑ Lump Sum
Amount Working Days
Original Contract: $5,218,171.95 260
Current Contract: $5,908,153.97 277
Estimated Net Change This Order: +$4,835.00 3
New Contract: $5,912,988.97 280
Pr ared By: Iss By:
5/23/23
i .. •-?..4--.4,2 r"—— 4 47:''
/ esiden er Date Engineer icit fRentonTransportation Date
Design Manager)
Reviewed By: Consent By:
--------.."-k-vk 0.______ 5/2.8/2023 N/A
Engineer of Record Date Surety urea 5%cost and/or 20% Date
ti ease)
Reviewed By: Endorsed By:
�/ 6/1/2023 CD k' +.� Tom, S 444(93
• Renton Project Manager Date Contractor Date
Reviewed By: Executed By:
CO SI6 dby.
Martin Pastucha 6/13/2023 I 11:06 AM PD
City Attorney Date City oenton Public Works Date
Administrator/Mayor
Change Order No. 33
Contract Title: Duvall Ave NE
Contract No. CAG 20-065
• Page 1 of 3
DocuSign Envelope ID:AC692699-B961-4CF2-88 5D3154585C
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
As required in FWD No 36-The Contractor is directed to do the following changed work:
Clean, prepare surface and reapply two coats of longitudinal paint line on Duvall
Avenue, per the schedule below:
Paint Line(White Wide Edge Line)
Sta Sta Length(LF) Passes Total
89094 89280 - 186 1 186
89358 90591 1233 1 1233
90672 91931 1259 1 1259
92022. 92760 738 1 738
92022 92122 100, 1 100
89358 89400 42 1 42
Bid Item A88 Paint Line- Total added 3558 LF
Paint Line(White Lane Line)
Sta Sta Length(LF) , Passes Total
90672 90926 254 1 254
91300. 91800 _ 500; 1 500
91800 91931 131 1 131
89358 90591 1233 1 1233
89400 89850 450 1 450
Bid Item A88 Paint Line- Total added 2568 LF
Paint Line(White Wide Lane Line)
Sta Sta Length(LE) Passes Total
90051 90112 61 1 61
Total added 61 LF
Paint Line(White Wide Dotted Lane Line)
Sta Sta Length'(LF) Passes Total
89358 89400 42 1 42
89903 8.99.5.3 50 1 50
Total added 92 LF
Change Order No. 33
Contract Title: Duvall Ave NE
Contract No. CAG 20-065
Page 2 of 3
DocuSign Envelope ID:AC692699-B961-4CF2-81;, 15D3154585C
The changed work will be paid via the following Contract Items at the Contract Unit price,this
quantity is approximate:
o Contract Item No.33-A121 PAINT LINE—FINAL APPLICATION—6279 LF @
$0.77/LF=$4,835.00
Reason for Change:
Several longitudinal lines within the Duvall Avenue project,within the project limits
have worn away glue to temporary lane shifts for construction phasing that lead to
vehicle wheel path directly on the newly striped paint lines. Several paints need a final
paint application.
Affects DBE Work: ❑ Yes ® No
No changes to DBE work.
Materials:
No changes.
Plans:
None
Equitable Adjustment:
This Change Order does include an equitable adjustment per Section 1-09.4 of the 2021
WSDOT/APWA Standard Specifications.
See the attachment.
Extension of Time:
The Time for Completion is extended 3 Working Days.
Sections.1-04.4 and.1-04.5 of the2021 WSDOT/APWA Standard Specifications shall govern
this Change Order.The Work of the referenced Contract is modified to include the changes
detailed herein.The payment provided for herein shall constitute the complete and final
settlement for all costs of labor,equipment, materials,overhead,profit,permit fees,and all
other claims that may be made by the Contractor as a result of this change.
To be attached to Change Order:
Plans
Change Order No. 33
Contract Title: Duvall Ave NE
Contract No. CAG 20-065
Page 3 of 3
DocuSign Envelope ID:AC692699-13961-4CF2-861, )5D3154585C
•
Equitable Adjustment Determination -CO No 33
Project Name:Duvall Avenue NE
Contractor:Reed Trucking&Excavating Inc.
Contract No:CAG 20-065
By: Tani Stafford
Construction Manager: Tani Stafford,PE Date:05/09/23
Bid Item Changes
Bid Item Quantity
No. Description ' Change Unit, Unit Price Cost
A121 Paint Line-Final Application 6279 IF $0.77 $4,834.83
.Bid Item Cost $4,834.83
ESTIMATED CHANGEVRDERCOST(Roundedh • _ • ._ iilTT$4835.00