HomeMy WebLinkAboutChange Order - 1 #"$ !
%
CAG-25-198, CO #1-25
CHANGE ORDER PROPOSAL COVER SHEET
PROJECT NAME/ADDRESS:
City of Renton - River view Park- Restroom vandalism repair
CHANGE ORDER NUMBER: 01
2901 Maple Valley Highway, Renton, WA 98057 DATE: August 14, 2025
CONTRACTOR NAME/ADDRESS:
Puget Sound Construction Partners. Inc
AMMOUNT: $17,898
930 Industry Drive, Tukwila, WA 98188 EMAIL ADDRESS:
THE CONTRACT IS CHANGED AS FOLLOWS:
1. The Drinking Fountain leaks quite a bit of water from the stainless-steel panel below the drain as well as the
faucet. Recommend replacing the whole drinking fountain. See Pictures A and B
2. The women’s Lavatory - When pushing the air switch for the lavatory, a substantial stream of water leaks from an
access panel below the lavatory. Appears as if some sort of Vermin got into it. Recommend New Air Control Valve
(ACORN) and plumbing at fixture See Pictures C, D, and F.
3. The Men’s Lavatory - When pushing the air switch for the lavatory, almost no water flow comes out. It seems to
have a blockage between the valve and faucet. Recommend replacing the Air Control Valve currently. See Picture
E.
4. The Access Panels - No key was found to access the access panels; Maintenance Team was called to open the
doors and ended up prying the access doors open. Will need to procure new ones and replace.
Image – A Image – B Image – C
#"$ !
#"$ !
General Contractor Cost Proposal Breakdown Summary
Riverview Park Bathroom Repair FA/COP No.COP 1
Date:8/14/2025
GENERAL CONTRACTOR Puget Sound Construction Partners
SUB-CONTRACTOR:Brix Plumbing
1. CRAFT LABOR COSTS
a. craft labor costs from breakdown $1,000.00
b. foreman (includes supervision)
c. lead foreman (includes supervision)
DIRECT LABOR SUBTOTAL $1,000.00
Supervision
d. direct supervision (NTE 15% of 1a)$150.00
e. payroll taxes
f. safety (NTE 2% of lines 1a, b, & c)$20.00
g. travel (if applicable, itemize)$0.00
1. CRAFT LABOR COSTS $1,170.00
2. MATERIALS COSTS
a. material costs
b. freight costs (itemize)$0.00
2. MATERIAL COSTS $0.00
3. EQUIPMENT COSTS
a. owned equipment (per spec approved source)$0.00
b. rental equipment (per invoices attached)$0.00
3. EQUIPMENT COSTS $0.00
4. SMALL TOOLS
a. small tools (NTE 3% of 1a, & b)
4. SMALL TOOLS $30.00
SUBTOTAL 1,2,3,&4 $1,200.00
5. OVERHEAD allowance
a. NTE 16% portion of 1,2,3, & 4 up to $50,000
b. NTE 4% portion of 1,2,3, & 4 in excess of $50,000
5. OVERHEAD $192.00
6. ALLOWANCE FOR CONTRACTOR PROFIT (NTE 6% OF 1,2,3, & 4)
(Contractor profit on work performed by Contractor's own forces)6. PROFIT $72.00
7. SUBCONTRACTORS
a.Brix Plumbing $13,750.00
b.$0.00
c.$0.00
d.$0.00
7. SUBCONTRACTORS $13,750.00
8. OVERHEAD ON SUBCONTRACTORS
a. NTE 6% portion of 7 up to $50,000 for each sub
b. NTE 4% portion of 7 in excess of $50,000 for each sub
8. OVERHEAD ON SUBCONTRACTORS $825.00
9. ALLOWANCE FOR PROFIT ON SUBCONTRACTOR (NTE 5% OF 7 & 8)
(Contractor profit on work performed by Subcontractor)9. PROFIT ON SUBCONTRACTORS $728.75
10. INSURANCE
a. payroll driven liability insurance (2% of 1)
b. volume driven liability insurance (2% of 1 thru 7)$304.28
10. INSURANCE $304.28
11. BOND
a. bond (3% of 1 thru 10)
11. BOND $521.29
TOTAL COST 1 THRU 11 $17,898
PROJECT NAME:
PROJECT NO.
8/14/2025 Page 1 of ___.General Contractor Cost Breakdown Riverview Park COP 1
#"$ !
General Contractor Cost Proposal Breakdown Summary
PROJECT NAME:Riverview Park Bathroom Repair FA/COP No. COP 1
RATE TOTAL UNIT TOTAL UNIT TOTAL
Office Labor
Office work labor 4 hrs $90.00 $360.00
Field Labor
Supervision 8 hrs $80.00 $640.00
hrs $0.00
hrs $0.00
Sub-Total Labor $1,000.00
Materials
$0.00
EQUIPMENT
ITEM HOURS UNIT
LABOR MATERIAL
8/14/2025 Page 1 of ___.General Contractor Cost Breakdown Riverview Park COP 1
#"$ !
Sub Contractor Cost Proposal Breakdown Summary
Riverview Park Bathroom Repair FA/COP No.COP 1
Date:8/14/2025
GENERAL CONTRACTOR Puget Sound Construction Partners
SUB-CONTRACTOR:Brix Plumbing
1. CRAFT LABOR COSTS
a. craft labor costs from breakdown $5,284.32
b. foreman (includes supervision)
c. lead foreman (includes supervision)
DIRECT LABOR SUBTOTAL $5,284.32
Supervision
d. direct supervision (NTE 15% of 1a)$0.00
e. payroll taxes
f. safety (NTE 2% of lines 1a, b, & c)$0.00
g. travel (if applicable, itemize)$0.00
1. CRAFT LABOR COSTS $5,284.32
2. MATERIALS COSTS
a. material costs $6,174.00
b. freight costs (itemize)$0.00
2. MATERIAL COSTS $6,174.00
3. EQUIPMENT COSTS
a. owned equipment (per spec approved source)$0.00
b. rental equipment (per invoices attached)$0.00
3. EQUIPMENT COSTS $0.00
4. SMALL TOOLS
a. small tools (NTE 3% of 1a, & b)
4. SMALL TOOLS $0.00
SUBTOTAL 1,2,3,&4 $11,458.32
5. OVERHEAD allowance
a. NTE 10% portion of 1,2,3, & 4 up to $50,000
b. NTE 4% portion of 1,2,3, & 4 in excess of $50,000
5. OVERHEAD $1,145.83
6. ALLOWANCE FOR CONTRACTOR PROFIT (NTE 10% OF 1,2,3, & 4)
(Contractor profit on work performed by Contractor's own forces)6. PROFIT $1,145.83
7. SUBCONTRACTORS
a.$0.00
b.$0.00
c.$0.00
d.$0.00
7. SUBCONTRACTORS $0.00
8. OVERHEAD ON SUBCONTRACTORS
a. NTE 6% portion of 7 up to $50,000 for each sub
b. NTE 4% portion of 7 in excess of $50,000 for each sub
8. OVERHEAD ON SUBCONTRACTORS $0.00
9. ALLOWANCE FOR PROFIT ON SUBCONTRACTOR (NTE 5% OF 7 & 8)
(Contractor profit on work performed by Subcontractor)9. PROFIT ON SUBCONTRACTORS $0.00
10. INSURANCE
a. payroll driven liability insurance (2% of 1)
b. volume driven liability insurance (2% of 1 thru 7)$0.00
10. INSURANCE $0.00
11. BOND
a. bond (3% of 1 thru 10)
11. BOND $0.00
TOTAL COST 1 THRU 11 $13,750
PROJECT NAME:
PROJECT NO.
8/14/2025 Page 1 of ___.Subcontractor Cost Breakdown Riverview Park COP 1
#"$ !
Sub Contractor Cost Proposal Breakdown Summary
PROJECT NAME:Riverview Park Bathroom Repair FA/COP No. COP 1
RATE TOTAL RATE TOTAL UNIT TOTAL
Office Labor
hrs $0.00 $0.00
Field Labor
Plumbing Labor Man Hours Demo 16 hrs $107.59 $1,721.44
Plumbing Labor Man Hours Install 32 hrs $107.59 $3,442.88
Admin Hours 2 hrs $60.00 $120.00
Sub-Total Labor $5,284.32
Materials
Wall Frame Access Door Retrofit 2 Ea $437.00 $874.00
Penal-Ware 1672 ADA Drinking
Fountain 1 Ea $2,682.00 $2,682.00
Air Control Replacement Valve
Assembly 2 Ea $1,309.00 $2,618.00
Sub-Total Labor $6,174.00
EQUIPMENT
ITEM HOURS UNIT
LABOR MATERIAL
8/14/2025 Page 1 of ___.Subcontractor Cost Breakdown Riverview Park COP 1
#"$ !
Proposed To:Puget Sound Construction Project Name:Riverview Park Bathroom Repair
Email:John lee Project Address:
Date: 8/11/2025
Attention:John lee Quote By:Carlos
Phone Number:425-625-1740 Phone Number:360.560.1927
Reference RFI#Email:carlos.roldan@brixplumb.com
Change Order #1
COUNT
1
1
1
1
2
QTY Plumbing Labor Man Hours Demo Rate Total
16 107.59$ 1,721.44$
Plumbing Labor Man Hours Install
32 107.59$ 3,442.88$
Admin Hours
2 60.00$ 120.00$
Materials
2 Wall Frame Access Door Retrofit 437.00$ 874.00$
1 Penal-Ware 1672 ADA Drinking Fountain 2,682.00$ 2,682.00$
2 Air Control Replacement Valve Assembly 1,309.00$ 2,618.00$
11,458.32$
2,291.66$
13,749.98$
Material:
Exclusions:
Date
Date
Authorized Brix Plumbing Signiture
Signed Approval of Proposal and Schedule of Values
Payment will be as follows- Net 30 - Need Approval before work can be started
Above /Below Ground DWV- Cast Iron,
Above / Below Ground Water - Copper Pipe and Fittings
Hangers and Support - N/A
Permits, Sales Tax, Sheetrock Removal, Demolition of Walls, Demolition of Cielings, Sheet rock Repair, Insulation, New Fixtures besides proposed.
Payment:
Renton
Work Order
Work Includes
Diagnosis
The Drinking Fountain leaks quite a bit of water from the stainless steel panel below the drain as well as the faucet. Recommend replacing the
whole drinking fountain. See Pictures A and B
The womens Lavatory - When pushing the air switch for the lavatory, a fairly substantial stream of water leaks from an access panel below the
lavatory. Appears as if some sort of Vermin got into it. Recommend New Air Control Valve (ACORN) and Plumbing at fixture See Pictures C, D, and
F
The Mens Lavatory - When pushing the air switch for the lavatory, Almost no water flow comes out. It seems to have a blockage between the valve
and faucet. Recommend replacing the Air Control Valve at this time. See Picture E
The Access Panels - No key was found to access the access panels, Maintance Team was called to open the doors and ended up prying the access
doors open. Will need to procure new ones and replace.
We Propose to hereby Provide material and labor in accordance with the above specifications
for the sum of:We reserve the right to withdraw this proposal if
not accepted within 30 days from the date of quote Total Price 13,749.98$
Subtotal
Overhead and Profit at 20%
Total
#"$ !
FEL - OLYMPIA #3037
402 CARPENTER ROAD SOUTHEAST
OLYMPIA, WA 98503
Phone: 360-456-2960
Fax: 360-456-4643
Deliver To:
From:Dean Jensen
dean.jensen@ferguson.com
Comments:
HOW ARE WE DOING? WE WANT YOUR FEEDBACK!
Scan the QR code or use the link below to
complete a survey about your bids:
https://survey.medallia.com/?bidsorder&fc=3038&on=1303392
12:06:11 AUG 11 2025
FERGUSON ENTERPRISES #3007
Price Quotation
Phone: 360-456-2960
Fax: 360-456-4643
Bid No:B901652
Bid Date:08/11/25
Quoted By:DLJ
Cust Phone:360-560-1927
Terms:NET 10TH PROX
Customer:BRIX PLUMBING LLC
446-79 MEIER RD
WINLOCK, WA 98596
Ship To:BRIX PLUMBING LLC
446-79 MEIER RD
WINLOCK, WA 98596
Cust PO#:CONTRACTOR Job Name:RIVERSIDE PARK
Page 1 of 2
Item Description Quantity Net Price UM Total
SP-A8292 WALL FRAME W DOOR RETROFIT 1 437.500 EA 437.50
in stock in CA
SP-A1672IBC03BRSFM PENAL-WARE 1672 ADA DRINKING FOUNT 1 2682.000 EA 2682.00
(6-7 weeks to build + transit)
SP-A3382BRS AIR CONTROL REPLACEMENT VALVE ASSEM 1 1309.000 EA 1309.00
(3 weeks to build + transit)
All FOB Factory: Industry,
CA, 91744
Net Total:$4428.50
Tax:$0.00
Freight:$0.00
Total:$4428.50
Quoted prices are based upon receipt of the total quantity for immediate shipment (48 hours). SHIPMENTS BEYOND 48 HOURS SHALL BE
AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE. QUOTES FOR PRODUCTS SHIPPED FOR RESALE
Due to the uncertain impact of potential tariffs, Ferguson's quotation/proposal has not included any provision or contingency for future tariffs or increase of existing tariffs. Ferguson reserves the right to adjust prices to reflect the impact of any new or increased tariffs that affect our costs at the time of shipment. Ferguson will provide notice of any such adjustments along with documentation supporting the changes.
CONTRACTOR CUSTOMERS: IF YOU HAVE DBE/MBE/WBE//VBE/SDVBE/SBE GOOD FAITH EFFORTS DIVERSITY GOALS/ REQUIREMENTS ON A FEDERAL, STATE, LOCAL GOVERNMENT, PRIVATE SECTOR PROJECT, PLEASE CONTACT YOUR BRANCH SALES REPRESENATIVE IMMEDIATELY PRIOR TO RECEIVING A QUOTE/ORDER.
ARE NOT FIRM UNLESS NOTED OTHERWISE.
https://www.ferguson.com/content/website-info/terms-of-sale
LEAD LAW WARNING: It is illegal to install products that are not "lead free" in accordance with US Federal or other applicable law in potable water systems anticipated for human consumption. Products with *NP in the description are NOT lead free and can only be installed in non-potable applications. Buyer is solely responsible for product selection. Buyer shall accept delivery of products within 60 days of Seller receiving the products at Seller's warehouse. If Buyer causes or requests a delay in delivery of the products, Buyer may be subject to storage fees and additional costs caused by such delay. Seller reserves the right to requote the products and reschedule the delivery date, subject to manufacturer's lead times and price increases, if Buyer is unable to accept delivery within 60 days.
Seller not responsible for delays, lack of product or increase of pricing due to causes beyond our control, and/or based upon
Local, State and Federal laws governing type of products that can be sold or put into commerce. This Quote is offered contingent upon the
Buyer's acceptance of Seller's terms and conditions, which are incorporated by reference and found either following this document, or
on the web at
Govt Buyers: All items are open market unless noted otherwise.
#"$ !
Page 2 of 2
12:06:11 AUG 11 2025
FERGUSON ENTERPRISES #3007
Price Quotation
Fax: 360-456-4643
Reference No:B901652
HOW ARE WE DOING? WE WANT YOUR FEEDBACK!
Scan the QR code or use the link below to
complete a survey about your bids:
https://survey.medallia.com/?bidsorder&fc=3038&on=1303392
#"$ !