HomeMy WebLinkAboutConstruction Observation Report 5-4-17 Construction ProgressCLIENT: City of Renton
PROJECT: Highlands Generator Replacement and Radio Equipment Relocation
ENGINEER: RH2 Engineering
CONTRACTOR: Colvico
FOREMAN: Ethan Giles
CREW SIZE
EQUIPMENT ON SITE
None
Excavator
WORK IN PROGRESS:
Digging of trench between HH-1 and HH-3.
Conduit installation between HH-1 and HH-3.
WORK COMPLETED:
Generator shelter columns and roof framing installed.
Outdoor heat pump unit and disconnect installed on exterior of radio room.
DISCREPIENCES NOTED:
None
DISCUSSIONS WITH CONTRACTOR:
None
ITEMS FOR OFFICE ACTION:
CAUSE FOR DISPUTE, CHANGE ORDERS, OR DELAYS:
EXTRA WORK IN PROGRESS, EQUIPMENT, AND MATERIALS:
Load bank staged on site
OBSERVATIONS BY: Isaac Oquist
TIME AT SITE: 2:30 PM – 2:45 PM
WEATHER: Overcast
TEMPERATURE: 70 deg F