Skanska USA Building Inc.
Seattle Office
400 Fairview Avenue North
Suite #1000
Seattle, WA 98109
Phone (813) 299-1530
Web www.skanska.com
PUD SUBMITTAL
HAZARDOUS MATERIAL MANAGEMENT STATEMENT
a. A description of refueling of construction vehicles that will occur on the site and an inventory of
hazardous materials expected to be temporarily stored, dispensed, used or handled on the site.
There will be no refueling of construction vehicles on site.
The hazardous materials identified in the ‘good faith inspection reports’ will be removed with demolition
of the existing structures on the project site. The removal steps of hazardous materials will follow strictly
of those described in the reports and meet local, state and federal regulations.
b. A description of how the requirements in RMC 4 -4-030C7, Construction Activity Standards – Zone 1 and
2, will be met by the applicant.
This section is not applicable, as there will be no refueling of construction vehicles on site, nor any
storage, disposal, use, or handling of hazardous materials .
CONSTRUCTION MITIGATION DESCRIPTION
a. Proposed construction dates
Construction will begin in July 2026 and run through October 2029.
b. Hours and days of operation
Construction hours will be between 7:00 a.m. and 5:00 p.m Monday through Friday.
Work hours on Saturdays, if necessary, will be between 9:00 a.m. and 5:00 p.m.
No work is anticipated on Sundays/Holidays.
c. Proposed hauling / transportation routes
Please see attached route map.
d. Measures to be implemented to minimize dust, traffic and transportation impacts, erosion, mud, noise,
and other noxious characteristics
• Dust control – dust from earthwork and demolition will be controlled by watering during construction
activities. Dust from construction vehicles traveling will be controlled by providing stabilized
construction entrances.
• Traffic and transportation impacts – construction deliveries will be directed onto arterial roads as
soon as they leave job site. This will help reduce traffic impacts on residential streets. ‘Just-In-Time’
delivery method will be implemented as a measure to control traffic volume flows through
Skanska USA Building Inc.
Seattle Office
400 Fairview Avenue North
Suite #1000
Seattle, WA 98109
Phone (813) 299-1530
Web www.skanska.com
neighborhood streets. Delivery trucks will not be staging on arterial streets and neighborhood roads
that are close to jobsite.
• Temporary erosion and sedimentation control (TESC) measures required by City of Renton will be
implemented and maintained for the duration of the project. A TESC plan will be developed by
project’s Civil Engineer and included in the final permit set for City of Renton’s review and approval.
Contractor will follow the plan and install/manage the approved TESC plan.
• Noise impact will be controlled by following City of Renton’s noise level regulations. Requests for
variances from the requirements will be made by applying for permits when necessary.
e. Any special hours proposed for construction or hauling (i.e. weekends, late nights)
The project is not anticipating any work during special hours.
f. Preliminary traffic control plan
The project has not yet prepared a Preliminary Traffic Control Plan. Once frontage and crosswalk
improvements have been reviewed and approved by the City of Renton, a traffic control plan will be
prepared in accordance with CoR’s standards.
RENTON HIGH SCHOOL REPLACEMENT
HAULING / TRANSPORTATION ROUTE
Major freeway intersection
Route from job site Route to job site
Route to job site
(limited to steel,
concrete and facade)
Route from job site
(limited to steel,
concrete and facade)
RENTON HIGH SCHOOL REPLACEMENT
HAULING / TRANSPORTATION ROUTE
Major freeway intersection
Route from job site Route to job site
Route to job site
(limited to steel,
concrete and facade)
Route from job site
(limited to steel,
concrete and facade)