HomeMy WebLinkAboutChange Order - 1C.O.# 1 SUMMARY OF PROPOSED CHANGE: BID ITEM NO. Unit Type Est. Qty. Unit Price Total Amount A-100 LS 1 $14,588.00 $14,588.00 A-101 LS 1 $15,523.22 $15,523.22 Sub Total Sales Tax (10.3%) CITY OF RENTON Additional Quantities Under This Change Order Description Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT CAG#: CONTRACTOR: CAG-25-110 OMA Construciton, Inc. Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: PROJECT NAME:Maplewood Creek & Madsen Creek Sediment Basin Cleaning 2025-2026 Total Work assoiciated with Work Change Directive No. 2 including: Uncovering damaged areas of liner, cleaning of liner and prepartion of subsurface at damaged areas, and repairing/patching damaged areas of pond liner. 30-mil PVC Liner Repair $30,111.22 $3,101.46 $33,212.68 Re-establish Cover Over the Liner Work associated with Work Change Directive No. 3.including placement of washed rock across bottom of Maplewood Creek Sediment Basin to re- establish the pond bottom and approximately 1-foot of cover over the pond liner. https://cityofrentonwa.sharepoint.com/sites/DEPT_PW_Admin/Shared Documents/Surface Water Engineering/SW CIP Projects/27-4357 Sediment Basin Cleaning/110 Construction/Change Orders/CO_1/SupDocs/CO #1_CAG- 25-110 1 of 2 "!#        !         !             CAG-25-110, CO #1-25 APPROVAL SIGNATURES: Approved By: Date: Approved By: Date: Brandon Akers, Vice President, OMA Construciton, Inc. Approved By: Date: Approved By: Date: Ronald Straka, Utility Systems Director Approved By: Date: Martin Pastucha, PW Administrator Approved By: Date: Cheryl Beyer, Renton City Attorney $432,155.40 $432,155.40 ESTIMATED NET CHANGE THIS ORDER $33,212.68 Joe Farah, Surface Water Utility Manager Troy Solly, Project Manager ESTIMATED CONTRACT TOTAL AFTER CHANGE CURRENT CONTRACT AMOUNT ORIGINAL CONTRACT AMOUNT $465,368.08 https://cityofrentonwa.sharepoint.com/sites/DEPT_PW_Admin/Shared Documents/Surface Water Engineering/SW CIP Projects/27-4357 Sediment Basin Cleaning/110 Construction/Change Orders/CO_1/SupDocs/CO #1_CAG- 25-110 2 of 2 "!#          $   $    $   !         "    !               "  Approved by Cheryl Beyer via email 9/18/2025