HomeMy WebLinkAboutChange Order - 3 (2)"!#
$
CAG-25-013, CO #3-25
Approved by Cheryl Beyer via email 8/22/2025
Change Order No. 3
Contract Title: Windsock & 243 Bldg. GA Apron &
Parking Lot Rehabilitation Project
Contract No. CAG-25-013
Page 2 of 2
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change: Adding Change Order Proposal 3.
Reason for Change: (COP 3) The airport recognized three line items in the bid that differed from
site conditions. (increase concrete removal volume, reduced excavation, increased Jbox
quantity) The airport also opted the replace the ADA parking stalls from Asphalt to Concrete.
This greatly improved the levelness of the ADA parking area. The airport also requested two
existing asphalt side walks that adjoined the new parking lot that needed to be replaced. The
airport also encountered soft soils at the Windsock apron and requested to add geofabric to
stabilize the soil. This will strengthen the soil to extend its useful life.
COP 3 = $31,971+ Sales Tax (10.3%) = $31,971+ $3,293.01= $35,264.01
Materials: See the attached price breakdown for the lump sum labor, equipment and materials.
Plans: N/A
Equitable Adjustment: N/A
Extension of Time: The Time for Completion is extended 0 Working Days.
Sections 1-04.4 and 1-04.5 of the 2018 WSDOT/APWA Standard Specifications shall govern
this Change Order. The Work of the referenced Contract is modified to include the changes
detailed herein. The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
܆ Plans
܆ Field Directive
܈ Change Order Quotation
܈ Estimated Change Order Cost
܈ Project Labor List
܆ Force Account Equipment Rate Request (DOT Form 422-010 EF)
܆ Equitable Adjustment Determination
"!#
Client:Renton Municipal Airport
Project:Gate & Perimeter Security Upgrades Project
Date:08/12/2025
By:BHB
Quantity Rectification Cost 5,234.50$
Additional Sidewalk Cost 11,776.50$
Geofabric Costs 6,000.00$
Concrete Removal WDSK $8,960.00
Total Cost 31,971.00$
WSST 10.3% 3,293.01$
Sum Total 35,264.01$
C.O. #3 Cost Summary
C.O. #3 Cost Summary
"!#
Client:Renton Municipal Airport
Project:Gate & Perimeter Security Upgrades Project
Date:08/11/2025
By:BHB
BID ITEM DESCRIPTION BID QUANTITY UNIT UNIT PRICE TOTAL AT BID ACTUAL ADD/DEDUCT TOTAL NOTE/REASON
B7 REMOVE CONCRETE 1375.00 SY 20.00$ 27,500.00$ 1684.55 $309.55 $6,191.00 CONCRETE UNDER ASPHALT
B11 EXCAVATION 2332.00 CY 50.00$ 116,600.00$ 2262.87 ($69.13) ($3,456.50)NET EXCAVATION UNDER BID QTY
B29 TYPE 2 JBOX 2.00 EA 2,500.00$ 5,000.00$ 3.00 $1.00 $2,500.00 SHORT COUNT AT BID PER DESIGN
SUBTOTAL 5,234.50$
TAX 539.15$
TOTAL 5,773.65$
PAY APP 2 BID ITEMS OVER 100%
C.O. #3 Quantity Rectifications
"!#
Client:Renton Municipal Airport
Project:Gate & Perimeter Security Upgrades Project
Date:08/11/2025
By:BHB
BID ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
B7 REM ASPHALT 62.00 SY $13.00 $806.00
B6 REM CONCRETE 47.06 SY $20.00 $941.20
B11 EXCAVATE-6 INCH ONLY 23.07 CY $50.00 $1,153.50
B13 BASE COURSE 33.19 TN $60.00 $1,991.40
B14 HMA 27.26 TN $190.00 $5,179.40
SUBTOTAL 10,071.50$
TAX 10.30%1,037.36$
TOTAL 11,108.86$
BID ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
B14 HMA 32.00 TN ($190.00) ($6,080.00)
B15 TACK COAT 2.00 GAL ($20.00) ($40.00)
B16 CURB AND GUTTER 15.00 LS ($60.00) ($900.00)
B19 FINAL STRIPE 150.00 SF $11.00 $1,650.00
B27 MULCH 25.00 SY ($25.00) ($625.00)
CO3-1 CONCRETE PAVING 140 SY $55.00 $7,700.00
SUBTOTAL $1,705.00
TAX 10.30%$175.62
TOTAL $1,880.62
ADDED SIDEWALK COST BREAKDOWN
ADA PARKING CHANGE FROM ASPHALT TO CONCRETE
C.O. #3 Sidewalk Costs
"!#
Client:Renton Municipal Airport
Project:Gate & Perimeter Security Upgrades Project
Date:08/12/2025
By:BHB
BID ITEM DESCRIPTION UNIT UNIT PRICE QUANTITY TOTAL
CO3-2 GEOFABRIC SY 3.00$ 2,000 6,000.00$
SUBTOTAL 6,000.00$
TAX 10.30%618.00$
TOTAL 6,618.00$
C.O. #3 Geofabric
"!#
Client:Renton Municipal Airport
Project:Gate & Perimeter Security Upgrades Project
Date:08/11/2025
By:BHB
BID ITEM DESCRIPTION BID QUANTITY UNIT UNIT PRICE TOTAL AT BID ACTUAL ADD/DEDUCT TOTAL NOTE/REASON
B7 REMOVE CONCRETE 0.00 SY 20.00$ -$ 618.00 618.00 12,360.00 CONCRETE UNDER ASPHALT
A9 EXCAVATION 3213.00 CY 50.00$ 160,650.00$ 3145.00 (68.00) (3,400.00)NET EXCAVATION UNDER BID QTY
SUBTOTAL $8,960.00
TAX 10.30%$922.88
TOTAL $9,882.88
C.O. #3 Concrete Removal at Windsock Apron
PAY APP 2 BID ITEMS OVER 100%
"!#