Loading...
HomeMy WebLinkAboutChange Order - 1Change Order No. #01 Contract Title: Legacy Square Phase 2 Contract No. CAG-25-257 Page 1 of 4 Change Order No. 01 Contract Title:LEGACY SQUARE PHASE 2 Contractor:Andersen Construction Company of Washington, LLC Contract No. :CAG-25-257 Amount Substantial Completion Date Original Contract: $1,248,000.00 March 20, 2026 Current Contract: $1,248,000.00 March 20, 2026 Estimated Net Change This Order:$322,652.00 New Contract:$1,570,652.00 April 30, 2026 AGREED DISPUTE RESOLUTION THE CONTRACT IS MODIFIED AS FOLLOWS: The Parties agree that payment in the amount of $322,652.00 increasing the contract price not to exceed and to be paid in the contract process to Contractor to resolve all disputes regarding the items below, to clarify the Scope of Work, and to facilitate the expedited dispute resolution process. Description of Change: After award and the execution of the Contract (CAG-25-257) and prior to issuance of the Notice to Proceed (NTP) (November 13, 2025), Andersen Construction Company of Washington, LLC (“Contractor”) raised ambiguities in the contract regarding several bid items. The parties dispute the ambiguities raised. To resolve the dispute and expedite the resolution accommodating the tight timeline of the project the parties agree to the resolution of the dispute as set forth in this Change Order #1. This Change Order #1 constitutes a settlement of the matters set forth below. The following terms of the Contract are amended in all locations in the project manual as follows : 1.Notice to Proceed Date: Notice to Proceed was formally issued November 13, 2025. Contract Time in the contract will be adjusted to these dates. There will be no liquidated damages or CAG-25-257, CO #1-25 Change Order No. #01 Contract Title: Legacy Square Phase 2 Contract No. CAG-25-257 Page 2 of 4 further cost adjustments to either party for this adjustmentother than the additional total payment of $322,652.00 for this settlement. 2.Mobilization Date: The Mobilization to Site date is amended from October 20, 2025, to December 8, 2025. Contractor is required to mobilize per the Contract and may mobilize to the site at any time prior to December 8, 2025. Contract Time in the contract will be adjusted to these dates. There will be no liquidated damages or further cost adjustments to either party for this adjustment other than the additional total payment of $322,652.00 for this settlement. 3. Substantial Completion: The Substantial Completion Date of the Contract is amended from March 20, 2026, to April 30, 2026. Contract Time in the contract will be adjusted to these dates. There will be no liquidated damages or further cost adjustments to either party for this adjustment other than the additional total payment of $322,652.00 for this settlement. 4. Fire Suppression Sprinklers and Fire Alarm: The requirement for fire suppression sprinklers specified in the Issued for Construction (IFC) Plans (Sheets A5.01 and A9.02)is removedfrom the project. There will be no further reduction in the Contract amount for this amendmentother than the additional total payment of $322,652.00 for this settlement. The requirement for a fire alarm, a fire alarm control panel, and fire alarm terminal cabinet specified in the Issued for Construction (IFC) Plans (Sheets G1.02, E0.01, E2.01, and AV0.00) is removed from the project. There will be nofurther reduction in the Contract amount for this amendmentother than the additional total payment of $322,652.00 for this settlement. 5. Standing Seam Metal Roof and Wall Panels: As previously determined by the Architect on October 29, 2025, and confirmed by the City on November 3, 2025, Contractor’s proposed use of product from AEP Span for the “Standing Seam Metal Roof and Wall Panels”(Section07 41 13) is denied. Contractor shall procure the material(s) specified in the Contract. Change Order No. #01 Contract Title: Legacy Square Phase 2 Contract No. CAG-25-257 Page 3 of 4 6.Integrated Audiovisual Systems and Equipment (“AV Package”): The Integrated Audiovisual Systems and Equipment (“AV Package”), as defined in Section 27 41 16 (Attachment A), shall be procured by Contractorand/or its subcontractor, and installed by said subcontractor, as specified in the Contract. Contractors proposed AV Package (Attachment B) shall be submitted for review pursuant to Section 01 30 00 (Administrative Requirements) to ensure the AV Package conforms to Section 27 41 16, and the subcontractor meets the requirements of Section 27 41 16, including but not limited to: 1.4 Contractor Qualifications 1.6 Submittals: Schedule of Values Non-equipment costs Service Contract System Enhancements Contractor Resume Project Approach 1.6.C: Installation Submittal 1.9 Performance Standards (Statement from proposed subcontractor affirming their system will meet the performance standards). The payment specified and agreed to in this Change Order includes every claim by the contractor for any extra payment with respect to the work described in this change order. There will be nofurther revision in the Contract amount for these amendments other than the additional total payment of $322,652.00 for this settlement. The work covered by this change order must be performed under the same terms and conditions as included in the original Contract. All the other terms of the original Contract remain in effect. Change Order No. #01 Contract Title: Legacy Square Phase 2 Contract No. CAG-25-257 Page 4 of 4 CITY OF RENTON By:_____________________________ CONTRACTOR By:____________________________ Armondo Pavone Mayor Name: Title: _____________________________ Date _____________________________ Date Attest _____________________________ Jason A. Seth City Clerk Approved as to Legal Form By: __________________________ Shane Moloney City Attorney Brian Price COO and Presiden Seattle Region 12/1/202512/10/2025 Approved by Cheryl Beyer via email 12/9/2025 Definitions. ATTACHMENT A Definitions. 013000 - Administrative Requirements 013000 014000 - Quality Requirements Section 017800 - Closeout Submittals 017800 - Closeout Submittals Communications Horizontal Cabling. ATTACHMENT B