PROJECT NUMBER: LUA17-000234, ECF, SHPL-A, MOD
APPLICANT: Jim Dalpay c/o Dalpay Properties, LLC, 4033 NE Sunset Blvd, Renton, WA 98059
PROJECT NAME: Dalpay Short Plat
PROJECT DESCRIPTION: The applicant is requesting Preliminary Short Plat approval, Environmental (SEPA)
Review, and two Modifications for the subdivision of an existing vacant 72,318 square foot site, zoned R-6, into 4 lots and
two tracts. The proposed lots would range in size from 7,462 square feet to 12,252 square feet. Tract A is proposed as a
1,950 square foot shared driveway tract and Tract B is proposed as a 31,649 square foot NGPE tract. Access to Lot 1 would
be provided via an existing private access off of NE 19th Street, which terminates at the north property line. Access to Lots
2-4 would be provided via a shared driveway off of Redmond Ct NE to the east of the project site. Two modifications to
the street standards are requested to allow the proposed lots to access the site via the existing private share accesses
which terminate at the north and east property lines. The site is mapped with a Wellhead Protection Area 2, sensitive and
protected slopes, and a Type Np stream. Type Ns streams require a standard buffer of 50 feet.
PROJECT LOCATION: S of NE 19th St. at the end of Redmond Pl NE (Private Road)
LEAD AGENCY: City of Renton
Environmental Review Committee
Department of Community & Economic Development
The City of Renton Environmental Review Committee has determined that it does not have a probable significant adverse
impact on the environment. An Environmental Impact Statement (EIS) is not required under RCW 43.21C.030(2)(c). This
Determination of Non-Significance is issued under WAC 197-11-340. Because other agencies of jurisdiction may be
involved, the lead agency will not act on this proposal for fourteen (14) days.
Appeals of the environmental determination must be filed in writing on or before 5:00 p.m. on June 22, 2018. Appeals
must be filed in writing together with the required fee with: Hearing Examiner, City of Renton, 1055 South Grady Way,
Renton, WA 98057. Appeals to the Examiner are governed by RMC 4-8-110 and more information may be obtained from
the Renton City Clerk’s Office, (425) 430-6510.
PUBLICATION DATE: June 8, 2018
DATE OF DECISION: June 4, 2018
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
6/4/2018 | 3:34 PM PDT
6/4/2018 | 4:32 PM PDT
6/5/2018 | 11:58 AM PDT
6/4/2018 | 12:36 PM PDT
DETERMINATION OF NON-SIGNIFICANCE – MITIGATED
(DNS-M) MITIGATION MEASURES AND ADVISORY NOTES
PROJECT NUMBER: LUA17-000234, ECF, SHPL-A, MOD, MOD
APPLICANT: Terrance Wilson, Wilson & Neal, PLLC, PO Box 158, Kent, WA
98035
PROJECT NAME: Dalpay Short Plat, PR17-000211
PROJECT DESCRIPTION: The applicant is requesting Preliminary Short Plat approval,
Environmental (SEPA) Review, and two Modifications for the subdivision of an existin g vacant 72,318
square foot site, zoned R-6, into 4 lots and two tracts for the eventual development of single family
residences. The proposed lots would range in size from 7,462 square feet to 12,252 square feet. Tract A
is proposed as a 1,950 square foot shared driveway tract and Tract B is proposed as a 31,649 square foot
Native Growth Protection Area (NGPA) tract. Access to Lot 1 would be provided via an existing private
access off of NE 19th Street, which terminates at the north property line. Access t o Lots 2-4 would be
provided via a shared driveway off of Redmond Ct NE to the east of the project site. Two modifications
to the street standards are requested to allow the proposed lots to access the site via the existing private
share accesses which terminate at the north and east property lines. The site is mapped with a Wellhead
Protection Area 2, sensitive and protected slopes, and a Type Np stream. Type Ns streams require a
standard buffer of 50 feet.
PROJECT LOCATION: 18XX Redmond Pl NE (Parcel No. 0423059032)
LEAD AGENCY: The City of Renton
Department of Community & Economic Development
Planning Division
MITIGATION MEASURES:
No mitigation measures are recommended.
ADIVISORY NOTES:
The following notes are supplemental information provided in conjunction with the administrative
land use action. Because these notes are provided as information only, they are not subject to the
appeal process for the land use actions.
See attached.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 of 2 LUA17-000234
ADVISORY NOTES TO APPLICANT
The following notes are supplemental information provided in conjunction with the administrative land use
action. Because these notes are provided as information only, they are not subject to the appeal process for
the land use action.
Planning:
(Contact: Name, 425-430-6598, jding@rentonwa.gov)
1. RMC section 4-4-030.C.2 limits haul hours between 8:30 am to 3:30 pm, Monday through Friday unless
otherwise approved by the Development Services Division.
2. Commercial, multi-family, new single family and other nonresidential construction activities shall be
restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through
Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight
o’clock (8:00) p.m. No work shall be permitted on Sundays.
3. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an
appropriate ground cover over any portion of the site that is graded or cleared of vegetation and where
no further construction work will occur within ninety (90) days. Alternative measures such as mulch,
sodding, or plastic covering as specified in the current King County Surface Water Management Design
Manual as adopted by the City of Renton may be proposed between the dates of November 1st and
March 31st of each year. The Development Services Division’s approval of this work is required prior to
final inspection and approval of the permit.
4. A National Permit Discharge Elimination System (NPDES) permit is required when more than one acre is
being cleared.
5. The applicant will be required to comply with all the code requirements of RMC 4-3-050 Critical Areas.
This includes, but is not limited to, placing the critical area within a Native Growth Protection Easement,
providing fencing and signage, and providing the City with a site restoration surety device and, later, a
maintenance and monitoring surety device.
6. The applicant may not fill, excavate, stack or store any equipment, dispose of any materials, supplies or
fluids, operate any equipment, install impervious surfaces, or compact the earth in any way within the
area defined by the drip line of any tree to be retained.
7. The applicant shall erect and maintain six foot (6') high chain link temporary construction fencing around
the drip lines of all retained trees, or along the perimeter of a stand of retained trees. Placards shall be
placed on fencing every fifty feet (50') indicating the words, “NO TRESPASSING – Protected Trees” or on
each side of the fencing if less than fifty feet (50'). Site access to individually protected trees or groups
of trees shall be fenced and signed. Individual trees shall be fenced on four (4) sides. In addition, the
applicant shall provide supervision whenever equipment or trucks are moving near trees.
8. This permit is shall comply with the Bald and Golden Eagle Protection Act. The permitted is responsible
for adhering to the U.S. Fish and Wildlife Service National Bald Eagle Management Guidelines (2007) and
/or your U.S. Fish and Wildlife Service permit.
Development Engineering:
(Contact: Rohini Nair, 425-430-7298, rnair@rentonwa.gov)
1. See Attached Development Engineering Memo dated May 23, 2018
Fire Authority:
(Contact: Corey Thomas, 425-430-7024, cthomas@rentonwa.gov)
EXHIBIT 5
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
ADVISORY NOTES TO APPLICANT
Page 2 of 2 LUA17-000234
1. The fire impact fees are currently applicable at the rate of $829.77 per single family unit. Fee is paid at
time of building permit.
2. The fire flow requirement for a single family home is 1,000 gpm minimum for dwellings up to 3,600
square feet (including garage and basements). If the dwelling exceeds 3,600 square feet, a minimum
of 1,500 gpm fire flow would be required. A minimum of one fire hydrant is required within 300-feet
of the proposed buildings and two hydrants if the fire flow goes up to 1,500 gpm. Existing hydrants can
be counted toward the requirements as long as they meet current code including 5-inch storz fittings.
It appears existing hydrants will meet minimum code requirements.
3. Fire department apparatus access roadways are required to be a minimum of 20-feet wide fully paved,
with 25-feet inside and 45-feet outside turning radius. Fire access roadways shall be constructed to
support a 30-ton vehicle with 75-psi point loading. Access is required within 150-feet of all points on
the buildings. Approved fire apparatus turnarounds already exist. Fire sprinkler systems are required
for all homes on dead end streets that exceed 500-feet long, this applies to lots 2, 3 and 4.
Technical Services:
(Contact: Amanda Askren, 425-430-7369, aaskren@rentonwa.gov)
1. None at this time.
Community Services:
(Contact: Leslie Betlach, 425-430-6619, lbetlach@rentonwa.gov)
1. Parks Impact fee applies.
Police:
(Contact: Cyndie Parks, 425-430-7521, cparks@rentonwa.gov)
1. None at this time.
Building:
(Contact: Craig Burnell, 425-430-7290, cburnell@rentonwa.gov)
1. Recommendations of the geotechnical report must be followed as a condition of building permits.
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE:May 23, 2018
TO:Jill Ding, Planner
FROM:Rohini Nair, Civil Plan Reviewer
SUBJECT:Utility and Transportation Comments for Dalpay short plat
Parcel Number 0423059032
LUA 17-000234
I have reviewed the application for the Dalpay short plat at PID # 0423059032 (located near the
intersection of NE 19th Street and Redmond Court NE) and have the following Conditions of approval and
the following review comments:
CONDITIONS OF APPROVAL:
Stormwater
The applicant should account for the impervious and pervious surface in proposed Lot1 also
in the new flow control facility and new basic water quality facility proposed for the project.
The proposed new flow control facility and new water quality facility is required to be resized
to account for Lot 1 also.
The TIR submitted with the land use application mentioned that the Lot 1 was already
accounted for in the existing stormwater facility already constructed for the Dalpay short plat
that was recorded in 2005. Since that short plat was recorded more than 5 years ago, the
stormwater is not vested with the already recorded short plat. If the applicant wants to use the
existing stormwater facility to account for Lot1, then the applicant should provide for City’s
review additional information that shows that the existing stormwater facility will meet the
current RSWDM requirements for the stormwater facility sizing, access, etc.
REVIEW COMMENTS
EXISTING CONDITIONS
The site is approximately 1.66 acres in size and is currently vacant.
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
Project/Plat Name – LUA00-000000
Page 2 of 6
Water Water service is provided by the City of Renton The site is in the Highlands service area in the
565 hydraulic pressure zone. There is an existing 8-inch water main (W-3373) within an
easement that ends along the east property line of the site (at the east edge of the proposed
private access tract, which can deliver 1,250 gallons per minutes (gpm). There is also an
existing 4-inch water main (W-3196) within an easement along Redmond Pl. NE than can
deliver 300 gpm. The static water pressure is about 60 psi at ground elevation of 420 feet. The
site is located within Zone 2 of an Aquifer Protection Area.
Sewer Wastewater service is provided by the City of Renton There is an existing 8-inch sewer main (S-
3373) located within an easement that ends along the east property line of the site (at the east
edge of the proposed private access tract. There is an existing 8-inch sewer main (S-3196)
located within an easement that ends along the north property line of the site (near the north
property line of proposed Lot 1).
Storm There is an existing stormwater mains in Redmond Court NE (see City plan no. SW-3373). The
existing property does not contain manmade stormwater facilities.
Streets The site does not have direct frontage to public right-of-way (ROW). The site gains access to
Redmond Court NE, a Residential Access street, by means of a recorded 20 feet wide private
access and utility easement (recording number 20110316900007) on the adjacent east parcel.
There is a 20 feet wide pavement in the recoded access and utility easement.
CODE REQUIREMENTS
WATER
1. The proposed water main improvements in the submitted conceptual utility plan along with the
changes in the comment 2 included below, are required to be provided for the project. Extension
of 8-inch-inch water main from the existing 8-inch-inch water main (W-3373) located in Redmond
Court NE until the east property line of proposed lot 3 is required to serve the proposed lots 2, 3,
and 4. Lot 1 is proposed to get water service from the existing water main (W-3196) on the north
of the site. Renton Fire Authority has determined that the fire flow requirement for a single family
home is 1,000 gpm minimum for dwellings up to 3,600 square feet (including garage and
basements). If the dwelling exceeds 3,600 square feet, a minimum of 1,500 gpm fire flow would
be required. Fire sprinkler systems are required for all homes on dead end streets that exceed
500-feet long, this applies to lots 2, 3 and 4.
2. The following water system improvements are required:
a. Blow off or fire hydrant will be required at the end of the water main extension.
b. Water main extension will be required to be located in the paved shared access tract.
c. Required minimum separation between water main and sewer main is 10 feet.
d. Minimum separation between water main and the outer edge of the private
stormwater facility is 5 feet.
3. Installation of fire hydrants within 300 feet of each lot is required by Renton Fire Authority. The
number and location of new hydrants will be dependent upon the finished square footage of the
homes.
4. Please refer to City of Renton General Design and Construction Standards for Water Main
Extensions as shown in Appendix J of the City’s 2012 Water System Plan.
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
Project/Plat Name – LUA00-000000
Page 3 of 6
5. Each lot shall have a separate meter. The project is required to provide one 1-inch water service
line and 1-inch domestic water meter to each lot, for a total of four (4) new domestic water service
lines and meters.
6. Water mains located outside of existing or proposed right-of-way will be required to be in public
easement of minimum 15 feet width.
7. The development is subject to applicable water system development charges and meter
installation fees based on the size of the water meters.
a. The current water system development charges for each proposed 1-inch domestic water
service is $3,727.00 per 1-inch meters.
b. The total water SDC fee is payable at construction permit issuance, the rate that is current
at time of issuance of the construction permit will be applicable.
8. Water service installation charges for each proposed 1-inch water service is $2,850.00 per meter.
This is payable at construction permit issuance.
9. The current drop-in meter fee is $460.00 per meter. This is payable at issuance of the building
permit. The rate that is current at time of issuance of the construction permit will be applicable.
10. Additional water system development charges and water meter charges will apply if a landscape
irrigation meter is required and is based on the size of the meter.
SEWER
1. The conceptual utility plan submitted with the land use application proposed an extension of 8-
inch diameter sewer main along the proposed private access tract from the existing sewer main
at the east property line of the parcel until the east property line of proposed lot 3. The sewer
extension was proposed to serve lots 2, 3, and 4. However there required minimum 10 feet
separation of sewer main from the water main is not available. Therefore, instead of the sewer
main extension the development can provide individual side sewers from the existing 8-inch
sewer main(S-3373) east of the site. Private sewer easement will be required on lot 4 for side
sewer to serve lot 3.
2. Lot 1 is proposed to get sewer service from the 6-inch sewer stub located near the northwest
corner of lot 1 subject to field verification (if the existing sewer connection is found to not meet
City standards, then alternate sewer connection meeting City standards is required to be
provided.
3. The following sewer system improvements are required:
a. Each lot shall be served by an individual side sewer. Dual side sewers are not allowed.
b. If a side sewer is to serve a lot through an open space tract or another property, then a
15-foot wide public sewer easement shall be provided.
c. The minimum separation between sewer main and water main is 10 feet.
4. Public sewer main extensions located outside of existing or proposed right-of-way will be required
to be in minimum 15 feet wide public easement.
5. The development is subject to applicable wastewater system development charges based on the
size of the new domestic water to serve the project.
a. SDC fee for a 1-inch meter is $2,837 per 1-inch meter. There will be four 1-inch meters for
the proposed 4 lot short plat
11. The total water SDC fee is payable at construction permit issuance. The rate that is current at time
of issuance of the construction permit will be applicable.
6. The Honey Creek Sewer Interceptor Special Assessment District fee will be applicable on all the
proposed 4 lots. The feet rate is $250 for each lot. Lot 1 will also have the Sierra Homes Special
Assessment District fee (SAD) fee which is $1,016.89. The rate that will be applicable on the
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
Project/Plat Name – LUA00-000000
Page 4 of 6
issuance day of the utility construction permit will be applicable on this project.
SURFACE WATER
a. A geotechnical report, dated December 23, 2015, and a response to comments letter dated
February 21, 2018 completed by Earth Solutions NW for the site has been provided. The
submitted report describes the site is not suitable for infiltration. A tightline conveyance of
the runoff across the steep slope area and controlled discharge via energy dissipater is
represented as the runoff conveyance option for the site. Erosion control measures will need
to be in place prior to starting grading activities on the site. Temporary construction
dewatering as well as temporary trench shoring may be necessary during utility excavation
and installation. Geotechnical recommendations presented need to be address within the
project plans and followed during construction.
b. A Preliminary Drainage Plan and Technical Information Report (TIR), dated April 25, 2018, was
submitted by Barghausen Inc. with the Land Use Application. Based on the City of Renton’s
flow control map, the site falls within the Flow Control Duration Standard area matching
Forested Site Conditions and is within the Honey Creek Drainage Sub Basin. The development
is subject to Full Drainage Review in accordance with the 2017 City of Renton Surface Water
Design Manual (RSWDM). All core requirements and the six special requirements must be
discussed in the Technical Information Report. The project proposes the use of a storm filter
to provide basic water quality treatment. A private detention vault is proposed as the flow
control facility. The following stormwater improvements are required and shall be discussed
within the TIR:
i. The applicant should account for the impervious and pervious surface in proposed Lot1
also in the new flow control facility and new basic water quality facility proposed for
the project. The proposed new flow control facility and new water quality facility is
required to be resized to account for Lot 1 also.
o The TIR submitted with the land use application mentioned that the Lot 1 was
already accounted for in the existing stormwater facility already constructed for
the Dalpay short plat that was recorded in 2005. Since that short plat was
recorded more than 5 years ago, the stormwater is not vested with the already
recorded short plat. If the applicant wants to use the existing stormwater
facility to account for Lot1, then the applicant should provide for City’s review
additional information that shows that the existing stormwater facility will
meet the current RSWDM requirements for the stormwater facility sizing,
access, etc.
ii.The stormwater facility, tract, easement, and facility access shall be in accordance with
the design requirements outlined in the RCSWDM.
iii. Applicant shall include a complete discussion of core requirement #9 on-site BMPs in the
drainage report submitted with the construction permit application. The On-site BMPs
in the order mentioned in RSWDM section 1.2.9.2 should be included. The applicable
infeasibility criteria that is mentioned in the RSWDM should be cited for each on-site
BMP that is not recommended as applicable for the site. The current submitted TIR did
not include some on-site BMP options such as Reduced Impervious surface, Tree
retention, perforated pie connection, etc. The drainage plans should show and label the
required type and amount of on-site BMP provided.
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
Project/Plat Name – LUA00-000000
Page 5 of 6
iv. Drainage report and drainage plans submitted with the construction permit should
include all requirements of the RSWDM.
v. Storm drainage pipes shall not be located beneath any landscape strip or any sidewalk.
Relocate the lines into the paved roadway and provide solid round locking lids where
required.
vi. Roof drains require a minimum 10-foot easement. Applicant shall provide details on
how the roof drains will be connected into the public storm drain system. Such
connections shall be in accordance with City of Renton standards and the 2009
KCSWDM.
c. The development shall not create protected slopes as defined by RMC 4-3-050.
d. Grading shall be in accordance with RMC 4-4-060.
e. Separate structural plans will be required to be submitted for review and approval under a
separate building permit for the stormwater vault. Special inspection from the building
department is required.
f. A Construction Stormwater General Permit from Department of Ecology will be required if
grading and clearing of the site exceeds one acre. A Stormwater Pollution Prevention Plan
(SWPPP) is required for this site.
g. A surface water development charge fee for each new single family residence will be
applicable on the project at the time of issuance of the construction permit. The current fee
rate is $1,718.00 per new single family residence. The project proposes the addition of 4 new
single family residences. The fee rate that is current at the time of issuance of the
construction permit will be applicable on the project.
TRANSPORTATION
1.The site does not have direct frontage to public ROW.
2.Access is proposed by connecting to existing recorded access easements.
a.Lots 2, 3, and 4 will be served by a new private access tract that will connect with existing
20 feet wide private access and utility easement (recording number 20110316900007) on
the adjacent east parcel. The applicant has submitted a modification request to allow lots
2, 3, and 4 to obtain access from the recorded private access easement. Staff
recommends support of the modification. The tract width, easement width, and
pavement width of the new private access tract should meet the requirements of RMC 4-
6-060 and the access requirements of the Renton Fire Authority. The individual lots will
gain access from the new private access tract by means of single family driveways.
b.Lot 1 is proposed to get single family driveway access from the 20 feet wide existing
private access Redmond Pl NE located to the north of lot 1. A street modification request
was submitted to allow lot 1 to gain access from the 20 feet wide existing private access
Redmond Pl NE. Staff recommends support of the modification. Single family driveways
shall meet the requirements of RMC 4-4-080. The access requirements of Renton Fire
Authority should also be satisfied by the project.
3. Paving and trench restoration shall comply with the City’s Trench Restoration and Overlay
Requirements.
4. Payment of the transportation impact fee is applicable on the construction of the development
at the time of single family building permit. The current rate of transportation impact fee is
$5,430.85 per single family home. The project proposes the addition of 4 new single family
DocuSign Envelope ID: 8DE21126-E6F7-42B8-8881-F421FA1E75F0
Project/Plat Name – LUA00-000000
Page 6 of 6
homes. The current estimated total fee is $21,723.4. Traffic impact fees are subject to change.
The transportation impact fee that is current at the time of building permit application will be
levied on the building permits.
5. Undergrounding of utilities is required.