Construction Permit: C24002123
IVR Number: 24002123
Permit Information
Permit Name: South Renton Transit Center
Address/Location:04/23/2024Application Date:1923059063Parcel Number: 101 S GRADY WAY
Permit Type:12/09/2025Issue Date:Engineering
Permit Work Class:12/09/2026Expiration Date:Construction
Plan Reviewer: Michael Sippo 425-430-7298
Description: Civil Construction Permit for the South Renton Transit Center Project Utility extensions, transportation
improvements, and construction of the transit center bus lanes. Temporary surface parking is proposed. #4332
Contacts
Name Address PhoneTypeBilling
Gregory McKnight
King County Metro
205 S 7th St B: (206) 477-0344Contact
Shimmick Construction Company Inc.5224 Olympic Dr
Gig Harbor, WA 98335
B: (253) 358-3174Contractor
Construction Contractor: SHIMMCC905JB
Ricardo Pargas
HDR Inc.
B: (520) 584-3654Engineer
John Hardy
(CPSRTA) Sound Transit
401 S Jackson St
Seattle, WA 98104
B: (206) 370-5579
C: (206) 304-8449
OwnerX
General Conditions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
Ÿ
This permit and plans must be posted at the job site at all times.Ÿ
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton codes and ordinances.
Ÿ
Call 425.430.7203 or go to: https://permitting.rentonwa.gov one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Ÿ
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.Ÿ
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 425.235.7736) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
Ÿ
(Date)(Signature)
Page 1 of 1THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Conditions for Permit C24002123
Engineering
1 Condition #2
2. A pre-construction meeting shall be held with the Applicant, Project Contractor, City Representatives and
Inspection Staff prior to City's Notice to Proceed.
2 Condition #8
8. Sheet BT120-CDP100 (Page 163): Pipe and easement ownership exhibit requirement.
3 Condition #1
1. Issuance of Civil Construction Permit C24002123 is for the purposes of final project final contractor
procurement. Construction shall not occur until the City Project Manager issues the City's Notice to Proceed.
Additional information such as contractor and subcontractor business licenses and insurance naming the City as
additionally insured shall be approved by City risk management and legal staff and in place prior to construction.
4 Condition #9
9. Sheet BT120-CDP105 (Page 166): Remove existing upstream pipe.
5 Condition #3
3. All project construction and inspection fees shall be paid prior to scheduling of pre-construction meeting and
issuance of the City's Notice to Proceed.
6 Condition #15
15. Sheets BT120-TDP101-103 (Sheets 265-265B): Traffic detour plans not approved. Separate submittal
required.
7 Condition #12
12. Sheet BT120-TSD101 (Page 239): Per Std. plan 140.
8 Condition #13
13. Sheet BT120-TSD102 (Page 240): #itsp+2515509990.
9 Condition #4
4. All temporary project entitlements such as construction easements and property permissions shall be in
place and copies provided to the City prior to issuance of the City's Notice to Proceed.
Page 1 of 2
10 Condition #5
5. Project Public Agency Service Agreement shall be in place and executed prior to City's Notice to Proceed.
11 Condition #14
14. Sheets BT120-TMN101 & TMP101-115 (Sheets 250-264): Traffic control plans not approved. Separate
submittal required..
12 Condition #7
7. Sheet BT120-CHP101 (Page 42): Detailed haul route submittal requirement.
13 Condition #18
18. Book 3: Traffic control and detour plans not approved. Traffic control and detour plans affecting City
operations to be reviewed in conjunction with WSDOT approvals and may require further coordination.
14 Condition #16
16. Sheet BT120-LRP104 (Sheet 313): Add backflow prevention notes.
15 Condition #17
17. Book 2 approval is for City indexing purposes only. Final book 2 based on approved building permit
submittals to be provided to City Project Manager during as-builts phase accurately reflecting approved and
constructed building permit plans.
16 Condition #6
6. All outside agency permits or approvals such as Department of Ecology or Washington State Department of
Transportation shall be in place and provided to the City prior to Notice to Proceed.
17 Condition #10
10. Sheet BT120-CDP105 (Page 166): Provide letter from WSDOT accepting maintenance responsibility of
storm drainage structure and pipe.
18 Condition #11
11. Sheet BT120-UWP201 (Page 216): 2" RPBA required.