HomeMy WebLinkAboutCapital Improvements Plan - Surface Water 1SURFACE WATER
UTILITY
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-173
Projects Priority
Actual through
12/31/2023 2024 2025 2026 2027 2028 2029 2030
Total Project
Expenditures
Monroe Ave NE & NE 2nd St Infiltration System Improvements High 6,723 15,329 - - - - - - 22,051
Burnett Ave S and Williams Ave S Water Quality Retrofit Project High 632 3,866 - - - - - - 4,498
SW 43rd Street/Lind Ave SW Storm System Improvements High 44 1,006 - - 3,200 - - - 4,250
SE 172nd St and 125th Ave N Storm System Improvement Project High 644 4,306 - - - - - - 4,950
Cedar River 205 Project Levee Recertification Project High 1,826 3,851 - - - - - - 5,677
Cedar River Gravel Removal (Maintenance Dredge) Project High 11,265 2,201 - 500 500 500 11,000 150 26,116
Windsor Hills Storm System Improvements High 34 3,876 - - - - - - 3,910
Surface Water Planning High 708 109 - - - - - - 817
Cedar River Flood Risk Reduction Feasibility Study Med 160 340 - - - - - - 500
SW 23rd Street Drainage and Fish Passage Improvements Med 9 341 250 500 - - 3,500 - 4,600
Hardie Ave SW-SW 7th St Storm System Improvements Med 7,414 2,150 - - 2,500 - - - 12,064
Copper Ridge Storm System Improvement Med - - - 400 - 1,500 - - 1,900
Small Scale Stormwater Projects Med 2,664 1,380 600 400 400 400 400 400 6,644
Rainier Ave and Oakesdale Ave Pump Station Upgrades Med 324 499 - - 1,700 100 100 2,000 4,723
Talbot Hill Area Mosquito Abatement Program Med 818 128 80 80 90 90 90 90 1,466
Big Soos Creek at 116th Ave SE Improvement Project Med - - - 500 - 1,000 - - 1,500
Springbrook Creek Restoration Med - 346 - - - - - - 346
Springbrook Terrace Water Quality Retrofit Med - 357 - - 400 - - - 757
Sedimentation Facility Cleaning Med 812 356 - 150 160 160 - 160 1,798
Ginger Creek and Honey Creek Basin Plan Med 39 561 - - - - - - 600
Stevens Ave NW to Lind Ave NW Storm System Med - - 350 500 - - - - 850
Taylor Ave Phase 2 Drainage Improvement Med - - - 500 - 1,000 - - 1,500
Highbury Park Retrofit Project Low - - - - - 500 1,000 - 1,500
Madsen Creek Improvement Project Low 1,176 - - - 100 500 500 500 2,776
Kennydale Drainage Improvement Low - - - - - 300 - 1,500 1,800
East Valley Road Storm System Improvements Low 120 369 102 104 - - - - 695
Total Expenditures 35,414 41,368 1,382 3,634 9,050 6,050 16,590 4,800 118,287
Resources:
Actual through
12/31/2023 2024 2025 2026 2027 2028 2029 2030
Total Project
Resources
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 16,542 23,015 - 500 920 1,400 12,300 650 55,326
Surfacewater Collection Fees 18,872 18,353 1,382 3,134 8,130 4,650 4,290 4,150 62,961
Property/B&O Taxes - - - - - - - - -
Interest - - - - - - - - -
Total Resources 35,414 41,368 1,382 3,634 9,050 6,050 16,590 4,800 118,287
- - - - - - - - -
Project Funding Status:
Secured 35,414 41,368 1,382 3,134 - - - - 81,297
Anticipated Funding*- - - 500 9,050 6,050 16,590 4,800 36,990
Total Project Funding 35,414 41,368 1,382 3,634 9,050 6,050 16,590 4,800 118,287
- - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
SURFACE WATER CAPITAL INVESTMENT PROGRAM SUMMARY
2025 through 2030 (in thousands of dollars)
ESTIMATED
ESTIMATED
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-174
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2019
Status:Existing Estimated Completion:4/1/2025
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 6,723 15,329 - - - - - - 22,051
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 1,052 12,175 - - - - - - 13,227
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 5,671 3,153 - - - - - - 8,825
Interest - - - - - - - - -
Total Sources 6,723 15,329 - - - - - - 22,051
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Monroe Avenue NW & NE 2nd Street Infiltration System Improvements
Project Summary: The project includes the design and construction of new water quality treatment
and infiltration facilities to provide increased drainage capacity to a 245-acre basin in the Renton
Highlands. Currently, drainage solely relies on infiltration through perforated pipes near the city's
maintenance shops prior to the construction of temporary overflow outfalls to 301 Monroe Avenue
NE. Two Ecology Water Quality grants were secured to partially fund this project. Construction began
in December 2023 and the project will be completed by the first quarter of 2025.
Project Benefit: This project includes drainage improvements to reduce the risk of flooding along
Monroe Avenue NE and NE 4th Street and water quality retrofits to treat stormwater that, upon
infiltration, feeds the Cedar River aquifer. This project supports the city's goal of protecting public
safety by reducing flooding along streets used by local and regional emergency and critical
operations crews, and supports the goal of increasing quality of life and fostering environmental
sustainability by protecting a sole source aquifer for the city's water supply.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-175
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2020
Status:Existing Estimated Completion:6/30/2025
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 632 3,866 - - - - - - 4,498
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 297 1,103 - - - - - - 1,399
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 335 2,763 - - - - - - 3,099
Interest - - - - - - - - -
Total Sources 632 3,866 - - - - - - 4,498
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Burnett Avenue S and Williams Avenue S Water Quality Retrofit Project
Project Summary: This project adds drainage improvements and water quality treatment retrofits to the
Burnett Avenue S and Williams Avenue S storm water systems north of S 2nd Street, which discharge directly to
the Cedar River, a waterbody listed on the Department of Ecology's 303(d) under multiple categories of
impairment. Design started in 2020 and was completed in April 2024. Construction will start in summer 2024 and
extend through the first quarter of 2025. The design and construction phases are partially funded by Ecology
Water Quality grants, and construction is partially funded by the King County Flood Control District Subregional
Opportunity Fund.
Project Benefit: This project includes drainage improvements to reduce the risk of flooding and
water quality retrofits to treat stormwater runoff along Williams Avenue S and Wells Avenue S. It will
primarily benefit the 95 Burnett apartment complex which flooded in May 2018. With its flood risk
reduction and environmental benefit, this project supports the city's goals of protecting public
safety, environmental sustainability, and increasing quality of life.
Operating Cost Impact: Despite the addition of two stormwater treatment facilities, this project
does not require additional resources to handle maintenance and operation. There is no significant
impact to annual operation expenses.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-176
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2024
Status:Existing Estimated Completion:12/31/2029
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 44 1,006 - - 3,200 - - - 4,250
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 44 1,006 - - 3,200 - - - 4,250
Interest - - - - - - - - -
Total Sources 44 1,006 - - 3,200 - - - 4,250
Anticipated Funding*- - - - 3,200 - - - 3,200
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
SW 43rd Street/Lind Avenue SW Storm System Improvements
Project Summary: SW 43rd Street has experienced a recurring flooding problem between East Valley
Road and Springbrook Creek, likely due to undersized pipes, insufficient inlet capacity, flow patterns
in upstream basin areas, and high tailwater conditions. Analysis conducted as part of the Eastside
Green River Watershed Plan identified that a new storm system along Lind Avenue SW and SW 39th
Street with an upgraded outfall to Springbrook Creek would provide a solution to the flooding issue
on SW 43rd Street. This project delivers these improvements and is currently in the design stage with
construction anticipated in 2027.
Project Benefit: This project provides significant flood risk reduction benefits to SW 43rd Street, a
major arterial roadway, WSDOT T1 truck route, and one of only four roadways between I-405 and SR
516 that crosses the Green River. SW 43rd Street provides convenient access to a multitude of
businesses in the Green River Valley, and a direct route to Valley Medical Center Hospital for
emergency vehicles and residents in the Green River Valley. By reducing flood risk along this corridor,
this project supports the city's goals of economic development, public safety, and quality of life.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-177
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2019
Status:Existing Estimated Completion:12/31/2026
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 644 4,306 - - - - - - 4,950
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 250 2,975 - - - - - - 3,225
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 394 1,331 - - - - - - 1,725
Interest - - - - - - - - -
Total Sources 644 4,306 - - - - - - 4,950
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
SE 172nd Street and 125th Avenue N Storm System Improvement Project
Project Summary: The project includes design and construction of green stormwater infrastructure
consisting of biofiltration facilities, pervious sidewalks, and a new storm system along SE 172nd
Street and its cross streets between 122nd Avenue SE and 125th Avenue SE. These improvements
provide water quality treatment and improved conveyance for stormwater runoff. The project
design started in 2019 and will be completed in 2024. Construction is partially funded by an Ecology
Water Quality construction grant and is expected to begin in the fourth quarter of 2024.
Project Benefit: This is a multi-benefit project that will reduce the risk of flooding through improved
collection and conveyance of stormwater and the elimination of an aging existing system that
traverses private properties. It will also improve the ease of maintenance and operation of the storm
system. Furthermore, treatment of stormwater runoff will improve water quality of runoff in the Big
Soos Creek subbasin. This project supports the city's goals of economic development, public safety,
environmental sustainability, and quality of life.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-178
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2015
Status:Existing Estimated Completion:12/31/2026
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 1,826 3,851 - - - - - - 5,677
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 1,420 3,851 - - - - - - 5,270
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 406 - - - - - - - 406
Interest - - - - - - - - -
Total Sources 1,826 3,851 - - - - - - 5,677
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Cedar River Levee Section 205 Certification
Project Summary: This project aims to accredit with FEMA the Cedar River levees that were
constructed by the U.S. Army Corps of Engineers in 1998. Corps certification of the levees was
discontinued in 2013. Accreditation will be realized by retrofitting the levees and floodwalls to meet
current Corps and FEMA levee design standards. This project is in the permitting and design stage
with construction anticipated in 2026. All project expenses are funded by the King County Flood
Control District capital program.
Project Benefit: Without accreditation, the properties protected by the levees would have to be
remapped in the 100-year floodplain. FEMA Accreditation of the Cedar River levees and floodwalls
keeps the area protected mapped outside of the floodplain, which keeps properties protected by the
levees and floodwalls exempt from the requirement to purchase flood insurance and subject to
floodplain development regulations. Bringing the levees into compliance with current standards
elevates the level of flood protection. The project aligns with the city's goals of economic
development, public safety, and quality of life.
Operating Cost Impact: There is no significant operating cost impact. This project does not require
the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-179
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2012
Status:Existing Estimated Completion:Ongoing
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 11,265 2,201 - 500 500 500 11,000 150 26,116
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 11,169 2,201 - 500 500 500 11,000 150 26,020
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 96 - - - - - - - 96
Interest - - - - - - - - -
Total Sources 11,265 2,201 - 500 500 500 11,000 150 26,116
Anticipated Funding*- - - 500 500 500 11,000 150 12,650
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Cedar River Gravel Removal (Maintenance Dredge) Projects
Project Summary: Periodic maintenance dredging along the lower 1.23 miles of the Cedar River is
necessary due to ongoing sediment transport and deposition. This project is a critical component of
the Lower Cedar River Section 205 Flood Hazard Reduction project and is entirely funded by the King
County Flood Control District's capital program. The last dredging project was completed in 2016; the
city is currently in the post-construction mitigation monitoring and reporting phase through 2026.
Planning and design efforts for the next maintenance dredge is anticipated to begin in 2026 with
construction in 2029.
Project Benefit: Gravel removal maintains the 100-year level of protection offered by the levees and
floodwalls built in the lower 1.23 miles of the Cedar River and keeps the city in compliance with the
project cooperation agreement signed with Corps following the flood hazard reduction project in
1998. Mitigation monitoring, maintenance, and reporting work currently taking place keeps the city
in compliance with the project permit and the mitigation plan agreement with Washington Fish and
Wildlife. This project supports the city's goals of economic development, public safety, and quality of
life.
Operating Cost Impact: There is no operating cost impact to removing gravel from the Cedar River.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-180
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:1/1/2023
Status:Existing Estimated Completion:12/31/2025
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 34 3,876 - - - - - - 3,910
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 34 3,876 - - - - - - 3,910
Interest - - - - - - - - -
Total Sources 34 3,876 - - - - - - 3,910
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Windsor Hills Storm System Improvements
Project Summary: The project consists of installing 4,300 linear feet of new storm pipes and 59 catch
basins, as well as tightlining three open channels in the Windsor Hills neighborhood in conjunction
with water system improvements delivered by the water utility. The existing storm system in the
Windsor Hills neighborhood does not meet current standards of collection, conveyance, and
minimum pipe size. Construction is anticipated to begin in July 2024 and to be completed by the end
of 2025.
Project Benefit: By replacing aging infrastructure and improving collection and conveyance of
stormwater in the Windsor Hills neighborhood, this project supports the city's goal of promoting
public safety. The project includes water and wastewater systems funded improvements also.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-181
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:High Estimated Start:Ongoing
Status:Existing Estimated Completion:Ongoing
Project Category:System Preservation
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 708 109 - - - - - - 817
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 188 14 - - - - - - 202
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 520 95 - - - - - - 615
Interest - - - - - - - - -
Total Sources 708 109 - - - - - - 817
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Surface Water Planning
Project Summary: Includes updates to the Utility Master Plan, a comprehensive management plan of
the city’s natural and constructed surface water systems, and Surface Water Design Manual to meet
the requirements of the city's Municipal Stormwater Permit. Prior updates were completed in 2022;
next updates are anticipated in 2026/2027 following issuance of the 2024 permit and King County
adopting a revised design manual. These changes will likely create new set of regulatory
requirements that the city is required to comply with.
Project Benefit: Planning efforts supports the city's goals of economic development, public safety,
and quality of life. The Utility Master Plan identifies current and future resource requirements,
policies, regulatory requirements, and design criteria associated with the management of surface
water runoff within the city. It serves as a guiding document for operations and capital programs.
The Surface Water Design Manual is a critical document that establishes standards for surface water
management for development and redevelopment projects.
Operating Cost Impact: Regulatory compliance with evolving requirements of the Municipal General
Stormwater Permit periodically require the acquisition of new equipment or the addition of
engineering or maintenance staff. There are no anticipated operating impacts in 2025 or 2026.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-182
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2021
Status:Existing Estimated Completion:6/30/2026
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 160 340 - - - - - - 500
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 160 340 - - - - - - 500
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - - - - - - - -
Interest - - - - - - - - -
Total Sources 160 340 - - - - - - 500
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Cedar River Flood Risk Reduction Feasbility Study
Project Summary: This study intends to assess the feasibility of improving the level of flood
protection and evaluate future flood risk reduction projects along the Cedar River from River Mile 0
to River Mile 2.7. This study will identify potential measures that would increase resiliency to floods
greater than the 100-year event and identify the most feasible level of flood protection that could be
achieved along this reach of the Cedar River, a critical area of development and economic activity
within the city. This study is fully funded by the King County Flood Control Zone District capital
program.
Project Benefit: By evaluating the feasibility of increasing the level of flood protection along the
Lower Cedar River, and reducing the risk of flooding to the surrounding economically significant area,
this project aligns with the city's goals of economic development, public safety, and quality of life.
Operating Cost Impact: There is no operating cost impact for this study. Operating costs will be
evaluated if this study results in infrastructure improvements.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-183
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2022
Status:Existing Estimated Completion:12/31/2030
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 9 341 250 500 - - 3,500 - 4,600
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 9 341 250 500 - - 3,500 - 4,600
Interest - - - - - - - - -
Total Sources 9 341 250 500 - - 3,500 - 4,600
Anticipated Funding*- - - - - - 3,500 - 3,500
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
SW 23rd Street Drainage and Fish Passage Improvements
Project Summary: This project consists of culvert replacements to convey flows from Panther Creek
and Rolling Hills Creek. The capacity of this channel is reduced due to vegetation growth and culverts
set below the grade of the channel. These improvements will be delivered by WSDOT as part of a
larger project aimed at providing fish passage from Rolling Hills Creek to Springbrook Creek. Funding
programmed for the project is the surface water utility's estimated share of the overall project cost.
A cost share interlocal agreement with WSDOT will be executed by mid 2026.
Project Benefit: This project presents an opportunity to partner with WSDOT and deliver capacity
and fish passage improvements along Panther Creek, which would benefit both the city and the State
of Washington. Such improvements would have had a higher cost if the city was individually
delivering them. This project supports the city's goals of protecting public safety, environmental
sustainability, and increasing quality of life. It fosters interagency cooperation and alignment of
resources towards a shared goal.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-184
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2011
Status:Existing Estimated Completion:12/31/2028
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 7,414 2,150 - - 2,500 - - - 12,064
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 642 - - - - - - - 642
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 6,772 2,150 - - 2,500 - - - 11,422
Interest - - - - - - - - -
Total Sources 7,414 2,150 - - 2,500 - - - 12,064
Anticipated Funding*- - - - 2,500 - - - 2,500
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Hardie Avenue SW/SW 7th Street Storm System Improvements
Project Summary: This project is phase 3 of the SW 7th Street storm system improvement project
and includes replacement of approximately 700 linear feet of 36-inch to 48-inch storm system,
between Hardie Avenue SW and SW 7th Street, with a new 60-inch to 72-inch storm system. The
new storm system will extend from Hardie Avenue SW south of the BNSF railroad underpass through
three private properties to SW 7th Street, 300 feet east of Lind Avenue SW. This project is currently
in the preliminary design and easement acquisition stage. Final design will begin in 2025 once the
required easements are secured.
Project Benefit: This project reduces the risk of flooding and road closures during large storm events
at Hardie Avenue SW near the BNSF railroad crossing and as such supports the city's goals of
improving public safety.
Operating Cost Impact: There is no significant operating cost impact. This project does not require
the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-185
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2026
Status:New Estimated Completion:12/31/2028
Project Category:System Preservation
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - - - 400 - 1,500 - - 1,900
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - - 400 - 1,500 - - 1,900
Interest - - - - - - - - -
Total Sources - - - 400 - 1,500 - - 1,900
Anticipated Funding*- - - - - 1,500 - - 1,500
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Copper Ridge Storm System Improvement
Project Summary: CCTV inspections revealed that a 15-inch and a 24-inch corrugated metal pipes
extending from Davis Avenue S on the north side of the Copper Ridge development are in a
deteriorated condition. This storm system is more than 50 years old; it is installed in the steep slope
of Talbot Hill and discharges to the Panther Creek wetland. This project replaces the deteriorated
sections of this storm system and rehabilitates sections in need of repair to reduce the risk of pipe
failure, flooding and landslide. Design is anticipated to start in 2026 with construction anticipated in
2028.
Project Benefit: By reducing the risk of storm system failure, flood risk and landslide, this project
supports the city's goal of promoting public safety.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-186
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:Ongoing
Status:Existing Estimated Completion:Ongoing
Project Category:System Preservation
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 2,664 1,380 600 400 400 400 400 400 6,644
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 183 - - - - - - - 183
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 2,482 1,380 600 400 400 400 400 400 6,462
Interest - - - - - - - - -
Total Sources 2,664 1,380 600 400 400 400 400 400 6,644
Anticipated Funding*- - - - 400 400 400 400 1,600
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Small Scale Stormwater Projects
Project Summary: This program consists of design and construction solutions to relatively simple
flooding problems, as well as minor storm system maintenance, repair, rehabilitation, and
replacements that are not large enough to be addressed as individual projects and can be grouped
together. Projects are identified annually through field observations, citizen complaints, CCTV
inspections, and input from the maintenance section. In 2025, this program will fund three storm
system replacement projects, and surface water's share of the NE 12th Street project and the
President Park Pipe Rehabilitation project.
Project Benefit: By replacing aging infrastructure and resolving flooding complaints, this program
supports the city’s goal of promoting public safety.
Operating Cost Impact: There is no significant operating cost impact. This project does not require
the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-187
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2019
Status:Existing Estimated Completion:12/31/2030
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 324 499 - - 1,700 100 100 2,000 4,723
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 324 499 - - 1,700 100 100 2,000 4,723
Interest - - - - - - - - -
Total Sources 324 499 - - 1,700 100 100 2,000 4,723
Anticipated Funding*- - - - 1,700 100 100 2,000 3,900
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Rainier Avenue and Oakesdale Avenue Pump Station Upgrades
Project Summary: This project adds on-site permanent emergency generators and control panel
upgrades at the Rainier Avenue S and Oakesdale Avenue S pump stations. A gas powered emergency
generator is being designed south of the Rainier Avenue S pump station between the sidewalk and
the edge of the right of way. Completed design is anticipated in 2026 with construction anticipated in
2027. Upgrades at the Oakesdale Avenue S pump stations will be designed following the construction
of upgrades at the Rainier Avenue S pump station.
Project Benefit: This project increases the reliability of the Rainier Avenue S and Oakesdale Avenue S
pump stations by providing uninterrupted power in an emergency event or a thunderstorm. Keeping
the pump stations operational, especially during a large storm event, reduces the risk of flooding on
major city arterials served by these pump stations. The Rainier Avenue pump station particularly
serves a critical role of protecting Rainier Avenue S from flooding along the sag point underneath the
BNSF railroad crossing. Because of the high flood risk reduction benefits, this project supports the
city's goals of promoting public safety and quality of life.
Operating Cost Impact: There is no significant operating cost impact. This project does not require
the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-188
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2015
Status:Existing Estimated Completion:Ongoing
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 818 128 80 80 90 90 90 90 1,466
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 818 128 80 80 90 90 90 90 1,466
Interest - - - - - - - - -
Total Sources 818 128 80 80 90 90 90 90 1,466
Anticipated Funding*- - - - 90 90 90 90 360
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Talbot Hill Area Mosquito Abatement Program
Project Summary: This annual program covers the treatment of upland areas around the Panther
Creek wetlands to control mosquitoes from the wetlands in response to citizen complaints in the
Talbot Hill area. This program also funds the annual treatment of city-owned stormwater water
quality and flow control facilities in response to the West Nile virus. It also provides additional
funding in the event of a West Nile virus outbreak occurs and any possible treatments advised by the
Washington State Department of Health.
Project Benefit: Because this program provides mosquito control and helps to protect the city
against a West Nile virus outbreak, it supports the city's goal of promoting public safety.
Operating Cost Impact: There is no operating cost impact for mosquito control.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-189
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2026
Status:New Estimated Completion:12/31/2029
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - - - 500 - 1,000 - - 1,500
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - - 500 - 1,000 - - 1,500
Interest - - - - - - - - -
Total Sources - - - 500 - 1,000 - - 1,500
Anticipated Funding*- - - - - 1,000 - - 1,000
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Big Soos Creek at 116th Avenue SE Improvement Project
Project Summary: The conveyance capacity of Big Soos Creek between 116th Avenue SE and SE
Petrovitsky Rd is significantly reduced due to overgrown vegetation and sediment deposition. The
majority of this section of the creek flows through private property, which creates a significant
challenge for adequate maintenance. The project will improve the channel by either removing
sediment and overgrown vegetation. It will also evaluate the feasibility of routing the creek in a
manner that reduces flood risk. An alternatives analysis, design, and permitting contract will be
executed in 2026 with construction anticipated in 2028.
Project Benefit: By restoring the conveyance capacity of the Big Soos Creek channel between 116th
Avenue SE and SE Petrovitsky Rd, this project reduces flood risk and supports the city's goal of
promoting public safety.
Operating Cost Impact: There is no anticipated operating cost impact for this project.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-190
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2024
Status:Existing Estimated Completion:12/31/2026
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - 346 - - - - - - 346
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - 150 - - - - - - 150
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - 196 - - - - - - 196
Interest - - - - - - - - -
Total Sources - 346 - - - - - - 346
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Springbrook Creek Restoration
Project Summary: This plan will guide the restoration of Springbrook Creek from SW 43rd Street to
the Black River Riparian Forest by identifying conceptual solutions to improve fish habitat and
ecological function, and defining an implementation schedule. It is partially funded by a WRIA 9
Cooperative Watershed Management grant. Conceptual designs will be developed for a minimum of
3 sites. It is anticipated that habitat improvements will be delivered through riparian plantings, large
woody material, pool construction, channel branch excavation, and a potential two-stage channel to
enhance channel complexity.
Project Benefit: Springbrook Creek is impaired across multiple water quality standards including
temperature, bacteria, dissolved oxygen, and biological function. The Springbrook Creek is one of the
most significant waterbodies in the valley and the subject of attention from youth group and
environmental activists. Developing an action plan to restore Springbrook Creek, and improve water
quality, supports the city's goal of fostering environmental sustainability and showcases Renton's
commitment to protecting its water resources.
Operating Cost Impact: There is no operating cost impact for this plan.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-191
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2024
Status:Existing Estimated Completion:12/31/2027
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - 357 - - 400 - - - 757
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - 207 - - 320 - - - 527
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - 150 - - 80 - - - 230
Interest - - - - - - - - -
Total Sources - 357 - - 400 - - - 757
Anticipated Funding*- - - - 400 - - - 400
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Springbrook Terrace Water Quality Retrofit
Project Summary: This project consists of design and construction of water quality treatment
retrofits at the Springbrook Terrace stormwater detention pond. This pond was constructed to
provide flow control for 5.2 acres of single-family residential land use in the Springbrook Terrace plat
development. Basic water quality treatment can be achieved by deepening the pond to create a wet
pool and allow the settling of sediment. The receiving waterbody is Upper Springbrook Creek. The
project is partially funded by an Ecology Water Quality design grant. This project is in the design
phase with construction anticipated in 2027.
Project Benefit: Retrofitting the Springbrook Terrace pond to treatment stormwater inflows will
reduce pollutant discharge from the pond and improve water quality in Upper Springbrook Creek.
This project supports the city's goal of protecting water resources and fostering environmental
sustainability.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the slightly increased maintenance requirements at
this facility as a result of this project.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-192
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2010
Status:Existing Estimated Completion:Ongoing
Project Category:Major Maintenance
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 812 356 - 150 160 160 - 160 1,798
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 107 - - - - - - - 107
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 705 356 - 150 160 160 - 160 1,691
Interest - - - - - - - - -
Total Sources 812 356 - 150 160 160 - 160 1,798
Anticipated Funding*- - - - 160 160 - 160 480
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Sedimentation Facility Cleaning
Project Summary: This program covers annual sediment removal from the Madsen Creek and
Maplewood Creek sedimentation facilities. The Madsen Creek facility was originally constructed by
King County in 1974 to control sediment resulting from erosion of steep slopes in the Madsen Creek
ravine and the Maplewood Creek Sedimentation Facility was constructed by Renton in 1996 in
conjunction with a fish passage channel across the Maplewood Golf Course to the Cedar River.
Funding is programmed for project management, permitting, and construction.
Project Benefit: Sediment removal from sedimentation facilities reduces the rate of sediment
deposition and loss of downstream channel capacity, which in turn reduces the risk of flooding. The
Maplewood Creek facility prevents the sediment from being deposited within the Maplewood Golf
Course during large storms and reduces the risk flooding the golf course and SR-169. The Madsen
Creek facility reduces the risk of flooding for Wonderland Estates mobile home park, Ron Regis Park,
and properties along 149th Avenue SE. This project supports the city's goals of promoting public
safety.
Operating Cost Impact: There is no operating cost impact. Facilities included in this program are not
typically maintained by the maintenance division.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-193
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:12/1/2023
Status:Existing Estimated Completion:12/31/2025
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 39 561 - - - - - - 600
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 39 561 - - - - - - 600
Interest - - - - - - - - -
Total Sources 39 561 - - - - - - 600
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Ginger Creek and Honey Creek Basin Plans
Project Summary: This project will develop comprehensive subbasin plans for sections of Ginger
Creek and Honey Creek channeled through large aging corrugated metal pipes. Conceptual
alternatives involving replacement, realignment, and possibly daylighting of these piped sections will
be developed. Developed subbasin plans and alternatives will guide the long-term capital
investments needed to address condition and capacity issues and reduce flood risk.
Project Benefit: This project would help to determine whether repairs or replacements are
necessary, and whether these pipes can accommodate the expected future flows within their
respective subbasins. This project will reduce the risk of pipe failure and flood risk through
commercial and residential areas, and it aligns with the city's goals of economic development and
promoting public safety.
Operating Cost Impact: There is no operating cost impact for this basin plan. Operating costs will
evaluated if this plan results in infrastructure improvements.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-194
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2025
Status:New Estimated Completion:12/31/2026
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - - 350 500 - - - - 850
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - 350 500 - - - - 850
Interest - - - - - - - - -
Total Sources - - 350 500 - - - - 850
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Stevens Avenue NW to Lind Avenue NW Storm System
Project Summary: Stormwater and sump pump discharge from uphill properties pond in the sag
point along Stevens Avenue NW and flow downhill towards Lind Avenue NW through the property at
312 Stevens Avenue NW. This project adds a stormwater system through the utility easement south
of 312 Stevens Avenue NW to provide adequate conveyance for stormwater runoff from Stevens
Avenue NW to Lind Avenue NW, and reduce the risk of private property damage. Design is
anticipated in 2025 with construction anticipated in 2026.
Project Benefit: By reducing flood risk, this project supports the city's goal of promoting public
safety.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-195
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Med Estimated Start:1/1/2026
Status:New Estimated Completion:12/31/2030
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - - - 500 - 1,000 - - 1,500
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - - 500 - 1,000 - - 1,500
Interest - - - - - - - - -
Total Sources - - - 500 - 1,000 - - 1,500
Anticipated Funding*- - - - - 1,000 - - 1,000
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Taylor Avenue Phase 2 Drainage Improvement
Project Summary: CCTV inspections revealed that the 24-inch corrugated metal pipe conveying
stormwater runoff from Taylor Avenue NW was in a severely deteriorated condition. Phase 1 of this
project diverted public stormwater runoff to a new system extending south along Taylor Avenue NW.
Phase 2 would fill the remaining portion of this pipe with flowable concrete and divert remaining
private connections, including downspouts, to the existing storm system on Hardie Avenue NW or
the south parking lot of the church. Design is anticipated to begin in 2026 with construction
anticipated in 2028.
Project Benefit: Abandoning the 24-inch corrugated metal pipe underneath the Church of Grace will
reduce the risk associated with a potential collapse of the pipe and support the city's goal of public
safety.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities. Any facilities
added as part of this project will be privately maintained.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-196
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Low Estimated Start:1/1/2028
Status:New Estimated Completion:12/31/2030
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - - - - - 500 1,000 - 1,500
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - 400 800 - 1,200
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - - - - 100 200 - 300
Interest - - - - - - - - -
Total Sources - - - - - 500 1,000 - 1,500
Anticipated Funding*- - - - - 500 1,000 - 1,500
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Highbury Park Retrofit Project
Project Summary: This project adds water quality retrofits along Edmonds Avenue NE in the
Highbury Park neighborhood through two media filtration vaults. Conceptual design called for an 8-ft
by 24-ft unit at the intersection of Edmonds Ct NE and Edmonds Avenue NE, and a 6-ft by 8-ft unit at
the intersection of Edmonds Avenue NE and Ferndale Avenue NE. This project maintains compliance
with the Municipal Stormwater General Permit. Funding is anticipated through an Ecology Water
Quality grant as this project is on an Ecology-approved action plan.
Project Benefit: Treating stormwater runoff will reduce pollutant discharge to the city's storm
system and improve water quality in Johns Creek. This project supports the city's goal of protecting
water resources and fostering environmental sustainability.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-197
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Low Estimated Start:1/1/2027
Status:Existing Estimated Completion:12/31/2030
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 1,176 - - - 100 500 500 500 2,776
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions 1,075 - - - 100 500 500 500 2,675
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 102 - - - - - - - 102
Interest - - - - - - - - -
Total Sources 1,176 - - - 100 500 500 500 2,776
Anticipated Funding*- - - - 100 500 500 500 1,600
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Madsen Creek Improvement Project
Project Summary: This project consists of the long term alternative solution of creating a single
channel for Madsen Creek from the sediment pond to the Cedar River. This single channel would
eliminate the need for a sediment basin and a high flow bypass, and restore the natural hydrology of
Madsen Creek. It would be large enough to convey all flows, allow the creation of an alluvial fan,
divert away from properties on 149th Avenue SE, and connect to the Cedar River. This phase is
contingent upon an agreement with King County, property acquisitions, and securing funding from
the King County Flood Control District.
Project Benefit: This project will reduce the risk of flooding associated with Madsen Creek at the
Wonderland Estates Manufactured Home Park, along 149th Avenue SE, and in Ron Regis Park. Flood
risk reduction benefits from the long term single channel solution will exceed those of the first
phase. Additionally, the long term solution will improve fish passage from the Cedar to Madsen
Creek. As such, this project supports the city's goal of promoting public safety and fostering
environmental sustainability.
Operating Cost Impact: If delivered, the next phase of the project may reduce operating and
maintenance costs along Madsen Creek by not needing to maintain the high flow bypass channel and
the Madsen Creek Sediment pond.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-198
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Low Estimated Start:1/1/2028
Status:New Estimated Completion:12/31/2030
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total - - - - - 300 - 1,500 1,800
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees - - - - - 300 - 1,500 1,800
Interest - - - - - - - - -
Total Sources - - - - - 300 - 1,500 1,800
Anticipated Funding*- - - - - 300 - 1,500 1,800
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
Kennydale Drainage Improvement
Project Summary: Long stretches of roads within the Kennydale area between Park Avenue N and
Burnett Avenue N lack adequate drainage infrastructure, namely N 35th Street, N 29th Street, and N
28th Street. This project installs new storm systems along these roads to improve collection and
conveyance of stormwater in accordance with current standards and reduce flood risk to private
property. Design is anticipated to begin in 2028 and with construction anticipated in 2030.
Project Benefit: By improving the collection and conveyance of stormwater within the Kennydale
area, and reducing flood risk, this project supports the city's goal of promoting public safety.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-199
SURFACE WATER UTILITY CAPITAL INVESTMENT PROGRAM
Priority:Low Estimated Start:1/1/2023
Status:Existing Estimated Completion:12/31/2030
Project Category:Development
Total Cost by Type (in thousands of dollars)
Type
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
Project Total 120 369 102 104 - - - - 695
Project Funding (in thousands of dollars)
Source
Actual Through
12/31/2023 2024 2025 2026 2027 2028 2029 2030 Total
REET - - - - - - - - -
Impact Fees - - - - - - - - -
Grant/Contributions - - - - - - - - -
Property/B&O Taxes - - - - - - - - -
Surfacewater Collection Fees 120 369 102 104 - - - - 695
Interest - - - - - - - - -
Total Sources 120 369 102 104 - - - - 695
Anticipated Funding*- - - - - - - - -
Operating Cost Impact:
Fund
General - - - - - - - - -
*Expenditures utilizing anticipated funding (e.g. grants/contributions) are considered unsecured and not included in the adopted budget.
East Valley Road Storm System Improvements
Project Summary: This project upsizes the existing storm system along the East Valley Rd between
SW 29th Street and SW 23rd Street to reduce the risk of flooding. This storm system discharges to
Panther Creek and its conveyance capacity is influenced by high tailwater. Flood risk during large
storm events was identified in the Eastside Green River Watershed Plan in 1997 and confirmed using
hydraulic modeling in 2023. This project is in the preliminary design stage. Construction will be
coordinated with the SW 23rd Street Drainage and Fish Passage Improvements that will be delivered
by WSDOT.
Project Benefit: By reducing the risk of flooding along East Valley Rd, this project aligns with the city's
goals of economic development and promoting public safety.
Operating Cost Impact: There is no significant operating cost impact. Individually, this project does
not require the addition of resources to handle the maintenance of installed facilities.
2025/2026 Adopted Budget City of Renton, Washington
Capital Investment Program - Surface Water Utility 5-200