Loading...
HomeMy WebLinkAboutWTR2700434(1) TALBOT R EXT WATER MAIN - SPECS W-434 e'. « rr�. err$ SPECIAL PROVISIONS (Cont.) a of 6 i PP_)JECT CONSTRUCTION AND IDENTIFICATION SI(ilS_LOADYAY pRf„IECTCi7Nlr�,[ont. 1 Edition of Manual of Uniform Traffic Control Devices for Ste at% and Highways, Ur, "ad States Department of Transportation . Federal High ay Administration. The cost of furnishing and placing all construction and identi llcatton signs shall be incidental j. . � to the project and rm compensation will be made. ; LINES AND GNADES � The Engineer shall hove the right to make reasonable changes in the grades as they are shown ' on the drawings. Grades will be established in the fop of offset stakes at distenres not t i greater than 50 feet, set in advance of the work. Whenever work is in progress, the Contractor shall have in his employ a worker comTetent to set batter boards or other construction guides neap the line and grade stakes given by the Engineer. . .... a a Such employees shall have the duty and responsibility of placing and maintaining such constructIW, 1 guides. Batter boards set with an engineer's level shall he used far all lines set on a grade pf 0.50% or less, at least three sets of batter hoards shall remain Li Place during pipe laying 1 operations. If, through the Contractor's negligence, any stakes shall be destroy d and require resetting, a sum :hall be deducted from the Contractor's final payment equivalent to the extra M cost to engineering required for such ropiacement. X The laser method Of establishing grade nay be used providing: t ♦ 1. bequest fcr use, equipment and method of operation are suLmitted for City review and approval at least 5 days prior to use. 2. grades are checked at leas: once every So feet and at least 3 times daily by conventional M methods. 1 3. Frpplr enchorinn o1 pipe IS performed :n locations where a box i3 M1ei no used fee excavation. The Contractor shall arrange his work to allow a reasonahle time for the sotting of stakes for the next phase of his operation to prevent work Jelays while waning fcr construction guides. EASEMENT AND RIGHTS-OF-MAY The Owner will obtain all tenements and franchises required for the project. The Contractor shalt limit his operation to the areas obtained and shall not trespass on private property, t 1 Ir LAMO PROVIDED BY O1WR i The rupee may provide certain lards, as indicated in connection with the work under the contractI together with th.. -ight of access to such lands. The Contractor shall not unreasonahly encumber the pram"•ses with his equipment or materials. ^� a LAND PROVIDED BY CONTRACTOR f i The Contractor shall provide with no liability .0 the Owner any additional lend and access .I thereto not shown or described that may of required for temporary construction facilities or storage of materials. He shall construct all access roads, detour roads, or other temporary works as required by his operations. The Contractor shall co fl .g his equipment, storage of j materials and operation of his workers to those areas shown end .escribed and such additional I! areas as he may provide. I� 1 REST9RpTEOW OF STRUCTUgES_AND SURFACES i" a. General. All construction work under this Contract on easements, right-of-way, over private Property or franchise, shall he confined to the limits of such easarrnt, right-of way or franchise. i Ail work shall he accomplished so a to cause the least amount of disturbance and a minimum *mount of damage. The Contn.ItOr shall schedule his worn so that trenches across easements shall not be left rren during weekends or holidays and bench shall not be left open for more than 46 hours. 5i b. Structure . The Contractor shall rmnuve such existinn strucr as may he necessary for the Perfpaynce of the work *nd, if required, shall rebuild the str- -s thus removed in as nowt a li cond1'.10n as found with minimum requirements as herein specifi, hall a`so emir all exist- , inn structures which may be damaged as a result of the work uw L s contract. j r • ,PECIAL PROVISIONS (Cone.) 3o/ E D:LIVERY OF TICKETS Lont,�. 4 b. Yj_Other %gs k- Method for measurement and Payment for material brought to the site by any ether means will be determined by Contractor - Owner agreement before award of contract. SIZEi_WFJGM ANO LQAD RESTPICTIONS a All raptor vMicles of the Contractor, Subcontractors, and suppliers %hail strictly adhere to Ch. s6.11 of the Motor Vehicle Laws Of the State of Washington (1967 Edition and amendmrnts thereof) in regard to 511e, weight, and loads of motor vehicles. 'a Payment will not be made for any material that is delivered 11 excess of the legal weight for which the vehicle is licensed. Any gross violation of these regulations shall Are rrportad to the affected law enforcemrn• agent. The Contractor is to furnish to the City Engineer a ifstiny of all haul vehicles us on this project, listing the vehicle numher, license number, tare weight are licensed load limit:. S U9CONTRACTORS AND SUPPf,7_eS A list of subcontractors and suppliers that will be Involved with this project shall be given 0 Thisto hlistgmossttrbe receivedvbfor his ywthe F.nDtneerand Approval befoorrr iatethet contraafter the c ntractbe has been awarded. CHANGE ORDERS All additional work that requires canuansatiun to the Contractor for items that prices are not Included In the contract shall require a written change order before work may be done. The Contractor shall be responsible for acquiring the necessary change orrers that are required by any of his subcontractors. PRE dON$TRUCTION CONFERE'_F, Prior to the start Of construction, the Contractor, Engineer, all subcontractors. Utility Depart- ment, Telephone Company and other interested departments shall attend A precoistruction conference, elftm, Place end data to he determined after awardance of the contract. Subsequently a representa- of the Contractor will attend a weekly conference to review pronress and discuss any problems •ey M Incurred. The time, place and date to he established at the preconstructl on confer- FIELD OFFICE The Contractor shad provide a field office with heat, lights, telephone and ell weather auto. mobile Access and parkind in a central location on the job site for the use of the Eogineer. The field office should be of sufficient si•w to accommodate the inspertor and allow adequate additional room for mettinps of up to three (3) people. Al! expenses incurred in supplying the field office shall be considered incidental to the Project. SANITATION FAf„�ILITIES Sanitation facilities should be provided in the area of the field office to conform with Se o cti • 7.22 of the Standard Specifications. All expenses incurred in supplyt ml access, perking And n sanitation facilities shall he considered Incidental to the project and no compensation hail br mane. PROJECT .STRUCTIWI AND IDENTIFICATION SI CN6IR01{pUIY PROJECTS ONI.Yl The Contractor shall furnish and Install project identification signs on each And of the project one (1) week 1n advance of construction. The signs shall conform to the specifications as per attschAd sMets. One Sign of each type Shall he installed At, each end of the project, �orn.__t-yrtl v_n Signs The Contractor shall furnish and install construction signs which conform to Part A of 1971 1 SPECIAL PRDY1S10NS (Cont.) 7 of 6 EMCAYATED MATFAUL SPlkL AAGJHASTE SIT€1Cont. _ The Contractor shall be prepared to use "ter trucks, power sweepers, and related equipmert as downed necessary by the ..1ty Engineer to Alleviate the problem of lost spoils along the route. Prompt restoration of the route is mandatory. Ul1ST.AND MUM CONTROL The Contractor shall be responsible for controlling dust aM mud within the project limits and 1 on any street which is utilized by his equipment for the duration of the project. The Contractor shall be prenarM to use watering trucks, power sweepers and other pieces of equipment as deemed necessary by the Engineer, to avoid creating a nuisance. a U Dust and mud control snap be considered as incidental to the project, and no compensation will be made for this section. Comolaini,s on dust, rwd or unsafe practices and/or oroperty damage to private Ownership will be 1 trenamitted to the Contractor and prompt Action In correcting will be required, written notice of correction of complaint items will be called for should repetitive complaints be received by the City. CTATE SALES TAY If all norms in this contract are a part of the construction of a public road improvement as defined in Rule 171, issued by the Excise Tax Division of the State of Washington, the Owner • is exempt from the payment of sales tax on all items. The Contractor shall include in his unit bid prices any Compensating tax that must he paid. set Section 7.09 of the Standard Specifications. If this project is other then a public road construction, the Washington State Sales Tax shall Aptly and be a separate bid item. • SURY[YS Section 5.06 of the Standard Specifications shell I* amended by the Addition of the following sentence: 'The Contractor shall notify the Engineer a minimum of 48 hours in advance of the need for surveys." OYE0.T111E FIELD ENGINEERING When the Contractor performs construction work over the accepted eight (9) hours per day or forty (40) hours war week, or on any City holiday, and the work requires inspection, then the _ Contractor shall reimburse the City at the rate of W.nfi per hour The City shall have the sole authority in determining the necessity of having the overtime inspection, and shall notify the Contractor of intent and said costs will be deducted from monies due the Contractor on each monthly estinis te. • DELIVERY OF TICKETS aF All delivery tickets that ere required for the purpose of calculating quantities nor payment must be received by the fngiaer at the ties, of delivery. No payment will he made on tickets turned in After dote of delivery of material. e. BY Try�rk, a Payment will not be made for delivery tickets which do not show type of material, gross weight, :are weight, truck number, data, and inspector's initials. Scale certification shall he submitted as arty in the project as possible. f Each weigh station shall maintair a record of the truck number, time, data and weight of all trucks providing material to the project. The weight list shall be mairtAined In duplicate with Ome signed copy transmitted dell y to the City by the scale attendant. In isolated C4as where scale weight is not available, the inspector 56e11 measure the truck volume And certify as to Its full `ad delivery. e ' .., VMexmitmdWwWfv.wau wamrwa''- xw,ynmo.vww.2:..ns•..cuo-.h...,.,. -..�.,«..:.......,....�..._...:, ti R CITY 0i RfNTON SPECIAL PeOVISIONS Srfp!al IKOYS410nt hare/a fter contained supow4ade any confl4cting provisions Of the stAadlrO srtettf/cetloms, nd the faregoltlg anenhnentt to the standard speclflatinns ere hera.,y made a part of this contract. Wherever rsfersnce 1s ads .o the Engineer, such refertnte shall he construed to mean the %blic forks Director, City of Cantor or his duly authorized asslsUnt or assistants. a OESCRIPTIfIt OF HORR ,e The work to be performd under this contract consists of furnishing materials, equipment, tools labor and other hWk or Items incidental thereto (excepting any mnterlals, eo•ttp ot, utilities or sarvlce, If any, specified herein to be furnished by the City or Others). and performing all work as required by the c.ltract to SCCOr<Ian-0 with plans and specifications and Standard SOKifl- c-tions, all of which 6.0 made a sort bersof• a %TE OF BID OPENING Sealed olds will he received by the City of Renton. Washington, by filing with the City clerk, municipal Building. Renton, Washington, until 2:00 o'clock P.M„ August 17 , 1976, and will be noenM and publicly read aloud. a TTK 9F Cop ET1QN The Contractor it expected to diligently prosecute the work to &Vletlon In all parts and rt- qulrsomts. The project shall be completed within Sixty (60 ) working days. Prbvilad. however, that the City Council shall have the right upon request of the Puhl!c Works Department, City of Renton, Washington, to extend the time of cosiptation of said work, No extension shall be rand unless the same be in writing and accompanied by the written consent a to such extension by the surety on the bond of the Contractor. Tim lost In replacing Improper work or aterlal shall not furnish any grounds to the Contractor for claiming an extension of time for the completion of the work, and shall tot release the Contractor from damages or Its- bilities for failure to caglete the work within the time required. WWI SCRIMINWTI(MI IR_ QTNENI Cootiacts for work under this proposal will obligate the Contractor: and sutaontractors not to e discriminate to moloyment practices. NOTJFICATI" COIISTRUCTJ ON The.The. Contractor shall notify all property owners along the construction area, by moll, prior to construction. Names and addresses will be furnished by the timer. The Contractor snail further notify each occupancy in person a mi-ifeae of three days prior to construction in front of rack property. A rMkS OF w)Rw The workinq hours for this oro,lect w1 he limited to reek days during the period from 8r00 a.m. to a,10___ p.m , anus otherwise approved by the City. --- cXCAVATEn MtTCAJAk s IL,u kS,% TE ssTc I fns Contractor shall COnlaw to Section 4.06 of Standard Ssoctfltations In •.gord to waste sites. All material deslgooted by too EnglnaK to he wstee shall be hauled• dtaepM and spread At the locations selected by the C011trector, The Contractor shall hawe the rMeenHbility of obtainlnq h',s owr. waste site. All work Include•1 In this sKHon shall be Considered to be incidental to other Ito" of work and nu further simper, 141 will he ads. `he rt '• tlken to thn nit, slta shall M malntnlnM solely my t�v contractor in A Manner as destrl. •-low: i . s t tt( t t A SPECIAL PR071S1OV Special Provisions Description of Work :Lta of Bid Openinq A Time of Completion Nondiscrimination in Fmolop*nt Notification of Construction Hours of York Excavated Material Spoll Area/Waste Site Dust and Mud Control "Cate .Sales Tax t Surveys Overtime Field Engineering Delivery of Tickets Site. Weight and Load Restrictions Suhcortractors and Suppliers Change Orders 1 ' Preconstructlon Conference Field Office Sanitation facilities PrOJect 'oftstruction and ldentlfiret'on !1gns iooudway Projects Only) Line are Grade r Fasement and Rfght-of-Wav Lane Provided by Amer Land Provided Ly Contractor Restoration of Structures and Surfaces Side Sewer Policy r Traffic Contro; Removing Traffic and Street Signs Soft l"formation Salvage Awarding of Contract r Liquidated Damages Authority of the Engineer i �yj _ 1F a • � a try t ,1hy •M1F'aya�^' `ly �, I�$I a,� � W a ra � y�r� a.>S � ,dye 4 � qr e� �s'�" 4 i a >,♦ a� ` 9 � 4 r 'M ti u. a � f4 j_,`" e ,a S.� `� "�• „a.Rw ir5., � a .r$�a ��a ar a'�' v � °� �t '�• '� rv} C' 9 j p � Y�t SSw . 1>^^ ;4M :• 14 y w rtrL rs �a..,mW+ysw++n.�revd;^.5rhxfl6NN+ a A . y v IN CO AT SPECIAL P - • • . j r A • e J 1 'mOIEPAL PROVISIONS (Cont.' D15pUTCS AND LITIGATION lColt.). a served, before commencing wsrk under this contract. ACCEPTANCE OF NOP.r the Contractor ")I notify the Engineer in writing of the completion of the work whereupon the engineer will promptly, by personal inspection, satisfy himself as to the actual completto, Of the work in accordance w th the terms of the contract, and shall thereupon recommend to t10 Owner that the work is acceptable. Final determination of the acceptability of the work shall .` he made by the Owner. CONTRACT COMPLIANCE, REPORTS_ EEO 1� The Contractor will he required to complete and submit the following document before pr^---ts and/or final payments to the Contractor w.il he aoprovpd by the Public Works Director: City of Renton affirmative Action Report for Contrac toy/Subcontractor (Monthly Manpower Utilization Report) The owner will •ornish these forms to the Prime Contractor durinq preconstruction meeting. An Fquai Employment Opportunity Report Certificate shall be executed by the bidder with his hid proposal on thl' project and which comes within the provisions of the equal amployment opportunity regulations of the Secretary of Labor as revised May 21, 19M. The form of certificate will be furnished to the Contractor with the propnsal, stating as to whether he, his firm, association, copartnership Or corporation has participated in any previous contracts or suhcontractors subject to the equal opportunity clause and if so, whether or not he has submitted all reports due under applicable filing requirements. Failure on the part of the bidder to furnish the required certificate will be due cause for rejection of the bid. If a contractor to whom an award is about to be made, except for lack of an Fqual tsployeent Opportunity Report Certificate, rafusas or fails to promptly execute and furnish the required certificate within In days after notice by the Dire:tor of Public Works that same is lacking fror, his proposal, the proposal guaranty, in fora of bond, check, or cash which accompanied the bid, will be forfeited to the City. Whenever a contractor requests permission to sublet a part of any contract and such contract comes within the provisions of the equal wployment opportunity regulations of the Secretary • Of Labor, revised Nay 21, 1968, he shall obtain this certification from his proposal subcon- tractor and forward it together with such request. No s0contract will be approved before receipt of such certifiration from the subcontractor For this purpose, certification forms may be obtained from the Project Eny1roor assigned to this project. As WIPING DAYS AND CONTRACT COMDLFTI(Ni The special irovisions and contract agreement shall state the contract time in working days. A working de, is any day not otherwise defined herein es a non-working day. A non-working day is defined as a >aturday, runday, a recognized holiday, or a day on which the Contractor is specifically rLsuired by the contract or the City to suspend Construction. Recognized holidays shalt be as foll.ws: New Year's Day, Lincoln's Birthday. George Washington's Birthday, Memorial Day. July A, Labor Day, Columbus Day, General Election Day, Veteran's Day, Thanksgiving Day. .► and Christmas Day. When any of the above recognized holidays fall on a Sundays, the following Monday shalt be counted as a holiday. At the beginning of any contract. a tentative date for completion of contract work will M established, based on the date of award of the contract and the number of working days specified. Such date will be adjusted at required from time to time for nor-working days and txtensions of time allowed under the contract and is recognized as not being a forecast Of actual anticipated completion date. -' .r Is t 4 3 w O[NERAC PPOYISIOkS (Cent.) 'y DAOTFCT►i1N OF COiRPRCTOR'S wad AND vaovvarr_1r,nt.l_ , '` tractor's employees, and for his and his subcontractor's plant and eryui Pment and the method Of prosecuting the work. 9NFAIN) LF WEATHER AhD 01111711 CONDITIONS During unfavorable wither end other conditions, the Contractor shall pursue only such portions of the work as shall not be damaged thereby. fly n No Portions of the work whose satisfac:pry quality or efficiency will be affected by unfavorable .DnditionS shall be unstrucied while these conditions exist, unless by special means or orecau. tions acceptable to the Engineer, the Contractor shall he able to Overcome them. C.007PACTOR_S C I'cS OF CpiTNACT_00CUKNTS The Contractor will be supplied A the Owner with 5 sets of lan% and s t"Y p specifications. least one corny late set of contract documents including one full size set of drawings shall M kept at the site of construction in good condition and at all times available to the Owner and the Engineer. Additional copies of the contract documents, if required, will be furnished by the Owner at met cost of reproduction. DISPOTES AND LITIGATION Any questions arising between the Inipectur and the Contractor or his superintendent or Foreman as to the meaning and Intent of any part Of the Plans and Specifications or any contract document, shall he Immediately brought to the attention of the puhllc Works Director or his rooresentetive p for Interpretation and adjustment, if warrant". ! Failure on the part of the Public works Director or his representative to discover :no _ondemn or reject improper, defective or inferior work or materials, shall not be construed as an '. acceptar.�e of any such Work or materials, or the part of the inerovement In which the same may ( ' have been used. i TO present utaputes and litigation. it is furthe. agreed by the parties hereto that the Dubl.c Works Director Or his representative shall determine the quantity and quality of the swami kinds of work embraced in these improvements. he shall decide all questions relative to the execution of the wO0 AM the interpretation of the Plans and Specifications. In the went the Coutr 'tor is of the opinion he will he deuged by such interpretation, he . .Rhin three (3) days, notify the Engineer and the City Clerk in writing of the antici- gated nat,re and amount of the damage or damages. Tine Is of the assoKe in the giving of such notice. In tie event an agreameot cannot then be reached within three (3) days the City and the Contractor will each appoint an arbitrator and the two shall select a third, within 30 days thereafter. The findings and decision of the Board of Arbitrators shall be final and bi Ming on the parties. unless the aggrieved party, within ten (10) days, challenga% the findings and decision by serving and filing a petition for review by the Superior Spurt tof ring County. Washington. The ;rounds a for the petition for review are limited to showing that the findings AM decision: 1. Are not responsive to the questions submn•ted: L Is contrary to the terms of the contract or any component thereof, 3. Is arbitrary and/or is not based upon the applicable facts and the law controlling the issues sulmi tted to arbitration. The Board of Arbitrators shall support Its decision by setting forth in writing their findings and cone lust tons based on the evidence adduced at any such hearing. TM arbitration shall be conducted in accordance with the statutes M the State of Washington and court decisions governing such procedure. The casts of Such arbitration shall b, borne equally by the City and the rontrector unless it is the Board's majority opinion that the Contractor's filing of the protest or action is capri- clous or without reasonable foundation. In the latter case. all costs shall be bone by the Contractor. -he venue of any suit shell be in zing County, Washington, and if the Contractor Is a non- resident of the State of Washington, he shell designate an agent, upon whom DnocMS may to 1 fp In rat:u*"d: 5 T' ry ' *r r } ',ENERAL PROVISIONS (Cont.) WRITTEN NOTICE "+ Written notice shall be doomed to have duly served If delivered in person to the Individual, or to a partner of the firm, or to in officer of the corporation of the Contactor or owner, or to an executive official if the Owner Is a governmental body, or if sent by 'legisttrad limited States flail to the business address shown in the Contract nocuFents. CONTRACTOR'S PLART AND,EQUIPIENT 14 a The Contractor Slone 11 at all times be responsibt, for the adequacy, efficiency and suffici- ency of nos and his sv'.,contractor's plant and equipmen ow w t. The owner shell have the right to mete use of the Contractor's plant and equipment in the performance of any work on the site of the work. The use of such plant and equipment shall be considered as extra work and paid for accord- ingly. .: `.:. ATTFRTION TO W1RK The Contractor shall give his personal attention to and shall supervise the work to the and that It shall be prosecuted faithfully, and when he Is not personally present on the work, he shall IG at ill reasonable time be reprasantod by a competent superintendent who shalt twelve and obey all instructions o^ orders given under the contract, and who shall have full authority to execute the scone, and to supply au.terlals, tools and labor without delay, and who shall be the legal representative of the Contractor. The Contractor shall be liable for the faithful observance of any Instructions delivered to him or to his authorized representative. :t Wj DFVIATION FROM CONTRACT The Contractor shall not make any alteration or variation in or addition to or deviation or mission few the terms of this contract without the Witten consent of the Owner. SUGGESTIONS,TO,CONTRACTOR Any plan or method of work suggested by the Owhar or the Engineer to the Contractor but not loci 3 specified or required, if adopted or followed by the Contractor in whole or In cart, shall be used at the risk and responsibility of the Contactor; and the owner and the Engineer shall assuae no, responsibility therefore. _ERRORS AND OMISSIONS If the LontrattOr, in LIe cOurat t the Work, betgmei ewer. of any errors or missions in the contract documents or In the layout as given by survey Doinb and instructions, or if he becomes e aware of any discrepancy between the contract documents and tl-e physical conditions or F-nt local- ity, he shall imeiediately inform the Engineer and the Engineer, if 00 deeed it necessary, shall rectify the matter and advise the Contractor accordingly. Any e+rk done after such disrovery. until authorized, will be done at the Contractor's risk. 1NFo1mMTMi.TO GE_FORNi SMSM_€D iL CONTRACTOR Tie Contractor shall furnish a'II drawings, specifications, descrintive data. certificates, samoles, tests, methods, schedules, and esnufacturer's Instructio,s as Spe71fiCA11y required in the contract dotumeots, and all other int ematlon as Say reasovt iy be required Lo demonstrate fully that the materials and tquipment to be furnished and the methods of wort comply with the provisions thecontracttent of the requirements. thelcations Contattorand shall, by a stateemantS. If the f In writingh�cnpanylM theS Any deviation information, advise the Engineer of the deviation and state tie reason therefore. .A OAtMGE TO WORK The work shall ba under the Contractor's respmaihle case end charge. The Contractor shall bear all loss and damage whatsoever and frm whatsoever cause, exctlt that caused solely by the act of the Owner which may Occur on Or to bre work dur1w the fulfillment of the contract. if any such loss or damage occurs. the Contracto- shall immertlately make good any such loss or damage, and in the event of the Contractor refusing or negie.ting to do so. the Amer may itself or by two, employment of some other person make good any such loss or dtaege, and the cost Sod ea- ,,, pease of so doing shall be charged to the Contractor. P;DqECTION gf.MrpACTOtS WORK AND PIWDERTy The Contractor alone shall At All times be responsible for the safety of ;'Is and his wbcan- ry f JS qF n , 5 fl SFYFRAL PWIVISIONS (Cont.) WAGE SCHEDb1E(Conte Included, the Contractor and/or subcontractor will be ='iiled of the correct rates by the Industrial Statistician and approval will be withheld until a correct statement is received. Copies of wage rate approvals will be furnished the awarding agency, and the Contractor (and the prime Contractor in the case of a subcontractor) by the industrial Statistician. rich voucher claim sunmitted by a Contractor for payment on a project estimate shall state that prevailing wages have been paid in accordance with the preflled Statement or Statements of Intent on III* with the Department of Labor and Industries as approved cy the industrial Statistician. 1 Affidavits of Wages paid (SF 9843) are to br filed with the State Treasurer, or the Treasurer of the county or municipal corporation or other officer or person charged with the custody and d1s- ie bursament of the state or corporate funds as the case may he and two f2) conies of each Affidavit are to he filed with the Director of the Department of Labor and Induttrits. Attention: Industrial Relations D1vis1.•i, 1601 Second Avenue, Seattle. Whenever practicable, affidavits pertairinn. to a narticular contract should be submitted as a package. w PUBLIC LIABILITY AID MRDPERTY DAMAGE INSURANCE The Contractor shall obtain and keep in force during the terns of the contract, public liability ana property damage insurance to companies and to form to be approved by the City. Said insur- ance shall provide coverage to the Contractor, any subcontractor performing work provided by this contract, and the City. The City shall be named as in Addlti Coal Insured on said policy insofar as the work and obligations performed under the contract are. concerned The coverage so pro-vided shall protect against claims for personal inJurias. including accidental death, as wall as claims for property damages which may arise from any act or omission of the Contractor, or the subcontractor, or by anyone directly or lnlerec tly employed by either of them. The minimum. MI'Cy limits Of such Insurance Chill be as follows: Bodily injury liability coverage with limits Of not less than S1(N/,000 for bodily injury, in- cluding accidental death, to any one person, and subject to that limit for each person. In an amount not less than S300,000 for each accident; and propert damage coverage in an am cant of not less than t50,000 for each accident. A copy of the insurance policy, together with a copy of the endorsement Action the City as an additional insured, shall be provided to the City within a reasonable time after receiving notice of award of contract. PROOF OF CARRIAGE OF INSURANCE 1 Tha Contractor shell furnish the City with satisfactory proof Of carriage of the insurance required. ` ACT OF GM "Act of God" means so earthquake, flood, cyclone or other cataclysmic pLenomenonoftnatre A A rain, windstorm, high water or other natural phandnenon Y specific locality of the work, which might reasonably have heen V-Iclpated from historical records of the genrrol locality of the work, shall not he construed as in act of God. SHOP DRAWIN65_ The tam "Shop Drawings" shell refer to the pictorial description of the details of proposed materiels, equipment, methods Of Installation, or other constfuctfon prepared by the Contractor, s a subcontractor or a manufacturer and submitted for the approval of the Owner. DR_ %!AL whom the tare "Or Equal* is used herein, the Owner, or the owner on recommendation of the Cngineer, shall be the sole Judge ':f the quality arA suitability of the or"Posed substil:.tian. APPROYA3) A The term "Approval" shall mean approval given by or given pr>perly on the behalf of tht Owner. y la 1 ,c 1 g a: t VNERAL PPO9ISIMIS (Cont.) PAyKKT TO THE CONTRACTOR Payments to he made to the Contractor will be made in the manner outlined I,, Section 9 of the i Standard Specifications. Payments shall be made in Cash Warrants. Partial payments on estimates MAY be withheld until A work progress schedule as described in these General mrovlsinms has been received and approved. SCHEDULING OF WDRK Section 8.01 of the Standard Specifications shall he deleted and the foilow•ng inserted: ' Immediately after execution and delivery of the contract and before the first partial payment is (` made, the Contractor shall deliver to the Engineer, in estimated construction progress schedule In frrm satisfactory to the Engineer, showing the proposed dates of commencement and completion of each of the various pay items of work required under the Contract Donmwnts and the anticipated amount of each monthly payment that will become due to the Contractor in accordance with the pro- gress schedule. The Contractor shall also furnish periodic itemized estimates of work done for the purpose of making partial payments thereon. The costs employed In making up any of these _.. schedules will he used only for determining the basis of partial payments and will not be consid- ered as fixing a has'. for additions to or deductions from the contract. Should it become evident at any time during construction that operations will or may fail behind the sthedule of this first program, the Contractor shall, upon request, pra.Eptly submit revised schedules in the same form as sperified herein; setting out operations, methods, and equipment, added labor forces or working shifts, night work, etc., by which time lost will he made up, and confer with the Engineer until an approved modification of the original schedule has been secured. Further, if at any time any portion of the accepted schedule is found to conflict with the con- tract provisions, it shall, upon request, be revised by the Contractor and the work shalt be per- formed in compliance with the contract provisions. Payments of any further estimates to the Contractor after such request is made and until an approved modified schedule has been provided by the Contractor may be withheld. Execution of the work according to the accepted schedule of construction, or approred modificatsons thereof, is hereby made an obligation of the contract. ' WAGE SCADULE Ina prevailing rate of wages to be paid to all workmen, laborers or mechaw ics wployed in the performance of any part of this contract shall be in accordance with the prwisions of Chapter 1n.12 RCN, as amended. The rules and regulations of the Department of Labour and industries and the schedule of prevailing wage rates for the lecolity or localities where this contract will be performed as determined by the Industrial Statistician of the Department of Labor and Industries. i m are by reference made a part of this contract as though fully set forth heroin. Inasmuch as the Contractor will be held responsible for paying .he prevailing wages, it is import- tlye that all Contractors familiarize themselves with the current wage rates before submitting Lids bssed on these specifications. In case any dispute arises as to what arm the prevailing rates of wages for work of a similar nature and such dispute cannot be Adjusted by the parties in Interest, Including la or and management representatives, the matter shalt be referred for arbitration to the Director of the Department of Labor AM Industries of the State, and his decisions therein shall be final and cocclusi,•s and binding on all parties Involved In the dispute as provided for by RCN 19.12.16n, as amended. The Contractor, on or before the date of commencement of work, shall file a statement under oath with the (honer and with the Director of Labor and industries certifying the rate of hourly mega paid and to he paid each tlessification of laborers, workmen, or mechanics employed upon the work a by the Contractor or subcontractor which shall be not less than the prevailing rate of wage. Sucn statement and any supplemental statements which way he necessary shall be filed in Accordance with the practices and procedures by the Department of Labor and Industries. Prior to commencing work, each Contactor and each and every subcontractor shall file a sworn 1 Statement of Intent (SF 9887) with the Owner and with the Department of Labor and Industries as to the prevailing wage rate, including fringe benefits, for each Job classification to be utili- zed. The wage rates thus filed w'11 be checked against the prevailing wage rates as determine 7 by the Industrial Statistician of the Department of Lahor And Industries. If he wage rat" are Correct, the Industrial Statistician will issue in ackncwledgm"t of approval to ✓,e contractor and/or subcontractor with a copy to the awarding agency (owner). If any incorrect wage rates Are y s r Of ciry OF RFNTON GENERAL PROVisiM6 -� '-TAN)ARD SPECIFICATION 1 _ The CtaMard Specifications for Municipal Public Yorks Construction prepared by the Washington `•tote Chanter of the American Public Works Association, 1915 Edition, shall be hereinafter re- ferred to as the 'Standard Specifications" and said specifications together with the laws of the :Late of Washington and the Ordinances and Charter of the City of Renton, so far es appItcahle, are hereby included to these spec if as though quoted in their entirety and shall apply except as amended or superseded by these Special Provisions. � copy of theta Standard Spacifications is on file in the office of the Director of Engineeriig. Runicipal Building, Renton, Washington, where they may be examined and consultad by any interested to party. Wherever reference is made in the Standard Specifications to the Owner, such reference shall oe construed to mean the City of Penton, and where reference is made to the Enc'near, such reference shall be construed to mean the nlrector of Fngineering. Clty of Renton, or his duty authorized assistant or assistants. NOTE: The General Provisions hereinafter contaln,d shall be in addition or shall superseae pro- visions of the Standard Specifications in conflict there.lth. HEADINGS Headings to parts, sections, forms, articles and suLarticles are inserted for convenience of reference only and shall not affect the interpretation of the contract documents. ORDER OF PRECEDENCE Where conflicting informatten as to specifications 1s found in the "Standard Specification.." Plans and Provisions. the plans shall mld over the "Standard Specifications" and the Provisions shall hold over both the Plans and "Standard Spec lfications". FAILURE TO MEET SPECIFICATIONS t In the event that any material or workmanship does not meet the rcquirements or specifications, the City may have the option to accept such material or workmanship if the Director of Engineer- I" deems such acceptance to be 1n the best interest of the City, provided, the City may nego- tiate paye,ent of a lower unit price for said ma tercel or workmanship. FIELD CHANGES Any alterations or variances from the plans. except minor adjustments in the field to meet existing conditions shall he requested in Writing and may not he instituted untli approved by the Public Works Director or his rerresentatives acting specifically upon his Instructions. In the event of disagreement of the necessity of such changes. the Engineer's decision the" be final. PROTECTION OF PUBLIC LND PRIVATE inlLlr.IES AMO FACILITIES The Contractor shall conform to Section 5.09 of Standard Specifications in regard to Protection of public and private utilities. Location and dimensions sham on the plans for existing underground facilities are in accordance with the best available Information without uncovering and wasurinq, The Owner does not guaran- tee the size and location of existing facilities. It shall be the Contractor's responsibility to contact ell public end private companies having utilities and/or facilities In the vicinity of the construction Area. PUBLIC CONVENIENCE AND SAFETY The Contractor shall, at his own expense, provide all signs, barricades. guards, construction warnings, AM night lights In order to protect the public At All times from injury as a result of his operations. If the " -tractor should fail to maintain sufficient lights ani barricades In the opinion of the Engineer, the City shall have the right to provide these 119hts and barrif ::ales and deduct such costs from pmyr.ents due the Contractor. F GENERALrl PROVISIONS Al ppppp c� E p ffl r�9 r 1� w w r l If sand-cast, the aluminum will be left in its natural finish, or, if die- cast, the aluminum shall receive a painted aluminum finish. All lutinaires shall be mounted level, both transverse and longitudinally, as measured across points specified by the manufacturer. Leveling shall be accoaFlished after pule plumbing. The slip-fitters shall be capable of adjustinq through a S° axis for the required leveling procedure. Refractors shall be formed from heat resistance, high impact molded borosii- icated glass. Is ALUMINUM POLES r General :11 light standards furnished under this contract shall be aluminum davit style in accordance with Section 9.29.6(l) of the Standard Specifications and with these Special Provisions. • Design All poles and bracket arms shall be designed to support a street lighting luminaire with a minimum weight of 50 lbs. and to withstand pressures caused by wind loads of 85 miles per hour •ith a gust factor of 1.3. d i • All poles to be furnished shall maintain a minimum safety factor of 4.38 on yiell strength of weight load and 2.33 for basic wind pressure. All materials furs.shed shall be in natural polished, aluminum color. { i Shafts a a.� The pole shaft shall be provided with a 4" x 6" (minimum dimensions) flush hand-hole near the base designed to prevent loss of shaft strength and provided with a matching metal cover secured 'rith stainless steel screws or bolts. The hand-hole shall he located near the base and on the same side of the pole as the bracket arm. A grounding nut or provision in land-hole frame • for accommodating a threaded bolt for the purpose of attaching a grounding connector shall be provided on the inside of the shaft. After fabrication, the shaft shall have a mechanical strength of not less than the temper of the aluminum material utilized for the manufacture of the pole. All shafts furnished for a mounting height of 40 feet shall be a round, tapered • tube or ma) consist of a base section of round, standard tube not greater than S feet in length with a round, tapered tube permanently welded atop this section so that the 5 foot section and fabricated )oiut shall be capable of resisting at yield strength stress the bending moment of the round, tapered tube at its yield strength stress. All joints shall be flush and provide n • oven and clean profile. Anchor Rase ]� A one piece anchor base of adequate strength, shape and size shall he secured I I s; r �R as specified or intended. Any faults in the system shall be corrected and retested. The cost for performing these tests and correcting the faults shall be paid by the Contractor. 'e P mcgger test shall be performed in accompaniment with the Lnginaer. Illumination System Underground cunductorr for the 240 vo:t street lighting circuits shall be -. stranded copper, THW grade with 600 volt insulation of the size noted on the plans and wiring schedule. Type OF conductor, standard size s10 AWG, 600 volts rating two conductor shall be used between the fixture and pole base. Cost of the OF conductor shall be considered incidental to item e5 of , Schedule "E." All connections in light standard bases shall be made with an approved, field applied, waterproof Wye connector kit, capable of being disconnected without "i damage, equsl to ESNA Elastimold Style 82s or a bussman Iron Fuseholder with Y Type Breakaway receptable and insulating boats. Wye connector kits shall be supplied, wired in place and fused by the Contractor for every pole installed. A connector capable of being disconnected without damage shall ',e supplied and installed in the base of the pole. Grounding of Service Grounding at electrical services shall confor., to requirements of .he latest e. ition of the National. Electrical Code any all applicable state and local regulations. Luminaires Luminaires for this pro)ect shall be 400 Watt, Sodium Vapor. ballast shall be of the regulator type. Luminaires shall have a cast-aluminum housing providing for slip-fitter i end mounting. The luminaires shall attach to 2-inch pipe tenons on most arms. The reflector of all luminaires shall be a snap-on design manufactured of polished aluminum or mold from prismatically formed borosilicate glass. The refractor shall be as,.int.ed in a door frame assembly which shall be hinged to the luminaire and secured in the closed position co the iuminaire by means of an automatic type latch. The refractor ant door frame ass( ibly, when closed, t shall exert pressure against a gasket seat. Caskets shall be composed of material capable of withstanding temperature involved and shall be securely held in place. Glassware shall be of the refractor type with prisms. All luminaires shall have their coaiponent� secured to the luminaire frame with stainless steel mounting hardware (nuts, _ults, washers, hinges, etc.) . The stainless steel shall be AISi, 500 serie,, , chrome-nickel grade. The housing, g complete with integral ballast, shall be weather-tight. 7 ti Sb 1 :>(.HLl81LE E TECHNICAL PROVISIONS STREET LICKING & VEHICLE DETECTION Sco)e of Mork - General The contemplated work to be performed from these Plans and Specifications for this project are intended to describe a complete operable street lighting ie system including conductors, conduits, excavation, junction boxes, and material or equipment necessary for a complete and operable street lighting system. Also included .n these provisions is the installation of an operable vehicle detection loop. Standard Specifications The following special provisions are to be used in conjunction with the Standard Specifications for Road and Bridge Const*uctio-., 1972, hereinafter calla "Standard Spec i ications." Said tandard Specifications and the following Special Provisions are hereby made s part of this contract. The Special Provisions hereinafter contained shall super. ode any conflicting provisions of the Standard Specifications. Source and Quality of Materials The Contractor shall submit a request for material approval at the earliest possible date to the 'traffic Engineer. Sources and all required technical data should be submitted at this time. � Material that is not appro-ed will not be allowed on the job site. Substitution of specified material must be approved by the Traffic Eng;veer prior to ordering. t Inspection and Testing of Street Li.ghttng System The Engineer reserves the right to inspect the manufacturing process of the light standards. All provisions for this inspection shall be provided by the Contractor. i final inspection and acceptance of installed material will not be given until final installation and testing has been completed on the system. Apprcval to install materials and equipment must be obtaired from the Engineer before installation. Before final acceptance, the Contractor shall field test the installation for continuity and ground of each circuit, installation resistance (megger test between each circuit and ground), and function, to insure operation d t � t r t TECi{NICAL PROVISIONS (Copt.) CHANNELIZATION Plastic Traffic Buttons The Contractor shall furnish and install white and yellow plastic traffic buttons where it is shown on the plans, or where directed by the Engineer. Plastic traffic buttons shall have the size, color, and diswansions as shown on the r:ans and their installation shall conform to appli- cable provisions of Sections 9-20 and B-09 of the Standard Highway Specifications, 1974 Edition. Line Markers The Contractor shall furnish and install white, Type No. 1, plastic line markers where it is sham on the plans, or where directed by the Engineer. 1' Pour-inch, Type 1, line markers shall conform to provisions contained In Section 9-21.1 of the Standard Highway Specifications, 1974 Edit.i.on. 1� . 1 a,} 1� f f 4 TF,CNNICAL PRfT/ISIONS (font.) ��- MONUMENT, CASE AND COVER !Cont.) The cast iron case and cover shall be the Washington State Highway Depar_..ent ° g standard case and cover or approved equal. The Contractor shall furnish monument .ae and cover and shall excavate fcr installation af`er roadway completio: City forces will set the monument (, and shall bn notified a minimum of 24 hours prior to excavation. t.. After installation of the monument,the Contractor shall got the case and cover and grout with cement concrete the case into the excavation, all to the satisfaction of the Engineer. ' Exact location shall be determined oy ties placed by the City prior to any excavation for placement of the monument, case and cover. The unit price bid shall be complete compensation for all labor, equipment and materials required for procurement, excavation, case and cover installa- tion, grout and finish and no further compensation will be made. )I 1/7lEEIA HAIR AAl`S'S - TYPE "H" Wheelchair ramps shall be installed per details these soecificaticns and as shown on Std. Plan No. 148. The unit price shall be full compsnsation for removal of existing sidewalk, curb and gutter, including necessary sawcutting expansion material, concrete i cement and all other work required for full and complete installation. The j unit price shall include all labor, materials and equipment required and no further compensation will be made. i 5PECIAL Cement Concrete Sidewalk - 6" Thickness Special attention shall be paid to the co-struction of cement concrete. sidewalk adjacent to the driveway sections. Five (5) feet on either side of proposed driveway section shall be prepared to accept a six (6) inch thick cement con- crete sidewalk. This special section shall be constructed of high-early, air-entrained cement concrete. Unit price shall include all materials, labor and equipment necessary for full U and complete installation and no further compensation will be made. Cament Concrete Driveways All driveway sections shall be of monolithic construction. That is, urL and gutter and the driveway section shall be. poured at the same time. 'rho 1: material used shall be hiyh-early, air-entrained cement concrete. 1) i l i" . TECHNICAL PROVISIONS (Continued) , EARTH EMBANKMENT CONSTRUCTION n Earth embankment construction shall conform to Section 13-3.10E1 and 13-3.10E4 (Method C) except successive layers shall he of one (1) foot depth. No compen- sation will be side for this item. SHOULDER RA:LAST n Where, in the opinion of the Engineer, additional wr% is required to maintain isthe backfill shoulder slopes, ballast conforming to "Ballast - 2-1/2" Minus" i is these specifications shall be placed and compacted. Unit prices for shoulder ballast and compaction shall be per "Ballast - 2-112" 41 Minus" and no further compensation will be made. P CEMENT CONCRETE PIPE - C ' DIAMETER Cement concrete pipe of six (6) inch inside diameter shall be used for connecting to new catch basins and to existing storm drain. See specific 4 sections these specifications for connection to existing pipe. Non-reinforced concrete pipe shall conform to A . .T.M. designation C-14R Table II (extra strength) except as otherwise provided. Joints shall be j manufactured for use of Brant Rubber Gasket: .r equal. 4 Fittings shall be of the same material and class as the concrete pipe. Ilf The pipe shall be furnished and installed in accordance with Sections E0, 61 and 65 of the Standard Specifications except as modified herein. Six (6) inches of bedding material are required under all sewer pipe. 1 (� Bedding material shall be of material described in these provisions. Section 61-3.05 shall include the following: The hand-placed backfill around the pipe and to a point six inches above the crown shall be foot-tamped until it is unyielding. The remaining backfill, whether native material or borrow, shall be mechanically tamped with hand-operated mechanical or pneumatic tampers. tr All excavation, placing of pipe and backfillinq shall be done in accordance with i. . State of Washington Safety Standards for Construction Work, part C of the latest ! edition. The unit price bid per linear foot shall constitute full compensation for all tl labor, material, fittings, tools and equipment necessary for installation, including excavation, placing of pipe and mechanically tamping the backfill material. No further compensation will be. made. MONUMENT, CASE AND COVER lJ The precast concrete monument shall be installed per Section 50-3.02 of th,, standard Specifications except as modified herein: The monument shall be Renton Concrete Products precast monument or AT+r1)v111j egos 1. 1 � Illy ' 'i•':u LAICAL PROVISIONS (Continued) CATCH BASIN - TYPE 1I f a,fer to Section 64 and Standard Plan Number 55 except as modified here Lr_ Cast iron frame and grade shall be per Standard Plan NNIM16. (UK WD. XAMA) The unit price shall be full compensation for complete installation including j labor, equipment, materials and add..tional grouting as required for watertight • tonnection and no further compensation will be made. �s CONNECTIONS TO EXISTING PIPES i Where shown on the plans, or as directed by the Engineer, new drain pipes shall Le connected to existing pipes. The Contractor shall be required to i,reak into w the pipe, shape the new pipe to fit and regrout the opening in a work:aanlike manner. The new pipe will be hand grouted and finished flush with the existing pile to cause no restriction to downstream flow and form a watertight permanent seal. a The unit bid price for each connection shall be full compensation for all lab-,r, equipment, excavation, materials and all incidental costs necessary to connect to existing pipes and no Sirther compensation will be made. WHEELCHAIR RAMPS - TYF Wheelchair ramps shall be Listalled per details chese specifications and as shown on Standard Plan No. 148. The unit price shall be full compensation for all labor, materials, and equip-merit required for complete installation and no further compensation will be C made. RENOVE EXISTING CURB AND (AMER Where shown on plans or as directed by the Engineer, the Contractor shall be required to remove existing concrete curb ` / using existing expansion ioints I tb and whatever method deemed necessary to complete removal and disposal. The unit bid price per lineal foot shill be oomplete compensation includiny labor and equipment and no further compensation will be mrde. ROADWAY BORROW f1 Borrow to be used for earthfill for roadway construction shal). comply with section 13-3.11 of the Standard Specifications. , Borrow pits shall be of a source secured by the Coutractor but source and quality shall ua approved icy the Engineer. • �1 The unit bid price shall include procurement, haul, and all labor, equipment and materials for placement and compaction per specifications and no further romoensation will be made. n Tk:CllNICAL PROVISIONS (Continued) i ASPHALT C(AP-RZTF. PAVEMENT Asphalt Concrete Pavement (AR-4000) shall Le in r_cordanee with Section 14 of the Standard Specifications except as herein modified. Specification Designation 10 AR-4000 Absolute Viscosity0 140• F. Wise 3000-5000 )s Kinemat:_ Viscosity 0 275• E'. C5, Min. 275 Penetration at 77° F. , 100 g/5 Sec., Min. 25 Percent of original penetration At 770 F, Min. 45 • Ductility at 77• F. , CM, Min. 75 Test on Original Asphalt Flaahpoint, Pensky-Martens, dsg. F. , Min. 440 Solubility in Trichlorethylene t Min. 99 Installation shall be any method determined by Contractor as adequate to place asphalt concrete and compacted to withstand loads imposed by vehicular traffic. Payment will be made for "Asphalt Concrete Pavement" per ton, whir`t 61,411 be full compensation for furnishing all labor, equipment, materials and supplies required in the construction of asphalt concrete pavement, the furnishing and placing of asphalt tack coat, and all other work incidental to fulfilling the requirements described in section 5-04 and not set forth as bid Items. No further payment will be made. CEMENT CONCRETE SIDEWALKS (See Special Note at find of Section) p Cement concrete sidewalks shall W Class "B' as shown on Standard Plans detailed these specifications and constructed of air entrained concrete. • Payment shall be full compensation for all forms, materials, equipment and labor i required for complete installation and no further compensation will W made. If CEMENT CONCRETE CURB AND GUTTER ,s Section 40 of the Standard Specifications is revised to indicate that air-..ntrainad 6 concrete - Class "C" will be used for cons-ruction of curb and gutter. CEMENT CONCRETE Dlkwgmy (See Special Note at End of Section) Section 41 of the Standard Specifications is supplemented by the following, All cement concrete driveways shall be constructed of air-entrained concrete ►+ to a thickness of six (6) inches. 4 4 Y:C.11)LCAL VRGV15iON5 (Continued) I � f BALLAST -22-1/2" MINUS j ' ♦ The unit price shall include all costs necessary for furnishing and placement including compaction, and shall comply with Section 23-2.02 and 23-3.11,A of the Standard Specifications including tools, aqul).mcnt, labor and au tun als i as required and no further compensation will be made. i EMBANKMENT COMPACTION It is anticipated that all new embankment construction required on this project shall be made with material meeting the requirements of Bank P.un Gravel - Class �s "S". Construction requirements, measurement and payment shall conform to section 15-2.O1A excepting payment shall Le by the cuLic yard compactud which I will include all labor, equipment and materials required for complete compaction • of fill and no further compensation will be made. CRUSHED SURFACING COMM i Crushed surfacing course (1-1/4" minus) shall meet the requiruments of Section j 22 of the Standard Specifications. The Contractor si,all select the source, but N ♦ the source and quality shall be approved by the Engineer. i!) where additional "fines" are required, the Engineer may require 5/8" minus 1 crushed rock meeting specifications, in lieu of 1-1/4" minus at no change in unit price. i 41 The unit price per ton for Crushed Surfacing Course (1-1/4" minus) shall be full i compensation for all labor, equipment, materials and all incidental costs neces- sary to complete the work and no further compensation will be made. ii GRAVEL FOR PIPE BEDDING - CLASS "B" M Gravel for pipe bedding (pea gravel) shall have 100% passing the U.S. Standard 3/4 inch opening aroi not m. :e than 3% shall pass the U.S. No. 200 (wet &love) , 0-8% will pass the U.S. No. 8 sieve and 95-100% will )ass the U.S. Standard 3/8" opening with a minimum sand equivalent of 50. Gravel for pipe bedding shall consist of crushed or naturally occuring granular ie materials from sources selected by the Contractor. The source and quality of material shall be approved by the Engineer. Class "b" bedding shall conform to Section 61-3.03C2 of the Standard Specifi- i catsmV. N 4 Pipe Ledding material shall be placed to a deptt of 4" below :,ottOM of pips or of sufficient depth to eliminate loading ci bell a,,d extend to spring line of pipe. Thu bid price for bedding gravel in place shall be full CMpensation for delivery, placement, and compaction and no further tompansetion will be IJ made. MISCELLANEOUS ASPHALT The unit price shall be full compensaticn for procurement, haul, placement, com- paction including lebor and equipment necessary for complete installation and / further compensation will not be considered. 1 TECHNICAL PROVISIONS (MOBILIZATION K i Mobilization shall consist of all preparatory work and operations performed by the Contractor, including, but not limited to those necessary for the move- °'`''•'' ^ ment of his personnel, equipment_, supplies and incidentals to the project site for facilities necessary for work on the for project; Premiums on bonds and i insurance for the project, and for other work and operations which he must dorm or costs he must incur before beginningvarious A it eg production work on the items on the project site. fha lump rum payment shall be full compensation for all of the above and any other incidental cost incurred by the contractor while p-_�rforming mobilization as specified and no further compensation will be made. v UNCLASSIFIED EXCAVATION Unclassified Excavation shall include; roa.'way excavation, drainage excavation, ditch excavation and all other excavation as required and shall comprise all materials of whatever nature or character excavated within the confines of this project without further classification. E This item shall consist of excavating the roadway, driveway approaches and all work necessary for the completion of cuts, embankments and slopes, incluaing disposal of all surplus material. All work shall be performed in accordance i L with the alignment, grades and cross-sections shown on the construction plans, or as determined by the Engineer. ; The bid price shall include all labor, equipment, materials and tools required p for complete excavation as detailed or as directed by the Engineer and no P further compensation will be made. � p BANK RUN GRAVEL ) Bank Run Gravel - Class "B" shall conform to Section 26-2 of the Standard f Specifications and shall be used to replace unsuitable material within the A excavated roadbed where shown on plans or as directed by the engineer and shall be compacted to 95% density. (see "Roadway Borrow" thetc provisions) . The unit price per ton saall be full compensation for all labor, equipment, { materials, including compaction, and all incidental cost necessary for fur- I nishing and placing this item. r I .X 9 b. �a , TECHNICAL PROVISIONS i a I i i i J t � I p H 1 w SPECIAL PPOVIS104S (Cont.) F of f i TPFFIC CONTINIL�Cont�j The Contractor shall maintain detour routes and other routes used by his equipment h, ling materials to and from the aree. In addition, the foliwing shall eoply: a. Two-my traffic and pedestrian access will be raintained as directed ty the Engineer. e h. Local polite and fire departments &hail be notified, in writing, prior to construction. -. Iniress and egress for local residents shell be maintained at all times. ie °EPOV{NG TRAFFIC AND STREET SIGNS i The Contractor shall he responsible for maintaining and preserving all traffic and street signs. In the event it shall be necessary to remove Or relocate a traffic or street sign, the Contractor shall notify the Engineer of all changes made. All signs revic d shall be collected by the Ccn- tractor, who shall then notify the Engineer to have the Traff�.. Division remove these signs iron the project site to the City yard. - - When work has been completed and prior to said area being opened to traffic, the Contractor j shall notify the Engineer who small have the Traffic Oivisi bn replace all signs necessary. . The Contractor shall be responsible for the reDlacanwrnt of all signs lost or damaged due to his 1 neglect. I SOIL INFORM_AT_IM The bidder shall make his Own deductions and conclusions as to the nature of the materials co be excavated, the difficulties of making and maintaining required excavations, the difficulties which may arise from subsurface conditions, and of doing any other work affected by the subsurface conditions and shall accept full responsibility.It SALVAGE All salvage material as noted on the plans and taken from any of the discarded facilities shall, at the Engineer's discretion, he car-fully salvaged and delivered to the City yard. 1�x Any cost incurred in salvaging and delivering such items shall W. considered incidental to the 0 project and no compensation will be made. AWARDING OF r.ONTAACT Awarding of contract will be based on total sum of all schedules of prices. No partial bids will be accepted. L{M210ATE0 DNIAGES �r Section 8.08 is amended as follws: � Liquidated damages for failure to execute the contract as specified will be assessed as per follwing table: III! Contract Price Ltqu ldated Die_, 0 - S 50,000 S 50.00/workino day 3 50,000 - $1500M 5100.00/working day 1f150,900 - S250,001) s200.00/working day 250,00n and over S3M.nO/working day The above figures do not include costs for inspection, supervising. legal expense and court costs incurred beyond contract ccelptetton date. The cost of additional Inspection end super- vision shall he an amount equal to actual salary cost plus one hundred percent Mgt) for overhead. AUTHORITY OF TINE ENGINEER The Engineer shall have sole authority to change and/or regulate work. hours, methods or location of work to accommodate actual field conditions. i � I � 1 1 r: SKCIAL PROVISIONS (Cont.) 6 oft RESTORATION OF STRLCTtlRF6 AND SURFACES CoM,1 c. Easements Cultivated Areas and Other Surface I rovement�. All cultivated areas, either r. agnaTtu" o`r Tewns, andotTie�s�ace T�pror�ynents c�ro dmraged by ectipnt of the con- tractor shall be restored as nearly at possible to their original conditi". i Prior to excavation on an easement or private right-of-way, the Contractor shalt strip top soil from the trench or construction area and stockpile it in such a manner that it may be replaced by him, upon Completi OM of construction. Ornamental trees and shrubbery shall hm -arefully removed, 1 with the earth surrounding their roots wrapped in burlap and replanted in their orfniml mama it+ohs within 48 hours. All shrubbery or trees destroyed, or damaged, shall he replaced by the Contract- or with nm lariat of equal qualityy at no additional cost to the Amer. In the event that it is (` necessary to trench throueh any lawo areas, the sod shall he carefully cut and rolled and replaced After the trenches have been backfilied. The lawn &red shall then be cleaned, by sweepinn or other means, of all earth and debris.The Contractor shall use rubber wheel equipment similar to the small tractor type backhoes used by side sewer Contractors for all work, includlnq excavation and backfill, on easements or richts-of-way which have lawn areas. All fences, markers. matt boxes. or other temmrary, uh- stacles shall be removed by the Contractor and immediately replaced arter trench is mackfilled in their original position. The Contractor shall notify the (Amer and property owner at lam st m 24 hours in advance of any work done on eaaemorts or rights-of-way. All construction work urder the Contract on easements, right-of-way over private property or h franchise shall be Confined to the limits of such easements, right-of-way or franchise. All work small be accomplished so at to cause the least amount of disturbance and a minimum amount of damage. The Contractor shall schedule his work so that trenches across easements shall not be left open during weekends or holidays, and trenches shall root be left open for more than 48 hours. Deamm to existing structures outside of easement areas that may result from demetering and/or "r other construction activity under this contract shall he restored to Its original condition or it better. The original condition shall to established by photographs taken and/or inspection • made prior to .onstruction. All such work shall he done to the sett taken o, of the property � croaks and the owner at the expense of the Contractor. sfectI d. Streets. The Contractor will assume all responsibility for restorawion of the surface of 1 471 strn $ (travelled ways) used by him and damaged. In the event the Contractor does not have labor or material immediately ava;lable to make f necessary repairs, the Contractor shall so inform the Owner. The Owoer wi71 make the necessary I repairs and the cost of such repairs shall be paid by the Contractor. SIDE SFIiER ROCKY 4o side $errs will he installed until such time as that section of the main sewer pipe line to which the side sewers ere to be connectO has been tested by the Contractor and a recvrmndwn of mpproval for such section has been Issued by the Owner. The Contractor and the Owner understand and agree that following the issuance by the owner of a menmpra nnum, which memorandum pproves a specified section of the main pipe line, the Owner may authorise any side sower contractor, duly licensed by the Ohmfr, to Install and connect and test one or more side sewers to any such approved main pipe line. After the first side so or is artually connected to the main pipe line, the Contractor shall hot be held responsible for 'my foreign matter, debris. mud, and sewage which reaches the main pipe line within a previously anoroved section. However, the Contractor Is In no way relieves from the responsibility ar< nuarantee here4nhefore and hereinafter set forth for materiels, workmanship and repair to con- tractor-installed pipe line and appurtenances. It Is further understood and agreed twat durinq the Contractor's guarantee period if there are any indications of failure of the main pipe line or one or more side sneers, the burden of prod as to whether the failure Is within the main line or the side sewer or sewers, -hall rust with the ikwner; however, if investigation of such failure aondur.ted by the Owner discloses that such failure is on the MAIM pipe line, the Contractor shall make repairs and promptly reimburse the ♦ Owner for actual cost of such Investigation. f TRA/fl--�I_.ONTROL !! i `,ectioe 7.16 of the Standard Specifications is supplemented by the following, `` 1 a. Y r ri.QiNICAL PROVISIONS (CONT It SCIIFDULE W '•.��iC`j # IW-10 1IPE INiTALLAT10,4 (C0NT. ) j I. Connection to Existing Pipe and structures (cont.) i I the Contractor shall be responsible for the protection of all existing Piping and appurtenances during construction, and shall take care not to damage them or th-Ir protective coatings or Impalr the operation of the existing system in ' s any way. #� to TW- 11 EXCAVATION AND EMBANKMENT Construct embankments and carry out excavation fur pipe Installation as L,dicated on the plans. Conform to Section 15 of the Standard Specifications. Ttie ~ Engineer will allow greater than 9" layers if satisfactury compaction can be Roble i n,eJ. TW-12 RESTORATION OF IMPROVED SURFACES ' a. General Roads, streets, driveways, shoulders and lal other surfaced areas, removed, broken, caved, settled or otherwise damaged due to Installation of the improve- nxtnts covered by this contract shall be repaired and resurfaced to match the existing pavement or landscaped areas as set forth in these specifications. « The ends and edges of the patched and resurfaced areas shall meet and match the i.r�r� existing surface and grade, and shall terminate in neat, even lines parallel to, and at r!ght angles to the roadway. No piecemeal patching or repair will beS allowed. Damaged, disturbed or otherwise affected areas as defined shall haye ;- edges of existing pavement trimmed back to provide clean, solid, vertical faces, A free frc^ loose material . b. Areas to be Resurfaced (1) Existing asphaltic concrete surfaces shall be patched with asphaltic concrete over a crushed rock base course. (2) Existing shoulders and existing gravel surfaces shall be repaired with crushed rock surfacing. (3) Existing pnrtland cement concrete surfaces shall be repaired with Portland Cement Concrete to match the existlrg.(4) Portions of the trench which lie within the limits of the !reef improvement project will he improved to match the street subgrade require- i ments. c. Temporary MC Cold Mlx Asphalt MC Cold premixed asphaltic concrete shall be required in pavement for temporary patching on this project where directed by the Engineer. pF9 x • j FI MAA p K� f Mhu� i IE UIN ICAL PROVISIONS (CUNT. ) :CHEUULE W ,Ri h TW IO PIPE INSTALLATION (Cont.) i i C. Valves and Valve Chambers � i Valve instailation shall be In accordance with aectior 15 of the Standard Specifications except as modified herein. 6" and 8" and IU' Gate Valves shall include an 8" x 24" cast Iron gate valve box and extensions if required by the Engineer. Valves larger than la' shall be installed in vaults. The 12" gate valve assemblies shall include: 12" gate valve, 1" bypass assembly and precast vault. an the 16" and larger Butterfly valve assemblies shall include: large butterfly valve, and precast vault. Standard Details for I" bypass valve, and precast vaults are bound Into the Standard Details. Valve chambers shall be In accordance with Section 16 of the Standard Specifica- tions except as modified by details bound in these specifications. d. Depth of Bury The 24" D. I. water main shall have a 4' cover over the barrel cf the pipe. .he 12" and smaller water mains shall have a 3' minimum cover over the barrel of the s pipe. The new 24" DI water main will cross under the existing 18" C. I . water main and 24" storm main. e. Fire Hydrant Assemblies s Fire Hydrant Assembly shall include. C. I. Tee (MJxFL), 6" Gate Valve (FLxMJ), 6" C. I. Spool (PExPE) , 5" MVO Fire Hydrant (MJ connection) , 8" x 24" C. I. Gate Valve Box, and 3/4" Shackle Rod with accessories. Paint shackle rods as specified in Special Anchorage of this section. The hydrant shall be for a 4 112' bury unless otherwise noted on the Plan. Upon completion of the project, all fire hydrants shall be painted to City of Renton specifications white. t The City of Renton Standard Detail for hydrant assembly is bound in these a specifications. � f. Connection to Existing Pipe and Structures { - i Connections to existing piping and tie-ins are indicated on the drawings. The Contractor most verify all existing piping, dimensions and ele'•ations to assure proper fit. t The Contractor shall make all connections and tie-ins under the direction of the City of Renton Utilities Department. The Contractor must also provide any specials required to make a satisfactory connection. I 1 rF CHN ICAL PROVISIONS (CONT. ) 1f ',(.0FD1)I.E W ti FW A TRENCH EXCAVATION, BEDOIN6 AND SACKFILL (ConL.) e. Select Trench Backfill (coat. ) pipe and not the bell or collar. Any excavation in excess of the above requirements shall be replaced with the native material or select backflll , as directed by the Engineer ar+ at the Contractor's expense. ! i The price per ton shall be full compensation for selecting the source, furnishing ' and placing the material as outlined in Section 26.2-01 of the Standard Speclfi- cations. d f. Unsuitable Foundation Excavation Unsuitable material shall be excavated by the Contractor as directed by the :ngineer to give the constructed embankment full bearing on solid ground. Old fills, or wastes, unstable materials including logs, stumps, peat and muck will be excavated when in the Judgment of the Engineer these materials will Impair the stability of the embankment. All costs and expenses involved In displacement or removal of unsuitable materials shall be incidental to the embankment Installation. Neither separate or extra payment of any kind will be made fur storing, handling , hauling or manipulation of unsuitable excavation. j TW-O, DUST CONTROL Provide minimum 1 ,500 gallon capacity water truck with pressure spray system 111 s designed for street cleaning. Clean streets of dust and debris at end of working day. In addition provide sprinkling as nece:;ary to alleviate dust nuisance or as directed by the Engineer. Obtain fire hydrant meter from City Utilities Departme.�t and keep records of water use. TW-10 PIPE INSTALLATION a. General Conform to Section 74 of the Standard Specifications except as herein modified. Jointing shall conform to the manufacturers' recommendations. Cut pipe with approved pipe saws only. Keep pipe plugged except during actual pipe laying. The Inspector will stop work unless an approved plus Is on site and available. b. Spaciai Anchorage Provide concrete blocking at all fittings and horizontal or varticai angle points. Conform to the Standard Detail for General Blocking herein and the APWA Standard Details for vertical blocks. t 1 W HNICAI PROVISIONS (CONT. ) r1lf.DUI E V i TN-08 TRENCH EXCAVATION, BEDDING AND BACKFILL (Cont.) Ij I C. foundation Preparation and Bedding (cont.) conditions. The trench shall be de-watered and an Inspection made by the Enyineer to determine the suitability of the trench material. All costs for 1� -. dewatering shall be the responsibility of the Contractor. Bedding material shall be as required for Bank Run Gravel Borrow. l d, Trench Backfill and Compaction - General Excavated materials that are free from mud, muck, organic matter, broken bituminous surfacing, stones larger than 8 Inches in dimension and other dehris shall be used for backfill except where otherwise reaulred. (2) Initial Backfill In1t7 shall be placed around the pipe In layers not exceed- ing eight Inches in depth and each layer shall be thoroughly compacted by mechanical tampers to at least 95% of maximum dry density at optimum moisture j content as determined by Standard Proctor Compaction Test, ASTM Designation @ �4 0698-58T, Method D. All work related to the testing of the co,.tpaction, 'Nr including proctor tests and compaction tests shall be taken on the water trench areas. The locations of the tests shall ae selected by the Engineer. If une or more tests do not meet the specifications as stated above, additional tests will be taken as requested by the Engineer at the Contractor's expense. (;) Subse uent Bacll )! subsequen tkfiTckfill under street and shoulder areas shall be placed in lifts not exceeding 8 Inches in loose depth, and each lift compacted to at least 95% of maximum density at optimum moisture content as determined by ASTM Designation D698-58T, Method D. In-place density determination shall be made In accordance with ASTM Designation D1556-58T, except as otherwise approved by the Engineer. Testing for compactions In the improved areas shall be in accordance with the testing as stated in section on initial backfill. (4) Payment No separate or extra payment of any kind will be made for compaction, wetting, drying, water, or processing of materials, but shall be Included in the applicable unit price paid for the waterline In place, complete. j e. Select Trench Backfill f Select trench backfill for the pipe shall consist of crushed or naturally occuring granular material from, sources selected by the Contractor. The source and quality of the material shall be subject to approval by the Engineer. Select trench backfill shall meet requirements for bank run gravel Class "B" as outlined �n Section 26-2.01 of the Standard Speclficatl6ns. The horirmtal limits for measuring select trench backfill in place shall be the side of the excavation except no payment will be made for material replaced out side of vertical planes, 1 .0 feet outside of an parallel to the barrel of the ( i i TECHNICAL PROVISIONS (CONT.) { HEDULE W TW 07 REMOVAL OF EXISTING SFREET IMPROVEMENT (Cont.) C. Saw Cutting (cont.) the method of saw cutting shall be approved by the Engineer. TW-08 TRENCH EXCAVATION, BEDDING AND BACKFILL u a. General Trench excavation, backfill, foundation preparation and bedding for waterline and appurtenances sha, i be In accordance with the applicable provisions of Section 73, A.P.W.A. Standard Specifications, except as modified herein. b. Excavation The contractor shall inform and satisfy himself as to the character, quantit/, t� and distribution of all material to be excavated. No payment shall be made for i any excavated material which Is used for purposes other than those designated. !! Should the contractor excavate below the designated lines and grades without prior approval , he shall replace such excavation with approved materials, in an approved manner and condition, at his own xpense. The engineer shall have complete control over the excavating, moving, placing, and disposition of all material , and shall determine the suitability of material to be used as backfill . All unsuitable material shall be wasted as t - speclfied. Excavation of every description, classification and of whatever substances t encountered within the limits of the project shall be performed to the tines and grades necessary for embankment pipe, bedding and structures, and as indicated on the drawings. Temporary drains and drainage ditches shall be Installed to Intercept or direct surface water which may affect the pramotion or condition of the work. All excavated materials not meeting the requirements for backfill and all excess materials shall be was. .d as specified. No separate or extra payment of any kind will be made for storing, handling, hauling or manipulation of excavated materials. c. Foundation Preparation and Bedding 9 Foundation preparation shall be in accordance with the applicable provisions of Section 73, A.P.W.A. Standard Specificatiors, except that the bottom of the trench must be shaped to uniformly support the bottom quandrant of the pipe throughout Its entire length. In case unstable or unsuitable existing material is encountered at the trench ' bottom, the engineer may direct the use of borrow bedding material In accordance with Section 73.2.05 of the A.P.W.A. Standard Specifications. Wet trerch conditions will not necessarily be considered as an Indication of unstable 3 yy 1 it r,nNl(At PROVISIONS (CONT. I S(HEDULE W j. 2" Blow Oft Assemblies (cont.) Galvanized steel pipe and fittings shall conform to the requirements in Section 72 of the Standard Specifications. t rld-05 EXISTING UTILITIES If, in the prosecution of the work, It becomes necessary to Interrupt existing ,a surface drainage, sewers, underdrains, conduit, utilities, or similar under- ground structures, or parts thereof, the contractor shall be responsible for, and shall take all necessary precautions, to protect and provide temporary ser- vices for same. The contractor shall at his own expense repair all damage to such facilities or structures due to his construction operations, to the satisfaction of the engineer except that water and sewer lines will be repaired by the Utility Department at the contractor's expense. y TW-06 CLEARING AND GRUBBING -• i s Conform to Section 12 of the Standard Specification. Remove all debris; no on-site burning. In easements limit clearing to Items specifically Indicated by Engineer. Clear and grub only as necessary for construrtion operation or to construct fills where excavated material Is used for f, ll construction, grab as necessary to keep organic matter out of fill. TW-07 RLMOVAL OF EXISTING STREET IMPROVEMENT a. General t Conform to Section 52 of the Standard Specification. t b. Pavement Removal The Contractor shall Inform and satisfy himself as to the character. Quantity and distribution of all pavement removal. Removal of existing pavement shall .a cover all types and thicknesses of pavement. tt 6 Cut pavement, or other street and road surfaces only to minimum width which will permit the proper excavation and bracing of the trench. Allow passage of vehicular and pedestrian traffic. All pavement cuts shall be made smooth, straight lines or to nearest construction joint, and shall be made with clean ,) vertical faces. c. Saw Cutting The Contractor shall saw cut existing asphalt concrete pavement and cement con- crete pavement where shown on the plans or as directed by the Engineer. The depth of the saw cut shall be a minimum of 1 1/2 Inches for asphalt and ) Inc hes for concrete. ti rf0i NICAL PROVISIONS (CONT.) SCHEDULE W TW 04 PIPING MATERIALS VALVES AND FITTINGS ETC. (L ON i. ) g. Butterfly Valyes (coot ) to body with seat bond withstanding 75d pull. Valve bearings shall be sleeve- tight, corrosion resistant, and self-lubricating, Valve operator shall conform 1 to AWWA C504-70 standards and shall be of the traveling nut type designed fr buried service. Valve shall close with a clockwise rotation of the nut, Operator components shall withstand an input torque of 300 feet pounds at the extreme operator positions without damage. Butterfly valves shall be Henry Pratt Groundhog or approved equal. Approval must be obtained prior to bid opening. h. Fire Hydrants flt ;;yd,dnls shall be Corey lype (opening with the pressure) conforming to AW'/A C-SO4-64 with a 6" Inlet and a minimum M.V.o. of 5", two 2 1/2" hose nozzles with National Standard 7 1/2 threads per inch and one 4" pumper nozzle with the new Seattle Pattern 6 threads per Inch, 60° V. threads, O.D. thread 4.875 and root diameter 4.6263, 1 1/4" pentagon operating nut and opening by turning counter clockwise (left). Hydrants shall be constructed with mechanical joint connec- tions unless otherwise specified in bld proposal description. Fire hydrants shall be of traffic type and provision shall be made for drainage of barrel to protect units from freezing. Fire hydrants shall be such length s as to be suitable for Installation with connections to piping in trenches 4 1/2' deep unless otherwise specified. Fire hydrants shall be IOWA, Pacific states, or approved equal. Approval must be obtained prior to bid opening. i . Concrete Valve Vaults a General All valves 12" and larger shall be installed In a precast concrete vault. The vaults shall be grouted and sealed as well as knockouts filled with a non-shrinking grout (Embeco or an approved equal). All Vaults shall have steps and shall meet all current O.S.H.A. standards. s Precast Vault for 12" Gate Valve Enclosed In this document Is a standard detail 'or a precast concrete valve chamber for 12" gate valves. Precast Vault for ?4" Butterfly Valve Enclosed in this document is a standard detail for a large precast concrete butterfly valve chamber, k k J. 2" Blow Off Assemblies * a , Water main blow off assemblies shall be constructed as shouv on City of Renton "Standard Detail for 2" Blow off Assembly" as bound in these specifications. 1a„ 'a TE01 NICAL PROVISIONS (CONT. ) Sr,NEDULE W rw,04 PIPING MATERIALS VALVES AND FITTINGS ETC. (tort .). C. Ductile Iron Pipe Cont. Pipe thickness class shall be as required by the bid proposal description. ti d. Pipe fittings Cast Iron pipe fittings shall be Class 250, Cast Iron, (C. I.) as per ANSI Specification A21. 10-1971 (AWA C110-70 , for 4" through 12", and Class 150 for fittings larger than 12". i Mechanical joints shall be as per ANSI Specification A21 . 11-1y64 (AWA CIII-64). Flange joints shall be as per ANSI 816. 1 , with 125 pound drilling pattern. ) � e. Gate Valve ;" through 12" ( s Gate valves shall be cast iron body, non-rising stem, full bronze mounted with double disc gates. All valves shall be designed for a minimum water operating pressure of two hundred (200) pounds per square inch and shall conform to AWA r Specification C-500-71 and any subsequent modification thereof. Each valve %hall be "0" ring type, provided with a standard square operating rut, and shall open by turning counter clockwise (left) . The valves shall be IOWA List 14, a Mueller, Kennedy, Pacific States or U.S. Pipe Metropolitan Valve. f. Gate Valves 14" through ?4" Gate valves shall be of tensile strength cast Iron, non-rising stem, full bronze mounted with double disc gates. All valves shall be designed for a minimum 4 water operating pressure of one hundred fifty (150) pounds per square inch and shall conform to AWA Specification C-500-61, and any subsequent modification thereof. The gate valves shall be for horizontal installation on horizontal pipe. The valves shall be equipped with bypass valves, enclosed bevel gearing and grease case, cracks, rollers, scrappers, and a standard square operating rrut v,, 'rh shall open by turning counter clockwise (left). The bypass valves shall conform to the specifications for 3" through 12" Ga.e Valves. r g. Butterfly Valves Butterfly valves shall be of the tight-closing, rubber-seat type, Class 1509, and R most the full requirements of A.M.4.A. Standard C504-70. Valve bodies shall be of Cast Iron ASTM A126 Class 8, and with ends as indicated on the drawing. Valve disc shall be constructed of either alloy cast Iron ASTM A436 Type 1 (NI resist), or for valves above 12" for 200 psi leak-tight service shall be constructed of 316 stainless steel. Valve shafts shall be turned, ground and polished of 18-8 y stainless steel , and shaft diameter must meet minimum requirements establ;shad by A.M.V.A. C504-70. Valve shall have bonded seats, molded In, vulcanized, and bonded f t t 3f ILCNhIf,AI PROVISIONS (CONT.) ScNEDULE W ♦ TW-04 PIPING MATEAIALS. VALVES, AND FITTINGS ETC -'J. General All pipe sizes as shown on the drawings, and as specified herein, are in reference to nominal diameter, unless utherwise ,ndicated. ! sl i One type of pipe as Indicated below will be considered for this project. All pipe shall be fabricated to fit the plan shorn on the drawings. One type of pipe shall be used throughout the entire project except as necessary to match existing piping ! or as otherwise specified by the Engineer. Where relocation of or replacement of existing piping is necessary during construction, materials used shall match the existing, subject to the approval of the Engineer. All pipe, valves, fittings, and specials shall be for water working pressure as described In the following specifications and plans and shall conform to the 1 requirements of the applicable sections of the A.P.W.A. Standard Specifications, as modified herein. b. Cast Iron Cast Iron pipe 4" through 12' shall conform to ASA Specification A 21.6-1970 (AWWA CI06-70) and/or A21.8-1970) (AWA C108-1970) and shall be thickness Class 22 designed to ASA Specification A21. 1 method of design using a modulus of rupture of 45,000 PSI and a tensile strength of 21 ,000 PSI. The cast Iron pipe shall be designed for a working pressure 0 through 300 PSI for laying condition B and 5 feet of cover. 14" through 24" cast Iron pipe shall conform to the above specifications except designed for working pressure 0 through 200 PSI , and 24" pipe shall be thickness Class 23. All cast iron pipe shall be cement lined and sealed in accordance with ASA Specification A21.4-1964 (AWWA C104-64) 4" through 12" pipe shall be 1/16" cement lined and 14" through 24" pipe shall be 3/32" cement lined. » The pipe joints shall conform to ASA Specification A21. 11-1964 (AWWA CIII-64) . Pipe joints shall be push-on and/or mechanical as required by the Bid Proposal description, C. Ductile Iron Pipe Ductile Iron Pipe stall conform to ANSI Specifications A21.51-1971 (AWWA C151-71) Grade 60-42-10. Ductile Iron Pipe shall be cement lined and sealed In accordance with ANSI Specification A21.4-19 (AWWA C104-11) , 4" through 12' pipe shall be 1/16" cement lined. M The pipe joints shall conform to ASA Specification A21. 11-1964 (AWWA CIII-64). Pipe joints shall be rubber gasketed push-on and/or mechanical is required by the bid proposal description. i t'a TECHNICAL PROVISIONS • SCHEDULE M TW-I DESCRIP110N OF WORK FOR SCHEDULE V The work to be performed under this contract consists of furnishing all materials, equipment, tools, labor, and other work or items Incidental thereto and performing all work as required by Schedule W of this contract, In accordance with the plan, a sheet tabled Schedule W and these specifications and the Standard Specifications, i ' The contractor shall supply all pipe fittings, casing pipe, gate and butterfly vaaves, valve chambers, cast Iron valve boxes, all required accessories, concrete blocking, and shackle rods where required, vllve markers, and all other materials • necessary to make a complete water main Installation. This schedule consists of the Installatiuir of 825 I.f. or 24", 43 I.f, of 16", and 43 I.f. of 12" ductile Iron water main, valves and appurtenances (w-434) . TW-02 GENERAL STATEMENT a `his section of the Technical Provisions is detoted to features of on-the-site conditions which are peculiar to the facilities U be constructed for W-434 ` Talbot Road Extension Transmission Main. Articles, materials, operations, or methods mentioned herein or Indicated on the drawings as being required for the proJect shall be provided by the contractor, • and he shall provide each item mentioned or Indicated and perform according to the conditions stated In each operation prescribed, and provide therefor all necessary labor, equ!pment and incidentals necessary to make a complete and operable installation. No attempt has been made in these specifications or plans to segregate work a c"vered by any trade or subcontract under one speol'ilcetion. Such segregation and establishment of subcontract limits will be ;olzly a matter of specific agreement between each contractor and his subcontractors, and shall not be based upon any Inclusion, segregation or arrangement In, or of, these specifications. The contractor and subcontractor In each case Is warned that work Included In any subcuntract may be divided between several general specifications, and that • each general specification or sub-head of the technical specifications may includ^ work covered by two or more subcontracts or work In excess of any one subcontract . TW-03 STANDARD SPECIFICATIONS ° All work under this contract shall in general be performed in accordance with the a applicable provisions of "Standard Specifications for Municipal Public W7rks Y . Construction" prepared by the Washington State Chapter, American Public Wnrks Association, and In accordance with the requirements of the City of Renton, exe,-ot as otherwise amended, modified, or specified In these Sxcial Technical P mvisi,,,,.., Items of work not specifically covered In these Special Technical Provisions -.halt be performed in accordance with the requirements specified in the A.P.W.A. A Standard Specifications, and in accordance with the City of Renton requiranrnr,. ,b Wiring used in the i stallation of the loops shall be No. 12 ANC, stranded b' copper wire type USE:LP or TMfW. The lead-in between the roadway loop and the - F+ junction box at the side of the road shall be the same wire as used for the <'. f loops. Where shown on the Plans, the 1/c lead-in between the roadside Junction box and the loop amplifier housed in the controller cabinet shall be as specified in the Electrical section of these Special Provisions. At those locations where two No. 12's are to be placed in a conduit rim, they shall be ti' � • twisted two turns per foot. _>w • The detection loops shall be installed as specified in Standard Plan J-21e and as noted below: The wire shall be placed on approximately 1/4 inch of sand or on a 3/8 inch polyethylene cord at the bottom of the sawcut and covered • by a 3/8 inch polyethylene cord. The conductor placed in the Sawwt for the loop detection shall be measured by the linear feet of sawcut and payment made in accordance with Item 9, Schedule "E." • f a • ar � t °r Junction Boxes '♦ The contractor shall provide and install junction boxes of the type and at the locations specified on the attached plans. All junction boxes shall be installed in conformance with provisions contained in Section 8-20 3(6) of the Standard Specifications and Standard Plans J-18b. ' • .Measurement for "Junction boxes" will be made by the unit in place. i Payment will be made under: ,s "Type B Juncticn Box," per each. ♦ The unit contract price per each for "Type B Junction Hox" shall be full compensation for the furnishing and placcment of same, Foundation • Foundation for standards shall be as per details on Standard Plans and Specification Sheet J-17. Trench and Backfill i All trenches shall be backfilled in accordance with the applicable portions of Section 7-02.3(3), Section 2-09.3, Section 5-04, and Section 9-03.12 of the Standard Specifications. When trenching is bring accomplished within the sidewalk area, the backfill can be made with acceptable material from the excavation and shall be ♦ considered a necessary part of and incidental to the excavation in accordance with Section 2-09.3(1) E. of the Standard Specifications. The tamping requirements for roadway backfill shall apply. The City reserves the right to make additions or deletions of trenching which proves necessary for the completion. • Payment will be made under: "Trench and Backfill, _`" wide _ deep," per linear foot. The unit contract trice for trench and backfill per linear foot shall be fall 41 compensation for excavating, loading, placing, temping, hauling or otherwise disposing of the material as shorn on the Plans or as directed by the Lnginee, . Induction Loop %'chicle Detectors The Contractor shall provide all material for and install the induction loop vehicle detectors at the locations and in the configuration indicated on the Plans as specified below. lk i to the lower end of the shaft so that the base shall he capable of resisting at yield strength stress the bending moment of the shaft at its yield strength • stress. The base shall be provided with four slotted or round holes to receive the anchor bolts. Bolt cover(s) shall be provided with each pole. Anchor Bolts Four high strength steel anchor bolts, each fitted with two hex nut%, shall be furnished with the poles. Each anchor bolt shall have an "6" bend at the bottom end and be threaded at the top end. Threaded ends, all nuts, and �a washers shall be hot-dip galvanized. The anchor bolts shall be capable of resisting at yield strength stress the bending moment of the shaft at its yield strength stress. • ALUMINUM BRACKET ARMS General All bracyet arms furnished under this contract shall be aluminum of the same temper utilized for the polr-s in accordance with Section 9.29.6(1) of the t Standard Specifications, with these Special Provisions, 'nd with the Detail Sheet attached hereto. • Davit Style Bracket Arm and Assembly Single Arm The davit style bracket arm shall be a minima of 8 feet long as measured from the centerline of the shaft and shall incorporate a S' 9" radius bend. The outer portion of the arm shall be nearly horizontal to • S° above horizontal and shall be furnished with a 2-3/8" O.D. tenon with a maximum a length of 7-1/2" to fit the luminaire specified hereinafter. The pole end of the single davit arm tube shall be fastened securely to the top of the shaft producing ■ flush joint with an even profile. • Conduit The contactor shall provide snd install all conduit, Schedule 40 and necessary fittings at the locations indicated on the attached plans. The conduit installation shall be in conformance with Section 8-20.3(5) of the Standard Specifications. Measurement for "conduits" will be mile by the linear foot. Payment wall be made under: "Conduit, __" per linear foot. Conduit will be paid for at the unit contract price per linear foot In ploik, which price shall be full compensation for the furnishing and placement of same. , a 1 i EIv�(piN>S"9E.ViNO 7y� '" / A 4-eAFVD s oN Caw 4 ,0 do iaA.vsiTinNAL cued SNAL L Bf �� ./ 1.n.�sr�uc%iD NeNOL/T.✓il.O(LY � \ SA(4AWo 7b AUXUD A*117Ae Cr1S71.16 CIAZ Al6-W C.91Z9 \r. Y --. s+arc+✓vorEs/i,✓7 SO � /�" � N/NEEL CNJiR Z4AfR �/�•� 4of;rA 7 S,EZ'TyoN A tl P 1� Page 208 Standard Drawings A{I MA LT CONCRETE 01 OITUMIOYS S hANT Mix A[PLACEMINT PATCH CUT SMALL It VIR.ICAL AIO IN Y PEAKS WE LOOSINED ASPHALT .TO)" Y-ATICALLV STRAIGHT LINES AS 01RI(T10 .n �XISLIMC AIOXALT PAVEN/NT �-CONCACTI [1Ia11Yf CON(RITE PAYEMIPI n -i TYP[AMOE O2, "I NI DD OENICO V EXISTING RIGID Gate_ ,,, - 1T TM[ ticlMln i E COMPACTED TAOCM IACOPTLL - Y A L T I A H A T E A ASPHALT COMCRf TI 04 IITUXINOUS { PLANT MIX PAVEMENT AV IAC[MENT CUT $MALL If Yf RTIC AI PATCH / AN FS O 1N STAAIGMt LINTS CS t3i1NG AECT[0 �;. r'It VITM H/U HAT. AYE H[NI IUTTV-\ E I C-IATH YIr NfRNES NT ILOE IA OI US 1" E11L11N1 ASIMALS .- -�.�. -� —IAYEMIM rNISITINA COYCAE if PAVIM[MT _ / EXISTING RIGIC RASE-- J-- / Nr 1 WHERE YIDTN Or PATLM IS v nr LESS TRAM 1' COMPACTED SELECT MATERIALS Mott PATC+1 IS 3. OR-% I IN WINE" I COMPACTED THEN[H IACNPItL _ -- -AI' -D PAVEMENT LATH ASPHALTCEMENT CONCArTE PAVEMENT- CONCRIfE Sw PA(f A C T t R I A T t If T V P I ( A L P A T C H r 0 A A 1 C 1 0 P A L' I M . A T + I PA CO NIR[TE ON IITYMIMO YS EIISTIML ASP MAU (OM':A/1f PLANT M X.n Rf IIACEME NI Mi(N V. NIM fUArACf T / V' AIM (RISTIME OIL HAS l. __ -[LISTING IRS[ 1 y,. COMPACTED SELECT HATER/ALA _ COMPACTED TRENCH IAf A[1LL T Y P I C A L P A T C H r 0 1 Y L I A I I L E P A Y E N I M T CI NE RAI Ntl lC: 00 NOT Sl AIE CONCRETE Mfg SMALL It CLASS {.Stl-I/TIN.t.1. ON CLASS S11-I/}) YHI(NIV[t I$ SPECIVISO. PAYMENT -CEMENT 10"CAM CLASS ( 1 TOM PAVEN[HT PATCH", Pik CYIIC TARO. "ASONAN CONCRETE (LAGS Y' PON PAVEMENT PATCH", Pavement Patching PIR EOM -I'TVAINOUS PLANT NIA TOR PAY[RINT PATCH'•, If1 ION Standard Plan No 15 � 1 It } _. D E A. '5T6NpARD CATCH BASIhJ Atop CURE iNt-ET r CAST IRO(��R��Y�, ANjZ CO, ER O�vrnD c FovNOn� TJo k(g?,%o %Tp, Oa. Eqv�►�.. &T ). PUAS Foe rt At BaWbGG: C.oriiT¢. ((574) i EXTEN.SIOLA CSctsv sT w No C E5 - 15 on Equs�. t I ",/ Ci�.0r 4 BASIN cv2tj �NI�e_ Et SrC TIOtJ E}n.S� AEG TiOti� G uw-rw coNa No. CB- 15 Gast rcw4c No CB - 17 o/- Cpvr " k •rr _J p a Jf. t a (� F Tn �ry ' . .�, VP if • E/�JLLN�S QENrNO / *A UFPrAxos ON CAW } i � wrorN � r r i. ivwvs„-,o ��c caee ra✓srracriU vi�vca/TNrcv[cY 4e i SluAlU 7D B[L.n/a t✓i7N E�rs7i.e/6 O.Q. w/t`c/ cN.eB ol az r,-fe �t• `� - �"_ r.�!/1!%r OBI✓f/�lN? i WNFEL CNA/R �iIM� SEri�av A s �► t r f ALTER-- RN— A— T- E I EXPANSION JOINT I rro, "0 ya- Zt� ~vN EXAWiNON JOINT(TYP) �7q EXPANSION JOIN? 6 6" d S'._ 1 VAR EXPANSION JOINT fTM1 �_-6 • ORWY SECTION DROP SECTION A-A TOP OFPAVING P sr EXPANSION JnINT(TYp) I.,P FINISNED TO I" n. �Iu3 X w� ALTERNATE 2 u / •' EXPANSION JGINT(IYP! r GENERAL NOTES JOINTS+ JpIMs Mall be ploced as snare w / ) d.rsafsI or Ins Endmesr MATE9,AL5- $MII mMl sascd,col,onl CITY`OF RENT ON CO#CRETE Snoa ss be la day Clan 4(,-1/2) av- a r,,e,d ENG/NNERING Of lot, Par hoed cement coerresl STANDARD _ ✓ROCEDUMS, Forms,plec,np, Imunmq and cwvp, per Spsc.6cap'" MEASUREMENT Far caatrefe drbeway,thal area placed oehmd ca otnq CEMENT CONC. DRIVEWAY PAYMENT "Clmeef Ca 'ff@ D•rvewaT('nrcknsw,class).. Der Sa Yd. DESIGNED f—�ASC DATE 3.2 T DRAWN G LASE LRXD � NOTE DRIVEWAYS ARE G'TNICX, SIOEWALMS ARE e" TNICN APPROVED � r v r } ' TYPICAL SIDEWALK DETAIL 1 A I ` I/2 x 4 E.ponsion 4c-er o;- I/4" R At Joints Ma te 4"Eapo» T-- Core CurbGuSCae Lines 'ro Be Rod,41 To Materi l "or Curb Gul W 1/4"P A' Jpnte 1 ; r 12""e" ',ponson Motefiol 1/4"R At -Joints L t } 1 -Score Lines i '•W"- Widfh Of S,dewc% I I III e 1/2•k4" Expansion Moraat 1/4" R At Joints ' I/2k4"Expansion Motcrip v4" R At Joints 1', I Sbpe 1/2" I/4"/ rt Slope 1/2"R Cu )( S Erponbiy Mate nal Curb Return OMY 1/2 R7 v2' R �'>"Tl %•nrentenr Asis_r Pi - 4^ Porentenr 64 Per Pions j i i Stondord Cem Con Curb 4 Parkway—� t-Stondord Cent Conic C6rb B Gufter a Ginter SECTION A-A SECTION B-B 1 GENERAL NOTES where The Sidewalk Is To Be Placed Against The Curb 9 Gutter, The Joint Shoo Be Cold Joint Expon,•on Motetiol Shall Be Ploced At All PT's & PC'$ Of All Curb Returns, And It Shall Be Plaeed At Every Fourth Sidewalk Panel The Concrete Mix For Sidewalks Shall Conform To The Requirements Of Class 501/2), The Maximum Slump Shall Be 31/2" t y Standard LMawlwgt Page 191 all 111<1 '..aYf W[I Na,•Mv aN arw•'!e•M1p pILYNIM rM NOrfa 11•INr cM<I•R\\ f.0 t.A'w ax•a N V11e eq.yyra Ipp61xM L.N ,•v( rO.IrtEk� ayrw,l lY ry aN4wl Aq•p•Oww NyY1 a.N10YM •NO+IGYRf L. pry,(p rN YM aYRxL M 'N<'Nwr•t l0[01t pR UNNi(pw\•(11� f Y•� Ma Our r1• /! r•I i I.p V4 pl YIIrI R•[I OY L1Yk _ N?.N {eYMl6•.Ipf•p1 aY4t•NfC IY:1 rMM IMwp•Vf VN LaF111 I(tl ..�� w CWY NaINIMWY b Rv[ tRYaU1 aPM•Npy+�! • I l 1 r TYrntcl►L f91GT1dM._I01t tYAN_I WTTIERTY►E A pWr40Na Oral. r.A: rYpai 4Y)II\ ---- --• Y Lr DR '«OIrINK II ILM1I ORIr• - M p .Ya.eN Y`arl _L_ Ye44! Ial.1 1 «oN YOY. . IOYeV I r i t ' l � I I N•Nt'O!\ f L •vt 1.wo e111 I.I.�f pNa lv.\t L...... !+rroK lyyti( Iw.•Nl ,.r1 �. O N Wep o'LV NwRN xw ro u lwo M 1• YZ M•NmVY q' ' Jmw.v I,A L+<aD,ow•5 K rw.Ku.aR wru Va1a pN<,Ip Yr rNf INu'NIA o.p !I Sp MORE MR µ'I• NIbN iM TYIV 10141f r• ( D'V!aION IY•t1a k ub!+\a 70 IEa O•pi .q Janra .,I wo, R[R kIK'lwk TfI TNwr •,!�pv«•a«lr lM• fH NOH N !'br\eVKMY arKEYl,aNa aN•.. J•at N dn'N+•. Nkt•aa1L4r IWt nRa w-' GRNlRAI• DATAif NOTE TYPICAL 5EC. 7�PE A-I 1 ! - '• ••« ..� l„If». Ir•.r+f.vo wel ♦1•• <•wv M.•\wNwyal 1 ! ��^"'"y w i fN•Lt 11 DI Rva l•MY D•»lNYrl q♦«t Lr•a YHYYII� ' ! fKaoT 1N/Lr r SY•LL I1T[KV eNIV (%f MrV WRry1. YY<iLIN. lirllYlcGrw Y Dr.»,aw'. - ' } -' IYlhv1 WNr!rl { !r$ t r! do'.' olws 11 4pN[4M_YR q a ' ! yq•.rf- i Y �p.. Y a11. .f NO\ .O•sJRp•f[/Y.NW LRN rWN!O LfL O.nw U•wN -.-, -' Y a • Yf RO vw.v w r S OI r Gl I.lr Dl Ria I."IY L w 1I«r f •Yn +•1 ♦ o• .... •ry N+•a venal • I"" • a«u •I Fp•fb • cofr• aNw - So ! Gm aYi Al RD too, Da iq cONrf w<• I .a•ft +IKIYllrli• Cement Concrete CJrb 61 rrlf./u nul r[!{ IlOwwlNRil rµ rvlft allts2•uiN (Butler Type A . i lt•rlr� lrwL.LM c•»INr pbrtNit C'.N1 a1�Y11 na a($) YWIRf ROR r I y0 wi ay\f NNM1N !M/Op Ma,Y0YM 1fflM flyRYa. 6 7,IPe A-I r I N•M M MO 14.•NL• f Dr N W Kf. N rMEM 41•<•{'�•i 6Nf P•vr ! •. � «raw s<urR <!IIr 10 r.aa ) p Los i`I�-• Iql l�._-`��_-�..._.. ---� ...._-_- 5tCr1(lar d (ivi rip l t.y gg • STANDARD DRAWINGS 0 0 M • � 4 i �rJl1. q ,.i TECHNICAL PROVISIONS (CONT.) .� SCHEDULE 'd x _ S TV- I6 MEASUREMENT AND PAYMENT (CONT ) ,$1Z I. Furnishing and Installing MC Cold Min Asphalt f Furnishing and insta-ling MC Cold Mix shall be Incidental to this contr:,c,. l s i .` M. Resurfeclny of Asphaltic Concrete and Portland Cemen• Concrete Pavement and Bituminous Surface Treatment t meet patching shall be measured and paid for at the applicable contract price, per Asphaltic concrete, Portland Cement Concrete Pavement and Bituminous Surface Treat- ton, payment of which shall constitute full compensation for the resurfacing com- a Plete, Including subgrade preparation, preparation of and connection to existing 'Pavements, base course, tack coat, finishing and all necessary incidental aork � n. Furnishing and Installing 2" Blow Off Assembly The price per each 2" Blow Off Assembly shall constitute full compensation for valves, piping, concrete boxes, and all other necessary accessories for a com late installation as well as all connections, and Installation work necessary for a complete installation. t, we,• t` a J f Y t fill TECHNICAL PROVISIONS (CONT.) SCHEDULE W j , 1 ♦ TW 16 MEASUREMENT AND PAYMENT (Cont.) e. Installing Mechanical Joint Water Pipe, Cast or Ductile Iron The price per lineal foot for and Installing of Mechanical Joint water pipe, size and 4uantity listed in the bid schedule, shall constitute full compensation for I ♦ the water line, in place, complete, including: all pavement removal , excavation, i trenching, backfll �, foundation preparation, compaction, pipe, pipe laying and f jointing; pipe blocking, special 'shackling and bracing; sheeting, shoring, and i dewatering, fitting, connections to exist;ng piping, all surface restoration ( li excluding crushed rock resurfacing, concrete, asphalt'c concrete resurfacing, and including furnishing and installing all fittings. • f. Furnishing and Installing Gate Valves 12" and larger gate valve assemblies shall be measured and paid for at the applicable unit price por each, in place, complete, which shall constitute full compensation for valve, bypass alve, concrete vault, steps, and cone. valve marker, 6" or B" gate valve assem`' , valve, valve box with extensions, if necessary, and cone. valve marker; an- _11 other necessary accessories for a complete installation. Hydrant auxiliary valves will be paid for under Fire „ldrant Assemblies. g. Furnish and Install Butterfly Valves Butterfly valve assemblies shall be measured and paid for at the applicable unit price per each. In place, complete, which shall constitute full compensation for valve, vault, steps, valve markers, and a; l other necessary accessories for a complete installation. h. Furnishing and installing Fire Hydrant Assemblies Fire Hydrant Assemblies shall be measured and paid for at the applicable unit price per each, In place, complete, which shall constitute full compensation for tee, valve, valve box, spool , fire hydrant, shackiling, installation of blocking, bracing, drains, fittings, and all other necessary accessories for a complete installation, Including paint and two concrete guard posts. • 1 . Furnishing and Installing of Fittings Furnishing and installing o` fittings shall be incidental to the contract. j . Furnishing and Installing of Concrete Blocking • Concrete blocking shall be measured and paid for at the applicable contract price, per cubic yard, payment of which shall constitute full compensation for furnishing i the material In place, complete. k. Furnishing and Installing of Shackle, Rods Furnishing and installing of shackle rod., shall be Incidental to the contract. ha 1 s rtf,Nttlf.RL PROVISIONS (CONT.) q SCKLIULE W tW-14 DISINFECTION Cont. Section 74 of the A.P.W.A. Standard Specifications and shall owet the it,reptance of the State of Washington Department of Health. the initial concenrration of chlorine in the line shall be 50 parts per million and this solution shall be held for a period of 24 hours. Olslnfectlon of the entire water system installed * or disturbed under this contract, Including pipe, pipe fittings, valves and appurtenances, is required to conform with the specifications stated herein. The contractor shall pay for all test sampling and laboratory costs for bacter- iological tests as required by the State Department of Social and Health Services All testing shall be done by the Smith Tower Lab of the Department of Social and Health Services. TW-15 LLLANUP During the time that the work Is in progress, the Contractor shall make every effort to ma tntain the site In a neat and orderly condition. All refuse, broken * pipe, excess excavated material, broken pavement, etc. , shall be removed as soon as practicable. Should the work not be maintained in a satisfactory condition the engineer may cause the work to stop until the "clean-up" portion of the work has been done to the satisfaction of the owner and/or the engineeer. TW-16 MEASUREMENT AND PAYMENT a. General Unit or lump sum bid prices for all items shall include all costs for labor, equipment, material , testing, relocation and modifications to existing utilities and all incidentals necessary to make the installation complete and operable. b. Clearing and Grubbing Clearing and grubbing of the project site shall be incidental to this contract. I C c. Furnishing and Installing Select Trench Backf!II Material ) * The price per ton shall be full compensation for selecting the source, furnishing, hauling and placing the material as outlined in Section 73-2.OJ of the Standard ,peclflcations. No separate payment of any kind will be made for compacting, wetting, drying, water, processing of materials, or removal of unsuitable soils. d. Furnishing and Installing Tyton Joint Water Pipe, Cast or Ductile Iron A The price per lineal f.- or installing of Tyton Joint water pipe, size and quantity listed in the '-id schedule, shall constitute full compensation for the water line, In place, i mplete, including: all pavement removal , excavation, trenching, backflll , f. ,.ndation preparation, compaction, pipe, pipe laying and jointing; pipe blocking, special shackling and bracing; sheeting, shoring, and dewatering, fitrirg connctions to existing piping, all surface restoration excluding crushed rock resurfacing, concret., asphaltic concrete resurfacing, and Including furnish and installing a! ! fittings. 40 +s ie' rECHNIfAL PPOVISIONS (CONT. ) ,(HEDULE W 4 IW 12 RESTORATION Cf IMPP.OVED SURFACE; (Cont.) 1 '1• Crushed Rock Surfacing (cunt.) shall continue until the required finish sdrface and density Is obtained. The crushed rock shall be compacted to at least 100 percent maximum dry density at optimum moisture content. Water shall be added as necessary during blading and rolling operations to obtain th- required compaction. {{ u 4 u h. Portland Cement Concrete Pavement Conform to subsection 54-3-03 of tLe Standard p.r.ificatlons. Compact the sub- + 1 grade with mechanical tampe-s to 95% of maximum density as determined by ASTM + Designation D698, Method D. Use Class 6.5 (1 112) H.E.S. concrete, same thick- I - ness as or.,lnal concrete. Complete parch with Class 8 asphaltic concrete to f match existing sectton. TW-13 TESTING - a. General Hydrostatic pressure and leakage tests on the new pipeline shall be made in accordance with applicable provisions of AWWA C-600 54T or C603-64T and Section 74 of the A.P.W.A. Standard Specifications, except as modified herein. All equipment necessary to make the tests shall be furnished by the contractor, and the contractor shall conduct all tests under the supervision of the Engineer. Any blow-off assemblies which may be required for testlnq shall be supplied by the Contractor. b. Pressure Test Prior to acceptance of the system, the installation shall be subjected to hydro- static pressure testing as per the Standard Spe.:ificatlon for Cast Iron Pipe only. Any leaks or imperfections developing under said pressure shall be remedied by the contractor before final acceptance of the system. The contractor , It shall provide all necessary equipment and shall perform all work connected with the tests and conduct said tests in the presence of a Utllitiss Department Inspector. Insofar as practical , tests shall be made with pipe joints, fittings and valves exposed for Inspection. c. Leakage Tests Leakage teats shall be male after the pressure test has been satisfactorily cuTpleted on the new pipeline or concurrently with the pressure test. The hydro- static pressure for the leakage test shall be equal to 100 psi. TW-14 DISINFECTION Di,infection of the new water system shall be required prior to completion of the l.roject and shall be in accordance with A.W.W.A. Specification C601-54 and r i TECHNICAL PROVISIONS (CONT,) SCHEDULE W Ilt TW 12 RESTORATION Of IMPROVED SURFACES (Cont.) d. Private Driveways Private driveways, walks, and other surfaced areas shall be repaired, patched and i resurfaced as required for the c X q type of surfacing encountered. e. Maximum Patchlna Width ,a The maximum patching width in trench area will be 5 feet except where overlay or street construction is called for on the plans. Any patching done beyond thia limit will be done at the Contractor's expense. f. Asphaltic Concrete Surfacing The finished patch or new road section shall pro- lde a minim,m thickness of 2 inches of asphaltic concrete over 4 inches of gushed rock base course, q y Betore placement of the asphaltic concrete patch, the base course material shall be shaped to the same section and slope as to the finished grade and com- pacted to 100 per cent maximum dry density at optimum moisture content as determined by Standard Proctor compaction test, ASTM Designation D698, Method D. the asphaltic concrete patch shall be placed over the base course so as to obtain a minimum thickness after compaction of 2 Inches, and shall match existing surfacing. The asphaltic concrete shall be rolled and crossrulled to obtain r rw., w° thorough compaction. d :d, Base course material shall meet the requirements se; forth herein for crnshed rock surfacing. 'w Asphaltic 4 c concrete shall be hot plant-mix, conforming to Section j4, A.P.W.A. t Standard Specifications, Class B. Paving asphalt shall he Grade AR 4000 or Section 27. g. Crushed Rock Surfacing Existing r' sulders, and existing gravel surfaces snail be resurfaced with crushed rock so that a minimuin finished thickness of 4 Inches is obtained. The yyy finished surface shall match the slope, crown and grade of the existing surface. Materl,ils and placing shall be in accordance with the applicable provisions of Se tion 23, A.P.W.A. Standard Specifications except as modified herein. Ballast and maintenance rock will not be required. Crushed ruck surfacing shall in all respects meet the requirements se'. forth !n Section 23-2.01 , A.P.W.A. Standard Specifications. Water shall be added during rolling operations as necessary to secure required compaction. The crushed rock may be apread in one layer and shall be adequately bladed and mixed to obtain even distribution of the rock. Alternate Lading and rolling 1 ► ' a Y b M\ \ W/ IMP M1 ENDING OF / • . t i �. >f 1*6� ��, r �< 51� � I f•e yrr •���'����/ n lb ot iq 1.4 I • , I � "�; rf . I � fl*A� J tly c : r• , 1 y A/ �1� ,]�/�O � y •� :it Y q�4 'r 1 I\1 I 1 i �! q 7 r jo-r,eve�vR, lXY r i' 888��1 fk1;�i s"riff' YA 1.4 ' ' rr...- - - - `'�� f ' r BF,HIND CUR5 OR SIDEWALK OAPPROK. I8"xWxI6" METER BCX— �.. �N YALVE BOX S A } 1 _ _ 8 J, K t 1/4" DRI�LEO HOLE C -- M 6"-2" GALV. PIPE i. )NOT TO SCALE ) i ITEM T BRAND ANT DESCRIPTION 4 A2 081E STRAP SERVICE CLA.AP MUELLER i NOTE VALVE IRON BODY, 2­ SQUARE B CORPORATION_STOP iMUEIIER H-10013 1 _ OPERATING NUT f( JI 9DO GALV IRON PLAIN ELL _ 2 )2 REQ PER SWING) K CLOSE GALV IRON NIPPLE _ I II REQ PER SWING) Ct GALV IRON WATER PIPE VAR _ M 2" GATE VALVE IS- S) `MUELLER A� I SEE NOTE i N B•24 C I GATE VALVE BOX OLYMPIC I J4 1/4 GALV IRON PLAIN Ell WITH I STANDARD DFTA�� I/4" DRILLED HOLE S 2- 2 1/2 ADAPTER IIPT a HOW FOR WITH CAP_ANO--CHAIN i 2" F3LOvb OFF ASSEMBLY E CAST IRON METER BOX OLYMPIC 4 5112 I •enar law -. yyppet tri??2'!• se.tcva Bwvb w tt •.j •.xr wrtcaal B.+tOf vB S e y — Ftrl us to, 4B •Y tii �VL � ioB JI S ;// �I * e 30D p tli•ut h ,� 20 t 20 S B 300 0 ,, •w 41 M t0 250 0 t i 16' IY! •t nCenf Yt1j9C1:K Io, S 7 t •O .� � p t 4., 40 1 a 4 1 1 7i .L. Typo �Btocr^4 k'r-1'1 VMISN Nrr11 i i•O\e of Fb typt�0►t�vq �-- 511lakY Bses--- lar�Y te.slca 6nb� "'\6. n them s�. . � \✓Ij U .' n I p 5 jL t t y 200 t 4 JA1 CIO\\Dl1FflCalc n 1 STANDARD DETAIL r FOR BLOCKING OF CONVEX VERTICAL BEND +� t • :AP16 i FLG14M I t . t. • Thrult at_P tt n sn Vr_na_• Typical TlrrusC Plnck 1;ucat4, r.:'a 1 w e1 aaiT.w w � rri IK If% Ion N0 ►1sfit, 1230 a —Ise INO $me II 70 ' IN Itl1 01! SIN WI m tl1O IIN s e'—Itl —f1 ERN MIN ism SO y 1a u09 K NN ae ion t"—I flsr "is Ion uH 1V10 NN tI1'0 ►III non � � n the IMe Y.w 1N0 fe' N K% IOm K" %]t Tf IN INK IIKO »0 Nf0 IN Il%0 mItl KH 4010 i00 1H00 IP% N`0 Ulp Ir- N If WO IH00 10600 17M Irr� I00 1]MIN1300 mN0 Itx00 .f0/ �' IN IHN x1e00 qN0 0310 IN efaa _ :aaas 11xao n» .sesr- la W 1000 S[]00 14M I1f0 IJt $K00 100 1f100 1W Ilia "M Isw IaaO . f00 ff'NO I1m I7r00 __Y 80 _ F it— K ltw f]I00--IN00 1370 Ise Me 3`10 Ir7m0 ION --- �•• IK t7m NI0 21100 ICNJ - l 100 uum m It100 fff00 IINO_ If—K 10M 41m x1900 -- 111m ¢I M %101 I%K 1e00 14M 01) IN 11000 KNO IGIN 11700 f10 _ %100 N100 !0)00 Iar00 70'— Y 1{700 61 we 30100 Ia100 IN 0f00 NI0 %HO 11,100 Its 11m 0N0 3"N NOW 7M 17101_ If00 %700 _ m500 Sit31100 LION 10000 Kim ltl um tl]K I1300 !]300 ! IN I17K VACemr NIK KO Nf00_ Na00 NS00 _ _M?0 N tlaw 11)000 111W ]S10J - I0 KI0 la10K t)NO NNO M KIN IfmO 7a slim �. HO IO/VIO IS0000 IIIO IIa00 IIK00 OWN I/KO a:f00 100 I"M OWN Km INK IN 15200 film nwoomw Nm m INON rlttll IIt0I1 Km TABLE 11 e Safe Pgarin9 load0 in LG/S9. 1't, .he safe beazing loads given in the following table Ire for horizontal thruste when the depth of cover over thR pipe exce, 1% 2 feet.. SAFE SLAB" LGA.) Of !21 1L. ner -Muck, peat, etc. 0 Solt Clay 11000 Sand 2,000 Sand and gravel 1,000 sand and gravel cemented with clay 4,000 Mud shale 10,000 •10 muck or peat all thnnta are restricted by piles or tie rods to solid foundations or by removal of muck or peat and replacement with ballast of sufficient rtal,ility to resist thrusts. Blocking Page 7 Yr CAIL'D1wT1UN 021ATI0t15 Maximum operatiny pressure = L', x noaal operatinq pressure Area of rmcreto (A) - Thrum nnsunda ` T_ r Eafe Hearing load in (Pounds/sq. ft.) SHI. MAximm height of thrust block I".) - Depth of trencJf,_ n [ - h 2 2 Depth of concrete thrust block . (width of trench in feet)(outside diameter Of Qc i nL[cetl„__ 2 iC4 he 2 Is Maxim,, length of thrust block fl*1 - A[ of concrete Maximum Height Negaired amount Of concrete (cu, yd.) 4 (Nei gist x depth x lemith)x0.03704=(IMxti xDc)xC.03704 i I:. F�MIPW r � ( 1. problem: r_alculatim of the amount of concrete required to block a 90c' bend in an R- G,I. ratemain; the normal operating pressure in . ( � the pipe will he 65 pal and t:,e soil condition in the Area indicates need and gravel. ' 2- soluti9,2: i - Maximum operatim( p- sure - 1.5 x 65 - 97,5 psi - Outside diw tter , ; ' pipe - 9.05 in. = 9.05/12 ft. . - Go to Table I: The calculated maximise operating pressure is 97.5 psi, the table does not list this fiqure eo we take the first fiqure in sequence being 100 psi For an H- vsterpips, having a maximum oaeratirq pressure of ion psi, ' t we ass that the thrust no a 900 ben: 1- 5,420 pounds. -Go to Table II: Table II gives the safe bearing load for send and gravel: 3,u00 lbs/sq.ft. • �.o to Figure I: Figure 2 indicates the position of the concrete for blm*inq the 90o bend -Gc to the specifications of the pro)ect amp find depth of trench (h) 3 fast wrdth of trench (11) - 3 feet With the above Assembled informatUan we Proceed to the final calculations: -Area of concrete (A) Th[UAC = A20 - 1.00 sq, ft. Safe hearing Load 3000 -Maximum height of thrust block (H,s - Depth of trench 11 . 1.5 ft- 2 2 2 4 -Depth of eor:crete thrust block (DC) Mjdth of trench in [e W) - outside Of star of Pipe ldl. 2 �- 9.05/12 . 1.12 ft 2 -Maximise length of thrust black Ma) - Area Sf f.mgdgSe =qa I.H °1.2 tr. Height of C,Cc. "1 1.50 f -Required Amount of concrete - (HeightxDnpthxlength) x 0.03704 - (f�, x In A Dc) x 0.03704 - (1.5 x 1.2 x 1.111 A 0.03704 - 0.074 cu.yd. blocking Page 2 qM A STANDARD DETAIL FOR GENERAL BLOCKING <_rs:(-'RETI: BIA)MINt: SIZING PRaCMIR9 A. GENERAL The amount of concrete required to anchor horizontal bends, tees, and doad ends depends on the strength of the soil. The methods of • ( � placing concrete to keep the joint accessible is shorn in Figure I. The arms in square feet of concrete which oust bear against the side of the trench is found by dividin.l the thrust in pounds sham is in Table I by the safe bearing load of the soil es shown in Table II. i R. CRITERIA � 1 . - The miring procedure is for horizontal or downward thrvet only. - Height of the throat block must be equal to or less the„ 1/2 the depth true the ground surface to tlue tla;k Lase- - The thrust block bearing phase is apprnximataly rectangular. - The concrete blocking Shall be as per APWA specification 7r-2.14. i SYMB04.5 d. Cautside Ctameter of ripe in Feet T Thrust in pounds at the fitting (Table II (( SBL. Safe Bearing load 1n pounds/sq. ft. Mile III h . Depth of trench in feet W • Width of trerxoh in fast Sit A . Area of concrete wl.ich must bear against the side of the trench in q. ft. He. Maxisim he+.gl• of the thrust block in feet �1 DC Depth of the concrete chrust block to Waring surface in feet ;P IS,. Maximm lengti of the thrust block itl fast as h t ••�N1sE3�iYi1" ; � t 1 i 5 ■lock ing Page 1 f yyA 9 � J 1 l SHALL INCLUDE �2" MIN-FINISHED GRADE i HYDRANT EXTEN WHEN NEEDED OLYMPIC FNDRY — OF EQUAL CI WLVE BOX I � 6" C I SPOOL — 6" GATE VALVE (Ft MJ) CG1NC _ 3/4"SHACKLE RODS / — BLOCKING — ; • c _BLOCKING .1 CKING I•I/2"WASHED GRAVEL X" 6` TEE J"FL) •.�' ` 16" 4" CONC— BLOCKING i HYDRANT 1 7 HYDRANT GUARD PO4TE SHALL BE STATE OF WASHINvTON DEFT. OF HMaHWAYS DESIGN GF CIRCULAR 2' 2 PRECAST CONCRETE GUARD FAIL POSTS. TWO(2' GUARU PGS" dIN) SHALL ( 1 BE SUPPLIED ANO/C NSTALLED ��� GL 40 POST (TYP) ADDITIONAL POSTS MAY BE REO'D BY ENGINEER FOR OPTIMUM PRO- TECTION FROM VEHICLES ALL FIRE HYORAWTS AND GUARD I POSTS SHALL BE PAINTED AS DIRECTED BY ENGINEER i STANDARD DETAIL FOR HYDRANT ASSEMBLY 3 HYD. GUARD POSTS a I N0. 4 BAR AT 8" O.C. NO. S BAR AT S" 0 C - NO. 3 BAR AT OPENING 4' --� BOX REINF: 3- 3 1/4- f/4 MESH WITH - 6,8. NO A PAR Al 12 vERT Ir N0. 3 BAR AROUND ALL OPENINGS I". 44" "a 0" f 20" 4STYROF041 0 0 0 0 Do 0 0 + 0 - f ,rL}jF it 8'0" STANDARD DETAIL NOTE' DIMENSIONS SHOWN ARE MINIMUM FOR FOR 24" BUTTERFLY VALVE, VALVE CHAMBER NO. VC- 20 (LUNDBERG CONCRETE Co., INC., TALOMA), BUTTERFLY Y VALVE CHAMBER AST CONCRETE OR APPROVED EQUAL I i r f MIN �I 12 MIN IN VAULT j"N ' YAULTCONSTRUCT10N 1190 • , REINFORCIN7 SWILL BE 124-MIN AS FOR LARGE VALVE - •,I IB MIN R f CHAMBER • 0 to '�;. .I 0 p o 1 ID •. MIN O O LID ANO RING SHALL BE • I 0 O OLYM"IC FNORY • 5822 ' O %,tH TYPE D LID OR I" EQUAL 'A"MIN ?- MIN lie STANC.• RD DETAIL FOR BUTTERFLY VALVE CHAMBER is'aup I i. 4 1 II{I{I I, 0 1 3 r � � o r � E n y — 3 4 ELEVATION VIEW PLAN VIEW (NOT 70 SCALE) f { MATERIAL LIST I ( 2) — M 10045 1" MUELER CORPORATION STOP Y ( 2)- 9 COPPER NIPPLE , 3 " ' .:49, MALE I P.T. x MALE I.P. T. ( 2)- 1 " M 134T6 CORPORATION STOP POO COUPLIN9 2 LINEAL FEET , TYPE W COPPER PIPE STANDARD D� `AIL FOR I BYPASS ASSI:MIJLY FOR 12" PATE VALVE t 4 1:r :1e h OLYMPIC FNDRY. CASTINii "21122 'PITH TYPE 0 LID OR EQUAL — - CONC. RINGS BLOCK OR ®RICKS (TYP - m C MORTAR (TYP.) j :t O O : :► t: V ( r • 4 I PRECAST VAULT SMALL BE STANDARD 120 VALVE CHAMBER ( LUNDBERG CONCRETE Co INC , TACOMA ) WITH 1- 12' ADDITIONAL SECTION OR APPROVED EQUAL STEPS SHALL BE INSTALLED AT I' SPACING AND SHALL BE APPROVED BY UTILITY ENQ. STANDARD DETAIL NOTE FOR PRECAST (I Ex PAN&ON JOINT MAT'L CONCRETE VALVE CHAMBER (STYROFOAM) AS REQ'D FOR 12' GATE VALVE (TYP) 1.� � 1 4 r vim own i 76:f��ldd �if�>'16D'-7d/1/v�OC�6/ XZ417G'/S��y TT ya