1
PRE-APPLICATION MEETING FOR
Bretzke Short Plat
PRE25-000143
CITY OF RENTON
Department of Community & Economic Development
Planning Division
May 29th, 2025
Contact Information:
Planner: Alex Morganroth, 425-430-7219, amorganroth@rentonwa.gov
Public Works Plan Reviewer: Heather Bray, 425-430-7383, hbray@rentonwa.gov
Fire Prevention Reviewer: Corey Thomas, 425-276-9582, cthomas@rentonrfa.org
Building Official: Rob Shuey, 425-430-7290, rshuey@rentonwa.gov
Please retain this packet throughout the course of your project as a reference.
Consider giving copies of it to any engineers, architects, and contractors who
work on the project. You will need to submit a copy of this packet when you
apply for land use and/or environmental permits.
Pre-screening: When you have the project application ready for submittal, call
and schedule an appointment with the project manager to have it pre-screened
before making all of the required copies.
The pre-application meeting is informal and non-binding. The comments
provided on the proposal are based on the codes and policies in effect at the
time of review. The applicant is cautioned that the development regulations are
regularly amended and the proposal will be formally reviewed under the
regulations in effect at the time of project submittal. The information contained
in this summary is subject to modification and/or concurrence by official
decision-makers (e.g., Hearing Examiner, Planning Director, Development
Services Director, Department of Community & Economic Development
Administrator, Public Works Administrator and City Council).
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
2
Renton Regional Fire Authority
M E M O R A N D U M
DATE: May 19, 2025
TO: Alex Morganroth, Principal Planner
FROM: Corey Thomas, Lead Plans Review Inspector
SUBJECT: Bretzke Short Plat
1. The fire flow requirement for a single-family home is 1,000 gpm minimum for dwellings up to
3,600 square feet (including garage and basements). If the dwelling exceeds 3,600 square feet, a
minimum of 1,500 gpm fire flow would be required. A minimum of one fire hydrant is required within
300-feet of the proposed buildings and two hydrants if the fire flow goes up to 1,500 gpm. Water is
provided by King County Water District 90. A water availability certificate is required. Looks like the
existing water main is a looped 8 inch main. It appears that there is one existing fire hydrant that will
meet the minimum requirements.
2. The fire impact fees are currently applicable at the rate of $421.98 per single family unit. This fee
is paid at building permit issuance. No charges apply to the existing house that is to remain or if it is
removed.
3. Fire department apparatus access roadways are required to be a minimum of 20-feet wide fully
paved, with 25-feet inside and 45-feet outside turning radius. Fire access roadways shall be constructed
to support a 30-ton vehicle with 75-psi point loading. Access is required within 150 feet of all points on
the buildings. The maximum grade is 15 percent.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
3
DEPARTMENT OF COMMUNITY
& ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: May 27th, 2025
TO: Alex Morganroth, Principal Planner
FROM: Heather Bray, Civil Plan Reviewer
SUBJECT: Bretzke Short Plat
5521 NE 10th St, Renton, WA 98059
PRE 25-000143
NOTE: The applicant is cautioned that information contained in this summary is preliminary and non -binding
and may be subject to modification and/or concurrence by official City decision-makers. Review comments
may also need to be revised based on site planning and other design changes required by City staff or made
by the applicant.
I have reviewed the application for the Bretzke Short Plat at 5521 NE 10th St APN 1023059358 and have the
following comments:
EXISTING CONDITIONS
The site is approximately 1.91 acres in size and is irregular in shape. There is 1 existing single-family
residence on site and an accessory shed structure. There are several trees and groundcover throughout the
site, and lawn in the eastern portion of the property designated for the residence.
Water Water service is provided by King County Water District 90.
Sewer Wastewater service is provided by the City of Renton. There is an existing 10-inch PVC gravity
wastewater main located in NE 10th St (see City plan no. S-327803). In addition, there is also an
existing 8-inch PVC gravity wastewater main that extends through the project site (see City plan no.
S-362009). There are two existing 6-inch side sewer stubs on-site (see City plan no S-362009).
Storm There is an existing 12-inch stormwater main in NE 10th St (see City plan no. R-34903) and a surface
water main on-site (see City plan no. R349403). The existing property has a 12-inch CPEP private
drainage pipe from a previous short plat (see City plan no. R349403). Based on the current site
topography, the site appears to sheet flow towards the southwest property line. The site contains
sensitive slopes up to 40%, high erosion hazard areas, and wetlands. There is also a non-fish
bearing, seasonal stream named Honey Creek to the west of the property within 25 feet of the
property line.
Streets NE 10th Street is a Residential Access Street with an existing right of way (ROW) width of 60.0-ft as
measured using the King County Assessor’s Map and approximately 24.0-ft of asphalt paving.
WATER COMMENTS
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
4
1. A water availability certificate from King County Water District 90 is required as part of the land-use
application.
2. A copy of the approved KCWD 90 plans shall be provided to the City prior to civil construction permit
approval. Contact KCWD 90 at (425) 255-9600 or info@kcwd90.com.
3. Adequate horizontal and vertical separation between water main and other utilities (storm, sewer,
vaults, power, gas, electrical, etc) shall be provided for the operations and maintenance of the City
mains.
4. A conceptual utility plan will be required as part of the land-use application for the subject
development.
SEWER COMMENTS
1. Individual side sewers are required for each lot. All new sewer stubs shall be a minimum of 6-inch
and shall run at a slope of at least 2% to the main. All new side sewers and sewer stubs shall
conform to the standards in RMC 4-6-040 and City of Renton Standard Details.
2. For lots where a gravity connection to the existing and proposed sewer main is not possible,
individual grinder pumps and force mains will be required for each lot. The applicant shall make
every effort to accomplish gravity side sewers. Should the applicant pursue grinder pumps, they will
be required to demonstrate it is not feasible to adjust grading or pad elevations to accomplish gravity
side sewers. The private force main should connect to a 6-inch sewer stub that is a minimum of 2%
in slope dedicated specifically to the private force main. Private utility easements will be needed for
any force main or gravity side sewer that passes through an adjacent lot prior to connecting to the
existing sewer main.
3. An improved access to the existing manholes must be maintained within the sewer access
easement (see City plan no. S-362009).
4. A conceptual utility plan will be required as part of the land use application for the subject
development.
5. The development is subject to a wastewater system development charge (SDC) fee. SDC fee for
sewer is based on the size of the new domestic water to serve the project. Current fees can be found
in the 2025 Development Fees Document on the City’s website.
a. The current sewer fee for a 1-inch meter install is $4,025.00 per meter.
b. Fees will be charged based on the rate at the time of construction permit issuance.
c. The full fee schedule can be found here.
SURFACE WATER COMMENTS
1. Drainage plans and a drainage report complying with the adopted 2022 Renton Surface Water Design
Manual (RSWDM) will be required. Refer to Figure 1.1.2.A – Flow Chart in the 2022 RSWDM to
determine what type of drainage review is required for this site. The site falls within the City’s Flow
Control Duration Standard (matching Forested site conditions). The site falls within the May Creek
drainage basin.
2. Drainage report and drainage plans based on 2022 RSWDM are required to be provided.
3. Storm drainage improvements along all public street frontages are required to conform to the City’s
Street and stormwater conveyance standards. Any new storm conveyance installed on or off-site
shall be designed and sized in accordance with standards found in Chapter 4 of the 2022 RSWDM.
New storm drains shall be designed to account for the total upstream tributary area, assuming
developed conditions for onsite tributary areas and existing conditions for any offsite tributary areas.
4. If the new plus replaced pollution generating impervious surface exceeds 5,000 SF, the applicant will
be required to provide basic water quality treatment. All proposed stormwater facilities shall be
designed in accordance with the current RSWDM at the time of civil construction permit application.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
5
Separate structural plans will be required to be submitted for review and approval under a separate
building permit for all proposed detention and/or water quality vaults.
5. Appropriate on-site BMPs satisfying Core Requirement #9 will be required to help mitigate the new
runoff created by this development to the maximum extent feasible. On-site BMPs shall be evaluated
as described in Section C.1.3 of the 2022 RSWDM. A preliminary drainage plan, including the
application of on-site BMPs, shall be included with the land use application, as appliable to the
project. The final drainage plan and drainage report must be submitted with the utility construction
permit construction.
6. Critical areas are present onsite or adjacent to the site that may affect stormwater review. There are
slopes up to 40%, high erosion hazard, wetlands, and an adjacent creek.
7. A geotechnical soils report for the site is required per the 2022 Renton Surface Water Design Manual
Section C.1.3. Information on the water table and soil permeability (measured infiltration rates), with
recommendations of appropriate on-site BMPs per Core Requirement #9 and Appendix C shall be
included in the report. The report should also include information concerning the soils, geology,
drainage patterns and vegetation present shall be presented to evaluate the drainage, erosion
control and slope stability for site development of the proposed plat. The applicant must
demonstrate the development will not result in soil erosion and sedimentation, landslide, slippage,
or excess surface water runoff.
8. Erosion control measures to meet the City requirements shall be provided.
9. A Construction Stormwater General Permit from the Washington Department of Ecology will be
required if site clearing equals one acre or more.
10. The current City of Renton Surface Water Standard Plans shall be used in all drainage submittals.
11. The development is subject to a surface water system development charge (SDC) fee. Fees will be
charged based on the rate at the time of construction permit issuance.
a. The 2025 Surface water system development fee is $2,350 per one new single-family
house.
b. The full schedule can be found here.
TRANSPORTATION COMMENTS
1. In accordance with RMC 4-6-060, if the site improvements and/or proposed building additions
exceed an overall valuation of $175,000, the project site(s) shall be required to meet the City’s
Complete Streets Standards:
a. NE 10th Street is classified as a residential access street. Per RMC 4-6-060, the minimum
right of way (ROW) width for a residential access street is 53-ft. To meet the City’s complete
street standards for Residential Access streets, a minimum ROW width of 53 feet is required,
half street improvements as taken from the ROW centerline will be required and include a
minimum 10-foot paved road, 0.5 feet of cub and gutter, an 8-foot planting strip, and 5-foot
sidewalk, street trees and storm drainage improvements.
2. If a shared driveway is proposed as part of this development, it shall meet the design standards
found in RMC 4-6-060. Shared driveways may be allowed for access to four (4) or fewer residential
lots. Shared driveways shall be wholly in a tract. Shared driveways shall not be more than 200 -ft in
length. The paved surface shall be a minimum of 20-ft to meet Renton Regional Fire Authority
standards. The maximum grade of the shared driveway shall not exceed 15%. Drainage
improvements per City standards are required along the shared driveway. An access easement shall
cover the entirety of the tract.
3. For dead end roads in excess of 150 feet an approved fire access turnaround is required. See city
code 4-6-060 for types of turnarounds allowed.
4. On-site and off-site curb ramps, sidewalk improvements will be reviewed in conjunction with the
civil construction permit and will require a grading plan consisting of spot elevations and slopes
showing that ADA and City specifications are being met.
5. Refer to City code 4-4-080 regarding driveway regulations.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
6
6. Undergrounding of all existing and proposed utilities is required on all frontages per RMC 4-6-090.
7. Paving and trench restoration shall comply with the City’s Trench Restoration and Overlay
Requirements.
8. Street lighting per City standards will not be required along the project’s NE 10th Street frontage as
the proposed development is less than 4 residential units.
9. A traffic impact analysis is required when estimated vehicular traffic generated from a proposed
development exceeds 20 vehicles per hour in either the AM (6:00 - 9:00) or PM (3:00 –6:00) peak
periods estimated by the applicant engineer using the current ITE Trip Generation book. The
applicant engineer can contact the City to determine the extent of the traffic study that will be
required for the project. If the peak trips exceed 20, a traffic impact study will be required to be
included with the land use application.
10. The transportation impact fee is based on the type of land use. For a single -family dwelling, the 2025
transportation impact fee is $11,485.67. Transportation impact fees are subject to change based on
the calendar year the building permit is issued.
GENERAL COMMENTS
1. All existing and proposed utility lines (i.e. electrical, phone, and cable services, etc.) along property
frontage or within the site must be underground. The construction of these franchise utilities must be
inspected and approved by a City of Renton inspector.
2. Maximum exposed retaining wall height is 6-ft and shall be setback a minimum of 3-ft from the right-
of-way as outlined in RMC 4-4-040 – Fences, Hedges and Retaining Walls. a. Show all retaining walls
on profile view. No walls shall be greater than 6’.
3. Retaining walls that are 4’ or taller from bottom of footing and stormwater detention vaults will
require a separate building permit. Structural calculations and plans prepared by a licensed
engineer will be required as part of the building permit review.
4. Adequate separation between utilities as well as other features shall be provided in accordance with
code requirements:
a. Provide rim and invert elevations on all drainage and sewer structures.
b. 7-ft minimum horizontal and 1-ft vertical separation between storm and other utilities is
required except for water lines which require 10-ft horizontal and 1.5-ft vertical.
c. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
d. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.
5. All civil construction permits for utility and street improvements will require separate plan
submittals. All utility plans shall confirm to the Renton Drafting Standards. A licensed Civil Engineer
shall prepare the civil plans. Please visit the Development Engineering Forms page for the most up-
to-date plan submittal requirements: http://rentonwa.gov/business/default.aspx?id=42473
6. A landscaping plan shall be included with the civil plan submittal. Each plan shall be on separate
sheets.
7. Fees quoted in this document reflect the fees applicable in the year 202 5 only and will be assessed
based on the fee that is current at the time of the permit application or issuance, as applicable to the
permit type. Please visit www.rentonwa.gov for the current development fee schedule.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
7
DEPARTMENT OF COMMUNITY
& ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: May 29, 2025
TO: Pre-Application File No. 25-000143
FROM: Alex Morganroth, Principal Planner
SUBJECT: Bretzke Short Plat – 5521 NE 10th St (APN 1023059358)
General: We have completed a preliminary review of the pre-application for the above-referenced
development proposal. The following comments on development and permitting issues are based on the
pre-application submittals made to the City of Renton by the applicant and the codes in effect on the
date of review. The applicant is cautioned that information contained in this summary may be subject to
modification and/or concurrence by official decision -makers (e.g., Hearing Examiner, Community &
Economic Development Administrator, Public Works Administrator, Planning Director, Development Services
Director, Development Engineering Director, and City Council). Review comments may also need to be
revised based on site planning and other design changes required by City staff or made by the applicant. The
applicant is encouraged to review all applicable sections of the Renton Municipal Code. The Development
Regulations are available online at https://www.codepublishing.com/WA/Renton.
Project Proposal: The applicant is proposing to subdivide the existing parcel into two (2) separate residential
lots in order to construct one new single-family residence. An existing single-family residence is proposed to
be retained on the site. The project site is located at 5521 NE 10th St (APN 1023059358) and encompasses
83,199 square feet (1.90 acres). The site has a Comprehensive Plan Land Use Designation of Residential Low
Density and is within the Residential-4 (R-4) zoning designation. The proposed lots would be 9,048 sq. ft. and
11,806 square feet in size. Access to the proposed lots was shown on the site plan via individual driveways off
of NE 10th St. According to City of Renton (COR) maps, a High Erosion Hazard, regulated slopes, wetlands,
and a Type F stream (Honey Creek) are mapped on or within 100 feet (100’) of the site.
Current Use: The site is currently developed with an 1,880 sq. ft. detached dwelling constructed in 1977 and
a detached accessory building.
1. Zoning /Land Use Designation, and Overlays: The subject property is located within the Residential-4
(R-4) zoning classification. The Residential Low Density Land Use designation is intended to implement
the R-4 zone. The R-4 zone is established to promote urban single family residential neighborhoods
serviceable by urban utilities and containing open space amenities. The R -4 designation serves as a
transition between rural designation zones and higher density residential zones. It is intended as an
intermediate lower density residential zone.
Detached dwellings are permitted within the Residential-4 (R-4) zone.
2. Density: The area of public rights-of-way, shared driveway tracts, and critical areas (i.e., very high
landslide hazard areas, protected slopes (except evaluate on a case -by-case basis those protected
slopes created by previous development, wetlands, Class 1 to 4 streams and lakes or floodways) would
be deducted from the gross site area to determine the “net” site area prior to calculating density. In order
to calculate the proposed density of the project, any area of public road, shared driveway, and/or cr itical
area dedication must be known. All fractions which result from net density calculations shall be truncated
at two (2) numbers past the decimal (e.g., 4.5678 becomes 4.56). Calculations for minimum or maximum
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
8
density that result in a fraction that is 0.50 or greater shall be rounded up to the nearest whole number.
Those density calculations resulting in a fraction that is less than 0.50 shall be rounded down to the
nearest whole number. The R-4 zone has a maximum density of four (4) dwelling units per acre with no
minimum density.
3. Development Standards: The project would be subject to RMC 4-2-110A , Development Standards for
Residential Zoning Designations effective at the time of complete application (noted as “R -4 standards”
herein).
Minimum Lot Size, Width and Depth – The minimum lot size required in the R-4 zone is 9,000 square feet
for parcels being subdivided. Minimum lot width is 70 feet (70); minimum lot width for corner lots is 80 feet
(80’); minimum lot depth is 100 feet (100’).
Based on the submitted site plan the proposed lots appear to comply with the required minimum lot
size, width and depth for the R-4 zone. Detailed information is required at the Short Plat submittal to
confirm compliance with lot width, depth, and size requirements. The submitted plans would need
to show compliance with the required lot size and dimensional standard with the land use
application.
Lot Coverage – The maximum building coverage permitted in the R-4 zone is 35% of the lot area. The
maximum impervious surface coverage in the R-4 zone is 50 percent (50%).
New development would need to comply with the maximum building coverage and impervious
surface requirements of the zone at the time of building permit review. Existing development
proposed for retention would also be required to comply with lot coverage limitations and would be
reviewed for compliance at the time of land use application.
Setbacks – Setbacks are the minimum required distance between the building footprint and the property
line and any private access easement or tract. For through lots, corner lots, and lots without street
frontage, the front yard will be determined by the Planning Division Director.
Minimum Front Yard 30 ft.
Minimum Secondary Front Yard 30 ft.
Minimum Freeway Frontage
Setback
10 ft. landscaped setback from the property
line.
Minimum Rear Yard 25 ft.
Minimum Side Yard Combined 20 ft. with not less than 7.5 ft. on
either side.
Clear Vision Area In no case shall a structure over 42 in. in height
intrude into the 20 ft. clear vision area defined
in RMC 4-11-030.
Compliance with the required setbacks for new development would be verified at the time of the
building permit application. Existing development proposed for retention would be reviewed for
compliance at the time of the land use application.
Building Height – The maximum wall plate height is restricted to 32 feet (32’), and the buildings shall be
not more than three (3) stories. Roofs with a pitch equal to or greater than 4:12 may project an additional
six (6) vertical feet from the maximum wall plate height; common rooftop features, such as chimneys, may
project an additional four vertical feet (4’) from the roof surface. Non -exempt vertical projections (e.g.,
decks, railings, etc.) shall not extend above the maximum wall plate height unless t he projection is
stepped back one-and-a-half horizontal feet (1.5’) from each façade for each one vertical foot (1’) above
the maximum wall plate height. The maximum wall plate height for detached accessory structures is 12
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
9
feet (12’) and the total floor area must be less than that of the primary structure. Accessory structures are
also included in building lot coverage calculations.
Building height shall not exceed the maximum allowed by the subject zoning district or the maximum
allowed pursuant to RMC 4-3-020, Airport Related Height and Use Restrictions, whichever is less.
New development would need to comply with the maximum building height regulations of the zone
at the time of building permit review.
4. Landscaping: Except for critical areas, all portions of the development area not covered by structures,
required parking, access, circulation or service areas, must be landscaped with native, drought -resistant
vegetative cover. The minimum on-site landscape width required along street frontages is 10 feet, with a
mix of trees, shrubs, and groundcover. refer to landscape regulations (RMC 4-4-070) for further general
and specific landscape requirements.
Storm drainage facilities are required to comply with the minimum 15-foot perimeter landscaping strip on
the outside of the fence unless otherwise determined through the site plan review or subdivision review
process. Please refer to landscape regulations RMC 4-4-070 for further general and specific landscape
requirements.
A conceptual landscape plan shall be provided with the land use application as prepared by a
licensed Landscape Architect, a certified nurseryman or other certified professional. All
landscaping shall meet the requirements of RMC 4-4-070, Landscaping.
5. Significant Tree Retention: When significant trees (greater than 6-inch caliper or 8-caliper inches for
alders and cottonwoods) are proposed to be removed, a tree inventory and a tree retention plan along with
an arborist report, tree retention plan and tree retention worksheet shall be provided with the formal land
use application as defined in RMC 4-8-120. The tree retention plan must show preservation of at least 30%
of significant trees. A review of COR Maps appears to show that there are mature trees on the site. Please
refer to RMC 4-4-130, Tree Retention and Land Clearing Regulations for further general and specific tree
retention and land clearing requirements.
In addition to retaining a minimum of 30% of existing significant trees, properties subject to an active land
development permit shall comply with minimum tree credit retention requirements of a minimum of 30
credits per net acre. Tree credits encourage retention of existing significant trees with larger trees being
worth more tree credits. The Administrator may authorize the planting of replacement trees on the
site if it can be demonstrated to the Administrator's satisfaction that an insufficient number of trees
can be retained.
TREE SIZE
TREE
CREDITS
New small species tree 0.25
New medium species tree 1
New large species tree 2
Preserved tree 6 – 9 caliper inches 4
Preserved tree 10 – 12 caliper inches 5
Preserved tree 12 – 15 caliper inches 6
Preserved tree 16 – 18 caliper inches 7
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
10
TREE SIZE
TREE
CREDITS
Preserved tree 19 – 21 caliper inches 8
Preserved tree 22 – 24 caliper inches 9
Preserved tree 25 – 28 caliper inches 10
Preserved tree 29 – 32 caliper inches 11
Preserved tree 33 – 36 caliper inches 12
Preserved tree 37 caliper inches and greater 13
Significant trees shall be retained in the following priority order:
Priority One: Landmark trees; significant trees that form a continuous canopy; significant trees on slopes
greater than twenty percent (20%); significant trees adjacent to critical areas and their associated buffers;
significant trees over sixty feet (60') in height o r greater than eighteen inches (18") caliper; and trees that
shelter interior trees or trees on abutting properties from strong winds, which could otherwise allow such
sheltered trees to be blown down if removed.
Priority Two: Healthy tree groupings whose associated undergrowth can be preserved; other significant
native evergreen or deciduous trees; and other significant non-native trees.
Priority Three: Alders and cottonwoods shall be retained when all other trees have been evaluated for
retention and are not able to be retained unless the alders and/ or cottonwoods are used as part of an
approved enhancement project within a critical area or its buffer.
The Administrator may require an independent review of any land use application that involves tree
removal and land clearing at the City's discretion.
The Administrator may authorize the planting of replacement trees on the site if it can be demonstrated to
the Administrator's satisfaction that replacement requirements in RMC 4-4-130H1e can be met.
The submitted site plan does not identify any existing trees on the subject property. Tree retention
standards shall be applied to the developable area, as defined in RMC 4-11-040, Definitions D, of a
property. A formal tree retention/planting plan and tree retention and tree credit worksheet
prepared by an arborist or landscape architect would be reviewed at the time of the land use
application.
6. Fences/Retaining Walls: The applicant would be required to show all existing fencing on the submitted
drawings. If the applicant intends to install any new fences or retaining walls as part of this project, the
location must be designated on the landscape plan or grading plan. A retaining wall that is 4 feet or taller,
as measured by the vertical distance from the bottom of the footing to the finish grade at the top of the
wall requires a building permit. The maximum height of any fence or retaining wall is 72 -inches subject to
further height limitations in setbacks and clear vision areas noted in RMC 4 -4-040D. A fence shall not be
constructed on top of a retaining wall unless the total combined height of the retaining wall and the fence
does not exceed the allowed height of a standalone fence. For more information about fences and
retaining walls refer to RMC 4-4-040.
7. Residential Design and Open Space Standards: Future single-family building permits would be subject
to the RMC 4-2-115, Residential Design and Open Space Standards. Requirements related to garages,
entries, modulation, windows/doors, scale, bulk, and character, roof forms, eaves, architectural
detailing, and materials/color should be reviewed in their entity prior to submitting permit applications.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
11
Compliance with building design requirements would be verified at the time of building permit
review.
8. Access/Parking: Access is proposed via individual driveways off of NE 10th St. Each lot is required to
accommodate off-street parking for a minimum of two (2) vehicles. The maximum width of single loaded
garage driveways shall not exceed nine feet (9’) and double loaded garage driveways shall not exceed 16
feet. Maximum driveway slopes shall not exceed 15 percent; provided, that driveways exceeding eight
percent (8%) shall provide slotted drains at the lower end with positive drainage discharge to restrict
runoff from entering the garage/residence or crossing any public sidewalk. Driveways shall not be closer
than five feet (5’) to any property line except as allowed per RMC 4-4-080I.9, Joint Use Driveways.
Compliance with street access standards for the R-4 zone would be verified at the time of the formal
Short Plat application. Compliance with parking, driveway spacing, safety, and design standards per
RMC 4-4-080 and RMC 4-6-060 would be required at the time of formal application.
9. Critical Areas: According to COR Maps, there are sensitive slopes (slopes greater than 25% up to 40%)
and high erosion hazard areas on the property.
The required study shall demonstrate the following review criteria can be met: (a) The proposal will not
increase the threat of the geological hazard to adjacent or abutting properties beyond pre -development
conditions; and (b) The proposal will not adversely impact other critical areas; and (c) The development
can be safely accommodated on the site. The geotechnical study must meet the requirements set forth in
the City of Renton Critical Areas Regulations, RMC 4-3-050. Per RMC 4-3-050 the City may require an
independent secondary review of any valid geotechnical reports by a qualified specialists selected by the
City, at the applicant’s expense. Based upon the results of a geotechnical report and/or independent
review, conditions of approval for developments may include increased buffers and/or increased
setbacks from buffers. Buffers are established from the top, toe, and sides of slopes. Alter ations to critical
areas buffers is subject to RMC 4-3-050.I. Protected slopes also require a 15-foot building setback beyond
the required buffer.
Geologically hazardous areas are present on the site. Whenever a proposed development requires
a development permit and a geologic hazard is present on the site of the proposed development
geotechnical studies by licensed professionals, such as a geotechnical engineer and/or engineering
geologist, are required.
Wetlands are present on the property. They require the following buffers and additional 15 -foot structure
setback based on a wetland report prepared by a qualified professional:
Critical Area Category or
Type
Critical Area Buffer Width
Structure
Setback
beyond
Buffer
Wetlands
All Other Land Uses:
High Habitat
Function (8-
9 points)
Moderate
Habitat
Function (5-
7 points)
Low Habitat
Function (3-
4 points)
All Other
Scores
15 ft.
Category I –
Bogs & Natural 200 ft.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
12
Heritage
Wetlands
Category I – All
Others
200 ft. 150 ft. 115 ft. 115 ft.
Category II 175 ft. 150 ft. 100 ft. n/a
Category III 125 ft. 100 ft. 75 ft. n/a
Category IV 50 ft. n/a
Alterations to wetland buffers may be permitted through buffer enhancement or buffer width
averaging per RMC 4-3-050I. Wetland buffer widths shall be reduced by no more than 25% of the
buffer requirement. The wetland and its buffer will need to be placed in a tract via the subdivision
and record a permanent and irrevocable covenant running with the land or deed restriction on the
property title of any critical area management tract or tracts created as a condition of a permit. Such
covenant or deed restriction(s) shall prohibit development, alteration, or disturbance within the
tract except for purposes of habitat enhancement as part of an enhancement project which has
received prior written approval from the City, and from any other agency with jurisdiction over such
activity. A covenant running with the land shall be placed on the tract restricting its separate sale.
Each abutting lot owner or the homeowners’ association shall have an undivided interest in the tract.
Honey Creek, a fish bearing season stream (Type F) per COR Maps, is approximately 23 feet (23’) to the
west of the parcel. Type F streams require a minimum buffer of 115 feet with an additional structure
setback from the buffer of 15 feet.
The submitted site plan does not show the location of the stream or its associated buffer. Alterations
to stream buffers may be permitted in the case of degraded stream buffer width with enhancement
or an averaged stream buffer width per RMC 4-3-050I.
Please note a stream study, prepared by a qualified biologist, would need to verify the classification and
delineation of the stream. The city does not have a wetland biologist on staff and may send out stream
studies and wetland reports to a secondary reviewer with all costs to be paid by the applicant.
A stream study is required because of the presence of the Type F stream within 100 feet of the lot. It
is the applicant’s responsibility to determine whether any other critical areas are present on the site
prior to formal land use application. An administrative variance meeting the requirements of RMC 4-
9-250B.1.7 would be required to reduce the buffer widths beyond prescribed allowances in RMC 4-
3-050.
***The City is in the process of updating wetland buffer standards in accordance with new
Department of Ecology guidelines. Wetland buffers are anticipated to increase.***
10. Environmental Review: The project would be subject to Washington State Environmental Policy Act
(SEPA) due to the presence of critical areas onsite, in accordance with RMC 4-9-070H.3. Therefore, an
environmental checklist is a submittal requirement. An environmental determination will be made by the
Renton Environmental Review Committee.
11. Waivers of Submittal Requirements: The submittal checklist is not an exhaustive list of submittal
requirements and may be modified in cases where additional information is required to complete the
review of an application. In addition, non-applicable submittal requirements may be waived. The
applicant should contact the assigned Project Manager if there are any questions regarding
submittal requirements.
12. Permit Requirements: The proposed project would require administrative short plat approval and
Environmental (SEPA) Review. The land use review would include public notice and a two -week public
comment period. The land use permits would be processed within an estimated time frame of 8 weeks.
CityofRenton\Department Folders\Community and Economic Development (CED)\Current Planning\Pre-Applications\2025\PRE25-000020
13
The application fees are as follows: $6,268 Preliminary Short Plat and $1,856.00 Environmental (SEPA)
Review. Each modification request is $299.00. A 5% technology fee added to the total cost of the reviews
would also be assessed at the time of the land use application . All fees are subject to change. Detailed
information regarding the land use permit application submittal requirements can be found on the Short
Plat Submittal Requirements checklist. Other informational applications and handouts can be found on
the City’s Digital Records Library. The City requires electronic plan submittal for all applications. Please
refer to the City’s Electronic File Standards.
A building permit must be obtained to build buildings and structures. A Construction Permit must be
obtained to install utility lines, transportation improvements and undertake work in City rights-of-
ways. Building and Construction Permits are separate permits.
13. Public Information Sign: Public Information Signs are required for a Short Plat application. as classified
by RMC 4-8-080. Public Information Signs are intended to inform the public of potential land development,
specific permits/actions being considered by the City, and to facilitate timely and effective public
participation in the review process. The applicant must follow the specifications provided in the public
information sign handout. The applicant is solely responsible for the construction, installation,
maintenance, removal, and any costs associated with the sign.
14. Impact Fees: In addition to the applicable building and construction fees, impact fees would be required.
Fees change periodically and the fees in effect at the time of building permit issuance would apply. For
informational purposes, the 2025 impact fees are as follows:
• A Transportation Impact Fee assessed at $11,485.67 per each new detached dwelling unit.
• A Parks Impact Fee assessed at $3,276.44 per each new detached dwelling unit.
• A Fire Impact Fee assessed at $421.98 per each new detached dwelling unit.
• A Renton School District Impact Fee assessed at $1,003.00 (plus a 5% processing charge) per each
new detached dwelling unit.
A handout listing all of the City’s Development related fees is available for your review at
https://edocs.rentonwa.gov/Documents/Browse.aspx?id=8217302&dbid=0&repo=CityofRenton
15. Next Steps: When the formal application materials are complete, the applicant shall have the materials
pre-screened prior to submitting the complete application package. Please contact Alex Morganroth,
Principal Planner, at 425-430-7219 or amorganroth@rentonwa.gov to submit prescreen materials and
subsequent land use application.
16. Expiration: Upon approval, the Short Plat is valid for five (5) years with a possible one -year extension (RMC