Exhibit D - Design Schedule
ID Task Mode Task Name Duration Start Finish 1 Contract NTP 48 days Thu 8/31/23 Mon 11/6/23 8 Project Kickoff 35 days Tue 11/7/23 Fri 1/5/24 13 Task 200 - Geotechnical 300 days Mon 2/26/24 Mon 5/12/25 24 Task 300 - Design 469 days Mon 1/8/24 Tue 11/25/25 25 CAD Setup 20 days Mon 1/8/24 Mon 2/5/24 29 PSE Service Application 12 mons Mon 7/15/24 Thu 7/3/25 30 60% Design 131 days Thu 8/1/24 Tue 2/18/25 42 90% Design 165 days Tue 2/18/25 Fri 10/10/25 43 City comments received 0 days Tue 2/18/25 Tue 2/18/25 44 Additional survey completed (CAD)0 days Fri 3/28/25 Fri 3/28/25 45 Plan reorganization feedback 0 days Mon 3/31/25 Mon 3/31/25 46 KC comments received 0 days Mon 4/7/25 Mon 4/7/25 47 Review & distribute 60% review comments 1 mon Mon 4/7/25 Fri 5/2/25 48 90% design - coordination 6 wks Mon 5/5/25 Mon 6/16/25 49 90% design - drawings 5 wks Tue 6/17/25 Wed 7/23/25 50 90% design - estimate, BODR, specs 3 wks Thu 7/24/25 Wed 8/13/25 51 QA/QC Review 5 days Thu 8/14/25 Wed 8/20/25 52 Revisions 5 days Thu 8/21/25 Wed 8/27/25 53 Submit 90% Design 1 day Thu 8/28/25 Thu 8/28/25 54 City 90% Review 3 wks Fri 8/29/25 Fri 9/19/25 55 King County 90% Review 6 wks Fri 8/29/25 Fri 10/10/25 56 90% Design Milestone 0 days Fri 9/19/25 Fri 9/19/25 57 100% Design 46 days Mon 9/22/25 Tue 11/25/25 58 Resolve 90% review comments 10 days Mon 9/22/25 Fri 10/3/25 59 Revise dwgs, specs, estimate, BODR 25 days Mon 10/6/25 Fri 11/7/25 60 QA/QC 5 days Mon 11/10/25 Mon 11/17/25 61 Prepare sealed documents 5 days Tue 11/18/25 Mon 11/24/25 62 Submit 100% Design to City, KC 1 day Tue 11/25/25 Tue 11/25/25 63 100% Design Milestone 0 days Tue 11/25/25 Tue 11/25/25 64 Task 400 - Real Property & Survey 366 days Tue 12/19/23 Tue 6/17/25 79 Task 500 - Permitting 471 days Thu 2/8/24 Fri 1/2/26 80 Corps Permit Prep 130 days Thu 2/8/24 Wed 8/14/24 85 Corps Permit Review 242 days Thu 8/15/24 Fri 8/8/25 86 Submit Corps permit 1 day Thu 8/15/24 Thu 8/15/24 87 Corps Nationwide Permit review 12 mons Fri 8/16/24 Thu 8/7/25 88 Notice - Assigned to reviewer 1 day Fri 10/25/24 Fri 10/25/24 89 Corps Nationwide Permit issuance 1 day Fri 8/8/25 Fri 8/8/25 90 City Permitting 448 days Thu 2/29/24 Thu 12/18/25 91 City Pre-Application Meeting 1 day Thu 2/29/24 Thu 2/29/24 2/18 3/28 3/31 4/7 9/19 90% Design Milestone 11/25 100% Design Milestone Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 2025 2026 Task Split Milestone Summary Project Summary Page 1 Project: Kennydale - Final Design Date: Fri 6/13/25 ID Task Mode Task Name Duration Start Finish 92 Arborist Inventory & Report 5 wks Wed 2/26/25 Tue 4/1/25 93 Prepare SEPA checklist 2 mons Tue 2/18/25 Mon 4/14/25 94 City land use permit (shoreline) prep 4 mons Fri 8/16/24 Wed 12/11/24 95 City SEPA Determination 4 mons Tue 4/15/25 Thu 8/7/25 96 City land use permit to to City 0 days Mon 5/5/25 Mon 5/5/25 97 Signature and Sign Posting 2 wks Mon 5/5/25 Fri 5/16/25 98 City land use Permit Review 2 mons Mon 5/19/25 Wed 7/16/25 99 City land use permit issuance 1 day Thu 7/17/25 Thu 7/17/25 100 City construction permit materials prep 4 wks Mon 9/22/25 Fri 10/17/25 101 City construction permit review 2 mons Mon 10/20/25 Wed 12/17/25 102 City construction permit issuance 1 day Thu 12/18/25 Thu 12/18/25 103 WDFW HPA 126 days Tue 4/15/25 Mon 10/13/25 104 Prepare WDFW HPA permit materials 1 mon Tue 4/15/25 Mon 5/12/25 105 WDFW HPA permit review 45 days Fri 8/8/25 Fri 10/10/25 106 WDFW HPA permit issuance 1 day Mon 10/13/25 Mon 10/13/25 107 DOE Permit 70 days Mon 9/22/25 Fri 1/2/26 108 Prepare DOE CSWGP 2 wks Mon 9/22/25 Fri 10/3/25 109 CSWGP review and issuance 60 days Mon 10/6/25 Fri 1/2/26 110 King County Permit 347 days Wed 7/10/24 Wed 12/3/25 111 Initial Draft Ops & Use Agreement from KC 1 day Wed 7/10/24 Wed 7/10/24 112 Renton comments to KC 1 day Fri 10/11/24 Fri 10/11/24 113 Confirmation of Easement Option 0 days Tue 2/18/25 Tue 2/18/25 114 Meeting with KC Real Estate 0 days Tue 4/22/25 Tue 4/22/25 115 Commercial Appraisal 6 wks Mon 6/16/25 Tue 7/29/25 116 Easement Development 8 mons Tue 2/18/25 Fri 10/3/25 117 Finalize Temp and Permanent Easement 2 mons Mon 10/6/25 Wed 12/3/25 118 Task 600 - Public Involvement 549 days Tue 2/6/24 Mon 4/20/26 119 Update Public Involvement Plan 6 wks Tue 2/6/24 Tue 3/19/24 120 Renton PW Strategy Approval 1 day Thu 3/28/24 Thu 3/28/24 121 Newsletter #1 - mailed to residents (general update, prep for field work) 1 day Fri 5/24/24 Fri 5/24/24 122 Preparation for Open House 6 wks Fri 4/26/24 Fri 6/7/24 123 Mailer #2 - Open House invitation 1 day Mon 6/17/24 Mon 6/17/24 124 Open House - Pump Ops, Easement 1 day Tue 7/16/24 Tue 7/16/24 125 PRR - New sub NTP 1 day Fri 9/6/24 Fri 9/6/24 126 Mailer #3 - Thanks for feedback, general update (to City) 1 day Fri 10/25/24 Fri 10/25/24 127 Summer Newsletter 1 wk Mon 6/9/25 Fri 6/13/25 128 Fall 2025 Newsletter 1 day Wed 11/26/25 Wed 11/26/25 129 Online Open House Notification 1 day Fri 3/20/26 Fri 3/20/26 5/5 2/18 4/22 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 2025 2026 Task Split Milestone Summary Project Summary Page 2 Project: Kennydale - Final Design Date: Fri 6/13/25 ID Task Mode Task Name Duration Start Finish 130 Online Open House - Construction impacts 1 day Mon 4/20/26 Mon 4/20/26 131 Float 20 days Fri 12/19/25 Mon 1/19/26 132 Unanticipated Delays 4 wks Fri 12/19/25 Mon 1/19/26 133 Task 700 - Bid Support & Advertisement 54 days Tue 1/20/26 Fri 4/3/26 134 City legal review 10 days Tue 1/20/26 Mon 2/2/26 135 Publish bid set 10 days Tue 2/3/26 Mon 2/16/26 136 Bid advertisement 3 wks Tue 2/17/26 Mon 3/9/26 137 Bids Received 0 days Mon 3/9/26 Mon 3/9/26 138 Evaluation of low bidder 1 wk Tue 3/10/26 Mon 3/16/26 139 Approval to award 3 days Tue 3/17/26 Thu 3/19/26 140 Contract award process 2 wks Fri 3/20/26 Thu 4/2/26 141 NTP 1 day Fri 4/3/26 Fri 4/3/26 142 Construction 360 days Fri 4/3/26 Fri 8/20/27 143 Construction Start 0 days Fri 4/3/26 Fri 4/3/26 144 (See construction schedule)18 mons Mon 4/6/26 Fri 8/20/27 3/9 Bids Received 4/3 Construction Start Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 2025 2026 Task Split Milestone Summary Project Summary Page 3 Project: Kennydale - Final Design Date: Fri 6/13/25