SUMMARY OF PROPOSED CHANGE:
BID
ITEM
NO.
Unit
Type ∆ Qty. Unit Price Total Amount
9 Ton (428) $65.00 -$27,820.00
11 Ton 39 $425.00 $16,575.00
12 Ton 64 $375.00 $24,000.00
Sub Total $12,755.00
Sales Tax (10.3%)$1,313.77
Total $14,068.77
APPROVAL SIGNATURES:
Approved By: Date:
Approved By: Date:
Approved By: Date:
Approved By: Date:
Ronald Straka, Utility Systems Director
Approved By: Date:
Martin Pastucha, PW Administrator
Approved By: Date:
Shane Moloney, Renton City Attorney
CITY OF RENTON
Quantity Adjustment
Bid Item Description
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT CAG#:
CONTRACTOR:
CAG-24-105
Rodarte Construction, Inc
PROJECT NAME:Sanitary Sewer Replacement Phase 1
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the adjusted
quantities as outlined below:
$806,084.29 $780,857.82 $14,068.77
Jared Rodarte, President/Owner, Rodarte Construction, Inc
Jesse Newman, Project Manager
Joe Stowell, Wastewater Utility Engineering Manager
$820,153.06
Decrease Quantity:
Select Import Backfill
CURRENT CONTRACT
AMOUNT
ORIGINAL CONTRACT
AMOUNT
Removing excess quantity due to the use of native backfill instead of
select import backfill.
ESTIMATED NET
CHANGE THIS
ESTIMATED CONTRACT TOTAL AFTER
CHANGE
Additional asphalt quantities to account for the increased overlay
area due to decision to overlay road instead of grind and overlay.
Increase Quantity:
2-Inch Grind and Overlay
Increase Quantity:
Full Depth Hot Mix Asphalt CL. 1/2 in PG 58 H-22
Increase quantity due to the existing thicker asphalt and field
revisions that increased asphalt quantities.
H:\File Sys\WWP - WasteWater\WWP-27-04078 Sanitary Sewer Replacement Project PH1\110 - Construction\Change Orders and Force Accounts\Change Orders\CO 2\Backup\20250611 - CO 2 - SRP Phase 1 1 of 1
CAG-24-105, CO #2-25
Approved by Cheryl Beyer via email 6/20/2025