HomeMy WebLinkAboutConstruction Observation Report 5-4-17 Construction ProgressCLIENT: City of Renton PROJECT: Highlands Generator Replacement and Radio Equipment Relocation ENGINEER: RH2 Engineering CONTRACTOR: Colvico FOREMAN: Ethan Giles   CREW SIZE EQUIPMENT ON SITE     None Excavator     WORK IN PROGRESS: Digging of trench between HH-1 and HH-3. Conduit installation between HH-1 and HH-3. WORK COMPLETED: Generator shelter columns and roof framing installed. Outdoor heat pump unit and disconnect installed on exterior of radio room. DISCREPIENCES NOTED: None DISCUSSIONS WITH CONTRACTOR: None ITEMS FOR OFFICE ACTION: CAUSE FOR DISPUTE, CHANGE ORDERS, OR DELAYS: EXTRA WORK IN PROGRESS, EQUIPMENT, AND MATERIALS: Load bank staged on site OBSERVATIONS BY: Isaac Oquist TIME AT SITE: 2:30 PM – 2:45 PM  WEATHER: Overcast TEMPERATURE: 70 deg F