ADVISORY NOTES TO APPLICANT
The following notes are supplemental information provided in conjunction with the administrative land use action.
Because these notes are provided as information only, they are not subject to the appeal process for the land use
action.
Planning:
(Contact: Alex Morganroth, 425-430-7219, amorganroth@rentonwa.gov)
1. RMC section 4-4-030.C.2 limits haul hours between 8:30 am to 3:30 pm, Monday through Friday unless
otherwise approved by the Development Services Division.
2. Commercial, multi-family, new single family and other nonresidential construction activities shall be restricted
to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through Friday. Work on
Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight o’clock (8:00) p.m. No
work shall be permitted on Sundays.
3. This permit is shall comply with the Bald and Golden Eagle Protection Act. The permitted is responsible for
adhering to the U.S. Fish and Wildlife Service National Bald Eagle Management Guidelines (2007) and /or your
U.S. Fish and Wildlife Service permit.
Development Engineering:
(Contact: Huy Huynh, 425-430-7384, hhuynh@rentonwa.gov)
1. See attached Memo dated August 22nd, 2025
Renton Regional Fire Authority:
(Contact: Corey Thomas, 425-276-9582, cthomas@rentonrfa.org)
Environmental Impact Comments:
1. Fire impact fees are applicable at the rate of $28.02 per student for day care use. Credit will be granted for
the existing office at the rate of $0.14 per square foot. This fee is paid at the time the building permit is
issued.
Fire Code Comments:
1. The fire flow and fire hydrant requirement is unchanged for the existing building. If a new addition is
proposed, the preliminary fire flow is calculated to be 1,500 gpm. A minimum of two fire hydrants are
required. One within 150 feet and one within 300 feet of the proposed larger building. One new fire hydrant
would be required for any new addition as only one hydrant currently exists. Applicant has not
acknowledged the requirement for a new fire hydrant and/or provided any preliminary plan to show
compliance.
2. For group E Occupancy, the occupant load would have to be less than 50 people and direct outside exits
doors would have to be provided from every room in which day care is provided. All exits shall be continuous
to a public way. If these conditions are met, no fire sprinkler or fire alarm system would have to be installed.
The applicant has not shown if this exiting requirement will or can be met as detailed plans have not been
provided and the comment has not been verbally stated as being able to be met. If this exiting requirement
cannot be met, fire sprinklers and fire alarm systems would have to be installed throughout the building.
3. Fire department apparatus access roadways are adequate as they exist. It appears that the neighboring
buildings utilize the existing driveway as a fire lane, thus this existing fire lane shall be maintained and
approved fire lane signage shall be maintained. Fire lane height clearance shall be minimum of 13 feet 6
inches.
ADVISORY NOTES TO APPLICANT
Page 2 of 5 LUA25-000246
DEPARTMENT OF COMMUNITY
& ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: August 22nd , 2025
TO: Alex Morganroth, Principal Planner
FROM: Huy Huynh, Civil Engineer II
SUBJECT: Radiance Learning Center
3507 NE Sunset Blvd
LUA25-000246
I have reviewed the application for the Radiance Learning Center and have the following comments:
EXISTING CONDITIONS
The site comprises of parcel 0423059204 of approximately 13,939 square feet. The site currently contains one
structure. The site is fronted by private property in the south, west, east, and NE Sunset Blvd to the North.
WATER: The proposed development is within the City’s water service area. There is an existing 12-inch water main
located in NE Sunet Blvd that can deliver a maximum flow capacity of 4.500 GPM (record drawing W-
031506). The static water pressure is approximately 67 PSI at ground elevation of 410. There is an existing
¾” water lateral (facility ID LAT-015790) and an existing ¾” water meter serving the parcel (Facility ID MTR-
016508).
SEWER: The proposed development is within the City’s sewer service area. There is an existing 24-inch concrete
gravity wastewater main located in NE Sunset Blvd (record drawing S-226809). There is an existing 8-inch
PVC wastewater main located in NE Sunset Blvd (record drawing S-359007). There is an existing 8-inch
concrete gravity wastewater main located on the parcel (record drawing S-003002).
STORM: The site is slightly sloped from the northeast to the southwest. There is an existing 12-inch stormwater
main located on the parcel (no record drawing available)
STREETS: The proposed development fronts NE Sunset Blvd along the North property line. NE Sunset Blvd is
classified as a Principal Arterial with a varies ROW width.
WATER COMMENTS
1. Civil plans for the water main improvements are required and must be prepared by a professional engineer
registered in the State of Washington. Refer to City of Renton General Design and Construction Standards
for Water Main Extensions as shown in Appendix K of the City’s 2019 Water System Plan. Adequate
horizontal and vertical separations between the new water main and other utilities (storm sewer pipes and
vaults, sanitary sewer, power, gas, electrical) shall be provided for the operation and maintenance of the
water main. Retaining walls, rockeries or similar structures cannot be installed over the water main unless
the water main is installed inside a steel casing.
• Improvement/alteration to the existing watermain on Sunset Blvd NE is not anticipated
with the proposed project.
ADVISORY NOTES TO APPLICANT
Page 3 of 5 LUA25-000246
2. Based on the review of project information submitted, Renton Regional Fire Authority has determined that
the fire flow and fire hydrant requirement is unchanged for the existing building.
• If a new addition is proposed, the preliminary fire flow is calculated to be 1,500 gpm.
One new fire hydrant would be required for any new addition. The new fire hydrant is
required to be within 50 feet of the fire department connection if FDC is required
3. Based on the information provided with the land use application submittal documents, the following
developer’s installed water main improvements will be required to provide domestic and fire protection
service to the development including but not limited to the items that follow.
• Installation of a “Storz” adapter on the existing hydrants within 300 feet of the
development if they are not already equipped with one.
• A Double Check Valve Assembly (DCVA) is required to be installed downstream of the
domestic water meter on-site
• Installation of a fire sprinkler stub with a doble check detector assembly (DCDA) is
required for backflow prevention to the building if the occupant loads exceed 50
students. The sizing of the fire sprinkler stub and related piping shall be done by a
register fire sprinkler designer/contractor. The DCDA shall be installed on private
property in an outside underground vault per City Standard Plan 350.3. The DCDA ma y
be installed inside the building if meets the conditions per City Standard Plan 350.3. For
the installation of DCDA inside the building, the DCDA location must be pre-approved
by the City Plan Reviewer and Water Utility Department.
4. The development is subject to applicable water system development charges and meter installation fees
based on the size of the water meters. Current fees can be found in the 2025 Development Fees Document
on the City’s website. Fees will be charged based on the rate at the time of Civil Construction Permit
issuance.
• The SDC fee for water is based on the size of the new domestic water to serve the project.
The 2025 water fee is $4,850.00 per 1-inch meter.
• Water service installation charges for each proposed domestic water service is applicable.
Water Service Installation is $2,875 per 1-in meter.
• Drop-in meter fee is $460.00 per 1-inch meter.
• Fire sprinkler service fee is $648.00 per 10inch service line, $3,238.00 per 1-1/2 inch service
line, and $5,181.00 per 2-inch service line.
• Final determination of applicable fees will be made after the water meter size has been
determined. SDC fees are assessed and payable at civil construction permit issuance.
• A credit will be applied to the existing service if abandoned.
• The full fee schedule can be found at:
https://edocs.rentonwa.gov/Documents/DocView.aspx?id=10067864&dbid=1&repo=Cityo
fRenton
SEWER COMMENTS
1. Sewer system improvement/alteration is not anticipated with the proposed change of use.
• The applicant is required to provide a recorded easement for the sewer main located
on the parcel. In the absence of an existing easement, a new easement must be
granted to the City.
2. The development will be subject to a wastewater system development charge (SDC) fee if upgrading or
addition domestic water meters are proposed. SDC fee for sewer is based on the size of the new domestic
water to serve the project. Current fees can be found in the 2025 Development Fees Document on the City’s
website. Fees will be charged based on the rate at the time of construction permit issuance.
a. The current sewer fee for a 1-inch meter is $4,025.00 per meter, 1-1/2-inch meter is $20,125.00 and
a 2-inch meter is $32,200.00.
b. SDC fees are payable at construction permit issuance.
ADVISORY NOTES TO APPLICANT
Page 4 of 5 LUA25-000246
c. The full fee schedule can be found at:
https://edocs.rentonwa.gov/Documents/Browse.aspx?id=8217302&dbid=1&repo=CityofRenton.”
STORM DRAINAGE COMMENTS
1. A geotechnical report and a Preliminary Technical Information Report (TIR) were not submitted with the Land
Use Application, as the total new and replaced impervious surface area is less than 2,000 square feet
• This project falls under Simplified Drainage Review and a Written Drainage
Assessment will be required at the time of Civil Construction Permit.
2. There is a 2024 System Development Charge of $0.92 per sqft. SDC fees are payable at construction permit
issuance.
TRANSPORTATION/STREET COMMENTS
1. Frontage improvements are required for all new construction with valuation in excess of $175,000. The
proposed development fronts NE Sunset Blvd to the North Property line
i. Pursuant to Exemption D.2 under RMC 4-6-060, this project qualifies as an interior
remodel and is therefore exempt from frontage improvement requirements.
2. Street lighting is required along all public street frontages for projects with more than 5,000 SF of commercial
space. See RMC 4-6-060 for street lighting requirements.
i. Streetlighting plan is not included as part of this submittal as the project consists of less
than 5,000 SF of commercial space improvements.
3. All existing and proposed utility lines along the property frontage must be relocated underground per RMC
4-6-090.
4. Refer to City code 4-4-080 regarding driveway regulations.
a. A minimum separation of 5 feet is required between driveway and the property line.
b. Maximum driveway slopes shall not exceed 15%. Driveways exceeding 8% shall provide slotted
drains.
c. The maximum width of a driveway is 30 feet exclusive of the radii of the returns and taper section.
d. There shall be no more than one driveway for each 165’ of street frontage serving any one property
or among properties
i. The submitted plan indicates two existing driveways located on the west and east
sides of the property. The applicant shall revise the plan to reflect the removal of one
driveway at the time of civil construction permit.
5. Paving and trench restoration within the City of Renton right of way shall comply with the City’s Restoration
and Overlay requirements.
6. Sites that generate 20 or more net new peak hour trips (either in the AM peak or PM peak) are required to do
a traffic impact analysis. The trips should be calculated based on the guidelines of the current ITE Trip
Generation Manual. Refer to the attached policy guidelines for traffic impact analysis for guidelines. If the
site generates 20 or more new peak hour trips in either AM peak or PM peak, then applicant should contact
the City to get information of the locations where traffic analysis is required. A preliminary traffic study was
submitted with the land use application stating that the site does not generate 20 or more peak hour trip in
either the AM or PM peak periods
a. Staff concurs with this conclusion and has determined that a traffic impact analysis is not
required.
GENERAL COMMENTS
1. The fees listed are for 2025. The fees that are current at the time of the respective permit issuance will be
levied. Please see the City of Renton website for the current fee schedule.
ADVISORY NOTES TO APPLICANT
Page 5 of 5 LUA25-000246
2. All civil plans shall conform to the current City of Renton survey and drafting standards. Current drafting
standards can be found on the City of Renton website.
3. A separate plan submittal will be required for a construction permit for utility work and street improvements.
All plans shall be prepared by a licensed Civil Engineer in the State of Washington. Please see the City of
Renton website for the Construction Permit Application and Construction Permit Process and Submittal
Requirements. Please contact the City to schedule a construction permit intake meeting.
4. A demo permit is required for the demolition of the existing building(s). The demo permit shall be acquired
through the building department.
5. All utility lines (i.e. electrical, phone, and cable services, etc.) serving the proposed development must be
underground in accordance with RMC 4-6-090. The construction of these franchise utilities must be
inspected and approved by a City of Renton inspector.
6. Retaining walls that are 4’ or taller from bottom of footing and stormwater detention vaults will require a
separate building permit. Structural calculations and plans prepared by a licensed engineer will be required
as part of the building permit review.
7. Paving and trench restoration within the City of Renton right of way shall comply with the City’s Trench
Restoration and Street Overlay Requirements.
8. Adequate separation between utilities as well as other features shall be provided in accordance
with code requirements.
a. 7-feet minimum horizontal and 1-foot vertical separation between storm and other
utilities is required with the exception of water lines which require 10-feet horizontal and
1.5-feet vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.