HomeMy WebLinkAboutReinforcing Steel Field Report_2025-10-13-Lindbergh High School Field Improvements-25B121-01_000002Inspection Information:
Inspection Date:10/13/2025 Time Onsite:09:20 Weather Conditions:50, Sunny
Inspection Performed: Reinforcing Steel
Subcontractor:J. Scott Continuous or Periodic:
Sheet(s):Location / Area:
Sidewalk on East side of lower baseball field
Details:3 / F210 Level / Elevation:Foundation
Approved Plans Dated:
Report Profile:
Any Deficiencies Noted:Yes No Deficiencies Cleared:Yes No
RFI:Yes No Show Up:Yes No
Retest / Reinspection:Yes No Standby:Yes No
Remarks:
MTC on site as requested to visually inspect reinforcing steel for the sidewalk on the East side of the lower baseball field.
MTC observed that the sidewalk was reinforced per the following plan details:
3 / F210.
MTC visually inspected the welded wire mesh at the locations noted and observed that the reinforcing steel complied with the
approved project plans and specifications. MTC observed the reinforcing steel size, type, and placement. MTC will verify the final
clearances prior to and during concrete placement.
To the best of MTC inspector's knowledge, the abovedescribed work was performed in general accordance with project
specifications and approved plans.
Work in progress. Additional inspection needed.
✔
✔✔
✔✔
✔
Reinforcing Steel Field Report RS00000200Report #:
Burlington
777 Chrysler Drive
Burlington, WA 98233
Phone: (360) 7551990
Client:
Renton School District No. 403
300 SW 7th St
Renton, WA 98057
Project:
25B12101 (Bldg Permit: B25002218)
Lindbergh High School Field Improvements
16426 128th Avenue Southeast
Renton, WA 98059
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and
authorization for publication of statements, conclusions or extracts from or regarding our reports is reserved pending our written
approval.
Page 1 of 4Page 1 of 3
Inspection Information:Inspection Date:10/13/2025 Time Onsite:09:20 Weather Conditions:50, SunnyInspection Performed: Reinforcing SteelSubcontractor:J. Scott Continuous or Periodic:Sheet(s):Location / Area:Sidewalk on East side of lower baseball fieldDetails:3 / F210 Level / Elevation:FoundationApproved Plans Dated:Report Profile:Any Deficiencies Noted:Yes No Deficiencies Cleared:Yes NoRFI:Yes No Show Up:Yes NoRetest / Reinspection:Yes No Standby:Yes NoRemarks:MTC on site as requested to visually inspect reinforcing steel for the sidewalk on the East side of the lower baseball field.MTC observed that the sidewalk was reinforced per the following plan details:
3 / F210.
MTC visually inspected the welded wire mesh at the locations noted and observed that the reinforcing steel complied with the
approved project plans and specifications. MTC observed the reinforcing steel size, type, and placement. MTC will verify the final
clearances prior to and during concrete placement.
To the best of MTC inspector's knowledge, the abovedescribed work was performed in general accordance with project
specifications and approved plans.
Work in progress. Additional inspection needed.
Images:
✔✔✔✔✔
✔
Reinforcing Steel Field Report RS00000200Report #:
Burlington
777 Chrysler Drive
Burlington, WA 98233
Phone: (360) 7551990
Client:
Renton School District No. 403
300 SW 7th St
Renton, WA 98057
Project:
25B12101 (Bldg Permit: B25002218)
Lindbergh High School Field Improvements
16426 128th Avenue Southeast
Renton, WA 98059
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and
authorization for publication of statements, conclusions or extracts from or regarding our reports is reserved pending our written
approval.
Page 2 of 4Page 2 of 3
Inspection Information:Inspection Date:10/13/2025 Time Onsite:09:20 Weather Conditions:50, SunnyInspection Performed: Reinforcing SteelSubcontractor:J. Scott Continuous or Periodic:Sheet(s):Location / Area:Sidewalk on East side of lower baseball fieldDetails:3 / F210 Level / Elevation:FoundationApproved Plans Dated:Report Profile:Any Deficiencies Noted:Yes No Deficiencies Cleared:Yes NoRFI:Yes No Show Up:Yes NoRetest / Reinspection:Yes No Standby:Yes NoRemarks:MTC on site as requested to visually inspect reinforcing steel for the sidewalk on the East side of the lower baseball field.MTC observed that the sidewalk was reinforced per the following plan details:3 / F210.MTC visually inspected the welded wire mesh at the locations noted and observed that the reinforcing steel complied with theapproved project plans and specifications. MTC observed the reinforcing steel size, type, and placement. MTC will verify the finalclearances prior to and during concrete placement.To the best of MTC inspector's knowledge, the abovedescribed work was performed in general accordance with projectspecifications and approved plans.Work in progress. Additional inspection needed.Images:
Reported By:Randy Stevenson Reviewed By:Kevin Walters
✔✔✔✔✔✔
Reinforcing Steel Field Report RS00000200Report #:
Burlington
777 Chrysler Drive
Burlington, WA 98233
Phone: (360) 7551990
Client:
Renton School District No. 403
300 SW 7th St
Renton, WA 98057
Project:
25B12101 (Bldg Permit: B25002218)
Lindbergh High School Field Improvements
16426 128th Avenue Southeast
Renton, WA 98059
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and
authorization for publication of statements, conclusions or extracts from or regarding our reports is reserved pending our written
approval.
Page 3 of 4Page 3 of 3