May 22, 2025
Yong Qi, Civil Engineer III
City of Renton, Development Engineering
1055 South Grady Way
Renton, WA 98057
RE: Response to First Review Comments
Harmony Ridge Final Plat – Phase 1
File No. LUA25-000103
Our Job No. 22298
Dear Yong:
We have revised the plans and technical documents for the above-referenced project in accordance with
your comment letter dated April 28, 2025. Enclosed are the following documents for your review and
approval:
1. Revised Final Plat Map prepared by Barghausen Consulting Engineers, LLC dated May 22,
2025
2. Updated Title Report prepared by Chicago Title Insurance Company dated April 24, 2025
3. Copy of Document, Rec. No. 5615593 (typo corrected on Sheet 2)
4. Revised Lot Closures prepared by Barghausen Consulting Engineers, LLC dated May 22, 2025
The following outline provides each of your comments in italics exactly as written, along with a narrative
response describing how each comment was addressed:
Sheet 1
Change to SHORT plat
Response: It would be inappropriate to call Phase 1 a short plat because no preliminary short
plat application exists, and no short plat decision has been issued. The Preliminary Plat
decision (see Hearing Examiner decision, Page 2 at Lines 11 – 18) was issued as a Phased
Plat (RMC 4-7-080-K). Phase 1 of the approved Preliminary Plat will segregate the church
parcel from the subdivision Parcel. Phase 2 will be the final subdivision of the subdivision
parcel [Confirmed with Yong Qi, email dated 5/21/2025].
Please provide draft of declaration
Response: An HOA is not proposed for Phase 1 so the note has been removed. Declarations
will be provided for Phase 2 final plat.
Parcel Number: 2023059067
Response: The parcel number has been added to the Plat.
Yong Qi, Civil Engineer III
City of Renton, Development Engineering -2- May 22, 2025
LUA25-000103 / LND20-0659
Response: The file number has been added to the Plat.
plats surveys
Response: Corrected.
Sheet 2
Title Note 14 – Is this Applicant’s fence or encroaching?
Response: The fence encroachment has been noted on the plat. The encroachment will be
resolved with Phase 2.
Title Note 16 – What is Parcel A? Title report may need to be updated post-BLA.
Response: An updated title report is enclosed.
Title Note 17 – Please provide copy of document 5615563
Response: Document 5615593 (typo corrected on Sheet 2) is provided in the updated title
report.
Please update Tract Z if renamed
Response: Tract Z has been renamed Lot B.
Public and private utility easement 10 ft wide to 12-ft wide (adjacent to public ROW’s & Tract)
Response: The variable width has been added.
Temporary Public Easement Restrictions/Provisions
Response: Corrected.
Plat Short Plat, Phase 1
Response: See response above.
Lot B? Shall not be a tract
Response: Tract Z has been renamed Lot B.
ROW dedication fronting the church building and parking lot shall be added here, what if the
future frontage improvement requires more ROW dedication along with construction
Response: Right of way dedication based on city road standards will be dedicated with Phase
2. If additional right of way or temporary construction easements are needed from the church
Yong Qi, Civil Engineer III
City of Renton, Development Engineering -3- May 22, 2025
during construction, it will be the responsibility of developer to negotiate said right of way or
easement from the church.
Provide temporary access easement provision on this sheet
Response: A temporary easement note has been added (Note 3).
Sheet 3
Separate text so all text is legible
Response: Corrected.
Please add monument #
Response: Monument numbers have been added on Sheet 3.
Please ensure/confirm fence is properly shown post-BLA
Response: The fence line on the west boundary is shown correctly post BLA.
Is this applicant’s fence or encroaching? Title note 14.D indicates it is 1’ north of property line
Response: The fence encroachment has been noted on the plan. The encroachment will be
resolved with Phase 2.
Sheet 4
Please show monuments set at property corners and show in legend
Response: Revision completed.
Addresses:
Lot 21: Address to remain 15509 116th Ave SE
Tract Z: Address(es) to be assigned as part of potential future development
If Tract Z is renamed, please update this to new name
Response: Revision completed.
Provide temporary access easement provision on Sheet 2
Response: Sheet Note 3, Sheet 2.
Please ensure/confirm fence is properly shown post-BLA
Response: The fence line on the west boundary is shown correctly post BLA.
Lot B? Shall not be a tract. Potential future development
Yong Qi, Civil Engineer III
City of Renton, Development Engineering -4- May 22, 2025
Response: Tract Z has been renamed Lot B.
Is this applicant’s fence or encroaching? Title note 14.D indicates it is 1’ north of property line
Response: The fence encroachment has been noted on the plan. The encroachment will be
resolved with Phase 2.
We believe that the above responses, together with the enclosed revised plans and technical documents,
address all of the comments in your letter dated April 28, 2025. Please review the enclosed at your earliest
convenience. If you have questions or need additional information, please do not hesitate to contact me at
this office. Thank you.
Respectfully,
Ivana Halvorsen
Senior Planner
IH/mf