HomeMy WebLinkAboutConstruction Observation Report 2-22-17 Conduit InspectionCLIENT: City of Renton
PROJECT: Highlands Generator Replacement and Radio Equipment Relocation
ENGINEER: RH2 Engineering
CONTRACTOR: Colvico
FOREMAN: Ethan Giles
CREW SIZE
EQUIPMENT ON SITE
(3) Contractors
Excavator and pipe bending equipment
WORK IN PROGRESS:
Installation of conduit in trench between Booster Pump Station and generator pad.
WORK COMPLETED:
Control Conduits Installed (between radio room or BPS and edge of road or generator pad):
C1, C2, C3, C4, C5, C8, C12, C14
Power Conduits Installed (between radio room or BPS and edge of road or generator pad):
P1, P9, P21, P22
Power and control conduits installed under generator pad:
Fuel line carrier pipe, C9, C11, P1, P4, P5, P18
DISCREPIENCES NOTED:
None
DISCUSSIONS WITH CONTRACTOR:
Contactor discovered a degraded conduit leading into the room below the radio room. See Figure 1 and Figure 2 for reference.
ITEMS FOR OFFICE ACTION:
CAUSE FOR DISPUTE, CHANGE ORDERS, OR DELAYS:
EXTRA WORK IN PROGRESS, EQUIPMENT, AND MATERIALS:
OBSERVATIONS BY: Isaac Oquist
TIME AT SITE: 8:45 AM – 9:30 PM
WEATHER: Overcast
TEMPERATURE: 50 deg F