FIELD REPORT
Project No. 6430.01 Page 1 of 3 Report ID 6430.01 S 2025 1010
Date Fri 10/10/2025 Weather 57°F, Raining
Arrival/Departure Time(s) 12:15pm - 12:40pm Travel Time (hr) 0.5
Project Name Grant Place
Location 1600 Grant Ave S, Renton
ESNW Rep., CESCL No.,
Phone No. & Report Statement
Nathan Dalton | ECO-3-10172203 | (206) 355-9308
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Client Info/Contact Apex Enterprises Group, LLC | Siki Chang
Permit No(s). WAR304993
Reviewed By MLP
Initials/Date
N/A
Field Supervisor Project Manager Initials/Date
Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the field representative’s
observations and testing of the contractor’s work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for
obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible
for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations,
is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
Type of visit: Daily Weekly Monthly Other
Precipitation since last inspection (approximate): 0.41 inches
Precipitation in last 24 hours (approximate): 0.01 inches
Phase of active construction (check all that apply):
Pre-construction Clearing, demolition, or grading Infrastructure or roads
Concrete handling Vertical construction Utilities
Off-site improvements Site temporarily stabilized Final stabilization
Was water quality sampling part of this inspection? Yes No
If “Yes”:
• Record results in the table below.
• Hanna Turbidity Meter No. 31
Monitoring
Point Monitoring Location Turbidity
(NTU) pH Description of
Discharge Notes
MP 1 Storm Vault (North Access) - - N/A No discharge from site
MP 2 Storm Vault (South Access) - - N/A No discharge from site
MP 3 Northern Construction Access - - N/A No discharge from site
eot ech nic al ngineering
nvironment al er vices
art hwork bservat ion esting
t ormwater ervices
Report ID 6430.01 S 2025 1010 Page 2 of 3
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
• Buffer zones around sensitive areas • Fence G N -Silt fence along the site perimeter
2. Establish Construction Access
• Fabric; quarry spalls
• Wheel wash
• Sweeper truck
G N -Site entrances are stabilized with quarry spalls
3. Control Flow Rates • Stormwater vault; facility
• Straw wattles
• Check dams
G N -Underground storm system installed
-Storm vault onsite
4. Install Sediment Controls
• Silt fence
• Vegetation
• Sediment ponds; traps • Treatment
G N -Silt fence along the site perimeter
5. Stabilize Soils
• Nets and blankets • Mulch; bark; rock
• Vegetation
• Plastic covering
• Water truck
F Y
-Cover exposed soil that is unworked for 7+ days
-Straw on exposed soil
-Reduced straw coverage in some areas; add
more straw
-Storm vault area is covered with gravel
-Stockpiles are covered with plastic sheeting
6. Protect Slopes
• Benching; track-walking • Pipe slope drains • Plastic covering
- - N/A
7. Protect Drain Inlets
• Catch basin inserts F Y -Maintain catch basin inserts
-Catch basin insert full of debris along north
perimeter; empty catch basin insert
8. Stabilize Channels and Outlets
• Channel lining
• Check dams • Outlet protection
- - N/A
9. Control Pollutants
• Chemical storage area covered
• Concrete handling
- - N/A
10. Control Dewatering - - -Notify ESNW prior to any discharging from site
11. Maintain BMPs F Y -See any details below
12. Maintain SWPPP & Site Logbook G N -Available upon request
13. Protect Low-Impact Development (LID BMPs)
• Bioretention rain garden facilities • Permeable pavement - - N/A
Do existing BMPs need to be modified or removed, or do other BMPs need to be installed? Yes No
List the action items in the table below:
Element
# Description and Location Action Required Completion
Date
2 Track out at south construction entrance Sweep frequently to avoid track out 10/10
4 Channeling and evidence of previous discharge at north
construction access Add silt fence 10/10
5 Reduced straw coverage in some areas Add more straw
7 Catch basin insert full of debris along north perimeter Empty catch basin insert
Report ID 6430.01 S 2025 1010 Page 3 of 3
BMP LEGEND
MONITORING POINT
STRAW
VERTICAL CONSTRUCTION
STORMWATER VAULT
STABILIZED CONSTRUCTION ACCESS
SILT FENCE
STOCKPILE
CATCH BASIN INSERT
PLASTIC COVERING
Empty catch
basin insert
MP 1
MP 2
MP 3
Add more straw