Loading...
HomeMy WebLinkAbout05 - Spec Provisions For Bid 4-10-2007 SPECIAL PROVISIONS 05 - Spec Provisions For Bid 4-10-2007.doc Page 1 DIVISION 1 GENERAL REQUIREMENTS 1-01 DEFINITIONS AND TERMS 1-01.3 Definitions (APWA Only) Add the following definitions. CITY The City of Renton Substantial Completion Date (APWA Only) The date established by the Contracting Agency or ENGINEER when the contract work is completed to a point that the formal procedures for liquidated damages will no longer be used and liquidated damages thereafter will be assessed on the basis of direct engineering and related cost for overruns of the contract time until the Actual Completion Date. Actual Completion Date (APWA Only) The date established by the ENGINEER as the date that all the work the contract requires is complete. Acceptance Date (APWA Only) The date the Contracting Agency accepts the completed contract and items of work shown in the final estimate 1-02 BID PROCEDURES AND CONDITIONS 1-02.4 Examination of Plans, Specifications, and Site Work 1-02.4(1) General Add the following to the end of Section 1-02.4(1): Locations of existing utilities shown on the Drawings are approximate and some existing utilities may have been omitted. It is the Contractor’s responsibility to verify the locations and elevations of existing pipelines, structures, grades, and utilities prior to construction. The Owner assumes no responsibility for any conclusions or interpretations made by the Contractor or the basis of the information made available. 1-02.5 Proposal Forms Delete the first sentence of this section and replace with the following: 05 - Spec Provisions For Bid 4-10-2007.doc Page 2 The Proposal and associated forms are included in these Contract Documents under Documents Submitted in Sealed Bid Package These forms shall not be altered by the bidder. Reference herein to the Proposal Form(s) shall mean the "Proposal” and "Schedule of Prices.” 1-03 AWARD AND EXECUTION OF CONTRACT 1-03.1(1) Consideration of Bids (additional Section) The contract, if awarded, will be awarded to the lowest, responsive, responsible bidder. 1-03.2 Award of Contract (Supplemental Section) The contract award or bid rejection will occur within 30 calendar days after the bid opening. 1-04 SCOPE OF THE WORK 1-04.12 Hours of Work (Additional Section) General hours of work for the Project shall he limited to the hours of 7:00 a.m. to 5:00 p.m. The Hours of Work may be changed at the discretion of the ENGINEER when it is in the interest of the public or the CONTRACTOR due to reasons of safety, health and welfare and must be approved in writing prior to the start of construction work. The CONTRACTOR shall give a minimum of 48 hours notice to the Contracting Agency prior to work on any roadway and shall do no work on the roadway without a traffic control plan approved by the City Transportation Division. 1-05 CONTROL OF WORK 1-05.4 Conformity with and Deviations from Plans and Stakes (Revised Section) Delete the first sentence of this section and replace with the following: The CONTRACTOR will lay out and set any construction stakes and marks needed to establish the lines, grades, slopes, cross-sections, and curve super-elevations. 1-05.5 Construction Stakes (Revised Section) The CONTRACTOR shall provide all required survey work, including such work as mentioned in Section 1-05.4, 1-05.5, 1-11 and elsewhere in these specifications as being provided by the Engineer. All costs of this survey work shall be included in "Construction Surveying, Staking, As-Builts” per lump sum, as described in Section 1-09.14 Measurement and Payment. 1-05.5(2) Construction Staking (Supplemental Section) The CONTRACTOR shall be responsible for securing the services of a professional land surveyor registered in the State of Washington who shall provide all required survey work, construction staking and as-builting including such work as mentioned in Section 1-05,4, 1-05,5, 1-11 and elsewhere in these specifications as being provided by the Engineer or Contractor. All costs of this survey work shall be included in "Construction Surveying, Staking, As-Builts” per lump sum, as described in the Measurement and Payment section of the special provisions. This staking shall consist of, but not limited to: 05 - Spec Provisions For Bid 4-10-2007.doc Page 3 Utility Construction limits Alignments ant Grade Stakes (w/offsets. 50 max. interval) Valve location, horizontal and vertical bends, air-vacuum release assemblies, manhole location Grading Limits and Grades Monuments (Reference and Restoration) Right-of-Way and Easement Limits Locating and Resetting of Key Landscape Features, Fences, etc. The CONTRACTOR shall supply the CITY with required survey notes and notify the CITY for inspection of the stalking at least two working days in advance of the work taking place The CONTRACTOR shall assume full responsibility for the accuracy of the staking and shall provide all replacement staking or re-staking as needed. The CITY will provide the contractor’s surveyor with the horizontal and vertical control needed to perform the construction surveying. The CONTRACTOR's surveyor shall provide the ENGINEER the original field notes and a set of the field notes which shall contain as-constructed locations of the improvements constructed under this CONTRACT These notes shall contain as a minimum the center line station and offset and cut to each cut stakes and offsets, and all other changes in alignment or grade as may be needed to draw accurate as constructed records of the project. These notes shall be kept legibly, in a format conforming to good engineering practice in a hard covered field book supplied to the CONTRACTOR’s surveyor by the CITY on request. It shall be the CONTRACTOR's responsibility to record the location, by centerline station, offset, and depth below pavement or finish grade of all existing utilities uncovered or crossed during his work as covered under this project. Water and Storm Water Alignment and Grade Stakes (50' max. interval for laser control) (30’ max. interval for batter boards) 1-06 CONTROL OF MATERIAL 1-06.1 Source of Supply and Quality of Materials (Supplemental Section) No source has been provided for any materials necessary for the construction of this improvement. The Contractor shall arrange to obtain the necessary materials at his own expense and all costs of acquiring, producing, and placing this material, in the finished work shall be included in the unit contract prices for the various items involved. If the sources of materials provided by the Contractor necessitate hauling over roads other than City streets, the Contractor shall, at his own cost and expense, make all arrangements for the use of the haul routes. 1-06.7 Shop Drawings and Submittals (Additional Section) 1-06.7(1) General (Additional Section) Shop drawing and submittal review will be limited to general design requirements only and shall not relieve the Contractor from responsibility for errors or omissions, or responsibility for consequences due to deviations from the contract documents. No changes may be made in any submittal after it has been reviewed except with written notice and approval from the Owner. 05 - Spec Provisions For Bid 4-10-2007.doc Page 4 By approving shop drawings, submittals, and samples, the Contractor thereby represents that he has determined and verified all field measurements, field construction criteria, materials, catalog numbers, and similar data, and that he has checked and coordinated each shop drawing with the requirements of the work and of the contract documents. Shop drawing and submittal data for each item shall contain sufficient information on each item to determine if it is in compliance with the contract requirements Owner will pay the costs and provide review services for a first and second review of each submittal item. Additional reviews shall be paid the Contractor by withholding the appropriate amounts from each payment estimate. Shop drawing and submittal items that have been installed in the work but have not been approved through the review process shall be removed and an approved product shall be furnished, all at the Contractor's expense. The Contractor shall review each submittal and provide approval in writing or by stamping with a statement indicating that the submittal has been approved and the Contractor has verified dimensional information, confirmed that specified criteria has been met, and acknowledges that the product, method, or information will function as intended. 1-06.7(2) Required Information (Additional Section) Submit five copies of each submittal to the Engineer. Shop drawings and submittals shall he submitted on 81/2”x11", 11”x17", or 22"x34" sheets and shall contain the following information: 1. Project 2. Contractor 3. Engineer 4. Owner 5. Applicable specification and drawings reference 6. A stamp showing that the Contractor has checked the equipment for conformance with the contract requirements, coordination with other work on the job, and dimensional suitability. 7. A place for the Engineer to place a 3-inch by 4-inch review stamp. 8. Shop or equipment drawings, dimensions, and weights 9. Catalog information 10. Manufacturer’s specifications 11. Special handling instructions 12. Maintenance requirements 13. Wiring and control diagrams 14. List of contract exceptions 15. Other information as required by the Engineer 1-06.7(3) Review Schedule (Additional Section) Shop drawings and submittals will be reviewed as promptly as possible, and transmitted to Contractor not later than 10 working days after receipt the Engineer. The Contractor shall revise and resubmit as necessary to obtain approval. Delays caused by the need for re-submittal may not be a basis for an 05 - Spec Provisions For Bid 4-10-2007.doc Page 5 extension of contract time or delay damages at the discretion of the Owner. At least one set of shop drawings will be returned to the Contractor after review. Additional sets will be returned to the Contractor, if remaining. 1-06.7(4) Substitutions (Additional Section) Any product or construction method that does not meet these specifications will be considered a substitution. Substitutions must he approved prior to their installation or use on this protect. 1-06.7(5) Submittal Requirements (Additional Section) The following submittal items shall be provided to the Engineer by the Contractor and additional submittal information shall be provided to the Engineer by the Contractor if required by the Engineer: Schedule of Values / Schedule Culvert Crossing Plan with Casing Details Traffic Control Plan and haul route Traffic Loop Restoration Plan 5-04 Asphalt Concrete Pavement Materials 7-05 Inlets and Catch Basins 7-06 Concrete Anchor Blocks 7-10.3 Pipe Foundation and Bedding Materials 7-10.3 Backfilling of Trenches 9-30 Ductile Iron Pipe and Fittings 9-30 Gate Valves 9-30 Fire Hydrants, Combination Air-Vac Release Assemblies 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC 1-07.1(1) Archaeological Discoveries and Historic Preservation Clause Addition The Contractor shall adhere to the National Historic Preservation Act of 1960 and 36 CFR 800 which provide for the preservation of potential historical, architectural, archaeological, or cultural resources (herein called “cultural resources") and fair compensation to the Contractor for delays resulting from such cultural resources investigations. In the event that potential cultural resources are discovered during subsurface excavations at the site of construction, the following procedures shall be instituted: 1. The Owner shall issue a Work Suspension Order directing the Contractor to cease all construction operations at the location of such potential cultural resources find. 2. If archaeological findings include human remains, the Engineer shall contact a qualified archaeologist in consultation with the State Historic Preservation Officer (SHPO) to evaluate the remains. 3. Such Work Suspension Order shall be effective until such time as a qualified archaeologist can be called by the Engineer to assess the significance of these potential cultural resources and make recommendations to the State Historical Preservation Officer. If the archaeologist, in consultation with State Historic Preservation, determines that the potential find is a significant cultural resource, the Owner shall extend the duration of the Work Suspension Order. 4. Suspension of work at the location of the find shall not be grounds for any claim by the Contractor unless the suspension extends beyond the contract working days allowed for the project, in which 05 - Spec Provisions For Bid 4-10-2007.doc Page 6 case the Engineer will make an adjustment for increased cost of performance of the contract. 1-07.16 Protection and Restoration of Property (Supplemental Section) Private property such as plants, shrubs, trees, fences, and rockeries within the work area shall be removed and restored to the satisfaction of the property owner. It shall be the CONTRACTOR’s responsibility to notify each property owner when it is necessary to remove such improvements to facilitate the CONTRACTOR's progress, and to remove those improvements to locations requested by the property owner or to restore them to near original location in as near original condition as possible, For the purpose of this contract, all property not within the Right of Way, including property owned by the City of Renton, will be considered private property. All lawn within the area to be disturbed by the CONTRACTOR's operations shall be cut with a sod-cutting machine, removed and disposed. The disturbed lawn area shall be restored with sod after trench is backfilled and compacted. The restoration of the distributed lawn area shall be performed under the following guidelines: A. Topsoil shall be placed at a depth of 3 inches. B. Topsoil shall be tilled to a depth sufficient to key into the subsoil, raked to a smooth even grade without low areas to trap water and compacted, all as approved by the ENGINEER. C. Sod strips shall be placed within 48 hours of being cut. Placement shall be without voids and shall have the end joints staggered. The sod shall be rolled with a smooth roller following placement. D. Barriers shall be erected, with warning signs where necessary, to preclude pedestrian traffic from access to the newly placed lawn during the establishment period. E. The watering schedule of all newly laid sod shall be four times a week for three weeks The watering shall be such duration as to soak the replaced sod thorough' and promote good root growth. F. Such removal, complete restoration and maintenance of the lawn shall be considered incidental to other items of work and no further compensation will be made. The CONTRACTOR shall notify all property owners along the construction area, by mail, prior to the start of construction. Names and addresses of all property owners will be furnished to the CONTRACTING AGENCY. The CONTRACTOR shall further notify each occupancy a minimum of three days prior to construction adjacent to each property. 1-07.16(3)A Protection and Restoration of Existing Markers and Monuments (Additional Section) All existing survey monuments and property corner markers shall be protected from movement or damage by the Contractor. All existing markers and/or monuments that are damaged or removed for construction purposes shall be referenced by survey ties and then replaced by the Contractor. The Contractor shall coordinate work with the City Engineer and City staff to reference the markers and/or monuments and replace them, as required by state law. All existing property corner markers disturbed or removed by the Contractor’s operations shall be replaced at the Contractor's own expense. 1-08 PROSECUTION AND PROGRESS 1-08.1(3) Hours of Work (Revised Section) The first paragraph in this section is replaced with the following three paragraphs: 05 - Spec Provisions For Bid 4-10-2007.doc Page 7 Except in the case of emergency, or unless otherwise stated in the Special Provisions, or indicated in the contract documents, or approved by the Contracting Agency, the normal straight time working hours for the contract shall be any consecutive 8 hour period between 7:00 a.m and 6:00 p.m. of a working day with a maximum 1-hour lunch break and a 5-day work week. The normal allowed working days, or the normal working hour start and stop times may be restricted or may otherwise vary over any portion of the work, as indicated in the special provisions, or other contract documents, or as approved by the Contracting Agency. The normal straight time 8-hour working period, or variations where they are indicated, for the contract shall be established at the preconstruction conference or prior to the Contractor commencing the work. Unless specifically approved in writing by the Owner, no weekend or holiday work will be allowed on, or immediately adjoining the Sam’s Club properties. Holidays shall be defined as shown on the Contract Drawings and any day in which the Owner staff do not normally work a full 8 hour shift. Contractor shall coordinate all work plans with Sam’s Club during the regular construction meetings. Owner reserves the right to modify the working hours as required in order to accommodate special needs, deliveries, or any other reasonable request on behalf of Sam’s Club. The permissible construction times for construction taking place the Benson Road, or SR 515 right-of-way shall be strictly limited as shown on the contract drawings. Unless noted otherwise in the Contract documents, all other work in, or pertaining to the public rights-of-ways shall be as follows; 1-09 MEASUREMENT AND PAYMENT 1-09.14 Payment Schedule (Additional Section) GENERAL 1-09.14( A ) Scope 1. Payment for the various items of the Bid Sheets, as further specified herein, shall include all compensation to be received by the CONTRACTOR f or furnishing all tools, equipment, supplies, and manufactured articles, and for all labor, operations, and incidentals appurtenant to the items of work being described, as necessary to complete the various items of the WORK all in accordance with the requirements of the Contract Documents, including all appurtenances thereto, and including all costs of compliance with the regulations of public regulations of public agencies having jurisdiction, including Safety and Health Administration of the U.S. Department of Labor (OSHA). No separate payment will be made for any item that is not specifically set forth in the Bid Schedules, and all costs therefore shall be included in the prices named in the Bid Schedules for the various appurtenant items of work, 2. The Owner shall not pay for material quantities which exceed the actual measured amount used and approved by the ENGINEER. 1-09.14(B) Bid Items Bid Item 1 – Mobilization & Demobilization (LS) Measurement for mobilization shall be based on the establishment of all site improvements required to begin construction, including: project schedule, and transportation of equipment to the project site, receipt of all bonds and insurance policies, obtaining all required permits, along with any other submittal and shop drawing requirements, provide protection of existing facilities and removal of all materials and equipment from the construction site after project completion. 05 - Spec Provisions For Bid 4-10-2007.doc Page 8 Payment for mobilization will be made at the lump sum amount bid based on the percent of completed work as defined in the 1996 Standard Specifications for Road, Bridge, and Municipal Construction (WSDOT) for mobilization. Such payment will be complete compensation for all mobilization of employees, equipment and materials, preparation of all necessary submittals, bonds, insurance, site improvements, etc. all in conformance with the Contract Documents. Bid Item 2 – Trench Excavation Safety Systems (LS) Measurement for trench excavation safety systems will be based on a percentage defined as the amount of water and storm pipelines installed divided by the total length of water and storm pipe shown to be installed. Payment for trench excavation safety systems will be made at the measured percentage amount for the pay period times the lump sum amount bid, said payment will be complete compensation for all equipment, labor, materials, hauling planning, design, engineering, submittals, furnishing and constructing and removal and disposal of such temporary sheeting, shoring, and bracing complete as required under the provisions of any permits and in the requirements of OSHA and RCW Chapter 49.17, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 3 – Construction Surveying, Staking, and As-Builts (LS) Measurement for construction surveying, staking and as-built information will be based on the percentage of total work complete, by dollar value, at the time of measurement Payment for construction surveying, staking and as-built information will be made at the measured percentage amount for the pay period times the lump sum amount bid, said payment will be complete compensation for all labor, materials, equipment, travel, surveying needed to construct the improvements to the line and grade as shown on the plans, to provide the required construction and as-constructed field (as-built information) notes and drawings, etc. required to complete this item of work in conformance with the Contract Documents. No more than 50% of the bid amount for this item shall be paid prior to the review and acceptance of the as-constructed information by the Engineer. Bid Item 4 – Temporary Erosion/Sedimentation Controls (LS) Measurement for temporary erosion/sediment control(s) will be based on the percentage of total work complete, by dollar value, at the time of measurement. Payment for trench excavation safety systems will be made at the measured percentage amount for the pay period times the lump sum amount bid, said payment shall be complete compensation for all erosion control work specified in the contract documents and plans, and shall include but not be limited to the following: • All catch basic protection, inserts, and all other protective measures. • All filter fabric fences, hay bales, placement of plastic sheets over exposed soil and stockpiles. • All required seeding, mulching, netting, geotextile surface treatments, covers, and anchors. • cleaning catch basins, temporary sediment ponds, etc., and any other activities needed to control erosion from the project. The surface water control requirements of King County shall apply and the King County, Washington, Surface Water Design Manual shall be used for sizing of all facilities. Bid Item 5 – Traffic Control (LS) Measurement for traffic control work will be based on the discrete portion of total work complete, as 05 - Spec Provisions For Bid 4-10-2007.doc Page 9 described by the Traffic Control Plan submittal acceptance and initial sign installation, the SR515 portion, and Sam’s Club portion, at the time of measurement. Payment for all submittals and initial signage, all traffic control work in SR 515, and all traffic control work within and adjoining Sam’s Club will be made as follows: • Upon acceptance of the Traffic Control Plan Submittal and initial signage installation, 30 percent times the lump sum amount bid, • Upon completion of all Traffic Control work within SR 515 rights-of-way, 35 percent times the lump sum amount bid, • Upon completion of all Traffic Control work within and adjoining the Sam’s Club Parking lots area, 35 percent times the lump sum amount bid; Said payment will be complete compensation for all submittals, permits, coordination, labor, materials, equipment, property owner notification of project work prepare and conform to the approved Traffic Control Plan, provide for public convenience and safety, detours, flagging, barricades, sequential arrow boards, signs, traffic control devices, temporary striping, cleanup, etc, required to complete this item of work in conformance with the Contract Documents. The signs will become property of the Contractor at the end of the contract. No separate pay item is provided for the project signs and the cost for construction and placing the signs will be included in the Lump Sum price for Traffic Control. Bid Item 6 – Existing CMP Culvert Crossing (LS) Measurement for furnishing and installing the special crossing complete with all appurtenances in conformance with the Contract Documents. Payment for furnishing and installing the culvert crossing shall be lump sum and shall be full compensation to complete the installation of the casing, insulators, spacers, end seals, CDF backfill, restoration, and all appurtenances required for a complete and functional installation. Payment shall also be full compensation for all initial excavations, and investigations in order to assess the condition of the existing storm drain culvert. Bid Item 6a – Existing Culvert Repair Contingency (LS) Measurement for existing culvert repair and all appurtenances shall be per lump sum. Repair shall include all labor, equipment, materials, materials hauling, finishing, restoration, cleanup, etc. required for a compete and functional repair to the existing culvert unless otherwise approved the ENGINEER. Any initial investigations as required to determine the actual conditions, dimensions, and extents of any possible repairs shall be considered as incidental to the cost of the work and shall not be considered as part of this Bid Item. The decision to exercise the culvert repair contingency and perform any actual repair shall be at the sole discretion of the Owner. Payment for actual culvert repairs installed shall be per lump sum, which payment will be complete compensation for all labor, equipment, materials, materials hauling, finishing, restoration, cleanup, etc. required for a compete and functional repair. Bid Item 6b – Benson Road Future I-405 Retaining Wall Casing Installation (LS) Measurement for furnishing and installing the Benson Road future I-405 retaining wall casing complete with all appurtenances in conformance with the Contract Documents. Payment for furnishing and installing the Benson Road future I-405 retaining wall casing shall be lump sum and shall be full compensation to complete the installation of the casing, insulators, spacers, end seals, restoration, and all appurtenances required for a complete and functional installation. Payment 05 - Spec Provisions For Bid 4-10-2007.doc Page 10 shall also be full compensation for the trench cut-off walls, drainage, and tie-in and restoration of all existing drainage features adjacent to the casing work. Bid Item 7 – Class 52, 16 inch, Ductile Iron Push-On Water Pipe with Poly-Wrap and Appurtenances – Complete (LF) Measurement for furnishing and installing all water pipes, fittings, couplers, devices, and appurtenances, of the size, type and class specified, for a complete and functional system, will be based on the actual lineal footage measured horizontally over the centerline of the installed pipe. Payment for furnishing and installing water pipes and fittings of the size, type and class specified will be made at the measured quantity put in place that pay period times the unit amount bid, and shall cover the complete cost of providing all labor, materials, and equipment required to complete the work specified in the contract documents and plans including but not limited to the following: • Locating existing utilities and all potholing, investigation, and coordination in advance to determine the horizontal and vertical location of all existing utilities, including but not limited to, fiber optic cables, power, communications, water, storm, sewer, and any other utilities whether on public rights-of-way, or private commercial properties. • Saw cutting, trench excavation, and removal, hauling, and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material. • Stockpiling suitable excavated material for use as pipe bedding and trench backfill. • Furnishing, installing, laying and jointing water pipes and fittings of the size, type and class shown, polyethylene encasement, special fittings, horizontal and vertical bends, vertical crosses for poly - pigging, shackle rods, temporary blow-off assemblies, and all incidentals and appurtenances associated with the pipe installation. • Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans. • Placing and compacting trench backfill. • Testing, poly-pigging, disinfecting and flushing of water mains. • Replacing, protecting and/or maintaining existing utilities. • The complete cost to provide all other miscellaneous work items not specifically identified elsewhere within the measurement and payment section 1-09, including all labor, equipment, materials, subcontractor, and coordination costs for a complete and functional project. Bid Item 7a – Class 52, 16 inch, Ductile Iron Restrained Joint Water Pipe with Poly-Wrap and Appurtenances – Complete (LF) Measurement for furnishing and installing all restrained joint water piping, and appurtenances, of the size, type and class specified, for a complete and functional system, will be based on the actual lineal footage measured horizontally over the centerline of the installed pipe. Payment for furnishing and installing all restrained joint water piping, and appurtenances, of the size, type and class specified, will be made at the measured quantity put in place that pay period times the unit amount bid, and shall cover the complete cost of providing all labor, materials, and equipment required to complete the work specified in the contract documents and plans. Bid Item 7b – Class 52, 6 inch, Ductile Iron Push-On Water Pipe with Poly-Wrap and Appurtenances – Complete (LF) Measurement for furnishing and installing all water pipes, fittings, couplers, devices, and appurtenances, 05 - Spec Provisions For Bid 4-10-2007.doc Page 11 of the size, type and class specified, for a complete and functional system, will be based on the actual lineal footage measured horizontally over the centerline of the installed pipe. Payment for furnishing and installing all restrained joint water piping, and appurtenances, of the size, type and class specified, will be made at the measured quantity put in place that pay period times the unit amount bid, and shall cover the complete cost of providing all labor, materials, and equipment required to complete the work specified in the contract documents and plans. Bid Item 8 – Gate Valve Assembly 16 Inch (EA) Measurement for furnishing and installing 16 inch gate valve assemblies will be per each for each gate valve assembly installed in conformance with the Standard Plans, Contract Specifications and Details. Payment for furnishing and installing gate valve assemblies of the size and type specified shall will be made at the measured quantity put in place that pay period times the unit amount bid, and shall cover the complete cost of providing all labor, materials, equipment and all incidental work necessary to complete the work specified in the contract documents and plans, and shall include but not be limited to the following: • Locating existing utilities and potholing in advance to determine their horizontal and vertical location • Saw cutting, trench excavation, and removal, hauling, and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material. • Provide all valve boxes, risers, extensions, raise to finish grade, and provide collar or pavement patch, seal, and match to finish pavement grade complete. • Stockpiling suitable excavated material for use as pipe bedding and trench backfill. • Furnishing, installing valves of the size and type shown, valve boxes and cover, stem extensions, valve location marker, shackle rods, polyethylene encasement, adjustment to finished grade, and all incidentals • Placing and compacting of bedding materials • Placing and compacting trench backfill • Replacing, protecting and/or maintaining existing utilities Bid Item 8a – Gate Valve Assembly 12 Inch (EA) Measurement for furnishing and installing gate valve assemblies as noted above in Item 8, except that the size and type specified shall be for all 12 inch gate valves. Payment for furnishing and installing gate valve assemblies of the size and type specified will be made at the measured quantity put in place that pay period times the unit amount bid and shall cover the complete cost of providing all labor, materials, equipment and all incidental work necessary to complete the work specified in the contract documents and plans. Bid Item 8b – Gate Valve Assembly 6-Inch (EA) Measurement for furnishing and installing gate valve assemblies as noted above in Item 8, except that the size and type specified shall be for all 6 inch gate valves. 05 - Spec Provisions For Bid 4-10-2007.doc Page 12 Payment for furnishing and installing gate valve assemblies of the size and type specified will be made at the measured quantity put in place that pay period times the unit amount bid and shall cover the complete cost of providing all labor, materials, equipment and all incidental work necessary to complete the work specified in the contract documents and plans. Bid Item 9 – Fire Hydrant Assembly (EA) Measurement for furnishing and installing fire hydrant assembly shall be per each, including tees, fittings, blocking, and appurtenances for a complete and functional system. Payment for furnishing and installing fire hydrant assemblies of the size and type specified will be made at the measured quantity put in place that pay period times the unit amount bid and shall cover the complete cost of providing all labor, materials, equipment and all incidental work necessary to complete the work specified in the contract documents and plans including, but not limited to the following: • Locating existing utilities and all potholing, investigation, and coordination in advance to determine the horizontal and vertical location of all existing utilities, including but not limited to, fiber optic cables, power, communications, water, storm, sewer, and any other utilities whether on public rights-of-way, or private commercial properties. • Saw cutting, trench excavation, and removal, hauling, and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material. • Stockpiling suitable excavated material for use as pipe bedding and trench backfill. • Furnishing, installing, laying and jointing water pipes and fittings of the size, type and class specified, polyethylene encasement, special fittings, horizontal and vertical bends, shackle rods, and all incidentals and appurtenances associated with the installation. • Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans. • Placing and compacting trench backfill. Bid Item 10 – Connection to Existing Water Mains (EA) Measurement for connections to existing mains will be per each for each connection to an existing main in conformance with the Contract Documents. Payment for connections to existing main will be made at the measured quantity put in place that pay period times the unit amount bid and shall cover the complete cost of providing all labor, materials equipment to complete the final connection and all work specified in the contract documents and plans and shall include but not be limited to the following: • Locating existing utilities and water mains and potholing in advance to determine their horizontal and vertical location. • Saw cutting, trench excavation, and removal, hauling, and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material. • Stockpiling suitable excavated material for use as pipe bedding and trench backfill. • Installation of concrete dead-man blocks around existing water mains in advance of the final connections. • Furnishing, installing, laying and jointing water pipes, fittings, and all necessary couplings of the size, type and class shown, polyethylene encasement, special fittings, horizontal and vertical bends, shackle rods, removal of temporary blow-off assemblies, disinfecting the pipes and fittings and all incidentals to complete the connection according to the contract plans and specifications. 05 - Spec Provisions For Bid 4-10-2007.doc Page 13 • Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans. • Placing and compacting trench backfill. • Replacing, protecting and/or maintaining existing utilities. Bid Item 11 – Concrete for Thrust Blocking, Dead-Man Anchor Blocks (CY) Measurement for concrete for thrust blocking, dead-mar, anchor blocks will be per cubic yard for all concrete installed for thrust blocking and dead-mar, anchor bolts in conformance with the Contract Documents. Payment for furnishing and installing concrete for thrust blocking, dead-man anchor blocks will be made at the measured quantity put in place that pay period times the unit amount bid and shall cover the complete cost of providing all labor, materials, equipment, excavation, haul dispose of waste, dewatering, concrete vertical and horizontal blocks, dead-man anchor bolts, reinforcing steel, shackle rods, clamp assembly, anchor bolts, and necessary form work. Concrete material weights shall be verified by providing a copy of certified truck tickets, which will accompany each load. Bid Item 12 – Removal of Unsuitable and Excess Spoils Material (TON) Measurement for removal of unsuitable and excess spoils material shall be measured in Tons based on the weight of material removed. Replacement of foundation material will be measured only for the areas authorized by the ENGINEER. Certified weight tickets shall accompany each load. A copy of tickets shall be given to the Owner’s Representative daily. Wasted materials will not be included in the measurement or payment. Payment for removal of unsuitable and excess spoils material will be made at the measured quantity for that pay period times the unit amount bid and shall be complete compensation for all, labor, materials, equipment, excavation, hauling, and disposal fees of waste material, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 13 – Select Imported Trench Backfill (TON) Measurement for select imported trench backfill, shall be measured in Tons based on the weight of material installed into the work. Certified weight tickets shall accompany each load. A copy of tickets shall be given to the ENGINEER daily. Wasted materials will not be included in the measurement or payment. Only materials placed within the pay limits shown will be considered for payment. Material placed outside of the pay limits shown on the plans or as approves by the ENGINEER will be deducted from the certified tickets. Payment for select imported trench backfill will be made at the measured quantity put in place that pay period times the unit amount bid and shall be complete compensation for all labor, materials, equipment, hauling, placement, water, compaction, removal and disposal of waste materials, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 13a – Gravel Backfill for Pipe Zone Bedding (TON) Measurement for gravel backfill for pipe zone bedding, shall be measured in Tons based on the weight of material installed into the work. Certified weight tickets shall accompany each load. A copy of tickets shall be given to the ENGINEER daily. Wasted materials will not be included in the measurement or payment. Only materials placed within the pay limits shown will be considered for payment. Material placed outside of the pay limits shown on the plans or as approves by the ENGINEER will be deducted from the certified tickets. Payment for gravel backfill for pipe zone bedding will be made at the measured quantity put in place that 05 - Spec Provisions For Bid 4-10-2007.doc Page 14 pay period times the unit amount bid and shall be complete compensation for all labor, materials, equipment, hauling, placement, water, compaction, removal and disposal of waste materials, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 14 – Crushed Surfacing Base Course (CSBC) (TON) Measurement for Crushed Surfacing Base Course (CSBC) backfill shall be measured in Ton based on the weight of material installed into the work. Certified weight tickets shall accompany each load. A copy of tickets shall be given to the ENGINEER. Wasted materials will not be included in the measurement or payment. Only materials placed within the pay limits shown will be considered for payment. Material placed outside of the pay limits shown on the plans or as approved by the ENGINEER will be deducted from the certified tickets. Payment for Crushed Surfacing Base Course (CSBC) backfill will be made at the measured quantity put in place that pay period times the unit amount bid and shall be complete compensation for all labor, materials, equipment, hauling, placement, water, compaction, removal and disposal of waste materials, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 14a – Crushed Surfacing Top Course (CSTC) (TON) Measurement for Crushed Surfacing Top Course (CSTC) backfill shall be measured in Ton based on the weight of material installed into the work. Certified weight tickets shall accompany each load. A copy of tickets shall be given to the ENGINEER. Wasted materials will not be included in the measurement or payment. Only materials placed within the pay limits shown will be considered for payment. Material placed outside of the pay limits shown on the plans or as approved by the ENGINEER will be deducted from the certified tickets. Payment for Crushed Surfacing Top Course (CSTC) backfill will be made at the measured quantity put in place that pay period times the unit amount bid and shall be complete compensation for all labor, materials, equipment, hauling, placement, water, compaction, removal and disposal of waste materials, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 15 – Temporary Asphalt Patch Class ‘1/2 Inch PG70’ Asphalt Concrete Pavement (TON) Measurement for asphalt concrete patch shall be per ton. Pavement repair measurement width shall be as defined by the limit of trench patch payment shown in the Contract Documents, unless otherwise approved the ENGINEER. Payment for asphalt concrete patch will be made at the measured quantity put in place that pay period times the unit amount bid and shall be complete compensation for all labor, materials, and equipment for: • Furnishing, placing, and compacting asphalt concrete pavement (ACP) • Furnishing, placing and compacting incidental ACP for pavement repair, dikes, berms, and wedge curbing • Furnishing, placing and compacting pre-leveling, leveling and wearing courses • Feathering pavement and • Furnishing and applying tack coat and crack sealing asphalt • Furnishing and installing and removing temporary asphalt concrete pavement (cold-mix) • Pavement saw cutting • No separate payment will be made for the installation and removal of the temporary asphalt patch, class B, or ACP for trench patch. 05 - Spec Provisions For Bid 4-10-2007.doc Page 15 • No additional payment will be made for work necessary to correct ACP not installed in accordance with specifications. Bid Item 16 – Asphalt Concrete Paving Class ‘1/2 Inch PG70’ (TON) Measurement for asphalt concrete overlay shall be per ton. Pavement repair measurement width shall be as defined by the limit of overlay shown in the Contract Documents, unless otherwise approved the ENGINEER. Payment for asphalt concrete Overlay will be made at the measured quantity put in place that pay period times the unit amount bid and shall be complete compensation for all labor, materials, and equipment. • All grinding, feathering, sweeping, cleaning and prep existing pavement to match existing grade at all seams, joints, catch basins, and other match points • Furnishing and applying tack coat and crack sealing asphalt • Furnishing, placing and compacting pre-leveling, leveling and wearing courses • Furnishing, placing, and compacting asphalt concrete pavement (ACP) • Furnishing, placing and compacting incidental ACP for pavement repair, dikes, berms, and wedge curbing • Pavement saw cutting, • No separate payment will be made for the installation and removal of the temporary asphalt patch, class B, or ACP for trench patch, • No additional payment will be made for rework necessary to correct ACP not installed in accordance with specifications. Bid Item 17 – Restore Traffic Detection Loop System (LS) Measurement for the restoration of the traffic detection loops and all appurtenances shall be per lump sum. Payment repair measurement width shall be as defined by the limit of restoration shown in the Contract Documents, unless otherwise approved the ENGINEER. Payment for the restoration of the traffic detection loops and all appurtenances shall be per lump sum, which payment will be complete compensation for all labor, materials, equipment, testing, removal and disposal of waste materials, etc. required for a complete and functional system, to complete this item of work in conformance with the Contract Documents. Bid Item 18 – Restore, Replace Lane Channelization, Crosswalks, Stripping, and All Temporary and Miscellaneous Pavement Markings (LS) Measurement for the restoration of the lane channelization, crosswalks, stripping, and all appurtenances shall be per lump sum. Pavement repair measurement width shall be as defined by the limit of restoration shown in the Contract Documents, unless otherwise approved the ENGINEER. Payment for the restoration of the lane channelization, crosswalks, stripping, and all appurtenances shall be per lump sum, and payment will be complete compensation for all labor, materials, equipment, removal and disposal of waste materials, etc. required to complete this item of work in conformance with the Contract Documents. Bid Item 19 – Remove and Replace Sidewalk and Driveway (SY) Measurement for replacement of sidewalk and driveways shall be in square yards of sidewalk and 05 - Spec Provisions For Bid 4-10-2007.doc Page 16 driveway repair for installation of utilities as shown in construction documents, unless otherwise approved the ENGINEER. Payment for removal and replacement of sidewalks and driveways will be made at the measured quantity put in place that pay period times the unit amount bid and shall be complete compensation for all labor, equipment, materials, hauling, preparation, forming, placement, finishing, cleanup, etc. required to compete this item in conformance with the Contract Documents. Bid Item 20 – Remove and Restore In-Kind Curbing, Lawn, Landscaping (LS) Measurement for landscape restoration shall be per lump sum of landscape restored as required to compete this item in conformance with Contract Documents. Payment for landscape restoration shall be per lump sum, which payment will be complete compensation for all labor, equipment, materials, materials hauling, sod, topsoil, trees, shrubs, rockeries in Lind, fencing, mail box placement, preparation, forming, placement, finishing, watering, cleanup, etc required to compete this item in conformance with the Contract Documents. This item includes construction and restoration of all ditches and swales for surface water runoff control encountered during construction activities and is considered incidental to this pay item. Bid Item 21 – Excavation Dewatering (LS) Measurement for excavation dewatering and all appurtenances shall be per lump sum. Dewatering shall include all temporary measures required to complete the contract scope of work, including, but not limited to all sump pumps, lines, settling tanks, or ponds, and all appurtenances that may be required. The limits of dewatering and excavation ground water control shall extend throughout the construction limits of the work, unless otherwise approved the ENGINEER. Payment for excavation dewatering will be made at the measured percentage amount for the pay period times the lump sum amount bid, which payment will be complete compensation for all labor, equipment, materials, hauling, preparation, forming, placement, finishing, cleanup, etc. required to compete this item in conformance with the Contract Documents. Bid Item 22 –SR 515 Storm Water Drainage Modification (LS) Measurement for all storm water drainage modifications and all appurtenances shall be per lump sum as required to compete this item in conformance with Contract Documents. Payment for storm water drainage modifications will be made at the lump sum amount bid, which payment will be complete compensation for all labor, equipment, materials, hauling, preparation, forming, placement, finishing, cleanup, etc. including utilities locating and protection, saw-cutting, excavation, catch basins, rims, grates, piping, and restoration. 05 - Spec Provisions For Bid 4-10-2007.doc Page 17 1-10 TEMPORARY TRAFFIC CONTROL 1-10.1 GENERAL 1-10.1 General (Additional Section) This Section is expanded by inserting the following paragraph at the beginning of the section: The Contractor shall be completely responsible for all traffic control associated with the work within, on, and adjoining all public rights-of-way, and the Sam’s Club properties, including all planning, submittals, permitting, coordination with Owner agencies, flaggers, signage, lane control, markers, barriers, labor, equipment, materials, and all other incidentals, required for the completion of the work. 1-10.2(2) Traffic Control Plans (Added Sections) This Section is expanded with the following: 1. The Contractor shall submit a Traffic Control Plan for approval by the Engineer prior to the start of any work within, or adjoining, any public right-of-way or the Sam’s Club properties. The Traffic Control Plan shall be coordinated with all Right-of-Way Use Permits and any other required permits. The Traffic Control Plan shall indicate the name(s) and contact number(s) for all responsible persons, the location and details for all signage, channeling devices, equipment and vehicle staging locations, and all other details required for a complete and functional Traffic Control Plan. 2. The drawings shown in the Supplemental Specifications, the Special Provisions, the contract plans, and elsewhere in the contract documents are generic in nature and are for the Contractor’s benefit in determining the concept, scope and level of detail required in preparing a detailed and comprehensive Traffic Control Plan. 3. All Traffic Control Plans shall be prepared, enforced, and administered by Contractor consistent with the WSDOT Standard Specifications Section 1-10.2, and shall conform to the standards established in the “Manual on Uniform Traffic Control Devices” (MUTCD) latest edition, and the WSDOT Standard Specifications Section1-10.3. 1-10.3(3) Construction Signs (Added Sections) Add the following to the first paragraph: The Contractor shall also provide and maintain all flaggers, warning vehicles, barricades, and any other safety equipment and personnel required in accordance with the approved Traffic Control Plan, and any associated permits through the duration of the work. 1-10.3(6) One Way Piloted Traffic Control Through The Construction Zone (Replaced Section) Delete this Section and replace it with the following: 1-10.3(6) Traffic Control Through The Construction Zone SR 515 and Benson Road rights-of-way (ROW) - The Contractor shall comply with all Construction Work Restrictions and observe the work hour, and work day restrictions indicated on the plans and permits. Unless otherwise approved in writing by the Owner, the Contractor shall maintain traffic in both directions, at all times, on all days, in the ROW. The Contractor may close one (or two lanes on an occasional basis) maximum, during the hours and locations indicated on the Contract plans. The Contractor shall observe the work hour restrictions indicated on the plans and permits. Contractor shall maintain lane openings and traffic directions required on the Contract plans and permits. 05 - Spec Provisions For Bid 4-10-2007.doc Page 18 Sam’s Club Parking Lots and Adjoining areas – The Contractor shall comply with all Construction Work Restrictions and observe the work hour, and work day restrictions indicated on the plans and permits. The Contractor shall coordinate all activities with Sam’s Club and the Owner. The Contractor may isolate only those portions of the Sam’s Club Parking lots indicated on the Contract plans for the Contractor’s use in performing the work. All traffic shall be safely protected from all construction activities. Contractor shall maintain traffic flow as required on the Contract plans and permits. The Contractor shall not stage equipment, store materials, or otherwise make use of any portion of the Sam’s Club property that is outside of the construction limits, or easements, indicated on the Contract plans. The Contractor shall be solely responsible for the protection of the work, public vehicular and pedestrian traffic, the protection of Sam’s Club employees, delivery vehicles, and utilities, near or adjoining the work, regardless of Owner’s approval of any Traffic Control Plan, submittals, permits, or revisions thereof. The Contractor shall be completely liable for, and shall hold Owner harmless from, any damages, injuries, or loss suffered from Contractor’s operations or negligence associated therewith. 1-10.4 Measurement (Revised Section) Delete the first sentence and replace it with the following: Measurement for Traffic Control shall be per 1-09.14(B) Bid Items, Bid Item 5 – Traffic Control, as described herein. 1-10.5 Payment (Revised Section) Delete the third paragraph, including items 1 and 2 (lines 11 through 17) and replace them with the following: Payment for Traffic Control shall be per 1-09.14(B) Bid Items, Bid Item 5 – Traffic Control, as described herein. 05 - Spec Provisions For Bid 4-10-2007.doc Page 19 DIVISION 2 EARTHWORK 2-01 CLEARING, GRUBBING AND ROADSIDE CLEANUP 2-01.1 Description Delete the first paragraph of this section and replace with the following: The Contractor shall clear, grub, and cleanup those areas shown on the Contract Plans which are required for the execution of construction activities. Trees and scrubs may be removed after approval by the City. 2-01.2 Disposal of Usable Material and Debris Delete the third paragraph of this section and replace with the following: Refuse and debris shall be hauled to a waste site secured by the Contractor and shall be disposed of in such manner as to meet all requirements of state, county and municipal regulations regarding health, safety and public welfare. 2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS 2-02.1 Description Supplement this section with the following: The work shall consist of necessary removal and disposal of existing improvements, including pavements, concrete road structures, manholes, abandoned piping, and other items necessary for the completion of the project. All removal will be considered incidental to the work unless specifically identified as a bid item. 2-02.3 Construction Details 2-02.3(1) General Requirements Supplement this section with the following: The removal shall be conducted in such a manner as not to damage existing utilities, roadway, and other structures that are to remain in place. The Contractor shall repair, replace, or otherwise restore damage resulting from his activities. The limits of removal for concrete or rigid materials shall be either the edge of the structure, an existing construction joint, or a new saw cut. The depth of saw cuts shall be such as will accomplish the intended purpose and will be determined in the field to the satisfaction of the ENGINEER. Sawing shall be considered incidental to the other bid items. 05 - Spec Provisions For Bid 4-10-2007.doc Page 20 2-112.3(1) A Salvage (New Section) Unless otherwise indicated in the Plans or Specifications, all removed items of recoverable value shall be carefully salvaged and delivered to the City in good condition, and as directed by the City. Materials and items deemed of no value by the City shall be removed by the Contractor, and shall become the Contractor's property to be disposed of at no additional cost to the City. 2-02.3(7) D Contractor Provided Disposal Site (Addition) Waste materials shall be hauled to a waste site secured by the Contractor and shall be disposed of in such a manner as to meet all requirements of state, county and municipal regulations regarding safety and public welfare. 2-02.5 Payment Delete entire section and replace with the following: See bid items descriptions for units of measure and payment. 05 - Spec Provisions For Bid 4-10-2007.doc Page 21 DIVISION 5 SURFACE TREATMENTS AND PAVEMENTS 5-O4 ASPHALT CONCRETE PAVEMENT 5-04.3 Construction Requirements 5-04.3(2) Hauling Equipment Add the following to the first paragraph: If truck has not used canvas to protect asphalt from weather during haul the Engineer, or its representative, reserves the right to reject the load. Rejection of load due to non-protection will not be basis for any compensation. 5-04.3(5) Conditioning the Existing Surface The Contractor shall maintain existing surface contour during patching, unless instructed by City Engineer. 5-04.3(5) Preparation of Existing Surface The Contractor shall provide his own mechanical sweeping equipment. The sweeper will be on the project prior to the start of paving, to insure the streets to be paved are clean before the tack coat is applied. The sweeper will keep the streets clean ahead of the paving machine and clear, the streets behind the empty trucks that have dumped their loads into the paving machine. The sweeper must sweep all streets made dirty by the CONTRACTOR’s equipment. If the paving machine is “walked" from one site to another, the sweeper must sweep up behind paving machine. The sweeper shall not leave the overlay site until given permission by the City’s inspector. All utilities shall be painted with a biodegradable "soap” to prevent the tack and ACP from sticking to the lids. Diesel will not be used. After the application of soap, catch basins must be covered to prevent tack and ACP from getting into catch basins. Preparation of existing surface shall be done as outlined in this section and a tack coat shall be applied at the rate of 0.02 to 0.0S gallons per square yard. Payment for preparation of the surface and application of the tack coat shall be considered incidental to the paving and no separate payment shall be made. The Contractor shall locate all utilities for access immediately after any paving and mark the location by means of painting a circle around the location and scooping a monitor of asphalt 4”-6” in diameter and the depth of the overlay from the center of the utility location. The Contractor shall locate and completely expose gas and water valves for access immediately after final rolling. During the adjustment of any utility, existing concrete bricks or grouting material that has been broken or cracked shall be removed and replaced at the CONTRACTOR’s expense. 05 - Spec Provisions For Bid 4-10-2007.doc Page 22 Utility adjustments must be completed within 15 working days after overlay is complete, and within the specified working days. Payment for utility adjustments includes all labor, materials, tools and equipment necessary to complete the adjustments and is incidental to pay item for Asphalt Patch (1-09.14(AF)). 5-04.3(9) Spreading and Finishing Supplement this section with the following: Asphalt Concrete Pavement (ACP) 1/2 Inch PG 70 ACP shall be placed the compacted depths specified herein, equal to existing ACP thickness for restored ACP, or as shown on the Contract Plans and City of Renton Standard Plan H032 as leveling and wearing course. Asphalt over 3 inches in compacted depth shall be placed in two equal lifts. Placement shall be in accordance with applicable provisions of Section 5-O4. 5-04.5 Payment See bid items descriptions for units of measure and payment, 5-04.6( 2) Traffic Control Notifications The Contractor shall be responsible for delivering notification twice to all properties that front on, or access from, any street or, which the asphalt concrete is to be applied. The first notification shall be made approximately one week prior to the day the work is scheduled to begin on the street and the second shall be made twenty-four hours (24 hours) prior to beginning work. On streets to be overlaid, the Contractor shall post "No Parking” signs a minimum of 72 hours in advance of the work taking place. The signs shall specify the date and hours that the parking restrictions will be in effect. The Contractor shall obtain prior approval for the parking restrictions from the City of Renton Department of Public Works Transportation Systems Division. The Contractor shall be responsible for coordinating with the City's inspector and/or Police Department if the need arises to tow any vehicles violating a posted "No Parking” sign. However, the Contractor shall first make effort to contact the vehicle owner if it is likely the owner is in the area. The Contractor shall provide and use sufficient traffic control equipment and trained personnel at all times in accordance with Section 1-10. 5-06 TEMPORARY RESTORATION IN PAVEMENT AREAS (ADDITIONAL SECTION) 5-06.1 Description (Additional Section) Pavement areas that have been removed by construction activities must be restored by the Contractor prior to the end of each working period, prior to use by vehicular traffic. Within paved streets, the Contractor may use temporary pavement to allow vehicular traffic to travel over the construction areas. Temporary pavement shall be placed around trench plates or others devices used to cover construction activities in a manner that provides a smooth and safe transition between surfaces. Within paved alleys, the Contractor may use compacted backfill to allow vehicular traffic to travel over construction areas. Trench plates or other devices used to cover construction activities shall be placed 05 - Spec Provisions For Bid 4-10-2007.doc Page 23 and anchored in a manner that provides a smooth and safe transition between and across surfaces. 5-06.2 Materials (Additional Section) Materials shall be ‘Hot Mix’ of either Class E asphalt or Asphalt Treated Base (ATB). The composition of other components of temporary asphalt pavement shall be determined by the Contractor to provide a product suitable for the intended application. The Contractor shall not use materials that are safety or health hazard. Temporary pavement material that does not form a consolidated surface after compaction shall be considered unsuitable and shall be removed from the site. Unsuitable temporary pavement shall be disposed of offsite. 5-06.3 Construction Requirements (Additional Section) The roadway sub-surfaces shall be prepared for the temporary pavement as defined in Section 2-06. Temporary pavement areas greater than ten (10) square feet shall be a minimum of four (4) inches thick and roller compacted to consolidation. The completed pavement shall be free from ridges, ruts, bumps, depressions, objectionable marks, or other irregularities. The Contractor shall immediately repair, patch, or remove any temporary pavement that does not provide a flat transition between existing pavement areas. All temporary asphalt concrete pavement shall be removed from the site by the end of the project and shall not be used as permanent asphalt pavement or sub-grade material. 05 - Spec Provisions For Bid 4-10-2007.doc Page 24 DIVISION 7 DRAINAGE STRUCTURES, STORM SEWERS, SANITARY SEWERS, WATER MAINS AND CONDUITS 7-08 GENERAL PIPE INSTALLATION REQUIREMENTS 7-08.3(1)E Trench Dewatering (Additional Section) Dewatering may be required during construction of the water and storm lines. If necessary, dewatering may consist of a combination of trench pumping, well points, and/or wells, and must satisfy the following requirements: • Prevent water from entering the trench and maintain dry trench conditions at the foundation level. • Prevent caving of the trench walls related to water migration through the walls. • Minimize turbidity in the effluent by utilizing properly sized filter hack materials on sumps, wells, and well points. • Preserve strength of foundation soils • Recovery of water levels may be rapid if pumping is interrupted. The Contractor shall provide standby equipment installed and ready to operate to ensure continuous pumping. • When wells and/or well points are no longer required, they shall be removed, backfilled, and abandoned. Wells can be left in place except the top three feet must be removed and provided they are abandoned in accordance with Chapter 173-16O WAC. • Turbid water must be treated if discharged to the storm system. Discharge of dewatering effluent to the storm system must comply with DOE dewatering permit conditions. The Contractor is required to obtain this permit prior to discharging dewatering effluent to the storm sewer system. All costs necessary to treat and monitor the dewatering effluent in accordance with the permit shall be the CONTRACTOR's responsibility. The dewatering program must be completed in such a way as to avoid excessive dewatering related settlement of adjacent facilities. 7-15.3(A) Service Connections (Addition) The Contractor shall complete the installation and testing of the new water main, hydrants, and new water service lines, make the final connections to the existing water mains, and connection of existing private service connection to new setters, unless otherwise directed by the Engineer. 05 - Spec Provisions For Bid 4-10-2007.doc Page 25 DIVISION 8 MISCELLANEOUS CONSTRUCTION 8-01 EROSION CONTROL 8-01.2 Materials Supplement this section with the following: Filter fabric used in the Sediment Control Fencing shall be equal to Mirafi 100X or approved equal. 8-01.3(3) Miscellaneous Erosion Control (New Section) Contractor shall take all necessary precautions to prevent sediment from construction activities from entering into storm water systems or natural waterways and from being transported away from the construction area by storm water. 8-04 CURBS, GUTTERS, AND SPILLWAYS 8-04.3 Construction Requirements Add the following: Curb and gutter shall match the existing curb and gutter, including type and dimensions. Grade shall meet adjacent curb and gutter in a smooth transition. 8-04.3(3) Width of Replacement (New Section) Contractor shall replace curb and gutter to the nearest construction joint, unless otherwise authorized by the ENGINEER. 8-14 CEMENT CONCRETE SIDEWALKS 8-14.1 Description (Revised Section) Replace paragraph with the following: This work shall consist of constructing replacement cement concrete sidewalks and driveways to restore sidewalks and driveways removed or damaged by the work of this contract. Cement concrete sidewalks and driveways shall be removed full width between existing joints. Replacement sidewalks and driveways shall be constructed in conformance with the details shown in the Standard Plans as specified and in conformity to lines and grades to match existing conditions. 05 - Spec Provisions For Bid 4-10-2007.doc Page 26 8-14.3(2) Placing and Finishing Concrete Add the following: Contractor shall match the existing dimensions of the sidewalk. Grade shall meet adjacent sidewalks in a smooth transition. 8-14.3(5) Width of Replacement (New Section) Contractor shall replace sidewalk to the nearest construction joint, unless otherwise authorized by the ENGINEER. 8-22 PAVEMENT MARKING 8-22.1 Description Supplement this section with the following: All existing pavement markings and markers that are removed by the Contractor’s activities related to this project shall be replaced in the original location and shall be of similar type. Markings and markers shall be in accordance with the City of Renton Standard Plans. 05 - Spec Provisions For Bid 4-10-2007.doc Page 27 RCS 19.122 UNDERGROUND UTILITIES 19.122.010 INTENT It is the intent of the legislature in enacting this chapter to assign responsibilities for locating and keeping accurate records of utility locations, protecting and repairing damage to existing underground facilities, and protecting the public health and safety from interruption in utility services caused by damage to existing underground utility facilities (1984 c 144 1.) 19.122.020 Definitions Unless the context clearly requires otherwise, the definitions in this section apply throughout this chapter. A. "Business day” means any day other than Saturday, Sunday or a legal local, state or federal holiday. B. "Damage” includes the substantial weakening of structural or lateral support of an underground facility, penetration, impairment, or destruction of any underground protective coating, housing, or other protective device, or the severance, partial or complete, of an,' underground facility to the extent that the project owner or the affected utility owner determines that repairs are required. C. "Emergency” means any condition constituting a clear and present danger to life or property, or a customer service outage. D. "Excavation" means any operation in which earth, rock, or other material or, or below the ground is moved or otherwise displaced by any means, except the tilling of soil less than twelve inches in depth for agricultural purposes, or road and ditch maintenance that does not change the original road grade or ditch flow line. E. "Excavator” means any person who engages directly in excavation. F. "Identified facility” means any underground facility, which is indicated in the project plans as being located within the area of proposed excavation. G. "Identified but un-locatable underground facility" means an underground facility, which has been identified but cannot be located with reasonable accuracy. H. "Locatable underground facility'' means an underground facility, which can be field-marked with reasonable accuracy. I. "Marking” means the use of stakes, paint, or other clearly identifiable materials to show the field location of underground facilities, in accord ance with the current color code standard of the American Public Works Association. Markings shall include identification letters indicating the specific type of the underground facility. J. "Person" means an individual, partnership, franchise holder, association, corporation, a state, a city, a county, or any subdivision or instrumentality of a state, and its employees, agents, or legal representatives. K. “Reasonable accuracy” means location within twenty-four (24) inches of the outside dimensions of both sides of an underground facility. L. “Underground facility” means any item buried or placed below for use in connection with the storage or conveyance of water, sewage, electronic, telephonic or telegraphic communications, cablevision, electronic energy, petroleum products, gas, gaseous vapors, hazardous liquid, or other substances and including but not limited to pipes, sewers, conduits, 05 - Spec Provisions For Bid 4-10-2007.doc Page 28 cables, valves, lines, wires, manholes, attachments, and those pans of poles or anchors below ground. M. “One-number locator service” means a service through which a person can notify utilities and request field marking of underground facilities. (16984 c 144 2.) 19.122.030 Notice of excavation to owners of underg round facilities - One-number locator service - Time for notice - Marking of underground facilities – Costs Before commencing any excavation, the excavator shall provide notice of the scheduled commencement of excavation to all owners of underground facilities through a one-number locator service. All owners of underground facilities within a one-number locator service area shall subscribe to the service. One number locator service rates for cable television companies will be based on the amount of their underground facilities. If no one-number locator service is available, notice shall be provided individually to those owners of underground facilities known to or suspected of having underground facilities within the area of proposed excavation. The notice shall be communicated to the owners of underground facilities not less than two business days or more than ten business days before the scheduled date for commencement of excavation, unless otherwise agreed by the parties. Upon receipt of the notice provided for in this section, the owner of the underground facility shall provide the excavator with reasonable accurate information as to its locatable underground facilities by surface- marking the location of the facilities. If there are identified but un-locatable underground facilities, the owner of such facilities shall provide the excavator with the best available information as to their locations. The owner of the underground facility providing the information shall respond no later than two business days after the receipt of the notice or before the excavation time, at the option of the owner, unless otherwise agreed by the parties. Excavators shall not excavate until all know facilities have been marked. Once marked by the owner of the underground facility, the excavator is responsible for maintaining the markings. Excavators shall have the right to receive compensation from the owner of the underground facility for costs incurred if the owner of the underground facility does not locate its facilities in accordance with this section. The Owner of the underground facility shall have the right to receive compensation for costs incurred in responding to excavation notices given less than two business days prior to the excavation from the excavator. An owner of underground facilities is not required to indicate the presence of existing service laterals or appurtenances if the presence of existing service laterals or appurtenances on the site of the construction project can be determined from the presence of other visible facilities, such as buildings, manholes, or meter and junction boxes on or adjacent to the construction site, Emergency excavations are exempt from the time requirements for notification provided in this section. If the excavator, while performing the contract, discovers underground facilities that are not identified, the excavator shall cease excavating in the vicinity of the facility and immediately notify the owner or operator of such facilities, or the one-number locator service. (1988 c99 1; 1984 c 144 3.) 19.122.04 Underground facilities identified in bid or contract - Excavator’s duty of reasonable care - Liability for damages - Attorney's Fees. A. Project owners shall indicate in bid or contract documents the existence of underground facilities known by the project owner to be located within the proposed area of excavation. The following shall be deemed changed or differing site conditions 1. An underground facility not identified as required by this chapter or other provision of law; and 05 - Spec Provisions For Bid 4-10-2007.doc Page 29 2. An underground facility not located, as required by this chapter or other provision of law, by the project owner or excavator if the project owner or excavator is also a utility. B. An excavator shall use reasonable care to avoid damaging underground facilities. An excavator shall: 1. Determine the precise location of underground facilities, which have been marked. 2. Plan the excavation to avoid damage to or minimize interference with underground facilities in and near Inc excavation area; and 3. Provide such support for underground facilities in and near the construction area, including during backfill operations, as may be reasonably necessary for the protection of such facilities. A. If an underground facility is damaged and such damage is the consequence of the failure to fulfill an obligation under this chapter, the party failing to perform that obligation shall be liable for any damages. Any clause in an excavation contract which attempts to allocate liability, or requires indemnification to shift the economic consequences of liability, different from the provisions of the chapter is against public policy and unenforceable. Nothing in this chapter prevents the parties to an excavation contract from contracting with respect to the allocation of risk for changed or differing site conditions. B. In any action brought under this section, the prevailing party is entitled to reasonable attorney’s fees. (1984 c 144 4.) 19.122.05 Damage to underground facility - No notification by excavator - Repairs or relocation of facility A. An excavator who, in the course of excavation, contacts or damages an underground facility shall notify the utility owning or operating such facility and the one-number locator service. If the damage causes an emergency condition, the excavator causing the damage shall also alert the appropriate local public safety agencies and take all appropriate steps to ensure the public safety. No damaged underground facility may he buried until it is repaired, or relocated. B. The owner of the underground facilities damaged shall arrange for repairs or relocation as soon as is practical or permit the excavator to do necessary repairs or relocation at a mutually acceptable price. (198 c 144 5.) 19.122.060 Exemption from notice and marking requirements for property owners An excavation of less than twelve inches in vertical depth on private non-commercial property shall be exempt from the requirements of RCW 19.122.030, if the excavation is being performed by the person, or an employee of the person who owns or occupies the property on which the excavation is being performed. (1984 c 144 6.) 19.122.070 Civil penalties - Treble damages - Exist ing remedies not affected A. Any person who violates any provision of this chapter, and which violation results in damage to underground facilities, is subject to a civil penalty of no more than one thousand dollars for each violation. All penalties recovered in such actions shall be deposited to the general fund. 05 - Spec Provisions For Bid 4-10-2007.doc Page 30 B. Any excavator who willfully or maliciously damages a field-marked underground facility shall be liable for treble the costs incurred in repairing or relocating the facility. In those cases in which an excavator fails to notify known underground facility owners or the one-number locator service, any damage to the underground facility shall he deemed willful and malicious and shall be subject to treble damages for costs incurred in repairing or relocating the facility. C. The chapter does not affect any civil remedies for personal injury or for property damage, including that to underground facilities, nor does this chapter crest any new civil remedies for such damage. (1984 c 144 7.) 19.122.080 Waiver of notification and marking requi rements The notification and marking provisions of this chapter may be waived for one or more designated persons by an underground facility owner with respect to all or part of that underground facility owner’s own underground facilities. (1984 c 144 9.) 19.122.090 Severability — 1984 c 144 If am provisions of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected. (1984 c 144 9.)