HomeMy WebLinkAboutPRE25-000313_ENG Comments (2)South Wastewater Treatment Plan (STP) Trailer Replacement PRE25-000313 Page 1 of 2
October 16th, 2025
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: October 16th, 2025
TO: Jill Ding, Senior Planner
FROM: Yong Qi, Civil Engineer III
SUBJECT: South Wastewater Treatment Plant (STP) Trailer Replacement
1200 Monster Rd SW
PRE25-000313
NOTE: The applicant is cautioned that information contained in this summary is preliminary and non -
binding and may be subject to modification and/or concurrence by official City decision-makers.
Review comments may also need to be revised based on site planning and other design changes
required by City staff or made by the applicant.
I have completed a preliminary review for the above-referenced proposal located at parcel(s)
2423049006. The following comments are based on the pre-application submittal made to the City
of Renton by the applicant.
WATER
1. Domestic water service to all of the buildings within the treatment plant are served by a privately -
owned interior water supply line.
2. Fire protection service to the plant is being provided by privately -owned interior water mains for
fire service hydrants. The private water mains are connected to the City’s water system at 2
locations, the first connection is at the west end of the SW 7th Street Bridge and the second
connection is near the access road along Monster Rd SW. There is an approved backflow
prevention assembly (RPBA) at each of the two (2) connections to the City’s water system.
3. The proposed trailers must be installed at least 10 feet away from the existing water mains. This
clearance is necessary to ensure adequate access for maintenance and repairs, as well as for
valve operations in the event of an emergency.
SEWER
1. A utility plan shall be provided to demonstrate that any proposed sewer connection for the
project will comply with the requirements for proper sewage disposal.
SURFACE WATER
1. Drainage plans and a drainage report complying with the adopted 2022 Renton Surface Water
Design Manual (RSWDM) will be required. Refer to Figure 1.1.2.A – Flow Chart in the 2022
RSWDM to determine what type of drainage review is required for this site. The site falls within
South Wastewater Treatment Plan (STP) Trailer Replacement PRE25-000313 Page 2 of 2
October 16th, 2025
the City’s Peak Rate Flow Control Standard (matching existing site conditions). The site falls
within the Black River drainage basin.
2. Drainage report and drainage plans based on 2022 RSWDM are required to be provided.
3. Storm drainage improvements along all public street frontages are required to conform to the
City’s Street and stormwater conveyance standards. Any new storm conveyance installed on or
off-site shall be designed and sized in accordance with standards found in Chapter 4 of the 2022
RSWDM. New storm drains shall be designed to account for the total upstream tributary area,
assuming developed conditions for onsite tributary areas and existing conditions for any offsite
tributary areas.
4. If the new plus replaced pollution generating impervious surface exceeds 5,000 SF, the applicant
will be required to provide enhanced basic water quality treatment. All proposed stormwater
facilities shall be designed in accordance with the current RSWDM at the time of civil
construction permit application. Separate structural plans will be required to be submitted for
review and approval under a separate building permit for all proposed detention and/or water
quality vaults.
5. Appropriate on-site BMPs satisfying Core Requirement #9 will be required to help mitigate the
new runoff created by this development to the maximum extent feasible. On -site BMPs shall be
evaluated as described in Section C.1.3 of the 2022 RSWDM. A preliminary drainage plan,
including the application of on-site BMPs, shall be included with the land use application, as
appliable to the project. The final drainage plan and drainage report must be submitted with the
utility construction permit construction.
6. A geotechnical soils report for the site is required per the 2022 Renton Surface Water Design
Manual Section C.1.3. Information on the water table and soil permeability (measured infiltration
rates), with recommendations of appropriate on-site BMPs per Core Requirement #9 and
Appendix C shall be included in the report. The report should also include information
concerning the soils, geology, drainage patterns and vegetation present shall be presented to
evaluate the drainage, erosion control and slope stabi lity for site development of the proposed
plat. The applicant must demonstrate the development will not result in soil erosion and
sedimentation, landslide, slippage, or excess surface water runoff.
7. Erosion control measures to meet the City requirements shall be provided.
8. The current City of Renton Surface Water Standard Plans shall be used in all drainage submittals.
9. The development is subject to a surface water system development charge (SDC) fee. Fees will
be charged based on the rate at the time of construction permit issuance.
a. The 2025 Surface water system development fee per dwelling is $0.94 per square foot of
new impervious surface, but not less than $2,350.
b. The developer will receive a credit for demolition of the existing structures.
c. The full schedule can be found here.
TRANSPORTATION
1. Based on the submittal items and project description, there are not anticipated transportation
requirements associated with this scope of work.
GENERAL COMMENTS
1. Fees quoted in this document reflect the fees applicable in the year 2025 only and will be
assessed based on the fee that is current at the time of the permit application or issuance, as
applicable to the permit type. Please visit www.rentonwa.gov for the current development fee
schedule.