HomeMy WebLinkAboutConstruction Observation Report 6-5-17 Construction Progress (2)RH2 ENGINEERING, INC.
CONSTRUCTION OBSERVATION REPORT
DATE: Monday, June 5th, 2017
PAGE 1 OF 2
CLIENT: City of Renton
PROJECT: Highlands Generator Replacement and Radio Equipment Relocation
ENGINEER: RH2 Engineering
CONTRACTOR: Colvico
FOREMAN: Ethan Giles
CREW SIZE EQUIPMENT ON SITE
(3) Contractors
(1) Excavator
WORK IN PROGRESS:
Installing conductors inside generator
Preparing to install fuel line in carrier pipe.
WORK COMPLETED:
Generator shelter light fixtures and conduit in ceiling installed.
Radio room furring and drywall installed.
Sidewalk from generator shelter to radio room installed.
HH-3 installed.
Fuel tank staged on fuel tank pad.
Load bank pad completed with load bank staged on pad.
DISCREPIENCES NOTED:
None
DISCUSSIONS WITH CONTRACTOR:
1. Colvico has been unable to located a supplier that has 8’ arborvitae in stock and plans to install the
largest available (6’-6”) that they are able to purchase. RH2 asked Colvico to submit an RFI to formally
confirm that the change was acceptable.
2. The area between the new sidewalk and the booster pump stations driveway has a strip that needs to be
restored now that the sidewalk is installed. Colvico has discussed with Hector Olvera and agreed that the
strip should be filled with gravel instead of dirt and hydro seed.
ITEMS FOR OFFICE ACTION:
CAUSE FOR DISPUTE, CHANGE ORDERS, OR DELAYS:
EXTRA WORK IN PROGRESS, EQUIPMENT, AND MATERIALS:
Radio room tables and other equipment in radio room awaiting assembly.
Conduits that will be installed on the elevated reservoir access ladder are staged on the ground near the elevated
reservoir.
RH2 ENGINEERING, INC.
CONSTRUCTION OBSERVATION REPORT
DATE: Monday, June 5th, 2017
PAGE 2 OF 2
OBSERVATIONS BY: Isaac Oquist TIME AT SITE: 9:00 AM – 10:00 AM
WEATHER: Sunny TEMPERATURE: 60 deg F