From:Jennifer Cisneros
To:Markwell, Thi
Cc:Clark Close
Subject:RE: City of Renton DNS-M Issuance: Oakesdale Ave SW Stormwater System Project, LUA25-000099, ECF
Date:Monday, June 9, 2025 7:53:00 AM
Attachments:Outlook-5ezkfwwl.pngOutlook-s5bh4cty.pngOutlook-a0hgfnhn.pngOutlook-0q2ffdkw.pngCONSTRUCTION INFORMATION REQUEST.docxCONSTRUCTION INFORMATION REQUEST PDF.pdf
Hi Thi,
Thank you for sharing your comments regarding this project. While there is no open comment
period for this decision, I appreciate you taking the time to provide this information. I will pass
your feedback along to the project manager for consideration.
Best,
JENNY CISNEROS, Planning Technician
City of Renton // Community and Economic Development
Virtual Permit Center // Online Applications and Inspections
office 425-430-6583
NOTICE OF PUBLIC DISCLOSURE: This message complies with Washington State’s Public Records Act – RCW 42.56
From: Markwell, Thi <tmarkwell@kingcounty.gov>
Sent: Friday, June 6, 2025 10:36 AM
To: Jennifer Cisneros <JCisneros@Rentonwa.gov>
Subject: Fw: City of Renton DNS-M Issuance: Oakesdale Ave SW Stormwater System Project, LUA25-
000099, ECF
Good morning,
King County received the notice referenced in the subject line above and has forwarded for
internal review.
Please see below for comments received:
From Construction coordination:
To All Contractors and Agencies performing construction work in Metro Transit Bus
Stops and Roadways:
Contractors or Agencies doing work that impact transit routes or bus stops, must
reach out to this office directly by sending an email to
construction.coord@kingcounty.gov, with the following information:
Construction Request Form (Attached)
All Approved TCPs and permits, (Required)
Please send all pertinent TCPs for this work along with a completed copy of the
attached construction request form.
Notification Guidelines:
Please note that King County Metro requires all contractors and agencies to
follow notification guidelines.
Visit KC Metro System Impacts web site for more details at: Transit System
Impacts - King County, Washington
Your project is not approved until you are notified by the KC Metro
Construction Impacts office in writing.
We will contact you if we require additional information or T-39 No Parking
Signs. The contractor is responsible for providing permitted no-park signage for
the placement of temporary bus stop placement or for the safe movement of
coaches on a planned reroute. No-Parks must be placed 72 hours prior to the
start of work to be enforceable.
Once we receive all required information, your request will be reviewed
and final written approval will be sent via email.
Once approval is received, the contractor may contact the permitting agency as
necessary.
KCM Construction Coordinators will arrange for the coordination of all bus stops
closures and the placement of temporary bus stops if necessary.
More notification lead time will be needed when impacting a KC Metro Layover
and access to Comfort Stations. Station.comfort@kingcounty.gov 206-477-9959
TCPs need to accurately dipict your traffic control and work site set up. This
includes noting the location of impacted bus stops.
Precon, Construction and Site Meetings:
· KCM Construction Coordinators are available to attend meetings.
Please send all meeting invites to construction.coord@kingcounty.gov
Site meetings can be coordinated with Construction Coordinators and
Metro Service Quality Field Supervisors.
Bus Stop Construction and Long-Term Bus Stop Impacts:
If the contractor needs to remove/reinstall bus stop equipment/structures, such
as zone flags, bus stop shelters, benches, and KC garbage cans, our Transit
Route Facilities group will work with you to coordinate this work.They can be
reached at: RFDOTTransitRouteFacilities@kingcounty.gov
If the contractor needs to find information on bus stop specifications, please
contact our Bus Stop Projects group at: busstopprojects@kingcounty.gov
NOTE: All work that will require the construction, removal or installation of bus
stop amenities requires 30 business days notification lead time.
Timely notification allows us to plan, mitigate, and most importantly, notify our
riders and operators of your work.
Single Bus Stop Closures: 5 business days (Not including holidays)
Projects that require multiple bus stop closures: 10 business days (Not
including holidays)
Street Closures that impact transit: 10 business days (Not including
holidays)
Long-term Bus Stop moves that require the closure and relocation of a
layover or access to Metro facilities: 30 business days (Not including
holidays)
See our website for details.
Please download, complete, and return the attached Bus Stop/Route Impact Request
form. If your project has multiple phases, please complete one form for each phase.
Be sure to include all approved TCPs and permits for this impact with your requestform.
Please be sure to reach out to the permitting agency (if applicable) for prior approvalof your project.
We appreciate you working with us so we can help you safely complete your project.
Thank you.
If you have any questions or concerns, please reach out. Thank you
Thi Markwell (She/Her)
Transit Environmental Planner II
Transit Real Estate and Environmental (TREE)P 206-263-2659 tmarkwell@kingcounty.gov
From: Chung, Lawrence <lachung@kingcounty.gov>
Sent: Wednesday, May 28, 2025 9:36 AM
To: Markwell, Thi <tmarkwell@kingcounty.gov>
Subject: OAP: City of Renton DNS-M Issuance: Oakesdale Ave SW Stormwater System Project,
LUA25-000099, ECF
From: Jennifer Cisneros <JCisneros@Rentonwa.gov>
Sent: Tuesday, May 27, 2025 4:18 PM
To: ktsang@muckleshoot.nsn.us; Laura Murphy <Laura.murphy@muckleshoot.nsn.us>;
sepacenter@dnr.wa.gov; Planning@TukwilaWA.gov; Mark Hofman <markh@newcastlewa.gov>;
sepa@pscleanair.org; Ishimaru, Jim <Jim.Ishimaru@kingcounty.gov>; McColloch, Duffy
<McCollD@wsdot.wa.gov>; NSchildmeyer <NSchildmeyer@kentwa.gov>; Madura, Jalaine
<Jalaine.Madura@seattle.gov>; 'katherine.fischer@kingcounty.gov'; SEPA@dahp.wa.gov;
culturalpreservation@duwamishtribe.org; R4Splanning@dfw.wa.gov;
NWS.Compliance@usace.army.mil; KCWTD Other Agency Planning
<KCWTD_otheragencyplanning@kingcounty.gov>; Chung, Lawrence <lachung@kingcounty.gov>
Cc: Clark Close <CClose@Rentonwa.gov>; Muang Saelee <MSaelee@rentonwa.gov>
Subject: City of Renton DNS-M Issuance: Oakesdale Ave SW Stormwater System Project, LUA25-
000099, ECF
[EXTERNAL Email Notice! ] External communication is important to us. Be cautious of phishing attempts. Do not
click or open suspicious links or attachments.
Hello,
Please see linked City of Renton DNS-M issuance and related documents for Oakesdale Ave SWStormwater System Project, LUA25-000099, ECF. You may access them following this link. Youcan also find the ERC Report (Exhibits 1-15) in that same folder.
Best,