HomeMy WebLinkAboutConcrete Field Report_2025-10-13-Lindbergh High School Field Improvements-25B121-01_000008Inspection Information:
Inspection Date:10/13/2025 Time Onsite:09:20 Weather Conditions:50, Sunny
Inspection Performed: Concrete
Subcontractor:J. Scott Continuous or Periodic:Continuous Inspection
Sheet(s):Location / Area:
Sidewalk on East side of lower baseball field
Details:3 / F210 Level / Elevation:Foundation
Approved Plans Dated:
Report Profile:
Any Deficiencies Noted:Yes No Deficiencies Cleared:Yes No
RFI:Yes No Show Up:Yes No
Retest / Reinspection:Yes No Standby:Yes No
Remarks:
CONCRETE PLACEMENT: Continuous Inspection
MTC inspector on site, as requested, to observe the placement of approximately 33 CY of concrete with Mix Design ID #1250AFG
supplied by Miles plant #202 into a sidewalk at the location noted above.
Concrete was placed via concrete pump, and was consolidated and finished by hand.
One set of five (4” x 8”) cylinders was cast for compressive strength test specimens. Refer to Report #5241 / Set 9, for field test
results and for more information.
To the best of MTC inspector's knowledge, the abovedescribed work was performed in general accordance with project
specifications and approved plans.
Work in progress. Additional inspection needed.
Images:
✔
✔✔
✔✔
✔
Concrete Field Report RCCON00000800Report #:
Burlington
777 Chrysler Drive
Burlington, WA 98233
Phone: (360) 7551990
Client:
Renton School District No. 403
300 SW 7th St
Renton, WA 98057
Project:
25B12101 (Bldg Permit: B25002218)
Lindbergh High School Field Improvements
16426 128th Avenue Southeast
Renton, WA 98059
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and
authorization for publication of statements, conclusions or extracts from or regarding our reports is reserved pending our written
approval.
Page 1 of 4Page 1 of 3
Inspection Information:Inspection Date:10/13/2025 Time Onsite:09:20 Weather Conditions:50, SunnyInspection Performed: ConcreteSubcontractor:J. Scott Continuous or Periodic:Continuous InspectionSheet(s):Location / Area:Sidewalk on East side of lower baseball fieldDetails:3 / F210 Level / Elevation:FoundationApproved Plans Dated:Report Profile:Any Deficiencies Noted:Yes No Deficiencies Cleared:Yes NoRFI:Yes No Show Up:Yes NoRetest / Reinspection:Yes No Standby:Yes NoRemarks:CONCRETE PLACEMENT: Continuous InspectionMTC inspector on site, as requested, to observe the placement of approximately 33 CY of concrete with Mix Design ID #1250AFGsupplied by Miles plant #202 into a sidewalk at the location noted above.Concrete was placed via concrete pump, and was consolidated and finished by hand.
One set of five (4” x 8”) cylinders was cast for compressive strength test specimens. Refer to Report #5241 / Set 9, for field test
results and for more information.
To the best of MTC inspector's knowledge, the abovedescribed work was performed in general accordance with project
specifications and approved plans.
Work in progress. Additional inspection needed.
Images:
✔✔✔✔✔
✔
Concrete Field Report RCCON00000800Report #:
Burlington
777 Chrysler Drive
Burlington, WA 98233
Phone: (360) 7551990
Client:
Renton School District No. 403
300 SW 7th St
Renton, WA 98057
Project:
25B12101 (Bldg Permit: B25002218)
Lindbergh High School Field Improvements
16426 128th Avenue Southeast
Renton, WA 98059
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and
authorization for publication of statements, conclusions or extracts from or regarding our reports is reserved pending our written
approval.
Page 2 of 4Page 2 of 3
Inspection Information:Inspection Date:10/13/2025 Time Onsite:09:20 Weather Conditions:50, SunnyInspection Performed: ConcreteSubcontractor:J. Scott Continuous or Periodic:Continuous InspectionSheet(s):Location / Area:Sidewalk on East side of lower baseball fieldDetails:3 / F210 Level / Elevation:FoundationApproved Plans Dated:Report Profile:Any Deficiencies Noted:Yes No Deficiencies Cleared:Yes NoRFI:Yes No Show Up:Yes NoRetest / Reinspection:Yes No Standby:Yes NoRemarks:CONCRETE PLACEMENT: Continuous InspectionMTC inspector on site, as requested, to observe the placement of approximately 33 CY of concrete with Mix Design ID #1250AFGsupplied by Miles plant #202 into a sidewalk at the location noted above.Concrete was placed via concrete pump, and was consolidated and finished by hand.One set of five (4” x 8”) cylinders was cast for compressive strength test specimens. Refer to Report #5241 / Set 9, for field testresults and for more information.To the best of MTC inspector's knowledge, the abovedescribed work was performed in general accordance with projectspecifications and approved plans.Work in progress. Additional inspection needed.Images:
Reported By:Randy Stevenson Reviewed By:Kevin Walters
✔✔✔✔✔✔
Concrete Field Report RCCON00000800Report #:
Burlington
777 Chrysler Drive
Burlington, WA 98233
Phone: (360) 7551990
Client:
Renton School District No. 403
300 SW 7th St
Renton, WA 98057
Project:
25B12101 (Bldg Permit: B25002218)
Lindbergh High School Field Improvements
16426 128th Avenue Southeast
Renton, WA 98059
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and
authorization for publication of statements, conclusions or extracts from or regarding our reports is reserved pending our written
approval.
Page 3 of 4Page 3 of 3