Change Order No.25
Contract Title: Park Avenue North Extension
Contractor: Olson Brothers Excavating, Inc.
Contract No.: CAG-22-265
Federal Aid No.: NA
cgJ Ordered by Engineer □Force Account□Proposed by the Contractor (VECP)cgJ Pay Item □Unilateral □Bid Item Price Adjustment
cgJ Lump Sum
Affects DBE Work: [gl No D Yes If yes, must receive concurrence from Local Programs
prior to execution.
Original Contract:
Current Contract:
Estimated Net Change This Order:
New Contract:
Prepared By: /71 . ,;,,,Jt'l ,A _2025.05.29 (_,,flllMH lAJV" -09:05:46-07'00'
Resident Engineer
Reviewed By:
Engineer of Record
Reviewed By:
City of Renton Project Manager
Reviewed By:
City Attorney
Change Order No.
Contract Title:
Contract No.
25
PARK AVE N
CAG-22-265
Date
2025.05.28
17:45:30-07'00'
Date
Date
Date
Amount Working Days
$3,636,341.81 100
$4,122,426.47 230.5
$2,421.14 0
$4,124,847.61 230.5
Design Manager)
Consent By:
Surety (Greater than 25% cost and/or 20%
time increase)
Endorsed By:
Pate· 2025 06-25 1 Q·Q9·58:-07'0Q' Contractor
Executed By:G"°""'"""
Martin Pastucha
888131 FD9884490 City of Renton Public Works
Administrator/ Mayor
Date
Date
6/27/2025 I 9:28 AM
Date
Page 1 of 6
CAG-22-265, CO #25-25
Approved by Cheryl Beyer via email 6/24/2025
Docusign Envelope ID: 07A384C4-7DB4-494B-ABA5-D0DD3A1C0628
Estimated Cost: $2,421.14
Extended Overhead: $ 0
Force Account Time related $ 0
damages per 1-09.6, 6.d.:
Total: $2,421.14
EXTENSION OF TIME: The Time for Completion is extended O Working Days.
AFFECTS DBE WORK: Explain how this Change Order affects DBE work.
NA.
Sections 1-04.4 and 1-04.5 of the 2022 WSDOT / APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
To be attached to Change Order:
� 1-Field Directive/Request for Information Response
� 2-Estimated Change Order Cost
D 3-Plans
D 4-Change Order Quotation
D 5-Project Labor List
D 6-Force Account Equipment Rate Request {DOT Form 422-010 EF)
� 7-Equitable Adjustment Determination
D 8-Additional Working Days Calculation
Change Order No.
Contract Title:
Contract No.
25
PARK AVE N
CAG-22-265
Page 3 of 6
Docusign Envelope ID: 07A384C4-7DB4-494B-ABA5-D0DD3A1C0628
Change Order Cost (Equitable Adjustment)
Project Name:
Contractor:
Contract No:
PARK AVENUE N EXTENSION
Olson Brothers Excavation
CAG-22-265
Federal Aid No:
Construction Manager: Perteet
Item No. Description
Al0l (new) Sidewalk Ponding
LABOR
Laborer ($65/hr for 1 day)
Operator ($88/hr for 1 day)
Flagger ($55/hr for 1 day)
Foreman ($91/hr for 1 day)
Labor Markup (29 % Labor and 2 % Sick Leave )
EQUIPMENT
Highway Truck ($52/hr for foreman)
Excavator ($65/hr for support)
Loader Equipment ($60/hr for support)
Equipment Markup (21 %)
MATERIALS
Materials Markup (21 %)
Lump Sum Estimate
Bid Item Change
Al0l (new) Remove concrete on the NW corner of Park/Logan-4/16/2024
Install drywell for sidewalk ponding issue -4/25/2024
Actual FA Cost= $2421.14
Per attached determination!
Estimated Change Order Cost
Summary of Contractors Quotes:
Item Quote Location
NA NA
Total Quoted Added Cost: $
Quoted Cost
NA
I Overhead
Quantity
5
6
1
2
$1,090.00
2
6
6
$854.00
1
$0.00
1
1
Change Order No. 25
Unit
HR
HR
HR
HR
Percentage
HR
HR
HR
Percentage
LS
Percentage
By: Chris Brown
Date: 12/5/2024
Unit Price
$ 65.00
$ 88.00
$ 55.00
$ 91.00
31.00%
$ 52.00
$ 65.00
$ 60.00
21.00%
21.00%
CALCULATED TOTAL:
ESTIMATED TOTAL:
LS $ 1,401.51
LS $ 1,019.63
TOTAL
By Agreement
Estimated Cost
$325.00
$528.00
$55.00
$182.00
$337.90
$104.00
$390.00
$360.00
$179.34
$0.00
$0.00
$2,461.24
$2,421.14
$1,401.51
$1,019.63
$2,421.14
$0.00
$2,421.14
801 2nd Avenue, Suite 302, Seattle, WA 98104 IP 206.436.0515
Project Name Federal Aid# Contract Na. Date
Park Avenue N. Extension CAG-22-265 2/5/2023
Field Directive No.
Sidewalk Panels 021
Olson Brothers Excavating, Inc
The following is documentation of an oral order given by the Engineer per WSDOT Specification 1-04.4.
The concrete sidewalk panels in the
Project Engineer (or Representative) Date
2/5/2024
Docusign Envelope ID: 07A384C4-7DB4-494B-ABA5-D0DD3A1C0628
#
P"Alb1s:;..-J '_ - - -( -�::·� �� - -
( 1.5 °/o --------------------------
<
,.
Remove a,nd replact.,&idewalk panels to eliminate ponding, provide same joint
locations (blue dashed lines) .
"Drywell" pit filled with CSTC, target depth= 1.5' deep (or max.
feasible), to be covered by topsoil
Match as-built elevation
Xo/o ) Construction slope requirements
Drawn by Brent Powell, PE
4/12/2024