Loading...
HomeMy WebLinkAboutEx_06_Construction_Mitigation_DescriptionMay 2025 Page 1 Kennydale Lakeline Sewer System Replacement Project CONSTRUCTION MITIGATION DESCRIPTION The following includes a narrative of anticipated construction activities and associated mitigation measures to reduce impacts to the community. Additional details are provided in the Project Narrative and Code Consistency Analysis. Proposed Construction Dates (Begin and End Dates) Phase 1 construction of the individual ILS with grinder pumps is projected to begin in early 2026. The anticipated duration of construction is approximately 18 months, although the construction schedule will be finalized during final design. It is estimated that the majority of work on each private property will take approximately 1 to 2 weeks, although the duration could be longer depending on conditions during construction. The detailed construction phasing will be determined by the contractor and their selected means and methods. It is generally anticipated that construction will be completed in 3 zones, associated with the 3 force main discharges. The electrical system and main line in the public roadway will need to be tested and operational prior to completing lateral and side sewer connections to the grinder pump stations. Once the replacement system is complete (i.e., Phase 1), the existing Kennydale lakeline system will be decommissioned (Phase 2). Lakeline decommissioning is scheduled to occur in 2027 or 2028 once the upland replacement system is installed. Decommissioning work will occur during approved in water work window for Lake Washington (July 16-December 31) and is expected to take approximately 6 weeks to complete. The anticipated timing is between July 16 and September 30, but could shift depending on construction needs. Hours and Days of Operation Hours and days of operations will be restricted to the construction standards identified under Renton Municipal Code (RMC) 4-4-030C.3.b. The zoning for the project is Residential (R)-6 and R-8. Construction activities for commercial, multi-family, new single family and other nonresidential construction activities shall be restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight o’clock (8:00) p.m. No work shall be permitted on Sundays. RECEIVED 07/30/2025 amorganroth PLANNING DIVISIONDocusign Envelope ID: A6950DB9-F338-45C7-991A-0D2425171124 Kennydale Lakeline Sewer System Replacement Project: Construction Mitigation Description May 2025 Page 2 Proposed Hauling/Transportation Routes The work will be performed primarily in private residences and within the public roadway adjacent to the private residences. During the pre-application meeting (PRE 24-000037), no expected transportation requirements were identified. In general, haul and transportation routes will extend from approximately 2725 Mountain View Ave N to 3903 Lake Washington Blvd N. Measures to be Implemented to Minimize Dust, Traffic and Transportation Impacts, Erosion, Mud, Noise, and Other Noxious Characteristics Typical construction best management practices to minimize dust, traffic and transportation impacts, erosion, mud, noise, and other noxious characteristics are provided in the Project Narrative and Code Consistency Analysis. Any Special Hours Proposed for Construction or Hauling (i.e., Weekends, Late Nights) No special hours are proposed for construction or hauling at this time, although it may be proposed if necessary to meet permitted seasonal work restrictions (i.e. in-water work window for lakeline system decommissioning) Preliminary Traffic Control Plan No preliminary Traffic Control Plan is needed at this time. Docusign Envelope ID: A6950DB9-F338-45C7-991A-0D2425171124