Loading...
HomeMy WebLinkAboutAttach D - Alternative Assessment Alternatives Assessment Panther Creek at Talbot Road South Culvert Replacement Project Renton, Washington for City of Renton March 12, 2025 1101 Fawcett Avenue, Suite 200 Tacoma, Washington 98402 253.386.4940 ATTACHMENT D Alternatives Assessment Panther Creek at Talbot Road South Culvert Replacement Project Renton, Washington File No. 0693-093-00 March 12, 2025 Prepared for: City of Renton 1055 South Grady Way Renton, Washington 98057 Attention: Jared McDonald, PE Prepared by: GeoEngineers, Inc. 1101 South Fawcett Avenue, Suite 200 Tacoma, Washington 98402 253.383.4940 KPFF Consulting Engineers, Inc. 1601 Fifth Avenue, Suite 1600 Seattle, Washington 98101 206.622.5822 Ken Fellows, PE Senior Civil Engineer David Conlin, PWS Associate Ecologist Eric Mendel, PE Associate Civil Engineer Aaron Olson, PE Principal Structural Engineer KF:EM:DC:AO:leh:atk Disclaimer: Any electronic form, facsimile, or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record. City of Renton | March 12, 2025 Page i File No. 0693-093-00 Table of Contents 1.0 Introduction .................................................................................................................. 1 2.0 Description of Existing Conditions .................................................................................. 1 2.1 Stream ........................................................................................................................................... 1 2.1.1 Watershed Characteristics ................................................................................................ 1 2.1.2 Site Conditions................................................................................................................... 1 2.1.3 Hydrology ........................................................................................................................... 2 2.1.4 Federal Emergency Management Agency (FEMA) Floodplain Mapping ......................... 4 2.2 Road............................................................................................................................................... 4 2.3 Utilities ........................................................................................................................................... 4 2.4 Geotechnical Summary ................................................................................................................ 5 3.0 Concept Development and Evaluation ............................................................................ 5 3.1 Stream Design............................................................................................................................... 5 3.1.1 Crossing Type ..................................................................................................................... 5 3.1.2 Alignment ........................................................................................................................... 6 3.1.3 Profile ................................................................................................................................. 6 3.1.4 Hydraulic Opening ............................................................................................................. 7 3.1.5 Channel Section ................................................................................................................ 8 3.1.6 Large Woody Material (LWM) ............................................................................................ 8 3.1.7 Stream Alternative Summary ............................................................................................ 8 3.2 Geotechnical Considerations ....................................................................................................... 8 3.2.1 Construction Methods ....................................................................................................... 8 3.2.2 Structure Foundation ........................................................................................................ 9 3.3 Roads and Utilities ...................................................................................................................... 10 3.3.1 Design Speed ................................................................................................................... 10 3.3.2 Cross Slope ...................................................................................................................... 10 3.3.3 Proposed Roadway Design ............................................................................................. 10 3.3.4 Maintenance of Traffic .................................................................................................... 11 3.3.5 Utilities ............................................................................................................................. 11 3.3.6 Stormwater ...................................................................................................................... 12 3.4 Structural Design ........................................................................................................................ 12 3.4.1 Structural Constraints ..................................................................................................... 12 3.4.2 Precast Concrete Box Culvert ......................................................................................... 12 3.4.3 Steel Plate Arch Culvert................................................................................................... 13 3.4.4 Bridge Structure Alternative............................................................................................ 13 3.5 Summary of Potential Design Alternatives ................................................................................ 14 4.0 Cost Estimates and Recommended Conceptual Design ................................................ 15 4.1 Estimate of Construction Cost.................................................................................................... 15 4.2 Preferred Alternative ................................................................................................................... 16 5.0 Data Gaps ................................................................................................................... 17 6.0 References .................................................................................................................. 17 Page ii File No. 0693-093-00 City of Renton | March 12, 2025 List of Figures Figure 1. Vicinity Map Figure 2. Plan View Figure 3. Profiles and Sections Figure 4. Road Closure and Detour Plan Appendices Appendix A. Hydraulic Design Field Report Appendix B. FEMA Flood Panel Appendix C. Design Concepts Appendix D. Conceptual Design Opinion of Probable Construction Cost City of Renton | March 12, 2025 Page 1 File No. 0693-093-00 1.0 Introduction This Alternative Assessment Report was prepared by GeoEngineers, Inc. (GeoEngineers) and KPFF Consulting Engineers, Inc. (KPFF) on behalf of the City of Renton (City) in support of the Panther Creek at Talbot Road South Culvert Replacement Project (project) in Renton, Washington. The City is proposing to replace the existing culvert conveying Panther Creek from east to west under Talbot Road South to improve fish passage and replace the existing crossing structure, which is in poor condition. The purpose of this assessment is to identify and evaluate conceptual project alternatives for replacement of the existing 32-inch-diameter pipe culvert with a fish-passable design. The project site is located at Talbot Road South, between South 38th Court and South 177th Street, in Renton, Washington (Figure 1, Vicinity Map). The site is just northeast of the Valley Medical Center and the intersections of State Route (SR) 167 and South 180th Street. 2.0 Description of Existing Conditions 2.1 STREAM 2.1.1 Watershed Characteristics The Panther Creek watershed covers 1.79 square miles that includes a mix of natural forested and wetland areas, as well as many residential developments. Panther Creek extends upstream of Talbot Road South approximately 2.8 miles to the southeast. The first 0.7 miles of creek upstream of the crossing lies in a confined ravine that has an increase in elevation from approximately 70 feet to approximately 400 feet, resulting in an average slope of approximately 8 percent. Over the remaining 2.1 miles, the creek flows at gentler slope of 1 to 2 percent over an upland plateau, where the watershed eventually reaches a high point of approximately 475 feet elevation. Approximately 850 feet downstream of the project crossing, the confined ravine topography transitions to a wider valley bottom as the creek approaches the greater Green River Valley. In the vicinity of the project crossing, the average creek slope is approximately 4 percent (City of Renton 2023). 2.1.2 Site Conditions KPFF completed a topographic survey of the project site in July 2023 (see Figure 2, Plan View). The survey extended approximately 300 feet upstream and 300 feet downstream of Talbot Road South. The vertical datum for the survey was North American Vertical Datum of 1988 (NAVD88) (feet). Project specific elevations noted in the remainder of this report are expressed in feet, NAVD88 vertical datum. The ravine in the vicinity of the project crossing is mapped by Mullineaux (1965) as the Renton Formation that is characterized by Arkosic sandstone, mudstone and shale. Areas surrounding the project crossing are mapped as glacial till, consisting of compact, unsorted sand, silt, clay and gravel. The existing culvert (Washington Department of Fish and Wildlife [WDFW] Site ID: 931933) is a 32-inch- diameter corrugated steel pipe that appears to have been lined with fiberglass, approximately 140 feet long, with a slope of approximately 4 percent (see Figure 2). The culvert is in poor condition. The bottom of the culvert is completely scoured away in places. This creates a risk of rapid and total failure during a flood event due to water leaking from the culvert, then flowing through pipe bedding and road embankment City of Renton | March 12, 2025 Page 2 File No. 0693-093-00 material. Replacement of the culvert is warranted due to its poor condition and also because the culvert downstream end is elevated approximately 4 feet over the receiving pool, which creates a total barrier to passage of salmonids. The existing culvert is undersized, causing upstream backwatering during flood events. Backwatering of flows appears to have resulted in deposits of sediment upstream of the culvert that are up to approximately 2 to 3 feet thick, causing the apparent stream bottom to widen as the ravine is filled over time. Based on several Wolman pebble counts completed during GeoEngineers’ site visit (Appendix A, Hydraulic Design Field Report), the existing streambed bed immediately adjacent to the culvert is a mix of sand, gravel, cobbles and boulders, with a D50 of 1.5 to 3 inches and a D95 of 6 to 9 inches. A reference reach is intended to be a section of creek that is relatively unaffected by artificial conditions or infrastructure that can serve as a guide to design new or restored channels. For this project, a reference reach approximately 100 feet long was identified approximately 450 feet upstream of the project crossing. The reference reach has a single thread channel located within a meander bend with the apex oriented along the right bank. The reach has an average slope of 4.4 percent and exhibits a step-pool bedform. An approximately 35-foot-long portion of the reference reach appears more as a pool-riffle morphology with steps upstream of pools. Water surface drops of several inches occur across these steps. Pools ranged from approximately 2 to 5 feet long with a maximum depth measured of 5 inches. Streambed material in the reference reach consists of small to medium-sized cobbles with coarse gravels and occasional small boulders. Fine to coarse sands were observed along channel bank toes with a fine to coarse gravel armor, or within undercut pools. A Wolman pebble count indicated a streambed sediment D50 of 2.3 inches and a D95 of 8.5 inches. There appears to be a natural and on-going supply of appropriately sized sediment from upstream areas to the project reach. No large wood was present in the reference reach. The average design bankfull width (BFW) for sizing the proposed channel and structure opening is 9.5 feet. The field report included in Appendix A includes a description of how this value was identified. A small wetland is located on the right bank floodplain bench just downstream of the culvert, likely supported by groundwater seepage (GeoEngineers 2023). No other wetlands were identified with the project reach. The Panther Creek Stream Assessment (see Appendix A) contains additional details about existing site conditions based on GeoEngineers’ site visits completed in June and July 2023. 2.1.3 Hydrology Hydrology within the Panther Creek watershed is understood to be highly influenced by urban development. Basin hydrology was assessed using multiple simple methods to obtain a range of several peak flow estimates for potential use in analysis and design. These simple methods included conducting a review of nearby gages to complete a basin transfer analysis, calculating regional regression equation values, completing a watershed scale rainfall-runoff continuous flow model analysis and reviewing existing literature. Table 1 summarizes the results of these methods. Panther Creek does not have a stream gaging station to provide a record of past flows. GeoEngineers performed the basin transfer analysis using stream gage data from the King County gage with site ID 31c located along Molasses Creek (King County 2023). The gage is located approximately City of Renton | March 12, 2025 Page 3 File No. 0693-093-00 2.9 miles northeast of the Panther Creek project crossing at Talbot Road South. The Molasses Creek watershed has an area approximately 98 percent that of Panther Creek at the project location. Visual inspection of aerial imagery within the Molasses Creek watershed suggests it is similar to that of Panther Creek. The results of the basin transfer analysis were lower than expected for Panther Creek given the size of the stream. Regression equations are not valid for basins with more than 5 percent impervious area and the Panther Creek watershed has an estimated impervious area of 30 percent. However, they are very easy to apply and can provide a low-end estimate of peak flow hydrology for a developed watershed. The results of this method were lower than those from the basin transfer method for both the 2- and 100-year events but slightly larger for the 500-year event. Rainfall-runoff modeling was carried out using MGSFlood, utilizing United Stated Geological Survey (USGS) soil data and land use data from the cities of Renton and Kent as inputs. Peak flow estimates resulting from the MGSFlood model were unrealistically high, with initial 2D model results indicating overtopping of Talbot Road South during the 2-year peak flow event. This is likely due to the coarseness of the model constructed, which represents the entire watershed as a single unit rather than dividing it into sub-watersheds and directly modeling the existing stormwater infrastructure. A study conducted by RW Beck (R.W. Beck 1997) includes descriptions of hydrology for the adjacent Springbrook Creek basin, which Panther Creek is a tributary to. The study lists peak flow inputs to Springbrook Creek from Panther Creek corresponding to the 2- and 100-year peak flow events on Springbrook Creek. Neither the 2- and 100-year events on Panther Creek, nor the peaks, necessarily coincide with those on Springbrook Creek. The flows for Panther Creek correspond to a location just upstream of a point along SR 167 approximately 1.5 miles downstream of the project crossing on Panther Creek. Most of this downstream reach of Panther Creek flows within a wetland running parallel to SR 167 along its east side, and there are several piped locations conveying flow from the wetland to the west below SR 167. The effects of these piped connections to the wetland are not well understood. Despite these facts, the flows reported seem reasonable for the Panther Creek crossing location at Talbot Road South and they were identified in the study using detailed hydrologic modeling and therefore in our judgement represent the best available hydrologic data and serve as the basis for our analyses for this project. TABLE 1: PEAK FLOW HYDROLOGY SUMMARY AVERAGE RECURRENCE INTERVAL PEAK FLOW EVENT (YEAR) BASIN TRANSFER FROM MOLASSES CREEK (CFSA) USGS REGRESSION (CFS) MGS FLOOD, 15-MIN TIMESTEP (CFS) SPRINGBROOK BASIN STUDY (CFS)B 2 37 28 179 67 100 90 57 500 197 500 111 127 638 251c Projected 2080 100d 107 68 597 235 Notes: 1. Bolded flows denote those used for analysis and design 2. Extrapolated from data using a logarithmic curve fit. 3. Estimated using WDFW climate change tool. cfs = cubic feet per second City of Renton | March 12, 2025 Page 4 File No. 0693-093-00 2.1.4 Federal Emergency Management Agency (FEMA) Floodplain Mapping Panther Creek at Talbot Road South is within a FEMA Zone X, indicating that it is unmapped by either detailed or approximate methods and considered to be within an area of minimal flood hazard risk, as shown in the FIRMette panel (FEMA 2023) included in Appendix B, FEMA Flood Panel. 2.2 ROAD Panther Creek crosses from east to west under Talbot Road South, which is a two-lane road aligned north and south. At the roadway centerline, the depth of fill over the top of the culvert is approximately 26 feet. The paved width of the road is approximately 40 feet with 11-foot lanes and 4-foot shoulders. There is an existing 5-foot sidewalk on the west side of the roadway. The east side of the roadway has a guardrail with no curb and gutter or sidewalk. At the south end of the culvert crossing, the roadway is transitioning from 2 lanes to 3 lanes. The roadway is crowned with a cross slope of approximately 4 percent. There is minimal illumination in the project area. Fill slopes on the east and west of the roadway are slightly steeper than 2H:1V (horizontal:vertical). The existing Talbot Road South surface is hot-mix asphalt (HMA). 2.3 UTILITIES Two storm drains discharge to the area upstream of and near to the project crossing. The nearest storm drainpipe conveys road runoff from Talbot Road South to Panther Creek on the left bank (south side) immediately upstream of the project culvert inlet near the toe of the roadway embankment. A second storm drainpipe outfalls to Panther Creek from the right bank (north side) approximately 95 feet upstream of the project culvert inlet. This latter storm drainpipe had variable flow over the duration of the site visit, increasing noticeably over just several hours while the flow in the channel remained essentially constant. This variability could be due to pumping. In addition to stormwater infrastructure in the vicinity of the crossing, both drinking and wastewater sanitary sewer main lines run underground north to south over the crossing parallel to Talbot Road South. The water main is a 12-inch steel pipe. According to as-built drawings provided by the City, there is also an abandoned 20-inch steel water main pipe adjacent to the active main. The sanitary sewer main is an 21-inch concrete pipe that runs north to south near the roadway centerline. The sanitary sewer line (top of pipe) is approximately 12 feet below existing grade in the vicinity of the existing culvert. Two-inch and 16-inch gas lines have been identified along the project limits. Both lines run north to south through the project on the west side of the roadway. Gas lines were assumed to have a minimum cover of 2 feet. Potholing will be performed later in design to confirm depths and locations. Multiple overhead power and communication lines have been located along Talbot Road South at the project location. Overhead power lines and poles are located on both the west and east side of the roadway. Franchise utility companies will need to be contacted to verify locations of existing facilities, including depth, of underground utilities, within the project limits. Potential relocation requirements, schedule, cost and design recommendations will be coordinated with utility owners during the design process. City of Renton | March 12, 2025 Page 5 File No. 0693-093-00 2.4 GEOTECHNICAL SUMMARY GeoEngineers completed a geotechnical investigation of the site, which is documented in a Preliminary Geotechnical Design Report for 10% Design (GeoEngineers 2025). The geotechnical study included installing three borings along the eastern edge of Talbot Road South. Boring B-1 was installed approximately 75 feet north of the existing culvert to a depth of approximately 30 feet below the ground surface. Boring B-2 was installed approximately 10 feet north of the existing culvert to a depth of approximately 25 feet below the ground surface where it met refusal. Boring B-3 was installed approximately 65 feet south of the existing culvert to a depth of approximately 35 feet below the ground surface. For reference, the road surface elevation varies from approximately 96 feet at the north boring to approximately 98 feet at the south boring and the culvert invert elevation at the road centerline is approximately 67 feet. Figure 3 in the Preliminary Geotechnical Design Report for 10% Design (GeoEngineers 2025) is a cross section along Talbot Road South depicting the materials encountered in the borings. Subsurface soils were identified as up to approximately 20 to 25 feet of various types of poor-quality fill (loose clayey silty sands) over a layer of dense glacial till approximately 10 to 15 feet thick, over Renton formation bedrock (siltstone/sandstone). The fill layer extends the deepest at Boring B-2, which met refusal at approximately Elevation 70 feet, possibly hitting a concrete object, possibly the foundation of a wood trestle bridge that previously existed at the site based on old King County plans recovered by the City (King County 1943). The fill layer likely extends to the north and south to the history valley walls. Boring B-2 did not reach the bottom of the fill layer; no glacial till or bedrock was encountered. Therefore, it is uncertain whether glacial till and/or bedrock are present in the immediate vicinity of the existing culvert. 3.0 Concept Development and Evaluation Several factors were considered in developing a suite of potential conceptual designs that the project team reduced in number using professional experience and judgement. These project alternatives were then evaluated and compared with the goal of selecting a preferred alternative to carry forward to preliminary design. The following sections summarize the various factors that were considered and discuss the benefits and constraints of each option. 3.1 STREAM DESIGN The primary stream factors that could be varied to develop conceptual alternatives include alignment, profile and hydraulic opening width. 3.1.1 Crossing Type The crossing under Talbot Road South should be formed of alluvial material to meet requirements of the Water Crossing Design Guidelines (WCDG) (Barnard et al. 2013). General conformance to the Washington State Department of Transportation (WSDOT) Hydraulics Manual (WSDOT 2023), while not mandatory, is recommended. Acceptable crossing structure types per these guidelines would be a bottomless three-sided concrete box culvert, a bottomless arch culvert, or a bridge. We expect the crossing will follow confined bridge methodology due to an estimated floodplain utilization ratio (FUR) less than 3.0 within the reference reach upstream of the crossing and of the channel downstream of the crossing. The floodplain utilization City of Renton | March 12, 2025 Page 6 File No. 0693-093-00 ratio is defined as the flood prone width (FPW), often taken to be the calculated 100-year water surface width, divided by the BFW at a given location within the channel. 3.1.2 Alignment Figure 2 shows the two proposed creek alignment alternatives. Alignment A closely follows the existing creek alignment. In the area just upstream of the existing culvert, the existing channel (Alternative A) alignment appears to be undergoing slow, but progressive migration to the north, eroding the base of the steep slopes on private property. Alternative A provides little space to install bank protection measures. Alignment B realigns the creek to be perpendicular to Talbot Road South. Upstream of the culvert, Alignment B shifts the creek to the south to remove the slight overshoot in the existing alignment and provide space for installation of bank protection measures. The overshoot is undesirable as it prevents flow from smoothly entering the culvert and could contribute to further bank erosion and channel migration to the north, making the overshoot worse with time. Downstream of the crossing, Alignment B moves the creek slightly north to reduce the potential for further erosion of the severely undercut left bank but shifts the creek into the wetland area on the right bank. The impact to the wetland appears to be under 1,000 square feet (a specific impact area will be identified during project preliminary design phase) and it is anticipated to be feasible to mitigate wetland impacts on-site resulting in no net loss. Due to the additional space available with Alternative B to install bank protection measures, the measures are expected to be more effective than for Alternative A. Additionally, the consequences of mild to moderate channel migration by Alternative B are less in comparison to similar migration associated with Alternative A. In the event that future maintenance is required, the maintenance needed for Alternative B is anticipated to be less costly and easier to implement as compared to Alternative A. 3.1.3 Profile The existing reach average slope in the vicinity of the crossing is 3.9 percent as identified from the channel survey limits. The WDCG (Barnard, et al. 2013) allow the restored profile to have a slope up to 1.25 times the existing reach average slope, equal to 4.9 percent. Profiles A and B follow Alignments A and B, respectively (see Figure 2). Alignment A and B start at the same physical points on the existing creek alignment downstream of the existing crossing, but upstream of the crossing Alignment A ties into the existing channel approximately 24 feet downstream of the stormwater outfall discharging from the right bank and Alignment B ties in approximately 33 feet upstream of it. Alignment B is therefore approximately 57 feet longer than Alignment A and ties into a higher elevation upstream than Alignment A. This results in both Profile A and Profile B having equal slopes of 4.8 percent when rounded to the nearest 10th of 1 percent. Both alternative creek profiles fill in the scour pool downstream of the existing culvert. To assess the effect of the increased creek slope on stream velocities, idealized stream sections were analyzed to estimate average flow velocities for the full cross sections at the estimated 2-year and 100-year flood flows. Table 2 summarizes the results of the analyses. Based on the similarity between these results, we are not recommending developing alternative design concepts that consider alternative creek slopes. City of Renton | March 12, 2025 Page 7 File No. 0693-093-00 TABLE 2: SUMMARY OF CALCULATED AVERAGE FLOW VELOCITIES OUTSIDE OF THE CROSSING STRUCTURE SCENARIO SLOPE (%) APPROXIMATE LENGTH OF STREAM RE- GRADE (FEET) 2-YEAR FLOOD FLOW VELOCITY (FEET PER SECOND) 2-YEAR FLOOD FLOW TOP WIDTH (FEET) 100-YEAR FLOOD FLOW VELOCITY (FEET PER SECOND) 100-YEAR FLOOD FLOW TOP WIDTH (FEET) Slope equal to existing reach average 3.9 618 3.8 20.8 4.9 24.7 Alternative A 4.8 365 4.1 20.5 5.3 24.2 Alternative B 4.8 392 4.1 20.5 5.3 24.2 Maximum slope per WCDG 4.9 383 4.2 20.5 5.4 24.2 3.1.4 Hydraulic Opening The conceptual alternatives considered in this alternatives analysis assume a minimum hydraulic opening (MHO) of 18 feet, with the final MHO to be determined during a future design phase. Based on various design methodologies, the estimates of the MHO ranges from 14 to 21 feet. The value of 14 feet is based on our measurements of the channel average BFW of 9.5 feet, and the stream simulation design method per the WCDG (Barnard, et al. 2013). The value of 18 feet considers additional hydraulic factors that will be further evaluated through hydraulic modeling to be completed at the preliminary design stage. The value of 21 feet is based on the design channel width outside the existing culvert. The City has identified advantages of structure width greater than 20 feet as compared to a narrower structure, including inclusion in the City’s bridge inspection program and potential availability of repair funds in the event of flood damage Increasing the proposed structure width would increase flood conveyance capacity, reduce velocities and is expected to have reduced scour as compared to the minimum width. Additionally, a wider hydraulic opening would provide additional areas of streambank floodplain benches that would provide more floodplain continuity with areas upstream and downstream of the crossing and allow for more complex channel morphology through the crossing that forms higher quality aquatic habitat for salmonids. Wider widths are also typically supported by co-managers, including WDFW and the Muckleshoot Indian Tribe; therefore, facilitating co-manager support of the project and streamlining permitting. The structure freeboard must provide a minimum of 2 feet vertical clearance above the proposed 100-year flood elevation. Detailed hydraulic modeling of the creek will be completed as part of preliminary design. Based on preliminary, simplified analyses completed for this alternatives assessment, the estimated 100-year water surface elevation at the road centerline is approximately 69 feet, based on a thalweg elevation of 67 feet, and a 100-year flood flow depth of 2 feet. Therefore, the elevation of crown of the culvert or bottom of the bridge structure at the roadway centerline must be at least 71.9 feet; however, as noted below, we recommend providing additional vertical clearance. The projected 2080 100-year flow would increase these values by 0.1 feet. For a culvert option, a higher culvert top elevation will also result in a shorter culvert length but increase the size of the culvert wing walls. For a bridge option, vertical clearance would be easily achieved due to the height of the existing road embankment. The conceptual alternatives considered in this alternatives analysis assume providing a minimum of 6.0 feet of maintenance clearance (above the floodplain bench). A maintenance clearance up to 8.0 feet is workable for a culvert option considering other project constraints and would have a negligible cost City of Renton | March 12, 2025 Page 8 File No. 0693-093-00 increase compared to the lower maintenance height. The final value will be determined during a future design phase. The purpose of the maintenance clearance is to accommodate channel inspections, and future adjustment of stream channel complexity and habitat features within the structure if necessary throughout the life of the project. A 6.0 foot maintenance clearance is consistent with guidance contained in the WSDOT Hydraulics Manual (WSDOT 2023). Greater clearance provides the City with additional flexibility during design, construction and the post-construction design life of the project. Greater clearance could also facilitate wildlife passage. 3.1.5 Channel Section Figure 3, Profiles and Sections illustrates the proposed typical channel section both upstream/downstream of the crossing and through the crossing. The proposed channel section outside of the crossing has a width of 20.5 feet at approximately the 2-year flood flow level, cresting above the proposed banks and inundating the adjacent floodplain benches. 3.1.6 Large Woody Material (LWM) LWM is expected to be incorporated into the proposed channel design outside of the crossing structure. It will be designed to promote the target channel morphology and follow standard engineering practices for the placement of LWM within streams in western Washington. 3.1.7 Stream Alternative Summary The conceptual alternatives considered in this alternatives analysis assume stream alignment Alternative B, an MHO of 18 feet, and minimum maintenance clearance of 6.0 feet. 3.2 GEOTECHNICAL CONSIDERATIONS 3.2.1 Construction Methods Open-cut excavation of the site appears feasible, subject to temporary road closure and temporary relocating utilities as described in Section 3.3 Roads and Utilities, below. The elevation of deepest excavation will be driven by depths needed for streambed substrate through the crossing as described in Section 3.2.2 Structure Foundation, below, which would be used to determine footing depths for a culvert option. Loose road embankment fill excavated to construct a culvert crossing is recommended to be disposed of offsite rather than re-used. For a culvert option, the excavation would be backfilled with granular structural fill. For a bridge option, less back fill would be necessary. A key geotechnical parameter to be developed in the preliminary design phase is the estimated practical temporary construction slope, which will determine the horizontal extents of the excavation and impacts to Talbot Road South and associated utilities. Potential trenchless construction methods include ramming, jacking and tunnelling; however, the identified subsurface conditions consisting of loose fill, dense glacial till and bedrock are not suitable for these construction methods, which are therefore not considered further. City of Renton | March 12, 2025 Page 9 File No. 0693-093-00 3.2.2 Structure Foundation 3.2.2.1 CULVERT OPTIONS Simple spread footings appear feasible to support a culvert, assuming dense material is present at a reasonable depth at the location of the proposed culvert. The presence of dense material was not confirmed because Boring B-2 encountered refusal at 25 feet below the ground surface, slightly above the elevation where adjacent borings suggest that till or bedrock might be present. The reason Boring B-2 met refusal is not known, as the till and bedrock encountered in the adjacent borings was drillable. The following sections describe the process to develop a preliminary estimate for the culvert footing depth, which will be refined during the project preliminary design phase. The footing depth will be based on the depth of alluvial streambed substrate needed in the culvert below the thalweg elevation, plus the footing thickness. 3.2.2.1.1 Streambed Substrate Depth From a permitting and fisheries perspective, the channel through the crossing may need to be comprised of alluvial streambed material to meet fish passage design requirements. Alluvial material is potentially unstable over a hard smooth surface such as concrete or bedrock. Therefore, our preliminary assumption is that till/bedrock would need to be removed (if present) to a depth that leaves at least 3 feet of material over any hard surface, after considering potential scour. This would promote fish passage conditions, which may otherwise be compromised if bedrock were exposed through the crossing. Exposure of bedrock through the crossing could possibly result in inadequate water depth during times of low flow and/or a vertical drop as a result of scour where bedrock transitions to gravel substrate. Although bedrock may have been the natural pre-disturbance condition in some portions of the stream bed, we anticipate that current regulatory requirements for crossing replacement will require fish passage parameters to be achieved, precluding the option of leaving a bedrock stream bed. Scour depth and long-term regrade will be evaluated after completion of hydraulic modeling during the preliminary design phase. As a preliminary estimate, the depth of streambed material through the crossing is recommended to be 5 feet, assuming a minimum scour depth of 3 feet per WSDOT design guidance plus 2 feet below the total scour depth. Assuming a thalweg elevation for the proposed creek of 67 feet at the Talbot Road South centerline, the estimated base of the streambed substrate would be at Elevation 62 feet. 3.2.2.1.2 Foundation Elevation The top of the footing is estimated to be at or below the base of the streambed substrate (estimated above at 62 feet). The bottom elevation of the footing is estimated at approximately 60 feet, assuming a footing thickness of 2 feet (to be refined during the project preliminary design phase). 3.2.2.1.3 Potential Removal of Till/Bedrock If dense glacial till and/or bedrock as encountered in Borings B-1 and B-3 is present at the location of the new culvert, it may need to be removed to elevation approximately 60 feet to construct the culvert footings. 3.2.2.2 BRIDGE OPTIONS For a bridge alternative, deep foundations are anticipated, assumed to be drilled shafts. The design flood and check flood scours are assumed to be 3 feet. The scour angle of repose is 26 degrees per Geotechnical City of Renton | March 12, 2025 Page 10 File No. 0693-093-00 recommendations. The scour catch point begins at the edge of the stream section. Lateral migration is a potential concern for this stream crossing and will need to be assessed in future design advancement. The top of shaft caps would be placed below the scour line in accordance with WSDOT BDM 7.1.7 and the bottom of wing walls, if necessary, would be placed 2 feet below the scour line or finished grade in accordance with WSDOT BDM 8.1.10. Foundations for the bridge option are advantageous over the culvert option described in the preceding section due to the likely presence of bedrock near the streambed elevation that may complicate design and construction of culvert foundations, particularly if additional geotechnical data is not obtained. 3.3 ROADS AND UTILITIES 3.3.1 Design Speed The existing roadway has a posted speed limit of 35 miles per hour (mph). The roadway will be designed in accordance with American Association of State Highway and Transportation Officials (AASHTO) Geometric Design of Highways and Streets (AASHTO 2018), using a design speed of 35 miles per hour. 3.3.2 Cross Slope The existing roadway has a 4 percent cross slope. The City standard is to provide a maximum of 2 percent cross slope. The proposed project will maintain the existing 4 percent cross slope to minimize the project impacts that would be required to provide 2 percent slopes and transition back into the existing 4 percent cross slopes. 3.3.3 Proposed Roadway Design The proposed roadway design will be similar to the existing horizontal and vertical alignment for Talbot Road South, which meets current sight distance requirements. Several alternative lane configurations were considered, as illustrated in Appendix C, Sheet C-7, including: 1. Two 11-foot vehicular lanes, two 4-foot shoulders, two 5.5-foot sidewalks with curbs, and 2-foot clearance between the back of sidewalk and slope on both sides (total road section is 45 feet). 2. Three 11-foot vehicular lanes, one 4-foot shoulder (one side) and one 5-foot bike lane (other side), two 5.5-foot sidewalks with curbs, and 2-foot clearance between the back of sidewalk and slope on both sides (total road section is 57 feet). Guardrail will not be required on this project, as the proposed roadway section satisfies clear zone requirements on both sides of the road. Traffic barrier and fall protection would be included for a bridge option and extended north and south of the bridge as needed to meet vertical grade difference requirements. Table 3 summarizes the roadway classifications and standards used for design criteria. City of Renton | March 12, 2025 Page 11 File No. 0693-093-00 TABLE 3: SUMMARY OF ROADWAY DESIGN PARAMETERS TALBOT ROAD SOUTH Roadway Functional Classification Major Collector Posted Speed 35 mph Design Speed 35 mph Minimum Right-of-Way (ROW) Width 60 feet Travel Lane Width 11 feet Shoulder Width 4 feet Shoulder Slopes 0.02 ft/ft Embankment Slopes 2H:1V Notes: ft/ft = feet per foot 3.3.4 Maintenance of Traffic Maintaining traffic through the work zone would be logistically challenging based on the topography of the ravine. Constructing the crossing while maintaining traffic would require a temporary bypass roadway adjacent to existing roadway or building the new structure in phases. A temporary bypass roadway (i.e., shoofly) would require a temporary bridge and approach roadway fills. Phasing construction would require significant shoring to support the existing prism. Either of these alternatives would add significant construction duration and costs when compared to a full roadway closure during construction. North of the project site is residential. A key criterion of the analysis was to ensure access to the hospital would be maintained during the construction period. In August 2023, the City met with representatives of the Valley Medical Center Hospital (a large regional hospital located just south of the project site) to discuss access needs during construction of the project. The hospital stated a full road closure, for approximately 3 to 4 months, would be acceptable with the proposed detours allowing access from the north. The south access to the hospital will remain unaffected by this project. The alternative to the full road closure would be to construct the crossing structure in phases with temporary shoring to allow one lane access through the project site on fill or using a temporary bridge structure on either side of the project site. This option adds significant costs for shoring or constructing a temporary bridge structure. This option would also increase the construction duration, associated traffic impacts and environmental impacts. This option was not analyzed further upon acceptance of full road closure by the hospital and the acceptable detour route available. Detour options are shown on Figure 4, Road Closure and Detour Plan. Detour planning and potential impacts to the residential areas to the north of the project site and the Valley Medical Center Hospital and other businesses to the south of the project site will be further considered during the project preliminary design phase. 3.3.5 Utilities The project site has significant utilities that cross over the existing culvert. A solution to attach the utilities to a bridge at the stream crossing is a major challenge of the bridge option considered. Attaching the utilities City of Renton | March 12, 2025 Page 12 File No. 0693-093-00 to a bridge would require them to be much higher in elevation than the existing utility locations or to be suspended well below the superstructure span. One of the existing utilities is a large diameter gravity sanitary sewer main. Raising this pipe up to attach it to a bridge would require expanding the work area laterally along Talbot Road South in both directions to vertically realign the sewer, which would result in unacceptable impacts to the hospital, potentially require addition of a pump station, and add significant cost to the project; this was therefore not considered a viable option. Suspending the sewer line below the bridge at its current elevation limits the structure types feasible for a bridge option or would require a separate utility bridge. The box culvert and arch culvert options allow the project to replace the existing utilities at the current elevations and support them in place or temporarily relocate utilities during the construction process. These relocations will be analyzed further during subsequent design phases. The length of the temporary utility relocation is anticipated to be from valley wall to valley wall, as noted in Section 3.2.2 due to the need to remove the full extent of loose embankment fill. 3.3.6 Stormwater The site has several existing stormwater catch basins and two storm drainage outfalls within the stream ravine on the east side of the road. The existing outfall on the southeast side of the stream crossing will need to be relocated and replaced. The proposed project is anticipated to create approximately 1,000 to 2,000 square feet of new impervious surfaces, depending on which road section is selected, as well as replace approximately 10,000 square feet of existing impervious surfaces. This project is exempt from flow control and water quality treatment requirements per the City of Renton Surface Water Design Manual (2022). Existing roadway drainage patterns will be largely maintained. 3.4 STRUCTURAL DESIGN 3.4.1 Structural Constraints The primary constraints that impact the structural alternatives analysis include estimated MHO, depth of roadway fill above the thalweg of the creek, maintenance of traffic (MOT), and buried utilities. The following section describes how these constraints impact the selection of the preferred structural alternative. The recommended MHO is 18 feet. If the face of the proposed structure were placed at the outside edge of the MHO, then the structure would not be classified as a bridge as defined by the Federal Highway Administration (FHWA), which regulates structures over 20 feet in length. Structural options for the shorter span length proposed include precast concrete culverts (three-sided or four-sided) and steel plate arch structures. 3.4.2 Precast Concrete Box Culvert This design alternative is illustrated in Appendix C, Sheets C-1, C-4 and C-8. A precast concrete box culvert would be placed at the bottom of the roadway prism and fill would be used to carry the road across the ravine. This structure type can be prefabricated offsite and then delivered and constructed relatively rapidly once embankment excavation is complete and utilities temporarily relocated. Installation would require removal of a significant amount of the existing roadway fill and then backfill with suitable roadway fill to restore the roadway after the structure has been placed. The existing fill soils contain a high percentage of fines with some organic material and are also more than double the moisture content required for adequate compaction. As such, on-site soils are not suitable for reuse as fill on the project. City of Renton | March 12, 2025 Page 13 File No. 0693-093-00 Precast concrete box culverts typically come in two varieties: three-sided and four-sided structures. A three-sided structure consists of an inverted u-shaped precast culvert section that is supported on a cast- in-place (CIP) concrete stem wall and footing. A four-sided structure consists of two C-shaped precast concrete units that are placed to form an enclosed box. The bottom section of the box serves as the foundation support for the culvert. In general, a three-sided box will have a longer construction duration associated with forming and pouring the CIP concrete stem wall and footing. However, it is our understanding based on early coordination with permitting and tribal stakeholders that a three-sided structure is generally preferred over a four-sided structure. Based on this feedback, only the three-sided box was advanced for further consideration. Construction of culvert footings may be complicated by the potential presence of bedrock at the stream elevation. 3.4.3 Steel Plate Arch Culvert This design alternative is illustrated in Appendix C, Sheets C-2, C-5 and C-9. Like a precast concrete box culvert, a steel plate arch culvert would also be placed at the bottom of the roadway prism and fill would be used to carry the road across the ravine. Like the precast concrete box culvert option, this structure type can be prefabricated offsite and then delivered and constructed relatively rapidly. Also, like the concrete box culvert option, installation would require removal of a significant amount of the existing roadway fill and then backfill with suitable roadway fill to restore the roadway after the structure has been placed. For a given MHO, the excavation necessary to install an arch culvert would be greater when compared to a box culvert. This is driven primarily by the geometric properties of the arch whereby the base of the arch must be much wider to fit a given MHO. Like three-sided box culverts, steel plate arch culverts require CIP concrete stem walls and footings. However, due to the thrust loads at the base of the arch, these foundations would likely need to be larger than a similarly sized three-sided box culvert foundation. For the proposed MHO, a steel plate arch culvert does not have any significant advantages when compared to a precast box culvert and will likely result in greater construction costs due to greater impacts to utilities and potentially needing to remove more bedrock as compared to a box culvert. 3.4.4 Bridge Structure Alternative This design alternative is illustrated in Appendix C, Sheets C-3, C-6 and C-10. As mentioned previously, Panther Creek is located in a steep ravine where the depth of roadway fill measured from the top of roadway to the thalweg of the creek is approximately 30 feet. Spanning the ravine from top of slope to top of slope would require a bridge structure with a minimum span of approximately 75 feet based on the MHO and anticipated side slopes, and up to approximately 150 feet if the entirety of the valley fill material is removed. Alternatively, if the abutment walls were placed at the edge of the MHO, they would be approximately 30 feet tall. The primary challenge with a bridge structure is that the buried roadway utilities would need to be permanently relocated around the site or attached to the structure itself. This is particularly challenging for the 21-inch sanitary sewer that is approximately 12 feet below the roadway surface and is gravity fed. This utility would either need to be raised to the girder level, suspended below the structure at its current elevation, or placed on a separate utility bridge structure. As noted above (Section 3.3.5 Utilities), raising the sewer line is not considered to be feasible for this project given its current configuration requiring significant, costly rework and additional impacts to hospital access. Suspending the sanitary sewer below the bridge or placing it on a separate utility bridge are more feasible options. City of Renton | March 12, 2025 Page 14 File No. 0693-093-00 3.5 SUMMARY OF POTENTIAL DESIGN ALTERNATIVES Table 4 summarizes the design alternatives that we evaluated, as discussed in the preceding sections. TABLE 4. SUMMARY OF POTENTIAL DESIGN ALTERNATIVES DESIGN FACTORS ALTERNATIVES EVALUATED DESCRIPTIONS AND VARIATIONS Stream alignment and profile Alignment A Existing stream alignment, 4.8 percent slope Alignment B Optimized stream alignment, 4.8 percent slope Hydraulic Opening Minimum width 14.0 feet Recommended width 18.0 feet Minimum height 10.2 feet (2.2 feet 100-year flood WSE plus 3 feet freeboard plus 3 feet scour depth plus 2 feet foundation burial below scour depth) Recommended height 13.0 feet (providing 6 feet of maintenance clearance in addition to minimum parameters above) Roadway Alternative 1 Two 11-foot vehicular lanes, two 4-foot shoulders, two 5.5-foot sidewalks with curbs, and 2-foot clearance between the back of sidewalk and slope on both sides (45-foot total road section) Alternative 2 Three 11-foot vehicular lanes, one 4-foot shoulder (one side) and one 5-foot bike lane (other side), two 5.5-foot sidewalks with curbs, and 2-foot clearance between the back of sidewalk and slope on both sides (57-foot total road section) Construction Methods and Maintenance of Traffic Cut and cover; remove existing fill; full road closure Shortest construction duration and lowest cost One-lane bypass or single-lane closure with phased construction Additional shoring or shoofly would be required, adding substantial cost, additional impacts, and extending construction duration. Utilities Replace in existing location Will need to be relocated and maintained during construction. For culvert options, utilities would be buried in fill prism over structure. For bridge option, sanitary sewer would be suspended below structure. Raise sanitary sewer to attach to bridge Would require extending utility work well beyond project footprint, impacting hospital access, and potentially requiring a lift station. Construct separate utility bridge More costly than suspending below bridge structure. Structure Type Alternative a: Precast Concrete Box Culvert Three-sided box on shallow foundation Four-sided box Alternative b: Steel Plate Arch Culvert Steel plate arch on shallow foundation Alternative c: Bridge Precast concrete girders on deep foundations Notes: WSE = water surface elevation City of Renton | March 12, 2025 Page 15 File No. 0693-093-00 4.0 Cost Estimates and Recommended Conceptual Design Based on the potential design alternatives summarized in Table 4, above, and the discussion of these various factors in Section 3.0 of this report, we identified eight feasible conceptual design alternatives and developed rough-order-of magnitude cost estimates for each. Conceptual design drawings are included in Appendix C, Design Concepts. For the bridge alternatives, sub-alternatives included supporting the utilities on the proposed bridge or constructing a separate utility bridge. These alternatives are summarized in Table 5, below. TABLE 5. CONCEPTUAL DESIGN ALTERNATIVES ALTERNATIVE ROAD SECTION STRUCTURE TYPE 1a 1 (45 feet) Three-sided pre-cast concrete box culvert on shallow slab 1b 1 (45 feet) Steel plate arch culvert on shallow slab 1c.1 1 (45 feet) Bridge, prestressed concrete girders, CIP concrete deck on drilled shafts with separate utility bridge 1c.2 1 (45 feet) Bridge, prestressed concrete girders, CIP concrete deck on drilled shafts with utilities hung on bridge 2a 2 (57 feet) Three-sided pre-cast concrete box culvert on shallow slab 2b 2 (57 feet) Steel plate arch culvert on shallow slab 2c.1 2 (57 feet) Bridge, prestressed concrete girders, CIP concrete deck on drilled shafts with separate utility bridge 2c.2 2 (57 feet) Bridge, prestressed concrete girders, CIP concrete deck on drilled shafts with utilities hung on bridge 4.1 ESTIMATE OF CONSTRUCTION COST The conceptual-level engineer’s estimate of probable costs for the eight alternatives identified above are provided in Appendix D, Conceptual Design Opinion of Probable Construction Cost. Key assumptions and data gaps related to the cost estimates are noted below: ■ For all alternatives, construction will require easements with owners of three to four private properties upstream, and four properties adjacent to the project. ■ Temporary stream bypass can be implemented using a gravity system without pumping. ■ Closure of Talbot Road South will be required with associated detour of traffic. As a preliminary estimate, road closure and detour are anticipated to take 12 to 20 weeks. Construction of the new crossing structure in upstream/downstream phases that would allow for keeping Talbot Road South open to alternating traffic is not considered feasible due to the extensive costs associated with temporary bridge structures and shoring associated with building in phases to maintain access. ■ Excavation extents north and south along Talbot Road South and associated utility impact zones remain to be identified. The current recommendation is to remove all of the loose embankment fill between the historic valley walls. City of Renton | March 12, 2025 Page 16 File No. 0693-093-00 ■ Costs for utility bypass are preliminary estimates that will be refined during preliminary design through coordination with utility owners. ■ Streambed substrate is anticipated to be a mix of boulders, cobbles, gravel and sand. A specific gradation will be developed during project final design. ■ Substantial quantities of large wood will be incorporated into the stream banks as required to meet applicable guidelines. ■ Minor impacts to the wetland downstream of the crossing are anticipated to be accommodated within the permitting process anticipated for the project, without additional mitigation. ■ Cost estimates include a 40 percent contingency. Costs for the alternatives ranged from $8.0 million for Alternative 1a to $10.3 million for Alternative 2c.1. The bridge alternatives are estimated to have higher costs as compared to the culvert alternatives. The difference in costs between the least expensive alternative (1a) and the most expensive alternative (2c.1) is approximately $2.3 million, which may be within the range of error given the conceptual level of design and contingency factor applied across all alternatives. All alternatives using the smaller road section are slightly less costly than the equivalent structure type for the larger road section. Bridge Alternative 2c.1 that included constructing a separate utility bridge was approximately 10 percent more expensive than alternative 2c.2 that supported utilities on the primary bridge structure. 4.2 PREFERRED ALTERNATIVE Selection of a preferred alternative was completed in collaboration with the City of Renton Surface Water Utility and Transportation Departments and was not based on cost alone. As noted above, the bridge alternatives were more costly than buried culvert alternatives; however, the difference in costs may be within the margin of error at the current level of design analysis. Furthermore, bridge alternatives offer the following advantages: ■ Bridge alternatives keep all permanent infrastructure within existing City-owned right-of-way. All culvert alternatives would require permanent easements or right-of-way acquisition on adjacent properties. ■ Bridge alternatives are more likely to gain acceptance by regulatory agencies, particularly in light of the potential bedrock present below the existing culvert. If a bridge crossing is selected and the stream channel erodes, exposing bedrock and resulting in formation of a fish passage barrier after crossing replacement, the barrier may be considered natural by regulatory agencies and not require corrective actions. For a culvert structure, fish passage parameters may be required to be maintained by the City. ■ There may be opportunity to complete some advanced work before shutting down the road completely during construction. For example, alternating lane closures may be feasible while installing drilled shaft bridge foundations. For culvert alternatives, embankment excavation would require road closure at the construction outset. ■ There are less design parameter data gaps for bridge foundations whereas the culvert footing design is subject to revision or possible adjustment during construction depending on where bedrock is encountered during excavation. ■ There is no need to backfill the valley excavation with a large amount of imported structural fill material with the bridge alternatives. City of Renton | March 12, 2025 Page 17 File No. 0693-093-00 ■ There may be more potential construction or maintenance funding opportunities associated with bridge infrastructure funding. ■ Bridge inspections and maintenance may be easier than descending into the ravine to conduct culvert inspections with limited headroom. For these reasons, the City prefers the bridge alternatives to the culvert alternatives examined in this analysis. The City has also selected to proceed with the larger of the two road section widths (Alternative 2), with some minor modifications: the two-way left turn lane width is increased to 12 feet and bike lanes are proposed on both sides of the roadway. The larger road section width provides for greater public safety and transportation connectivity by providing bike lanes as well as continuing the existing central two-way left turn lane present to the south onto the bridge, which provides vehicles more time to merge into traffic. Suspending the utilities from the bridge structure is estimated to be less costly than constructing a separate utility bridge, which provides no other advantages. Therefore, the preferred alternative has the following parameters: ■ Structure: bridge, prestressed concrete girders, CIP concrete deck on drilled shafts. ■ Stream Alignment and Channel Section: Alternative B, slope of 4.8 percent, 18-foot channel section width. ■ Road Section: Two 11-foot vehicular lanes, one 12-foot two-way left turn lane, two 5-foot bike lanes, two 5.5-foot sidewalks with curbs, and 2-foot clearance between the back of sidewalk and slope on both sides (total road section is 59 feet). ■ Maintenance of Traffic: full road closure during construction with detour route. ■ Utilities: replaced in existing location and suspended from bridge structure. 5.0 Data Gaps The following data gaps have been identified and are recommended to be addressed as part of 30 percent design advancement: ■ Identify appropriate excavation slopes to develop extents of excavation. ■ Coordinate with utility providers regarding allowable outages and other temporary relocation requirements during construction activities, and associated costs. ■ Verify utility depth and location with potholing to advance design and reduce project risk. ■ Additional geotechnical borings may be needed at each proposed bridge abutment. 6.0 References American Association of State Highway and Transportation Officials (AASHTO). 2018. A Policy on Geometric Design of Highways and Streets, 7th Edition. ISBN No. 978-1-56051-676-7. City of Renton | March 12, 2025 Page 18 File No. 0693-093-00 Barnard, R., Johnson, J., Brooks, P., Bates, K., Heiner, B., Klavas, J., Powers, P. .2013) Water Crossing Design Guidelines. Washington Department of Fish and Wildlife. Olympia, WA. City of Renton. 2023. City of Renton COR MAPS System, 2021 Digital Elevation Model Layer, Accessed November 8, 2023) Federal Emergency Management Agency (FEMA). 2023. National Flood Hazard Layer FIRMette, Panel 53033C0979G, effective 8/19/2020. Exported on November 7, 2023. GeoEngineers, Inc. (GeoEngineers). 2023. Critical Areas Assessment, Panther Creek at Talbot Rd S Culvert Replacement Project. Prepared for City of Renton, October 23, 2023. GEI File No. 0693-093-00. GeoEngineers, Inc. (Geoengineers). 2025. Preliminary Geotechnical Design Report for 10% Design, Panther Creek Culvert Replacement Project, Renton, Washington. Prepared for City of Renton, February 12, 2025. GEI File No. 0693-093-00. King County. 2023. Hydrologic Information Center. Retrieved from Kingcounty.gov: https://green2.kingcounty.gov/hydrology/DataDownload.aspx?G_ID=97&Parameter=Stream%20 Flow King County. 1943. John Langston Rd Revn for Fill Bridge No. 80c. King County Sec. Road Proj. No. 49, Comissioner's District 2, Approved Feb 19, 1934. Mullineaux, D. 1965. Geologic map of the Auburn quadrangle, King and Pierce Counties, WA. U.S. Geologic Survey, Geologic Quadrangle Map GQ-406. R.W. Beck. 1997. East Side Green River Watershed Project, Environmental. Prepared for City of Renton, September 1997. Washington State Department of Transportation (WSDOT). 2023. Hydraulics Manual. Design Office, Engineering and Regional Operations Division, Publication Number M23-03. Figures Burling ton N orthe rn S an t a F e Bu rl i ng ton N o r t h e rn Sa nta Fe B u r l i n g t o n N o r t h e r n S a n ta F e Talb o t R d S S W 34th St SW 4 1 st S t L i n d A v e S W S W 39th S t E V a l l e y R d 167 Valley Medical Center B u rli ng t on Nor t hern Sa nta Fe S 5 0th St S 18 7th St 90 th Ave S S 18 0th S t 167 Great Wall Mall S38th C t Mi l l A v e S 108t h A v e S E Ta l b o t Rd S Mo r r i s A ve S S 3 6 t h P l 10 3 rd A ve S E SE 1 72 nd St 1 0 6 t h A v e S E B e n s o n R d S B e n s o n D r S S E Carr Rd 515 P a n t h e r C r e e k S E C arr R d 515 SITE Vicinity Map Figure 1 Panther Creek at Talbot Road S. Culvert Replacement Project Renton, Washington 3 Alpine Lakes Wilderness Kent Tacoma Seattle 0 1,000 Feet P: \ 0 \ 0 6 9 3 0 9 3 \ G I S \ 0 6 9 3 0 9 3 _ P r o j e c t \ 0 6 9 3 0 9 3 _ P r o j e c t . a p r x \ 0 6 9 3 0 9 3 0 0 _F 0 1 _ V i c i n i t y M a p D a t e E x p o r t e d : 1 1 / 0 9 / 2 3 b y c c a b r e r a Source(s): • ESRI Coordinate System: NAD 1983 StatePlane Washington North FIPS 4601 Feet Disclaimer: This figure was created for a specific purpose and project. Any use of this figure for any other project or purpose shall be at the user's sole risk and without liability to GeoEngineers. The locations of features shown may be approximate. GeoEngineers makes no warranty or representation as to the accuracy, completeness, or suitability of the figure, or data contained therein. The file containing this figure is a copy of a master document, the original of which is retained by GeoEngineers and is the official document of record. a. .--i "' ri .--i "'"' 0 "' .--i i::ij!lg � Cl "' 0 " If) "O 15" 0 i'> C "' �: �I 0 gi 0 "'a,co� -� � � 0 � Cl <( "'a,0 gi co � � " ',, \ ......... \ \ \ \ \ \ \ ($.! l///1/f///// I I \ qJ �\, ' \, ',,,, ',, __________ ...... \\\\\\\'\r::/1////////// ii \ t1 \ '� ',\ ',,______ ------,,, \ \ \ .-l \ \ \ ', / ; / / ; / / /; ; ( ( �, [ !\ '\ Existing Thalweg -"'-,,____ N282.PROPPl:ff{f�140, \ / / i ( ( ( (:, '(j , '<<',,',,\\r--J i \ , \ ..... ,, --------.... 3721-�ALBotRb\$�\ \ \ \'\ '\'\''<'< '" >�·\>><\�, !\ 00 '' ', ',.. 't=11 c=11\\I\\I\ ,,,,,,,, I 1 i ',, �'--,,, '--T?N 302QQ�9,0;./4\ \ \ \ \ \ \ \ \ \ \ \\\\\\\ I \ '� ',, ', ',,_ ', \ \ \ \ \ \ \ \ \�1 \ \ I \ \ '\ \ \ \ \ \ \ \ \ \ ' ,��',, '-.,, ',, ', ', ',, 1\\\\\1\ \\\\\',\\\\\\\\[ I Proposed Thalweg 11Alternative A" Alignment , '-.,,',,, \ \ \ \ \ \ \ \ , \ \ \ \ \,, \�\ \ \ \ \ \ \ \ \ 1, \ ',,\ ,', I 1\1\\111\\\\\\�\1\111\II\ ! (Match toExistingSta.0+61.31) , __ � \ \ \\\\\\\\\\',,,',,,',\\\\\\\\\\\\ / i I I ' I,-/? I ' I I / I I I!'! "I I II ! I � I I ii! II I I I I I � 0 6 ·---�--<:::::----��---------��---,---��--------�----<><>',,,, ',,,',,,__ >\ \\ \ \ \\\\\::,�::;:::::::::::�::�::::::::,:�,:::{<�\}�::\ / /1 o --°'�--------:_����/�-�----:��:�-.:-��---\ '1 �1 ',,\ ',,_',,,, '--,\ \� \ \ \ \\,:�<::<:,::::<,\>::--?;·1)Y1\111 l l l fi,,tj ;:/., '--��:---:_:�---\ \ \ / / loo f l \ \ \ '\, \�\ \ \ \ '\ ',1 '1� ! f / / j j if / ! f ! / / ( ,1 "j"' I I I I II I I I I I ,1+ �\ l \ \ // / f I '\. \ \ \ \ \ \ \ \ \ I 1111 /11/:11:/l:i/11 1 --� )\, \ J / / / I \, \ \ '1 \ \ \ \ \ \ } / ff ,f ! I/ f ! If f I I I If I ) 1515 �� I / ! I I I , I I l I 1 ,, I I I I I I I I I I r I I I I I I I 1/'/i Proposed Thalw .,. ;A } / J I !t,_ ',, \ \ : \ \ \ \, \ 'i ; ! I I ii I I f 'o' / ,I I f I f I ! i ! � 11Alternative B11 '',,.___ � --x l \\ '\\ 1] \ l \ \ \ \ I ) I I ; ! ! I I I I I I i f I I ! I I I ! I I 0 ; I I I I I I e I I I I i I I I I , I CJ ,11 I ' ' ' I I l 1 I 1N' r,,,,,,r,1 11 /Jr/1/ "'/ ,, � 111 1 , , 1 1 1 1 1 1, ( 1 1 1 1r1/r11 j,1//1}11 , / It Alignment (Match to ___ ---------------\ \\\/ / --�;3-'--::--�----\ l l \ \ \ \ \ ! I !if f f II/ f ! ff ff f ! j I Pia Existing Sta. 0+61.31) ----------.. ----------,'L ..--::�;.:::;Si:�\--.. , \ l \ \ \ \ \ \ \ { t'! 11I11 I! f If: I/ 11 /Ii "<,',,, 1 \ -----...-�v,ic.._.-::-,,:_-...:,,-..� .... ,:-,,',,2-..., l \ \ 11 I \ \ 'I I I I / I I / I / / I I ,_ I I I I I 4 . I.................. \\ ��� .... :::� �L!l� .. :::::-�.:-,:-.:-..,,.:-.,:-...... --\ \ \ \ \ \ \: 1 \ \ I I / f / I I I 1, a , __ o ....... , \�� .... /--"<>--... ":.:-..:--=-.:-t\\\ \ \ \ \ \ : I ! : N \ l:: r / / ............ \ '�1 ----�--- _w_ -'''--�"--: ....... �\,\\\\ \ I \ \ Tl I 1 l I ml I:// 1 1::r:/ ,, \ \I -...l..lL ...I.IL ...I.IL ...l..lL \\\l11111 I I I If I 111 I I 1111 10 ::r; BROLIN-VALLEYVIEWLLC ...... ... ... \ \'� ,,/' \\\'S\\\ \ \ \ i I i !ii! !1 ,1,� 350 S 38TH CT ................ \ ...........� � �ijl_g. ...... � �4\\\\\ \ \ \ : M : 1 1 l \ l l I I I It I I • .... ... \ \,, \, _w_ _Ill_ .,...,..., .... _Ill_ �\\\\\\\ \ l r I H I : : I ; ; / / /; / / /: TPN 3023059111 ......... \ ----... , , �µ_..-----...l.lL � \\\\\\\\\ \ 1 : : 1 i 1 1} / / i: / / 1 / / / / / / 0 ...... , ',,, '-., __ .,., Ws[L-=---lt�\; \\\\\\\\\ ( \ \ \ \ \ }/liJ//!l/t!f O 0 1-. -., '-.., \ �\\1\\111 l I\\\ 111//111 l /1 1//1-----Q ......... '',, ....... __ ' .... , ....... '/.�\ / \\'\\\\\\ \ \ \ \ }///////////////I _-_:::...,----......... -............ ,...... ·l')m,,.,._t;:.,,;;::;' \ \11 \' \\\}!ft!/// ,1/Jt//l I -----_----.... :--::::--................. "' .... .':c:"!',=,.Q!� \ \ Jj I fl I ! I I I l / l I l e I I I "I I e I I I I " I II I I ' I I/ I I I I II I e ,f' I "I I ! I' I I / I / I I I I , ff/ I II I ,? I I I I, II I I I ,'R I, I I/ I ,f I Source(s): PUBLIC HOSPITAL DISTRICT #1 3401 TALBOT RDS. TPN 3023059034 PUBLIC HOSPITAL DISTRICT #1 3901 TALBOT RDS. TPN 3123059065 •Survey from KPFF, dated 7/14/2023. Coordinate System: Washington State Plane, North Zone, NAD83, US Foot. Disclaimer: This figure was created for a specific purpose and project. Any use of this figure for any other project or purpose shall be at the user's sole risk and without liability to GeoEngineers. The locations of features shown may be approximate. Geo Engineers makes no warranty or representation as to the accuracy, completeness, or suitability of the figure, or data contained therein. The file containing this figure is a copy of a master document, the original of which is retained by GeoEngineers and is the official document of record. y v-' / _______________________________ )v., -p---== ss---ss RIM= IE 18" CONG (NJ =87.45 IE 18" CONG (SJ = 89.16 -1£8"� �@:..---=!8--!-rJi'Bc/=c¼l IE 8" CONG (WJ =88.60 8" TO 6" ADAPTER WEST OF SSMH >--------< ---OHW------WETL---..... --............. __..... ---................ __ ,,. ---P--- ---OH--- ---TC--- ---w--- ---G--- Legend (Exi�ting) f Parcel Property Line Culvert Ordinary High Water Line Wetland Line Panther Creek Thalweg Alignment Existing Major (5-ft) Contour Line Existing Minor (1-ft) Contour Line Underground Power Overhead Utilities Underground Telecommunications Water Line Gas Line V''I I I I I II I I e ' II I ii! I I II '" ' I I I I + I B-3 I i'i_l I I I I I Legend(Proposed) Panther Creek Thalweg "Alternative A" Alignment Panther Creek Thalweg "Alternative B" Alignment I I 0 Feet I I I 30 -SSMH#2 RIM=93.62 IE 12" CONG (NJ= 80. 71 IE 12" CONG (EJ =80.65 IE 18" CONG (5) =79.90 IE 18" CONG (WJ =79.87 Plan View i 0 Cf) 'O i3 I a I a I a + a I ;,; I I I Panther Creek at Talbot Road S . Culvert Replacement Project Renton, Washington Figure 2 a:---------------------------------------------------------------------------------------------------------------------------------------------------· EL E V A T I O N ( F E E T ) EL E V A T I O N ( F E E T ) STATION (FEET) 0 50 100 150 0 50 100 150 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 5+93 EL E V A T I O N ( F E E T ) EL E V A T I O N ( F E E T ) STATION (FEET) 0 50 100 150 0 50 100 150 0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+505+68 Existing Ground Surface 4.8% 4.6% 367.9' 424.6' Proposed Thalweg (See Note 1) Match to Existing Grade Match to Existing Grade Existing Ground Surface Proposed Thalweg (See Note 1) Match to Existing Grade Match to Existing Grade Existing Panther Creek Thalweg Talbot Road S. CLExisting 36" CMP Culvert Talbot Road S. CL Existing 36" CMP Culvert Existing Panther Creek Thalweg EL E V A T I O N ( F E E T ) EL E V A T I O N ( F E E T ) OFFSET (FEET) 65 70 75 80 65 70 75 80 0 5 10 15 200-5-10-15-20 Streambed Material Existing Ground Surface Proposed Grade Match to Existing Grade Match to Existing Grade 10:1 2:1 2:110:1 10:1 10:1 2:1 20.0' 3.0' EL E V A T I O N ( F E E T ) EL E V A T I O N ( F E E T ) OFFSET (FEET) 55 60 65 70 75 80 85 90 95 100 55 60 65 70 75 80 85 90 95 100 0 5 10 15 200-5-10-15-20 2:1 Topsoil and Native Planting on Floodplain Benches and Slopes Preliminary Minimum Hydraulic Opening = 14 - 18 Ft (18 Ft Recommended, to be Refined During Preliminary Design) Existing Ground Surface Existing Culvert (Approximate) Talbot Road S. CL Preliminary Culvert Height Above Thalweg (5.3 Ft) Culvert Type and Size to Determined. Section Shows Preliminary Concept for 18 Ft. Wide 3-Sided Concrete Box Culvert. Fill: Typically Clayey to Silty Fine Sand with Gravel (Variable, Loose) Possible Zone of Renton Formation Bedrock (Inferred from Geotechnical Borings). See Note 3. Possible Zone of Very Dense Glacial Till (Inferred from Geotechnical Borings). See Note 3. Thalweg at Talbot Rd. S. CL (See Profile): Alt A IE: 66.70 Ft Alt B IE: 66.72 Ft Streambed Material 10.0' 1.0' Preliminary Estimate of Footing Depth Below Thalweg (5 Ft). Remove Bedrock to this Depth. Additional Bedrock Removal May be Needed for Footing Thickness. Figure 3 Profiles and Sections Datum: NAVD88 Disclaimer: This figure was created for a specific purpose and project.  Any use of this figure for any other project or purpose shall be at the user's sole risk and without liability to GeoEngineers.  The locations of features shown may be approximate.  GeoEngineers makes no warranty or representation as to the accuracy, completeness, or suitability of the figure, or data contained therein.  The file containing this figure is a copy of a master document, the original of which is retained by GeoEngineers and is the official document of record. P: \ 0 \ 0 6 9 3 0 9 3 \ C A D \ 0 0 \ A l t e r n a t i v e A n a l y s i s \ 0 6 9 3 0 9 3 0 0 _ F 0 2 _ F 0 3 _ P l a n V i e w _ P r o f i l e s a n d S e c t i o n s . d w g 3 D a t e E x p o r t e d : 1 0 / 2 3 / 2 0 2 3 1 2 : 3 6 P M - b y S u n g - C h u l S o n n y Y i Horizontal Feet 0 100 100 Vertical Feet 0 Vertical Exaggeration = X1 Panther Creek at Talbot Road S. Culvert Replacement Project Renton, Washington Alternative A Profile Alternative B Profile Horizontal Feet 0 10 10 Vertical Feet 0 Vertical Exaggeration = X1 Typical Creek Section Typical Creek Section in Culvert Notes: 1. Creek thalweg will have vertical undulations to create pool/riffle habitat zones. 2. Proposed streambed substrate will be mix of fines, sand, gravel, and cobbles similar to existing reference reach. 3. The subsurface conditions shown are based on interpolation between widely spaced explorations and should be considered approximate; actual subsurface conditions may vary from those shown. 4. Existing utilities not shown (See Figure X). 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com Feet 0 500 1000 PANTHER CREEK CULVERT REPLACEMENT ROAD CLOSURE AND DETOUR PLAN Figure 4 Appendices Appendix A Hydraulic Design Field Report ☐ THIS FIELD REPORT IS PRELIMINARY A preliminary report is provided solely as evidence that field observation was performed. Observations and/or conclusions and/or recommendations conveyed in the final report may vary from and shall take precedence over those indicated in a preliminary report. FIELD REPRESENTATIVE DATE Chelsey Gohr, LG 8/2/23 Evan Deal, PE 8/2/23 David Conlin, PWS 7/20/23 ☒ THIS FIELD REPORT IS FINAL A final report is an instrument of professional service. Any conclusions drawn from this report should be discussed with and evaluated by the professional involved. REVIEWED BY DATE Ken Fellows, PE 8/7/23 Dan Eggers, PE 8/13/23 This report presents opinions formed as a result of our observation of activities relating to our services only. We rely on the contractor to comply with the plans and specification throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the work of others. Our firm will not be responsible for job or site safety of others on this project. DISCLAIMER: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record. Attachments: Figures 1 through 15 Distribution: Field Report File Number: 0693-093-00 1101 Fawcett Ave, Suite 200 Tacoma, WA 98402 253.383.4940 Project: City of Renton, Panther Creek Culvert Replacement Date(s): June 28, 2023, July 31, 2023 Owner: City of Renton Time of Arrival: 9:00 AM Report Number: FR-01 Prepared by: Chelsey Gohr, LG, Peter Savchik, Bea Renaud, David Conlin, PWS, and Evan Deal, PE Location: Panther Creek at Talbot Road South Renton, Washington Time of Departure: varies Page: 1 of 16 Purpose of visit: Stream Reconnaissance Weather: Sunny, dry Travel Time: varies Permit Number: n/a Upon arrival to the site, I assessed personal safety hazards: Yes or Referred to Site Safety Plan and Safety Tailgate if applicable Safety Hazards Were Addressed by : Staying Alert to Traffic Slip, Trip and Falls 0BINTRODUCTION Washington Department of Fish and Wildlife (WDFW) has identified the crossing of Panther Creek under Talbot Road South (WDFW Site ID: 931933) as a total fish passage barrier due to water surface drop (WDFW 2022) (Figure 1 and Figure 2). The City of Renton has also identified the existing crossing structure at this location as failing, presenting a risk to traveling public. GeoEngineers, Inc. (GeoEngineers) is working under contract to the City of Renton to complete a hydraulic design for replacement of the deteriorated crossing structure at this location that meets fish passage criteria and reduces risk to the public. This field report documents our observations of the existing geomorphic, biological, and hydraulic conditions of Panther Creek in the vicinity of the existing crossing. Fieldwork was completed on June 28 and July 31, 2023, including general site observations, assessment of stream conditions, identification of a reference reach, and collecting bankfull width measurements and Wolman pebble count data. The GeoEngineers’ field team (Table 1) assessed the crossing structure inlet and outlet, the upstream channel within approximately 230 feet upstream and from approximately 350 to 450 feet upstream of the culvert inlet, and the downstream reach within approximately 200 feet downstream from the culvert outlet. File No. 0693-093-00 August 14, 2023 Page 2 TABLE 1. FIELD TEAM Name Role Evan Deal, PE River Engineer Peter Savchik Staff River Engineer Chelsey Gohr, LG Staff Fluvial Geomorphologist David Conlin, PWS Senior Ecologist Bea Renaud Staff Biologist 1BGENERAL SITE DESCRIPTION The project site is located in the City of Renton, Washington, in King County. The subject crossing is located where Panther Creek crosses Talbot Road South, just north of Valley Medical Center. The City of Renton plans to replace the culvert passing underneath Talbot Road South, as it is deteriorated and therefore at risk of failure, as well as being a barrier to fish passage. Talbot Road South, at this location, provides hospital access from the north. The project crossing of Panther Creek is located along the gradual transition from steeper sloped terrain near the stream headwaters on Benson Hill to shallower sloped terrain in the valley bottom associated with the Green River floodplain and several tributaries to the Green River. Panther Creek originates at Panther Lake approximately 1.75 miles to the southeast and flows generally northwest or west through a confined ravine and through the project crossing. Approximately 850 feet downstream of the project crossing, the confined ravine topography transitions to a wider valley bottom in the greater Green River Valley. Through the Green River Valley, Panther Creek flows north for approximately one-half mile through several low-gradient wetland complexes before turning west under SR 167. The remainder of Panther Creek is generally ditched through an industrial and commercial area, where it flows into Springbrook Creek approximately 0.85 miles downstream of the SR 167 crossing, and then into the Black River and Green/Duwamish River, eventually flowing into the Puget Sound at the Duwamish waterway in Seattle. Downstream of the project crossing, there are no other structures currently considered by WDFW to be barriers to fish passage (WDFW 2023). The ravine in which the project site is located is mapped by Mullineaux (1965) as the Renton Formation and is characterized by Arkosic sandstone, mudstone, and shale. All other areas surrounding the project reach, including the reference reach, are mapped as glacial till, consisting of compact, unsorted sand, silt, clay, and gravel. 2BREFERENCE REACH A reference reach was established during the July 31st site visit starting approximately 350 feet upstream of the project crossing where longitudinal channel slopes are similar to design slope targets. The field team then progressed upstream to an area assumed to be out of the area of influence of the confluence of unnamed tributary (UNT) to Panther Creek and Panther Creek (located at approximately 500 feet upstream of the crossing inlet) to mark the upstream most end of the reference reach approximately 450 feet upstream of the project crossing. See Figure 3 and Figure 4 for upstream and downstream reference conditions. The approximately 100-foot-long reference reach is a single thread channel located within a meander bend with the apex oriented along the right bank. The reach has an average slope of 4.4 percent (Washington State Department of Natural Resources, 2021) and exhibits a step-pool bedform. An approximate 35-foot-long portion of the reference reach appears more as a step-riffle morphology as pools are very shallow. Water surface drops off several inches occur across these steps (Figure 5). Pools ranged from approximately 2 to 5 feet long with a File No. 0693-093-00 August 14, 2023 Page 3 maximum depth measured of 5-inches deep. Streambed material in the reference reach consists of small to medium-sized cobbles with coarse gravels and occasional small boulders. Fine to coarse sands were observed along channel bank toes with a fine to coarse gravel armor, or within undercut pools. On the inside (left bank) of the meander bend, the banks were up to 6 feet high. Undercut banks were common and multiple areas of bank failure were observed as bare (lack of vegetation), vertical banks. On the right bank, or outside of the meander bend, channel banks ranged from a few inches to up to 1.5 feet high. Floodplains and discontinuous benches were observed along the right bank throughout the reference reach with the exception of the downstream end of the reference reach where the right bank rises up to 4 feet above the channel and the left bank becomes accessible to higher flows (Figure 6). 3BSEDIMENT SAMPLING GeoEngineers completed four Wolman pebble counts (PCs): three upstream and one downstream of the project crossing (Table 3). One pebble count (PC1) is located within the reference reach. The field team collected each pebble count across 10 separate linear transects perpendicular to flow through a riffle and within the bankfull width. The largest naturally occurring clasts in the system were small to medium boulder sized. TABLE 2: WOLMAN PEBBLE COUNT DATA Pebble Count PC1 Upstream (Reference Reach) (in) PC2 Upstream (in) PC3 Upstream* (in) PC4 Downstream (in) Diameter Percentile D16 0.6 0.4 1.1 0.5 D50 2.3 1.5 2.9 1.6 D84 5.8 4.2 4.9 4.3 D95 8.5 9.6 6.8 6.0 *Note – Pebble count data collected in a location with a bankfull width measurement excluded from the design average BFW calculation 4BBANKFULL WIDTH The field team recorded nine bankfull width measurements (BFWs; Table 3); six upstream of the crossing and three downstream. Three of the upstream measurements were taken within the reference reach. Four of the bankfull measurements coincide with the locations of pebble counts collected at the site. Table 3 presents the bankfull width measurements and locations. The two bankfull width measurements upstream of and nearest to the crossing inlet were not included in the design bankfull width calculation. These measurements were not considered to be representative of the natural stream condition because they are likely within a depositional reach caused by the backwater influence of the existing, undersized crossing structure expected to occur during flood flows. File No. 0693-093-00 August 14, 2023 Page 4 TABLE 3: GEOENGINEERS BANKFULL WIDTH MEASUREMENTS Approximate Distance (feet) Upstream or Downstream from Crossing Inlet or Outlet Respectively Bankfull Width (feet) Used in Design BFW Average? 40 (Upstream) 17.5 No 70 (Upstream, at PC3) 14 No 215 (Upstream, at PC2) 8.8 Yes 350 (Upstream within reference reach; at PC1) 9 Yes 405 (Upstream within reference reach 9.8 Yes 450 (Upstream within reference reach) 8.7 Yes 75 (Downstream, downstream of pool) 14.3 Yes 172 (Downstream) 8.6 Yes 182 (Downstream, at PC4) 7 Yes Design Average 9.5 - 5BOBSERVATIONS 8BProject Crossing The project crossing is comprised of a 32-inch diameter fiberglass reinforced corrugated steel pipe with a slope of 4.11 percent (WDFW, 2022). There is a significant amount of road fill above the culvert; about 34 feet at the downstream end and 20 feet at the upstream end. The upstream end of the culvert is framed by a concrete headwall and wingwall, and considerable structural damage to the pipe due to gravel wear along its invert was observed within the first several feet of pipe length at the inlet (Figure 1). This damage is likely the result of wear from sediment transported through the pipe. A channel-spanning log was observed within the channel at the inlet, creating an approximately 1.5-foot drop into the inlet and accumulating streambed sediment upstream. Downstream, the elevated crossing outlet has produced a 3.9-foot drop, as measured at the time of the field reconnaissance, from the culvert exit into a large scour pool below (Figure 2). The outlet scour pool had a maximum water depth of approximately 4 feet, as measured at the time of the field reconnaissance. In addition to the project culvert, two additional flow inputs were observed upstream of the crossing: stormwater road runoff from Talbot Road South was observed entering Panther Creek at the left bank immediately upstream of the project culvert inlet, and a municipal stormwater pipe was observed discharging to Panther Creek from the right bank approximately 95 feet upstream of the crossing inlet. 9BLarge Woody Material In the approximately 230-foot reach observed upstream of the project crossing, large woody material (LWM) is typically lacking, with several notable exceptions. At the upstream end of the observed reach (230 feet upstream of the inlet), woody material pieces consisting of fallen branches and small mobile woody material were present and contributed to the development of diverse micro habitats and in-channel complexity. Approximately 180 feet upstream of the crossing, a roughly 2-foot diameter channel spanning log covered by a thick layer of vines (English ivy, Hedera helix) was observed. The log rests approximately 3 feet above the channel on both the right and left banks and provides cover and shade over the channel. Just before the crossing, there is a large channel spanning log embedded into the channel bottom and wedged between the concrete wingwalls and/or riprap armor material, creating an approximately 1.5-foot drop into the culvert inlet (Figure 7). Several pieces of large, milled lumber line File No. 0693-093-00 August 14, 2023 Page 5 the right bank just upstream of the inlet and appear to be placed material, forming a bank armoring structure. These pieces appear to have little interaction with the channel except for at higher flows. Approximately 35 feet upstream of the crossing there is a collection of woody material concentrated on the right of the channel, followed by a scour pool (Figure 8). Downstream of the culvert, there are a number of pieces of LWM interacting with flow. Directly below the culvert outlet several LWM pieces were observed within the scour pool. Downstream from the scour pool, several single logs were observed interacting with flow, either entering obliquely from the bank or spanning the channel, creating steps and pools (Figure 9). No LWM was observed within the reference reach. Portions of the reference reach included branches up to approximately 0.5 inches in diameter hanging into the channel (Figure 3). Near the upstream end of the reference reach there were fallen branches of approximately 1.0 to 2.0 inches in diameter racked up near an approximately 36-inch diameter boulder. Combined, these branches spanned the channel reinforcing the step adjacent to the boulder. 10BGeomorphology Panther Creek flows as a sinuous, single-thread channel with varying slopes, bedforms and cross-sectional characteristics. Average reach slopes range from about 1.9 to 4.4 percent. A reach-based longitudinal profile is presented in Figure 11. Upstream of Project Crossing Panther Creek flows slightly sinuous to sinuous and is confined within a ravine. Between the crossing inlet and the confluence with the municipal stormwater pipe (approximately the first 100 feet upstream of the inlet), the channel widens to nearly double the size of the uppermost observed reaches. Bed material is predominantly cobbles, small boulders, and gravel and form steps within the channel down to the inlet. Just upstream of the confluence with the municipal stormwater pipe (approximately 95 feet upstream of inlet) channel banks are nearly vertical and range from 1.0 to 2.5 feet high and channel widths were observed to be approximately 7 to 9 feet. Minor toe erosion was observed throughout, and banks were heavily vegetated to the channel bank toe. Channel morphology is pool-riffle. Both riffles and pools were generally long running with pool depths no more than a few inches deep. Narrow, lateral gravel and sand bars were also observed. Throughout the entire upstream reach observed, floodplains are generally more accessible along the left bank. Sediment is predominantly very coarse gravel with cobbles and occasional boulders and a few angular concrete pieces of riprap were observed. Most of the boulder-sized material is covered with moss and not likely mobile except at very high flows. Few pieces of large wood interact with flow as are observed hanging over the channel with branches in the flow racking minor small mobile woody material. See Reference Reach section above for detailed geomorphic assessment of the reference reach. Downstream of Project Crossing At the downstream outlet, there is a large scour pool that reaches depths of approximately 4 feet. Immediately downstream of the pool, there is an accumulation of small cobbles and gravel with sand (Figure 12). The left bank coincides with the left valley wall, and exposed sandstone and mudstone is observed (Figure 14). The right bank offers backwater habitat at high flows that is most accessible approximately 27 feet downstream of the pool. The 200 feet of observed reach downstream of the culvert is pool-riffle morphology, with riffles on average measuring File No. 0693-093-00 August 14, 2023 Page 6 twice as long as pools (Figure 13). Bedform is mainly riffle, with some sections that are glide. Pool depths ranged from just a few inches to up to 1.1 feet deep. The deeper pools were observed just downstream of log pieces. For almost the entire reach that was observed, the left valley wall is confined with no accessible floodplain; discontinuous benches are approximately 2 feet above channel bed, but as high as 4 feet with vertical banks. In general, the right banks are sloped back and are no higher than 1.5 feet. Minor undercutting and toe erosion were observed. Lateral spanning channel bars consisted of coarse gravels and cobbles and a few sand deposits were observed. As the slope declines (1.9 percent slope) moving downstream, the left bank floodplain becomes accessible. 11BAquatic Habitat Panther Creek appears to provide decent habitat for fish, particularly upstream of the project crossing, which has more intact riparian forest vegetation (e.g., Figure 4). Flow is perennial and sufficient to support all life stages of salmon or trout year-round. The primary physical limiting factors for fish utilization in the project vicinity are anticipated to be: (a) limited riparian cover and closure in the reach immediately downstream (Figure 15), and (b) the total fish barrier presented by the subject culvert. Water quality may also be an issue, particularly in light of the stormwater discharge to the creek as well as the large outfall from a stormwater detention pond. Panther Creek is 303(d) listed for Benthic Index of Biotic Integrity, indicating degraded water quality. Panther Creek is also listed as Category 4A for temperature and there is a total maximum daily load (TMDL) in place for the Green River Watershed. Stormwater management from urban runoff as well as lack of riparian shade may contribute to elevated temperatures in Panther Creek. There are no fish barriers present within the system downstream of the project crossing. Anadromous fish may access Panther Creek up to the project crossing, but the subject culvert is believed to be a total fish barrier (WDFW 2022). Resident fish populations may occur both upstream and downstream of the crossing, and would also benefit from crossing replacement. The stream gradient is typically within the range for fish utilization. Substrate conditions throughout the reaches observed appeared generally appropriate for use by salmonids. Embeddedness is low and the distribution of sediment sizes, including boulders, cobbles, gravel, and sand appears to be appropriate for salmonid use (e.g., Figure 4 and Figure 13). However, some materials of artificial origin (e.g., broken concrete, angular rock) were also observed in the channel, and bank armoring (e.g., angular rock, milled lumber) is present, particularly upstream of the crossing. Pools are present throughout the observed reach, typically associated with LWM and/or naturally occurring boulder clusters forcing small steps followed by small pools (e.g., Figures 3, 4, 5, 6 and 9). LWM is generally limited, except in a few select locations described above (Figures 8 and 9). Several key pieces of LWM are present in the short reach immediately upstream and immediately downstream of the crossing, but overall the quantities currently occurring are insufficient to provide optimal fish habitat conditions. 12BRiparian Areas Panther Creek flows through a forested ravine, with urban residential, commercial, and institutional development beyond the immediate riparian area at the top of the valley walls. The vegetated ravine is typically approximately 130 to 200 feet wide in the vicinity of the project crossing both upstream and downstream, interrupted only by Talbot Road South, which crosses perpendicular to the stream. The Panther Creek ravine immediately upstream of the crossing is forested, creating dense shade even on the hot summer day that characterized site reconnaissance. Typical forest canopy species include bigleaf maple (Acer macrophyllum), red alder (Alnus rubra), and Western redcedar (Thuja plicata). Understory vegetation is severely File No. 0693-093-00 August 14, 2023 Page 7 compromised in this reach by invasive species, including English ivy (Hedera helix) and Himalayan blackberry (Rubus armeniacus). Native understory vegetation includes salmonberry (Rubus spectabilis), vine maple (Acer circinatum), sword fern (Polystichum munitium) and field horsetail (Equisetum arvense). Downstream of the project crossing, the forest canopy is more open immediately adjacent to the stream. The open area is dominated by invasive species, typically Himalayan blackberry and reed canarygrass (Phalaris arundinacea), as well as native salmonberry and beaked hazelnut (Corylus cornuta). Forested canopy set back from the stream bank includes bigleaf maple (Acer macrophyllum), Western redcedar (Thuja plicata) and some Western hemlock (Tsuga heterophylla). Forested areas and slopes in this area are also affected by proliferate English ivy (Hedera helix). 6BREFERENCES Mullineaux, D.R. 1965. Geologic map of the Renton quadrangle, King County, Washington, Washington: U.S. Geological Survey Numbered Series Map 405, scale 1:24,000, https://ngmdb.usgs.gov/Prodesc/proddesc_872.htm. Washington Department of Fish and Wildlife. 2022. Fish Passage & Diversion Screening Inventory Database Site Description Report: Site ID 931933. February 28, 2022. Washington Department of Fish and Wildlife. 2023. Washington State Fish Passage Online Database. Accessed July 2023. Available at: https://geodataservices.wdfw.wa.gov/hp/fishpassage/ index.html. Washington State Department of Natural Resources. (2021). King County (WA) West 2021. Retrieved from WA LiDAR Portal : https://lidarportal.dnr.wa.gov/ File No. 0693-093-00 August 14, 2023 Page 8 7BPHOTOS Figure 1. Project crossing inlet, looking downstream. File No. 0693-093-00 August 14, 2023 Page 9 Figure 2. Project crossing outlet, looking upstream File No. 0693-093-00 August 14, 2023 Page 10 Figure 4. At bottom of reference reach, looking downstream Figure 3. Upstream end of reference reach, looking upstream File No. 0693-093-00 August 14, 2023 Page 11 Figure 5. Cobble and boulder steps within the reference reach, looking upstream Figure 6. Example of confined left bank and accessible right bank floodplain within reference reach, looking upstream File No. 0693-093-00 August 14, 2023 Page 12 Figure 8. Large wood jam and scour pool approximately 35 feet upstream of crossing inlet, looking downstream Figure 7. Channel spanning log creating a 1.5-foot drop into inlet File No. 0693-093-00 August 14, 2023 Page 13 Figure 10: Small branches racked up on and beside an approximately 36-inch diameter boulder within the reference reach, looking upstream Figure 9. LWM within channel approximately 85 feet downstream of the outlet, looking upstream File No. 0693-093-00 August 14, 2023 Page 14 Figure 11. Reach-based longitudinal profile of the project crossing File No. 0693-093-00 August 14, 2023 Page 15 Figure 13. Pool-riffle channel morphology downstream of the outlet, looking upstream Figure 12. Channel spanning cobble and gravel bar at downstream end of outlet scour pool, looking downstream File No. 0693-093-00 August 14, 2023 Page 16 Figure 14. Siltstone and mudstone exposed along the left bank near the outlet File No. 0693-093-00 August 14, 2023 Page 17 Figure 15. Typical open riparian canopy downstream, dominated by invasive species with few trees set further back from the stream channel. Appendix B FEMA Flood Panel National Flood Hazard Layer FIRMette 0 500 1,000 1,500 2,000250 Feet Ü SEE FIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT SPECIAL FLOOD HAZARD AREAS Without Base Flood Elevation (BFE) Zone A, V, A99 With BFE or DepthZone AE, AO, AH, VE, AR Regulatory Floodway 0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mileZone X Future Conditions 1% Annual Chance Flood HazardZone X Area with Reduced Flood Risk due to Levee. See Notes.Zone X Area with Flood Risk due to LeveeZone D NO SCREEN Area of Minimal Flood Hazard Zone X Area of Undetermined Flood HazardZone D Channel, Culvert, or Storm Sewer Levee, Dike, or Floodwall Cross Sections with 1% Annual Chance 17.5 Water Surface Elevation Coastal Transect Coastal Transect Baseline Profile Baseline Hydrographic Feature Base Flood Elevation Line (BFE) Effective LOMRs Limit of Study Jurisdiction Boundary Digital Data Available No Digital Data Available Unmapped This map complies with FEMA's standards for the use of digital flood maps if it is not void as described below. The basemap shown complies with FEMA's basemap accuracy standards The flood hazard information is derived directly from the authoritative NFHL web services provided by FEMA. This map was exported on 11/7/2023 at 1:38 AM and does not reflect changes or amendments subsequent to this date and time. The NFHL and effective information may change or become superseded by new data over time. This map image is void if the one or more of the following map elements do not appear: basemap imagery, flood zone labels, legend, scale bar, map creation date, community identifiers, FIRM panel number, and FIRM effective date. Map images for unmapped and unmodernized areas cannot be used for regulatory purposes. Legend OTHER AREAS OF FLOOD HAZARD OTHER AREAS GENERAL STRUCTURES OTHER FEATURES MAP PANELS 8 B 20.2 The pin displayed on the map is an approximate point selected by the user and does not represent an authoritative property location. 1:6,000 122°13'W 47°26'54"N 122°12'22"W 47°26'30"N Basemap Imagery Source: USGS National Map 2023 Appendix C Design Concepts 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 1a - PLAN 0 15'30' C-1 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT 0 15'30' PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 1b - PLAN 0 15'30' C-2 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT 0 15'30' PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 1c - PLAN 0 15'30' C-3 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT 0 15' PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 2a - PLAN 0 15'30' C-4 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT 0 15'30' PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 2b - PLAN 0 15'30' C-5 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT 0 15'30' PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 2c - PLAN 0 15'30' C-6 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com C-7 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 1 - PROFILE AND CULVERT SECTION Figure 6 DR A F T C-83-SIDED BOX CULVERT PROFILE AND SECTION 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com PANTHER CREEK CULVERT REPLACEMENT ALTERNATIVE 2 - PROFILE AND CULVERT SECTION Figure 9 DR A F T C-9STEEL PLATE ARCH CULVERT PROFILE AND SECTION PANTHER CREEK CULVERT REPLACEMENT CITY OF RENTON 1601 5th Avenue, Suite 1600 Seattle, WA 98101 206.622.5822 www.kpff.com 10 % D E S I G N - N O T F O R C O N S T R U C T I O N City of Renton 1055 S. Grady Way Renton, WA 98057 (425) 430-6400 Know what's below before you digCall R PANTHER CREEK CULVERT REPLACEMENT ROADWAY PLAN AND PROFILE RD01C-10BRIDGE PLAN AND PROFILE Appendix D Conceptual Design Opinion of Probable Construction Cost Estimate of Probable Cost Panther Creek at Talbot Rd S Culvert Replacement Project Renton, WA Unit Price Unit QTY Total Cost QTY Total Cost QTY Total Cost QTY Total Cost QTY Total Cost QTY Total Cost QTY Total Cost QTY Total Cost PREPARATION, GENERAL 1 Mobilization (10% of total)LS 1 439,050$ 1 468,254$ 1 560,166$ 1 505,166$ 1 443,468$ 1 479,831$ 1 566,063$ 1 511,063$ 2 Clearing, Grubbing, and Roadside Cleanup 50,000$ AC 0.45 22,500$ 0.38 19,000$ 0.38 19,000$ 0.38 19,000$ 0.45 22,500$ 0.38 19,000$ 0.38 19,000$ 0.38 19,000$ 3 Removal of Structures and Obstructions 10,000$ LS 1 10,000$ 1 10,000$ 1 10,000$ 1 10,000$ 1 10,000$ 1 10,000$ 1 10,000$ 1 10,000$ 4 Sawcut Asphalt Conc. Pavement 45$ LF 101 4,545$ 101 4,545$ 101 4,545$ 101 4,545$ 101 4,545$ 101 4,545$ 101 4,545$ 101 4,545$ 5 Planing Butiminous Pavement 55$ SY 184 10,120$ 184 10,120$ 184 10,120$ 184 10,120$ 184 10,120$ 184 10,120$ 184 10,120$ 184 10,120$ 6 Structure Surveying 5,000$ LS 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 7 Roadway Surveying 5,000$ LS 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 8 As-bult Survey and Record Drawings 5,000$ LS 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 1 5,000$ 9 Work Access (stream)50,000$ LS 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 10 TESC Measures (5% of total)LS 1 219,525$ 1 234,127$ 1 280,083$ 1 252,583$ 1 221,734$ 1 239,916$ 1 283,031$ 1 255,531$ SUB-TOTAL 770,740$ 811,046$ 948,914$ 866,414$ 777,367$ 828,412$ 957,759$ 875,259$ EARTHWORK AND SURFACING 11 Roadway Excavation, incl. Haul 55$ CY 359 19,745$ 359 19,745$ 359 19,745$ 359 19,745$ 385 21,175$ 385 21,175$ 385 21,175$ 385 21,175$ 12 Rock Excavation 1,000$ CY 485 485,000$ 649 649,000$ 485 485,000$ 485 485,000$ 485 485,000$ 649 649,000$ 485 485,000$ 485 485,000$ 13 Structure Excavation Class A incl. Haul 60$ CY 15,371 922,260$ 15,105 906,300$ 8,362 501,720$ 8,362 501,720$ 15,382 922,920$ 15,311 918,660$ 8,440 506,400$ 8,440 506,400$ 14 Channel Excavation Incl. Haul 100$ CY 600 60,000$ 600 60,000$ 600 60,000$ 600 60,000$ 600 60,000$ 600 60,000$ 600 60,000$ 600 60,000$ 15 Dewatering 20,000$ LS 1 20,000$ 1 20,000$ 1 20,000$ 1 20,000$ 1 20,000$ 1 20,000$ 1 20,000$ 1 20,000$ 16 Streambed Sediment 100$ Ton 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 17 Streambed Sand 200$ Ton 80 16,000$ 80 16,000$ 80 16,000$ 80 16,000$ 80 16,000$ 80 16,000$ 80 16,000$ 80 16,000$ 18 Streambed Cobbles 100$ Ton 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 720 72,000$ 19 Streambed Boulder Type 1 150$ EA 300 45,000$ 300 45,000$ 300 45,000$ 300 45,000$ 300 45,000$ 300 45,000$ 300 45,000$ 300 45,000$ 20 Compost 50$ CY 100 5,000$ 100 5,000$ 100 5,000$ 100 5,000$ 100 5,000$ 100 5,000$ 100 5,000$ 100 5,000$ 21 Crushed Surfacing Base Course 60$ Ton 501 30,060$ 501 30,060$ 146 8,760$ 146 8,760$ 534 32,040$ 534 32,040$ 154 9,240$ 154 9,240$ 22 Gravel Borrow 30$ Ton 27,100 813,000$ 25,200 756,000$ 1,400 42,000$ 1,400 42,000$ 27,800 834,000$ 26,600 798,000$ 1,700 51,000$ 1,700 51,000$ 23 HMA CL. 1/2 IN. PG 58H-22 200$ TN 215 43,000$ 215 43,000$ 63 12,600$ 63 12,600$ 232 46,400$ 232 46,400$ 67 13,400$ 67 13,400$ 24 Cement Conc. Sidewalk 150$ SY 288 43,200$ 288 43,200$ 58 8,700$ 58 8,700$ 292 43,800$ 292 43,800$ 65 9,750$ 65 9,750$ SUB-TOTAL 2,646,265$ 2,737,305$ 1,368,525$ 1,368,525$ 2,675,335$ 2,799,075$ 1,385,965$ 1,385,965$ STRUCTURE 25 3-Sided Conc. Box Culvert incl. footings, stemwalls, headwalls and wingwalls 1,102,500$ LS 1 1,102,500$ - -$ - -$ - -$ 1 1,117,605$ - -$ - -$ - -$ 26 Steel Plate Arch Culvert incl. footings and wingwalls 1,307,000$ LS - -$ 1 1,307,000$ - -$ - -$ - -$ 1 1,361,000$ - -$ - -$ 27 Bridge w/ SS on own bridge 3,594,899$ LS - -$ - -$ 1 3,594,899$ - -$ - -$ - -$ 1 3,636,426$ - -$ 28 Bridge w/ SS on structure 3,044,899$ LS - -$ - -$ - -$ 1 3,044,899$ - -$ - -$ - -$ 1 3,086,426$ SUB-TOTAL 1,102,500$ 1,307,000$ 3,594,899$ 3,044,899$ 1,117,605$ 1,361,000$ 3,636,426$ 3,086,426$ UTILITIES 26 Adjust Catch Basin 800$ Each 1 800$ 1 800$ 1 800$ 1 800$ 1 800$ 1 800$ 1 800$ 1 800$ 27 Drain Pipe, 12" Diam.30$ LF 69 2,070$ 69 2,070$ 69 2,070$ 69 2,070$ 69 2,070$ 69 2,070$ 69 2,070$ 69 2,070$ 28 Temporary Utility Relocations 100,000$ LS 1 100,000$ 1 100,000$ 1 100,000$ 1 100,000$ 1 100,000$ 1 100,000$ 1 100,000$ 1 100,000$ SUB-TOTAL 102,870$ 102,870$ 102,870$ 102,870$ 102,870$ 102,870$ 102,870$ 102,870$ TRAFFIC 29 Temporary Traffic Control (3% of total)LS 1 131,715$ 1 140,476$ 1 168,050$ 1 151,550$ 1 133,040$ 1 143,949$ 1 169,819$ 1 153,319$ 30 Paint Line 3$ LF 401 1,203$ 401 1,203$ 401 1,203$ 401 1,203$ 401 1,203$ 401 1,203$ 401 1,203$ 401 1,203$ 31 Permanent Signing 1,500$ LS 1 1,500$ 1 1,500$ 1 1,500$ 1 1,500$ 1 1,500$ 1 1,500$ 1 1,500$ 1 1,500$ SUB-TOTAL 134,418$ 143,179$ 170,753$ 154,253$ 135,743$ 146,652$ 172,522$ 156,022$ HABITAT AND LANDSCAPE 32 Riparian Restoration 200,000$ AC 1 200,000$ 1 200,000$ 1 200,000$ 1 200,000$ 1 200,000$ 1 200,000$ 1 200,000$ 1 200,000$ 33 Temporary Stream Diversion 50,000$ LS 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 1 50,000$ 34 Log Structure 6,000$ EA 29 174,000$ 29 174,000$ 29 174,000$ 29 174,000$ 29 174,000$ 29 174,000$ 29 174,000$ 29 174,000$ SUB-TOTAL 424,000$ 424,000$ 424,000$ 424,000$ 424,000$ 424,000$ 424,000$ 424,000$ CONSTRUCTION COST SUBTOTAL 5,180,794$ 5,525,401$ 6,609,961$ 5,960,961$ 5,232,920$ 5,662,009$ 6,679,542$ 6,030,542$ CONTINGENCY 40.0% 2,072,317$ 40.0% 2,210,160$ 40.0% 2,643,984$ 40.0% 2,384,384$ 40.0% 2,093,168$ 40.0% 2,264,804$ 40.0% 2,671,817$ 40.0% 2,412,217$ SALES TAX 10.1%732,564$ 10.1%781,292$ 10.1%934,649$ 10.1%842,880$ 10.1%739,935$ 10.1%800,608$ 10.1%944,487$ 10.1%852,719$ ESTIMATED TOTAL CONSTRUCTION COST W/CONTINGENCY & SALES TAX 7,985,675$ 8,516,853$ 10,188,594$ 9,188,226$ 8,066,023$ 8,727,421$ 10,295,846$ 9,295,478$ Alternative 1a Pre-Cast Concrete Box Item#Item Description Alternative 1c.1 Bridge w/ SS on own Bridge Alternative 2c.1 Bridge w/ SS on own Bridge Alternative 2c.2 Bridge w/ SS on Structure Alternative 2a Pre-Cast Concrete Box Alternative 1b Steel Plate Arch Alternative 2b Steel Plate Arch Alternative 1c.2 Bridge w/ SS on Structure GeoEngineers KPFF Conceptual Design Alternatives Page 1