HomeMy WebLinkAboutConstruction Observation Report 6-27-17 Construction Progress (2)RH2 ENGINEERING, INC.
CONSTRUCTION OBSERVATION REPORT
DATE: Monday, June 27th, 2017
PAGE 1 OF 1
CLIENT: City of Renton
PROJECT: Highlands Generator Replacement and Radio Equipment Relocation
ENGINEER: RH2 Engineering
CONTRACTOR: Colvico
FOREMAN: Chris Keithley
CREW SIZE EQUIPMENT ON SITE
(2) Contractors
Pipe bending equipment
WORK IN PROGRESS:
Contractor is presently installing conductors inside chlorination building
Conduit and conduit supports are partially installed on elevated reservoir.
Automatic transfer switch is partially installed in booster pump station.
WORK COMPLETED:
Generator shelter receptacles installed.
Generator fuel lines installed in carrier pipe and terminated at fuel tank.
Conduit to fiber optic cabinet.
Transformer installed in chlorination building.
DISCREPIENCES NOTED:
None
DISCUSSIONS WITH CONTRACTOR:
1. The contractor has ordered larger, mogul style, LBs to replace the existing 2” LBs located near the
automatic transfer switch that are part of P1 to provide additional space for its conductors. This should
resolve any concerns the City has with the existing LBs.
2. The contractor was aware of the City’s concern over the fiber optic bending radius requirements and the
existing LBs installed at the radio room. After reviewing and modeling the submitted fiber optic cable
information and the existing LBs, there does not appear to be any issue with using the installed LBs with
the submitted fiber optic cables.
ITEMS FOR OFFICE ACTION:
CAUSE FOR DISPUTE, CHANGE ORDERS, OR DELAYS:
EXTRA WORK IN PROGRESS, EQUIPMENT, AND MATERIALS:
OBSERVATIONS BY: Isaac Oquist TIME AT SITE: 9:30 AM – 10:30 AM
WEATHER: Overcast TEMPERATURE: 65 deg F