HomeMy WebLinkAboutConstruction Observation Report 2-22-17 Conduit InspectionCLIENT: City of Renton PROJECT: Highlands Generator Replacement and Radio Equipment Relocation ENGINEER: RH2 Engineering CONTRACTOR: Colvico FOREMAN: Ethan Giles   CREW SIZE EQUIPMENT ON SITE     (3) Contractors Excavator and pipe bending equipment     WORK IN PROGRESS: Installation of conduit in trench between Booster Pump Station and generator pad. WORK COMPLETED: Control Conduits Installed (between radio room or BPS and edge of road or generator pad): C1, C2, C3, C4, C5, C8, C12, C14 Power Conduits Installed (between radio room or BPS and edge of road or generator pad): P1, P9, P21, P22 Power and control conduits installed under generator pad: Fuel line carrier pipe, C9, C11, P1, P4, P5, P18 DISCREPIENCES NOTED: None DISCUSSIONS WITH CONTRACTOR: Contactor discovered a degraded conduit leading into the room below the radio room. See Figure 1 and Figure 2 for reference. ITEMS FOR OFFICE ACTION: CAUSE FOR DISPUTE, CHANGE ORDERS, OR DELAYS: EXTRA WORK IN PROGRESS, EQUIPMENT, AND MATERIALS: OBSERVATIONS BY: Isaac Oquist TIME AT SITE: 8:45 AM – 9:30 PM  WEATHER: Overcast TEMPERATURE: 50 deg F   Figure 1  Figure 2